1. WEEKLY PROGRESS REPORT (week 8)
PERIOD 31th Oct – 06th Nov, 2022
• PROYEK PEMBANGUNAN
INFRASTRUKTUR KUSAN BARU
2. Content
1. Issue Register
2. Man Hour
3. HSE performance
4. Procurement Status
5. Progress
6. Site Activity & Photos
7. Varian Order/ Add Work
3. No Minutes Date Raised ActionBy Due date Status
1 Pengajuan Comm sarana triton 04 Okt 2022 GGL 08 Oktober 2022 Closed
2 Pengajuan mine permit 04 Okt 2022 GGL 08 Oktober 2022 Closed
3 Ditambahkan Due date shop
drawing
04 Okt 2022 GGL 05 Okt 2022 Closed
4 Submit hit analisa strutur WS
servis
11 Okt 2022 GGL Closed
5 Submit Drawing struktur WS
servis
11 Okt 2022 GGL Closed
6. Lahan Rumah Genset ada
perubahan koordinat
17 Okt 2022 SIS Open
7. Lahan Washing perlu material
keras
17 Okt 2022 SIS Closed
4. 11/8/2022
Progress MCU
MCU 26
Follow up 0
Unfit 0
Review 2
FIT to WORK 24
Sudah FIT to WORK
Sdh Induksi 26
Blm Induksi 0
Status Permit Active
Standby 0
waskat 4
Mine permit 22
Total MP 26
0 0 2
24
Follow up Unfit Review FIT to WORK
MCU Progress Manpower
0
4
22
Standby waskat Mine permit
Status Permit Active
Man Hours
Name Jabatan Last Week these week total
Staff 742 224 966
Tukang 1281 343 2779
3745
5. INCIDENT CATEGORY LAST WEEK THESE WEEK TOTAL CASES
Fatality
Sub-contractor
Lost Time Injury (LTI)
Restricted Work Injury (RWI)
Medical Treatment Injury (MTI)
First Aid Injury (FAI)
Properti Damaged Incident (PDI)
Envronmental Incident (EI)
Nea Miss (NM)
TOTAL - - - -
8. MANPOWER DETAILS
15-18 19-25 26-30 01-09 10-16 17-23 24-30 31-06
W1 W2 W3 W4 W5 W6 W7 W8
Indirect
1 Site Manager/PJO 1 Orang plan 1 1 1 1 1 1 1 1
1 Orang actual 1 1 1 1 1 1
2 Project Control 1 Orang plan 1 1 1 1
actual
3 Safety Officer 1 Orang plan 1 1 1 1 1 1 1 1
1 Orang actual 1 1 1 1 1 1 1 1
4 Safety Man 1 Orang plan 1 1 1 1
actual
5 Civil Supervisor 2 Orang plan 1 1 1 1
actual 1
6 Steel Structure Supervisor 1 Orang plan
actual
7 Mech & Elect Plumbing Supervisor 1 Orang plan
actual
8 Surveyor 1 Orang plan 1 1 1 1 1
actual 2 2
9 Logistik 1 Orang plan 1 1 1 1
actual 1
10 Mechanic 1 Orang plan 1 1 1 1
actual
Jumlah Indirect 11 Orang 2 Orang 2 2 2 3 8 8 8 8
Direct MP
1 Pekerja Sipil
Foreman 4 Orang plan 1 1 1 1 1
1 Orang actual 1 1 1 1 1 1 1
Tukang kayu/besi 20 Orang plan 8 10 10 10 10
6 Orang actual 6 6 6 6 6 6 6
Tukan batu 50 Orang plan 10 10 10
actual 5 5 5 5
Helper 20 Orang plan 5 5 10 10 10
actual 5 5 5 5
4 Driver/Operator 2 Orang 1 plan 1 1 1 2 2
actual 1 2 2 2 2
