SlideShare a Scribd company logo
1 of 17
Download to read offline
FIRST QUANTUM MINERALS
TSX: FM SEPTEMBER 2016
CAUTIONARY NOTE REGARDING FORWARD-LOOKING STATEMENT
Some of the statements contained in the following material are
forward-looking statements and not statement of facts. Such
statements are based on the current beliefs of management, as well
as assumptions based on management information currently
available.
Forward-looking statements are subject to various risks,
uncertainties and other factors that could cause actual results to
differ materially from expected results.
Readers must rely on their own evaluation of these uncertainties.
Note: all dollar amounts in US dollars unless otherwise indicated
2
DISCUSSION TOPICS
EXECUTION OF ACTION PLAN DELIVERING DESIRED RESULTS Slide
Stronger financial position 4, 5, 6, 7
Solid operating base 8, 10
Sustainable cost reductions 9
On-track development of the Cobre Panama project 11, 12, 13, 14
UPCOMING CATALYSTS
Lower tax regime in Zambia 16
Energization of 2nd power line to Trident 16
Completion of project financing for Cobre Panama 15
Construction completion of power plants in Panama 11
Resolution of Zambian VAT receivable 16
3
STRONGER FINANCIAL POSITION
 New improved Facility:
 Comprised of a $907.5M term loan and a $907.5M revolving credit facility
 Improved financial covenants and an amortization schedule that starts June 2017
 Same liquidity within the next 12 months compared to the previous $3.0B facility
 $593M of committed undrawn facilities, $895M in unrestricted cash, working
capital of $553M as at June 30 2016
IMPROVED NET DEBT:EBITDA RATIO COVENANTS
PERIOD MAXIMUM RATIO
Current – June 30 2017 5.50:1
July 1 2017 – December 31 2017 5.00:1
January1 2018 – June 30 2018 4.50:1
July 1 2018 – December 31 2018 3.50:1
January 1 2019 - Termination 3.25:1
4
5
No bond principle due until 2019
Q2 2016 liquidity:
$895m unrestricted cash
$593m undrawn RCF (expires 2019)
Liquidity
Net debt/EBITDA covenant ratio of
4.0x - within bank covenant of 5.5x
Covenant Ratio
Debt Maturity Profile ($m)
STRONGER FINANCIAL POSITION – LONG-TERM DEBT PROFILE
6
STRONGER FINANCIAL POSITION – CAPITAL EXPENDITURE
1 Capital expenditure excludes capitalized interest, capitalized pre-production costs and all
capital expenditures related to discontinued operations (Kevitsa) up to the date of sale.
Cobre Panama Funding ($bn)
FirstQuanumincurred 3rdPartyincurred
FirstQuantumto spend 3rdPartto spend
US$ million Q2 2016 YTD 2016
Cobre Panama 187 341
Net to First Quantum 112 205
Trident project 26 54
Stripping costs 27 43
Other sustaining capex and other projects 29 52
Total net capex1
194 354
US$ billion Total
First
Quantum 3rd Party
Cobre Panama project
Capital spend to December 2015 2.72 1.86 0.86
H1 2016 spend incurred 0.34 0.20 0.14
Estimated 2016 remaining capital spend 0.31 0.19 0.12
Estimated post 2016 capital spend 2.11 1.13 0.98
Total Cobre Panama 5.48 3.38 2.10
Funded by
$5.48bn
KEVITSA SALE COMPLETED;
POSITIVE RESPONSE FROM CREDIT RATINGS AGENCIES
 Completed sale of Kevitsa for $712 million in cash, excluding working capital
adjustments on June 1, 2016
 Positive response from credit ratings agencies:
 S&P upgraded the current B- credit rating outlook to stable from negative
 Moody’s upgraded from Caa1 to B-, with negative outlook
 Fitch reaffirmed the B rating and upgraded the outlook to stable from negative
