SlideShare a Scribd company logo
1 of 182
Kanban In The Enterprise
                          Kevin Ryan : Agile Practices Consultant




Monday, 11 October 2010
The Starting Point
      • Scrum project
      • Running for two years
      • Second architectural refresh
      • Highly pressurised environment
      • Low stakeholder confidence
      • Combined on-shore and off-shore resource
      • Project head count around 50
      • Unable to estimate reliable completion dates
      • Product considered critical to business strategy
      • Increasing technical debt
Monday, 11 October 2010
Evolution : 0
  Enterprise              Program Level Process   Team Level Process         Program Level Process   Enterprise
  Process                                                                                            Process

                                                         Team A Scrum




                                                         Team B Scrum




                                                         Team C Scrum




                                                         Team D Scrum




                                                              Value Stream
Monday, 11 October 2010
Evolution : 1
  Enterprise              Program Level Process   Team Level Process         Program Level Process   Enterprise
  Process                                                                                            Process

                                                         Team A Scrum




                                                          Team B Kanban




                                                         Team C Scrum




                                                         Team D Scrum




                                                              Value Stream
Monday, 11 October 2010
Evolution : 2
  Enterprise              Program Level Process   Team Level Process         Program Level Process   Enterprise
  Process                                                                                            Process

                                                         Team A Scrum




                                                          Team B Kanban




                                                         Team C Scrum




                                                          Team D Kanban




                                                              Value Stream
Monday, 11 October 2010
Evolution : 3
  Enterprise              Team Level Process   Program Level Process     Team Level Process   Program Level Process   Enterprise
  Process                                                                                                             Process

                                                                  Team A Scrum




                                                                  Team B Kanban




               Program Leadership Kanban

                                                                  Team C Scrum




                                                                   Team D Kanban




                                                                       Value Stream
Monday, 11 October 2010
Evolution : 4
  Enterprise              Team Level Process   Program Level Process    Team Level Process   Program Level Process         Team Level Process   Enterprise
  Process                                                                                                                                       Process

                                                                  Team A Scrum




                                                                  Team B Kanban




               Program Leadership Kanban                                                                             Program Cohesion Kanban

                                                                  Team C Scrum




                                                                   Team D Kanban




                                                                       Value Stream
Monday, 11 October 2010
Evolution : X
  Enterprise              Team Level Process   Program Level Process    Team Level Process   Program Level Process         Team Level Process   Enterprise
  Process                                                                                                                                       Process


                                                                  Team A Kanban




                                                                   Team B Kanban



               Program Leadership Kanban                                                                             Program Cohesion Kanban



                                                                   Team C Kanban




                                                                   Team D Kanban




                                                                       Value Stream
Monday, 11 October 2010
Stories...



Monday, 11 October 2010
Monday, 11 October 2010
Monday, 11 October 2010
Monday, 11 October 2010
Scrum Boards



Monday, 11 October 2010
Monday, 11 October 2010
Scrum Discipline



Monday, 11 October 2010
Monday, 11 October 2010
Monday, 11 October 2010
Monday, 11 October 2010
Applying Lean Principles




Monday, 11 October 2010
Sharing The Big Picture




Monday, 11 October 2010
Monday, 11 October 2010
Monday, 11 October 2010
Focusing on Value



Monday, 11 October 2010
Monday, 11 October 2010
Reducing Variability



Monday, 11 October 2010
Monday, 11 October 2010
Monday, 11 October 2010
Monday, 11 October 2010
Introducing Kanban



Monday, 11 October 2010
Program Leadership



Monday, 11 October 2010
Monday, 11 October 2010
Just In Time


       “	
  If	
  you’re	
  early	
  you	
  are	
  was/ng	
  your	
  /me,
                                       if	
  you’re	
  late	
  you	
  are	
  was/ng	
  mine.”




                                                    !"#$%&'()*+($&,)-+.)&/#*$#01&2*-&3.4#&56&/#$$"78-57&


Monday, 11 October 2010
Monday, 11 October 2010
Monday, 11 October 2010
Monday, 11 October 2010
Monday, 11 October 2010
Monday, 11 October 2010
Monday, 11 October 2010
Monday, 11 October 2010
Monday, 11 October 2010
Monday, 11 October 2010
Workflow



                Falcon Program Level Kanban Workflow Definition

                Two Week Cadence
                Workflow Stage   Baseline High Level Form Architectural                       Requirements           Resolve                Story Breakdown &        Estimate Points     Resolve Team            Ready For Technical
                WIP Limit        Business Objectives 3 Design                2                Cohesion          2    Organisational     2   Traceability         2                     2 Dependencies     2      Implementation    4
                Exit Criteria    Named product owner Falcon touchpoints                       None functional        Named contacts for     Story acceptance         Stories are broken Resource                 Appropriate
                                                        identified                            requirements agreed    external               criteria expressed in    down to a           dependencies            development team
                                 Named key                                                                           dependencies           a manner that allows     reasonably          between teams have      identified
                                 stakeholders           External interfaces                   Functional                                    for executable           consistent size     been identified
                                                        identified                            requirements agreed External                  specification                                                        Team have reviewed
                                 Descriptive paragraph                                                            dependencies aware                                 Stories have a       Named points of        materials and are
                                 of theme and sub-      High level                            User interface      of scheduled change       Product verification     relative points      contact between        willing to accept
                                 themes                 components                            prototypes produced                           checks identified        estimate             teams exist            feature into
                                                        identified                                                Impact between                                                                                 development
                                 Problem/Value                                                                    external                  Testability features                          Multiple teams are     process
                                 Statements             Strategic review                                          dependencies              have been identified                          aware of scheduled
                                                        complete                                                  identified                (eg: logging, tracing)                        change and have    Technical skills exist
                                 Bullet pointed list of                                                           (possible breaking                                                      capacity to manage within the team to
                                 business objectives    Any third party                                           change?)                                                                dependencies       deliver specified
                                                        suppliers identified                                                                                                                                 feature
                                 External
                                 dependencies           Impact on physical                                                                                                                                       Named development
                                 identified             architecture                                                                                                                                             owner
                                                        identified
                                 Stakeholder
                                 agreement              None functional
                                                        aspects identified
                                                        and listed




                                                                                                              I=D=75B./"C71N"
                                         %#"

                                                                                                                                                                                               ,-./-0123"
                                         %!"                                                                                                                                                   456/78-/"98:;"</./7"4=68-/66">?@/AB./6"
                                                                                                                                                                                               C12D"E2A;80/A0=257"F/68:-"
                                                                                                                                                                                               G/H=82/D/-06"I1;/681-"
                  S12M",0/D"42/5MK1N-"




                                         $#"
                                                                                                                                                                                               G/617./">2:5-865B1-57"F/J/-K/-A8/6"
                                                                                                                                                                                               L0123"42/5MK1N-"O"P25A/5?87803"
                                         $!"
                                                                                                                                                                                               Q6BD50/"R18-06"
                                                                                                                                                                                               G/617./"P/5D"F/J/-K/-A8/6"
                                          #"                                                                                                                                                   G/5K3"C12"P/A;-8A57",DJ7/D/-05B1-"
                                                                                                                                                                                               ,DJ7/D/-05B1-"
                                                                                                                                                                                               ,-"R21K=AB1-"
                                          !"
                                               $"   %"   &"   '"   #"   ("   )"   *"   +"   $!"   $$"   $%"   $&"   $'"   $#"   $("   $)"   $*"   $+"    %!"   %$"     %%"   %&"   %'"   %#"

                                                                                                        F536"Q75J6/K",-"L5DJ7/"



                                                                                                                                                                   Page 1



Monday, 11 October 2010
Program Baseline




Monday, 11 October 2010
Falcon Program Level Kanban Workflow Definition
     Two Week Cadence
     Workflow Stage   Baseline High Level                                 Form Architectural         Requirements              Resolve                   Story Breakdown &         Estimate Points         Resolve Team             Ready For Technical
                      Business Objectives                                 Design                     Cohesion                  Organisational            Traceability                                      Dependencies             Implementation                                                                                                Notes
                                                                                                                               Dependencies
     WIP Limit                                                        3                          2                         2                         2                         2                       2                    2                                4                             This document is not an estimate of work remaining.
     Exit Criteria                          Named product owner           Falcon touchpoints         None functional           Named contacts for        Story acceptance          Stories are broken    Resource                   Appropriate
                                                                          identified                 requirements agreed       external                  criteria expressed in a   down to a reasonably dependencies                development team
                                            Named key                                                                          dependencies              manner that allows for    consistent size       between teams have         identified
                                                                                                                                                                                                                                                                                           This document is not a commitment to delivery dates.
                                            stakeholders                  External interfaces        Functional                                          executable                                      been identified
                                                                          identified                 requirements agreed       External                  specification             Stories have a                                   Team have reviewed                                     This document is a derived model based upon the current defined development process and is
                                            Descriptive paragraph                                                              dependencies aware                                  relative points       Named points of            materials and are                                      intended as a tool to improve estimation and maximise requirements flow.
                                            of theme and sub-             High level            User interface                 of scheduled change       Product verification      estimate              contact between            willing to accept
                                            themes                        components identified prototypes produced                                      checks identified                               teams exist                feature into
                                                                                                                               Impact between                                                                                       development process                                    Definitions
                                            Problem/Value                 Strategic review                                     external                  Testability features                              Multiple teams are                                                              Flow : The movement of requirements through the program workflow and into production.
                                            Statements                    complete                                             dependencies              have been identified                              aware of scheduled       Technical skills exist
                                                                                                                               identified                (eg: logging, tracing)                            change and have          within the team to
                                            Bullet pointed list of        Any third party                                      (possible breaking                                                          capacity to manage       deliver specified
                                                                                                                                                                                                                                                                                           Cycle Time : The duration of any given feature or requirement to complete its development cycle.
                                            business objectives           suppliers identified                                 change?)                                                                    dependencies             feature
                                                                                                                                                                                                                                                                                           Flow Rate : The frequency at which features or requirements complete a development workflow.
                                            External dependencies Impact on physical                                                                                                                                                Named development
                                            identified            architecture identified                                                                                                                                           owner
                                                                                                                                                                                                                                                                                           Intended Outcome :
                                            Stakeholder agreement None functional                                                                                                                                                                                                          Positive actions to reduce cycle times at the Program, Theme and Story Level.
                                                                  aspects identified and
                                                                  listed                                                                                                                                                                                                                   Positive actions to increase flow rate at the Program, Theme and Story Level.
                                                                          Technical frameworks
                                                                          identified (eg. Spring)

