SlideShare a Scribd company logo
1 of 46
Download to read offline
TURNING VISION INTO REALITY
JUNE2014
TSX: FM; LSE: FQM
CAUTIONARY NOTE REGARDING FORWARD-LOOKING STATEMENT
Some of the statements contained in the following material are forward-looking
statements and not statement of facts. Such statements are based on the current
beliefs of management, as well as assumptions based on management information
currently available.
Forward-looking statements are subject to various risks, uncertainties and other
factors that could cause actual results to differ materially from expected results.
Readers must rely on their own evaluation of these uncertainties.
Note: all dollar amounts in US dollars unless otherwise indicated
2
FIRST QUANTUM MINERALS AT A GLANCE
3
• A Global Company
– Operations and projects in 8 countries
• Efficient Operations
– 7 operations
– 2013 production:
 copper 412,281 tonnes
 nickel 47,066 tonnes
 gold 248,078 ounces
– Cash cost of production
 copper $1.30/lb; nickel $5.02/lb
• Strong Liquidity & Cash Flow
– Cash at March 31’14 = $747.2M
– Cash from operations = $370.1M
– Available & undrawn facilities of $1.3B
– Senior Notes = $850M
• Industry-Leading Growth
– 5 major projects under development
– Production capacities to rise to 1.1 Mtpa
for copper and 110 ktpa for nickel by 2018
• Unique Core Strength
– In-house project development team
– Delivered projects at an average of 40% of
the industry’s average capital per tonne of
capacity
• Strong Track Record
– Delivered over $2.4B in projects within 6%
of budget
– Returned a compounded annual gain of
over 30% since listing
GOOD OPERATING PERFORMANCE CONTINUES INTO 2014
• Production up
– Copper up 43% to 113,118 tonnes
– Nickel up 7% to 11,838 tonnes
– Gold up 8% to 60,164 ounces
– Platinum and palladium up 22% to
15,342 ounces
• Cash cost lowered
– Copper down 9% to $1.38 per pound
– Nickel down 18% to $4.37 per pound
• Comparative net earnings of $126.8
million or $0.22 per share including:
– $26.7 million or $0.05 per share of
unfavorable, recurring acquisition-
related adjustments.
– Unfavorable impact of $152 million
from lower commodity prices and the
build-up in concentrate inventory at
Kansanshi
4
Q1 '13 Q2'13 Q3'13 Q4'13 Q1'14 Q1 '13 Q2'13 Q3'13 Q4'13 Q1'14 Q1 '13 Q2'13 Q3'13 Q4'13 Q1'14 Q1 '13 Q2 '13 Q3'13 Q4'13 Q1'14
Copper Production
000’s tonnes
Nickel Production
000’s tonnes
Gold Production
000’s ounces
Copper C1 Cost
US$/lb
OUR PIORITIES
 Build a leading copper-focused company
 Maintain an optimal capital and financing
structure
 Operate efficiently
5
BUILDING A LEADING COPPER-FOCUSED COMPANY
Cobre Panama – A Tier 1 Copper Project
 Acquired March 2013
 Critical review following acquisition
– Focused mainly on Engineering,
Contracts and Construction initially
– Copied major areas of the design of
the almost-complete Sentinel
process plant
 Made significant changes
– Unwound ~US$1.7B of commitments
– Rectified multiple deficiencies
– Readied the site for construction
– Connected mine site to port site
– Changed to an in-house, self-perform
arrangement
6
BUILDING A LEADING COPPER-FOCUSED COMPANY
Cobre Panama – A Tier 1 Copper Project
 A larger, more robust project
– Installed capacity Yrs 1-10 = ~70 Mtpa
 17% higher than prior
 Expansion up to 100 Mtpa
beyond
Yr 10
– Average annual LOM* copper
production of 320,000 tonnes
 ~ 20% higher than prior
– Average annual LOM by-product
production
 100,000 ounces gold; 1,800,000
ounces silver and 3,500 tonnes
molybdenum
 Mine life of 34 years
7
* On the basis of the current Resource estimate and the planned installed capacity of about 70 Mtpa
BUILDING A LEADING COPPER-FOCUSED COMPANY
Cobre Panama – A Tier 1 Copper Project
 Capex estimate of $6.4 billion
– inclusive of $913 million incurred
prior to acquisition
 Capital per installed tonne of capacity
of $17,125
– ~25% lower than prior
 A realistic and well-defined timeframe
– 230 KV overland power line – Q4 ’15
– 300 MW powerstation – Q1 ‘17
– Tailings management facility – Q2 ’17
– Process plant construction – Q3 ‘17
– Commissioning & 1st concentrate
production – Q4 ‘17
8
COBRE PANAMA PROJECT – PROCESS PLANT SITE EARTHWORKS
9
COBRE PANAMA PROJECT – MILL PAD EARTHWORKS
10
COBRE PANAMA PROJECT – PROCESS PLANT STOCKPILE PAD
11
COBRE PANAMA PROJECT – POWER STATION AREA
12
COBRE PANAMA PROJECT
BREAKWATER AND MATERIAL OFFLOADING FACILITY
13
 Phase 1
– Processing capacity of 1.2 Mtpa
– Combination of concentrate from
Kansanshi & Sentinel
– Average copper grade 26%
 Copper production 300,000 Tpa;
acid production 1.0 Mtpa
 Commissioning from 2H2014
 Estimated savings:
– US$340M - US$510M/year
 Phase 2 being planned to increase
processing capacity to between 2 to 2.4
Mtpa in 2017
BUILDING A LEADING COPPER-FOCUSED COMPANY
Copper Smelting Complex
14
BUILDING A LEADING COPPER-FOCUSED COMPANY
Copper Smelting Complex - Phase 1 Smelter – Cold Box Lifts – April 2014
15
BUILDING A LEADING COPPER-FOCUSED COMPANY
Trident Project
 Located ~ 140 km northwest of
Solwezi, northern Zambia
 Includes Sentinel copper and
Enterprise nickel
 Sentinel’s M&I resource of 1,027 Mt at
0.51% Cu grade, containing 5.2 Mt Cu
 Estimates:
– 2.2:1 LOM strip ratio
– >15 years mine life
– Production of up to 300 Ktpa
copper; 38 to 60 Ktpa nickel in
concentrate
– US$2.0B capex
– Completion from mid-2014 for
Sentinel & Q1 2015 for Enterprise
16
• Flexible 4 Mtpa nickel facility can
augment copper capacity
• 55 Mtpa copper throughput
• 3 semi-mobile in pit crushers and
assembly of large scale mining
equipment
• Large operating SAG/Ball mill trains
(100MW milling power)
• 265 Kt of freight = 14,500 truckloads
of materials
• 2 rivers to be dammed/diverted
BUILDING A LEADING COPPER-FOCUSED COMPANY
Trident Project
17
• Life of mine tailings storage facility
• 600 km of 330kV power
transmission lines from Lumwana –
Kalumbila – Lusaka West
• 690 staff houses plus 590 houses in
resettlement
• Development of a new town,
airport, clinic, school etc….
BUILDING A LEADING COPPER-FOCUSED COMPANY
Trident Project
18
19
SENTINEL – 80 METER FEED SHUTTLE CONVEYOR TRUSS - APRIL 2014
SENTINEL - 100MW MILLING – 2 X 40’SAG MILLS + 2 X 28’BALL MILLS
20
SENIOR HOUSING - SINGLES 31-MAR-2013
SENIOR HOUSING AREA 28-FEB-2013
SPORTS FACILITY 04-NOV-2013
TRIDENT PREPARATORY SCHOOL 05-NOV-2013
SENTINEL – COMMUNITY DEVELOPMENT
21
TRUST SCHOOL 05-NOV-2013
AFFORDABLE HOUSING LAYOUT TEACHER’S HOME 3-JAN-2014
COMPLETED 4-BEDROOM HOUSE 3-JAN-2014
SENTINEL – COMMUNITY DEVELOPMENT
22
• Refinanced the short-term US$2.5B revolver at FQM (Akubra) with a $1.2B Term
Loan Facility five-year Term and and a $1.8B Revolving Credit Facility
• Exchanged the FQM (Akubra) Inc. US$1.49B 8.75% 2020 and US$500M 7.50% 2021
notes for new 6.75% 6-year notes and new 7.00% 7-year notes
• In conjunction with the Exchange Offer, made covenant changes to better match
the Company's needs going forward
• Made certain amendments to the existing indentures of the US$350M 7.25%
Senior Notes due 2019 through a consent solicitation offer to bondholders
• Retired the project financing at Kevitsa and Kansanshi and put in place a $350M
unsecured facility at Kansanshi
• Completed $850M 7.25% Senior Notes Offering due 2022
23
OPTIMIZED CAPITAL STRUCTURE & FINANCIAL FLEXIBILITY
As at March 31, 2014
Illustrative Pro Forma Corporate Structure Chart
24
ONE OF THE
FEW MINING
COMPANIES
INVESTING IN
BUILDING CAPACITY
25
A Small Copper Surplus Now, But…..
• EXPLORATION
– Majors have cut back on exploration and juniors are mainly un-financeable
