SlideShare a Scribd company logo
1 of 27
2012
WES Biosolids Program GPS & GIS Implementation




                                 Susan Ottersen

                                 GIS Analyst/Engineer Tech III

                                 Water Environment Services

                                 Clackamas County

                                 4/16/2012
                                                      1|Page
  2012 URISA AWARD APPLICATION
A: System -------------------------------------------------------------------------------------------------------------- 4
   1. Name of the System and ESIG™ Award Categories: ---------------------------------------------------------- 4
   2. Executive administrator letter: ------------------------------------------------------------------------------------- 4
   3. Summary: ---------------------------------------------------------------------------------------------------------------- 4
   4. Three user testimonials: --------------------------------------------------------------------------------------------- 5

B: Jurisdiction--------------------------------------------------------------------------------------------------------- 5
   1. Name of jurisdiction: -------------------------------------------------------------------------------------------------- 5
   2. Population served by the organization:-------------------------------------------------------------------------- 5
   3. Annual total budget for jurisdiction: ----------------------------------------------------------------------------- 5
   4. Chief elected official: -------------------------------------------------------------------------------------------------- 5
   5. System Contact: -------------------------------------------------------------------------------------------------------- 5

C: System Design ---------------------------------------------------------------------------------------------------- 6
   1. What motivated the system development? -------------------------------------------------------------------- 6
   2. What specific service or services was the system intended to improve? ------------------------------- 6
   3. What, if any, unexpected benefits did you achieve? --------------------------------------------------------- 7
   4. What system design problems were encountered? ---------------------------------------------------------- 7
   5. What differentiates this system from other similar systems? -------------------------------------------- 10

D: Implementation ------------------------------------------------------------------------------------------------ 11
   1. What phases did you go through in developing the system? --------------------------------------------- 11
   2. Were there any modifications to the original system design? Why? What? ------------------------ 11

E: Organizational Impact ---------------------------------------------------------------------------------------- 12
   1. What user community does the system serve and how? -------------------------------------------------- 12
   2. What are the ultimate decisions/operations/services being affected? If appropriate,
      provide a few examples including, but not limited to: screen input/output forms, paper
      products, or other descriptive graphics ------------------------------------------------------------------------ 12
   3. What were the quantitative and qualitative impacts of the system? ---------------------------------- 14
   4. What effect has the system had on productivity? ----------------------------------------------------------- 15
   5. What, if any, other impacts has the system had? ------------------------------------------------------------ 16
   6. How did the system change the way business is conducted with and/or service delivered
      to clients? Give specific examples comparing the old way with the new ---------------------------- 16


                                                                                                                    2|Page
2012 URISA AWARD APPLICATION
F: System Resources ---------------------------------------------------------------------------------------------- 16
   1. What are the system’s primary hardware components? Give a brief list or description of
      the hardware configuration supporting the system . ------------------------------------------------------ 16
   2. What are the system’s primary software components? Describe the primary software and,
      if a commercial package, any customizations required for the system. ------------------------------ 16
   3. What data does the system work with? List and briefly describe the database(s) ----------------- 17
   4. What staff resources were required to implement the system? (approximate staff and
      consultant time as FTE’s) ------------------------------------------------------------------------------------------- 17
   5. Comment on anything unusual about the resources used to develop your system, such as
       data, software, personnel and financing. --------------------------------------------------------------------- 17

APPENDIX A: -------------------------------------------------------------------------------------------------------- 18
APPENDIX B: -------------------------------------------------------------------------------------------------------- 20
APPENDIX C: -------------------------------------------------------------------------------------------------------- 24




                                                                                                                3|Page
2012 URISA AWARD APPLICATION
Application for 2011 URISA ESIG™
A: System

    1. Name of the System and ESIG™ Award Categories:

Single Process System

    2. Executive administrator letter:

See Appendix A.

    3. Summary:

Water Environment Services (WES) began its Biosolids program in the 1980’s. Then, environmental
requirements were more lenient and record maintenance sporadic where now greater attention to
environment safety has produced stricter standards from the program’s regulator, Oregon’s Department
of Environmental Quality (DEQ). In 2009, an internal assessment revealed that WES was not meeting
the regulator’s record keeping and soil testing standards and, from a management perspective, was not
managing program risk associated with land application of liquid biosolids. Compelled by the risk of
scraping the Liquid Biosolids Program altogether unless practices were brought into compliance and risk
managed, WES took steps to ensure compliance and mitigate program risk. WES achieved that due, in
part, to this GPS/GIS project, which provided for greater internal controls that enhanced field
management and narrowed the variance associated with spraying onto fields and for stakeholders,
strengthened customer service and documentation for the farming community, neighbors, and
regulators.

Biosolids spreading is not a precise application and, as discovered with WES’ internal audit / assessment,
can generate land-application risk. DEQ has strict guidelines for application of Biosolids to agricultural
land with specific distances from buildings, water supply wells or springs, streams, ditches, roads, and
other features. Given those regulatory guidelines, WES faced several issues:
        Lacking in WES’ liquid Biosolids program was a method to track all land-application updates at
        the farms that were receiving the liquid Biosolids on their fields.
        Needed was a system that recorded precisely where biosolids were applied and, more
        importantly, identified the location of land-sensitive buffered zones and if buffer violations
        occurred during application.
The only system that made sense as a solution which identified and tracked data was implementing a
GPS system with mapping in ArcGIS.

The GPS/GIS project used Trimble GPS technology (handheld devices for field mapping and dashboard
devices for truck drivers) and ArcGIS mapping software to manage all steps associated with the
application of liquid biosolids onto agricultural fields. Included was the education of staff who mapped
the fields using the Trimble 2008 GeoXt handheld unit equipped with TerraSync software and the
Biosolids drivers, responsible for liquid land application, who used the EZ Guide 500 dashboard truck
device.




                                                                                               4|Page
2012 URISA AWARD APPLICATION
Lack of field staff buy-in and active participation would have rendered this project a failure. Staff that
mapped the agricultural fields with the handheld devices and drove the land-application trucks with the
dashboard truck device were the end users of this technology and identified the obstacles in using this
GPS/GIS application.


    4. Three user testimonials:


See Appendix B.


B: Jurisdiction


    1. Name of jurisdiction:

Clackamas County Service District No. 1, Water Environment Services of Clackamas County (WES)

    2. Population served by the organization:

Clackamas County Water Environment Services (WES) manages sanitary sewer and surface water
services for over 150,000 people in two special districts located within Clackamas County and operates
seven wastewater treatment facilities; three of these facilities produce biosolids. Facilities that produce
liquid biosolids are located in Clackamas County Service District No. 1: Kellogg Wastewater Treatment
Plant and Hoodland Treatment Plant.

Clackamas County Service District No. 1 provides retail sanitary sewer and surface water management
services to unincorporated portions of North Clackamas County as well as the City of Happy Valley,
Damascus, Boring, the communities of the Hoodland corridor, Fischer’s Forest Park near Redland, and
wholesale wastewater treatment services to the cities of Milwaukie and Johnson City. These services are
largely funded by revenues derived from rates and fees for development.

    3. Annual total budget for jurisdiction:

Clackamas County Service District No. 1: Proposed FY2012-13 Operating Budget of $27,232,000 and
Capital Budget of $11,361,000.

    4. Chief elected official:

Mike Kuenzi, Director
150 Beavercreek Road
Oregon City, Oregon 97045

    5. System Contact:

 Susan Ottersen, GIS Analyst/Engineer Tech III
 150 Beavercreek Road

                                                                                                5|Page
2012 URISA AWARD APPLICATION
Oregon City, Oregon 97045
 Phone: 503-742-4613
 Fax: 503-742-4565
 susanott@co.clackamas.or.us


C: System Design

    1. What motivated the system development?

Water Environment Services operates a liquid biosolids program out of the Kellogg Creek (KC)
Wastewater Treatment Plant and the Hoodland (HD) Sewage Treatment Plant. WES’ liquid program is
the largest liquid biosolids land application program in the state of Oregon. WES generates 13,000,000
gallons of liquid biosolids annually serving over 100 different fields. WES also manages a cake biosolids
program out of the Tri-City (TC) Wastewater Treatment Plant. Both KC and TC require biosolids to be
removed daily from the plant do to capacity issues, which has been occurring since the 1980’s. With the
increased DEQ requirements, it compelled WES to implement a more accurate and stringent monitoring
program.