                                                                          Internal interfaces
                                                                          defined

                                                                          Named technical
                                                                          owner




                                                                                                       I1-0217"456/78-/"I=D=75B./"C71N"                                                                                                                                                                                               Baseline Characteristics
                                                                                                                                                                                                                                                                                           Sample Start Date                                                                                  01-May-10
                                  %#"
                                                                                                                                                                                                                                                                                           Sample End Date                                                                                    31-Dec-10
                                                                                                                                                                                                                                                                                           Days In Sample                                                                                           245
                                                                                                                                                                                                                                                                                           Size Of Program Level Inventory                                                                            20
                                                                                                                                                                                                                                                                                           Business Feature Cycle Time Days                                                                           64
                                  %!"                                                                                                                                                                             ,-./-0123"                                                               Business Feature Flow Rate Days                                                                             7
           S12M",0/D"42/5MK1N-"




                                                                                                                                                                                                                                                                                           Inventory Released Downstream Per Business Feature                                                         25
                                                                                                                                                                                                                  456/78-/"98:;"</./7"4=68-/66">?@/AB./6"
                                                                                                                                                                                                                                                                                           Number of Teams Downstream                                                                                  5
                                                                                                                                                                                                                  C12D"E2A;80/A0=257"F/68:-"                                               Downstream Cycle Time Days                                                                                  7
                                  $#"                                                                                                                                                                             G/H=82/D/-06"I1;/681-"
                                                                                                                                                                                                                                                                                           Downstream Flow Rate                                                                                    0.75
                                                                                                                                                                                                                                                                                           Initial Product Increment                                                                           07-Jul-10
                                                                                                                                                                                                                  G/617./">2:5-865B1-57"F/J/-K/-A8/6"                                      Final Product Increment                                                                            13-Nov-10
                                                                                                                                                                                                                  L0123"42/5MK1N-"O"P25A/5?87803"                                          Program Cycle Time                                                                                       197
                                  $!"                                                                                                                                                                                                                                                      Weekly Expenditure                                                                                  £250,000
                                                                                                                                                                                                                  Q6BD50/"R18-06"                                                          Monthly Client Subscription Cost                                                                      £35.00
                                                                                                                                                                                                                  G/617./"P/5D"F/J/-K/-A8/6"
                                                                                                                                                                                                                  G/5K3"C12"P/A;-8A57",DJ7/D/-05B1-"
                                    #"
                                                                                                                                                                                                                  ,DJ7/D/-05B1-"
                                                                                                                                                                                                                  ,-"R21K=AB1-"


                                    !"
                                           $"
                                           &"
                                           '"


                                          $*"
                                          %#"
                                          %+"
                                          ($"
                                          ('"


                                          &*"
                                          ##"
                                          #+"
                                          )$"
                                          )'"


                                          '*"
                                          +#"
                                          ++"
                                          *$"
                                          *'"
                                         $!!"
                                         $!("
                                         $!)"
                                         $!*"
                                         $$%"
                                         $$#"
                                         $$+"
                                         $%$"
                                         $%&"
                                         $%'"
                                         $(!"
                                         $(("
                                         $()"
                                         $(*"
                                         $&%"
                                         $&#"
                                         $&+"
                                         $#$"
                                         $#&"
                                         $#'"
                                         $)!"
                                         $)("
                                         $))"
                                         $)*"
                                         $'%"
                                         $'#"
                                         $'+"
                                         $+$"
                                         $+&"
                                         $+'"
                                         $*!"
                                         $*("
                                         $*)"
                                         $**"
                                         %!%"
                                         %!#"
                                         %!+"
                                         %$$"
                                         %$&"
                                         %$'"
                                         %%!"
                                         %%("
                                         %%)"
                                         %%*"
                                         %(%"
                                         %(#"
                                         %(+"
                                         %&$"
                                         %&&"
                                          $!"
                                          $("
                                          $)"
                                          %%"


                                          (&"
                                          &!"
                                          &("
                                          &)"
                                          #%"


                                          )&"
                                          '!"
                                          '("
                                          ')"
                                          +%"


                                          *&"




                                                                                                                 F536"Q75J6/K",-"L5DJ7/"


                                                  !"#$%&'(9:+%.;%(12'2"%(3(45(6787(                                                                                     ),<%.'()#;'(12'2"%(3(45(6787(                                                                                 !"#=2&'(!%">#"*0.&%(12'2"%(3(45(6787(                                                                !"#$%&'()#*+,%-#.(/0'%(12'2"%(3(45(6787(
                                                                                                                                                                                                                                                        %#"                                                                                                      'TV5-T$$"
       )X!!!X!!!"                                                                                                                      &!"
                                                                                                                                       (#"                                                                                                                                                                                                                     $+TW1.T$!"
       #X!!!X!!!"                                                                                                                                                                                                                                       %!"
                                                                                                                                       (!"
       &X!!!X!!!"                                                                                                                      %#"                                                                                                                                                                                                                     %*TL/JT$!"
                                                                                                                                                                                                                                                        $#"
       (X!!!X!!!"                                                                                                                      %!"
                                                                                                                                                                                                                                                                                                                                                               $!TE=:T$!"
                                                                                                                                       $#"                                                                                                              $!"
                                                                                                                                                                                                                                                                                                                                        R21K=A0"R/2Z12D5-A/"
       %X!!!X!!!"                                                                                    R21@/A0"QYJ/-6/"C=0=2/"                                                                                           I78/-0"I160"C=0=2/"                                                                                                                                                                                            R21@/A0"I1DJ7/B1-"F50/"C=0=2/"
                                                                                                                                       $!"                                                                                                                                                                                              C=0=2/"                %$TV=-T$!"
                                                                                                                                                                                                                                                         #"
       $X!!!X!!!"                                                                                                                       #"
                                                                                                                                                                                                                                                                                                                                                               %TU53T$!"
                         !"                                                                                                             !"                                                                                                               !"
                                                                                                                                                                                                                                                                                                                                                                             $" (" #" '" *" $$"$("$#"$'"$*"%$"%("%#"%'"%*"($"(("(#"
                                  $" (" #" '" *" $$"$("$#"$'"$*"%$"%("%#"%'"%*"($"(("(#"                                                     $" (" #" '" *" $$" $(" $#" $'" $*" %$" %(" %#" %'" %*" ($" ((" (#"                                                  $" (" #" '" *" $$" $(" $#" $'" $*" %$" %(" %#" %'" %*" ($" ((" (#"

                                                                                                                                                                                      S//M"                                                                                                            S//M"                                                                                                  S//M"
                                                                     S//M"




Monday, 11 October 2010
Baseline Model : Week 0
      Inventory                                                                        Production

         3        2       1
         6        5       4
         9        8       7
        12        11      10
                                Program Leadership Kanban
        15        14      13
        18        17      16
                  20      19




                      Expense                   Client Cost   Performance   Schedule




Monday, 11 October 2010
Baseline Model : Week 1
      Inventory                                                                        Production

         3        2
         6        5       4
         9        8       7
        12        11      10
                                Program Leadership Kanban
        15        14      13
        18        17      16
                  20      19       1




                      Expense                   Client Cost   Performance   Schedule




Monday, 11 October 2010
Baseline Model : Week 2
      Inventory                                                                         Production

         3
         6        5       4
         9        8       7
        12        11      10
                                Program Leadership Kanban
        15        14      13
        18        17      16
                  20      19       2         1




                      Expense                    Client Cost   Performance   Schedule




Monday, 11 October 2010
Baseline Model : Week 3
      Inventory                                                                         Production




         6        5       4
         9        8       7
        12        11      10
                                Program Leadership Kanban
        15        14      13
        18        17      16
                  20      19       3         2          1




                      Expense                    Client Cost   Performance   Schedule




Monday, 11 October 2010
Baseline Model : Week 4
      Inventory                                                                             Production




         6        5
         9        8       7
        12        11      10
                                Program Leadership Kanban
        15        14      13
        18        17      16
                  20      19       4         3          2      1




                      Expense                    Client Cost       Performance   Schedule




Monday, 11 October 2010
Baseline Model : Week 5
      Inventory                                                                                 Production




         6
         9        8       7
        12        11      10
                                Program Leadership Kanban
        15        14      13
        18        17      16
                  20      19       5         4          3      2   1




                      Expense                    Client Cost           Performance   Schedule




Monday, 11 October 2010
Baseline Model : Week 6
      Inventory                                                                                 Production