Jumlah Direct 144 Orang 8 Orang Orang - - - 15 17 32 33 33
Plan 155 Orang 2 2 2 18 25 40 41 41
Actual 9 Orang 1 9 9 10 21 21 23 24
Deviation (1) 7 7 (8) (4) (19) (18) (17)
REMARK
PLANNED
No. POSITION
Schedule
ONSITE
(STANDBY)
ONISTE
(WORK)
QUANTITIES
SEPTEMBER 2022 OKTOBER 2022 NOVEMBER 2022 REMARK
1 2 3
9. EQUIPMENT DETAILS
15-18 19-25 26-30 01-09 10-16 17-23 24-30 31-06 07-13 14-20 21-27
W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11
A Heavy Equipment
A.1 Excavator (by SIS) 1 Unit Plan 1 1 1 1
Actual
A.2 Greader Unit Plan
Actual
A.3 Vibro Roller Unit Plan
Actual
A.4 Crane (by SIS) Unit Plan 1 1 1
Actual
A.5 Sarana Elf 1 Unit Plan 1 1 1 1 1 1 1
Actual 1 1 1 1 1 1
A.6 Sarana Triton 2 Unit Plan 1 1 2 2 2 2 2
Actual 1 1 1 1 1
B Civil Tools
B.1 Bar cutter (gunting besi) 4 Unit Plan 1 1 1 2 2 4 4
Actual 1 1
B.2 Bar bending (bending manual) 4 Unit Plan 1 1 1 1 2 4 4
Actual 1 1
B.3 Pompa air celup 3" 3 Unit Plan 1 1 1 1 2 2 2
Actual 1 1
B.3 Stamper 4 Unit Plan 1 1 1 1 2 4 4
Actual 1 1
B.4 Concrete vibrator 4 Unit Plan 1 1 1 1 2 4 4
Actual 1 1
B.5 Mesin gerinda portable 4 Unit Plan 1 1 1 1 4 4 4
Actual 1 1
B.6 Mesin potong keramik 4 Unit Plan 1 1 1 1 4 4 4
Actual
B.7 Mesin bor portable 4 Unit Plan 1 1 1 1 4 4 4
Actual
B.10 Pesawat theodolite complit tripot Unit Plan 1 1 1 1 1 1 1
Actual 1 1
B.11 Pesawat waterpass complit tripot Unit Plan 1 1 1 1 1 1 1
Actual 1 1
B.8 Mesin molen cap / electric start 4 Unit Plan 1 1 2 2 3 3 3
1 1
B.9 Panel Listrik 2 unit Plan 1 1 1 1 1 2 2 2
Actual 1 1 1 1 1
C Steel Tools
D Mechanical dan Electrical Tools
E Perancah
No Jabatan
Schedule
REMARK
PLANNED
ONSITE
(STAND
BY)
ONISTE
(WORK)
1
QUANTITIES
SEPTEMBER 2022 OKTOBER 2022 NOVEMBER 2022
2 3
10. MATERIAL NAME PURPOSE DELIVERY QUANTITIES REMARKS
Pancang Ws servis 60 batang
Besi Beton dadn wiremesh TPS B3 5,5 ton
11. 20.19 %
21.03 %
0.84 %
progress (%) progress (%) progress (%)
PERSIAPAN
1 Pengurusan HIRA - JSA 1 ls 0.58 100.00% 0.58 - 100.00% 0.58 0.58 - 0.58
-
2 Pengukuran dan Bouwplank 1.00 ls 2.50 36.36% 0.91 9.09% 0.23 45.45% 1.14 1.14 - 1.36
-
3 Direksi Keet, Kantor Lapangan, Barak kerja dan Gudang 1.00 ls 2.73 105.00% 2.86 25.00% 0.68 130.00% 3.55 2.73 0.82 2.73
-
4 Penyediaan listrik kerja ( power by owner ) 1.00 ls 0.58 45.45% 0.26 18.18% 0.11 63.64% 0.37 0.32 0.05 0.37
-
5 Penyediaan air Kerja ( suplly by owner )+Alat penampungan dari DSS 1.00 ls 0.47 13.79% 0.06 3.45% 0.02 17.24% 0.08 0.08 - 0.10
-
