UEM CONSTRUCTION SDN BHD http://www.uembuilders.com/uemc_n/
UEM Builders (Singapore) Pte Ltd UEM Builders-Ansal API Pvt Ltd CORPORATE STRUCTURE
Roads  Rail Drainage Bridges Utilities Landscaping Hospitals  Airports Townships Stadiums  Industrial Parks Residential & Commercial - Earth cutting and filling - Ground treatment - Retaining wall system Infrastructure
Year USD Million Revenue
40 years’ experience in engineering & construction 880 experienced professional staff (Engineers, Architects, QS, Accountants) USD 315 million paid up capital USD 1.3 billion total assets Machineries available for local and international projects USD 80mil worth of equipment in India, Malaysia and Qatar UEM Builder's Strengths & Resources
http://www.uembuilders.com/uemc_n/ LANDMARK PROJECTS
848 km of tolled expressway Completed in 1993 Project cost: USD 1.8 bil. Role: Concessionaire, Project Management, Construction NORTH SOUTH EXPRESSWAY
KUALA LUMPUR INTERNATIONAL AIRPORT Integrated Development Development Area 100 km 2 Development Period 7 years Gross Development Value (GDV) USD 3.6 bil  Role Project Management Construction (Satellite Building)
NATIONAL SPORTS COMPLEX 100,000 seat capacity National Stadium (outdoor stadium) 16,000 seat Putra Stadium (indoor stadium) 3,700 seat National Aquatic Centre (swimming complex) Completed in 1998 Project cost: USD 400 million Role: Concessionaire, Project Management, Construction
KUALA LUMPUR LIGHT RAIL TRANSIT Total length: 29 km (22 km elevated, 5 km underground and 2 km at-grade) First world’s longest driverless LRT system completed in 1999 Capacity: 25,000 passengers/hr/direction Project cost: USD2.04 billion   Role: Concessionaire, Project Management, Construction.
http://www.uembuilders.com/uemc_n/ COMPLETED PROJECTS
NORTH SOUTH EXPRESSWAY CENTRAL LINK Construction and O&M of 45 km of tolled expressway PENANG BRIDGE Operation and Maintenance of 13.5 km bridge NORTH SOUTH  EXPRESSWAY MALAYSIA SINGAPORE SECOND CROSSING Construction and O&M of 44 km of highways including 2 km bridge Construction and O&M of  955 km tolled Highway EXPRESSWAYS
Construction of several packages amounting to 203 km  dual two lanes tolled expressway. Involved in implementation of heavy repair works and  routine maintenance of the completed 848 km  expressway since 1994. Completed in May 1995. Project cost: USD 630 million. NORTH-SOUTH EXPRESSWAY
Construction of 45 km of tolled expressway linking NKVE to Nilai North Interchange at NSE.  Gateway to KLIA airport and Cyberjaya/Putrajaya. Involved in implementation of heavy repair works and routine maintenance of the completed 60 km expressway since 1997. Completed in December 1997. Project cost: USD 236 million. NORTH SOUTH EXPRESSWAY CENTRAL LINK
Construction of 44 km of dual two/three lane tolled expressway and 2 km of bridge linking Johor to Singapore and to Johor City & NSE.  Involved in implementation of heavy repair works and routine maintenance of the completed 44 km expressway since 1997.  Completed in December 1997. Project cost: USD 310 million.  MALAYSIA-SINGAPORE SECOND CROSSING BRIDGE
NORTH-SOUTH EXPRESSWAY- THIRD LANE WIDENING North South Expressway – Proposed Third Lane Widening and Modification for Non-Stop Through Traffic for Packages 1, 2A, 2B, 3A, 3B, 4, 5 and 5A.  Commenced:  Package 1 -July 2005 (Completed) Package 2A,2B,3A,3B & 4 –Aug  2005 (Completed) Package 5 – August 2005 (Completed) Package 5A –July 2005 (Completed) Value : USD 253 million
PENANG BRIDGE WIDENING  Construction of widening of the existing Penang Bridge.  Involvement of rejuvenation of the existing east side approach embankment foundations alongside extending the existing substructure of the main viaduct and providing longitudinal beams and construction of Uni-Directional Ramps to mainland side.  Completed on  August 2009. Project cost: USD 143 million.
