Due to the diverse projects within Tanga Region, the
  region will be divided into three operational areas
Motivational Factors:

To decrease the demand in the complexity of planning and to enhance
and secure fluent logistics at all times

To simplify the overall management of the various projects within the
region into three confined areas and project boundaries

To have better control and coordination over the reporting
structures, movement of personnel, materials and equipment

To identify the availability and utilization of specific resources within
specific areas

To optimize the use of all available resources in the region when and
where needed, including “crossboundry” activities
Team 1




Team 2




                  Team 3
Project Statistics



Total Estimated Line                            Material
       Lengths


             HV -
            56Km
             20%

     LV -
    225Km
     80%


                                  HV Poles - 542     LV Poles - 4467
                                  Trfr's - 46
Regional Organogram
                                     Regional
                                     Manager



                    Local             Local              Local
                  Supervisor        Supervisor         Supervisor


                  Foreman            Foreman           Foreman


                  Linesman           Linesman          Linesman
                     (9)                (9)               (9)

                    Driver            Driver             Driver
Key:                 (2)               (3)                (3)
Lushoto Team
Korogwe Team
Tanga City Team
                      All teams to consist of HV and LV personnel
Vehicles and Equipment
                   Regional Manager
                   1 x D/Cab Pick-Up



Local Supervisor   Local Supervisor    Local Supervisor
  1 x Pick-Up        1 x Pick-Up         1 x Pick-Up

   1 x Bedford         1 x Bedford        1 x Bedford
truck with crane    truck with crane   truck with crane


2 x Compressors      1 x Line truck     1 x Line truck



1 x Wire Puller     1 x Bucket truck   1 x Bucket truck



 1 x Tensioner      1 x Wire Trailer   1 x Wire Trailer


                     1 x Personnel      1 x Personnel
1 x Pole Trailer
                         Carrier            Carrier


1 x Wire Trailer
                                                          Key:
  1 x Tractor                                             Lushoto Team
                                                          Korogwe Team
 1 x Personnel                                            Tanga City Team
     Carrier
Regional Issues and Concerns


Communication

Cellphone Service Providers in regional areas

Internet availability for regional areas

Safety of Public and property during construction in Tanga City

Bush clearing and demolishing of buildings in rural areas

Material Schedules – Dependant on suppliers

Project commencement schedules
Communication tools for region


                                 Phones
 Cellphones with the option of three different Service Providers

 Service providers - Airtel, Vodacom and Tigo

 Cost = Tsh 90 000 for Nokia K7 and Tsh 1 000 per Sim card


                                Internet
 TCCL for office in Tanga

 Vodacom Internet dongles for Lushoto and Korogwe

 Cost = Tsh 25 000 per dongle and Tsh 30 000 for uncapped data per month
Safety of public, property and staff during
                construction in Tanga City


 Schedule road closures/diversions in conjunction with Traffic
authorities when and where necessary

 Maintain road closures if necessary

 Secure road closures after hours when and where necessary with
assistance of local police

 Barricading of excavations/construction areas when and where
necessary

Schedule power outages with Tanesco locally for LV shutdowns

Schedule power outages with Tanesco Control Room Scheduler for HV
shutdowns
Bush clearing and demolishing of buildings in rural areas
 Muheza District:

 Lot of bush clearing, including large trees to be
 done, as well as demolishing of structures in path of
 line

 Line access would not be an issue

 Korogwe District:

 Lot of bush clearing, including large trees to be done

 Line access would not be an issue

  Lushoto District:

 Lot of bush clearing, including large trees to be done

 Line access is a major issue, especially Line 518, dual
 structure on top of mountain
Outstanding tasks for Tanga region
Completed tasks for Tanga region


Meet with Tanesco Regional Manager
Meet with MCAT Engineer
Meet with Tanesco Manager for Muheza District
Meet with Tanesco Supervisor for Muheza District
Meet with Tanesco Manager for Korogwe District
Meet with Tanesco Supervisor for Korogwe District

Project priorities as set out by the client:

1.   Muheza District
2.   Korogwe District
3.   Lushoto District
4.   Handeni District
5.   Kiringi District

More Related Content

Viewers also liked

November 2013: Healthcare Tech Analysis
November 2013: Healthcare Tech AnalysisNovember 2013: Healthcare Tech Analysis
November 2013: Healthcare Tech AnalysisTyler Soliday
 
Artroplastia total do quadril em espondilite anquilosante
Artroplastia total do quadril em espondilite anquilosanteArtroplastia total do quadril em espondilite anquilosante
Artroplastia total do quadril em espondilite anquilosanteFisiohcare
 
RegisterPatient- Facebook App
RegisterPatient- Facebook AppRegisterPatient- Facebook App
RegisterPatient- Facebook AppTyler Soliday
 
Punjabppt 091109114016-phpapp01
Punjabppt 091109114016-phpapp01Punjabppt 091109114016-phpapp01
Punjabppt 091109114016-phpapp01Akhilesh Shukla
 