7
SOLID OPERATING BASE – Q2 2016 RESULTS1
Set a new quarterly records for copper
production and sales of 131,349 tonnes and
132,030 tonnes, respectively
Fifth consecutive quarter of lower copper
cash cost (“C1”), All-in sustaining (“AISC”)
and total cost (“C3”) per lb:
 C1 = $0.98; AISC = $1.32; C3 = $1.80
Cost profile lowered:
 Guidance for the year 2016:
 C1 = $1.05 to $1.15 per lb2
 AISC = $1.40 to $1.60 per lb2
1 Continuing operations which exclude Kevitsa
2 Excluding Sentinel
8
$34
$36
$10
$39
Savings Q2’16 vs Q2‘15
$ millions
Employee/Contractors/Maintenance costs
Fuel/Power/Freight/Consumables
G&A + Exploration
Smelter savings1 Adjusted to remove the impact of FX
9
SUSTAINABLE COST REDUCTIONS1 – Q2 2016 VS. Q2 2015
$119
million
 Net acid costs $39m lower driven by
Kansanshi smelter production of
sulphuric acid
 Lower employee, contractor and
maintenance costs
 Lower consumable, fuel, power and
freight costs
 Lower general and administration
and exploration costs of $10m
excludes the impact of FX
 Zambian royalty costs $38m lower
as rate was 20% in Q2 2015 and
reduced to 9% in April/May
 Zambian royalty further reduced to
5% in June 2016
SOLID OPERATING BASE
Active sales hedge programs:
 Copper: contributed $0.08 per lb in Q2
2016; $0.36 per lb for six months 2016
 Copper: open position at July 27, 2016
= 309,650 tonnes @ $2.20 per lb
 Nickel: contributed $0.13 per lb in Q2
2016
 Nickel: open position at July 27, 2016 =
11,004 tonnes @ $4.68 per lb
Forecast production
10
2016F 2017F 2018F
Copper (excl Sentinel) – 000’s tonnes 380 380 385
Copper – Sentinel – 000’s tonnes 135-155 210-240 230-260
Nickel – 000’s contained tonnes 23 28 28
Gold – 000’s ounces 210 208 208
 Most challenging aspect of the
project is well under control
 Priority given to the power station
and associated infrastructure
 Revenues from power sales
expected in 2nd half 2017
 Expenditures being managed to suit
market conditions
 Capex lowered to $5.48B
COBRE PANAMA DEVELOPMENT ON TRACK
11
12
COBRE PANAMA – POWER PLANT & PORT OVERVIEW
13
COBRE PANAMA – POWER PLANT – 150 MW UNIT 1
14
COBRE PANAMA – BALL MILL AND MOTOR INSTALLATION
ADVANCING THE PROJECT FINANCING PROCESS
 Cost competitive, long-term financing
 Phase 1 completed
 Phase 2 initiated covering due diligence, information memorandum, engaging
consultants, ECA and bank selection, and term sheet negotiation
 Financial close could be achieved within 12 months
 Targeting up to $2.5B
15
POSITIVE ZAMBIAN DEVELOPMENTS
 Power situation has stabilized:
 Sentinel currently receiving ~80% of total power requirement
 Itezhi-Tehzi hydro is feeding ~120MW into the system
 Maamba Collieries has introduced 150MW; expects to introduce the 2nd 150MW (300MW
total) shortly
 Completion of the Maamba switchyard is ongoing – expect completion in about a month
 Electrification of 2nd power line planned to follow shortly thereafter
 Changes to Zambian mining tax regime enacted June 1 2016:
 Variable profits tax repealed
 20% royalty lowered to between 4-6% depending on the monthly average LME copper trading
price (currently 5%)
 VAT accrued to June 30 2016 = $241 million
 Refunds of $72M received between March 2015 – June 2016
 Discussions with relevant authorities continue
 General elections completed; incumbent re-elected
16
FIRST QUANTUM MINERALS
TSX: FM SEPTEMBER 2016