The land application of liquid biosolids is particularly challenging. The liquid land application program
serves farmers within 15 miles of the KC plant. This area is mostly zoned residential/rural, where the
agricultural land application sites are adjacent to homes, schools, roads, and other denser populated
areas. It is a patchwork quilt of fields in an ever expanding populated area that provides little room for
error. For example, the largest field is a mere 33 acres. In contrast, our cake program in Eastern Oregon
serves farmers with areas in the 200 – 500 acre ranges.

The land application of biosolids in Oregon is regulated by the Oregon Department of Environmental
Quality (DEQ) which authorizes all sites for biosolids application. Every site must be authorized by DEQ
and each site has unique requirements based on its location.

After an internal audit / assessment in 2009, it was clear that there were opportunities to improve our
compliance with DEQ rules and our relationship with neighbors adjacent to land application sites. Key
findings included:

        Application on unauthorized land
        Over application of biosolids on some fields resulting in elevated Nitrates in the soil
        Subjective boundaries around sensitive features resulting in repeated buffer violations
        Soil samples not taken or sampling sites not recorded
        Daily spreading records not being maintained
        Interruption of field application because of rain, equipment problems, staffing, etc. There was
        no clear record of where spreading had stopped.

    2. What specific service or services was the system intended to improve?



                                                                                               6|Page
2012 URISA AWARD APPLICATION
WES provides a service of delivery and land application of liquid biosolids to privately owned agricultural
land. The land owner in the past was defined as our customer; now the adjacent neighbors and
community at large are included in this definition of customer. Our service extends to them by assuring
protection of their wells, surface water and minimizing odors.

The ability to continue this service is dependent on maintaining compliance and gaining reasonable
acceptance in the community. The use of GPS/GIS guided land application has allowed us to achieve
both.

    3. What, if any, unexpected benefits did you achieve?

A. Better customer service, less customer complaints and educational opportunities. This required on
   the ground mapping of the land to locate all sensitive features, including adjacent wells. This
   resulted in contact with neighbors and the opportunity to talk with them about the program and
   provide contact information if they have any concerns before, during or after the land application.
   We believe the increased contact with neighbors, in combination with respecting buffers, reduced
   complaints during and after land application events. Now, when complaints do occur, we respond
   with a site visit to share with the complainant how we run our program, and assure them we are
   doing the land application as safely as possible to protect human health and the environment. This
   provides an opportunity to educate the community on our program and to share how we use
   GPS/GIS in the protection of health and the environment.

B. Land-owner financial support. We are now able to recover a portion of land-application costs from
   the farming community where before, politically, this would have been unlikely.

C. Better regulatory relationship. CCSD#1 now realizes a stronger relationship with the regulating
   agency, DEQ due, in part, to this GPS/GIS application.

    4. What system design problems were encountered?

Problem 1a: Blank screen with initial ArcGIS created shapefile when used in EZ Guide 500 GPS unit.

        Cause:
        The EZ Guide 500 directory files are hard coded into the system.

        Initial Solution:
        Create an easy file in the EZ Guide 500 resolved the hardcoded directory file structure and the
        hardware bridging. (AgGPSDatatemplatetemplateFarmtemplateField)




                                                                                                7|Page
2012 URISA AWARD APPLICATION
Problem 1b: Blank screen with initial ArcGIS created shapefile when used in EZ Guide 500 GPS unit.

        Cause: The shapefile created in ArcGIS was based on the Oregon State plane Zone 15 coordinate
        system. EZ Guide 500 GPS unit uses the geographic coordinate system of WGS NAD 1984 which
        in the shapefile created in the truck GPS unit creates a positional (.pos) file for the unit to
        properly determine its real world location.

         Solution: Create an original template shapefile within the EZ Guide 500 unit and transfer the
        positional file into each ArcGIS created field shapefile. Note: there is a distance restriction from
        the original .pos file. In order to read shapefiles for instance, in another county, a new
        positional file must be created.




Problem 2: EZ Guide 500 GPS unit distorts/warps true circle buffers around point features, i.e., wells.

        Cause:
        The reason for the distortion is that the truck hardware does not allow for the mathematical
        computation of circles labeled as buffered zones around any point feature found within
        geographic field boundaries. ArcGIS map software reads true circle objects, while Trimble truck
        GPS hardware does not, thus creating distorted buffers in shapefiles.

        Solution:
        Within ArcGIS, vertices were added to the arc of the true circle giving the GPS unit in the truck
        the ability to convert the arc to its true geographic position, mitigating the chance of land-
        application error risk. See Image D.




                                                                                                 8|Page
2012 URISA AWARD APPLICATION
Shapefile of RSA viewed in ArcGIS



                                                   Warped shapefile over SDE file




Problem 3: The truck Trimble GPS hardware misplaces and repositions ArcGIS created vertices that
provide ghost polygons and false areas, which, again, as in problem 2, creates land-application error risk.

        Cause:
        The truck GPS unit cannot read a complex multipart polygon possibly do to (a) compute the
        longitude and latitude of vertices created in ArcGIS (b) Truck GPS unit character field truncates
        the character length of the ArcGIS vertices positional location causing an accuracy issue.

        Solution:
        Explode a multi-part polygon into separate shapefiles which are then applied as separate shapes
        that constitute one field. Once land-application is completed and the spread data are
        downloaded, data are merged as one multipart polygon.




                                                                                               9|Page
2012 URISA AWARD APPLICATION
Original RSA boundaries of 1 field with 3
                                                   associated polygons.
Scrambled boundaries because of vertices
relocations


   5. What differentiates this system from other similar systems?

Every stage, from field mapping to regulatory reporting, uses GPS technology and ArcGIS mapping
software to comply with regulatory requirements. Mapping process is comprehensive, robust, updating
and analyzing field application changes that enable WES to manage every step associated with liquid
biosolids land application.

Other agencies use GIS or GPS in various forms.

University of Nebraska, Lincoln, Nebraska              1. Post Biosolids Spray: Walks outline of
                                                          spray to calculate total acreage using a
                                                          handheld device for billing purpose.
Virginia Beach, VA                                     1. Maps fields with GPS handheld device and
                                                          creates GIS maps to record soil types and
                                                          features.
Metro Wastewater Reclamation District, Denver,         1. Uses GPS technology to map swaths where
CO                                                        liquid biosolids have been applied.
Clackamas County Service District No. 1, Water         1. Maps fields with GPS handheld device and
Environment Services, Clackamas County                    creates GIS maps to record sensitive
                                                          features .
                                                       2. Creates shapefiles in ArcGIS to use in truck
                                                          GPS unit with all required buffers.
                                                       3. Maps swaths where liquid biosolids have
                                                          been applied
                                                       4. Uses spread maps for post-application to
                                                          analyze any buffer violations
                                                       5. Creates reports using maps for regulatory
                                                          documentation showing compliance
Program comparisons.


                                                                                         10 | P a g e
2012 URISA AWARD APPLICATION
D: Implementation
    1. What phases did you go through in developing the system?

a) Reviewed current processes that included the development of process maps for current practices
b) Examined regulatory requirements on land-application constraints (buffered land zones) and
   reporting procedures
c) Accessed accuracy needs for field application and recommended a 1-meter accuracy variance for
   handheld devices based on land-application spraying methods and equipment cost
d) Discussed data and equipment needs with end users
e) Analyzed time-line requirements with program managers
f) Researched fleet GPS systems for driver use
g) Trained myself on handheld GeoXT, handheld device software TerraSync & truck GPS unit EZ Guide
   500 and related software
h) Developed TerraSync Data Dictionary to represent all required DEQ sensitive features
i) Trained staff for on handheld device application (handheld GeoXT device and software TerraSync)
j) Trained BAT II Supervisor on the uploading & downloading of data onto EZ Guide 5000
k) Trained drivers in use of GPS unit and calculating spray width.
l) Mapped new processes associated with GPS and GIS application in liquids biosolids program


    2. Were there any modifications to the original system design? Why? What?

A. Python programs were developed to execute command-line programs that were once done
   manually. Before the Python programs, each command for BUFFER, ERASE, etc for each applicable
   sensitive feature for each field, which for agricultural field could contain up to 20 buffers per field.
   As a result of incorporating the Python programs for command lines, the buffering process become
   a 15-minute task or less where before it would take from 3 hours to 5 hours to execute per field.