COMPLETED HIGHWAYS IN INDIA
MAJOR HIGHWAYS COMPLETED IN INDIA Construction & Maintenance (for 15 years) of  Tuni - Anakapalli, NH 5, Andhra Pradesh  Length   : 59 km. Project Cost (@ EPC)  : USD 48 mil. Construction & Maintenance (for 15 years) of  Tambaram-Tindivanam,NH 45,Tamil Nadu Length   : 93 km. Project Cost  : USD 63 mil. Tumkur–Haveri-NH4, Pkg. 2,4,5-Karnataka  Length   : 200 km. Project Cost (@ EPC)  : USD 152.7 mil.
MAJOR HIGHWAYS COMPLETED IN INDIA Etawah to Sikandra-NH 2, Uttar Pradesh – Pckg.1C Length   : 72km. Project Cost  : USD 63 mil. Bhiwandi-Kalyan-Shil Phata, Maharastra Length   : 25 km. Project Cost  : USD 17 mil. Kerala State Transport Project Phase-1 Length   : 127 km. Project Cost  : USD 50 mil.
Upgrading of existing R1 Expressway Length: 6.6km dual 3-lane highway Completed: April 1998 Project cost: USD23 million MANILA-CAVITE TOLL EXPRESSWAY PKG 1, PHILIPPINES
PROJECT IN QATAR Qatar Primary Routes - Salwa Road Phase 1 Upgrading 81 km dual 4 lane highway linking Qatar-Saudi Border at Salwa to Doha Total project cost: USD 265 million. Completed: December 2008
LIGHT RAIL TRANSIT SYSTEM Construction of total 29km elevated, underground and at grade track including stations for the driverless automated Light Rail Transit. ELECTRIFIED DOUBLE TRACK  Construction of total 182km of Electrified Double Track Railway Lines between two major cities TRANSPORTATION
PUTRA LIGHT RAIL TRANSIT STATIONS, KUALA LUMPUR Completed: 1999 Value: USD 494.3 million Project involved the construction of 29 km track way for Light Rail Transit System in Kuala Lumpur involving 22 km elevated track, 5 km underground tunnel and 2 km at-grade track. Construction of 5 underground LRT stations, 17 above-ground and 2 at-grade stations throughout the LRT system. Longest driverless automated LRT in the world.  Implemented in November 1994 and completed in June 1999.
Construction of 155 bridge crossings for the 182 km electrified railway line linking Rawang to Ipoh. Project Cost: USD 436 million. 31 st  March 2007 IPOH-RAWANG ELECTRIFIED DOUBLE TRACKING
NATIONAL SPORTS COMPLEX Construction of National Stadium, aquatic centre and indoor stadium for the nation sport facilities. KUALA LUMPUR INTERNATIONAL AIRPORT (KLIA) Construction of Satellite Building and ancillary works for the Malaysia’s largest airport. BUILDINGS & FACILITIES JSNAC Construction of Johor State New Administration Centre in Johor MARDI Agriculture Centre Construction of National Stadium, aquatic centre and indoor stadium for the nation sport facilities. MINISTRY OF FINANCE II BUILDING Construction of Government Building for the Federal Government Administrative Centre in Putrajaya.  NATIONAL HEART INSTITUTE Construction of new healthcare facilities for the extension of the National Heart Institute.
NATIONAL SPORTS COMPLEX, BUKIT JALIL, KUALA LUMPUR Completed: 1998 Value: USD 286 million 100,000 capacity National Stadium (outdoor stadium), 3,700 seat National Aquatic Centre (swimming complex) and 16,000 seat Putra Stadium (indoor stadium). Implemented in January 1994 and completed in July 1998 for the XVI Commonwealth Games.
COMMONWEALTH GAMES VILLAGE, BUKIT JALIL, KUALA LUMPUR Completed: 1998 Value: USD 77.7 million Gross Floor Area: 198,774 m²  Construction of multi storey apartment blocks complete with recreational facilities. 1,500 units were built in total.
KUALA LUMPUR INTERNATIONAL AIRPORT,  SATELLITE BUILDING, SEPANG Completed: 1998 Value: USD 157 million Gross Floor Area: 148,000 m². Design and construction of the satellite building and its ancillary works as part of the Kuala Lumpur International Airport Complex. Project implementation in joint venture with international construction companies as consortium partners.