More Related Content

What's hot

What's hot (20)

Teekay Tankers Q4-2017 Earnings Presentation
Teekay Tankers Q4-2017 Earnings PresentationTeekay Tankers Q4-2017 Earnings Presentation
Teekay Tankers Q4-2017 Earnings Presentation
 
4Q 2019 Earnings
4Q 2019 Earnings4Q 2019 Earnings
4Q 2019 Earnings
 
TK Q4-20 Earnings Presentation
TK Q4-20 Earnings PresentationTK Q4-20 Earnings Presentation
TK Q4-20 Earnings Presentation
 
DUG Permian Basin 2015
DUG Permian Basin 2015DUG Permian Basin 2015
DUG Permian Basin 2015
 
First Quantum Minerals Corporate Presentation - May 2014
First Quantum Minerals Corporate Presentation - May 2014First Quantum Minerals Corporate Presentation - May 2014
First Quantum Minerals Corporate Presentation - May 2014
 
Company website presentation (a) june 2016
Company website presentation (a)   june 2016Company website presentation (a)   june 2016
Company website presentation (a) june 2016
 
Arex 4 q and fy15 results presentation
Arex 4 q and fy15 results presentationArex 4 q and fy15 results presentation
Arex 4 q and fy15 results presentation
 
Presentation june - final
Presentation   june - finalPresentation   june - final
Presentation june - final
 
Teekay Tankers Q3-2015 Earnings Presentation
Teekay Tankers Q3-2015 Earnings PresentationTeekay Tankers Q3-2015 Earnings Presentation
Teekay Tankers Q3-2015 Earnings Presentation
 
Am website presentation june 2016
Am website presentation   june 2016Am website presentation   june 2016
Am website presentation june 2016
 
TK Q3 2021 Earnings Presentation
TK Q3 2021 Earnings PresentationTK Q3 2021 Earnings Presentation
TK Q3 2021 Earnings Presentation
 
Am website presentation (a) may 2016
Am website presentation (a)   may 2016Am website presentation (a)   may 2016
Am website presentation (a) may 2016
 
Company Overview - April 2015
Company Overview - April 2015Company Overview - April 2015
Company Overview - April 2015
 
Company Presentation - October 2014
Company Presentation - October 2014Company Presentation - October 2014
Company Presentation - October 2014
 
TNK Q4-20 Earnings Presentation
TNK Q4-20 Earnings PresentationTNK Q4-20 Earnings Presentation
TNK Q4-20 Earnings Presentation
 
Company website presentation (a) march 2016
Company website presentation (a)   march 2016Company website presentation (a)   march 2016
Company website presentation (a) march 2016
 
Teekay Corporation Q3-2015 Earnings Presentation
Teekay Corporation Q3-2015 Earnings PresentationTeekay Corporation Q3-2015 Earnings Presentation
Teekay Corporation Q3-2015 Earnings Presentation
 
Am website presentation (a) june 2016
Am website presentation (a)   june 2016Am website presentation (a)   june 2016
Am website presentation (a) june 2016
 
TGP Q1-2020 Earnings Presentation
TGP Q1-2020 Earnings PresentationTGP Q1-2020 Earnings Presentation
TGP Q1-2020 Earnings Presentation
 
Teekay Tankers Q1-2019 Earnings Presentation
Teekay Tankers Q1-2019 Earnings PresentationTeekay Tankers Q1-2019 Earnings Presentation
Teekay Tankers Q1-2019 Earnings Presentation
 

Similar to Presentation september - final

02 24-16 fourth quarter & fy 2015 financial review final
02 24-16 fourth quarter & fy 2015 financial review final02 24-16 fourth quarter & fy 2015 financial review final
02 24-16 fourth quarter & fy 2015 financial review final
AES_BigSky
 
Presentation may - final
Presentation   may - finalPresentation   may - final
Presentation may - final
FirstQuantum
 
11 06-14 third quarter 2014 financial review final
11 06-14 third quarter 2014 financial review final11 06-14 third quarter 2014 financial review final
11 06-14 third quarter 2014 financial review final
AES_BigSky
 

Similar to Presentation september - final (20)