         9        8       7
        12        11      10
                                Program Leadership Kanban
        15        14      13
        18        17      16
                  20      19       6         5          4      3   2     1




                      Expense                    Client Cost           Performance   Schedule




Monday, 11 October 2010
Baseline Model : Week 7
      Inventory                                                                                     Production




         9        8
        12        11      10
                                Program Leadership Kanban
        15        14      13
        18        17      16
                  20      19       7         6          5      4   3     2           1




                      Expense                    Client Cost           Performance       Schedule




Monday, 11 October 2010
Baseline Model : Week 8
      Inventory                                                                                        Production




         9
        12        11      10
                               Program Leadership Kanban
        15        14      13
        18        17      16
                  20      19      8         7          6      5   4     3           2   1




                   Expense                      Client Cost           Performance           Schedule




Monday, 11 October 2010
Baseline Model : Week 9
      Inventory                                                                                            Production




        12        11      10
                               Program Leadership Kanban
        15        14      13
        18        17      16
                  20      19      9         8          7      6   5     4           3   2   1




                   Expense                      Client Cost           Performance               Schedule




Monday, 11 October 2010
Baseline Model : Week 10
      Inventory                                                                                            Production

                                                                                                             1




        12        11
                               Program Leadership Kanban
        15        14      13
        18        17      16
                  20      19     10         9          8      7   6     5           4   3   2




                   Expense                      Client Cost           Performance               Schedule




Monday, 11 October 2010
Baseline Model : Week 11
      Inventory                                                                                            Production

                                                                                                             1          2




        12
                               Program Leadership Kanban
        15        14      13
        18        17      16
                  20      19     11        10          9      8   7     6           5   4   3




                   Expense                      Client Cost           Performance               Schedule




Monday, 11 October 2010
Baseline Model : Week 12
      Inventory                                                                                            Production

                                                                                                             1          2   3




                               Program Leadership Kanban
        15        14      13
        18        17      16
                  20      19     12        11         10      9   8     7           6   5   4




                   Expense                      Client Cost           Performance               Schedule




Monday, 11 October 2010
Baseline Model : Week 13
      Inventory                                                                                             Production

                                                                                                              1          2   3
                                                                                                              4



                               Program Leadership Kanban
        15        14
        18        17      16
                  20      19     13        12         11      10   9     8           7   6   5




                   Expense                      Client Cost            Performance               Schedule




Monday, 11 October 2010
Baseline Model : Week 14
      Inventory                                                                                              Production

                                                                                                               1          2   3
                                                                                                               4          5



                               Program Leadership Kanban
        15
        18        17      16
                  20      19     14        13         12      11   10     9           8   7   6




                   Expense                      Client Cost             Performance               Schedule




Monday, 11 October 2010
Baseline Model : Week 15
      Inventory                                                                                              Production

                                                                                                               1          2   3
                                                                                                               4          5   6



                               Program Leadership Kanban



        18        17      16
                  20      19     15        14         13      12   11    10           9   8   7




                   Expense                      Client Cost             Performance               Schedule




Monday, 11 October 2010
Baseline Model : Week 16
      Inventory                                                                                               Production

                                                                                                                1          2   3
                                                                                                                4          5   6
                                                                                                                7

                               Program Leadership Kanban



        18        17
                  20      19     16        15         14      13   12    11           10   9   8




                   Expense                      Client Cost             Performance                Schedule




Monday, 11 October 2010
Baseline Model : Week 17
      Inventory                                                                                                Production

                                                                                                                 1          2   3
                                                                                                                 4          5   6
                                                                                                                 7          8

                               Program Leadership Kanban



        18
                  20      19     17        16         15      14   13    12           11   10   9




                   Expense                      Client Cost             Performance                 Schedule




Monday, 11 October 2010
Baseline Model : Week 18
      Inventory                                                                                                 Production

                                                                                                                  1          2   3
                                                                                                                  4          5   6
                                                                                                                  7          8   9

                               Program Leadership Kanban




                  20      19     18        17         16      15   14    13           12   11   10




                   Expense                      Client Cost             Performance                  Schedule




Monday, 11 October 2010
Baseline Model : Week 19
      Inventory                                                                                               Production

                                                                                                                1          2   3
                                                                                                                4          5   6
                                                                                                                7          8   9
                                                                                                               10
                             Program Leadership Kanban




                  20           18        18         17      16   15    14           13   12   11




                   Expense                    Client Cost             Performance                  Schedule




Monday, 11 October 2010
Baseline Model : Week 20
      Inventory                                                                                               Production

                                                                                                                1          2   3
                                                                                                                4          5   6
                                                                                                                7          8   9
                                                                                                               10      11
                             Program Leadership Kanban




                               20        19         18      17   16    15           14   13   12




                   Expense                    Client Cost             Performance                  Schedule




Monday, 11 October 2010
Baseline Model : Week 21
      Inventory                                                                                               Production

                                                                                                                1          2   3
                                                                                                                4          5   6
                                                                                                                7          8   9
                                                                                                               10      11      12
                             Program Leadership Kanban




                                         20         19      18   17    16           15   14   13




                   Expense                    Client Cost             Performance                  Schedule




Monday, 11 October 2010
Baseline Model : Week 22
      Inventory                                                                                              Production

                                                                                                               1          2   3
                                                                                                               4          5   6
                                                                                                               7          8   9
                                                                                                              10      11      12
                             Program Leadership Kanban
                                                                                                              13


                                                   20      19   18    17           16   15   14




                   Expense                   Client Cost             Performance                  Schedule




Monday, 11 October 2010
Baseline Model : Week 23
      Inventory                                                                                              Production

                                                                                                               1          2   3
                                                                                                               4          5   6
                                                                                                               7          8   9
                                                                                                              10      11      12
                             Program Leadership Kanban
                                                                                                              13      14


                                                           20   19    18           17   16   15




                   Expense                   Client Cost             Performance                  Schedule




Monday, 11 October 2010
Baseline Model : Week 24
      Inventory                                                                                         Production

                                                                                                          1          2   3
                                                                                                          4          5   6
                                                                                                          7          8   9
                                                                                                         10      11      12
                             Program Leadership Kanban
                                                                                                         13      14      15


                                                           20    19           18   17   16




                   Expense                   Client Cost        Performance                  Schedule




Monday, 11 October 2010
Baseline Model : Week 25
      Inventory                                                                                    Production

                                                                                                     1          2   3
                                                                                                     4          5   6
                                                                                                     7          8   9
                                                                                                    10      11      12
                             Program Leadership Kanban
                                                                                                    13      14      15
                                                                                                    16
                                                            20           19   18   17




                   Expense                   Client Cost   Performance                  Schedule




Monday, 11 October 2010
Baseline Model : Week 26
      Inventory                                                                                    Production

                                                                                                     1          2   3
                                                                                                     4          5   6
                                                                                                     7          8   9
                                                                                                    10      11      12
                             Program Leadership Kanban
                                                                                                    13      14      15
                                                                                                    16      17
                                                                         20   19   18




                   Expense                   Client Cost   Performance                  Schedule




Monday, 11 October 2010
Baseline Model : Week 27
      Inventory                                                                               Production

                                                                                                1          2   3
                                                                                                4          5   6
                                                                                                7          8   9
                                                                                               10      11      12
                             Program Leadership Kanban
                                                                                               13      14      15
                                                                                               16      17      18
                                                                         20   19




                   Expense                   Client Cost   Performance             Schedule




Monday, 11 October 2010
Baseline Model : Week 28
      Inventory                                                                          Production

                                                                                           1          2   3
                                                                                           4          5   6
                                                                                           7          8   9
                                                                                          10      11      12
                             Program Leadership Kanban
                                                                                          13      14      15
                                                                                          16      17      18
                                                                         20               19




                   Expense                   Client Cost   Performance        Schedule




Monday, 11 October 2010
Baseline Model : Week 29
      Inventory                                                                     Production

                                                                                      1          2   3
                                                                                      4          5   6
                                                                                      7          8   9
                                                                                     10      11      12
                             Program Leadership Kanban
                                                                                     13      14      15
                                                                                     16      17      18
                                                                                     19      20




                   Expense                   Client Cost   Performance   Schedule




Monday, 11 October 2010
Baseline Model : Week 30
      Inventory                                                                     Production

                                                                                      1          2   3
                                                                                      4          5   6
                                                                                      7          8   9
                                                                                     10      11      12
                             Program Leadership Kanban
                                                                                     13      14      15
                                                                                     16      17      18
                                                                                     19      20




                   Expense                   Client Cost   Performance   Schedule




Monday, 11 October 2010
Baseline Model : Over Time
      Inventory                                                                     Production

                                                                                      1          2   3
                             Backlog                                                  4          5   6
                                                                                      7          8   9
                                                                                     10      11      12
                             Program Leadership Kanban
                                                                                     13      14      15
                                                                                     16      17      18
                                                                                     19      20




                   Expense                   Client Cost   Performance   Schedule




Monday, 11 October 2010
Baseline Model : Over Time
      Inventory                                                                       Production

                                                                                        1          2   3
                                                                                        4          5   6
                                                                         Done           7          8   9
                                                                                       10      11      12
                             Program Leadership Kanban
                                                                                       13      14      15
                                                                                       16      17      18
                                                                                       19      20




                   Expense                   Client Cost   Performance     Schedule




Monday, 11 October 2010
Baseline Model : Over Time
      Inventory                                                                             Production