– It takes 12-15 years to get from discovery to production
• BROWN FIELD EXPANSIONS
– Should be lower capital intensity but are not
– Capital projects cancelled or deferred from shareholder pressure
• GREENFIELD PROJECTS
– High capital intensity
– Capital projects cancelled or deferred as above
– Very poor track record of developing projects efficiently
26
CURRENT STATE OF THE COPPER INDUSTRY
27
CURRENT STATE OF THE COPPER INDUSTRY
Results in a Looming Deficit
Global copper mine supply growth and price
0%
0%
1%
0%
-1%
7%
9%
4%
7%
5%
4%
3%
-1%
1%
7%
2% 2%
3%
1%
2%
0%
0%
3%
7%
-2%
0%
2%
4%
6%
8%
10%
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
2013
Copperminesupplygrowth%YoY
0
50
100
150
200
250
300
350
400
Copperprice,cents/lb
Mine supply growth Price
Source: Wood Mackenzie, Macquarie Research, February 2014
28
LACK OF SUPPLY RESPONSE TO PRICE WAS STAGGERING OVER 2006-2012PERIOD
So why is the industry cutting investment?
 Pressure from shareholders who have a much shorter time horizon than
miners
This is not going to change
 There is not much out there that the majors want
With the cut-back in exploration, this is unlikely to change
 The capital intensity of new projects is rising rapidly
Why is this so?
29
SO THE SEEDS OF THE NEXT COPPER PRICE BUBBLE ARE ALREADY SOWN …
AND IT IS COMING SOON
Source: Brook Hunt, Freeport McMoRan
Average Copper Grades
30
 Falling grades
• Difficult geographies
• Geopolitics
WHY IS CAPITAL INTENSITY RISING?
Source: Wood Mackenzie, CRU, Macquarie Research, February 2014
Weighted average copper project by year of delivery
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
1.8
0 5000 10000 15000 20000 25000 30000 35000 40000
Life of mine capital intensity
Averageheadgrade
2000-2011
2012-2018f
2000
2001
2002
2004
2005
2006
2007
2008 2009
2010
2011
2012
2013f
2014f
2015f
2016f
2017f
2018f
AS HEAD GRADES FALL, CAPITAL INTENSITY RISES RAPIDLY
31
0 5,000 10,000 15,000 20,000 25,000 30,000
Kansanshi (First Quantum)
Kansanshi Expansion (First Quantum)
Sentinel (First Quantum)
Buenavista DC (Southern Copper)
Antapaccay (Xstrata)
Antamina (BHP)
Guelb Moghrein (First Quantum)
Canariaco (Candente)
Las Cruces (Inmet)
Los Bronces (Anglo American)
Oyu Tolgoi (Rio Tinto)
Ministro Mina Hales (Codelco)
Sierra Gorda (KGHM)
Toromocho (Chinalco)
Tampakan (Xstrata)
Las Bambas (Xstrata)
CobrePanama (FirstQuantum)
Galeno (Minmetals)
CAPITALINTENSITY
(US$/t)
Source: First Quantum, Broker Research
A producing First Quantum mine
A current First Quantum project
BUT IT IS POSSIBLE TO BUILD PROJECTS EFFICIENTLY
32
Weighted average copper project by year of delivery
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
1.8
0 5000 10000 15000 20000 25000 30000 35000 40000
Life of mine capital intensity
Averageheadgrade
2000-2011
2012-2018f
2000
2001
2002
2004
2005
2006
2007
2008 2009
2010
2011
2012
2013f
2014f
2015f
2016f
2017f
2018f
COBRE PANAMA
33
Source: Wood Mackenzie, CRU, Macquarie Research,
February 2014
COBRE PANAMA HAS SUBSTANTIALLY LOWER CAPITAL INTENSITY
COMPARED TO OTHER PROJECTS WITH SIMILAR START-UP HORIZONS
EFFICIENT
OPERATIONS
34
 Located near Solwezi in the north
western Province of Zambia
 First production in 2005
 Open pit mining
 Flexible ore treatment to allow for
variation in ore type :
– sulphide circuit; oxide circuit; gold
facility
 As at December 31, 2013, the
estimated mine life was ~17 years
 Workforce = ~1,937
35
EFFICIENT OPERATIONS
Kansanshi Cu-Au mine, Zambia
 Q1 2014
– 71 kt of copper
– 40 kozs of gold
– $1.57/lb copper C1 cash cost
 2014 outlook
– 255 to 270 kt of copper
– 145 to 160 kozs of gold
 Multi-phase capacity expansion project
– 2012 – 2017
60% increase in overall production capacity
– 2012 – 2014
130% increase in oxide production capacity
– 2017
90% increase in sulphide production capacity
36
Project Capacity Status
Estimate
Cost
Production
Impact
(US$M)
Oxide 7.2 Mtpa Complete 34 Copper: 10,000 - 15,000 Tpa
Oxide 14.5 Mtpa Complete 280 Copper: 60,000 - 75,000 Tpa
Sulphide 25 Mtpa 2017 565 Copper: 60,000 - 70,000 Tpa
EFFICIENT OPERATIONS
Kansanshi Cu-Au mine, Zambia
 Acquired in March 2013
 Estimated mine life of 9 years;
potential for extension
 Current average reserve grade of 5.4%
copper
 Workforce = ~254
 Q1 2014
– 19 Kt of copper; $0.98/lb copper C1
cash cost
 2014 Outlook
– 69 to 72 kt of copper
37
EFFICIENT OPERATIONS
Las Cruces Cu mine, Spain
 100% ownership
 Located 250 kilometres northeast of
the nation’s capital, Nouakchott
 As at December 31, 2013, the
estimated mine life was ~ 8 years
(including stockpiles) based on current
operations
 First production in 2006
 Workforce = ~1,170
38
EFFICIENT OPERATIONS
Guelb Moghrein Cu-Au mine, Mauritania
EFFICIENT OPERATIONS
Guelb Moghrein Cu-Au mine, Mauritania
 Q1 2014
– 9 kt tonnes of copper
– 14 kozs of gold
– $1.56/lb copper C1 cash cost
 2014 Outlook
– 36 to 39 kt of copper
– 55 to 60 k ozs of gold
 Magnetite plant project:
– In detailed design stage
– Estimated capex of $50M
– Expected production of 1 – 2 Mtpa tonnes
of 69% Fe magnetite concentrate
– Expected start up in mid-2014
– Expected to extend mine life through
retreatment of tailings dam
39
 Acquired as a decommissioned plant
in 2010
 First production within 20 months
of purchase
 Estimated mine life of 32 years
 Commercial production declared
Dec 2011
 Workforce = ~428
 Q1 2014
– 9 kt of nickel @ $4.02/lb C1 cash cost
 2014 Outlook
– 33 to 37 kt of nickel
40
EFFICIENT OPERATIONS
Ravensthorpe Ni mine, Australia
 Built, commissioned and started commercial
operations within 36 months of board approval
 Estimated mine life of 29 years
 Commercial production declared August 2012
 Workforce = ~337
 Further potential
– Process optimization
– Approval to increase throughput to a
maximum of 10 Mtpa from 5.5 Mtpa
 Q1 2014 = 4 kt of copper @ $1.52/lb C1 cash
cost ; 2 kt of nickel @ $5.19/lb nickel C1 cash
cost
 2014 Outlook
– 69 to 72 kt of copper; 9 to 10 kt of nickel
41
EFFICIENT OPERATIONS
Kevitsa Ni-Cu-PGE mine, Finland
 Acquired in March 2013
 Estimated mine life of 6 years with
potential for an additional 3 years
 Average grade of 3.1% copper and
3.6% zinc
 Workforce = ~520 employees
 Q1 2014
– 7 kt of copper; 10 kt of zinc
– $0.76/lb copper C1 cash cost
 2014 Outlook
– 27 to 29 kt of copper
– 38 to 42 kt of zinc
42
EFFICIENT OPERATIONS
Çayeli Cu-Zn mine, Turkey
 Acquired in March 2013
 One of the most efficient underground
mines in the world
 Estimated mine life of 6 years
 Average grade of 1.05% copper and
1.79% zinc
 Workforce = ~228 employees
 Q1 2014
– 4 kt of copper; 5 kt of zinc
– $0.52/lb copper C1 cash cost
 2014 Outlook
– 14 to 15 kt of copper; 21 to 23 kt of zinc
EFFICIENT OPERATIONS
Pyhäsalmi Cu-Zn mine, Finland
43
• Production
– Copper between 418,000 - 444,000
tonnes
– Nickel between 42,000 - 47,000
tonnes
– Gold between 221,000 - 246,000
ounces
– Zinc between 59,000 - 65,000 tonnes
– Palladium and platinum between
22,000 - 24,000 ounces each
• C1 cash cost
– Copper between $1.32 -
$1.48/lb.
– Nickel between $4.40 - $4.90/lb
• Capital expenditures
– $2.1B to $2.2B
44
FULL YEAR 2014 GUIDANCE
A COPPER-FOCUSED, GLOBAL COMPANY
Signifiant Nickel and Gold Production
Operations and Projects in 8 countries
High-Quality, Stable, Efficient Operations
Strong Liquidity & Cash Flow
Industry-Leading Growth
Unique Core Strength of In-House Project
Development
Strong Track Record of Project
Development and Shareholder Returns
Copper
72%
Nickel
16%
Gold
6%
Zinc
2%
Other
3%
Revenues
TURNING VISION INTO REALITY
JUNE2014
TSX: FM; LSE: FQM