Presentation november - final
Presentation   november - finalPresentation   november - final
Presentation november - final
 
Presentation bmo - final
Presentation   bmo - finalPresentation   bmo - final
Presentation bmo - final
 
Presentation march - final
Presentation   march - finalPresentation   march - final
Presentation march - final
 
Presentation november final
Presentation   november finalPresentation   november final
Presentation november final
 
February 2017 Corporate Presentation
February 2017 Corporate PresentationFebruary 2017 Corporate Presentation
February 2017 Corporate Presentation
 
Presentation january 2018 - final
Presentation   january 2018 - finalPresentation   january 2018 - final
Presentation january 2018 - final
 
AES Third Quarter 2016 Financial Review
AES Third Quarter 2016 Financial ReviewAES Third Quarter 2016 Financial Review
AES Third Quarter 2016 Financial Review
 
11 04-16 third quarter 2016 financial review final (revised mw appendix)
11 04-16 third quarter 2016 financial review final (revised mw appendix)11 04-16 third quarter 2016 financial review final (revised mw appendix)
11 04-16 third quarter 2016 financial review final (revised mw appendix)
 
Trc q4 2016 earnings slides final
Trc q4 2016 earnings slides finalTrc q4 2016 earnings slides final
Trc q4 2016 earnings slides final
 
X Investors Meeting - CPFL Energia
X Investors Meeting - CPFL EnergiaX Investors Meeting - CPFL Energia
X Investors Meeting - CPFL Energia
 
02 24-16 fourth quarter & fy 2015 financial review final
02 24-16 fourth quarter & fy 2015 financial review final02 24-16 fourth quarter & fy 2015 financial review final
02 24-16 fourth quarter & fy 2015 financial review final
 
Presentation may - final
Presentation   may - finalPresentation   may - final
Presentation may - final
 
Department of Public Enterprises presentation on SOEs
Department of Public Enterprises presentation on SOEsDepartment of Public Enterprises presentation on SOEs
Department of Public Enterprises presentation on SOEs
 
11 07 51st annual eei financial conference - original (appendix mw revised)
11 07 51st annual eei financial conference - original (appendix mw revised)11 07 51st annual eei financial conference - original (appendix mw revised)
11 07 51st annual eei financial conference - original (appendix mw revised)
 
11 06-14 third quarter 2014 financial review final
11 06-14 third quarter 2014 financial review final11 06-14 third quarter 2014 financial review final
11 06-14 third quarter 2014 financial review final
 
05 08-17 first quarter 2017 financial review final
05 08-17 first quarter 2017 financial review final05 08-17 first quarter 2017 financial review final
05 08-17 first quarter 2017 financial review final
 
06 26-16 jpm energy conference final
06 26-16 jpm energy conference final06 26-16 jpm energy conference final
06 26-16 jpm energy conference final
 
3Q17 Results Presentation - CPFL Energia
3Q17 Results Presentation - CPFL Energia3Q17 Results Presentation - CPFL Energia
3Q17 Results Presentation - CPFL Energia
 
Q3 2014 AES Corporation Earnings Conference Call
Q3 2014 AES Corporation Earnings Conference CallQ3 2014 AES Corporation Earnings Conference Call
Q3 2014 AES Corporation Earnings Conference Call
 
PTNNT sale presentation June2016
PTNNT sale presentation June2016PTNNT sale presentation June2016
PTNNT sale presentation June2016
 

More from FirstQuantum

Presentation february - final
Presentation   february - finalPresentation   february - final
Presentation february - final
FirstQuantum
 
First Quantum Minerals Corporate Presentation - June 2014
First Quantum Minerals Corporate Presentation - June 2014First Quantum Minerals Corporate Presentation - June 2014
First Quantum Minerals Corporate Presentation - June 2014
FirstQuantum
 
First Quantum Minerals Corporate Presentation - January, 2014
First Quantum Minerals Corporate Presentation - January, 2014First Quantum Minerals Corporate Presentation - January, 2014
First Quantum Minerals Corporate Presentation - January, 2014
FirstQuantum
 