EAST MALAYSIA HOSPITALS The planning, design, construction, equipping, commissioning and maintenance of six hospitals with a combined total of 976 beds were delivered to the Ministry of Health Malaysia in stages from 2002 till 2005.  Five of the hospitals are located in the state of Sabah in East Malaysia, namely Lahad Datu, Keningau, Kuala Penyu, Pitas and Kunak. One more hospital is located in the state of Sarawak, also in East Malaysia, in Sarikei. Completed: 2005 Value: USD 256 million
Sarikei, Sarawak Completed: December 2005 Value: USD 74 million Total of 268 beds Gross Floor Area: 40,000 sq. ft EAST MALAYSIA HOSPITALS Pitas, Sabah Completed: June 2005 Value: USD 24 million Total of 76 beds Gross Floor Area: 15,284 m 2
EAST MALAYSIA HOSPITALS Kuala Penyu, Sabah Completed: May 2005 Value: USD 22 million Total of 76 beds Gross Floor Area: 15,284 m 2 Kunak, Sabah Completed: May 2005 Value: USD 24 million Total of 76 beds Gross Floor Area: 15,284 m 2
EAST MALAYSIA HOSPITALS Keningau, Sabah Completed: September 2002 Value: USD 58 million Total of 212 beds Gross Floor Area: 63,477 m 2
EAST MALAYSIA HOSPITALS Lahad Datu, Sabah Completed: January 2002 Value: USD 61 million Total of 268 beds Gross Floor Area: 68,1000 m 2
Sarikei Hospital, Malaysia (268 Beds) EAST MALAYSIA HOSPITALS Completed: December 2003 Value: USD 74 million Total of 268 beds Gross Floor Area: 40,000 sqft.
UNIVERSITY OF TECHNOLOGY PETRONAS (UTP) MOSQUE,  TRONOH, PERAK Completed: October 2005 Value: USD 7.7 million Gross Floor Area: 5,659 m² The construction and completion of this uniquely designed ‘floating’ mosque at Bandar Seri Iskandar, Perak has a capacity to accommodate 4,000 people. The enclosed main prayer area is air-conditioned and can accommodate 1,000 people. The covered prayer area, accommodating 3,000 people, which was previously ventilated naturally, has been changed into an air-conditioned system.
Commenced: 10 September 2004 Completion: 6 November 2005 Value: USD90.5 million Construction and completion of 64 units of 3-storey link home and sewerage pump, Danau Villa Link Home, Taman Desa, Kuala Lumpur. DANAU VILLA LINK HOME, TAMAN DESA, KUALA LUMPUR
MINISTRY OF FINANCE BUILDING 2, PUTRAJAYA Commenced: 4 December 2002 Completed: 30 April 2007 Value: USD 60 million Gross Floor Area: 67,108 m²  Design, construction and completion of office buildings to house agencies under the Ministry of Finance at the New Federal Government Administrative Centre in Putrajaya.  2 office blocks, 8 and 10-storey high with each housing two levels of basement car parks. Scope of works include interior design works.
CASA DESA CONDOMINIUM, KUALA LUMPUR Commenced: 11 July 2005 Completed : 31 March 2008 Value: USD 24 million Gross Floor Area: 9,794  m 2 For the 410-unit Casa Desa Condominium, the contract package consists of substructure works and superstructure works. Project involves construction of 7 blocks of condominium buildings including earthworks, bored piling and pile caps.
Project : Agriculture Exposition Centre (Phase 2) – MARDI, Serdang Commenced : 27 November 2007 Completed : 30 June 2008 Value : USD 64 million  Gross Floor Area: 25,000 m²  AGRICULTURE EXPOSITION CENTRE (PHASE 2)-MARDI, SERDANG
JOHOR STATE NEW ADMINISTRATIVE CENTRE (JSNAC),  PHASE 1, JOHOR   Commenced: November 2005 Completed: August 2008 Value: USD 62 million  The development of the JSNAC on a 320-acre site located at Bandar Nusajaya, 25 km from Johor Bahru, Johor is divided into three precincts comprising the Government precinct (273 acres), VIP residences and Istana reserve (17 acres) and government housing reserve (30 acres). Phase 1 of this development is divided into five packages where three packages, has been awarded. Project involves the construction of office buildings for the new state administrative centre in Johor.
STATE DEPARTMENT COMPLEX (JSNAC), NUSAJAYA   Commenced: November 2005 Completed: February 2009 Value: USD 63 million
UEM GROUP NEW CORPORATE OFFICE, KUALA LUMPUR Commenced: 1 June 2005 Completed: December 2008 Value: USD 45 million  Gross Floor Area: 35,000 m² This project involves the design and construction of a 29-storey office building with an 8-storey annex building at KL Sentral. The scope of works involves interior design.
