Business Proposal
Challenge 3: Bank of America
University Technology Challenge 2015
Lancaster University
25/11/15
Daniel Abreu, Cyprian Brytan, Dan Lu, Bartek Mika, Dominika Stylinska
Challenge 3: Bank Of America Lancaster University
Page | 1
TABLE OF CONTENTS
Executive Summary................................................................................................................................................3
Introduction To The Project...............................................................................................................................4
The Design Brief......................................................................................................................................................5
Problems to Address ........................................................................................................................................5
Requirements .......................................................................................................................................................5
Features and Design..............................................................................................................................................6
Main screen......................................................................................................................................................6
Menu screen ....................................................................................................................................................6
My events..........................................................................................................................................................7
Event search.....................................................................................................................................................7
View Profile.......................................................................................................................................................8
Friends ................................................................................................................................................................8
Leader board....................................................................................................................................................8
Achievement.....................................................................................................................................................9
Event Page........................................................................................................................................................9
Settings...............................................................................................................................................................9
Notification screen..................................................................................................................................... 10
Request system............................................................................................................................................ 10
Technology.............................................................................................................................................................. 11
Front-End Development............................................................................................................................... 11
System Architecture ....................................................................................................................................... 11
Example of Use............................................................................................................................................ 13
Delivery Schedule................................................................................................................................................. 14
Agile Methodology......................................................................................................................................... 14
Planning............................................................................................................................................................... 15
Task Breakdown............................................................................................................................................... 16
Challenge 3: Bank Of America Lancaster University
Page | 2
Execution............................................................................................................................................................. 17
Review and Retrospective............................................................................................................................ 17
Post Implementation...................................................................................................................................... 18
Implementation Plan................................................................................................................................. 19
Post Implementation Plan....................................................................................................................... 21
Project Teams ........................................................................................................................................................ 22
Cost Analysis.......................................................................................................................................................... 23
RAIDS Analysis....................................................................................................................................................... 25
Risks....................................................................................................................................................................... 25
Assumptions ...................................................................................................................................................... 26
Technical......................................................................................................................................................... 26
Functional....................................................................................................................................................... 26
Issues..................................................................................................................................................................... 26
Dependencies.................................................................................................................................................... 26
Challenge 3: Bank Of America Lancaster University
Page | 3
EXECUTIVE SUMMARY
Bank of America Merrill Lynch has set a goal of conducting two million hours of volunteer work
all across the globe in a push in favour of cooperate responsibility and sustainability. Currently
employees keep track of their volunteer hours through a web-interface located within the internal
network, and it has problems of network restrictions, complexity of use, non-location specific
events. This proposal aims to show the new design of the app, technology used in the app, and
plan and estimate of the project.
Based on the requirements of the app, design of the interfaces (e.g. Main Screen) and relevant
functions are provided along with technology used in the app design and dataflow analysis.
In delivery schedule, by using Agile methodology, 4 sprints (each takes 2 weeks) will be
conducted and the whole project will take 2 months. Each sprint includes planning, execution,
review and retrospective process.
Considering the timeline, roles in Agile, location and man rates, a delivery team and a
maintenance team will conduct the project. Besides, a cost analysis is provided in the proposal,
taking into consideration of employee salaries, cost of servers, marketing cost, contingency cost
and iOS publishing fees.
RAIDS analysis identifies risks and mitigation, general assumptions along with technology and
employee assumptions, key issues and dependencies.
Challenge 3: Bank Of America Lancaster University
Page | 4
INTRODUCTION TO THE PROJECT
Guided by principles of community betterment and corporate responsibility, Bank of America
Merrill Lynch has been incentivising its employees to do volunteer work for various causes. The
benefits of this practice can be seen in the well-being of the community but also in its employees
who are able to have their personal passions supported by the company.
With all this in mind Bank of America Merrill Lynch has set a goal of conducting two million hours
of volunteer work all across the globe.
Employees keep track of their volunteer hours through a web-interface located within the Bank
of America Merrill Lynch network. Whilst functionally adequate this solution does have its
downfalls, primarily due to the interface being located within the bank’s secure network, many
employees cannot access their profiles without being connected to an internal network, usually
their office. This is a difficulty as it means employees cannot find volunteering options or log their
hours unless they’re in their office, which is not the ideal time for this information.
Another issue with the system is the over complexity and impracticality of its use, and an overhaul
with a focus on automation and simplicity would be well regarded.
The project is therefore to implement a new way for employees to track their hours and sign up
for volunteering opportunities. The predefined medium is an application that can run on
employees’ smart devices and allows employees to access the volunteering information without
local network restrictions.
Challenge 3: Bank Of America Lancaster University
Page | 5
THE DESIGN BRIEF
Problems to Address
1. Events are not location-specific
2. Logging employees’ hours needs to be done on Bank’s internal central network
3. Employees forget to log their hours (or postpone it because it’s cumbersome)
Requirements
1. Easy to install
2. Encourage more sign-ups
3. Needs to work on iOS, Android and Windows 10
4. Include some sort of location service (both automatic and manual)
5. Check miles walked, laps swam etc.
6. Alerts for upcoming events
7. Method to sign-up for events
8. Event availability (limited number of people)
9. Notifications and reminders
10. Sense of progress
11. Consistent with Bank of America branding
12. Allow users to choose switch alerting on/off and location track
13. Gather information from internal website, and data collection will be uploaded to
internal website (no need to be real time)
Challenge 3: Bank Of America Lancaster University
Page | 6
FEATURES AND DESIGN
Main screen is the one that
appears while opening the
application. It contains information
about the hours remaining to
achieve the goal and upcoming
events. It also allows users to access
the main menu, settings and
notifications.
The three progress trackers are
designed to incentivise more
volunteering. They track personal
hours against a personally set goal,
an accumulative hour for an
employee’s team, and finally the
corporate assigned goal of the
year, currently assigned at two
million hours.
Menu screen allows users to
switch between different screens.
Easy navigation throughout the
app is important. It will be
universally present from a single
swipe in from the left edge of the
screen.
Challenge 3: Bank Of America Lancaster University
Page | 7
My events screen shows
upcoming events as well as the
ones from the past. The user can
tap on each of them to reveal more
information such as availability,
date, location, capacity and add
alerts.
Event search screen allows users
to search and sign up for a specific
event. Additionally, it allows users
to invite other people to take part
in the event. There are two ways in
which users can search for the
events:
1. Search by location - app
uses GPS to triangulate
user’s location and then
displays nearby events.
2. Advanced search - users
can search for an event
based on specific criteria
(e.g. location, length, event
type, date).
Challenge 3: Bank Of America Lancaster University
Page | 8
View Profile each person’s profile
shows events they have
participated in, achievements and
basic information. For privacy
reasons, an employee can always
choose to keep their event
history/achievements/hours
private.
Friends screen allows users to look
at other people’s profiles, invite
them for events and search for new
friends. This social feature could
encourage employees to take part
in more events.
Leader board shows current
leaders as well as the user’s
position. Instead of sorting the
users based on the number of
hours they did, we created a simple
point system: current score = 2 x
hours + achievement points. The
aim of this feature is to promote
friendly competition within the
bank.
Challenge 3: Bank Of America Lancaster University
Page | 9
Achievement screen shows user’s
current achievements. The aim of
the achievement system is to
incentivise employees to volunteer