                         Python buffering program interface

                                                                                               11 | P a g e
2012 URISA AWARD APPLICATION
B. The completion of uploading and downloading data onto and off of the truck GPS unit became more
   efficient when that task was shifted from the GIS specialist / Engineer Technician 3 to the Biosolids
   Application Technician. A savings of 1 - 3 hours per field was generated from this task shift for the
   GIS Analyst as the BAT 2 was already in the field for pre-field application authorization.


E: Organizational Impact

    1. What user community does the system serve and how?

User Community        How served
Biosolids               Provide guided land application via truck mounted units that display field and its
Application             buffer zones.
Technicians (land-      On-going mapping updates field’s annually to capture site usage changes that
application truck       affect buffer zones and spreadable acres.
drivers)                Assures proper agronomic loading rates due to actual spreadable acres vs.
                        acreage of the entire site.
BAT 2 and               Assure staff are performing as requested
Supervisor              Eliminates manual flagging of sensitive areas
                        Identify needs for training
                        Knowledge transfer of field locations and unique requirements
Manager                 Overall program management including
                        Selecting sites
                        Understanding potential problems based on mapping; locating potential new
                        sites that meet select criteria (slope, soil type, adjacent properties, etc)
                        Assuring all sensitive features are accounted for and mapped.


    2. What are the ultimate decisions/operations/services being affected? If appropriate, provide a
       few examples including, but not limited to: screen input/output forms, paper products, or
       other descriptive graphics

A: The imagine below shows the technology process that Water Environment Services developed for
managing field application of liquid Biosolids. Affected was staff and data flow because, before this GPS
and GIS project, all processes were done manually. Before this project, burden for reporting compliance
fell upon the shoulders of the drivers and the manager who supervised the drivers. This included
‘coloring in’ of vague maps of farm fields of areas that where biosolids had been spread. With the
implementation of this project, this tracking transferred from the drivers to other staff such as the
engineer, source control technician, the surface water technician and water quality analyst.

Two Major Decisions
The first decision related to the field mapping that had to be conducted before spraying began using
GPS and GIS technology. For end-users, WES had to guarantee that data flowed smoothly from the
hand-held device to the truck dashboard device and then to ArcGIS and finally back to the truck
dashboard device where sensitive land areas identified buffers that would not be sprayed with liquid
Biosolids. The process itself guaranteed the smooth flow of data and thus the process map serves as the
solution for timely, smooth data flow.

                                                                                             12 | P a g e
2012 URISA AWARD APPLICATION
The second decision centered on determining eligible fields using the data results from the initial field
mapping that had been performed by the surface water technician and water quality analyst. Before
any liquid biosolids was applied onto a field, analysis results determine if a field was still viable for land
application by calculating a final spreadable acreage. An analysis of the final size of the field and the
‘cutting up’ of the field do to buffers would determine if the cost and risk of spread violations was still
beneficial for WES and farm.



Application of Liquid Biosolids using GPS Units
                                                                               Determining Eligible Farms                                                                                                                                       GPS Data
                                          Biosolids Application Technician




                                                                                        START

                                                                                                                             AND b)
                                                                                                                          EXP t & Bo
                                                                                                                              , Jane
                                                                                                                          hryn
                                                                                                                      (Kat                                                                                                                 Uploads
                                                                                                                                                                                                        Selects fields to spray
                                                                                                                                                                                                            (Applies rating                  data
                                                                                                Identifies eligible                                                                                      methodology. Sets                  of field
                                                                                                agricultural fields                                                                                     priority on the order of             to be
                                                                                                                                                                                                        agricultural fields that           sprayed
                                                                                                                                                                                                           will be sprayed.)
                                                                                                                                                                                                                                                                                              Downloads closed           Files the following:
                                                                                                                                                                                                                                                                                              fields                          Farm and Remaining
                                                                                                                                                                                 TAZimportBiosolids_GPSB_Uploads to EZAgGPSdataWES                                                      Uploads new fields              Spreadable Acreage map
                                                                                                                                                                                                                                                                                              Deletes fields where            Soil sampling map
                                                                                                                                                                                                                                                                                              swath data has been
                                                                                                                                                                                                                                                                                              mapped
                                    SW Tech and Water
                                      Quality Analyst




                                                                                                   Maps the                                   GPS
                                                                                                agricultural field                         Pathfinder
                                                                                                 using Trimble                               Office
                                                                                                  Geo-XT unit                               Software



                                                                                                                               TAZimportBiosolids_GPS A_FieldVerifield            Downloads
                                                                                                                                                                                      *.SSF files
                                    Another source control




                                                                                                                                                                                                                                                                 Digital copies of maps
                                         technician




                                                                                                   Maps soli                                  GPS
                                                                                                 sampling site                             Pathfinder                                                                                                            TazImportBioSolids_GPSJPGs
                                                                                                 using Trimble                               Office
                                                                                                  Geo-XT unit                               Software                                                                                                             <farmname>RSA.jpg = Map of Remaining Spreadable Acres
                                                                                                                                                                        Downloads                                                                                <farmname>SS.jpg = Map of Soil Sampling Locations
                                                                                                                                                                        *.SSF files                                                                              <farmname>Spread.jpg = Map of Application Spread
                                                                                                                                 TAZimportBiosolids_GPS Soils




                                                                                                                                                                                                                                                                                           Exports to .shp formatted
                                                                                                                                                                                                                                                                                           specifically for Easyguide
                                          Engineering Technician 3




                                                                                                                                                                                              `                                                                                                     500 unit
                                                                                                                                                                                                    TAZimportBiosolids_GPS


                                                                                                                                                                                                                                                                                                                               ArcGIS Software:
                                                                                                                                                                                                                                                                                                                                Creates farm and
                                                                                                                                                                                                                                                                                           Buffers for and excludes
                                                                                                                                                                                  GPS                                                                                                                                           Remaining
                                                                                                                                                                                                                                                                                          water wells, ditches, roads,
                                                                                                                                                                               Pathfinder                                                                                                                                       Spreadable Acreage
                                                                                                                                                                                                                                                                                            low points, > 12˚ grades
                                                                                                                                                                                 Office                                                                                                                                         map
                                                                                                                                                                                                                                                                                          and residential development
                                                                                                                                                                                Software                                                                                                                                        Creates soil sampling
                                                                                                                                                                                                                                                                                              from agricultural field.
                                                                                                                                                                                                                                                                                                                                map
                                                                                                                                                                                                                                   Converts *.cor file into
                                                                                                                                                                                                                                   *.SHP shape file
                                                                                                                                                                             Makes                                                 Produces polygon
                                                                                                                                                                             differential                                                                              Imports into
                                                                                                                                                                                                                                   showing boundaries of              Spatial Data              Scrubs data for
                                                                                                                                                                             corrections to                                        field (to be sprayed)              Engine (SDE)              topology errors
                                                                                                                                                                             *.ssf.                                                using the *.SHP shape                Software
                                                                                                                                                                             Creates *.COR                                         file
                                                                                                                                                                             file




Application of Liquid Biosolids using GPS Units
                                                                                 Spraying of Biosolids on Field                                                                                                Data Analysis

                                                                             CON’D
  Biosolid Application Technician




                                                                                                                                               Down
                                                                                                                                               loads
                                                                                                                                              previous                                                                                                         Swath Map
                                                                                                                                                data




                                                                                                                                                                                                                                                                 ArcGIS
                                                                                                                                                                                                                                                                Software:
                                                                                                                                                                                                                                                              Creates swath
  Engineering Technician 3




                                                                                                                                                                                                                                                                  map



                                                                                                                                                                                                                  `


                                                                                                                                                                                       TAZimportBiosolids_GPSDownLoads



                                                                                                                                                                                                                                                              Imports shape
                                                                                                                                                                                                                                                               file into SDE




                                                                                                                                                                                                                                                                                                                                                        13 | P a g e
2012 URISA AWARD APPLICATION
B: An established set of maps for each step of the process is created, reviewed and finalized by both the
BAT II Supervisor and the Biosolids Manager.

The series of maps include:

              A soil sampling location map
              An RSA map
              And a Spread map

See Appendix C for examples.

    3. What were the quantitative and qualitative impacts of the system?

Quantitative:

Complaints are resolved between WES and the complainant rather than being elevated to the County
Commissioners level. Zero complaints were elevated to mayors or Council members since
implementation. While historical data is incomplete, staff recalls this happening on numerous occasions.