More Related Content

What's hot

MRL Corporation (ASX:MRF) Investor Roadshow Presentation Sept 2015
MRL Corporation (ASX:MRF) Investor Roadshow  Presentation Sept 2015 MRL Corporation (ASX:MRF) Investor Roadshow  Presentation Sept 2015
MRL Corporation (ASX:MRF) Investor Roadshow Presentation Sept 2015 Symposium
 
Symposium Investor Roadshow November 2015 - WPG Resources
Symposium Investor Roadshow November 2015 - WPG ResourcesSymposium Investor Roadshow November 2015 - WPG Resources
Symposium Investor Roadshow November 2015 - WPG ResourcesSymposium
 
Nov. 2013 Champion Corporate Presentation - English
Nov. 2013 Champion Corporate Presentation - EnglishNov. 2013 Champion Corporate Presentation - English
Nov. 2013 Champion Corporate Presentation - EnglishChampionMines
 
Presentation december - final
Presentation   december - finalPresentation   december - final
Presentation december - finalFirstQuantum
 
Canada cobalt-presentation-october-16-2019
Canada cobalt-presentation-october-16-2019Canada cobalt-presentation-october-16-2019
Canada cobalt-presentation-october-16-2019MomentumPR
 
Auriga Gold Corp. (AIA.V) - Maverick Gold Project Presentation May 2014.
Auriga Gold Corp. (AIA.V) - Maverick Gold Project Presentation May 2014. Auriga Gold Corp. (AIA.V) - Maverick Gold Project Presentation May 2014.
Auriga Gold Corp. (AIA.V) - Maverick Gold Project Presentation May 2014. Gorden Glenn
 
Canada cobalt-presentation-june-4-2019
Canada cobalt-presentation-june-4-2019Canada cobalt-presentation-june-4-2019
Canada cobalt-presentation-june-4-2019MomentumPR
 
newmont mining 09_NEM_Final
newmont mining 09_NEM_Finalnewmont mining 09_NEM_Final
newmont mining 09_NEM_Finalfinance37
 
DFS Section 2 Executive Summary
DFS Section 2 Executive SummaryDFS Section 2 Executive Summary
DFS Section 2 Executive SummaryFrank Henry
 
Alabama Graphite Corp. Announces Positive Preliminary Economic Assessment for...
Alabama Graphite Corp. Announces Positive Preliminary Economic Assessment for...Alabama Graphite Corp. Announces Positive Preliminary Economic Assessment for...
Alabama Graphite Corp. Announces Positive Preliminary Economic Assessment for...Ann-Marie Pamplin
 
Woxna The Rebirth of Flike Graphite Production in Sweden
Woxna The Rebirth of Flike Graphite Production in SwedenWoxna The Rebirth of Flike Graphite Production in Sweden
Woxna The Rebirth of Flike Graphite Production in SwedenGraphite Graphite
 
Feb. 2013 Champion Corporate Presentation - English
Feb. 2013 Champion Corporate Presentation - EnglishFeb. 2013 Champion Corporate Presentation - English
Feb. 2013 Champion Corporate Presentation - EnglishChampionMines
 
Eia lucky electric power company 660 mw coal power project
Eia  lucky electric power company  660 mw coal power projectEia  lucky electric power company  660 mw coal power project
Eia lucky electric power company 660 mw coal power projectzubeditufail
 
Sept. 2013 Champion Corporate Presentation - English
Sept. 2013 Champion Corporate Presentation - EnglishSept. 2013 Champion Corporate Presentation - English
Sept. 2013 Champion Corporate Presentation - EnglishChampionMines
 
Investor presentation macquarie
Investor presentation   macquarieInvestor presentation   macquarie
Investor presentation macquarieFirstQuantum
 
Huguenot Project Presentation
Huguenot Project PresentationHuguenot Project Presentation
Huguenot Project PresentationColonialCoal
 
Annual & Special meeting
Annual & Special meetingAnnual & Special meeting
Annual & Special meetingLake Shore Gold
 
Energy Equipment & Services: Industry Insights & Happenings
Energy Equipment & Services: Industry Insights & HappeningsEnergy Equipment & Services: Industry Insights & Happenings
Energy Equipment & Services: Industry Insights & HappeningsCapstone Headwaters
 

What's hot (19)

MRL Corporation (ASX:MRF) Investor Roadshow Presentation Sept 2015
MRL Corporation (ASX:MRF) Investor Roadshow  Presentation Sept 2015 MRL Corporation (ASX:MRF) Investor Roadshow  Presentation Sept 2015
MRL Corporation (ASX:MRF) Investor Roadshow Presentation Sept 2015
 
Symposium Investor Roadshow November 2015 - WPG Resources
Symposium Investor Roadshow November 2015 - WPG ResourcesSymposium Investor Roadshow November 2015 - WPG Resources
Symposium Investor Roadshow November 2015 - WPG Resources
 
Nov. 2013 Champion Corporate Presentation - English
Nov. 2013 Champion Corporate Presentation - EnglishNov. 2013 Champion Corporate Presentation - English
Nov. 2013 Champion Corporate Presentation - English
 
Presentation december - final
Presentation   december - finalPresentation   december - final
Presentation december - final
 
Canada cobalt-presentation-october-16-2019
Canada cobalt-presentation-october-16-2019Canada cobalt-presentation-october-16-2019
Canada cobalt-presentation-october-16-2019
 
Auriga Gold Corp. (AIA.V) - Maverick Gold Project Presentation May 2014.
Auriga Gold Corp. (AIA.V) - Maverick Gold Project Presentation May 2014. Auriga Gold Corp. (AIA.V) - Maverick Gold Project Presentation May 2014.
Auriga Gold Corp. (AIA.V) - Maverick Gold Project Presentation May 2014.
 