6 Laporan & photo proyek 1.00 ls 0.14 24.14% 0.03 3.45% 0.00 27.59% 0.04 0.04 - 0.04
-
7 Papan nama Proyek 1.00 ls 0.03 100.00% 0.03 0.00% - 100.00% 0.03 0.03 - 0.03
-
8 K-3 / Safety / MCU/PROKES COVID 19 1.00 ls 10.96 13.79% 1.51 3.45% 0.38 17.24% 1.89 1.89 - 2.27
-
9 Mobilisasi dan Demobilisasi 1.00 ls 28.95 13.79% 3.99 3.45% 1.00 17.24% 4.99 4.99 - 5.99
-
10 Fee design 1.00 ls 2.06 45.00% 0.92 6.67% 0.14 51.67% 1.06 1.10 (0.03) 1.23
11 Biaya Security & CSR -
a. 8.00 Bln 0.60 13.79% 0.08 3.45% 0.02 17.24% 0.10 0.10 - 0.12
-
12 Site Management 1.00 Bln 50.42 10.71% 5.40 3.57% 1.80 14.29% 7.20 7.20 - 9.00
100.00
- 20.19 23.83
16.66 4.37 21.03
0.84
NO Description Unit Quantity
Value
(%)
Plan
Actual
Deviation
PROGESS RENCANA
plan
PROGRESS
KET
DEVIASI
Plan Next
period
(week 8)
Deviation
PROGESS RENCANA KOMULATIF
PROGESS AKTUAL
PROGESS AKTUAL KOMULATIF
Last Period This Period Cumulative
21. PROSES REVIEW REVISI APPROVED
SUBMIT RECEIVED SUBMIT RECEIVED SUBMIT RECEIVED SUBMIT RECEIVED SUBMIT RECEIVED
1 WORKSHOP SERVICE 1 DRAWING ARSITEKTUR 10/20/2022 REVIEW 02-Nov-22
2 DRAWING STRUKTUR 10/20/2022 REVIEW 12-Oct-22
2.1 DRAWING STRUKTUR BAJA 9/24/2022 9/30/2022 10/18/2022 REVIEW 19-Oct-22
3 DRAWING MECHANICAL & PLUMBING PROSES 22-Dec-22
4 DRAWING ELECTRICAL PROSES 22-Dec-22
2 TPS B3
1 DRAWING ARSITEKTUR 9/12/2022 9/21/2022 9/26/2022 9/30/2022 10/6/2022 10/13/2022 10/19/2022 10/20/2022 REVIEW 16-Nov-22
2 DRAWING STRUKTUR 9/12/2022 9/21/2022 9/26/2022 9/30/2022 10/6/2022 10/13/2022 10/19/2022 10/20/2022 REVIEW 12-Oct-22
2.1 DRAWING STRUKTUR BAJA 10/6/2022 10/13/2022 10/20/2022 REVIEW 16-Nov-22
3 DRAWING ELECTRICAL PROSES 07-Dec-22
4 DRAWING MECHANICAL & PLUMBING PROSES 07-Dec-22
3 WASHING BAYS
1 DRAWING ARSITEKTUR PROSES 02-Nov-22
2 DRAWING STRUKTUR 9/5/2022 10/12/2022 10/28/2022 REVIEW 12-Oct-22
3 DRAWING ELECTRICAL PROSES 02-Nov-22
4 DRAWING MECHANICAL & PLUMBING PROSES 02-Nov-22
4 RUMAH GENSET
1 DRAWING ARSITEKTUR 10/8/2022 9/30/2022 10/7/2022 10/17/2022 10/20/2022 REVIEW 09-Nov-22
2 DRAWING STRUKTUR 10/8/2022 9/30/2022 10/7/2022 10/17/2022 10/20/2022 REVIEW 12-Oct-22
2.1 DRAWING STRUKTUR BAJA 10/6/2022 10/17/2022 10/21/2022 REVIEW
3 DRAWING ELECTRICAL PROSES 09-Nov-22
4 DRAWING MECHANICAL & PLUMBING PROSES 09-Nov-22
REMARKS
NAMA GAMBAR R4
No. NAMA BANGUNAN STATUS
SUBMIT
PLAN BY
GGL
SUBMIT
R0 R1 R2 R3
DRAWING APPROVAL
SIS JOBSITE BORO
Sumbitted by : PT. Gelar Gatra Laras
Project : MIA KUSAN
22. SUBMIT RECEIVED