                        Year         Total number or        Estimated complaints
                                     recorded complaints    to elected officials

                        2004*        4                      unknown

                        2005         6                      unknown

                        2006         7                      unknown

                        2007         9                      3

                        2008         9                      5

                        2009         14                     unknown

                        2010         11                     0

                        2011         6                      0

                          *First year the complaint database went on-line



Qualitative:




                                                                                            14 | P a g e
2012 URISA AWARD APPLICATION
A more professional program that considers risk management as a critical component to
        program management.
        Enhanced dialog with neighbors as a result of well mapping. This results in an opportunity to
        share this technology and reassure them WES was managing the Liquids Biosolids Program as
        safely as possible.
        Knowledge transfer regarding field locations and buffered areas.
        Validation of acres spread for billing purposes
        Validating correct spreading occurred if compliance or complaint situation presents
        Land Application Technicians appreciate hard buffers; subjective buffers cause problems.



    4. What effect has the system had on productivity?

A. A processing time line has been set for each step of the biosolids tracking once the land application
   has been completed.
       a) BAT 2 downloads spread data and advises GIS Analyst
       b) GIS Analyst has 2 days to create spread map and then advises BAT 2
       c) BAT 2 has 3 days to do post-application check using ‘Spread Map’.
       d) Biosolids manager has 5 days to finalize all data and maps are in farm binder for that
          particular land application

These turn around dates are tracked by the Biosolids Manager and analyzed/reviewed quarterly.
Biosolids team has a meeting to review timeline productivity.




                                                                                             15 | P a g e
2012 URISA AWARD APPLICATION
B. The BAT 2 Coordinator no longer has to take time to walk the field marking sensitive features with
   flags for each field. This has added 1-3 hours of extra time for tracking and properly recording
   information for post-application procedures.

C. The drivers now have quicker turn around times on the land application as there is no longer the
   issue of reapplying biosolids on already sprayed areas. They now know exactly where to start or
   stop the application procedure without having to wait and discuss with other drivers at the field.

    5. What, if any, other impacts has the system had?

Risk management and general confidence in the land application component of the program.

    6. How did the system change the way business is conducted with and/or service delivered to
       clients? Give specific examples comparing the old way with the new

1. This system had significant changes to the way business is conducted. In the past, before the
   implementation of this GPS/GIS application, the drivers were limited to using a printed tax map and
   then colored in the areas where they applied Biosolids. Consequently, biosolids were land applied
   with little consideration for buffers and correct acreage (resulting in fields being overloaded and
   risking groundwater contamination or runoff to surface water). In addition, Technicians were
   persuaded by farmers to apply on land that was not authorized by DEQ to receive biosolids. With
   mapping, all of these challenges are now under control.

2. There was also no review of the field after application to assess proper spreading. Now with the
   mapping, field inspections are made with the spread map, and closure can occur with confidence
   that the driver applied correctly. This has provided a mechanism for the Supervisor to know when
   training might be needed.


F: System Resources

    1. What are the system’s primary hardware components? Give a brief list or description of the
       hardware configuration supporting the system .

Trimble EZ-Guide 500 Lightbar Guidance System
Trimble GeoXT 2008 with TerraSync

    2. What are the system’s primary software components? Describe the primary software and, if a
       commercial package, any customizations required for the system.

ArcGIS 9.3 – after outlining the processes, a series of small python programs were developed to speed
up processing.




                                                                                            16 | P a g e
2012 URISA AWARD APPLICATION
3. What data does the system work with? List and briefly describe the database(s)

Wells                     Roads (public & private)   Power Lines                Wind Mills
Buildings                 Ravines                    Trees                      Streams
Water                     Slope                      Septic Tanks               Drain Fields
Culvert                   Ditches                    Field Boundary             Special Requests
Buffers



    4. What staff resources were required to implement the system? (approximate staff and
       consultant time as FTE’s)

It was a significant undertaking to get this operational. Equipment and software needed to
be purchased; our GIS Technician required some time to resolve problems in the field with
recording and/or downloading and all fields required GPS mapping; all fields required
mapping. Estimated FTE to become fully operational with few problems was 2.0 over the
course of 1 year.

    5. Comment on anything unusual about the resources used to develop your system, such as
       data, software, personnel and financing.

Did not have an immediate buy-in by drivers, as they were not favorable of computer tracking. Did not
want to deal with ‘electronic’ equipment and thought the system was going to be complex and
cumbersome and waste time. After a few field applications, the drivers now are very favorable of the
spread tracking and with training have found the units to be easy to use. The truck GPS units were
chosen mainly for the general simplicity of the unit and the larger screen. There was also a cost issue
determinant, but if needed a higher end unit could have been purchased. The EZ Guide GPS unit is a
mid-level Agricultural GPS system.




                                                                                             17 | P a g e
2012 URISA AWARD APPLICATION
APPENDIX A:




                                             18 | P a g e
2012 URISA AWARD APPLICATION
19 | P a g e
2012 URISA AWARD APPLICATION
APPENDIX B:




                                             20 | P a g e
2012 URISA AWARD APPLICATION
21 | P a g e
2012 URISA AWARD APPLICATION
22 | P a g e
2012 URISA AWARD APPLICATION
23 | P a g e
2012 URISA AWARD APPLICATION
APPENDIX C:




                                             24 | P a g e
2012 URISA AWARD APPLICATION
Soil Sampling Location Map


                               25 | P a g e
2012 URISA AWARD APPLICATION
RSA (Remaining Spreadable Acres) Map



                                       26 | P a g e
2012 URISA AWARD APPLICATION
Spread Data Map


                               27 | P a g e
2012 URISA AWARD APPLICATION

More Related Content

Viewers also liked

Situación desafiante de la ética
Situación desafiante de la éticaSituación desafiante de la ética
Situación desafiante de la éticaRafa Tó
 
Situación desafiante de la ética en guatemala
Situación desafiante de la ética en guatemalaSituación desafiante de la ética en guatemala
Situación desafiante de la ética en guatemalaRafa Tó
 
Willamette river
Willamette riverWillamette river
Willamette riverSuKaOt
 
Metodologi Desain - PSX ( Kelompok 2)
Metodologi Desain - PSX ( Kelompok 2)Metodologi Desain - PSX ( Kelompok 2)
Metodologi Desain - PSX ( Kelompok 2)Burhanudin Abu Sujak
 
Metodologi Desain - The Deep Dive (Kelompok 2)
Metodologi Desain - The Deep Dive (Kelompok 2)Metodologi Desain - The Deep Dive (Kelompok 2)
Metodologi Desain - The Deep Dive (Kelompok 2)Burhanudin Abu Sujak
 
4. ch 6 financial statement analysis
4. ch 6 financial statement analysis4. ch 6 financial statement analysis
4. ch 6 financial statement analysisirfan_1
 
The life of a sea turtle
The life of a sea turtleThe life of a sea turtle
The life of a sea turtleantmes123
 
1. introduction to corporate finance
1. introduction to corporate finance1. introduction to corporate finance
1. introduction to corporate financeirfan_1
 

Viewers also liked (9)

Situación desafiante de la ética
Situación desafiante de la éticaSituación desafiante de la ética
Situación desafiante de la ética
 
Situación desafiante de la ética en guatemala
Situación desafiante de la ética en guatemalaSituación desafiante de la ética en guatemala
Situación desafiante de la ética en guatemala
 
Willamette river
Willamette riverWillamette river
Willamette river
 
Metodologi Desain - PSX ( Kelompok 2)
Metodologi Desain - PSX ( Kelompok 2)Metodologi Desain - PSX ( Kelompok 2)
Metodologi Desain - PSX ( Kelompok 2)
 
Metodologi Desain - The Deep Dive (Kelompok 2)
Metodologi Desain - The Deep Dive (Kelompok 2)Metodologi Desain - The Deep Dive (Kelompok 2)
Metodologi Desain - The Deep Dive (Kelompok 2)
 
4. ch 6 financial statement analysis
4. ch 6 financial statement analysis4. ch 6 financial statement analysis
4. ch 6 financial statement analysis
 
Democrito
DemocritoDemocrito
Democrito
 
The life of a sea turtle
The life of a sea turtleThe life of a sea turtle
The life of a sea turtle
 
1. introduction to corporate finance
1. introduction to corporate finance1. introduction to corporate finance
1. introduction to corporate finance
 

Similar to GPS & GIS Implementation Strengthens Compliance for WES Biosolids Program