Canada cobalt-presentation-june-4-2019
Canada cobalt-presentation-june-4-2019Canada cobalt-presentation-june-4-2019
Canada cobalt-presentation-june-4-2019
 
newmont mining 09_NEM_Final
newmont mining 09_NEM_Finalnewmont mining 09_NEM_Final
newmont mining 09_NEM_Final
 
DFS Section 2 Executive Summary
DFS Section 2 Executive SummaryDFS Section 2 Executive Summary
DFS Section 2 Executive Summary
 
Alabama Graphite Corp. Announces Positive Preliminary Economic Assessment for...
Alabama Graphite Corp. Announces Positive Preliminary Economic Assessment for...Alabama Graphite Corp. Announces Positive Preliminary Economic Assessment for...
Alabama Graphite Corp. Announces Positive Preliminary Economic Assessment for...
 
Woxna The Rebirth of Flike Graphite Production in Sweden
Woxna The Rebirth of Flike Graphite Production in SwedenWoxna The Rebirth of Flike Graphite Production in Sweden
Woxna The Rebirth of Flike Graphite Production in Sweden
 
Feb. 2013 Champion Corporate Presentation - English
Feb. 2013 Champion Corporate Presentation - EnglishFeb. 2013 Champion Corporate Presentation - English
Feb. 2013 Champion Corporate Presentation - English
 
Eia lucky electric power company 660 mw coal power project
Eia  lucky electric power company  660 mw coal power projectEia  lucky electric power company  660 mw coal power project
Eia lucky electric power company 660 mw coal power project
 
Sept. 2013 Champion Corporate Presentation - English
Sept. 2013 Champion Corporate Presentation - EnglishSept. 2013 Champion Corporate Presentation - English
Sept. 2013 Champion Corporate Presentation - English
 
Marketing Presentation
Marketing PresentationMarketing Presentation
Marketing Presentation
 
Investor presentation macquarie
Investor presentation   macquarieInvestor presentation   macquarie
Investor presentation macquarie
 
Huguenot Project Presentation
Huguenot Project PresentationHuguenot Project Presentation
Huguenot Project Presentation
 
Annual & Special meeting
Annual & Special meetingAnnual & Special meeting
Annual & Special meeting
 
Energy Equipment & Services: Industry Insights & Happenings
Energy Equipment & Services: Industry Insights & HappeningsEnergy Equipment & Services: Industry Insights & Happenings
Energy Equipment & Services: Industry Insights & Happenings
 

Similar to First Quantum Minerals Corporate Presentation - June 2014

Corporate Presentation - February 2014
Corporate Presentation - February 2014Corporate Presentation - February 2014
Corporate Presentation - February 2014FirstQuantum
 
First Quantum Minerals Corporate Presentation - January, 2014
First Quantum Minerals Corporate Presentation - January, 2014First Quantum Minerals Corporate Presentation - January, 2014
First Quantum Minerals Corporate Presentation - January, 2014FirstQuantum
 
Corporate Presentation - November 2013
Corporate Presentation - November 2013Corporate Presentation - November 2013
Corporate Presentation - November 2013FirstQuantum
 
Presentation may - final
Presentation   may - finalPresentation   may - final
Presentation may - finalFirstQuantum
 
Corporate Presentation - August 2013
Corporate Presentation - August 2013Corporate Presentation - August 2013
Corporate Presentation - August 2013FirstQuantum
 
Corporate Presentation February 2015
Corporate Presentation February 2015Corporate Presentation February 2015
Corporate Presentation February 2015FirstQuantum
 
Presentation february - final
Presentation   february - finalPresentation   february - final
Presentation february - finalFirstQuantum
 
Presentation march - final
Presentation   march - finalPresentation   march - final
Presentation march - finalFirstQuantum
 
Corporate Presentation December 2012
Corporate Presentation December 2012Corporate Presentation December 2012
Corporate Presentation December 2012FirstQuantum
 
Investor Presentation - October 2014
Investor Presentation - October 2014Investor Presentation - October 2014
Investor Presentation - October 2014CobreDelMayo
 
Oct. 2013 Champion Corporate Presentation - English
Oct. 2013 Champion Corporate Presentation - EnglishOct. 2013 Champion Corporate Presentation - English
Oct. 2013 Champion Corporate Presentation - EnglishChampionMines
 
Q3 9 months 2014 kghmi bond call
Q3 9 months 2014 kghmi bond callQ3 9 months 2014 kghmi bond call
Q3 9 months 2014 kghmi bond callKGHM
 
Consolidated investor presentation 2014 10 28
Consolidated investor presentation 2014 10 28Consolidated investor presentation 2014 10 28
Consolidated investor presentation 2014 10 28CobreDelMayo
 
AMEC Convention 2017 - Driving the next cycle
AMEC Convention 2017 - Driving the next cycleAMEC Convention 2017 - Driving the next cycle
AMEC Convention 2017 - Driving the next cycleAlkane Resources
 
20150527_KrebsD_The Kvanefjeld Project_0
20150527_KrebsD_The Kvanefjeld Project_020150527_KrebsD_The Kvanefjeld Project_0
20150527_KrebsD_The Kvanefjeld Project_0Damien Krebs
 
Investor Presentation | MacPherson' Resources (ASX:MRP) | Gold Investment Sym...
Investor Presentation | MacPherson' Resources (ASX:MRP) | Gold Investment Sym...Investor Presentation | MacPherson' Resources (ASX:MRP) | Gold Investment Sym...
Investor Presentation | MacPherson' Resources (ASX:MRP) | Gold Investment Sym...Symposium
 
Q1 2014 kghmi results bond call - final
Q1 2014 kghmi results bond call - finalQ1 2014 kghmi results bond call - final
Q1 2014 kghmi results bond call - finalKGHM
 
Fortune Minerals June 2012 Investor Presentation
Fortune Minerals June 2012 Investor PresentationFortune Minerals June 2012 Investor Presentation
Fortune Minerals June 2012 Investor PresentationCompany Spotlight
 
December 10, 2013 Analyst Site Visit
December 10, 2013 Analyst Site VisitDecember 10, 2013 Analyst Site Visit
December 10, 2013 Analyst Site VisitLake Shore Gold
 

Similar to First Quantum Minerals Corporate Presentation - June 2014 (20)

Corporate Presentation - February 2014
Corporate Presentation - February 2014Corporate Presentation - February 2014
Corporate Presentation - February 2014
 
First Quantum Minerals Corporate Presentation - January, 2014
First Quantum Minerals Corporate Presentation - January, 2014First Quantum Minerals Corporate Presentation - January, 2014
First Quantum Minerals Corporate Presentation - January, 2014
 
Corporate Presentation - November 2013
Corporate Presentation - November 2013Corporate Presentation - November 2013
Corporate Presentation - November 2013
 
Presentation may - final
Presentation   may - finalPresentation   may - final
Presentation may - final
 
Corporate Presentation - August 2013
Corporate Presentation - August 2013Corporate Presentation - August 2013
Corporate Presentation - August 2013
 
Corporate Presentation February 2015
Corporate Presentation February 2015Corporate Presentation February 2015
Corporate Presentation February 2015
 
Presentation february - final
Presentation   february - finalPresentation   february - final
Presentation february - final
 
Presentation march - final
Presentation   march - finalPresentation   march - final
Presentation march - final
 
Corporate Presentation December 2012
Corporate Presentation December 2012Corporate Presentation December 2012
Corporate Presentation December 2012
 
Investor Presentation - October 2014
Investor Presentation - October 2014Investor Presentation - October 2014
Investor Presentation - October 2014
 
Rare earths: not so rare but sought after
Rare earths: not so rare but sought afterRare earths: not so rare but sought after
Rare earths: not so rare but sought after
 
Oct. 2013 Champion Corporate Presentation - English
Oct. 2013 Champion Corporate Presentation - EnglishOct. 2013 Champion Corporate Presentation - English
Oct. 2013 Champion Corporate Presentation - English
 
Q3 9 months 2014 kghmi bond call
Q3 9 months 2014 kghmi bond callQ3 9 months 2014 kghmi bond call
Q3 9 months 2014 kghmi bond call
 
Consolidated investor presentation 2014 10 28
Consolidated investor presentation 2014 10 28Consolidated investor presentation 2014 10 28
Consolidated investor presentation 2014 10 28
 
AMEC Convention 2017 - Driving the next cycle
AMEC Convention 2017 - Driving the next cycleAMEC Convention 2017 - Driving the next cycle
AMEC Convention 2017 - Driving the next cycle
 
20150527_KrebsD_The Kvanefjeld Project_0
20150527_KrebsD_The Kvanefjeld Project_020150527_KrebsD_The Kvanefjeld Project_0
20150527_KrebsD_The Kvanefjeld Project_0
 
Investor Presentation | MacPherson' Resources (ASX:MRP) | Gold Investment Sym...
Investor Presentation | MacPherson' Resources (ASX:MRP) | Gold Investment Sym...Investor Presentation | MacPherson' Resources (ASX:MRP) | Gold Investment Sym...
Investor Presentation | MacPherson' Resources (ASX:MRP) | Gold Investment Sym...
 