                                                                                              1          2   3
                                                                   In Progress
                                                                                              4          5   6

                                             In Progress
                                                                                              7          8   9
                                                                                             10      11      12
                             Program Leadership Kanban
                                                                                             13      14      15
                                                                                             16      17      18
                                                                                             19      20




                   Expense                   Client Cost   Performance           Schedule




Monday, 11 October 2010
Hawks



Monday, 11 October 2010
Monday, 11 October 2010
Scenario
          •      15th Feb Iteration 53
          •      Tasked with resolving performance related technical debt
          •      Tasked with resolving scalability related technical debt
          •      Spent two iterations analysing system
          •      Under pressure to produce user stories
          •      Under pressure to provide reliable estimates for stories
          •      Failing to deliver on iteration commitments
          •      Level of uncertainty too high to provide consistent estimation
          •      Migrating to Kanban to manage development and incremental improvement




Monday, 11 October 2010
Monday, 11 October 2010
Monday, 11 October 2010
Monday, 11 October 2010
Monday, 11 October 2010
Monday, 11 October 2010
Monday, 11 October 2010
Monday, 11 October 2010
Monday, 11 October 2010
Monday, 11 October 2010
Monday, 11 October 2010
Monday, 11 October 2010
Monday, 11 October 2010
Color coding of work
                                                                                                         Time & Date                      items
                                                                                                       ‘Record Triggers’
           Separate bins for waste divided
              between time waste and                                                                                                                      Statistical process
                requirements waste               Prioritized inventory of       Filter for highest                                                          control charts
                                                      requirements                priority work
                                                                                                                                                     ‘Fast-Lane’ for work
                                                                                                                                                    with priority conditions
                                                                                                                                                           of service




                                                                                                                                                    Work In Progress limits




                                                                                                                                                        Program level
                                                                                                                                                      consistent practice




                                                                                                                                                    Exit Criteria



                                                                       Ideas for process improvement                                         Easy access to tools
                                Photos of last kaizen                      that are outside teams                                               and materials
                                 event whiteboard                                                                 Entry Criteria
                                                                              immediate control




Monday, 11 October 2010
Monday, 11 October 2010
Monday, 11 October 2010
Monday, 11 October 2010
Silver Bullet

                                                                                                                               Rob                       1
                                !          !                        !
                              Defect                              Functional
                              DE1504
                              Launch Preditor
                                                                  US7306-1
                                                                  Browser Bookmark Launch
                                                                                                                RELEASE        Rob                       2
                              Bookmarklet : Can cause JS
                              error if clicked during page load
                              Class of Service
                              Expedite
                                                                  Class of Service                                             Rob                       3
                                                                  Standard
                              Number of Cycles                    Number of Cycles
                                                                                             !                                  !
             Impediment!                                                                     !                                  ! !                             !
                              Analysis                            Analysis                  Analysis                           Analysis
                                                                                                                                Design                         De
                              Start Date                                                    Named product                      Named product
                                                                                                                                 Documented                    Doc
                                                                  Start Date                owner                              owner
                              End Date                            End Date                  Named domain                       Named Reviewed
                                                                                                                                 Peer domain                   Pee
                              Design                              Design                    experts                            experts
                              Start Date                          Start Date                Identify benefits                  Identify benefits
                                                                                                                                 Identify                      Iden
                              End Date                                                                                           interfaces                    inte
                                                                  End Date                                                       (AMDD)                        (AM
                              Awaiting Implementation                                       Identify risks                     Identify risks
                                                                  Awaiting Implementation                                        Identify                      Iden
                              Start Date                          Start Date                                                     Components                    Com
                                                                                            Identify test                        (AMDD)
                                                                                                                               Identify test                   (AM
                              End Date                            End Date                  Approach                           Approach
                                                                                                                                 Consider                      Con
              BLOCKED!        Implementation                      Implementation            Outline technical
                                                                                                                                 Alternatives
                                                                                                                               Outline technical
                                                                                                                                                               Alte
                              Start Date                          Start Date                approach                           approach
                                                                                                                                 List Non                      List
                                                                                                                                 Functional                    Fun
                              End Date                                                      Agreed with                        Agreed with
                                                                  End Date                  users
                                                                                                                                 Considerations
                                                                                                                               users
                                                                                                                                                               Con
                                                                                                                                 Technical                     Tec
                              Committed                           Committed                 Agreed with                          Spike?
                                                                                                                               Agreed with                     Spik
                              Start Date                          Start Date                product owner!                     product owner!
                              End Date                            End Date                  Peer Review!                       Peer Review!
                              Is Packaged                         Is Packaged
                              Start Date                          Start Date
                              End Date                            End Date

                  1           Test
                              Start Date
                                                                  Test
                                                                  Start Date

             DEFECT           End Date
                              Ready For Test Release
                              Start Date
                                                                  End Date
                                                                  Ready For Test Release
                                                                  Start Date
                              End Date                            End Date
                              Release To Test                     Release To Test
                              Start Date                          Start Date
                              End Date                            End Date
                              Ready For Live Release              Ready For Live Release
                              Start Date                          Start Date
            WIP               End Date                            End Date

          THROTTLE            Release To Live
                              Start Date
                                                                  Release To Live
                                                                  Start Date
                              End Date                            End Date

                                                                                                            Associated Tasks               Associated Tasks
                                                                                                                                            Associated Tasks




                                                                                               !                                 ! !                             !
                                                                                               !                                 ! !                             !
                                                                                               !                                 ! !                             !
                                                                                               !                                   !                             !
                                                                                               !                                   !                             !
                                                                                               !                                   !                             !
                                                                                               !                                   !                             !
                                                                                               !                                   !                             !
Monday, 11 October 2010                                                                        !                                   !                             !
Monday, 11 October 2010
Monday, 11 October 2010
Administration




Monday, 11 October 2010
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan
Applying lean principles and kanban in the enterprise - Kevin Ryan

More Related Content

What's hot

Simulating Software Teams
Simulating Software Teams Simulating Software Teams
Simulating Software Teams AgileSparks
 
Introduction To Agile
Introduction To AgileIntroduction To Agile
Introduction To AgileTony Deng
 
Agile tour 2011 ralph jocham
Agile tour 2011   ralph jochamAgile tour 2011   ralph jocham
Agile tour 2011 ralph jochamAgora Group
 
The Manager's Dilemma
The Manager's DilemmaThe Manager's Dilemma
The Manager's DilemmaOla Sundin
 
Accounting cycle puzzle..
Accounting cycle puzzle..Accounting cycle puzzle..
Accounting cycle puzzle..SlideTeam.net
 
Accounting cycle puzzle ppt templates
Accounting cycle puzzle ppt templatesAccounting cycle puzzle ppt templates
Accounting cycle puzzle ppt templatesSlideTeam.net
 
Beyond Scrum: Scaling Agile with Continuous Delivery and Subversion
Beyond Scrum: Scaling Agile with Continuous Delivery and SubversionBeyond Scrum: Scaling Agile with Continuous Delivery and Subversion
Beyond Scrum: Scaling Agile with Continuous Delivery and SubversionProduct Marketing Services
 
Amy.stapleton
Amy.stapletonAmy.stapleton
Amy.stapletonNASAPMC
 
Agile Scrum in 60 minutes
Agile Scrum in 60 minutesAgile Scrum in 60 minutes
Agile Scrum in 60 minutesSyed Arh
 
Timelessness of Lean Management
Timelessness of Lean ManagementTimelessness of Lean Management
Timelessness of Lean ManagementVersionOne
 
David Weir And Graham Fisher - Scaling Agility Across the Enterprise
David Weir And Graham Fisher - Scaling Agility Across the EnterpriseDavid Weir And Graham Fisher - Scaling Agility Across the Enterprise
David Weir And Graham Fisher - Scaling Agility Across the EnterpriseAgile Lietuva
 

What's hot (14)

Simulating Software Teams
Simulating Software Teams Simulating Software Teams
Simulating Software Teams
 
Introduction To Agile
Introduction To AgileIntroduction To Agile
Introduction To Agile
 
Agile tour 2011 ralph jocham
Agile tour 2011   ralph jochamAgile tour 2011   ralph jocham
Agile tour 2011 ralph jocham
 
Agiletools
AgiletoolsAgiletools
Agiletools
 
The Manager's Dilemma
The Manager's DilemmaThe Manager's Dilemma
The Manager's Dilemma
 
Accounting cycle puzzle..
Accounting cycle puzzle..Accounting cycle puzzle..
Accounting cycle puzzle..
 