PLUS HEADQUARTERS, SUBANG Development of one block of 10-storey office tower at Subang Toll, Petaling Jaya, Selangor Darul Ehsan Commenced : 15 January 2007 Completed :  December 2008 Value : USD 29 million
NATIONAL HEART INSTITUTE, KUALA LUMPUR Commenced: 5 September 2005 Completed: March 2009 Value: USD 64.6 million Gross Floor Area: 32,840 m ² Design, construction, supply and commissioning and maintenance of new healthcare facilities for the extension of the National Heart Institute. This project is divided into four phases and works entail the renovating and refurbishing of existing facilities.
COLLEGE OF TECHNOLOGY (COT), DOHA, QATAR   Construction of 21 multidisciplinary buildings comprising classrooms, workshops/labs, cafeterias, recreation facilities, auditorium and administration buildings with a total area of 63,000 m 2  and external infrastructure for campus area of 300,000 m 2 . Project cost: USD 100 million. Completed: October 2006
Project : 548 Units (5 Blocks) Apartment Using Industrialised Building System (IBS) Method Commenced : September 2006 Exp. Completion : March 2008 Value : USD 39 million Gross Floor Area: 60,500 m² GOVERNMENT APARTMENTS, PUTRAJAYA
Proposed Basement Structural Works for Universal Studio  Commenced: March 2008 Completed: July 2008 Value: USD 4.5 million Gross Floor Area: 65,800 m²  RESORTS WORLD AT SENTOSA, SINGAPORE MC04-F1
http://www.uembuilders.com/uemc_n/ ON-GOING PROJECTS
BANK KERJASAMA RAKYAT HEADQUARTERS, KUALA LUMPUR Design, construction and completion of 2 office towers (32 and 38-storeys), 1 block of 8-storey annex comprises of car parks and 1 unit PPU Commenced : 1 June 2009 Exp. Completion : December 2011 Value : USD 26 million Gross Floor Area: 188,000 m²
PENANG SECOND BRIDGE Project : Design, Construction and Completion of the Penang Second Bridge. Package 2 : Super-structure Works of Approach Spans.  Overall length - 24 km Length over water - 17 km,  Main span : Length - 250 meters Height clearance (above water) – 30 meters  Number of vehicle lanes – 2 + 1 for motorcycles (each direction)  Commenced : June 2009 Exp. Completion : March 2013 Value : USD 473 million
PHG’-S’GOR  RAW WATER TRANSFER PROJECT Pahang - Selangor Raw Water Transfer Project Lot 1-1, Water Transfers Tunnel & Related Works (2,260 Mld.) Commenced : June 2009 Exp. Completion : May 2014 Value : USD 400 million   Length: 44.6km ; Diameter: 5.2m
1,765-acre Sushant Golf City Project in Lucknow, Uttar Pradesh Project : Construction of various building and engineering works at Sushant Golf City, Lucknow U.P. India. Commenced : 1 April 2008 Exp. Completion : February 2012 Value : USD 497 million   Total Development Area : 1,765 acre
Project : 4000 units Housing Project for the National Housing Scheme, Brunei.  Commenced : 2 February 2010 Exp. Completion : February 2014 Value : USD 290 million Total Development Area: 309 hectares 4000 UNITS HOUSING PROJECT, BRUNEI
NEW LCC TERMINAL AT KLIA, SEPANG Project : Design, Construction and  Completion, Testing, Commissioning and Maintenance of Main Terminal Building, Satellite Building, Sky Bridge and Piers. Commenced : 16 August 2010 Exp. Completion : April 2012 Value : USD 316 million
Thank You This document is the property of United Engineers (Malaysia) Berhad. Neither the whole nor any part of this document may be reproduced, stored or transmitted in any forms or by any means without written permission of United Engineers (Malaysia) Berhad. This document is designed to provide information in relation to the subject matter covered for this presentation and should not be used for any other purpose. Whilst every care has been taken in its preparation, no person should draw conclusions purely on the basis of the material contained herein. If assistance is required, reference should be made to the relevant professional of United Engineers (Malaysia) Berhad.

Uemc apr 19_2011

  • 1.
    UEM CONSTRUCTION SDNBHD http://www.uembuilders.com/uemc_n/
  • 2.
    UEM Builders (Singapore)Pte Ltd UEM Builders-Ansal API Pvt Ltd CORPORATE STRUCTURE
  • 3.