World Pipelines - Better Together - SCADA and GIS
World Pipelines - Better Together - SCADA and GISWorld Pipelines - Better Together - SCADA and GIS
World Pipelines - Better Together - SCADA and GISsmrobb
 
Systems Analysis & Design Project
Systems Analysis & Design Project Systems Analysis & Design Project
Systems Analysis & Design Project Amanda Blakley
 
IRJET- Detecting Performance of Clouds by Uploading Applications
IRJET- Detecting Performance of Clouds by Uploading ApplicationsIRJET- Detecting Performance of Clouds by Uploading Applications
IRJET- Detecting Performance of Clouds by Uploading ApplicationsIRJET Journal
 
Hec geo ras-43_users_manual
Hec geo ras-43_users_manualHec geo ras-43_users_manual
Hec geo ras-43_users_manualGerman Gutierrez
 
IRJET- Performance Evaluation of Irrigation Projects
IRJET- Performance Evaluation of Irrigation ProjectsIRJET- Performance Evaluation of Irrigation Projects
IRJET- Performance Evaluation of Irrigation ProjectsIRJET Journal
 
Geographical information system (gis) for water resources management
Geographical information system (gis) for water resources managementGeographical information system (gis) for water resources management
Geographical information system (gis) for water resources managementeSAT Journals
 
Geographical information system (gis) for water
Geographical information system (gis) for waterGeographical information system (gis) for water
Geographical information system (gis) for watereSAT Publishing House
 
Geographical information system (gis) for water resources management
Geographical information system (gis) for water resources managementGeographical information system (gis) for water resources management
Geographical information system (gis) for water resources managementeSAT Journals
 
Powero GIS Road Map Presentation1
Powero GIS Road Map Presentation1Powero GIS Road Map Presentation1
Powero GIS Road Map Presentation1Lokesh Addagada
 
IRJET- LORA based Solid Waste Management
IRJET- LORA based Solid Waste ManagementIRJET- LORA based Solid Waste Management
IRJET- LORA based Solid Waste ManagementIRJET Journal
 
Capgemini ses - smart grid operational services - gis pov (gr)
Capgemini   ses - smart grid operational services - gis pov (gr)Capgemini   ses - smart grid operational services - gis pov (gr)
Capgemini ses - smart grid operational services - gis pov (gr)Gord Reynolds
 
Use case of Disaster Management System by using Geopaparazzi and MapGuide Ope...
Use case of Disaster Management System by using Geopaparazzi and MapGuide Ope...Use case of Disaster Management System by using Geopaparazzi and MapGuide Ope...
Use case of Disaster Management System by using Geopaparazzi and MapGuide Ope...Hirofumi Hayashi
 
Implementing ArcGIS for Water Utilities
Implementing ArcGIS for Water UtilitiesImplementing ArcGIS for Water Utilities
Implementing ArcGIS for Water UtilitiesEsri
 
SoftwareIntegrationStrategy
SoftwareIntegrationStrategySoftwareIntegrationStrategy
SoftwareIntegrationStrategyVeronica Gardner
 
Smart Irrigation System Using IOT
Smart Irrigation System Using IOTSmart Irrigation System Using IOT
Smart Irrigation System Using IOTIRJET Journal
 
Mud Reporting: Streamlined Process and Data Management
Mud Reporting: Streamlined Process and Data ManagementMud Reporting: Streamlined Process and Data Management
Mud Reporting: Streamlined Process and Data Managementpvisoftware
 

Similar to GPS & GIS Implementation Strengthens Compliance for WES Biosolids Program (20)

World Pipelines - Better Together - SCADA and GIS
World Pipelines - Better Together - SCADA and GISWorld Pipelines - Better Together - SCADA and GIS
World Pipelines - Better Together - SCADA and GIS
 
Systems Analysis & Design Project
Systems Analysis & Design Project Systems Analysis & Design Project
Systems Analysis & Design Project
 
IRJET- Detecting Performance of Clouds by Uploading Applications
IRJET- Detecting Performance of Clouds by Uploading ApplicationsIRJET- Detecting Performance of Clouds by Uploading Applications
IRJET- Detecting Performance of Clouds by Uploading Applications
 
APGWD User Manual_updated
APGWD User Manual_updatedAPGWD User Manual_updated
APGWD User Manual_updated
 
Mrp Final
Mrp FinalMrp Final
Mrp Final
 
Earth Science Data and Information System (ESDIS) Project Update
Earth Science Data and Information System (ESDIS) Project UpdateEarth Science Data and Information System (ESDIS) Project Update
Earth Science Data and Information System (ESDIS) Project Update
 
Hec geo ras-43_users_manual
Hec geo ras-43_users_manualHec geo ras-43_users_manual
Hec geo ras-43_users_manual
 
IRJET- Performance Evaluation of Irrigation Projects
IRJET- Performance Evaluation of Irrigation ProjectsIRJET- Performance Evaluation of Irrigation Projects
IRJET- Performance Evaluation of Irrigation Projects
 
Geographical information system (gis) for water resources management
Geographical information system (gis) for water resources managementGeographical information system (gis) for water resources management
Geographical information system (gis) for water resources management
 
Geographical information system (gis) for water
Geographical information system (gis) for waterGeographical information system (gis) for water
Geographical information system (gis) for water
 
Geographical information system (gis) for water resources management
Geographical information system (gis) for water resources managementGeographical information system (gis) for water resources management
Geographical information system (gis) for water resources management
 
Powero GIS Road Map Presentation1
Powero GIS Road Map Presentation1Powero GIS Road Map Presentation1
Powero GIS Road Map Presentation1
 
IRJET- LORA based Solid Waste Management
IRJET- LORA based Solid Waste ManagementIRJET- LORA based Solid Waste Management
IRJET- LORA based Solid Waste Management
 
Capgemini ses - smart grid operational services - gis pov (gr)
Capgemini   ses - smart grid operational services - gis pov (gr)Capgemini   ses - smart grid operational services - gis pov (gr)
Capgemini ses - smart grid operational services - gis pov (gr)
 
Use case of Disaster Management System by using Geopaparazzi and MapGuide Ope...
Use case of Disaster Management System by using Geopaparazzi and MapGuide Ope...Use case of Disaster Management System by using Geopaparazzi and MapGuide Ope...
Use case of Disaster Management System by using Geopaparazzi and MapGuide Ope...
 
Implementing ArcGIS for Water Utilities
Implementing ArcGIS for Water UtilitiesImplementing ArcGIS for Water Utilities
Implementing ArcGIS for Water Utilities
 
UserManual43.pdf
UserManual43.pdfUserManual43.pdf
UserManual43.pdf
 
SoftwareIntegrationStrategy
SoftwareIntegrationStrategySoftwareIntegrationStrategy
SoftwareIntegrationStrategy
 
Smart Irrigation System Using IOT
Smart Irrigation System Using IOTSmart Irrigation System Using IOT
Smart Irrigation System Using IOT
 
Mud Reporting: Streamlined Process and Data Management
Mud Reporting: Streamlined Process and Data ManagementMud Reporting: Streamlined Process and Data Management
Mud Reporting: Streamlined Process and Data Management
 