Accounting cycle puzzle ppt templates
Accounting cycle puzzle ppt templatesAccounting cycle puzzle ppt templates
Accounting cycle puzzle ppt templates
 
Beyond Scrum: Scaling Agile with Continuous Delivery and Subversion
Beyond Scrum: Scaling Agile with Continuous Delivery and SubversionBeyond Scrum: Scaling Agile with Continuous Delivery and Subversion
Beyond Scrum: Scaling Agile with Continuous Delivery and Subversion
 
Transforming your sw development to agile
Transforming your sw development to agileTransforming your sw development to agile
Transforming your sw development to agile
 
Magic of scrum with SAP
Magic of scrum with SAPMagic of scrum with SAP
Magic of scrum with SAP
 
Amy.stapleton
Amy.stapletonAmy.stapleton
Amy.stapleton
 
Agile Scrum in 60 minutes
Agile Scrum in 60 minutesAgile Scrum in 60 minutes
Agile Scrum in 60 minutes
 
Timelessness of Lean Management
Timelessness of Lean ManagementTimelessness of Lean Management
Timelessness of Lean Management
 
David Weir And Graham Fisher - Scaling Agility Across the Enterprise
David Weir And Graham Fisher - Scaling Agility Across the EnterpriseDavid Weir And Graham Fisher - Scaling Agility Across the Enterprise
David Weir And Graham Fisher - Scaling Agility Across the Enterprise
 

Viewers also liked

Enterprise kanban at mobile.de - Markus Andrezak
Enterprise kanban at mobile.de - Markus AndrezakEnterprise kanban at mobile.de - Markus Andrezak
Enterprise kanban at mobile.de - Markus AndrezakAGILEMinds
 
Diacritice romanesti in linux
Diacritice romanesti in linuxDiacritice romanesti in linux
Diacritice romanesti in linuxdianaifrim
 
Chu National Press Club112910
Chu National Press Club112910Chu National Press Club112910
Chu National Press Club112910James McDougall
 
Ireland, Part 2
Ireland, Part 2Ireland, Part 2
Ireland, Part 2iamjak123
 
Invito Rist.Giapponese
Invito Rist.GiapponeseInvito Rist.Giapponese
Invito Rist.Giapponeseguest3473710
 
Hola! Powerpoint
Hola! PowerpointHola! Powerpoint
Hola! PowerpointBrendaKubly
 
Concurso postres halloween
Concurso postres halloweenConcurso postres halloween
Concurso postres halloweenjosec9911
 
Bab 4 kerja paip
Bab 4 kerja paipBab 4 kerja paip
Bab 4 kerja paipBasri Bsr
 
Enjin lejang1
Enjin lejang1Enjin lejang1
Enjin lejang1Basri Bsr
 
Online Affiliate Presentation 1
Online  Affiliate  Presentation 1Online  Affiliate  Presentation 1
Online Affiliate Presentation 1OhnoDesign
 
Group 4 Project
Group 4 ProjectGroup 4 Project
Group 4 ProjectCindy Cho
 
Organizational culture
Organizational cultureOrganizational culture
Organizational cultureNeha Rathi
 

Viewers also liked (16)

6.1 Scientific Method
6.1 Scientific Method6.1 Scientific Method
6.1 Scientific Method
 
Enterprise kanban at mobile.de - Markus Andrezak
Enterprise kanban at mobile.de - Markus AndrezakEnterprise kanban at mobile.de - Markus Andrezak
Enterprise kanban at mobile.de - Markus Andrezak
 
Diacritice romanesti in linux
Diacritice romanesti in linuxDiacritice romanesti in linux
Diacritice romanesti in linux
 
Hr Hlb
Hr HlbHr Hlb
Hr Hlb
 
Chu National Press Club112910
Chu National Press Club112910Chu National Press Club112910
Chu National Press Club112910
 
Ireland, Part 2
Ireland, Part 2Ireland, Part 2
Ireland, Part 2
 
Invito Rist.Giapponese
Invito Rist.GiapponeseInvito Rist.Giapponese
Invito Rist.Giapponese
 
Hola! Powerpoint
Hola! PowerpointHola! Powerpoint
Hola! Powerpoint
 
Keyboarding 6th
Keyboarding 6thKeyboarding 6th
Keyboarding 6th
 
Concurso postres halloween
Concurso postres halloweenConcurso postres halloween
Concurso postres halloween
 
Bab 4 kerja paip
Bab 4 kerja paipBab 4 kerja paip
Bab 4 kerja paip
 
Enjin lejang1
Enjin lejang1Enjin lejang1
Enjin lejang1
 
Online Affiliate Presentation 1
Online  Affiliate  Presentation 1Online  Affiliate  Presentation 1
Online Affiliate Presentation 1
 
Group 4 Project
Group 4 ProjectGroup 4 Project
Group 4 Project
 
Fractures
FracturesFractures
Fractures
 
Organizational culture
Organizational cultureOrganizational culture
Organizational culture
 

Similar to Applying lean principles and kanban in the enterprise - Kevin Ryan

Agile Development 2012 sharing and Kanban Introduction
Agile Development 2012 sharing and Kanban IntroductionAgile Development 2012 sharing and Kanban Introduction
Agile Development 2012 sharing and Kanban IntroductionJen-Chieh Ko
 
Scaling Scrum in the Enterprise with Kanban
Scaling Scrum in the Enterprise with KanbanScaling Scrum in the Enterprise with Kanban
Scaling Scrum in the Enterprise with KanbanChristophe Achouiantz
 
Bättre Scrum i stor skala med Kanban
Bättre Scrum i stor skala med KanbanBättre Scrum i stor skala med Kanban
Bättre Scrum i stor skala med KanbanAgila Sverige
 
Agile Fundamental Skill Set
Agile Fundamental Skill SetAgile Fundamental Skill Set
Agile Fundamental Skill SetTsuyoshi Ushio
 
Implementation of an agile process for multiple teams using SVN
Implementation of an agile process for multiple teams using SVNImplementation of an agile process for multiple teams using SVN
Implementation of an agile process for multiple teams using SVNDr. Alexander Schwartz
 
Introduction to kanban lean ghm_02022010
Introduction to kanban lean ghm_02022010Introduction to kanban lean ghm_02022010
Introduction to kanban lean ghm_02022010Mads Troels Hansen
 
Agile conference2010 upstream-kanban_at_ctct
Agile conference2010 upstream-kanban_at_ctctAgile conference2010 upstream-kanban_at_ctct
Agile conference2010 upstream-kanban_at_ctctMike Fitterman
 
Scrumban (Lean Agile Fusion) V1.1
Scrumban (Lean Agile Fusion) V1.1Scrumban (Lean Agile Fusion) V1.1
Scrumban (Lean Agile Fusion) V1.1Michael O'Rourke
 
Scrumban (Lean-Agile Fusion) v1.1
Scrumban (Lean-Agile Fusion) v1.1Scrumban (Lean-Agile Fusion) v1.1
Scrumban (Lean-Agile Fusion) v1.1michaelorourke00
 
Agile DevOps: The Long, Ugly Story of How We Got Better
Agile DevOps: The Long, Ugly Story of How We Got BetterAgile DevOps: The Long, Ugly Story of How We Got Better
Agile DevOps: The Long, Ugly Story of How We Got BetterTommy Norman
 
Lean & agile 101 for Astute Entrepreneurs
Lean & agile 101 for Astute EntrepreneursLean & agile 101 for Astute Entrepreneurs
Lean & agile 101 for Astute EntrepreneursClaudio Perrone
 
Distributed Agile Teams
Distributed Agile TeamsDistributed Agile Teams
Distributed Agile TeamsBrian Estep
 
Dietmar Strasser - Traditional QA meets Agile Development
Dietmar Strasser -  Traditional QA meets Agile DevelopmentDietmar Strasser -  Traditional QA meets Agile Development
Dietmar Strasser - Traditional QA meets Agile DevelopmentTEST Huddle
 
Nearshore presentation (feb 2013)
Nearshore presentation (feb 2013)Nearshore presentation (feb 2013)
Nearshore presentation (feb 2013)Peter Stroeve
 
Refactoring the Organization Design (LESS2010)
Refactoring the Organization Design (LESS2010)Refactoring the Organization Design (LESS2010)
Refactoring the Organization Design (LESS2010)Ken Power
 
Scrum vs Kanban: Is there really a battle?
Scrum vs Kanban: Is there really a battle?Scrum vs Kanban: Is there really a battle?
Scrum vs Kanban: Is there really a battle?Flavius Stef
 
Agile cambridge 27th September 2012
Agile cambridge 27th September 2012Agile cambridge 27th September 2012
Agile cambridge 27th September 2012Carl Bruiners
 

Similar to Applying lean principles and kanban in the enterprise - Kevin Ryan (20)

Agile Development 2012 sharing and Kanban Introduction
Agile Development 2012 sharing and Kanban IntroductionAgile Development 2012 sharing and Kanban Introduction
Agile Development 2012 sharing and Kanban Introduction
 
Scaling Scrum in the Enterprise with Kanban
Scaling Scrum in the Enterprise with KanbanScaling Scrum in the Enterprise with Kanban
Scaling Scrum in the Enterprise with Kanban
 
Bättre Scrum i stor skala med Kanban
Bättre Scrum i stor skala med KanbanBättre Scrum i stor skala med Kanban
Bättre Scrum i stor skala med Kanban
 
Intro to Agile
Intro to AgileIntro to Agile
Intro to Agile
 
Agile Fundamental Skill Set
Agile Fundamental Skill SetAgile Fundamental Skill Set
Agile Fundamental Skill Set
 
Implementation of an agile process for multiple teams using SVN
Implementation of an agile process for multiple teams using SVNImplementation of an agile process for multiple teams using SVN
Implementation of an agile process for multiple teams using SVN
 
Introduction to kanban lean ghm_02022010
Introduction to kanban lean ghm_02022010Introduction to kanban lean ghm_02022010
Introduction to kanban lean ghm_02022010
 
Agile at AT&T
Agile at AT&TAgile at AT&T
Agile at AT&T
 
Agile conference2010 upstream-kanban_at_ctct
Agile conference2010 upstream-kanban_at_ctctAgile conference2010 upstream-kanban_at_ctct
Agile conference2010 upstream-kanban_at_ctct
 
Scrumban (Lean Agile Fusion) V1.1
Scrumban (Lean Agile Fusion) V1.1Scrumban (Lean Agile Fusion) V1.1
Scrumban (Lean Agile Fusion) V1.1
 