Corporate Presentation December 2013
Corporate Presentation December 2013Corporate Presentation December 2013
Corporate Presentation December 2013
FirstQuantum
 
Corporate Presentation - September 2013
Corporate Presentation - September 2013Corporate Presentation - September 2013
Corporate Presentation - September 2013
FirstQuantum
 
Corporate Presentation - August 2013
Corporate Presentation - August 2013Corporate Presentation - August 2013
Corporate Presentation - August 2013
FirstQuantum
 
Corporate Presentation_June 21, 2013
Corporate Presentation_June 21, 2013Corporate Presentation_June 21, 2013
Corporate Presentation_June 21, 2013
FirstQuantum
 

More from FirstQuantum (16)

Presentation may 3 final
Presentation may 3   finalPresentation may 3   final
Presentation may 3 final
 
Presentation may-3
Presentation may-3Presentation may-3
Presentation may-3
 
Presentation may - final
Presentation   may - finalPresentation   may - final
Presentation may - final
 
Presentation february - final
Presentation   february - finalPresentation   february - final
Presentation february - final
 
Corporate Presentation February 2015
Corporate Presentation February 2015Corporate Presentation February 2015
Corporate Presentation February 2015
 
Presentation september - final
Presentation   september - finalPresentation   september - final
Presentation september - final
 
First Quantum Minerals Q2 2014 Investor Presentation
First Quantum Minerals Q2 2014 Investor PresentationFirst Quantum Minerals Q2 2014 Investor Presentation
First Quantum Minerals Q2 2014 Investor Presentation
 
First Quantum Minerals Corporate Presentation - June 2014
First Quantum Minerals Corporate Presentation - June 2014First Quantum Minerals Corporate Presentation - June 2014
First Quantum Minerals Corporate Presentation - June 2014
 
Corporate Presentation - February 2014
Corporate Presentation - February 2014Corporate Presentation - February 2014
Corporate Presentation - February 2014
 
First Quantum Minerals Corporate Presentation - January, 2014
First Quantum Minerals Corporate Presentation - January, 2014First Quantum Minerals Corporate Presentation - January, 2014
First Quantum Minerals Corporate Presentation - January, 2014
 
Corporate Presentation December 2013
Corporate Presentation December 2013Corporate Presentation December 2013
Corporate Presentation December 2013
 
Corporate Presentation - November 2013
Corporate Presentation - November 2013Corporate Presentation - November 2013
Corporate Presentation - November 2013
 
Corporate Presentation
Corporate PresentationCorporate Presentation
Corporate Presentation
 
Corporate Presentation - September 2013
Corporate Presentation - September 2013Corporate Presentation - September 2013
Corporate Presentation - September 2013
 
Corporate Presentation - August 2013
Corporate Presentation - August 2013Corporate Presentation - August 2013
Corporate Presentation - August 2013
 
Corporate Presentation_June 21, 2013
Corporate Presentation_June 21, 2013Corporate Presentation_June 21, 2013
Corporate Presentation_June 21, 2013
 

Recently uploaded

Terna - 1Q 2024 Consolidated Results Presentation
Terna - 1Q 2024 Consolidated Results PresentationTerna - 1Q 2024 Consolidated Results Presentation
Terna - 1Q 2024 Consolidated Results Presentation
Terna SpA
 
Corporate Presentation Probe Canaccord Conference 2024.pdf
Corporate Presentation Probe Canaccord Conference 2024.pdfCorporate Presentation Probe Canaccord Conference 2024.pdf
Corporate Presentation Probe Canaccord Conference 2024.pdf
Probe Gold
 

Recently uploaded (20)

Teck Supplemental Information, May 2, 2024
Teck Supplemental Information, May 2, 2024Teck Supplemental Information, May 2, 2024
Teck Supplemental Information, May 2, 2024
 
Teekay Tankers Q1-24 Earnings Presentation
Teekay Tankers Q1-24 Earnings PresentationTeekay Tankers Q1-24 Earnings Presentation
Teekay Tankers Q1-24 Earnings Presentation
 