Q1 2014 kghmi results bond call - final
Q1 2014 kghmi results bond call - finalQ1 2014 kghmi results bond call - final
Q1 2014 kghmi results bond call - final
 
Fortune Minerals June 2012 Investor Presentation
Fortune Minerals June 2012 Investor PresentationFortune Minerals June 2012 Investor Presentation
Fortune Minerals June 2012 Investor Presentation
 
December 10, 2013 Analyst Site Visit
December 10, 2013 Analyst Site VisitDecember 10, 2013 Analyst Site Visit
December 10, 2013 Analyst Site Visit
 

More from FirstQuantum

Presentation may 3 final
Presentation may 3   finalPresentation may 3   final
Presentation may 3 finalFirstQuantum
 
Presentation may-3
Presentation may-3Presentation may-3
Presentation may-3FirstQuantum
 
Presentation bmo - final
Presentation   bmo - finalPresentation   bmo - final
Presentation bmo - finalFirstQuantum
 
Presentation january 2018 - final
Presentation   january 2018 - finalPresentation   january 2018 - final
Presentation january 2018 - finalFirstQuantum
 
Presentation november final
Presentation   november finalPresentation   november final
Presentation november finalFirstQuantum
 
Presentation november - final
Presentation   november - finalPresentation   november - final
Presentation november - finalFirstQuantum
 
Presentation september - final
Presentation   september - finalPresentation   september - final
Presentation september - finalFirstQuantum
 
Presentation june - final
Presentation   june - finalPresentation   june - final
Presentation june - finalFirstQuantum
 
Presentation may - final
Presentation   may - finalPresentation   may - final
Presentation may - finalFirstQuantum
 
Presentation april - final
Presentation   april - finalPresentation   april - final
Presentation april - finalFirstQuantum
 
Presentation september - fina lv2
Presentation   september - fina lv2Presentation   september - fina lv2
Presentation september - fina lv2FirstQuantum
 
Corporate Presentation September 2015
Corporate Presentation September 2015Corporate Presentation September 2015
Corporate Presentation September 2015FirstQuantum
 
First Quantum Minerals Q2 2014 Investor Presentation
First Quantum Minerals Q2 2014 Investor PresentationFirst Quantum Minerals Q2 2014 Investor Presentation
First Quantum Minerals Q2 2014 Investor PresentationFirstQuantum
 
Corporate Presentation_June 21, 2013
Corporate Presentation_June 21, 2013Corporate Presentation_June 21, 2013
Corporate Presentation_June 21, 2013FirstQuantum
 

More from FirstQuantum (14)

Presentation may 3 final
Presentation may 3   finalPresentation may 3   final
Presentation may 3 final
 
Presentation may-3
Presentation may-3Presentation may-3
Presentation may-3
 
Presentation bmo - final
Presentation   bmo - finalPresentation   bmo - final
Presentation bmo - final
 
Presentation january 2018 - final
Presentation   january 2018 - finalPresentation   january 2018 - final
Presentation january 2018 - final
 
Presentation november final
Presentation   november finalPresentation   november final
Presentation november final
 
Presentation november - final
Presentation   november - finalPresentation   november - final
Presentation november - final
 
Presentation september - final
Presentation   september - finalPresentation   september - final
Presentation september - final
 
Presentation june - final
Presentation   june - finalPresentation   june - final
Presentation june - final
 
Presentation may - final
Presentation   may - finalPresentation   may - final
Presentation may - final
 
Presentation april - final
Presentation   april - finalPresentation   april - final
Presentation april - final
 
Presentation september - fina lv2
Presentation   september - fina lv2Presentation   september - fina lv2
Presentation september - fina lv2
 
Corporate Presentation September 2015
Corporate Presentation September 2015Corporate Presentation September 2015
Corporate Presentation September 2015
 
First Quantum Minerals Q2 2014 Investor Presentation
First Quantum Minerals Q2 2014 Investor PresentationFirst Quantum Minerals Q2 2014 Investor Presentation
First Quantum Minerals Q2 2014 Investor Presentation
 
Corporate Presentation_June 21, 2013
Corporate Presentation_June 21, 2013Corporate Presentation_June 21, 2013
Corporate Presentation_June 21, 2013
 

Recently uploaded

Basic Accountants in|TaxlinkConcept.pdf
Basic  Accountants in|TaxlinkConcept.pdfBasic  Accountants in|TaxlinkConcept.pdf
Basic Accountants in|TaxlinkConcept.pdftaxlinkcpa
 
Osisko Gold Royalties Ltd - Corporate Presentation, April 23, 2024
Osisko Gold Royalties Ltd - Corporate Presentation, April 23, 2024Osisko Gold Royalties Ltd - Corporate Presentation, April 23, 2024
Osisko Gold Royalties Ltd - Corporate Presentation, April 23, 2024Osisko Gold Royalties Ltd
 
如何办理(UTS毕业证书)悉尼科技大学毕业证学位证书
如何办理(UTS毕业证书)悉尼科技大学毕业证学位证书如何办理(UTS毕业证书)悉尼科技大学毕业证学位证书
如何办理(UTS毕业证书)悉尼科技大学毕业证学位证书Fis s
 
如何办理伦敦大学毕业证(文凭)London学位证书
如何办理伦敦大学毕业证(文凭)London学位证书如何办理伦敦大学毕业证(文凭)London学位证书
如何办理伦敦大学毕业证(文凭)London学位证书Fis s
 
The Concept of Humanity in Islam and its effects at future of humanity
The Concept of Humanity in Islam and its effects at future of humanityThe Concept of Humanity in Islam and its effects at future of humanity
The Concept of Humanity in Islam and its effects at future of humanityJohanAspro
 
VIP Kolkata Call Girl Rishra 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rishra 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rishra 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rishra 👉 8250192130 Available With Roomdivyansh0kumar0
 
9654467111 Low Rate Call Girls In Tughlakabad, Delhi NCR
9654467111 Low Rate Call Girls In Tughlakabad, Delhi NCR9654467111 Low Rate Call Girls In Tughlakabad, Delhi NCR
9654467111 Low Rate Call Girls In Tughlakabad, Delhi NCRSapana Sha
 
如何办理密苏里大学堪萨斯分校毕业证(文凭)UMKC学位证书
如何办理密苏里大学堪萨斯分校毕业证(文凭)UMKC学位证书如何办理密苏里大学堪萨斯分校毕业证(文凭)UMKC学位证书
如何办理密苏里大学堪萨斯分校毕业证(文凭)UMKC学位证书Fir La
 
如何办理东俄勒冈大学毕业证(文凭)EOU学位证书
如何办理东俄勒冈大学毕业证(文凭)EOU学位证书如何办理东俄勒冈大学毕业证(文凭)EOU学位证书
如何办理东俄勒冈大学毕业证(文凭)EOU学位证书Fir La
 
VIP Kolkata Call Girls Bidhannagar 8250192130 Available With Room
VIP Kolkata Call Girls Bidhannagar 8250192130 Available With RoomVIP Kolkata Call Girls Bidhannagar 8250192130 Available With Room
VIP Kolkata Call Girls Bidhannagar 8250192130 Available With Roomrran7532
 
Cyberagent_For New Investors_EN_240424.pdf
Cyberagent_For New Investors_EN_240424.pdfCyberagent_For New Investors_EN_240424.pdf
Cyberagent_For New Investors_EN_240424.pdfCyberAgent, Inc.
 