Scrumban (Lean-Agile Fusion) v1.1
Scrumban (Lean-Agile Fusion) v1.1Scrumban (Lean-Agile Fusion) v1.1
Scrumban (Lean-Agile Fusion) v1.1
 
Agile DevOps: The Long, Ugly Story of How We Got Better
Agile DevOps: The Long, Ugly Story of How We Got BetterAgile DevOps: The Long, Ugly Story of How We Got Better
Agile DevOps: The Long, Ugly Story of How We Got Better
 
Lean & agile 101 for Astute Entrepreneurs
Lean & agile 101 for Astute EntrepreneursLean & agile 101 for Astute Entrepreneurs
Lean & agile 101 for Astute Entrepreneurs
 
Distributed Agile Teams
Distributed Agile TeamsDistributed Agile Teams
Distributed Agile Teams
 
Dietmar Strasser - Traditional QA meets Agile Development
Dietmar Strasser -  Traditional QA meets Agile DevelopmentDietmar Strasser -  Traditional QA meets Agile Development
Dietmar Strasser - Traditional QA meets Agile Development
 
Nearshore presentation (feb 2013)
Nearshore presentation (feb 2013)Nearshore presentation (feb 2013)
Nearshore presentation (feb 2013)
 
Scrumban
ScrumbanScrumban
Scrumban
 
Refactoring the Organization Design (LESS2010)
Refactoring the Organization Design (LESS2010)Refactoring the Organization Design (LESS2010)
Refactoring the Organization Design (LESS2010)
 
Scrum vs Kanban: Is there really a battle?
Scrum vs Kanban: Is there really a battle?Scrum vs Kanban: Is there really a battle?
Scrum vs Kanban: Is there really a battle?
 
Agile cambridge 27th September 2012
Agile cambridge 27th September 2012Agile cambridge 27th September 2012
Agile cambridge 27th September 2012
 

More from AGILEMinds

Lean Startup - Customer Development - Aarrr metrics
Lean Startup - Customer Development - Aarrr metricsLean Startup - Customer Development - Aarrr metrics
Lean Startup - Customer Development - Aarrr metricsAGILEMinds
 
Sami honkonen scheduling work in kanban
Sami honkonen   scheduling work in kanbanSami honkonen   scheduling work in kanban
Sami honkonen scheduling work in kanbanAGILEMinds
 
Patrick steyaert lean adaptive management - achieving complex business goal...
Patrick steyaert   lean adaptive management - achieving complex business goal...Patrick steyaert   lean adaptive management - achieving complex business goal...
Patrick steyaert lean adaptive management - achieving complex business goal...AGILEMinds
 
Olav maassen risk management
Olav maassen   risk managementOlav maassen   risk management
Olav maassen risk managementAGILEMinds
 
Nick boucart lean startups
Nick boucart   lean startupsNick boucart   lean startups
Nick boucart lean startupsAGILEMinds
 
Mike burrows level demand, balance workload and manage schedule risk with c...
Mike burrows   level demand, balance workload and manage schedule risk with c...Mike burrows   level demand, balance workload and manage schedule risk with c...
Mike burrows level demand, balance workload and manage schedule risk with c...AGILEMinds
 
Michael kennedy set-based decision making taming system complexity
Michael kennedy   set-based decision making taming system complexityMichael kennedy   set-based decision making taming system complexity
Michael kennedy set-based decision making taming system complexityAGILEMinds
 
Mattias skarin what would you do - analysing charts
Mattias skarin   what would you do - analysing chartsMattias skarin   what would you do - analysing charts
Mattias skarin what would you do - analysing chartsAGILEMinds
 
Matthias bohlen team and contracts
Matthias bohlen   team and contractsMatthias bohlen   team and contracts
Matthias bohlen team and contractsAGILEMinds
 
Mark robinson what does lean mean for software testing
Mark robinson   what does lean mean for software testingMark robinson   what does lean mean for software testing
Mark robinson what does lean mean for software testingAGILEMinds
 
Karl scotland science of kanban
Karl scotland   science of kanbanKarl scotland   science of kanban
Karl scotland science of kanbanAGILEMinds
 
Jurgen de smet yves hanoulle real options
Jurgen de smet yves hanoulle   real optionsJurgen de smet yves hanoulle   real options
Jurgen de smet yves hanoulle real optionsAGILEMinds
 
John seddon it’s the system stupid!
John seddon   it’s the system stupid!John seddon   it’s the system stupid!
John seddon it’s the system stupid!AGILEMinds
 
Jasper sonnevelt pitfalls of a large kanban implementation
Jasper sonnevelt   pitfalls of a large kanban implementationJasper sonnevelt   pitfalls of a large kanban implementation
Jasper sonnevelt pitfalls of a large kanban implementationAGILEMinds
 
Jason yip kanban for it operations
Jason yip   kanban for it operationsJason yip   kanban for it operations
Jason yip kanban for it operationsAGILEMinds
 
Eric willeke when models collide
Eric willeke   when models collideEric willeke   when models collide
Eric willeke when models collideAGILEMinds
 
Don reinertsen is it time to rethink deming
Don reinertsen   is it time to rethink demingDon reinertsen   is it time to rethink deming
Don reinertsen is it time to rethink demingAGILEMinds
 
David joyce jalipo build it and they will come
David joyce   jalipo build it and they will comeDavid joyce   jalipo build it and they will come
David joyce jalipo build it and they will comeAGILEMinds
 
David anderson kanban when is it not appropriate
David anderson   kanban when is it not appropriateDavid anderson   kanban when is it not appropriate
David anderson kanban when is it not appropriateAGILEMinds
 
Dave snowden practice without sound theory will not scale
Dave snowden   practice without sound theory will not scaleDave snowden   practice without sound theory will not scale
Dave snowden practice without sound theory will not scaleAGILEMinds
 

More from AGILEMinds (20)

Lean Startup - Customer Development - Aarrr metrics
Lean Startup - Customer Development - Aarrr metricsLean Startup - Customer Development - Aarrr metrics
Lean Startup - Customer Development - Aarrr metrics
 
Sami honkonen scheduling work in kanban
Sami honkonen   scheduling work in kanbanSami honkonen   scheduling work in kanban
Sami honkonen scheduling work in kanban
 
Patrick steyaert lean adaptive management - achieving complex business goal...
Patrick steyaert   lean adaptive management - achieving complex business goal...Patrick steyaert   lean adaptive management - achieving complex business goal...
Patrick steyaert lean adaptive management - achieving complex business goal...
 
Olav maassen risk management
Olav maassen   risk managementOlav maassen   risk management
Olav maassen risk management
 
Nick boucart lean startups
Nick boucart   lean startupsNick boucart   lean startups
Nick boucart lean startups
 
Mike burrows level demand, balance workload and manage schedule risk with c...
Mike burrows   level demand, balance workload and manage schedule risk with c...Mike burrows   level demand, balance workload and manage schedule risk with c...
Mike burrows level demand, balance workload and manage schedule risk with c...
 
Michael kennedy set-based decision making taming system complexity
Michael kennedy   set-based decision making taming system complexityMichael kennedy   set-based decision making taming system complexity
Michael kennedy set-based decision making taming system complexity
 
Mattias skarin what would you do - analysing charts
Mattias skarin   what would you do - analysing chartsMattias skarin   what would you do - analysing charts
Mattias skarin what would you do - analysing charts
 
Matthias bohlen team and contracts
Matthias bohlen   team and contractsMatthias bohlen   team and contracts
Matthias bohlen team and contracts
 
Mark robinson what does lean mean for software testing
Mark robinson   what does lean mean for software testingMark robinson   what does lean mean for software testing
Mark robinson what does lean mean for software testing
 
Karl scotland science of kanban
Karl scotland   science of kanbanKarl scotland   science of kanban
Karl scotland science of kanban
 
Jurgen de smet yves hanoulle real options
Jurgen de smet yves hanoulle   real optionsJurgen de smet yves hanoulle   real options
Jurgen de smet yves hanoulle real options
 
John seddon it’s the system stupid!
John seddon   it’s the system stupid!John seddon   it’s the system stupid!
John seddon it’s the system stupid!
 