The Leonardo 1Q 2024 Results Presentation
The Leonardo 1Q 2024 Results PresentationThe Leonardo 1Q 2024 Results Presentation
The Leonardo 1Q 2024 Results Presentation
 
Camil Institutional Presentation_Mai24.pdf
Camil Institutional Presentation_Mai24.pdfCamil Institutional Presentation_Mai24.pdf
Camil Institutional Presentation_Mai24.pdf
 
AMG Quarterly Investor Presentation May 2024
AMG Quarterly Investor Presentation May 2024AMG Quarterly Investor Presentation May 2024
AMG Quarterly Investor Presentation May 2024
 
Nicola Mining Inc. Corporate Presentation May 2024
Nicola Mining Inc. Corporate Presentation May 2024Nicola Mining Inc. Corporate Presentation May 2024
Nicola Mining Inc. Corporate Presentation May 2024
 
Financial Results for the Fiscal Year Ended March 2024
Financial Results for the Fiscal Year Ended March 2024Financial Results for the Fiscal Year Ended March 2024
Financial Results for the Fiscal Year Ended March 2024
 
Terna - 1Q 2024 Consolidated Results Presentation
Terna - 1Q 2024 Consolidated Results PresentationTerna - 1Q 2024 Consolidated Results Presentation
Terna - 1Q 2024 Consolidated Results Presentation
 
Teekay Corporation Q1-24 Earnings Results
Teekay Corporation Q1-24 Earnings ResultsTeekay Corporation Q1-24 Earnings Results
Teekay Corporation Q1-24 Earnings Results
 
ITAU EQUITY_STRATEGY_WARM_UP_20240505 DHG.pdf
ITAU EQUITY_STRATEGY_WARM_UP_20240505 DHG.pdfITAU EQUITY_STRATEGY_WARM_UP_20240505 DHG.pdf
ITAU EQUITY_STRATEGY_WARM_UP_20240505 DHG.pdf
 
countries with the highest gold reserves in 2024
countries with the highest gold reserves in 2024countries with the highest gold reserves in 2024
countries with the highest gold reserves in 2024
 
Corporate Presentation Probe Canaccord Conference 2024.pdf
Corporate Presentation Probe Canaccord Conference 2024.pdfCorporate Presentation Probe Canaccord Conference 2024.pdf
Corporate Presentation Probe Canaccord Conference 2024.pdf
 
Collective Mining | Corporate Presentation - May 2024
Collective Mining | Corporate Presentation - May 2024Collective Mining | Corporate Presentation - May 2024
Collective Mining | Corporate Presentation - May 2024
 
Osisko Gold Royalties Ltd - Corporate Presentation, May 2024
Osisko Gold Royalties Ltd - Corporate Presentation, May 2024Osisko Gold Royalties Ltd - Corporate Presentation, May 2024
Osisko Gold Royalties Ltd - Corporate Presentation, May 2024
 
SME IPO Opportunity and Trends of May 2024
SME IPO Opportunity and Trends of May 2024SME IPO Opportunity and Trends of May 2024
SME IPO Opportunity and Trends of May 2024
 
Osisko Gold Royalties Ltd - Q1 2024 Results
Osisko Gold Royalties Ltd - Q1 2024 ResultsOsisko Gold Royalties Ltd - Q1 2024 Results
Osisko Gold Royalties Ltd - Q1 2024 Results
 
Osisko Development - Investor Presentation - May 2024
Osisko Development - Investor Presentation - May 2024Osisko Development - Investor Presentation - May 2024
Osisko Development - Investor Presentation - May 2024
 
Diligence Checklist for Early Stage Startups
Diligence Checklist for Early Stage StartupsDiligence Checklist for Early Stage Startups
Diligence Checklist for Early Stage Startups
 
Camil Institutional Presentation_Mai24.pdf
Camil Institutional Presentation_Mai24.pdfCamil Institutional Presentation_Mai24.pdf
Camil Institutional Presentation_Mai24.pdf
 