GPS & GIS Implementation Strengthens Compliance for WES Biosolids Program

  • 1. 2012 WES Biosolids Program GPS & GIS Implementation Susan Ottersen GIS Analyst/Engineer Tech III Water Environment Services Clackamas County 4/16/2012 1|Page 2012 URISA AWARD APPLICATION
  • 2. A: System -------------------------------------------------------------------------------------------------------------- 4 1. Name of the System and ESIG™ Award Categories: ---------------------------------------------------------- 4 2. Executive administrator letter: ------------------------------------------------------------------------------------- 4 3. Summary: ---------------------------------------------------------------------------------------------------------------- 4 4. Three user testimonials: --------------------------------------------------------------------------------------------- 5 B: Jurisdiction--------------------------------------------------------------------------------------------------------- 5 1. Name of jurisdiction: -------------------------------------------------------------------------------------------------- 5 2. Population served by the organization:-------------------------------------------------------------------------- 5 3. Annual total budget for jurisdiction: ----------------------------------------------------------------------------- 5 4. Chief elected official: -------------------------------------------------------------------------------------------------- 5 5. System Contact: -------------------------------------------------------------------------------------------------------- 5 C: System Design ---------------------------------------------------------------------------------------------------- 6 1. What motivated the system development? -------------------------------------------------------------------- 6 2. What specific service or services was the system intended to improve? ------------------------------- 6 3. What, if any, unexpected benefits did you achieve? --------------------------------------------------------- 7 4. What system design problems were encountered? ---------------------------------------------------------- 7 5. What differentiates this system from other similar systems? -------------------------------------------- 10 D: Implementation ------------------------------------------------------------------------------------------------ 11 1. What phases did you go through in developing the system? --------------------------------------------- 11 2. Were there any modifications to the original system design? Why? What? ------------------------ 11 E: Organizational Impact ---------------------------------------------------------------------------------------- 12 1. What user community does the system serve and how? -------------------------------------------------- 12 2. What are the ultimate decisions/operations/services being affected? If appropriate, provide a few examples including, but not limited to: screen input/output forms, paper products, or other descriptive graphics ------------------------------------------------------------------------ 12 3. What were the quantitative and qualitative impacts of the system? ---------------------------------- 14 4. What effect has the system had on productivity? ----------------------------------------------------------- 15 5. What, if any, other impacts has the system had? ------------------------------------------------------------ 16 6. How did the system change the way business is conducted with and/or service delivered to clients? Give specific examples comparing the old way with the new ---------------------------- 16 2|Page 2012 URISA AWARD APPLICATION
  • 3. F: System Resources ---------------------------------------------------------------------------------------------- 16 1. What are the system’s primary hardware components? Give a brief list or description of the hardware configuration supporting the system . ------------------------------------------------------ 16 2. What are the system’s primary software components? Describe the primary software and, if a commercial package, any customizations required for the system. ------------------------------ 16 3. What data does the system work with? List and briefly describe the database(s) ----------------- 17 4. What staff resources were required to implement the system? (approximate staff and consultant time as FTE’s) ------------------------------------------------------------------------------------------- 17 5. Comment on anything unusual about the resources used to develop your system, such as data, software, personnel and financing. --------------------------------------------------------------------- 17 APPENDIX A: -------------------------------------------------------------------------------------------------------- 18 APPENDIX B: -------------------------------------------------------------------------------------------------------- 20 APPENDIX C: -------------------------------------------------------------------------------------------------------- 24 3|Page 2012 URISA AWARD APPLICATION
  • 4. Application for 2011 URISA ESIG™ A: System 1. Name of the System and ESIG™ Award Categories: Single Process System 2. Executive administrator letter: See Appendix A. 3. Summary: Water Environment Services (WES) began its Biosolids program in the 1980’s. Then, environmental requirements were more lenient and record maintenance sporadic where now greater attention to environment safety has produced stricter standards from the program’s regulator, Oregon’s Department of Environmental Quality (DEQ). In 2009, an internal assessment revealed that WES was not meeting the regulator’s record keeping and soil testing standards and, from a management perspective, was not managing program risk associated with land application of liquid biosolids. Compelled by the risk of scraping the Liquid Biosolids Program altogether unless practices were brought into compliance and risk managed, WES took steps to ensure compliance and mitigate program risk. WES achieved that due, in part, to this GPS/GIS project, which provided for greater internal controls that enhanced field management and narrowed the variance associated with spraying onto fields and for stakeholders, strengthened customer service and documentation for the farming community, neighbors, and regulators. Biosolids spreading is not a precise application and, as discovered with WES’ internal audit / assessment, can generate land-application risk. DEQ has strict guidelines for application of Biosolids to agricultural land with specific distances from buildings, water supply wells or springs, streams, ditches, roads, and other features. Given those regulatory guidelines, WES faced several issues: Lacking in WES’ liquid Biosolids program was a method to track all land-application updates at the farms that were receiving the liquid Biosolids on their fields. Needed was a system that recorded precisely where biosolids were applied and, more importantly, identified the location of land-sensitive buffered zones and if buffer violations occurred during application. The only system that made sense as a solution which identified and tracked data was implementing a GPS system with mapping in ArcGIS. The GPS/GIS project used Trimble GPS technology (handheld devices for field mapping and dashboard devices for truck drivers) and ArcGIS mapping software to manage all steps associated with the application of liquid biosolids onto agricultural fields. Included was the education of staff who mapped the fields using the Trimble 2008 GeoXt handheld unit equipped with TerraSync software and the Biosolids drivers, responsible for liquid land application, who used the EZ Guide 500 dashboard truck device. 4|Page 2012 URISA AWARD APPLICATION
  • 5. Lack of field staff buy-in and active participation would have rendered this project a failure. Staff that mapped the agricultural fields with the handheld devices and drove the land-application trucks with the dashboard truck device were the end users of this technology and identified the obstacles in using this GPS/GIS application. 4. Three user testimonials: See Appendix B. B: Jurisdiction 1. Name of jurisdiction: Clackamas County Service District No. 1, Water Environment Services of Clackamas County (WES) 2. Population served by the organization: Clackamas County Water Environment Services (WES) manages sanitary sewer and surface water services for over 150,000 people in two special districts located within Clackamas County and operates seven wastewater treatment facilities; three of these facilities produce biosolids. Facilities that produce liquid biosolids are located in Clackamas County Service District No. 1: Kellogg Wastewater Treatment Plant and Hoodland Treatment Plant. Clackamas County Service District No. 1 provides retail sanitary sewer and surface water management services to unincorporated portions of North Clackamas County as well as the City of Happy Valley, Damascus, Boring, the communities of the Hoodland corridor, Fischer’s Forest Park near Redland, and wholesale wastewater treatment services to the cities of Milwaukie and Johnson City. These services are largely funded by revenues derived from rates and fees for development. 3. Annual total budget for jurisdiction: Clackamas County Service District No. 1: Proposed FY2012-13 Operating Budget of $27,232,000 and Capital Budget of $11,361,000. 4. Chief elected official: Mike Kuenzi, Director 150 Beavercreek Road Oregon City, Oregon 97045 5. System Contact: Susan Ottersen, GIS Analyst/Engineer Tech III 150 Beavercreek Road 5|Page 2012 URISA AWARD APPLICATION