more often. If this feature is well
received, there would be abilities to
add new achievements to keep the
system growing. The system could
also allow timed events to appear,
where employees would have a
certain number of weeks to try to
unlock them, which opens up
possibilities for some themed
events nearing annual holidays or
corporate events.
Event Page is designed to give all
the information needed about an
event in a simple presentation.
Notable additions include event
capacity and a space for charities to
add small descriptions for their
events.
Settings allow users to change
privacy, location and alert
preferences. This would also allow
for the setting of personal hour
goals.
Challenge 3: Bank Of America Lancaster University
Page | 10
Notification screen is accessible
from the main menu allowing users
to check current notifications.
There are a few notification types:
1. Event invite: invitation to
participate in an event from
other users.
2. Event reminder: notification
that reminds about a
certain event. It allows users
to confirm the attendance
or cancel the event. If users
tap on ‘Confirm’, the hours
of an event are set to be
recorded.
3. Friend request.
Request system is another
important feature of the
notification system. To avoid an
even larger income of emails or
notifications, if an employee asks
their manager for permission to
miss some hours to do volunteer
work, their manager will not receive
a push notification. Instead, a
simple badge counter will show a
number near the app’s icon on their
main screen. Managers will have
access to a request approval page
where they can answer request in a
non-invasive method.
Challenge 3: Bank Of America Lancaster University
Page | 11
TECHNOLOGY
Front-End Development
Regarding front-end, the application has to work on iOS, Android and Windows devices. That
means developing three applications at the same time which will require a larger scrum team
(See Project Teams page 21).
It is important to note that this project assumes that the smartphones are up to date. Some older
versions (e.g. iOS 6 or Android Ice Cream Sandwich) may not be supported due to device
hardware limitations. (See RAIDS analysis page 24 )
The app will be developed simultaneously for all platforms so that it can be released for all devices
at the same time. Prior to the release of an application, a beta version will be released for a
calculated amount of employees. This will help in the gathering of feedback and making final
corrections before releasing the app to all Bank of America employees. The final version of the
app is going to be uploaded onto the Apple AppStore, Google Play and Windows Marketplace
to simplify the installation process.
It is also important to be able to ensure longevity as the app would be futile if unusable in a year’s
time. To guarantee longevity, the project will be developed on three different languages for each
operating system, as follows;
1. Android - Java,
2. iOS - Swift,
3. Windows Mobile - C++.
By choosing three different languages for each platform we can guarantee a longer longevity for
the app on each ecosystem. That is because platform updates do not affect native languages, or
in other words, the inevitable phone upgrades will not change the way the app functions.
System Architecture
Besides the technology used for an app design, dataflow between the app, internal servers and
external servers is shown below.
Challenge 3: Bank Of America Lancaster University
Page | 12
Although it might be more time consuming and costly, an external server, which is physically
separate from the internal one, will be used to place the application and all the new volunteering-
related features. Currently, the volunteering data is kept on an internal Bank of America server
that also contains confidential information. An external server would act as a intermediate
between the data on the internal servers and the employees smartphone. This extra layer would
allow for limited access to the internal servers minimizing security risks. The phone itself will not
be able to connect directly to the internal server. Instead, it will be connected with an external
one that will then establish a secure connection to retrieve volunteering data.
In essence, the app will be able to access the data in a real time as it is connected to the external.
However, data collected would be uploaded periodically to reduce traffic on the internal server.
Only booking data will be uploaded in a real time in order to avoid double booking.
In order to provide a sufficient level of security, the following technologies will be used:
 Internal Server - External server connection — VPN tunnel
 External Server - Client — SSL over HTTP connection
 Confidential data encryption — SHA-2
A VPN tunnel to link the external server with the internal one will provide a secure and permanent
connection. It enables sending and receiving the encrypted packets between two servers. The
external server will have limited access to the internal, allowing only to read/write the
volunteering data.
Client - External Server will be connected with SSL HTTP protocol, as it does not require a
complicated configuration on a client side. This differs from the VPN tunnel as it creates only a
short term session that allows a client to send and retrieve the data from the server.
The confidential data such as users’ credentials will be encrypted on an external server using
SHA-2 algorithm to provide an additional layer of security. This is a reasonable choice as the
algorithms are frequently used for this kind of application. Furthermore, the secure cryptographic
hashing algorithm doesn’t strain the servers as it has a rapid response time.
Challenge 3: Bank Of America Lancaster University
Page | 13
For the security purposes, each employee will have to create a new user account instead of using
the one used on internal website however, the volunteering data will be synced automatically on
both accounts. To ensure that the server protocols remain up-to-date a maintenance team has
been accounted for in the budget. (See Cost Analysis page 22)
Example of Use
1. User opens app.
a. A GET request is sent to the external server to update the data such as goal
progress etc.(also occurs when app is running in the background)
b. The external server gets the request, verifies it and then sends the SQL query to
an internal server to get the required data.
c. The required data stored in an external server along with the data obtained from
an internal one is passed to an app.
d. Information is updated.
2. User opens ‘map search’ option, and taps/clicks on an event displayed on the map.
a. App sends another GET request to retrieve information displayed on the event
page. General event information such as available places, name of an event, and
capacity are retrieved from an internal server. App-specific data such as event
photo and a detailed description are retrieved from an external server.
b. Data is passed to the client.
3. User taps on a ‘sign up’ button.
a. A POST request containing a booking information is sent to an external server
The external server, after validation of a POST request, sends the ‘UPDATE’ SQL
Query to the Internal one.
b. ‘Available spaces’ field is instantly decremented.
Challenge 3: Bank Of America Lancaster University
Page | 14
DELIVERY SCHEDULE
Agile Methodology
Compared to the traditional waterfall (table shown below), Agile methodology has benefits of
speed-to-market (supporting early and regular release), flexibility (changes in requirements are
expected), business engagement and customer satisfaction (active involvement of user
representative/ product owner). Therefore, Agile methodology, especially Scrum, will be
conducted in the delivery of the project.
Criteria Waterfall Agile
Length Typically 9-12 months Typically 2-3 months
Project size Hard to tailor down to small
projects
Well matched to small products and teams
Requirements Requirements defined upfront Flexible requirements
Clients involvement Does not involve clients Clients are highly involved in the
development of the project
Users interaction Only when gathering
requirements and user testing
Interact with users with constant meet ups
Testing Separate phase at the end of
the project
Fully-automated, continuous testing at
both functional and unit level
Cost of change High Low
With the assumptions that each Sprint takes 2 weeks to complete, the delivery timeline is shown
below.
Challenge 3: Bank Of America Lancaster University
Page | 15
Planning
At the beginning of each Sprint, planning is the first phase (shown below).
The Product Owner is responsible to prioritise the requirements and put each Product Backlog
Item (usually in User Story form) in Product Backlog. Then, the Product Owner and the team will
hold a Sprint Planning Meeting to negotiate which Product Backlog Items they will attempt to
convert to working product during each Sprint. While the Product Owner is responsible to declare
which items are important, the team is responsible for selecting the amount of work they feel
they can implement without accruing technical debt. Towards the end of the Sprint Planning
Meeting, the team breaks the selected Product Backlog Items into Sprint Backlog and related
Tasks.
According to the requirements of the application, Product Backlog, Sprint Backlog and Sprint
Tasks for each Sprint are shown below.
Challenge 3: Bank Of America Lancaster University
Page | 16
Task Breakdown
Product Backlog
Sprint
Number Sprint Task
High Priority
Finding a volunteering opportunity for
themselves in the upcoming weeks. 1
Search opportunities by key words.
Search opportunities by tags.
Filter opportunities by distance to user.
Search opportunities by location.
Search opportunities by charity.
Search opportunities by service work type.
After volunteering, an employee wants to
see how many hours they have done in
total and see how close they are to a set
goal.
2
Automatic logging of hours after
volunteering.
Ability to manually edit the logged hours.
Visual representation of the logged hours.
Hours count towards personally
set/company set goals.
An employee finds a cause of particular
interest to them and performs volunteer
works surrounding it. They then have to
manually add the hours and charity into the
system.
3
Interface for manual logging of hours.
Interface to add charities manually into the
system.
An employee requires permission from
their manager to partake in a volunteering
opportunity, however, due to the high
volume of emails, the request is lost.
Ability to connect employees to their
respective managers.
A system to request permission from
managers.
A system to alert managers of pending
requests.
A system to alert employee of
approved/denied requests.
Medium Priority
An employee checks the capacity of an
event before choosing what volunteering
opportunity to partake in.
4
New design of the opportunity page.
Visualization of event capacity.
Visualization of number of available spaces
remaining.
Filter event by popularity/availability when
searching.
Low Priority
An employee finds a volunteering
opportunity that they believe a co-worker
would be interested in and suggests it to
them.
4
Send other employees suggestions for
events.
An incoming page to manage suggested
events.
A method to respond to suggested events.
Challenge 3: Bank Of America Lancaster University
Page | 17
Execution
After Sprint Backlog and Sprint Tasks are determined, the next phase will be Execution, including
the execution of the Sprint, Backlog Refining Meeting and Daily Scrum Meeting (shown below).
The general execution of a Sprint includes defining requirements of Sprint Tasks, analysis and
design, implementation & deployment, testing and final evaluation of the final works.
In the Daily Scrum Meeting, the Scrum Development Team members spend around 15 minutes
reporting what they have done, and what they will do to each other. The meeting is intended to
disrupt old habits of working separately, and be more self-organised. For Backlog Refining
Meeting, as most Product Backlog Items (PBIs) initially need refinement that they are too large
and poorly understood, it is useful to take some time out of Sprint Execution to help prepare the
Product Backlog for the next Sprint Planning Meeting.
Review and Retrospective
After the final works are finished in each Sprint, a Sprint Review Meeting and Sprint Retrospective
meeting will be held (shown below).
After Sprint execution, the team holds a Sprint Review Meeting to demonstrate a working product
increment to the Product Owner and shareholders, and the Product Owner will declare items
considered completed. Incomplete items are returned to the Product Backlog and ranked
according to the Product Owner’s revised priorities as candidates for future Sprints. For
stakeholders, it is the opportunity to inspect and adapt the product as it emerges, and iteratively
refine everyone’s understanding of the requirements.
Team
Daily Scrum
Meeting
(Team & Scrum
Master)
Backlog Refining
Meeting
(Team & Scrum
Master)
Requirements
Analyis & Design
Implementation &
Deployment
Testing
Evaluation
Challenge 3: Bank Of America Lancaster University
Page | 18