Jasper sonnevelt pitfalls of a large kanban implementation
Jasper sonnevelt   pitfalls of a large kanban implementationJasper sonnevelt   pitfalls of a large kanban implementation
Jasper sonnevelt pitfalls of a large kanban implementation
 
Jason yip kanban for it operations
Jason yip   kanban for it operationsJason yip   kanban for it operations
Jason yip kanban for it operations
 
Eric willeke when models collide
Eric willeke   when models collideEric willeke   when models collide
Eric willeke when models collide
 
Don reinertsen is it time to rethink deming
Don reinertsen   is it time to rethink demingDon reinertsen   is it time to rethink deming
Don reinertsen is it time to rethink deming
 
David joyce jalipo build it and they will come
David joyce   jalipo build it and they will comeDavid joyce   jalipo build it and they will come
David joyce jalipo build it and they will come
 
David anderson kanban when is it not appropriate
David anderson   kanban when is it not appropriateDavid anderson   kanban when is it not appropriate
David anderson kanban when is it not appropriate
 
Dave snowden practice without sound theory will not scale
Dave snowden   practice without sound theory will not scaleDave snowden   practice without sound theory will not scale
Dave snowden practice without sound theory will not scale
 

Applying lean principles and kanban in the enterprise - Kevin Ryan

  • 1. Kanban In The Enterprise Kevin Ryan : Agile Practices Consultant Monday, 11 October 2010
  • 2. The Starting Point • Scrum project • Running for two years • Second architectural refresh • Highly pressurised environment • Low stakeholder confidence • Combined on-shore and off-shore resource • Project head count around 50 • Unable to estimate reliable completion dates • Product considered critical to business strategy • Increasing technical debt Monday, 11 October 2010
  • 3. Evolution : 0 Enterprise Program Level Process Team Level Process Program Level Process Enterprise Process Process Team A Scrum Team B Scrum Team C Scrum Team D Scrum Value Stream Monday, 11 October 2010
  • 4. Evolution : 1 Enterprise Program Level Process Team Level Process Program Level Process Enterprise Process Process Team A Scrum Team B Kanban Team C Scrum Team D Scrum Value Stream Monday, 11 October 2010
  • 5. Evolution : 2 Enterprise Program Level Process Team Level Process Program Level Process Enterprise Process Process Team A Scrum Team B Kanban Team C Scrum Team D Kanban Value Stream Monday, 11 October 2010
  • 6. Evolution : 3 Enterprise Team Level Process Program Level Process Team Level Process Program Level Process Enterprise Process Process Team A Scrum Team B Kanban Program Leadership Kanban Team C Scrum Team D Kanban Value Stream Monday, 11 October 2010
  • 7. Evolution : 4 Enterprise Team Level Process Program Level Process Team Level Process Program Level Process Team Level Process Enterprise Process Process Team A Scrum Team B Kanban Program Leadership Kanban Program Cohesion Kanban Team C Scrum Team D Kanban Value Stream Monday, 11 October 2010
  • 8. Evolution : X Enterprise Team Level Process Program Level Process Team Level Process Program Level Process Team Level Process Enterprise Process Process Team A Kanban Team B Kanban Program Leadership Kanban Program Cohesion Kanban Team C Kanban Team D Kanban Value Stream Monday, 11 October 2010
  • 13. Scrum Boards Monday, 11 October 2010
  • 20. Sharing The Big Picture Monday, 11 October 2010
  • 23. Focusing on Value Monday, 11 October 2010
  • 32. Just In Time “  If  you’re  early  you  are  was/ng  your  /me, if  you’re  late  you  are  was/ng  mine.” !"#$%&'()*+($&,)-+.)&/#*$#01&2*-&3.4#&56&/#$$"78-57& Monday, 11 October 2010
  • 42. Workflow Falcon Program Level Kanban Workflow Definition Two Week Cadence Workflow Stage Baseline High Level Form Architectural Requirements Resolve Story Breakdown & Estimate Points Resolve Team Ready For Technical WIP Limit Business Objectives 3 Design 2 Cohesion 2 Organisational 2 Traceability 2 2 Dependencies 2 Implementation 4 Exit Criteria Named product owner Falcon touchpoints None functional Named contacts for Story acceptance Stories are broken Resource Appropriate identified requirements agreed external criteria expressed in down to a dependencies development team Named key dependencies a manner that allows reasonably between teams have identified stakeholders External interfaces Functional for executable consistent size been identified identified requirements agreed External specification Team have reviewed Descriptive paragraph dependencies aware Stories have a Named points of materials and are of theme and sub- High level User interface of scheduled change Product verification relative points contact between willing to accept themes components prototypes produced checks identified estimate teams exist feature into identified Impact between development Problem/Value external Testability features Multiple teams are process Statements Strategic review dependencies have been identified aware of scheduled complete identified (eg: logging, tracing) change and have Technical skills exist Bullet pointed list of (possible breaking capacity to manage within the team to business objectives Any third party change?) dependencies deliver specified suppliers identified feature External dependencies Impact on physical Named development identified architecture owner identified Stakeholder agreement None functional aspects identified and listed I=D=75B./"C71N" %#" ,-./-0123" %!" 456/78-/"98:;"</./7"4=68-/66">?@/AB./6" C12D"E2A;80/A0=257"F/68:-" G/H=82/D/-06"I1;/681-" S12M",0/D"42/5MK1N-" $#" G/617./">2:5-865B1-57"F/J/-K/-A8/6" L0123"42/5MK1N-"O"P25A/5?87803" $!" Q6BD50/"R18-06" G/617./"P/5D"F/J/-K/-A8/6" #" G/5K3"C12"P/A;-8A57",DJ7/D/-05B1-" ,DJ7/D/-05B1-" ,-"R21K=AB1-" !" $" %" &" '" #" (" )" *" +" $!" $$" $%" $&" $'" $#" $(" $)" $*" $+" %!" %$" %%" %&" %'" %#" F536"Q75J6/K",-"L5DJ7/" Page 1 Monday, 11 October 2010
  • 44. Falcon Program Level Kanban Workflow Definition Two Week Cadence Workflow Stage Baseline High Level Form Architectural Requirements Resolve Story Breakdown & Estimate Points Resolve Team Ready For Technical Business Objectives Design Cohesion Organisational Traceability Dependencies Implementation Notes Dependencies WIP Limit 3 2 2 2 2 2 2 4 This document is not an estimate of work remaining. Exit Criteria Named product owner Falcon touchpoints None functional Named contacts for Story acceptance Stories are broken Resource Appropriate identified requirements agreed external criteria expressed in a down to a reasonably dependencies development team Named key dependencies manner that allows for consistent size between teams have identified This document is not a commitment to delivery dates. stakeholders External interfaces Functional executable been identified identified requirements agreed External specification Stories have a Team have reviewed This document is a derived model based upon the current defined development process and is Descriptive paragraph dependencies aware relative points Named points of materials and are intended as a tool to improve estimation and maximise requirements flow. of theme and sub- High level User interface of scheduled change Product verification estimate contact between willing to accept themes components identified prototypes produced checks identified teams exist feature into Impact between development process Definitions Problem/Value Strategic review external Testability features Multiple teams are Flow : The movement of requirements through the program workflow and into production. Statements complete dependencies have been identified aware of scheduled Technical skills exist identified (eg: logging, tracing) change and have within the team to Bullet pointed list of Any third party (possible breaking capacity to manage deliver specified Cycle Time : The duration of any given feature or requirement to complete its development cycle. business objectives suppliers identified change?) dependencies feature Flow Rate : The frequency at which features or requirements complete a development workflow. External dependencies Impact on physical Named development identified architecture identified owner Intended Outcome : Stakeholder agreement None functional Positive actions to reduce cycle times at the Program, Theme and Story Level. aspects identified and listed Positive actions to increase flow rate at the Program, Theme and Story Level. Technical frameworks identified (eg. Spring) Internal interfaces defined Named technical owner I1-0217"456/78-/"I=D=75B./"C71N" Baseline Characteristics Sample Start Date 01-May-10 %#" Sample End Date 31-Dec-10 Days In Sample 245 Size Of Program Level Inventory 20 Business Feature Cycle Time Days 64 %!" ,-./-0123" Business Feature Flow Rate Days 7 S12M",0/D"42/5MK1N-" Inventory Released Downstream Per Business Feature 25 456/78-/"98:;"</./7"4=68-/66">?@/AB./6" Number of Teams Downstream 5 C12D"E2A;80/A0=257"F/68:-" Downstream Cycle Time Days 7 $#" G/H=82/D/-06"I1;/681-" Downstream Flow Rate 0.75 Initial Product Increment 07-Jul-10 G/617./">2:5-865B1-57"F/J/-K/-A8/6" Final Product Increment 13-Nov-10 L0123"42/5MK1N-"O"P25A/5?87803" Program Cycle Time 197 $!" Weekly Expenditure £250,000 Q6BD50/"R18-06" Monthly Client Subscription Cost £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onday, 11 October 2010