Western Copper and Gold - May 2024 Presentation
Western Copper and Gold - May 2024 PresentationWestern Copper and Gold - May 2024 Presentation
Western Copper and Gold - May 2024 Presentation
 

Presentation september - final

  • 1. FIRST QUANTUM MINERALS TSX: FM SEPTEMBER 2016
  • 2. CAUTIONARY NOTE REGARDING FORWARD-LOOKING STATEMENT Some of the statements contained in the following material are forward-looking statements and not statement of facts. Such statements are based on the current beliefs of management, as well as assumptions based on management information currently available. Forward-looking statements are subject to various risks, uncertainties and other factors that could cause actual results to differ materially from expected results. Readers must rely on their own evaluation of these uncertainties. Note: all dollar amounts in US dollars unless otherwise indicated 2
  • 3. DISCUSSION TOPICS EXECUTION OF ACTION PLAN DELIVERING DESIRED RESULTS Slide Stronger financial position 4, 5, 6, 7 Solid operating base 8, 10 Sustainable cost reductions 9 On-track development of the Cobre Panama project 11, 12, 13, 14 UPCOMING CATALYSTS Lower tax regime in Zambia 16 Energization of 2nd power line to Trident 16 Completion of project financing for Cobre Panama 15 Construction completion of power plants in Panama 11 Resolution of Zambian VAT receivable 16 3
  • 4. STRONGER FINANCIAL POSITION  New improved Facility:  Comprised of a $907.5M term loan and a $907.5M revolving credit facility  Improved financial covenants and an amortization schedule that starts June 2017  Same liquidity within the next 12 months compared to the previous $3.0B facility  $593M of committed undrawn facilities, $895M in unrestricted cash, working capital of $553M as at June 30 2016 IMPROVED NET DEBT:EBITDA RATIO COVENANTS PERIOD MAXIMUM RATIO Current – June 30 2017 5.50:1 July 1 2017 – December 31 2017 5.00:1 January1 2018 – June 30 2018 4.50:1 July 1 2018 – December 31 2018 3.50:1 January 1 2019 - Termination 3.25:1 4
  • 5. 5 No bond principle due until 2019 Q2 2016 liquidity: $895m unrestricted cash $593m undrawn RCF (expires 2019) Liquidity Net debt/EBITDA covenant ratio of 4.0x - within bank covenant of 5.5x Covenant Ratio Debt Maturity Profile ($m) STRONGER FINANCIAL POSITION – LONG-TERM DEBT PROFILE
  • 6. 6 STRONGER FINANCIAL POSITION – CAPITAL EXPENDITURE 1 Capital expenditure excludes capitalized interest, capitalized pre-production costs and all capital expenditures related to discontinued operations (Kevitsa) up to the date of sale. Cobre Panama Funding ($bn) FirstQuanumincurred 3rdPartyincurred FirstQuantumto spend 3rdPartto spend US$ million Q2 2016 YTD 2016 Cobre Panama 187 341 Net to First Quantum 112 205 Trident project 26 54 Stripping costs 27 43 Other sustaining capex and other projects 29 52 Total net capex1 194 354 US$ billion Total First Quantum 3rd Party Cobre Panama project Capital spend to December 2015 2.72 1.86 0.86 H1 2016 spend incurred 0.34 0.20 0.14 Estimated 2016 remaining capital spend 0.31 0.19 0.12 Estimated post 2016 capital spend 2.11 1.13 0.98 Total Cobre Panama 5.48 3.38 2.10 Funded by $5.48bn
  • 7. KEVITSA SALE COMPLETED; POSITIVE RESPONSE FROM CREDIT RATINGS AGENCIES  Completed sale of Kevitsa for $712 million in cash, excluding working capital adjustments on June 1, 2016  Positive response from credit ratings agencies:  S&P upgraded the current B- credit rating outlook to stable from negative  Moody’s upgraded from Caa1 to B-, with negative outlook  Fitch reaffirmed the B rating and upgraded the outlook to stable from negative 7