In the final stage of each sprint, clients and users will be involved by providing feedback of the
final works. Any required improvement of the current works will be taken to next sprint and
discussed in the sprint retrospective meeting.
Each Sprint ends with a retrospective that the team reflects on its own process and dedicated
Scrum Masters will find alternative actions for the next level.
For example, at the end of Sprint 1, a sprint review meeting will be held to discuss what sprint
tasks are considered completed. Suppose the task ‘search opportunities by charity’ is not
completed, this task will be returned to product backlog for future sprints. Besides, clients and
users will be asked to try the new features and provide feedback, which will be considered in the
retrospective meeting and in Sprint 2. Furthermore, in the retrospective stage, the Agile team will
reflect on the process and figure out alternatives for Sprint 2.
Besides, at the end of the Sprint 4, a final review and retrospective should be implemented to
review the previous work and develop alternative actions for future steps. (See implementation
plan on page 19)
Post Implementation
After Sprint 4 is complete a beta will be released to a cross-section of employees for testing and
final debugging. Other than data on number of usage and usage habits, questionnaires will be
circulated asking employee’s to give their opinions on the application. The questionnaires will
also ask employees to grade to what extent they believe the app matched each of the original
specifications addressed by the brief. This will give the scrum team the information needed to
make any necessary changes before the Go-Live date.
After the Go-Live date the maintenance team will start a 12 month qualitative and quantitative
study of the app. The aim of Post-implementation review (PIR) is to insure that the initial
requirements were met and that the app is being well received within the company, but also to
produce material that Bank of America can use for future projects. Firstly, the team will gather
quantitative data to form a scope of use for the app. Metrics may include; number of users,
adoption rate, daily usage rate and the number of SQL queries being run by the external server
over a period of time. These metrics will be collected in real time and will go into a weekly report
produced by the maintenance team. For qualitative data the team will be conducting user
feedback studies through a number of circulated questionnaires. These will be sent on a quarterly
basis to a cross-section of employees and will evaluate many aspects of the app such as; UI
design, functionality, any problems found and overall opinion. These questionnaires may also
specifically ask employee’s about the initial project requirements to see if any were not met and
may need iterating in the future. The results will be analysed and compiled together with the
weekly usage studies to form a benefits review that will be released on a quarterly basis.
The aim of this system to insure that the project has a larger scope than simply the release of the
app. The PIR process will provide Bank of America with invaluable information on its employee’s
preferences and usage habits that can easily be transferred into future iterations of the volunteer
app or into other projects. A plan for the post implementation can be seen on page 21.
Page | 19
Implementation Plan
Task Time Frame (8 weeks) Duration
(week)1 2 3 4 5 6 7 8
Sprint1 Weeks 1-2
Identify requirements, create product backlog and sprint 1 backlog 0.5
Design search opportunities by key words 1
Design search opportunities by tags 1
Design filter opportunities by distance to user 1
Design search opportunities by location 1
Design search opportunities by charity 1
Design search opportunities by service work type 1
Implementation & deployment of new features 1
Testing on new features 1.5
Conduct surveys with clients and review feedback on the features 1
Review and retrospective of sprint 1 0.5
Sprint 2 Weeks 3-4
Select product backlog items and create sprint 2 backlog 0.2
Design automatic logging of hours after volunteering 1
Design the function to manually edit the logged hours 1
Create the visual representation of the logged hours 1
Set hours counting function towards personally set/company set goals 1
Implementation & deployment of new features 1
Testing on new features 1.8
Conduct surveys with clients and review feedback on the feature 1
Review and retrospective of sprint 2 0.5
Challenge 3: Bank Of America Lancaster University
Page | 20
Task Time Frame (8 weeks) Duration
(week)
1 2 3 4 5 6 7 8
Sprint 3 Weeks 5-6
Select product backlog items and create sprint 3 backlog 0.2
Design the interface for manual logging of hours 1
Design the interface to add charities manually into the system 1
Design the function to connect employees to their respective managers 1
Design a system to request permission from managers 1
Design a system to alert managers of pending requests 1
Design a system to alert employee of approved/denied requests 1
Implementation & deployment of new features 1
Testing on new features 1.8
Promotional activities within employees (emails, updates on website) 1
Conduct surveys with clients and review feedback on the features 1
Review and retrospective of sprint 3 0.5
Sprint 4 Weeks 7-8
Select product backlog items and create sprint 4 backlog 0.2
New design of the opportunity page 1
Visualization of event capacity 1
Visualization of number of available spaces remaining 1
Filter event by popularity/availability when searching 1
Design of sending other employees suggestions for events 1
Design an incoming page to manage suggested events 1
Design a method to respond to suggested events 1
Challenge 3: Bank Of America Lancaster University
Page | 21
Task Time Frame (8 weeks) Duration
(week)
1 2 3 4 5 6 7 8
Implementation & deployment of new features 1
Testing on new features 1.8
Conduct surveys with clients and review feedback on the features 1
Review and retrospective of sprint 4 0.5
Final review and retrospective of the whole project 0.5
Post Implementation Plan
Task Time Frame (12 months)
3 4 5 6 7 8 9 10 11 12
Promotional activities (launch day competition, emails, updates on website)
Beta version release (Android, iOS and Windows version)
Review of Beta version (user & functionality)
Public release (Android, iOS and Windows version)
PIR – (team & users)
Access usage and effect of promotion
Maintenance and updates
Page | 22
PROJECT TEAMS
The project assumes one team working on the delivery of the project and the other responsible
for maintenance of the application.
Delivery team will be based on Agile Methodology, with 13 team members, each of them actively
participating in the delivery process. Our ideal agile team is made up of one scrum master and
12 other team members. These team members would have cross-functional roles and be able to
adapt their skills to the given sprint. The onshore team would work for a total 40 days, not
accounting for contingencies, and the offshore maintenance team for 250 days.
In the project outline, there was a list of team members which would be more suitable to the
Waterfall Methodology, however, we have decided to choose roles from the list, with the
assumption that each of these people would be willing and knowledgeable to work as a part of
agile team.
The list above is our allocation of roles from a waterfall methodology to that of a scrum team.
Role Role in Agile Location
Number of
Employees
Project Manager Scrum Master
Onshore
1
Solution Architect
Team
2
Test Analyst 2
UAT Analyst 2
Technical Developer (Build) 4
IT Security 2
BAU Service Manager
Maintenance Offshore
1
BAU Analyst 2
Challenge 3: Bank Of America Lancaster University
Page | 23
COST ANALYSIS
There are three main cost generating areas of the project: delivery team, the servers and
maintenance team. The fourth section are minor costs as well as contingency cost.
For the delivery team, the estimated delivery time is 2 months, which corresponds to 40 working
days. In addition, personnel cost will also include the maintenance team, working for 250 days
which is the full year.
The delivery team is placed onshore and generates the cost of £192,000.00. (See page 18 for full
breakdown.) The maintenance team will work offshore in order to decrease costs (any changes
to their daily cost incurs huge differences as they work for 250 days), with total cost of
£162,500.00.
Servers, will be provided by a third party, as Bank of America’s servers would involve high security
risk, are assumed to generate £20,000.00. This may vary depending upon the providers and
negotiations with them as Bank of America may have some partners in this sector who would be
able to offer reduced fees.
Other costs include iOS app publishing, which is £200.00 and, for marketing purposes, launch
day prize of iPad Air that would cost approximately £400.00.
Contingency cost has been set at £20,000.00, which has been allocated for unexpected costs such
as; project delays, changes to the sprint backlog. It is worth mentioning that these are incurred
costs for accounting purposes and do not have to occur in the project’s life or afterwards.
The total cost of the project is, therefore, £395,100.00, which does not exceed the given budget
of £400,000.00. That shows high cost efficiency of the project as well as good resource planning,
as all possible risks and additional outflowing cash flows have been taken into account.
Therefore a significant part (41%) of the whole cost is the maintenance team, that we assume will
work as a technological part of Bank of America. Nonetheless, this may not be required if training
for already employed employees was provided and is dependent on Bank of America’s HR
management.
Page | 24
Role Role in Agile Location Number of Employees Man Day Rate Result
Project Manager Scrum Master
Onshore
1 £ 400.00 £ 16,000.00
Solution Architect
Team
2 £ 600.00 £ 48,000.00
Test Analyst 2 £ 300.00 £ 24,000.00
UAT Analyst 2 £ 300.00 £ 24,000.00
Technical Developer
(Build)
4 £ 300.00 £ 48,000.00
IT Security 2 £ 400.00 £ 32,000.00
Total: 13 Days Worked: 40
BAU Service Manager
Offshore
1 £ 300.00 £ 75,000.00
BAU Analyst 2 £ 175.00 £ 87,500.00
Total: 3 Days Worked: 250
Additional Costs
Servers £ 20,000.00
iOS app publishing £ 200.00
Contingency cost (provision for updates) £ 20,000.00
Marketing Cost £ 2 000.00
Total
£ 396, 700.00
Page | 25
RAIDS ANALYSIS
Risks
Risk Impact Mitigation
Likelihood: Medium
Poor marketing of a
new application may
result in low
downloading volume
This would result in low
participation rate and
employee disengagement.
Hosting a launch event where
employees can win a prize.
Changing
expectations of the
product owner
A delay in implementation Scrum methodology allows for an
agile response to any product
requirements.
Likelihood: Low
Lack of access to
smart technology
Exclusion of employees The application will work parallel
with the website.
Hacking The impact of hacking is low
because the pauses in the
functioning of the system
would not affect the final
volunteering results to a great
extent.
The application will use advanced
security protocols.
Data theft The impact of hacking would
be quite low as the data stored
in the application will not be
confidential relatively to other
bank data.
The application will use advanced
security protocols.
Exchange rate
variability
It may affect salaries for off-
shore employees, which
subsequently may cause
budget constraint.
Budget accounts for contingency
costs.
Challenge 3: Bank Of America Lancaster University
Page | 26
Assumptions
1. Estimated up to 200 000 unique users in 12 months’ time
2. Each sprint takes two weeks to complete
3. Project delivery time is 2 months (40 working days)
4. Salaries proposed in the budget include tax
Technical
a. Application download size is between 50-100 MB
b. Devices have an internet access
c. Application works independently from bank’s internal website
d. Users have at least iOS 7 or Android Jelly Bean software versions on the mobile
devices
Functional
e. The team is cross-functional and self-managing. Each employee is engaged at
every stage of product design, development and implementation
f. The scrum team is based on-shore to facilitate effective communication with a
product owner.
g. The BAU team is based off-shore for the efficiency and cost-saving reasons
h. The provision for unexpected costs is set in the budget
i. The product owner is involved in every sprint review meeting
Issues
1. Privacy issue: bank employees publicly disclose their volunteering activity
Most issue will result after the project commences, usually being realized from the risks.
Dependencies
5. The progression from one sprint to another depends on a feedback from the product
owner
6. The final UI design depends on the users feedback after the beta version is released
7. The maximum size of the application depends on the maximum amount of space
designated for it in an external server
8. Speed of application depends as well on the speed on the internet connection and on
the version of the software installed
9.
10. Because in Agile methodology sprints are independent of each other, the dependencies
list is significantly reduced.

