Project_Plan-Datalake_v1.0_26-10-2022.pptx
1. DB
Migration to
AWS
Data lake
PROJECT TIMELINE
Sep 16 Sep 23 Sep 30 Oct 7 Oct 14 Oct 21 Oct 28 Nov 4 Nov 11 Nov 18 Nov 25 Dec 2
Dec
9
Dec
16
Dec
23
Dec
30
Completed
In Progress
Leaves
New Joiner
Milestones/Deliverabl
es
To be started
DB Migration
• Finance DB
• ArchiveDB
• Marketing DB
DB Migration
• Dailer
• Faq Service
• Rewards
• Collection
DB Migration
• Collections-
external
• finance_logs
DB Migration
• smartcredit-
roach2
• Smartcredit
1. DB Migration
• Analytics DB
• Auth
Left over table migration in all the DB’s with issues
Timescale DB optimization
Tuning
Performance Improvement
DB Migration
• mpokketlive
• mpokket
• mpokket – common
• Marketing
Dataease contract
renewal
CE report migration
• 15 report migration to Athena
• Report Validation
• Scheduling over jenkins
CE report go live for 15
reports
2. Data
Modeling
Aggregate
generation
and
Analytics
and CE
Report
Storage
Saving
Performance
optimization
PROJECT TIMELINE
Nov 15 Nov 30 Dec 15 Dec 30 Jan 15 Jan 30 Feb 15 Feb 28 Mar 15 Mar 30
Completed
In Progress
Leaves
New Joiner
Milestones/Deliverabl
es
To be started
• Base data model
• Master Creation
• Source system study
• Future scope
Identification
of reports
which can be
delivered via
EMR
Dataease contract
renewal
• Aggregate development
• Testing
• Deployment in production
Batch 1 of 15 CE reports
• Development
• Testing
Batch 1
• Productio
n go live
Batch 2 of 15 CE reports
• Development
• Testing
Batch 1
• Productio
n go live
Batch 3 of 15 CE reports
• Development
• Testing
Batch 1
• Productio
n go live