No 1 AMil Baba In Islamabad No 1 Amil Baba In Lahore No 1 Amil Baba In Faisl...
No 1 AMil Baba In Islamabad  No 1 Amil Baba In Lahore No 1 Amil Baba In Faisl...No 1 AMil Baba In Islamabad  No 1 Amil Baba In Lahore No 1 Amil Baba In Faisl...
No 1 AMil Baba In Islamabad No 1 Amil Baba In Lahore No 1 Amil Baba In Faisl...First NO1 World Amil baba in Faisalabad
 
9654467111 Call Girls In Katwaria Sarai Short 1500 Night 6000
9654467111 Call Girls In Katwaria Sarai Short 1500 Night 60009654467111 Call Girls In Katwaria Sarai Short 1500 Night 6000
9654467111 Call Girls In Katwaria Sarai Short 1500 Night 6000Sapana Sha
 
Methanex Investor Presentation (April 2024)
Methanex Investor Presentation (April 2024)Methanex Investor Presentation (April 2024)
Methanex Investor Presentation (April 2024)Methanex Corporation
 

Recently uploaded (20)

Basic Accountants in|TaxlinkConcept.pdf
Basic  Accountants in|TaxlinkConcept.pdfBasic  Accountants in|TaxlinkConcept.pdf
Basic Accountants in|TaxlinkConcept.pdf
 
Osisko Gold Royalties Ltd - Corporate Presentation, April 23, 2024
Osisko Gold Royalties Ltd - Corporate Presentation, April 23, 2024Osisko Gold Royalties Ltd - Corporate Presentation, April 23, 2024
Osisko Gold Royalties Ltd - Corporate Presentation, April 23, 2024
 
如何办理(UTS毕业证书)悉尼科技大学毕业证学位证书
如何办理(UTS毕业证书)悉尼科技大学毕业证学位证书如何办理(UTS毕业证书)悉尼科技大学毕业证学位证书
如何办理(UTS毕业证书)悉尼科技大学毕业证学位证书
 
如何办理伦敦大学毕业证(文凭)London学位证书
如何办理伦敦大学毕业证(文凭)London学位证书如何办理伦敦大学毕业证(文凭)London学位证书
如何办理伦敦大学毕业证(文凭)London学位证书
 
The Concept of Humanity in Islam and its effects at future of humanity
The Concept of Humanity in Islam and its effects at future of humanityThe Concept of Humanity in Islam and its effects at future of humanity
The Concept of Humanity in Islam and its effects at future of humanity
 
VIP Kolkata Call Girl Rishra 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rishra 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rishra 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rishra 👉 8250192130 Available With Room
 
9654467111 Low Rate Call Girls In Tughlakabad, Delhi NCR
9654467111 Low Rate Call Girls In Tughlakabad, Delhi NCR9654467111 Low Rate Call Girls In Tughlakabad, Delhi NCR
9654467111 Low Rate Call Girls In Tughlakabad, Delhi NCR
 
young call girls in Hauz Khas,🔝 9953056974 🔝 escort Service
young call girls in Hauz Khas,🔝 9953056974 🔝 escort Serviceyoung call girls in Hauz Khas,🔝 9953056974 🔝 escort Service
young call girls in Hauz Khas,🔝 9953056974 🔝 escort Service
 
young call girls in Govindpuri 🔝 9953056974 🔝 Delhi escort Service
young call girls in Govindpuri 🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Govindpuri 🔝 9953056974 🔝 Delhi escort Service
young call girls in Govindpuri 🔝 9953056974 🔝 Delhi escort Service
 
如何办理密苏里大学堪萨斯分校毕业证(文凭)UMKC学位证书
如何办理密苏里大学堪萨斯分校毕业证(文凭)UMKC学位证书如何办理密苏里大学堪萨斯分校毕业证(文凭)UMKC学位证书
如何办理密苏里大学堪萨斯分校毕业证(文凭)UMKC学位证书
 
如何办理东俄勒冈大学毕业证(文凭)EOU学位证书
如何办理东俄勒冈大学毕业证(文凭)EOU学位证书如何办理东俄勒冈大学毕业证(文凭)EOU学位证书
如何办理东俄勒冈大学毕业证(文凭)EOU学位证书
 
young call girls in Yamuna Vihar 🔝 9953056974 🔝 Delhi escort Service
young  call girls in   Yamuna Vihar 🔝 9953056974 🔝 Delhi escort Serviceyoung  call girls in   Yamuna Vihar 🔝 9953056974 🔝 Delhi escort Service
young call girls in Yamuna Vihar 🔝 9953056974 🔝 Delhi escort Service
 
Escort Service Call Girls In Shalimar Bagh, 99530°56974 Delhi NCR
Escort Service Call Girls In Shalimar Bagh, 99530°56974 Delhi NCREscort Service Call Girls In Shalimar Bagh, 99530°56974 Delhi NCR
Escort Service Call Girls In Shalimar Bagh, 99530°56974 Delhi NCR
 
VIP Kolkata Call Girls Bidhannagar 8250192130 Available With Room
VIP Kolkata Call Girls Bidhannagar 8250192130 Available With RoomVIP Kolkata Call Girls Bidhannagar 8250192130 Available With Room
VIP Kolkata Call Girls Bidhannagar 8250192130 Available With Room
 
Cyberagent_For New Investors_EN_240424.pdf
Cyberagent_For New Investors_EN_240424.pdfCyberagent_For New Investors_EN_240424.pdf
Cyberagent_For New Investors_EN_240424.pdf
 
No 1 AMil Baba In Islamabad No 1 Amil Baba In Lahore No 1 Amil Baba In Faisl...
No 1 AMil Baba In Islamabad  No 1 Amil Baba In Lahore No 1 Amil Baba In Faisl...No 1 AMil Baba In Islamabad  No 1 Amil Baba In Lahore No 1 Amil Baba In Faisl...
No 1 AMil Baba In Islamabad No 1 Amil Baba In Lahore No 1 Amil Baba In Faisl...
 
9654467111 Call Girls In Katwaria Sarai Short 1500 Night 6000
9654467111 Call Girls In Katwaria Sarai Short 1500 Night 60009654467111 Call Girls In Katwaria Sarai Short 1500 Night 6000
9654467111 Call Girls In Katwaria Sarai Short 1500 Night 6000
 
Model Call Girl in Udyog Vihar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Udyog Vihar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Udyog Vihar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Udyog Vihar Delhi reach out to us at 🔝9953056974🔝
 
Methanex Investor Presentation (April 2024)
Methanex Investor Presentation (April 2024)Methanex Investor Presentation (April 2024)
Methanex Investor Presentation (April 2024)
 
young Call girls in Dwarka sector 1🔝 9953056974 🔝 Delhi escort Service
young Call girls in Dwarka sector 1🔝 9953056974 🔝 Delhi escort Serviceyoung Call girls in Dwarka sector 1🔝 9953056974 🔝 Delhi escort Service
young Call girls in Dwarka sector 1🔝 9953056974 🔝 Delhi escort Service
 