    Roads RailDrainage Bridges Utilities Landscaping Hospitals Airports Townships Stadiums Industrial Parks Residential & Commercial - Earth cutting and filling - Ground treatment - Retaining wall system Infrastructure
  • 4.
  • 5.
    40 years’ experiencein engineering & construction 880 experienced professional staff (Engineers, Architects, QS, Accountants) USD 315 million paid up capital USD 1.3 billion total assets Machineries available for local and international projects USD 80mil worth of equipment in India, Malaysia and Qatar UEM Builder's Strengths & Resources
  • 6.
  • 7.
    848 km oftolled expressway Completed in 1993 Project cost: USD 1.8 bil. Role: Concessionaire, Project Management, Construction NORTH SOUTH EXPRESSWAY
  • 8.
    KUALA LUMPUR INTERNATIONALAIRPORT Integrated Development Development Area 100 km 2 Development Period 7 years Gross Development Value (GDV) USD 3.6 bil Role Project Management Construction (Satellite Building)
  • 9.
    NATIONAL SPORTS COMPLEX100,000 seat capacity National Stadium (outdoor stadium) 16,000 seat Putra Stadium (indoor stadium) 3,700 seat National Aquatic Centre (swimming complex) Completed in 1998 Project cost: USD 400 million Role: Concessionaire, Project Management, Construction
  • 10.
    KUALA LUMPUR LIGHTRAIL TRANSIT Total length: 29 km (22 km elevated, 5 km underground and 2 km at-grade) First world’s longest driverless LRT system completed in 1999 Capacity: 25,000 passengers/hr/direction Project cost: USD2.04 billion Role: Concessionaire, Project Management, Construction.
  • 11.
  • 12.
    NORTH SOUTH EXPRESSWAYCENTRAL LINK Construction and O&M of 45 km of tolled expressway PENANG BRIDGE Operation and Maintenance of 13.5 km bridge NORTH SOUTH EXPRESSWAY MALAYSIA SINGAPORE SECOND CROSSING Construction and O&M of 44 km of highways including 2 km bridge Construction and O&M of 955 km tolled Highway EXPRESSWAYS
  • 13.
    Construction of severalpackages amounting to 203 km dual two lanes tolled expressway. Involved in implementation of heavy repair works and routine maintenance of the completed 848 km expressway since 1994. Completed in May 1995. Project cost: USD 630 million. NORTH-SOUTH EXPRESSWAY
  • 14.
    Construction of 45km of tolled expressway linking NKVE to Nilai North Interchange at NSE. Gateway to KLIA airport and Cyberjaya/Putrajaya. Involved in implementation of heavy repair works and routine maintenance of the completed 60 km expressway since 1997. Completed in December 1997. Project cost: USD 236 million. NORTH SOUTH EXPRESSWAY CENTRAL LINK
  • 15.
    Construction of 44km of dual two/three lane tolled expressway and 2 km of bridge linking Johor to Singapore and to Johor City & NSE. Involved in implementation of heavy repair works and routine maintenance of the completed 44 km expressway since 1997. Completed in December 1997. Project cost: USD 310 million. MALAYSIA-SINGAPORE SECOND CROSSING BRIDGE
  • 16.
    NORTH-SOUTH EXPRESSWAY- THIRDLANE WIDENING North South Expressway – Proposed Third Lane Widening and Modification for Non-Stop Through Traffic for Packages 1, 2A, 2B, 3A, 3B, 4, 5 and 5A. Commenced: Package 1 -July 2005 (Completed) Package 2A,2B,3A,3B & 4 –Aug 2005 (Completed) Package 5 – August 2005 (Completed) Package 5A –July 2005 (Completed) Value : USD 253 million
  • 17.
    PENANG BRIDGE WIDENING Construction of widening of the existing Penang Bridge. Involvement of rejuvenation of the existing east side approach embankment foundations alongside extending the existing substructure of the main viaduct and providing longitudinal beams and construction of Uni-Directional Ramps to mainland side. Completed on August 2009. Project cost: USD 143 million.
  • 18.
  • 19.
    MAJOR HIGHWAYS COMPLETEDIN INDIA Construction & Maintenance (for 15 years) of Tuni - Anakapalli, NH 5, Andhra Pradesh Length : 59 km. Project Cost (@ EPC) : USD 48 mil. Construction & Maintenance (for 15 years) of Tambaram-Tindivanam,NH 45,Tamil Nadu Length : 93 km. Project Cost : USD 63 mil. Tumkur–Haveri-NH4, Pkg. 2,4,5-Karnataka Length : 200 km. Project Cost (@ EPC) : USD 152.7 mil.