More Related Content

Viewers also liked

Ziua Nationala a Romaniei
Ziua Nationala a RomanieiZiua Nationala a Romaniei
Ziua Nationala a RomanieiNae Gabriel
 
Il castello veronica e lilla
Il castello veronica e lillaIl castello veronica e lilla
Il castello veronica e lillaclassefenomeno15
 
1 സർവ്വവും സൂര്യനാൽ
1 സർവ്വവും സൂര്യനാൽ1 സർവ്വവും സൂര്യനാൽ
1 സർവ്വവും സൂര്യനാൽiqbal muhammed
 
Guia básico de Trello
Guia básico de TrelloGuia básico de Trello
Guia básico de TrelloLucas Rolim
 
2 കാറ്റിന്റെ ഉറവിടം തേടി
2 കാറ്റിന്റെ ഉറവിടം തേടി 2 കാറ്റിന്റെ ഉറവിടം തേടി
2 കാറ്റിന്റെ ഉറവിടം തേടി iqbal muhammed
 

Viewers also liked (14)

Agricoltura
AgricolturaAgricoltura
Agricoltura
 
Il castello alessandra
Il castello alessandraIl castello alessandra
Il castello alessandra
 
VocoPresentation
VocoPresentationVocoPresentation
VocoPresentation
 
Il castello elisa a.
Il castello elisa a.Il castello elisa a.
Il castello elisa a.
 
Yandex Metrica - Data Restart konference 2015
Yandex Metrica - Data Restart konference 2015Yandex Metrica - Data Restart konference 2015
Yandex Metrica - Data Restart konference 2015
 
Il castello sara
Il castello  saraIl castello  sara
Il castello sara
 
Ziua Nationala a Romaniei
Ziua Nationala a RomanieiZiua Nationala a Romaniei
Ziua Nationala a Romaniei
 
Il castello veronica e lilla
Il castello veronica e lillaIl castello veronica e lilla
Il castello veronica e lilla
 
BRM ppt
BRM pptBRM ppt
BRM ppt
 
Programas para presentaciones
Programas para presentacionesProgramas para presentaciones
Programas para presentaciones
 
1 സർവ്വവും സൂര്യനാൽ
1 സർവ്വവും സൂര്യനാൽ1 സർവ്വവും സൂര്യനാൽ
1 സർവ്വവും സൂര്യനാൽ
 
Guia básico de Trello
Guia básico de TrelloGuia básico de Trello
Guia básico de Trello
 
2 കാറ്റിന്റെ ഉറവിടം തേടി
2 കാറ്റിന്റെ ഉറവിടം തേടി 2 കാറ്റിന്റെ ഉറവിടം തേടി
2 കാറ്റിന്റെ ഉറവിടം തേടി
 
His02 world20 cent
His02 world20 centHis02 world20 cent
His02 world20 cent
 

Similar to The-Report-V7

Project Management Report - 2Assignment 2Project Managemen.docx
Project Management Report - 2Assignment 2Project Managemen.docxProject Management Report - 2Assignment 2Project Managemen.docx
Project Management Report - 2Assignment 2Project Managemen.docxwkyra78
 
IT Application Development - with SDLC.pptx
IT Application Development - with SDLC.pptxIT Application Development - with SDLC.pptx
IT Application Development - with SDLC.pptxdjualaja88
 
Final Project 3 Document
Final Project 3  DocumentFinal Project 3  Document
Final Project 3 DocumentLinda Calkins
 
Project Report - Acquisition Credit Scoring Model
Project Report - Acquisition Credit Scoring ModelProject Report - Acquisition Credit Scoring Model
Project Report - Acquisition Credit Scoring ModelSubhasis Mishra
 
Improving Effort Estimation in Agile Software Development Projects
Improving Effort Estimation in Agile Software Development ProjectsImproving Effort Estimation in Agile Software Development Projects
Improving Effort Estimation in Agile Software Development ProjectsGedi Siuskus
 
“RAKTANCHAL” An Blood bank finder application (Priyanka Tiwari) (4) (1).docx
“RAKTANCHAL” An Blood bank finder application (Priyanka Tiwari) (4) (1).docx“RAKTANCHAL” An Blood bank finder application (Priyanka Tiwari) (4) (1).docx
“RAKTANCHAL” An Blood bank finder application (Priyanka Tiwari) (4) (1).docxArpitMishra139426
 
System Analysis & Design (CHAPTER TWO) (1).ppt
System Analysis & Design (CHAPTER TWO) (1).pptSystem Analysis & Design (CHAPTER TWO) (1).ppt
System Analysis & Design (CHAPTER TWO) (1).pptAynetuTerefe2
 
Application of Savings and Loan Cooperative Services
Application of Savings and Loan Cooperative ServicesApplication of Savings and Loan Cooperative Services
Application of Savings and Loan Cooperative ServicesYogeshIJTSRD
 