  • 6. Oregon City, Oregon 97045 Phone: 503-742-4613 Fax: 503-742-4565 susanott@co.clackamas.or.us C: System Design 1. What motivated the system development? Water Environment Services operates a liquid biosolids program out of the Kellogg Creek (KC) Wastewater Treatment Plant and the Hoodland (HD) Sewage Treatment Plant. WES’ liquid program is the largest liquid biosolids land application program in the state of Oregon. WES generates 13,000,000 gallons of liquid biosolids annually serving over 100 different fields. WES also manages a cake biosolids program out of the Tri-City (TC) Wastewater Treatment Plant. Both KC and TC require biosolids to be removed daily from the plant do to capacity issues, which has been occurring since the 1980’s. With the increased DEQ requirements, it compelled WES to implement a more accurate and stringent monitoring program. The land application of liquid biosolids is particularly challenging. The liquid land application program serves farmers within 15 miles of the KC plant. This area is mostly zoned residential/rural, where the agricultural land application sites are adjacent to homes, schools, roads, and other denser populated areas. It is a patchwork quilt of fields in an ever expanding populated area that provides little room for error. For example, the largest field is a mere 33 acres. In contrast, our cake program in Eastern Oregon serves farmers with areas in the 200 – 500 acre ranges. The land application of biosolids in Oregon is regulated by the Oregon Department of Environmental Quality (DEQ) which authorizes all sites for biosolids application. Every site must be authorized by DEQ and each site has unique requirements based on its location. After an internal audit / assessment in 2009, it was clear that there were opportunities to improve our compliance with DEQ rules and our relationship with neighbors adjacent to land application sites. Key findings included: Application on unauthorized land Over application of biosolids on some fields resulting in elevated Nitrates in the soil Subjective boundaries around sensitive features resulting in repeated buffer violations Soil samples not taken or sampling sites not recorded Daily spreading records not being maintained Interruption of field application because of rain, equipment problems, staffing, etc. There was no clear record of where spreading had stopped. 2. What specific service or services was the system intended to improve? 6|Page 2012 URISA AWARD APPLICATION
  • 7. WES provides a service of delivery and land application of liquid biosolids to privately owned agricultural land. The land owner in the past was defined as our customer; now the adjacent neighbors and community at large are included in this definition of customer. Our service extends to them by assuring protection of their wells, surface water and minimizing odors. The ability to continue this service is dependent on maintaining compliance and gaining reasonable acceptance in the community. The use of GPS/GIS guided land application has allowed us to achieve both. 3. What, if any, unexpected benefits did you achieve? A. Better customer service, less customer complaints and educational opportunities. This required on the ground mapping of the land to locate all sensitive features, including adjacent wells. This resulted in contact with neighbors and the opportunity to talk with them about the program and provide contact information if they have any concerns before, during or after the land application. We believe the increased contact with neighbors, in combination with respecting buffers, reduced complaints during and after land application events. Now, when complaints do occur, we respond with a site visit to share with the complainant how we run our program, and assure them we are doing the land application as safely as possible to protect human health and the environment. This provides an opportunity to educate the community on our program and to share how we use GPS/GIS in the protection of health and the environment. B. Land-owner financial support. We are now able to recover a portion of land-application costs from the farming community where before, politically, this would have been unlikely. C. Better regulatory relationship. CCSD#1 now realizes a stronger relationship with the regulating agency, DEQ due, in part, to this GPS/GIS application. 4. What system design problems were encountered? Problem 1a: Blank screen with initial ArcGIS created shapefile when used in EZ Guide 500 GPS unit. Cause: The EZ Guide 500 directory files are hard coded into the system. Initial Solution: Create an easy file in the EZ Guide 500 resolved the hardcoded directory file structure and the hardware bridging. (AgGPSDatatemplatetemplateFarmtemplateField) 7|Page 2012 URISA AWARD APPLICATION
  • 8. Problem 1b: Blank screen with initial ArcGIS created shapefile when used in EZ Guide 500 GPS unit. Cause: The shapefile created in ArcGIS was based on the Oregon State plane Zone 15 coordinate system. EZ Guide 500 GPS unit uses the geographic coordinate system of WGS NAD 1984 which in the shapefile created in the truck GPS unit creates a positional (.pos) file for the unit to properly determine its real world location. Solution: Create an original template shapefile within the EZ Guide 500 unit and transfer the positional file into each ArcGIS created field shapefile. Note: there is a distance restriction from the original .pos file. In order to read shapefiles for instance, in another county, a new positional file must be created. Problem 2: EZ Guide 500 GPS unit distorts/warps true circle buffers around point features, i.e., wells. Cause: The reason for the distortion is that the truck hardware does not allow for the mathematical computation of circles labeled as buffered zones around any point feature found within geographic field boundaries. ArcGIS map software reads true circle objects, while Trimble truck GPS hardware does not, thus creating distorted buffers in shapefiles. Solution: Within ArcGIS, vertices were added to the arc of the true circle giving the GPS unit in the truck the ability to convert the arc to its true geographic position, mitigating the chance of land- application error risk. See Image D. 8|Page 2012 URISA AWARD APPLICATION
  • 9. Shapefile of RSA viewed in ArcGIS Warped shapefile over SDE file Problem 3: The truck Trimble GPS hardware misplaces and repositions ArcGIS created vertices that provide ghost polygons and false areas, which, again, as in problem 2, creates land-application error risk. Cause: The truck GPS unit cannot read a complex multipart polygon possibly do to (a) compute the longitude and latitude of vertices created in ArcGIS (b) Truck GPS unit character field truncates the character length of the ArcGIS vertices positional location causing an accuracy issue. Solution: Explode a multi-part polygon into separate shapefiles which are then applied as separate shapes that constitute one field. Once land-application is completed and the spread data are downloaded, data are merged as one multipart polygon. 9|Page 2012 URISA AWARD APPLICATION
  • 10. Original RSA boundaries of 1 field with 3 associated polygons. Scrambled boundaries because of vertices relocations 5. What differentiates this system from other similar systems? Every stage, from field mapping to regulatory reporting, uses GPS technology and ArcGIS mapping software to comply with regulatory requirements. Mapping process is comprehensive, robust, updating and analyzing field application changes that enable WES to manage every step associated with liquid biosolids land application. Other agencies use GIS or GPS in various forms. University of Nebraska, Lincoln, Nebraska 1. Post Biosolids Spray: Walks outline of spray to calculate total acreage using a handheld device for billing purpose. Virginia Beach, VA 1. Maps fields with GPS handheld device and creates GIS maps to record soil types and features. Metro Wastewater Reclamation District, Denver, 1. Uses GPS technology to map swaths where CO liquid biosolids have been applied. Clackamas County Service District No. 1, Water 1. Maps fields with GPS handheld device and Environment Services, Clackamas County creates GIS maps to record sensitive features . 2. Creates shapefiles in ArcGIS to use in truck GPS unit with all required buffers. 3. Maps swaths where liquid biosolids have been applied 4. Uses spread maps for post-application to analyze any buffer violations 5. Creates reports using maps for regulatory documentation showing compliance Program comparisons. 10 | P a g e 2012 URISA AWARD APPLICATION
  • 11. D: Implementation 1. What phases did you go through in developing the system? a) Reviewed current processes that included the development of process maps for current practices b) Examined regulatory requirements on land-application constraints (buffered land zones) and reporting procedures c) Accessed accuracy needs for field application and recommended a 1-meter accuracy variance for handheld devices based on land-application spraying methods and equipment cost d) Discussed data and equipment needs with end users e) Analyzed time-line requirements with program managers f) Researched fleet GPS systems for driver use g) Trained myself on handheld GeoXT, handheld device software TerraSync & truck GPS unit EZ Guide 500 and related software h) Developed TerraSync Data Dictionary to represent all required DEQ sensitive features i) Trained staff for on handheld device application (handheld GeoXT device and software TerraSync) j) Trained BAT II Supervisor on the uploading & downloading of data onto EZ Guide 5000 k) Trained drivers in use of GPS unit and calculating spray width. l) Mapped new processes associated with GPS and GIS application in liquids biosolids program 2. Were there any modifications to the original system design? Why? What? A. Python programs were developed to execute command-line programs that were once done manually. Before the Python programs, each command for BUFFER, ERASE, etc for each applicable sensitive feature for each field, which for agricultural field could contain up to 20 buffers per field. As a result of incorporating the Python programs for command lines, the buffering process become a 15-minute task or less where before it would take from 3 hours to 5 hours to execute per field. Python buffering program interface 11 | P a g e 2012 URISA AWARD APPLICATION
  • 12. B. The completion of uploading and downloading data onto and off of the truck GPS unit became more efficient when that task was shifted from the GIS specialist / Engineer Technician 3 to the Biosolids Application Technician. A savings of 1 - 3 hours per field was generated from this task shift for the GIS Analyst as the BAT 2 was already in the field for pre-field application authorization. E: Organizational Impact 1. What user community does the system serve and how? User Community How served Biosolids Provide guided land application via truck mounted units that display field and its Application buffer zones. Technicians (land- On-going mapping updates field’s annually to capture site usage changes that application truck affect buffer zones and spreadable acres. drivers) Assures proper agronomic loading rates due to actual spreadable acres vs. acreage of the entire site. BAT 2 and Assure staff are performing as requested Supervisor Eliminates manual flagging of sensitive areas Identify needs for training Knowledge transfer of field locations and unique requirements Manager Overall program management including Selecting sites Understanding potential problems based on mapping; locating potential new sites that meet select criteria (slope, soil type, adjacent properties, etc) Assuring all sensitive features are accounted for and mapped. 2. What are the ultimate decisions/operations/services being affected? If appropriate, provide a few examples including, but not limited to: screen input/output forms, paper products, or other descriptive graphics A: The imagine below shows the technology process that Water Environment Services developed for managing field application of liquid Biosolids. Affected was staff and data flow because, before this GPS and GIS project, all processes were done manually. Before this project, burden for reporting compliance fell upon the shoulders of the drivers and the manager who supervised the drivers. This included ‘coloring in’ of vague maps of farm fields of areas that where biosolids had been spread. With the implementation of this project, this tracking transferred from the drivers to other staff such as the engineer, source control technician, the surface water technician and water quality analyst. Two Major Decisions The first decision related to the field mapping that had to be conducted before spraying began using GPS and GIS technology. For end-users, WES had to guarantee that data flowed smoothly from the hand-held device to the truck dashboard device and then to ArcGIS and finally back to the truck dashboard device where sensitive land areas identified buffers that would not be sprayed with liquid Biosolids. The process itself guaranteed the smooth flow of data and thus the process map serves as the solution for timely, smooth data flow. 12 | P a g e 2012 URISA AWARD APPLICATION