  • 45. Baseline Model : Week 0 Inventory Production 3 2 1 6 5 4 9 8 7 12 11 10 Program Leadership Kanban 15 14 13 18 17 16 20 19 Expense Client Cost Performance Schedule Monday, 11 October 2010
  • 46. Baseline Model : Week 1 Inventory Production 3 2 6 5 4 9 8 7 12 11 10 Program Leadership Kanban 15 14 13 18 17 16 20 19 1 Expense Client Cost Performance Schedule Monday, 11 October 2010
  • 47. Baseline Model : Week 2 Inventory Production 3 6 5 4 9 8 7 12 11 10 Program Leadership Kanban 15 14 13 18 17 16 20 19 2 1 Expense Client Cost Performance Schedule Monday, 11 October 2010
  • 48. Baseline Model : Week 3 Inventory Production 6 5 4 9 8 7 12 11 10 Program Leadership Kanban 15 14 13 18 17 16 20 19 3 2 1 Expense Client Cost Performance Schedule Monday, 11 October 2010
  • 49. Baseline Model : Week 4 Inventory Production 6 5 9 8 7 12 11 10 Program Leadership Kanban 15 14 13 18 17 16 20 19 4 3 2 1 Expense Client Cost Performance Schedule Monday, 11 October 2010
  • 50. Baseline Model : Week 5 Inventory Production 6 9 8 7 12 11 10 Program Leadership Kanban 15 14 13 18 17 16 20 19 5 4 3 2 1 Expense Client Cost Performance Schedule Monday, 11 October 2010
  • 51. Baseline Model : Week 6 Inventory Production 9 8 7 12 11 10 Program Leadership Kanban 15 14 13 18 17 16 20 19 6 5 4 3 2 1 Expense Client Cost Performance Schedule Monday, 11 October 2010
  • 52. Baseline Model : Week 7 Inventory Production 9 8 12 11 10 Program Leadership Kanban 15 14 13 18 17 16 20 19 7 6 5 4 3 2 1 Expense Client Cost Performance Schedule Monday, 11 October 2010
  • 53. Baseline Model : Week 8 Inventory Production 9 12 11 10 Program Leadership Kanban 15 14 13 18 17 16 20 19 8 7 6 5 4 3 2 1 Expense Client Cost Performance Schedule Monday, 11 October 2010
  • 54. Baseline Model : Week 9 Inventory Production 12 11 10 Program Leadership Kanban 15 14 13 18 17 16 20 19 9 8 7 6 5 4 3 2 1 Expense Client Cost Performance Schedule Monday, 11 October 2010
  • 55. Baseline Model : Week 10 Inventory Production 1 12 11 Program Leadership Kanban 15 14 13 18 17 16 20 19 10 9 8 7 6 5 4 3 2 Expense Client Cost Performance Schedule Monday, 11 October 2010
  • 56. Baseline Model : Week 11 Inventory Production 1 2 12 Program Leadership Kanban 15 14 13 18 17 16 20 19 11 10 9 8 7 6 5 4 3 Expense Client Cost Performance Schedule Monday, 11 October 2010
  • 57. Baseline Model : Week 12 Inventory Production 1 2 3 Program Leadership Kanban 15 14 13 18 17 16 20 19 12 11 10 9 8 7 6 5 4 Expense Client Cost Performance Schedule Monday, 11 October 2010
  • 58. Baseline Model : Week 13 Inventory Production 1 2 3 4 Program Leadership Kanban 15 14 18 17 16 20 19 13 12 11 10 9 8 7 6 5 Expense Client Cost Performance Schedule Monday, 11 October 2010
  • 59. Baseline Model : Week 14 Inventory Production 1 2 3 4 5 Program Leadership Kanban 15 18 17 16 20 19 14 13 12 11 10 9 8 7 6 Expense Client Cost Performance Schedule Monday, 11 October 2010
  • 60. Baseline Model : Week 15 Inventory Production 1 2 3 4 5 6 Program Leadership Kanban 18 17 16 20 19 15 14 13 12 11 10 9 8 7 Expense Client Cost Performance Schedule Monday, 11 October 2010
  • 61. Baseline Model : Week 16 Inventory Production 1 2 3 4 5 6 7 Program Leadership Kanban 18 17 20 19 16 15 14 13 12 11 10 9 8 Expense Client Cost Performance Schedule Monday, 11 October 2010
  • 62. Baseline Model : Week 17 Inventory Production 1 2 3 4 5 6 7 8 Program Leadership Kanban 18 20 19 17 16 15 14 13 12 11 10 9 Expense Client Cost Performance Schedule Monday, 11 October 2010
  • 63. Baseline Model : Week 18 Inventory Production 1 2 3 4 5 6 7 8 9 Program Leadership Kanban 20 19 18 17 16 15 14 13 12 11 10 Expense Client Cost Performance Schedule Monday, 11 October 2010
  • 64. Baseline Model : Week 19 Inventory Production 1 2 3 4 5 6 7 8 9 10 Program Leadership Kanban 20 18 18 17 16 15 14 13 12 11 Expense Client Cost Performance Schedule Monday, 11 October 2010
  • 65. Baseline Model : Week 20 Inventory Production 1 2 3 4 5 6 7 8 9 10 11 Program Leadership Kanban 20 19 18 17 16 15 14 13 12 Expense Client Cost Performance Schedule Monday, 11 October 2010
  • 66. Baseline Model : Week 21 Inventory Production 1 2 3 4 5 6 7 8 9 10 11 12 Program Leadership Kanban 20 19 18 17 16 15 14 13 Expense Client Cost Performance Schedule Monday, 11 October 2010
  • 67. Baseline Model : Week 22 Inventory Production 1 2 3 4 5 6 7 8 9 10 11 12 Program Leadership Kanban 13 20 19 18 17 16 15 14 Expense Client Cost Performance Schedule Monday, 11 October 2010
  • 68. Baseline Model : Week 23 Inventory Production 1 2 3 4 5 6 7 8 9 10 11 12 Program Leadership Kanban 13 14 20 19 18 17 16 15 Expense Client Cost Performance Schedule Monday, 11 October 2010
  • 69. Baseline Model : Week 24 Inventory Production 1 2 3 4 5 6 7 8 9 10 11 12 Program Leadership Kanban 13 14 15 20 19 18 17 16 Expense Client Cost Performance Schedule Monday, 11 October 2010
  • 70. Baseline Model : Week 25 Inventory Production 1 2 3 4 5 6 7 8 9 10 11 12 Program Leadership Kanban 13 14 15 16 20 19 18 17 Expense Client Cost Performance Schedule Monday, 11 October 2010
  • 71. Baseline Model : Week 26 Inventory Production 1 2 3 4 5 6 7 8 9 10 11 12 Program Leadership Kanban 13 14 15 16 17 20 19 18 Expense Client Cost Performance Schedule Monday, 11 October 2010
  • 72. Baseline Model : Week 27 Inventory Production 1 2 3 4 5 6 7 8 9 10 11 12 Program Leadership Kanban 13 14 15 16 17 18 20 19 Expense Client Cost Performance Schedule Monday, 11 October 2010
  • 73. Baseline Model : Week 28 Inventory Production 1 2 3 4 5 6 7 8 9 10 11 12 Program Leadership Kanban 13 14 15 16 17 18 20 19 Expense Client Cost Performance Schedule Monday, 11 October 2010
  • 74. Baseline Model : Week 29 Inventory Production 1 2 3 4 5 6 7 8 9 10 11 12 Program Leadership Kanban 13 14 15 16 17 18 19 20 Expense Client Cost Performance Schedule Monday, 11 October 2010
  • 75. Baseline Model : Week 30 Inventory Production 1 2 3 4 5 6 7 8 9 10 11 12 Program Leadership Kanban 13 14 15 16 17 18 19 20 Expense Client Cost Performance Schedule Monday, 11 October 2010
  • 76. Baseline Model : Over Time Inventory Production 1 2 3 Backlog 4 5 6 7 8 9 10 11 12 Program Leadership Kanban 13 14 15 16 17 18 19 20 Expense Client Cost Performance Schedule Monday, 11 October 2010
  • 77. Baseline Model : Over Time Inventory Production 1 2 3 4 5 6 Done 7 8 9 10 11 12 Program Leadership Kanban 13 14 15 16 17 18 19 20 Expense Client Cost Performance Schedule Monday, 11 October 2010
  • 78. Baseline Model : Over Time Inventory Production 1 2 3 In Progress 4 5 6 In Progress 7 8 9 10 11 12 Program Leadership Kanban 13 14 15 16 17 18 19 20 Expense Client Cost Performance Schedule Monday, 11 October 2010
  • 81. Scenario • 15th Feb Iteration 53 • Tasked with resolving performance related technical debt • Tasked with resolving scalability related technical debt • Spent two iterations analysing system • Under pressure to produce user stories • Under pressure to provide reliable estimates for stories • Failing to deliver on iteration commitments • Level of uncertainty too high to provide consistent estimation • Migrating to Kanban to manage development and incremental improvement Monday, 11 October 2010
  • 94. Color coding of work Time & Date items ‘Record Triggers’ Separate bins for waste divided between time waste and Statistical process requirements waste Prioritized inventory of Filter for highest control charts requirements priority work ‘Fast-Lane’ for work with priority conditions of service Work In Progress limits Program level consistent practice Exit Criteria Ideas for process improvement Easy access to tools Photos of last kaizen that are outside teams and materials event whiteboard Entry Criteria immediate control Monday, 11 October 2010
  • 98. Silver Bullet Rob 1 ! ! ! Defect Functional DE1504 Launch Preditor US7306-1 Browser Bookmark Launch RELEASE Rob 2 Bookmarklet : Can cause JS error if clicked during page load Class of Service Expedite Class of Service Rob 3 Standard Number of Cycles Number of Cycles ! ! Impediment! ! ! ! ! Analysis Analysis Analysis Analysis Design De Start Date Named product Named product Documented Doc Start Date owner owner End Date End Date Named domain Named Reviewed Peer domain Pee Design Design experts experts Start Date Start Date Identify benefits Identify benefits Identify Iden End Date interfaces inte End Date (AMDD) (AM Awaiting Implementation Identify risks Identify risks Awaiting Implementation Identify Iden Start Date Start Date Components Com Identify test (AMDD) Identify test (AM End Date End Date Approach Approach Consider Con BLOCKED! Implementation Implementation Outline technical Alternatives Outline technical Alte Start Date Start Date approach approach List Non List Functional Fun End Date Agreed with Agreed with End Date users Considerations users Con Technical Tec Committed Committed Agreed with Spike? Agreed with Spik Start Date Start Date product owner! product owner! End Date End Date Peer Review! Peer Review! Is Packaged Is Packaged Start Date Start Date End Date End Date 1 Test Start Date Test Start Date DEFECT End Date Ready For Test Release Start Date End Date Ready For Test Release Start Date End Date End Date Release To Test Release To Test Start Date Start Date End Date End Date Ready For Live Release Ready For Live Release Start Date Start Date WIP End Date End Date THROTTLE Release To Live Start Date Release To Live Start Date End Date End Date Associated Tasks Associated Tasks Associated Tasks ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! Monday, 11 October 2010 ! ! !