  • 20.
    MAJOR HIGHWAYS COMPLETEDIN INDIA Etawah to Sikandra-NH 2, Uttar Pradesh – Pckg.1C Length : 72km. Project Cost : USD 63 mil. Bhiwandi-Kalyan-Shil Phata, Maharastra Length : 25 km. Project Cost : USD 17 mil. Kerala State Transport Project Phase-1 Length : 127 km. Project Cost : USD 50 mil.
  • 21.
    Upgrading of existingR1 Expressway Length: 6.6km dual 3-lane highway Completed: April 1998 Project cost: USD23 million MANILA-CAVITE TOLL EXPRESSWAY PKG 1, PHILIPPINES
  • 22.
    PROJECT IN QATARQatar Primary Routes - Salwa Road Phase 1 Upgrading 81 km dual 4 lane highway linking Qatar-Saudi Border at Salwa to Doha Total project cost: USD 265 million. Completed: December 2008
  • 23.
    LIGHT RAIL TRANSITSYSTEM Construction of total 29km elevated, underground and at grade track including stations for the driverless automated Light Rail Transit. ELECTRIFIED DOUBLE TRACK Construction of total 182km of Electrified Double Track Railway Lines between two major cities TRANSPORTATION
  • 24.
    PUTRA LIGHT RAILTRANSIT STATIONS, KUALA LUMPUR Completed: 1999 Value: USD 494.3 million Project involved the construction of 29 km track way for Light Rail Transit System in Kuala Lumpur involving 22 km elevated track, 5 km underground tunnel and 2 km at-grade track. Construction of 5 underground LRT stations, 17 above-ground and 2 at-grade stations throughout the LRT system. Longest driverless automated LRT in the world. Implemented in November 1994 and completed in June 1999.
  • 25.
    Construction of 155bridge crossings for the 182 km electrified railway line linking Rawang to Ipoh. Project Cost: USD 436 million. 31 st March 2007 IPOH-RAWANG ELECTRIFIED DOUBLE TRACKING
  • 26.
    NATIONAL SPORTS COMPLEXConstruction of National Stadium, aquatic centre and indoor stadium for the nation sport facilities. KUALA LUMPUR INTERNATIONAL AIRPORT (KLIA) Construction of Satellite Building and ancillary works for the Malaysia’s largest airport. BUILDINGS & FACILITIES JSNAC Construction of Johor State New Administration Centre in Johor MARDI Agriculture Centre Construction of National Stadium, aquatic centre and indoor stadium for the nation sport facilities. MINISTRY OF FINANCE II BUILDING Construction of Government Building for the Federal Government Administrative Centre in Putrajaya. NATIONAL HEART INSTITUTE Construction of new healthcare facilities for the extension of the National Heart Institute.
  • 27.
    NATIONAL SPORTS COMPLEX,BUKIT JALIL, KUALA LUMPUR Completed: 1998 Value: USD 286 million 100,000 capacity National Stadium (outdoor stadium), 3,700 seat National Aquatic Centre (swimming complex) and 16,000 seat Putra Stadium (indoor stadium). Implemented in January 1994 and completed in July 1998 for the XVI Commonwealth Games.
  • 28.
    COMMONWEALTH GAMES VILLAGE,BUKIT JALIL, KUALA LUMPUR Completed: 1998 Value: USD 77.7 million Gross Floor Area: 198,774 m² Construction of multi storey apartment blocks complete with recreational facilities. 1,500 units were built in total.
  • 29.
    KUALA LUMPUR INTERNATIONALAIRPORT, SATELLITE BUILDING, SEPANG Completed: 1998 Value: USD 157 million Gross Floor Area: 148,000 m². Design and construction of the satellite building and its ancillary works as part of the Kuala Lumpur International Airport Complex. Project implementation in joint venture with international construction companies as consortium partners.
  • 30.
    EAST MALAYSIA HOSPITALSThe planning, design, construction, equipping, commissioning and maintenance of six hospitals with a combined total of 976 beds were delivered to the Ministry of Health Malaysia in stages from 2002 till 2005. Five of the hospitals are located in the state of Sabah in East Malaysia, namely Lahad Datu, Keningau, Kuala Penyu, Pitas and Kunak. One more hospital is located in the state of Sarawak, also in East Malaysia, in Sarikei. Completed: 2005 Value: USD 256 million
  • 31.