  • 13. The second decision centered on determining eligible fields using the data results from the initial field mapping that had been performed by the surface water technician and water quality analyst. Before any liquid biosolids was applied onto a field, analysis results determine if a field was still viable for land application by calculating a final spreadable acreage. An analysis of the final size of the field and the ‘cutting up’ of the field do to buffers would determine if the cost and risk of spread violations was still beneficial for WES and farm. Application of Liquid Biosolids using GPS Units Determining Eligible Farms GPS Data Biosolids Application Technician START AND b) EXP t & Bo , Jane hryn (Kat Uploads Selects fields to spray (Applies rating data Identifies eligible methodology. Sets of field agricultural fields priority on the order of to be agricultural fields that sprayed will be sprayed.) Downloads closed Files the following: fields Farm and Remaining TAZimportBiosolids_GPSB_Uploads to EZAgGPSdataWES Uploads new fields Spreadable Acreage map Deletes fields where Soil sampling map swath data has been mapped SW Tech and Water Quality Analyst Maps the GPS agricultural field Pathfinder using Trimble Office Geo-XT unit Software TAZimportBiosolids_GPS A_FieldVerifield Downloads *.SSF files Another source control Digital copies of maps technician Maps soli GPS sampling site Pathfinder TazImportBioSolids_GPSJPGs using Trimble Office Geo-XT unit Software <farmname>RSA.jpg = Map of Remaining Spreadable Acres Downloads <farmname>SS.jpg = Map of Soil Sampling Locations *.SSF files <farmname>Spread.jpg = Map of Application Spread TAZimportBiosolids_GPS Soils Exports to .shp formatted specifically for Easyguide Engineering Technician 3 ` 500 unit TAZimportBiosolids_GPS ArcGIS Software: Creates farm and Buffers for and excludes GPS Remaining water wells, ditches, roads, Pathfinder Spreadable Acreage low points, > 12˚ grades Office map and residential development Software Creates soil sampling from agricultural field. map Converts *.cor file into *.SHP shape file Makes Produces polygon differential Imports into showing boundaries of Spatial Data Scrubs data for corrections to field (to be sprayed) Engine (SDE) topology errors *.ssf. using the *.SHP shape Software Creates *.COR file file Application of Liquid Biosolids using GPS Units Spraying of Biosolids on Field Data Analysis CON’D Biosolid Application Technician Down loads previous Swath Map data ArcGIS Software: Creates swath Engineering Technician 3 map ` TAZimportBiosolids_GPSDownLoads Imports shape file into SDE 13 | P a g e 2012 URISA AWARD APPLICATION
  • 14. B: An established set of maps for each step of the process is created, reviewed and finalized by both the BAT II Supervisor and the Biosolids Manager. The series of maps include:  A soil sampling location map  An RSA map  And a Spread map See Appendix C for examples. 3. What were the quantitative and qualitative impacts of the system? Quantitative: Complaints are resolved between WES and the complainant rather than being elevated to the County Commissioners level. Zero complaints were elevated to mayors or Council members since implementation. While historical data is incomplete, staff recalls this happening on numerous occasions. Year Total number or Estimated complaints recorded complaints to elected officials 2004* 4 unknown 2005 6 unknown 2006 7 unknown 2007 9 3 2008 9 5 2009 14 unknown 2010 11 0 2011 6 0 *First year the complaint database went on-line Qualitative: 14 | P a g e 2012 URISA AWARD APPLICATION
  • 15. A more professional program that considers risk management as a critical component to program management. Enhanced dialog with neighbors as a result of well mapping. This results in an opportunity to share this technology and reassure them WES was managing the Liquids Biosolids Program as safely as possible. Knowledge transfer regarding field locations and buffered areas. Validation of acres spread for billing purposes Validating correct spreading occurred if compliance or complaint situation presents Land Application Technicians appreciate hard buffers; subjective buffers cause problems. 4. What effect has the system had on productivity? A. A processing time line has been set for each step of the biosolids tracking once the land application has been completed. a) BAT 2 downloads spread data and advises GIS Analyst b) GIS Analyst has 2 days to create spread map and then advises BAT 2 c) BAT 2 has 3 days to do post-application check using ‘Spread Map’. d) Biosolids manager has 5 days to finalize all data and maps are in farm binder for that particular land application These turn around dates are tracked by the Biosolids Manager and analyzed/reviewed quarterly. Biosolids team has a meeting to review timeline productivity. 15 | P a g e 2012 URISA AWARD APPLICATION
  • 16. B. The BAT 2 Coordinator no longer has to take time to walk the field marking sensitive features with flags for each field. This has added 1-3 hours of extra time for tracking and properly recording information for post-application procedures. C. The drivers now have quicker turn around times on the land application as there is no longer the issue of reapplying biosolids on already sprayed areas. They now know exactly where to start or stop the application procedure without having to wait and discuss with other drivers at the field. 5. What, if any, other impacts has the system had? Risk management and general confidence in the land application component of the program. 6. How did the system change the way business is conducted with and/or service delivered to clients? Give specific examples comparing the old way with the new 1. This system had significant changes to the way business is conducted. In the past, before the implementation of this GPS/GIS application, the drivers were limited to using a printed tax map and then colored in the areas where they applied Biosolids. Consequently, biosolids were land applied with little consideration for buffers and correct acreage (resulting in fields being overloaded and risking groundwater contamination or runoff to surface water). In addition, Technicians were persuaded by farmers to apply on land that was not authorized by DEQ to receive biosolids. With mapping, all of these challenges are now under control. 2. There was also no review of the field after application to assess proper spreading. Now with the mapping, field inspections are made with the spread map, and closure can occur with confidence that the driver applied correctly. This has provided a mechanism for the Supervisor to know when training might be needed. F: System Resources 1. What are the system’s primary hardware components? Give a brief list or description of the hardware configuration supporting the system . Trimble EZ-Guide 500 Lightbar Guidance System Trimble GeoXT 2008 with TerraSync 2. What are the system’s primary software components? Describe the primary software and, if a commercial package, any customizations required for the system. ArcGIS 9.3 – after outlining the processes, a series of small python programs were developed to speed up processing. 16 | P a g e 2012 URISA AWARD APPLICATION
  • 17. 3. What data does the system work with? List and briefly describe the database(s) Wells Roads (public & private) Power Lines Wind Mills Buildings Ravines Trees Streams Water Slope Septic Tanks Drain Fields Culvert Ditches Field Boundary Special Requests Buffers 4. What staff resources were required to implement the system? (approximate staff and consultant time as FTE’s) It was a significant undertaking to get this operational. Equipment and software needed to be purchased; our GIS Technician required some time to resolve problems in the field with recording and/or downloading and all fields required GPS mapping; all fields required mapping. Estimated FTE to become fully operational with few problems was 2.0 over the course of 1 year. 5. Comment on anything unusual about the resources used to develop your system, such as data, software, personnel and financing. Did not have an immediate buy-in by drivers, as they were not favorable of computer tracking. Did not want to deal with ‘electronic’ equipment and thought the system was going to be complex and cumbersome and waste time. After a few field applications, the drivers now are very favorable of the spread tracking and with training have found the units to be easy to use. The truck GPS units were chosen mainly for the general simplicity of the unit and the larger screen. There was also a cost issue determinant, but if needed a higher end unit could have been purchased. The EZ Guide GPS unit is a mid-level Agricultural GPS system. 17 | P a g e 2012 URISA AWARD APPLICATION
  • 18. APPENDIX A: 18 | P a g e 2012 URISA AWARD APPLICATION
  • 19. 19 | P a g e 2012 URISA AWARD APPLICATION
  • 20. APPENDIX B: 20 | P a g e 2012 URISA AWARD APPLICATION
  • 21. 21 | P a g e 2012 URISA AWARD APPLICATION
  • 22. 22 | P a g e 2012 URISA AWARD APPLICATION
  • 23. 23 | P a g e 2012 URISA AWARD APPLICATION
  • 24. APPENDIX C: 24 | P a g e 2012 URISA AWARD APPLICATION
  • 25. Soil Sampling Location Map 25 | P a g e 2012 URISA AWARD APPLICATION
  • 26. RSA (Remaining Spreadable Acres) Map 26 | P a g e 2012 URISA AWARD APPLICATION
  • 27. Spread Data Map 27 | P a g e 2012 URISA AWARD APPLICATION