Review Approved Review Approved Review Approved Review Approved Review Approved Review Approved Review Approved Review Approved Review Approved Review Approved Review Approved
1 001/GGL-STR-SIS/VII/2022 MATERIAL APPROVAL BESI BETON & WIREMESH 9/9/2022 9/14/2022 APPROVED - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1
2 002/GGL-STR-SIS/VII/2022 MATERIAL APPROVAL BAJA 10/5/2022 10/17/2022 APPROVED - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1
3 003/GGL-STR-SIS/VII/2022 MATERIAL APPROVAL CAT BAJA 9/9/2022 9/14/2022 APPROVED - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1
4 004/GGL-STR-SIS/VII/2022 MATERIAL APPROVAL CAT DEMARKASI 9/18/2022 9/19/2022 APPROVED - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1
5 005/GGL-STR-SIS/VII/2022 MATERIAL APPROVAL ATAP ZINCALUME & WALL CLADING 9/9/2022 9/14/2022 APPROVED - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1
6 006/GGL-STR-SIS/VII/2022 MATERIAL APPROVAL RANGKA ATAP 9/9/2022 9/14/2022 APPROVED - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1
7 007/GGL-STR-SIS/VII/2022 MATERIAL APPROVAL INSULATION ATAP 10/5/2022 REVIEW x x x x 1 - x x x x x x 1 - x x x x 1 - 1 -
8 008/GGL-STR-SIS/VII/2022 MATERIAL APPROVAL TALANG DATAR 9/9/2022 9/14/2022 APPROVED - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1
9 009/GGL-STR-SIS/VII/2022 MATERIAL APPROVAL PLAFOND GYPSUM, PLAFON GRC, RANGKA HOLLOW ZINCALUM 9/9/2022 9/14/2022 APPROVED x x x x x x x x x x x x - 1 x x x x x x - 1
10 010/GGL-STR-SIS/VII/2022 MATERIAL APPROVAL CAT PLAFOND, CAT INTERIOR & EXTERIOR 9/24/2022 9/27/2022 APPROVED x x x x - 1 - 1 x x x x - 1 - 1 - 1 - 1 - 1
11 011/GGL-STR-SIS/VII/2022 MATERIAL APPROVAL KUSEN PINTU, JENDELA & DAUN JENDELA 9/18/2022 9/19/2022 APPROVED x x x x x x x x x x x x - 1 x x x x - 1 - 1
12 012/GGL-STR-SIS/VII/2022 MATERIAL APPROVAL KERAMIK 9/28/2022 10/5/2022 APPROVED x x x x x x x x x x x x x x x x x x - 1 - 1
13 013/GGL-STR-SIS/VII/2022 MATERIAL APPROVAL PAGAR BRC 9/24/2022 9/27/2022 APPROVED x x x x - 1 x x x x x x x x x x x x x x -
14 014/GGL-STR-SIS/VII/2022 MATERIAL APPROVAL SANITARY 9/18/2022 9/19/2022 APPROVED x x x x x x x x x x x x x x x x x x - 1 - 1
15 015/GGL-MEP-SIS/VII/2022 MATERIAL APPROVAL LAMPU 10/5/2022 10/11/2022 APPROVED - 1 x x x x - 1 - 1 - 1 - 1 x x x x x x -
16 016/GGL-MEP-SIS/VII/2022 MATERIAL APPROVAL KABEL 9/18/2022 9/10/2022 APPROVED - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1
17 017/GGL-MEP-SIS/VII/2022 MATERIAL APPROVAL PANEL