    Sarikei, Sarawak Completed:December 2005 Value: USD 74 million Total of 268 beds Gross Floor Area: 40,000 sq. ft EAST MALAYSIA HOSPITALS Pitas, Sabah Completed: June 2005 Value: USD 24 million Total of 76 beds Gross Floor Area: 15,284 m 2
  • 32.
    EAST MALAYSIA HOSPITALSKuala Penyu, Sabah Completed: May 2005 Value: USD 22 million Total of 76 beds Gross Floor Area: 15,284 m 2 Kunak, Sabah Completed: May 2005 Value: USD 24 million Total of 76 beds Gross Floor Area: 15,284 m 2
  • 33.
    EAST MALAYSIA HOSPITALSKeningau, Sabah Completed: September 2002 Value: USD 58 million Total of 212 beds Gross Floor Area: 63,477 m 2
  • 34.
    EAST MALAYSIA HOSPITALSLahad Datu, Sabah Completed: January 2002 Value: USD 61 million Total of 268 beds Gross Floor Area: 68,1000 m 2
  • 35.
    Sarikei Hospital, Malaysia(268 Beds) EAST MALAYSIA HOSPITALS Completed: December 2003 Value: USD 74 million Total of 268 beds Gross Floor Area: 40,000 sqft.
  • 36.
    UNIVERSITY OF TECHNOLOGYPETRONAS (UTP) MOSQUE, TRONOH, PERAK Completed: October 2005 Value: USD 7.7 million Gross Floor Area: 5,659 m² The construction and completion of this uniquely designed ‘floating’ mosque at Bandar Seri Iskandar, Perak has a capacity to accommodate 4,000 people. The enclosed main prayer area is air-conditioned and can accommodate 1,000 people. The covered prayer area, accommodating 3,000 people, which was previously ventilated naturally, has been changed into an air-conditioned system.
  • 37.
    Commenced: 10 September2004 Completion: 6 November 2005 Value: USD90.5 million Construction and completion of 64 units of 3-storey link home and sewerage pump, Danau Villa Link Home, Taman Desa, Kuala Lumpur. DANAU VILLA LINK HOME, TAMAN DESA, KUALA LUMPUR
  • 38.
    MINISTRY OF FINANCEBUILDING 2, PUTRAJAYA Commenced: 4 December 2002 Completed: 30 April 2007 Value: USD 60 million Gross Floor Area: 67,108 m² Design, construction and completion of office buildings to house agencies under the Ministry of Finance at the New Federal Government Administrative Centre in Putrajaya. 2 office blocks, 8 and 10-storey high with each housing two levels of basement car parks. Scope of works include interior design works.
  • 39.
    CASA DESA CONDOMINIUM,KUALA LUMPUR Commenced: 11 July 2005 Completed : 31 March 2008 Value: USD 24 million Gross Floor Area: 9,794 m 2 For the 410-unit Casa Desa Condominium, the contract package consists of substructure works and superstructure works. Project involves construction of 7 blocks of condominium buildings including earthworks, bored piling and pile caps.
  • 40.
    Project : AgricultureExposition Centre (Phase 2) – MARDI, Serdang Commenced : 27 November 2007 Completed : 30 June 2008 Value : USD 64 million Gross Floor Area: 25,000 m² AGRICULTURE EXPOSITION CENTRE (PHASE 2)-MARDI, SERDANG
  • 41.
    JOHOR STATE NEWADMINISTRATIVE CENTRE (JSNAC), PHASE 1, JOHOR Commenced: November 2005 Completed: August 2008 Value: USD 62 million The development of the JSNAC on a 320-acre site located at Bandar Nusajaya, 25 km from Johor Bahru, Johor is divided into three precincts comprising the Government precinct (273 acres), VIP residences and Istana reserve (17 acres) and government housing reserve (30 acres). Phase 1 of this development is divided into five packages where three packages, has been awarded. Project involves the construction of office buildings for the new state administrative centre in Johor.
  • 42.
    STATE DEPARTMENT COMPLEX(JSNAC), NUSAJAYA Commenced: November 2005 Completed: February 2009 Value: USD 63 million
  • 43.