  • 8. SOLID OPERATING BASE – Q2 2016 RESULTS1 Set a new quarterly records for copper production and sales of 131,349 tonnes and 132,030 tonnes, respectively Fifth consecutive quarter of lower copper cash cost (“C1”), All-in sustaining (“AISC”) and total cost (“C3”) per lb:  C1 = $0.98; AISC = $1.32; C3 = $1.80 Cost profile lowered:  Guidance for the year 2016:  C1 = $1.05 to $1.15 per lb2  AISC = $1.40 to $1.60 per lb2 1 Continuing operations which exclude Kevitsa 2 Excluding Sentinel 8
  • 9. $34 $36 $10 $39 Savings Q2’16 vs Q2‘15 $ millions Employee/Contractors/Maintenance costs Fuel/Power/Freight/Consumables G&A + Exploration Smelter savings1 Adjusted to remove the impact of FX 9 SUSTAINABLE COST REDUCTIONS1 – Q2 2016 VS. Q2 2015 $119 million  Net acid costs $39m lower driven by Kansanshi smelter production of sulphuric acid  Lower employee, contractor and maintenance costs  Lower consumable, fuel, power and freight costs  Lower general and administration and exploration costs of $10m excludes the impact of FX  Zambian royalty costs $38m lower as rate was 20% in Q2 2015 and reduced to 9% in April/May  Zambian royalty further reduced to 5% in June 2016
  • 10. SOLID OPERATING BASE Active sales hedge programs:  Copper: contributed $0.08 per lb in Q2 2016; $0.36 per lb for six months 2016  Copper: open position at July 27, 2016 = 309,650 tonnes @ $2.20 per lb  Nickel: contributed $0.13 per lb in Q2 2016  Nickel: open position at July 27, 2016 = 11,004 tonnes @ $4.68 per lb Forecast production 10 2016F 2017F 2018F Copper (excl Sentinel) – 000’s tonnes 380 380 385 Copper – Sentinel – 000’s tonnes 135-155 210-240 230-260 Nickel – 000’s contained tonnes 23 28 28 Gold – 000’s ounces 210 208 208
  • 11.  Most challenging aspect of the project is well under control  Priority given to the power station and associated infrastructure  Revenues from power sales expected in 2nd half 2017  Expenditures being managed to suit market conditions  Capex lowered to $5.48B COBRE PANAMA DEVELOPMENT ON TRACK 11
  • 12. 12 COBRE PANAMA – POWER PLANT & PORT OVERVIEW
  • 13. 13 COBRE PANAMA – POWER PLANT – 150 MW UNIT 1
  • 14. 14 COBRE PANAMA – BALL MILL AND MOTOR INSTALLATION
  • 15. ADVANCING THE PROJECT FINANCING PROCESS  Cost competitive, long-term financing  Phase 1 completed  Phase 2 initiated covering due diligence, information memorandum, engaging consultants, ECA and bank selection, and term sheet negotiation  Financial close could be achieved within 12 months  Targeting up to $2.5B 15
  • 16. POSITIVE ZAMBIAN DEVELOPMENTS  Power situation has stabilized:  Sentinel currently receiving ~80% of total power requirement  Itezhi-Tehzi hydro is feeding ~120MW into the system  Maamba Collieries has introduced 150MW; expects to introduce the 2nd 150MW (300MW total) shortly  Completion of the Maamba switchyard is ongoing – expect completion in about a month  Electrification of 2nd power line planned to follow shortly thereafter  Changes to Zambian mining tax regime enacted June 1 2016:  Variable profits tax repealed  20% royalty lowered to between 4-6% depending on the monthly average LME copper trading price (currently 5%)  VAT accrued to June 30 2016 = $241 million  Refunds of $72M received between March 2015 – June 2016  Discussions with relevant authorities continue  General elections completed; incumbent re-elected 16
  • 17. FIRST QUANTUM MINERALS TSX: FM SEPTEMBER 2016