18 018/GGL-MEP-SIS/VII/2022 MATERIAL APPROVAL PIPA PVC 9/24/2022 10/3/2022 APPROVED x x x x x x x x x x x x - 1 x x x x - 1 - 1
19 019/GGL-MEP-SIS/VII/2022 MATERIAL APPROVAL BOOSTER PUMP 9/18/2022 10/3/2022 APPROVED - 1 x x x x x x - 1 - 1 x x x x x x x x -
20 020/GGL-MEP-SIS/VII/2022 MATERIAL APPROVAL KOMPRESSOR (GIP MED) 9/18/2022 10/11/2022 APPROVED - 1 x x x x x x - 1 - 1 x x x x x x x x -
21 021/GGL-MEP-SIS/VII/2022 MATERIAL APPROVAL BALL VALVE 10/7/2022 10/11/2022 APPROVED - 1 x x x x x x - 1 - 1 x x x x x x x x -
22 022/GGL-MEP-SIS/VII/2022 MATERIAL APPROVAL CABLE LADDER 9/24/2022 10/3/2022 APPROVED - 1 x x x x x x - 1 1 - 1 x x x x 1 -
23 023/GGL-MEP-SIS/VII/2022 MATERIAL APPROVAL PIPA OLI 10/5/2022 REVISI 1 - x x x x x x 1 - 1 - x x x x x x x x -
24 024/GGL-MEP-SIS/VII/2022 MATERIAL APPROVAL GATE VALVE 10/7/2022 10/11/2022 APPROVED x x x x - 1 x x x x x x x x x x x x x x -
25 025/GGL-MEP-SIS/VII/2022 MATERIAL APPROVAL PENANGKAL PETIR 10/5/2022 10/11/2022 APPROVED - 1 x x - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1
26 026/GGL-MEP-SIS/VII/2022 MATERIAL APPROVAL TATA UDARA AC 9/24/2022 10/3/2022 APPROVED x x x x x x x x x x x x x x x x x x - 1 - 1
27 027/GGL-MEP-SIS/VII/2022 MATERIAL APPROVAL STOP KONTAK 10/6/2022 10/11/2022 APPROVED - 1 x x - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1 - 1
28 028/GGL-MEP-SIS/VII/2022 MATERIAL APPROVAL WATER TANK 10/6/2022 10/11/2022 APPROVED x x x x x x x x x x x x - 1 x x x x - 1 - 1
29 029/GGL-MEP-SIS/VII/2022 MATERIAL APPROVAL SEPTIC TANK 10/5/2022 10/11/2022 APPROVED x x x x x x x x x x x x - 1 x x x x - 1 - 1
30 030/GGL-MEP-SIS/VII/2022 MATERIAL APPROVAL PANEL SENDWITCH 10/6/2022 10/17/2022 APPROVED x x x x x x x x x x x x - 1 x x x x - 1 - 1
31 031/GGL-STR-SIS/X/2022 MATERIAL APPROVAL TIANG PANCANG 10/21/2022 10/25/2022 APPROVED - 1 x x x x x x x x x x x x x x x x x x x x
1 16 0 8 1 13 0 12 1 15 1 15 1 19 0 11 0 11 1 20 1 20
5.9% 94.1% 0.0% 100.0% 7.1% 92.9% 0.0% 100.0% 6.3% 93.8% 6.3% 93.8% 5.0% 95.0% 0.0% 100.0% 0.0% 100.0% 4.8% 95.2% 4.8% 95.2%
GUDANG
OLI
MAIN
OFFICE
MASJID
TPS
B3
WORKSHOP
TYRE
WORKSHOP
FABRIKASI
WARE
HOUSE
GUDANG
KOMP
FORM UPDATE MATERIAL APPROVAL
PROYEK PEKERJAAN WORKSHOP MODULAR
SIS BORO KUSAN ATAS-KALIMANTAN SELATAN
SUBMIT
R0
No. Nomor Dokumen Nama Dokumen STATUS
WS
SERVICE
WASHING
BAY
RUMAH
GENSET
23. Fabrikasi begesting
TPS B3
Pek Galian pondasi PC1 Mapping pek pancang
Pek pelurusan besi D19 Pek Pancang as B Fabrikasi besi PC 1