    UEM GROUP NEWCORPORATE OFFICE, KUALA LUMPUR Commenced: 1 June 2005 Completed: December 2008 Value: USD 45 million Gross Floor Area: 35,000 m² This project involves the design and construction of a 29-storey office building with an 8-storey annex building at KL Sentral. The scope of works involves interior design.
  • 44.
    PLUS HEADQUARTERS, SUBANGDevelopment of one block of 10-storey office tower at Subang Toll, Petaling Jaya, Selangor Darul Ehsan Commenced : 15 January 2007 Completed : December 2008 Value : USD 29 million
  • 45.
    NATIONAL HEART INSTITUTE,KUALA LUMPUR Commenced: 5 September 2005 Completed: March 2009 Value: USD 64.6 million Gross Floor Area: 32,840 m ² Design, construction, supply and commissioning and maintenance of new healthcare facilities for the extension of the National Heart Institute. This project is divided into four phases and works entail the renovating and refurbishing of existing facilities.
  • 46.
    COLLEGE OF TECHNOLOGY(COT), DOHA, QATAR Construction of 21 multidisciplinary buildings comprising classrooms, workshops/labs, cafeterias, recreation facilities, auditorium and administration buildings with a total area of 63,000 m 2 and external infrastructure for campus area of 300,000 m 2 . Project cost: USD 100 million. Completed: October 2006
  • 47.
    Project : 548Units (5 Blocks) Apartment Using Industrialised Building System (IBS) Method Commenced : September 2006 Exp. Completion : March 2008 Value : USD 39 million Gross Floor Area: 60,500 m² GOVERNMENT APARTMENTS, PUTRAJAYA
  • 48.
    Proposed Basement StructuralWorks for Universal Studio Commenced: March 2008 Completed: July 2008 Value: USD 4.5 million Gross Floor Area: 65,800 m² RESORTS WORLD AT SENTOSA, SINGAPORE MC04-F1
  • 49.
  • 50.
    BANK KERJASAMA RAKYATHEADQUARTERS, KUALA LUMPUR Design, construction and completion of 2 office towers (32 and 38-storeys), 1 block of 8-storey annex comprises of car parks and 1 unit PPU Commenced : 1 June 2009 Exp. Completion : December 2011 Value : USD 26 million Gross Floor Area: 188,000 m²
  • 51.
    PENANG SECOND BRIDGEProject : Design, Construction and Completion of the Penang Second Bridge. Package 2 : Super-structure Works of Approach Spans. Overall length - 24 km Length over water - 17 km, Main span : Length - 250 meters Height clearance (above water) – 30 meters Number of vehicle lanes – 2 + 1 for motorcycles (each direction) Commenced : June 2009 Exp. Completion : March 2013 Value : USD 473 million
  • 52.
    PHG’-S’GOR RAWWATER TRANSFER PROJECT Pahang - Selangor Raw Water Transfer Project Lot 1-1, Water Transfers Tunnel & Related Works (2,260 Mld.) Commenced : June 2009 Exp. Completion : May 2014 Value : USD 400 million Length: 44.6km ; Diameter: 5.2m
  • 53.
    1,765-acre Sushant GolfCity Project in Lucknow, Uttar Pradesh Project : Construction of various building and engineering works at Sushant Golf City, Lucknow U.P. India. Commenced : 1 April 2008 Exp. Completion : February 2012 Value : USD 497 million Total Development Area : 1,765 acre
  • 54.
    Project : 4000units Housing Project for the National Housing Scheme, Brunei. Commenced : 2 February 2010 Exp. Completion : February 2014 Value : USD 290 million Total Development Area: 309 hectares 4000 UNITS HOUSING PROJECT, BRUNEI
  • 55.
    NEW LCC TERMINALAT KLIA, SEPANG Project : Design, Construction and Completion, Testing, Commissioning and Maintenance of Main Terminal Building, Satellite Building, Sky Bridge and Piers. Commenced : 16 August 2010 Exp. Completion : April 2012 Value : USD 316 million
  • 56.
    Thank You Thisdocument is the property of United Engineers (Malaysia) Berhad. Neither the whole nor any part of this document may be reproduced, stored or transmitted in any forms or by any means without written permission of United Engineers (Malaysia) Berhad. This document is designed to provide information in relation to the subject matter covered for this presentation and should not be used for any other purpose. Whilst every care has been taken in its preparation, no person should draw conclusions purely on the basis of the material contained herein. If assistance is required, reference should be made to the relevant professional of United Engineers (Malaysia) Berhad.