First Quantum Minerals Corporate Presentation - June 2014

  • 1. TURNING VISION INTO REALITY JUNE2014 TSX: FM; LSE: FQM
  • 2. CAUTIONARY NOTE REGARDING FORWARD-LOOKING STATEMENT Some of the statements contained in the following material are forward-looking statements and not statement of facts. Such statements are based on the current beliefs of management, as well as assumptions based on management information currently available. Forward-looking statements are subject to various risks, uncertainties and other factors that could cause actual results to differ materially from expected results. Readers must rely on their own evaluation of these uncertainties. Note: all dollar amounts in US dollars unless otherwise indicated 2
  • 3. FIRST QUANTUM MINERALS AT A GLANCE 3 • A Global Company – Operations and projects in 8 countries • Efficient Operations – 7 operations – 2013 production:  copper 412,281 tonnes  nickel 47,066 tonnes  gold 248,078 ounces – Cash cost of production  copper $1.30/lb; nickel $5.02/lb • Strong Liquidity & Cash Flow – Cash at March 31’14 = $747.2M – Cash from operations = $370.1M – Available & undrawn facilities of $1.3B – Senior Notes = $850M • Industry-Leading Growth – 5 major projects under development – Production capacities to rise to 1.1 Mtpa for copper and 110 ktpa for nickel by 2018 • Unique Core Strength – In-house project development team – Delivered projects at an average of 40% of the industry’s average capital per tonne of capacity • Strong Track Record – Delivered over $2.4B in projects within 6% of budget – Returned a compounded annual gain of over 30% since listing
  • 4. GOOD OPERATING PERFORMANCE CONTINUES INTO 2014 • Production up – Copper up 43% to 113,118 tonnes – Nickel up 7% to 11,838 tonnes – Gold up 8% to 60,164 ounces – Platinum and palladium up 22% to 15,342 ounces • Cash cost lowered – Copper down 9% to $1.38 per pound – Nickel down 18% to $4.37 per pound • Comparative net earnings of $126.8 million or $0.22 per share including: – $26.7 million or $0.05 per share of unfavorable, recurring acquisition- related adjustments. – Unfavorable impact of $152 million from lower commodity prices and the build-up in concentrate inventory at Kansanshi 4 Q1 '13 Q2'13 Q3'13 Q4'13 Q1'14 Q1 '13 Q2'13 Q3'13 Q4'13 Q1'14 Q1 '13 Q2'13 Q3'13 Q4'13 Q1'14 Q1 '13 Q2 '13 Q3'13 Q4'13 Q1'14 Copper Production 000’s tonnes Nickel Production 000’s tonnes Gold Production 000’s ounces Copper C1 Cost US$/lb
  • 5. OUR PIORITIES  Build a leading copper-focused company  Maintain an optimal capital and financing structure  Operate efficiently 5
  • 6. BUILDING A LEADING COPPER-FOCUSED COMPANY Cobre Panama – A Tier 1 Copper Project  Acquired March 2013  Critical review following acquisition – Focused mainly on Engineering, Contracts and Construction initially – Copied major areas of the design of the almost-complete Sentinel process plant  Made significant changes – Unwound ~US$1.7B of commitments – Rectified multiple deficiencies – Readied the site for construction – Connected mine site to port site – Changed to an in-house, self-perform arrangement 6
  • 7. BUILDING A LEADING COPPER-FOCUSED COMPANY Cobre Panama – A Tier 1 Copper Project  A larger, more robust project – Installed capacity Yrs 1-10 = ~70 Mtpa  17% higher than prior  Expansion up to 100 Mtpa beyond Yr 10 – Average annual LOM* copper production of 320,000 tonnes  ~ 20% higher than prior – Average annual LOM by-product production  100,000 ounces gold; 1,800,000 ounces silver and 3,500 tonnes molybdenum  Mine life of 34 years 7 * On the basis of the current Resource estimate and the planned installed capacity of about 70 Mtpa
  • 8. BUILDING A LEADING COPPER-FOCUSED COMPANY Cobre Panama – A Tier 1 Copper Project  Capex estimate of $6.4 billion – inclusive of $913 million incurred prior to acquisition  Capital per installed tonne of capacity of $17,125 – ~25% lower than prior  A realistic and well-defined timeframe – 230 KV overland power line – Q4 ’15 – 300 MW powerstation – Q1 ‘17 – Tailings management facility – Q2 ’17 – Process plant construction – Q3 ‘17 – Commissioning & 1st concentrate production – Q4 ‘17 8
  • 9. COBRE PANAMA PROJECT – PROCESS PLANT SITE EARTHWORKS 9
  • 10. COBRE PANAMA PROJECT – MILL PAD EARTHWORKS 10
  • 11. COBRE PANAMA PROJECT – PROCESS PLANT STOCKPILE PAD 11
  • 12. COBRE PANAMA PROJECT – POWER STATION AREA 12
  • 13. COBRE PANAMA PROJECT BREAKWATER AND MATERIAL OFFLOADING FACILITY 13
  • 14.  Phase 1 – Processing capacity of 1.2 Mtpa – Combination of concentrate from Kansanshi & Sentinel – Average copper grade 26%  Copper production 300,000 Tpa; acid production 1.0 Mtpa  Commissioning from 2H2014  Estimated savings: – US$340M - US$510M/year  Phase 2 being planned to increase processing capacity to between 2 to 2.4 Mtpa in 2017 BUILDING A LEADING COPPER-FOCUSED COMPANY Copper Smelting Complex 14
  • 15. BUILDING A LEADING COPPER-FOCUSED COMPANY Copper Smelting Complex - Phase 1 Smelter – Cold Box Lifts – April 2014 15
  • 16. BUILDING A LEADING COPPER-FOCUSED COMPANY Trident Project  Located ~ 140 km northwest of Solwezi, northern Zambia  Includes Sentinel copper and Enterprise nickel  Sentinel’s M&I resource of 1,027 Mt at 0.51% Cu grade, containing 5.2 Mt Cu  Estimates: – 2.2:1 LOM strip ratio – >15 years mine life – Production of up to 300 Ktpa copper; 38 to 60 Ktpa nickel in concentrate – US$2.0B capex – Completion from mid-2014 for Sentinel & Q1 2015 for Enterprise 16
  • 17. • Flexible 4 Mtpa nickel facility can augment copper capacity • 55 Mtpa copper throughput • 3 semi-mobile in pit crushers and assembly of large scale mining equipment • Large operating SAG/Ball mill trains (100MW milling power) • 265 Kt of freight = 14,500 truckloads of materials • 2 rivers to be dammed/diverted BUILDING A LEADING COPPER-FOCUSED COMPANY Trident Project 17
  • 18. • Life of mine tailings storage facility • 600 km of 330kV power transmission lines from Lumwana – Kalumbila – Lusaka West • 690 staff houses plus 590 houses in resettlement • Development of a new town, airport, clinic, school etc…. BUILDING A LEADING COPPER-FOCUSED COMPANY Trident Project 18
  • 19. 19 SENTINEL – 80 METER FEED SHUTTLE CONVEYOR TRUSS - APRIL 2014
  • 20. SENTINEL - 100MW MILLING – 2 X 40’SAG MILLS + 2 X 28’BALL MILLS 20
  • 21. SENIOR HOUSING - SINGLES 31-MAR-2013 SENIOR HOUSING AREA 28-FEB-2013 SPORTS FACILITY 04-NOV-2013 TRIDENT PREPARATORY SCHOOL 05-NOV-2013 SENTINEL – COMMUNITY DEVELOPMENT 21
  • 22. TRUST SCHOOL 05-NOV-2013 AFFORDABLE HOUSING LAYOUT TEACHER’S HOME 3-JAN-2014 COMPLETED 4-BEDROOM HOUSE 3-JAN-2014 SENTINEL – COMMUNITY DEVELOPMENT 22
  • 23. • Refinanced the short-term US$2.5B revolver at FQM (Akubra) with a $1.2B Term Loan Facility five-year Term and and a $1.8B Revolving Credit Facility • Exchanged the FQM (Akubra) Inc. US$1.49B 8.75% 2020 and US$500M 7.50% 2021 notes for new 6.75% 6-year notes and new 7.00% 7-year notes • In conjunction with the Exchange Offer, made covenant changes to better match the Company's needs going forward • Made certain amendments to the existing indentures of the US$350M 7.25% Senior Notes due 2019 through a consent solicitation offer to bondholders • Retired the project financing at Kevitsa and Kansanshi and put in place a $350M unsecured facility at Kansanshi • Completed $850M 7.25% Senior Notes Offering due 2022 23 OPTIMIZED CAPITAL STRUCTURE & FINANCIAL FLEXIBILITY
  • 24. As at March 31, 2014 Illustrative Pro Forma Corporate Structure Chart 24
  • 25. ONE OF THE FEW MINING COMPANIES INVESTING IN BUILDING CAPACITY 25
