The document outlines the process for removing and upgrading system boards from servers. It involves:
1. Twitter technicians removing 20-40 servers from racks and handing them off to onsite technicians daily.
2. Technicians removing the system boards from the server chassis, packing them for shipment, and a carrier picking them up for rework to upgrade capacitors.
3. Once reworked, the system boards are shipped back and reinstalled into the server chassis by technicians. The servers then undergo power testing and are returned to Twitter.
2. Overview
Remove system boards together with all
internal components
Send boxed board offsite for rework.
Reinstall system boards into chassis upon
return.
Daily Volumes 20 or 40
3. Work Stream Overview
1. Twitter removes 20 to 40 servers from
racks and hands off to Onsight technician.
2. Technicians removes system boards from
server chassis.
3. Technicians pack system boards for
shipment.
4. Carrier pick up from Twitter arrives at
Data Center to exchange motherboards