Project Management Leadership, And Skills : Planning And Control | Assignment...
Project Management Leadership, And Skills : Planning And Control | Assignment...Project Management Leadership, And Skills : Planning And Control | Assignment...
Project Management Leadership, And Skills : Planning And Control | Assignment...Emre Dirlik
 
Detailed Programme Case Study
Detailed Programme Case StudyDetailed Programme Case Study
Detailed Programme Case StudySteve Syder
 
CIS 477 - Senior Project - Imagination Portal
CIS 477 - Senior Project - Imagination PortalCIS 477 - Senior Project - Imagination Portal
CIS 477 - Senior Project - Imagination PortalChristopher Kimberlain
 
5 example from a course with different learning outcomes
5 example from a course with different learning outcomes5 example from a course with different learning outcomes
5 example from a course with different learning outcomesHuy Trần
 
Development Frameworks and Methods (University of Greenwich BIT Coursework) b...
Development Frameworks and Methods (University of Greenwich BIT Coursework) b...Development Frameworks and Methods (University of Greenwich BIT Coursework) b...
Development Frameworks and Methods (University of Greenwich BIT Coursework) b...Nay Linn Ko
 
A Global Web Enablement Framework for Small Charities and Voluntary Sector Or...
A Global Web Enablement Framework for Small Charities and Voluntary Sector Or...A Global Web Enablement Framework for Small Charities and Voluntary Sector Or...
A Global Web Enablement Framework for Small Charities and Voluntary Sector Or...Tom Robinson
 
project (Salon Management).pptx
project (Salon Management).pptxproject (Salon Management).pptx
project (Salon Management).pptxssuserefca8b
 
computer science.docx. Mohit Class 12 follow for more
computer science.docx. Mohit Class 12 follow for morecomputer science.docx. Mohit Class 12 follow for more
computer science.docx. Mohit Class 12 follow for morekimchibhendalbhai070
 

Similar to The-Report-V7 (20)

Project Management Report - 2Assignment 2Project Managemen.docx
Project Management Report - 2Assignment 2Project Managemen.docxProject Management Report - 2Assignment 2Project Managemen.docx
Project Management Report - 2Assignment 2Project Managemen.docx
 
IT Application Development - with SDLC.pptx
IT Application Development - with SDLC.pptxIT Application Development - with SDLC.pptx
IT Application Development - with SDLC.pptx
 
Final Project 3 Document
Final Project 3  DocumentFinal Project 3  Document
Final Project 3 Document
 
Project Report - Acquisition Credit Scoring Model
Project Report - Acquisition Credit Scoring ModelProject Report - Acquisition Credit Scoring Model
Project Report - Acquisition Credit Scoring Model
 
Improving Effort Estimation in Agile Software Development Projects
Improving Effort Estimation in Agile Software Development ProjectsImproving Effort Estimation in Agile Software Development Projects
Improving Effort Estimation in Agile Software Development Projects
 
“RAKTANCHAL” An Blood bank finder application (Priyanka Tiwari) (4) (1).docx
“RAKTANCHAL” An Blood bank finder application (Priyanka Tiwari) (4) (1).docx“RAKTANCHAL” An Blood bank finder application (Priyanka Tiwari) (4) (1).docx
“RAKTANCHAL” An Blood bank finder application (Priyanka Tiwari) (4) (1).docx
 
System Analysis & Design (CHAPTER TWO) (1).ppt
System Analysis & Design (CHAPTER TWO) (1).pptSystem Analysis & Design (CHAPTER TWO) (1).ppt
System Analysis & Design (CHAPTER TWO) (1).ppt
 
Application of Savings and Loan Cooperative Services
Application of Savings and Loan Cooperative ServicesApplication of Savings and Loan Cooperative Services
Application of Savings and Loan Cooperative Services
 
Thesis
ThesisThesis
Thesis
 
2018-Case-Study.pdf
2018-Case-Study.pdf2018-Case-Study.pdf
2018-Case-Study.pdf
 
Project Management Leadership, And Skills : Planning And Control | Assignment...
Project Management Leadership, And Skills : Planning And Control | Assignment...Project Management Leadership, And Skills : Planning And Control | Assignment...
Project Management Leadership, And Skills : Planning And Control | Assignment...
 
Detailed Programme Case Study
Detailed Programme Case StudyDetailed Programme Case Study
Detailed Programme Case Study
 
CIS 477 - Senior Project - Imagination Portal
CIS 477 - Senior Project - Imagination PortalCIS 477 - Senior Project - Imagination Portal
CIS 477 - Senior Project - Imagination Portal
 
5 example from a course with different learning outcomes
5 example from a course with different learning outcomes5 example from a course with different learning outcomes
5 example from a course with different learning outcomes
 
MoneySafe-FinalReport
MoneySafe-FinalReportMoneySafe-FinalReport
MoneySafe-FinalReport
 
Development Frameworks and Methods (University of Greenwich BIT Coursework) b...
Development Frameworks and Methods (University of Greenwich BIT Coursework) b...Development Frameworks and Methods (University of Greenwich BIT Coursework) b...
Development Frameworks and Methods (University of Greenwich BIT Coursework) b...
 
A Global Web Enablement Framework for Small Charities and Voluntary Sector Or...
A Global Web Enablement Framework for Small Charities and Voluntary Sector Or...A Global Web Enablement Framework for Small Charities and Voluntary Sector Or...
A Global Web Enablement Framework for Small Charities and Voluntary Sector Or...
 
project (Salon Management).pptx
project (Salon Management).pptxproject (Salon Management).pptx
project (Salon Management).pptx
 
Report
ReportReport
Report
 
computer science.docx. Mohit Class 12 follow for more
computer science.docx. Mohit Class 12 follow for morecomputer science.docx. Mohit Class 12 follow for more
computer science.docx. Mohit Class 12 follow for more
 