  • 26. A Small Copper Surplus Now, But….. • EXPLORATION – Majors have cut back on exploration and juniors are mainly un-financeable – It takes 12-15 years to get from discovery to production • BROWN FIELD EXPANSIONS – Should be lower capital intensity but are not – Capital projects cancelled or deferred from shareholder pressure • GREENFIELD PROJECTS – High capital intensity – Capital projects cancelled or deferred as above – Very poor track record of developing projects efficiently 26 CURRENT STATE OF THE COPPER INDUSTRY
  • 27. 27 CURRENT STATE OF THE COPPER INDUSTRY Results in a Looming Deficit
  • 28. Global copper mine supply growth and price 0% 0% 1% 0% -1% 7% 9% 4% 7% 5% 4% 3% -1% 1% 7% 2% 2% 3% 1% 2% 0% 0% 3% 7% -2% 0% 2% 4% 6% 8% 10% 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 Copperminesupplygrowth%YoY 0 50 100 150 200 250 300 350 400 Copperprice,cents/lb Mine supply growth Price Source: Wood Mackenzie, Macquarie Research, February 2014 28 LACK OF SUPPLY RESPONSE TO PRICE WAS STAGGERING OVER 2006-2012PERIOD
  • 29. So why is the industry cutting investment?  Pressure from shareholders who have a much shorter time horizon than miners This is not going to change  There is not much out there that the majors want With the cut-back in exploration, this is unlikely to change  The capital intensity of new projects is rising rapidly Why is this so? 29 SO THE SEEDS OF THE NEXT COPPER PRICE BUBBLE ARE ALREADY SOWN … AND IT IS COMING SOON
  • 30. Source: Brook Hunt, Freeport McMoRan Average Copper Grades 30  Falling grades • Difficult geographies • Geopolitics WHY IS CAPITAL INTENSITY RISING?
  • 31. Source: Wood Mackenzie, CRU, Macquarie Research, February 2014 Weighted average copper project by year of delivery 0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 0 5000 10000 15000 20000 25000 30000 35000 40000 Life of mine capital intensity Averageheadgrade 2000-2011 2012-2018f 2000 2001 2002 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013f 2014f 2015f 2016f 2017f 2018f AS HEAD GRADES FALL, CAPITAL INTENSITY RISES RAPIDLY 31
  • 32. 0 5,000 10,000 15,000 20,000 25,000 30,000 Kansanshi (First Quantum) Kansanshi Expansion (First Quantum) Sentinel (First Quantum) Buenavista DC (Southern Copper) Antapaccay (Xstrata) Antamina (BHP) Guelb Moghrein (First Quantum) Canariaco (Candente) Las Cruces (Inmet) Los Bronces (Anglo American) Oyu Tolgoi (Rio Tinto) Ministro Mina Hales (Codelco) Sierra Gorda (KGHM) Toromocho (Chinalco) Tampakan (Xstrata) Las Bambas (Xstrata) CobrePanama (FirstQuantum) Galeno (Minmetals) CAPITALINTENSITY (US$/t) Source: First Quantum, Broker Research A producing First Quantum mine A current First Quantum project BUT IT IS POSSIBLE TO BUILD PROJECTS EFFICIENTLY 32
  • 33. Weighted average copper project by year of delivery 0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 0 5000 10000 15000 20000 25000 30000 35000 40000 Life of mine capital intensity Averageheadgrade 2000-2011 2012-2018f 2000 2001 2002 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013f 2014f 2015f 2016f 2017f 2018f COBRE PANAMA 33 Source: Wood Mackenzie, CRU, Macquarie Research, February 2014 COBRE PANAMA HAS SUBSTANTIALLY LOWER CAPITAL INTENSITY COMPARED TO OTHER PROJECTS WITH SIMILAR START-UP HORIZONS
  • 35.  Located near Solwezi in the north western Province of Zambia  First production in 2005  Open pit mining  Flexible ore treatment to allow for variation in ore type : – sulphide circuit; oxide circuit; gold facility  As at December 31, 2013, the estimated mine life was ~17 years  Workforce = ~1,937 35 EFFICIENT OPERATIONS Kansanshi Cu-Au mine, Zambia
  • 36.  Q1 2014 – 71 kt of copper – 40 kozs of gold – $1.57/lb copper C1 cash cost  2014 outlook – 255 to 270 kt of copper – 145 to 160 kozs of gold  Multi-phase capacity expansion project – 2012 – 2017 60% increase in overall production capacity – 2012 – 2014 130% increase in oxide production capacity – 2017 90% increase in sulphide production capacity 36 Project Capacity Status Estimate Cost Production Impact (US$M) Oxide 7.2 Mtpa Complete 34 Copper: 10,000 - 15,000 Tpa Oxide 14.5 Mtpa Complete 280 Copper: 60,000 - 75,000 Tpa Sulphide 25 Mtpa 2017 565 Copper: 60,000 - 70,000 Tpa EFFICIENT OPERATIONS Kansanshi Cu-Au mine, Zambia
  • 37.  Acquired in March 2013  Estimated mine life of 9 years; potential for extension  Current average reserve grade of 5.4% copper  Workforce = ~254  Q1 2014 – 19 Kt of copper; $0.98/lb copper C1 cash cost  2014 Outlook – 69 to 72 kt of copper 37 EFFICIENT OPERATIONS Las Cruces Cu mine, Spain
  • 38.  100% ownership  Located 250 kilometres northeast of the nation’s capital, Nouakchott  As at December 31, 2013, the estimated mine life was ~ 8 years (including stockpiles) based on current operations  First production in 2006  Workforce = ~1,170 38 EFFICIENT OPERATIONS Guelb Moghrein Cu-Au mine, Mauritania
  • 39. EFFICIENT OPERATIONS Guelb Moghrein Cu-Au mine, Mauritania  Q1 2014 – 9 kt tonnes of copper – 14 kozs of gold – $1.56/lb copper C1 cash cost  2014 Outlook – 36 to 39 kt of copper – 55 to 60 k ozs of gold  Magnetite plant project: – In detailed design stage – Estimated capex of $50M – Expected production of 1 – 2 Mtpa tonnes of 69% Fe magnetite concentrate – Expected start up in mid-2014 – Expected to extend mine life through retreatment of tailings dam 39
  • 40.  Acquired as a decommissioned plant in 2010  First production within 20 months of purchase  Estimated mine life of 32 years  Commercial production declared Dec 2011  Workforce = ~428  Q1 2014 – 9 kt of nickel @ $4.02/lb C1 cash cost  2014 Outlook – 33 to 37 kt of nickel 40 EFFICIENT OPERATIONS Ravensthorpe Ni mine, Australia
  • 41.  Built, commissioned and started commercial operations within 36 months of board approval  Estimated mine life of 29 years  Commercial production declared August 2012  Workforce = ~337  Further potential – Process optimization – Approval to increase throughput to a maximum of 10 Mtpa from 5.5 Mtpa  Q1 2014 = 4 kt of copper @ $1.52/lb C1 cash cost ; 2 kt of nickel @ $5.19/lb nickel C1 cash cost  2014 Outlook – 69 to 72 kt of copper; 9 to 10 kt of nickel 41 EFFICIENT OPERATIONS Kevitsa Ni-Cu-PGE mine, Finland
  • 42.  Acquired in March 2013  Estimated mine life of 6 years with potential for an additional 3 years  Average grade of 3.1% copper and 3.6% zinc  Workforce = ~520 employees  Q1 2014 – 7 kt of copper; 10 kt of zinc – $0.76/lb copper C1 cash cost  2014 Outlook – 27 to 29 kt of copper – 38 to 42 kt of zinc 42 EFFICIENT OPERATIONS Çayeli Cu-Zn mine, Turkey
  • 43.  Acquired in March 2013  One of the most efficient underground mines in the world  Estimated mine life of 6 years  Average grade of 1.05% copper and 1.79% zinc  Workforce = ~228 employees  Q1 2014 – 4 kt of copper; 5 kt of zinc – $0.52/lb copper C1 cash cost  2014 Outlook – 14 to 15 kt of copper; 21 to 23 kt of zinc EFFICIENT OPERATIONS Pyhäsalmi Cu-Zn mine, Finland 43
  • 44. • Production – Copper between 418,000 - 444,000 tonnes – Nickel between 42,000 - 47,000 tonnes – Gold between 221,000 - 246,000 ounces – Zinc between 59,000 - 65,000 tonnes – Palladium and platinum between 22,000 - 24,000 ounces each • C1 cash cost – Copper between $1.32 - $1.48/lb. – Nickel between $4.40 - $4.90/lb • Capital expenditures – $2.1B to $2.2B 44 FULL YEAR 2014 GUIDANCE
  • 45. A COPPER-FOCUSED, GLOBAL COMPANY Signifiant Nickel and Gold Production Operations and Projects in 8 countries High-Quality, Stable, Efficient Operations Strong Liquidity & Cash Flow Industry-Leading Growth Unique Core Strength of In-House Project Development Strong Track Record of Project Development and Shareholder Returns Copper 72% Nickel 16% Gold 6% Zinc 2% Other 3% Revenues
  • 46. TURNING VISION INTO REALITY JUNE2014 TSX: FM; LSE: FQM