The-Report-V7

  • 1. Page | 0 Business Proposal Challenge 3: Bank of America University Technology Challenge 2015 Lancaster University 25/11/15 Daniel Abreu, Cyprian Brytan, Dan Lu, Bartek Mika, Dominika Stylinska
  • 2. Challenge 3: Bank Of America Lancaster University Page | 1 TABLE OF CONTENTS Executive Summary................................................................................................................................................3 Introduction To The Project...............................................................................................................................4 The Design Brief......................................................................................................................................................5 Problems to Address ........................................................................................................................................5 Requirements .......................................................................................................................................................5 Features and Design..............................................................................................................................................6 Main screen......................................................................................................................................................6 Menu screen ....................................................................................................................................................6 My events..........................................................................................................................................................7 Event search.....................................................................................................................................................7 View Profile.......................................................................................................................................................8 Friends ................................................................................................................................................................8 Leader board....................................................................................................................................................8 Achievement.....................................................................................................................................................9 Event Page........................................................................................................................................................9 Settings...............................................................................................................................................................9 Notification screen..................................................................................................................................... 10 Request system............................................................................................................................................ 10 Technology.............................................................................................................................................................. 11 Front-End Development............................................................................................................................... 11 System Architecture ....................................................................................................................................... 11 Example of Use............................................................................................................................................ 13 Delivery Schedule................................................................................................................................................. 14 Agile Methodology......................................................................................................................................... 14 Planning............................................................................................................................................................... 15 Task Breakdown............................................................................................................................................... 16
  • 3. Challenge 3: Bank Of America Lancaster University Page | 2 Execution............................................................................................................................................................. 17 Review and Retrospective............................................................................................................................ 17 Post Implementation...................................................................................................................................... 18 Implementation Plan................................................................................................................................. 19 Post Implementation Plan....................................................................................................................... 21 Project Teams ........................................................................................................................................................ 22 Cost Analysis.......................................................................................................................................................... 23 RAIDS Analysis....................................................................................................................................................... 25 Risks....................................................................................................................................................................... 25 Assumptions ...................................................................................................................................................... 26 Technical......................................................................................................................................................... 26 Functional....................................................................................................................................................... 26 Issues..................................................................................................................................................................... 26 Dependencies.................................................................................................................................................... 26
  • 4. Challenge 3: Bank Of America Lancaster University Page | 3 EXECUTIVE SUMMARY Bank of America Merrill Lynch has set a goal of conducting two million hours of volunteer work all across the globe in a push in favour of cooperate responsibility and sustainability. Currently employees keep track of their volunteer hours through a web-interface located within the internal network, and it has problems of network restrictions, complexity of use, non-location specific events. This proposal aims to show the new design of the app, technology used in the app, and plan and estimate of the project. Based on the requirements of the app, design of the interfaces (e.g. Main Screen) and relevant functions are provided along with technology used in the app design and dataflow analysis. In delivery schedule, by using Agile methodology, 4 sprints (each takes 2 weeks) will be conducted and the whole project will take 2 months. Each sprint includes planning, execution, review and retrospective process. Considering the timeline, roles in Agile, location and man rates, a delivery team and a maintenance team will conduct the project. Besides, a cost analysis is provided in the proposal, taking into consideration of employee salaries, cost of servers, marketing cost, contingency cost and iOS publishing fees. RAIDS analysis identifies risks and mitigation, general assumptions along with technology and employee assumptions, key issues and dependencies.
  • 5. Challenge 3: Bank Of America Lancaster University Page | 4 INTRODUCTION TO THE PROJECT Guided by principles of community betterment and corporate responsibility, Bank of America Merrill Lynch has been incentivising its employees to do volunteer work for various causes. The benefits of this practice can be seen in the well-being of the community but also in its employees who are able to have their personal passions supported by the company. With all this in mind Bank of America Merrill Lynch has set a goal of conducting two million hours of volunteer work all across the globe. Employees keep track of their volunteer hours through a web-interface located within the Bank of America Merrill Lynch network. Whilst functionally adequate this solution does have its downfalls, primarily due to the interface being located within the bank’s secure network, many employees cannot access their profiles without being connected to an internal network, usually their office. This is a difficulty as it means employees cannot find volunteering options or log their hours unless they’re in their office, which is not the ideal time for this information. Another issue with the system is the over complexity and impracticality of its use, and an overhaul with a focus on automation and simplicity would be well regarded. The project is therefore to implement a new way for employees to track their hours and sign up for volunteering opportunities. The predefined medium is an application that can run on employees’ smart devices and allows employees to access the volunteering information without local network restrictions.
  • 6. Challenge 3: Bank Of America Lancaster University Page | 5 THE DESIGN BRIEF Problems to Address 1. Events are not location-specific 2. Logging employees’ hours needs to be done on Bank’s internal central network 3. Employees forget to log their hours (or postpone it because it’s cumbersome) Requirements 1. Easy to install 2. Encourage more sign-ups 3. Needs to work on iOS, Android and Windows 10 4. Include some sort of location service (both automatic and manual) 5. Check miles walked, laps swam etc. 6. Alerts for upcoming events 7. Method to sign-up for events 8. Event availability (limited number of people) 9. Notifications and reminders 10. Sense of progress 11. Consistent with Bank of America branding 12. Allow users to choose switch alerting on/off and location track 13. Gather information from internal website, and data collection will be uploaded to internal website (no need to be real time)
  • 7. Challenge 3: Bank Of America Lancaster University Page | 6 FEATURES AND DESIGN Main screen is the one that appears while opening the application. It contains information about the hours remaining to achieve the goal and upcoming events. It also allows users to access the main menu, settings and notifications. The three progress trackers are designed to incentivise more volunteering. They track personal hours against a personally set goal, an accumulative hour for an employee’s team, and finally the corporate assigned goal of the year, currently assigned at two million hours. Menu screen allows users to switch between different screens. Easy navigation throughout the app is important. It will be universally present from a single swipe in from the left edge of the screen.
  • 8. Challenge 3: Bank Of America Lancaster University Page | 7 My events screen shows upcoming events as well as the ones from the past. The user can tap on each of them to reveal more information such as availability, date, location, capacity and add alerts. Event search screen allows users to search and sign up for a specific event. Additionally, it allows users to invite other people to take part in the event. There are two ways in which users can search for the events: 1. Search by location - app uses GPS to triangulate user’s location and then displays nearby events. 2. Advanced search - users can search for an event based on specific criteria (e.g. location, length, event type, date).
  • 9. Challenge 3: Bank Of America Lancaster University Page | 8 View Profile each person’s profile shows events they have participated in, achievements and basic information. For privacy reasons, an employee can always choose to keep their event history/achievements/hours private. Friends screen allows users to look at other people’s profiles, invite them for events and search for new friends. This social feature could encourage employees to take part in more events. Leader board shows current leaders as well as the user’s position. Instead of sorting the users based on the number of hours they did, we created a simple point system: current score = 2 x hours + achievement points. The aim of this feature is to promote friendly competition within the bank.
  • 10. Challenge 3: Bank Of America Lancaster University Page | 9 Achievement screen shows user’s current achievements. The aim of the achievement system is to incentivise employees to volunteer more often. If this feature is well received, there would be abilities to add new achievements to keep the system growing. The system could also allow timed events to appear, where employees would have a certain number of weeks to try to unlock them, which opens up possibilities for some themed events nearing annual holidays or corporate events. Event Page is designed to give all the information needed about an event in a simple presentation. Notable additions include event capacity and a space for charities to add small descriptions for their events. Settings allow users to change privacy, location and alert preferences. This would also allow for the setting of personal hour goals.
  • 11. Challenge 3: Bank Of America Lancaster University Page | 10 Notification screen is accessible from the main menu allowing users to check current notifications. There are a few notification types: 1. Event invite: invitation to participate in an event from other users. 2. Event reminder: notification that reminds about a certain event. It allows users to confirm the attendance or cancel the event. If users tap on ‘Confirm’, the hours of an event are set to be recorded. 3. Friend request. Request system is another important feature of the notification system. To avoid an even larger income of emails or notifications, if an employee asks their manager for permission to miss some hours to do volunteer work, their manager will not receive a push notification. Instead, a simple badge counter will show a number near the app’s icon on their main screen. Managers will have access to a request approval page where they can answer request in a non-invasive method.
  • 12. Challenge 3: Bank Of America Lancaster University Page | 11 TECHNOLOGY Front-End Development Regarding front-end, the application has to work on iOS, Android and Windows devices. That means developing three applications at the same time which will require a larger scrum team (See Project Teams page 21). It is important to note that this project assumes that the smartphones are up to date. Some older versions (e.g. iOS 6 or Android Ice Cream Sandwich) may not be supported due to device hardware limitations. (See RAIDS analysis page 24 ) The app will be developed simultaneously for all platforms so that it can be released for all devices at the same time. Prior to the release of an application, a beta version will be released for a calculated amount of employees. This will help in the gathering of feedback and making final corrections before releasing the app to all Bank of America employees. The final version of the app is going to be uploaded onto the Apple AppStore, Google Play and Windows Marketplace to simplify the installation process. It is also important to be able to ensure longevity as the app would be futile if unusable in a year’s time. To guarantee longevity, the project will be developed on three different languages for each operating system, as follows; 1. Android - Java, 2. iOS - Swift, 3. Windows Mobile - C++. By choosing three different languages for each platform we can guarantee a longer longevity for the app on each ecosystem. That is because platform updates do not affect native languages, or in other words, the inevitable phone upgrades will not change the way the app functions. System Architecture Besides the technology used for an app design, dataflow between the app, internal servers and external servers is shown below.
  • 13. Challenge 3: Bank Of America Lancaster University Page | 12 Although it might be more time consuming and costly, an external server, which is physically separate from the internal one, will be used to place the application and all the new volunteering- related features. Currently, the volunteering data is kept on an internal Bank of America server that also contains confidential information. An external server would act as a intermediate between the data on the internal servers and the employees smartphone. This extra layer would allow for limited access to the internal servers minimizing security risks. The phone itself will not be able to connect directly to the internal server. Instead, it will be connected with an external one that will then establish a secure connection to retrieve volunteering data. In essence, the app will be able to access the data in a real time as it is connected to the external. However, data collected would be uploaded periodically to reduce traffic on the internal server. Only booking data will be uploaded in a real time in order to avoid double booking. In order to provide a sufficient level of security, the following technologies will be used:  Internal Server - External server connection — VPN tunnel  External Server - Client — SSL over HTTP connection  Confidential data encryption — SHA-2 A VPN tunnel to link the external server with the internal one will provide a secure and permanent connection. It enables sending and receiving the encrypted packets between two servers. The external server will have limited access to the internal, allowing only to read/write the volunteering data. Client - External Server will be connected with SSL HTTP protocol, as it does not require a complicated configuration on a client side. This differs from the VPN tunnel as it creates only a short term session that allows a client to send and retrieve the data from the server. The confidential data such as users’ credentials will be encrypted on an external server using SHA-2 algorithm to provide an additional layer of security. This is a reasonable choice as the algorithms are frequently used for this kind of application. Furthermore, the secure cryptographic hashing algorithm doesn’t strain the servers as it has a rapid response time.
  • 14. Challenge 3: Bank Of America Lancaster University Page | 13 For the security purposes, each employee will have to create a new user account instead of using the one used on internal website however, the volunteering data will be synced automatically on both accounts. To ensure that the server protocols remain up-to-date a maintenance team has been accounted for in the budget. (See Cost Analysis page 22) Example of Use 1. User opens app. a. A GET request is sent to the external server to update the data such as goal progress etc.(also occurs when app is running in the background) b. The external server gets the request, verifies it and then sends the SQL query to an internal server to get the required data. c. The required data stored in an external server along with the data obtained from an internal one is passed to an app. d. Information is updated. 2. User opens ‘map search’ option, and taps/clicks on an event displayed on the map. a. App sends another GET request to retrieve information displayed on the event page. General event information such as available places, name of an event, and capacity are retrieved from an internal server. App-specific data such as event photo and a detailed description are retrieved from an external server. b. Data is passed to the client. 3. User taps on a ‘sign up’ button. a. A POST request containing a booking information is sent to an external server The external server, after validation of a POST request, sends the ‘UPDATE’ SQL Query to the Internal one. b. ‘Available spaces’ field is instantly decremented.
  • 15. Challenge 3: Bank Of America Lancaster University Page | 14 DELIVERY SCHEDULE Agile Methodology Compared to the traditional waterfall (table shown below), Agile methodology has benefits of speed-to-market (supporting early and regular release), flexibility (changes in requirements are expected), business engagement and customer satisfaction (active involvement of user representative/ product owner). Therefore, Agile methodology, especially Scrum, will be conducted in the delivery of the project. Criteria Waterfall Agile Length Typically 9-12 months Typically 2-3 months Project size Hard to tailor down to small projects Well matched to small products and teams Requirements Requirements defined upfront Flexible requirements Clients involvement Does not involve clients Clients are highly involved in the development of the project Users interaction Only when gathering requirements and user testing Interact with users with constant meet ups Testing Separate phase at the end of the project Fully-automated, continuous testing at both functional and unit level Cost of change High Low With the assumptions that each Sprint takes 2 weeks to complete, the delivery timeline is shown below.
  • 16. Challenge 3: Bank Of America Lancaster University Page | 15 Planning At the beginning of each Sprint, planning is the first phase (shown below). The Product Owner is responsible to prioritise the requirements and put each Product Backlog Item (usually in User Story form) in Product Backlog. Then, the Product Owner and the team will hold a Sprint Planning Meeting to negotiate which Product Backlog Items they will attempt to convert to working product during each Sprint. While the Product Owner is responsible to declare which items are important, the team is responsible for selecting the amount of work they feel they can implement without accruing technical debt. Towards the end of the Sprint Planning Meeting, the team breaks the selected Product Backlog Items into Sprint Backlog and related Tasks. According to the requirements of the application, Product Backlog, Sprint Backlog and Sprint Tasks for each Sprint are shown below.
  • 17. Challenge 3: Bank Of America Lancaster University Page | 16 Task Breakdown Product Backlog Sprint Number Sprint Task High Priority Finding a volunteering opportunity for themselves in the upcoming weeks. 1 Search opportunities by key words. Search opportunities by tags. Filter opportunities by distance to user. Search opportunities by location. Search opportunities by charity. Search opportunities by service work type. After volunteering, an employee wants to see how many hours they have done in total and see how close they are to a set goal. 2 Automatic logging of hours after volunteering. Ability to manually edit the logged hours. Visual representation of the logged hours. Hours count towards personally set/company set goals. An employee finds a cause of particular interest to them and performs volunteer works surrounding it. They then have to manually add the hours and charity into the system. 3 Interface for manual logging of hours. Interface to add charities manually into the system. An employee requires permission from their manager to partake in a volunteering opportunity, however, due to the high volume of emails, the request is lost. Ability to connect employees to their respective managers. A system to request permission from managers. A system to alert managers of pending requests. A system to alert employee of approved/denied requests. Medium Priority An employee checks the capacity of an event before choosing what volunteering opportunity to partake in. 4 New design of the opportunity page. Visualization of event capacity. Visualization of number of available spaces remaining. Filter event by popularity/availability when searching. Low Priority An employee finds a volunteering opportunity that they believe a co-worker would be interested in and suggests it to them. 4 Send other employees suggestions for events. An incoming page to manage suggested events. A method to respond to suggested events.
  • 18. Challenge 3: Bank Of America Lancaster University Page | 17 Execution After Sprint Backlog and Sprint Tasks are determined, the next phase will be Execution, including the execution of the Sprint, Backlog Refining Meeting and Daily Scrum Meeting (shown below). The general execution of a Sprint includes defining requirements of Sprint Tasks, analysis and design, implementation & deployment, testing and final evaluation of the final works. In the Daily Scrum Meeting, the Scrum Development Team members spend around 15 minutes reporting what they have done, and what they will do to each other. The meeting is intended to disrupt old habits of working separately, and be more self-organised. For Backlog Refining Meeting, as most Product Backlog Items (PBIs) initially need refinement that they are too large and poorly understood, it is useful to take some time out of Sprint Execution to help prepare the Product Backlog for the next Sprint Planning Meeting. Review and Retrospective After the final works are finished in each Sprint, a Sprint Review Meeting and Sprint Retrospective meeting will be held (shown below). After Sprint execution, the team holds a Sprint Review Meeting to demonstrate a working product increment to the Product Owner and shareholders, and the Product Owner will declare items considered completed. Incomplete items are returned to the Product Backlog and ranked according to the Product Owner’s revised priorities as candidates for future Sprints. For stakeholders, it is the opportunity to inspect and adapt the product as it emerges, and iteratively refine everyone’s understanding of the requirements. Team Daily Scrum Meeting (Team & Scrum Master) Backlog Refining Meeting (Team & Scrum Master) Requirements Analyis & Design Implementation & Deployment Testing Evaluation
  • 19. Challenge 3: Bank Of America Lancaster University Page | 18 In the final stage of each sprint, clients and users will be involved by providing feedback of the final works. Any required improvement of the current works will be taken to next sprint and discussed in the sprint retrospective meeting. Each Sprint ends with a retrospective that the team reflects on its own process and dedicated Scrum Masters will find alternative actions for the next level. For example, at the end of Sprint 1, a sprint review meeting will be held to discuss what sprint tasks are considered completed. Suppose the task ‘search opportunities by charity’ is not completed, this task will be returned to product backlog for future sprints. Besides, clients and users will be asked to try the new features and provide feedback, which will be considered in the retrospective meeting and in Sprint 2. Furthermore, in the retrospective stage, the Agile team will reflect on the process and figure out alternatives for Sprint 2. Besides, at the end of the Sprint 4, a final review and retrospective should be implemented to review the previous work and develop alternative actions for future steps. (See implementation plan on page 19) Post Implementation After Sprint 4 is complete a beta will be released to a cross-section of employees for testing and final debugging. Other than data on number of usage and usage habits, questionnaires will be circulated asking employee’s to give their opinions on the application. The questionnaires will also ask employees to grade to what extent they believe the app matched each of the original specifications addressed by the brief. This will give the scrum team the information needed to make any necessary changes before the Go-Live date. After the Go-Live date the maintenance team will start a 12 month qualitative and quantitative study of the app. The aim of Post-implementation review (PIR) is to insure that the initial requirements were met and that the app is being well received within the company, but also to produce material that Bank of America can use for future projects. Firstly, the team will gather quantitative data to form a scope of use for the app. Metrics may include; number of users, adoption rate, daily usage rate and the number of SQL queries being run by the external server over a period of time. These metrics will be collected in real time and will go into a weekly report produced by the maintenance team. For qualitative data the team will be conducting user feedback studies through a number of circulated questionnaires. These will be sent on a quarterly basis to a cross-section of employees and will evaluate many aspects of the app such as; UI design, functionality, any problems found and overall opinion. These questionnaires may also specifically ask employee’s about the initial project requirements to see if any were not met and may need iterating in the future. The results will be analysed and compiled together with the weekly usage studies to form a benefits review that will be released on a quarterly basis. The aim of this system to insure that the project has a larger scope than simply the release of the app. The PIR process will provide Bank of America with invaluable information on its employee’s preferences and usage habits that can easily be transferred into future iterations of the volunteer app or into other projects. A plan for the post implementation can be seen on page 21.
  • 20. Page | 19 Implementation Plan Task Time Frame (8 weeks) Duration (week)1 2 3 4 5 6 7 8 Sprint1 Weeks 1-2 Identify requirements, create product backlog and sprint 1 backlog 0.5 Design search opportunities by key words 1 Design search opportunities by tags 1 Design filter opportunities by distance to user 1 Design search opportunities by location 1 Design search opportunities by charity 1 Design search opportunities by service work type 1 Implementation & deployment of new features 1 Testing on new features 1.5 Conduct surveys with clients and review feedback on the features 1 Review and retrospective of sprint 1 0.5 Sprint 2 Weeks 3-4 Select product backlog items and create sprint 2 backlog 0.2 Design automatic logging of hours after volunteering 1 Design the function to manually edit the logged hours 1 Create the visual representation of the logged hours 1 Set hours counting function towards personally set/company set goals 1 Implementation & deployment of new features 1 Testing on new features 1.8 Conduct surveys with clients and review feedback on the feature 1 Review and retrospective of sprint 2 0.5
  • 21. Challenge 3: Bank Of America Lancaster University Page | 20 Task Time Frame (8 weeks) Duration (week) 1 2 3 4 5 6 7 8 Sprint 3 Weeks 5-6 Select product backlog items and create sprint 3 backlog 0.2 Design the interface for manual logging of hours 1 Design the interface to add charities manually into the system 1 Design the function to connect employees to their respective managers 1 Design a system to request permission from managers 1 Design a system to alert managers of pending requests 1 Design a system to alert employee of approved/denied requests 1 Implementation & deployment of new features 1 Testing on new features 1.8 Promotional activities within employees (emails, updates on website) 1 Conduct surveys with clients and review feedback on the features 1 Review and retrospective of sprint 3 0.5 Sprint 4 Weeks 7-8 Select product backlog items and create sprint 4 backlog 0.2 New design of the opportunity page 1 Visualization of event capacity 1 Visualization of number of available spaces remaining 1 Filter event by popularity/availability when searching 1 Design of sending other employees suggestions for events 1 Design an incoming page to manage suggested events 1 Design a method to respond to suggested events 1
  • 22. Challenge 3: Bank Of America Lancaster University Page | 21 Task Time Frame (8 weeks) Duration (week) 1 2 3 4 5 6 7 8 Implementation & deployment of new features 1 Testing on new features 1.8 Conduct surveys with clients and review feedback on the features 1 Review and retrospective of sprint 4 0.5 Final review and retrospective of the whole project 0.5 Post Implementation Plan Task Time Frame (12 months) 3 4 5 6 7 8 9 10 11 12 Promotional activities (launch day competition, emails, updates on website) Beta version release (Android, iOS and Windows version) Review of Beta version (user & functionality) Public release (Android, iOS and Windows version) PIR – (team & users) Access usage and effect of promotion Maintenance and updates
  • 23. Page | 22 PROJECT TEAMS The project assumes one team working on the delivery of the project and the other responsible for maintenance of the application. Delivery team will be based on Agile Methodology, with 13 team members, each of them actively participating in the delivery process. Our ideal agile team is made up of one scrum master and 12 other team members. These team members would have cross-functional roles and be able to adapt their skills to the given sprint. The onshore team would work for a total 40 days, not accounting for contingencies, and the offshore maintenance team for 250 days. In the project outline, there was a list of team members which would be more suitable to the Waterfall Methodology, however, we have decided to choose roles from the list, with the assumption that each of these people would be willing and knowledgeable to work as a part of agile team. The list above is our allocation of roles from a waterfall methodology to that of a scrum team. Role Role in Agile Location Number of Employees Project Manager Scrum Master Onshore 1 Solution Architect Team 2 Test Analyst 2 UAT Analyst 2 Technical Developer (Build) 4 IT Security 2 BAU Service Manager Maintenance Offshore 1 BAU Analyst 2
  • 24. Challenge 3: Bank Of America Lancaster University Page | 23 COST ANALYSIS There are three main cost generating areas of the project: delivery team, the servers and maintenance team. The fourth section are minor costs as well as contingency cost. For the delivery team, the estimated delivery time is 2 months, which corresponds to 40 working days. In addition, personnel cost will also include the maintenance team, working for 250 days which is the full year. The delivery team is placed onshore and generates the cost of £192,000.00. (See page 18 for full breakdown.) The maintenance team will work offshore in order to decrease costs (any changes to their daily cost incurs huge differences as they work for 250 days), with total cost of £162,500.00. Servers, will be provided by a third party, as Bank of America’s servers would involve high security risk, are assumed to generate £20,000.00. This may vary depending upon the providers and negotiations with them as Bank of America may have some partners in this sector who would be able to offer reduced fees. Other costs include iOS app publishing, which is £200.00 and, for marketing purposes, launch day prize of iPad Air that would cost approximately £400.00. Contingency cost has been set at £20,000.00, which has been allocated for unexpected costs such as; project delays, changes to the sprint backlog. It is worth mentioning that these are incurred costs for accounting purposes and do not have to occur in the project’s life or afterwards. The total cost of the project is, therefore, £395,100.00, which does not exceed the given budget of £400,000.00. That shows high cost efficiency of the project as well as good resource planning, as all possible risks and additional outflowing cash flows have been taken into account. Therefore a significant part (41%) of the whole cost is the maintenance team, that we assume will work as a technological part of Bank of America. Nonetheless, this may not be required if training for already employed employees was provided and is dependent on Bank of America’s HR management.
  • 25. Page | 24 Role Role in Agile Location Number of Employees Man Day Rate Result Project Manager Scrum Master Onshore 1 £ 400.00 £ 16,000.00 Solution Architect Team 2 £ 600.00 £ 48,000.00 Test Analyst 2 £ 300.00 £ 24,000.00 UAT Analyst 2 £ 300.00 £ 24,000.00 Technical Developer (Build) 4 £ 300.00 £ 48,000.00 IT Security 2 £ 400.00 £ 32,000.00 Total: 13 Days Worked: 40 BAU Service Manager Offshore 1 £ 300.00 £ 75,000.00 BAU Analyst 2 £ 175.00 £ 87,500.00 Total: 3 Days Worked: 250 Additional Costs Servers £ 20,000.00 iOS app publishing £ 200.00 Contingency cost (provision for updates) £ 20,000.00 Marketing Cost £ 2 000.00 Total £ 396, 700.00
  • 26. Page | 25 RAIDS ANALYSIS Risks Risk Impact Mitigation Likelihood: Medium Poor marketing of a new application may result in low downloading volume This would result in low participation rate and employee disengagement. Hosting a launch event where employees can win a prize. Changing expectations of the product owner A delay in implementation Scrum methodology allows for an agile response to any product requirements. Likelihood: Low Lack of access to smart technology Exclusion of employees The application will work parallel with the website. Hacking The impact of hacking is low because the pauses in the functioning of the system would not affect the final volunteering results to a great extent. The application will use advanced security protocols. Data theft The impact of hacking would be quite low as the data stored in the application will not be confidential relatively to other bank data. The application will use advanced security protocols. Exchange rate variability It may affect salaries for off- shore employees, which subsequently may cause budget constraint. Budget accounts for contingency costs.
  • 27. Challenge 3: Bank Of America Lancaster University Page | 26 Assumptions 1. Estimated up to 200 000 unique users in 12 months’ time 2. Each sprint takes two weeks to complete 3. Project delivery time is 2 months (40 working days) 4. Salaries proposed in the budget include tax Technical a. Application download size is between 50-100 MB b. Devices have an internet access c. Application works independently from bank’s internal website d. Users have at least iOS 7 or Android Jelly Bean software versions on the mobile devices Functional e. The team is cross-functional and self-managing. Each employee is engaged at every stage of product design, development and implementation f. The scrum team is based on-shore to facilitate effective communication with a product owner. g. The BAU team is based off-shore for the efficiency and cost-saving reasons h. The provision for unexpected costs is set in the budget i. The product owner is involved in every sprint review meeting Issues 1. Privacy issue: bank employees publicly disclose their volunteering activity Most issue will result after the project commences, usually being realized from the risks. Dependencies 5. The progression from one sprint to another depends on a feedback from the product owner 6. The final UI design depends on the users feedback after the beta version is released 7. The maximum size of the application depends on the maximum amount of space designated for it in an external server 8. Speed of application depends as well on the speed on the internet connection and on the version of the software installed 9. 10. Because in Agile methodology sprints are independent of each other, the dependencies list is significantly reduced.