Apple HealthKit Impact on HealthIT: Rough Draft
Apple HealthKit Impact on HealthIT: Rough DraftApple HealthKit Impact on HealthIT: Rough Draft
Apple HealthKit Impact on HealthIT: Rough DraftTyler Soliday
 
Register Patient: Product Features
Register Patient: Product Features Register Patient: Product Features
Register Patient: Product Features Tyler Soliday
 
Harness the power of internal social media
Harness the power of internal social mediaHarness the power of internal social media
Harness the power of internal social mediasikandarbansal
 
Team 5 Brand Concept Presentation- RTV4930
Team 5 Brand Concept Presentation- RTV4930Team 5 Brand Concept Presentation- RTV4930
Team 5 Brand Concept Presentation- RTV4930Tyler Soliday
 
Healthcare Technology: Markets To 2020
Healthcare Technology: Markets To 2020Healthcare Technology: Markets To 2020
Healthcare Technology: Markets To 2020Tyler Soliday
 
The teaching of mathematics
The teaching of mathematicsThe teaching of mathematics
The teaching of mathematicsRaveendranath Vs
 
Urban planning presentation 01
Urban planning presentation 01Urban planning presentation 01
Urban planning presentation 01Halima A. Othman
 

Viewers also liked (15)

Guide for parents
Guide for parentsGuide for parents
Guide for parents
 
November 2013: Healthcare Tech Analysis
November 2013: Healthcare Tech AnalysisNovember 2013: Healthcare Tech Analysis
November 2013: Healthcare Tech Analysis
 
Artroplastia total do quadril em espondilite anquilosante
Artroplastia total do quadril em espondilite anquilosanteArtroplastia total do quadril em espondilite anquilosante
Artroplastia total do quadril em espondilite anquilosante
 
RegisterPatient- Facebook App
RegisterPatient- Facebook AppRegisterPatient- Facebook App
RegisterPatient- Facebook App
 
DesignerFred
DesignerFredDesignerFred
DesignerFred
 
Presentation slides
Presentation slidesPresentation slides
Presentation slides
 
Probability +2
Probability +2Probability +2
Probability +2
 
Punjabppt 091109114016-phpapp01
Punjabppt 091109114016-phpapp01Punjabppt 091109114016-phpapp01
Punjabppt 091109114016-phpapp01
 
Apple HealthKit Impact on HealthIT: Rough Draft
Apple HealthKit Impact on HealthIT: Rough DraftApple HealthKit Impact on HealthIT: Rough Draft
Apple HealthKit Impact on HealthIT: Rough Draft
 
Register Patient: Product Features
Register Patient: Product Features Register Patient: Product Features
Register Patient: Product Features
 
Harness the power of internal social media
Harness the power of internal social mediaHarness the power of internal social media
Harness the power of internal social media
 
Team 5 Brand Concept Presentation- RTV4930
Team 5 Brand Concept Presentation- RTV4930Team 5 Brand Concept Presentation- RTV4930
Team 5 Brand Concept Presentation- RTV4930
 
Healthcare Technology: Markets To 2020
Healthcare Technology: Markets To 2020Healthcare Technology: Markets To 2020
Healthcare Technology: Markets To 2020
 
The teaching of mathematics
The teaching of mathematicsThe teaching of mathematics
The teaching of mathematics
 
Urban planning presentation 01
Urban planning presentation 01Urban planning presentation 01
Urban planning presentation 01
 

Similar to Tanga Regional Planning Presentation 1 [Autosaved]

Integrating Technology into Water Trail Managemetnt Practices - Walter Opusz...
Integrating Technology into Water Trail  Managemetnt Practices - Walter Opusz...Integrating Technology into Water Trail  Managemetnt Practices - Walter Opusz...
Integrating Technology into Water Trail Managemetnt Practices - Walter Opusz...rshimoda2014
 
Group 2 PPP Workshop PPT_Final.pptx
Group 2 PPP Workshop PPT_Final.pptxGroup 2 PPP Workshop PPT_Final.pptx
Group 2 PPP Workshop PPT_Final.pptxPMUHaryanaTourism
 
Future of Traffic Management and ITS
Future of Traffic Management and ITSFuture of Traffic Management and ITS
Future of Traffic Management and ITSSerge Hoogendoorn
 
L1 Traffic Flow Parameters
L1 Traffic Flow ParametersL1 Traffic Flow Parameters
L1 Traffic Flow ParametersHossam Shafiq I
 
IoT beneath your feet - building smart roads and networks
IoT beneath your feet - building smart roads and networksIoT beneath your feet - building smart roads and networks
IoT beneath your feet - building smart roads and networksAlcatel-Lucent Enterprise
 

Similar to Tanga Regional Planning Presentation 1 [Autosaved] (7)

Integrating Technology into Water Trail Managemetnt Practices - Walter Opusz...
Integrating Technology into Water Trail  Managemetnt Practices - Walter Opusz...Integrating Technology into Water Trail  Managemetnt Practices - Walter Opusz...
Integrating Technology into Water Trail Managemetnt Practices - Walter Opusz...
 
Transportation
TransportationTransportation
Transportation
 
Group 2 PPP Workshop PPT_Final.pptx
Group 2 PPP Workshop PPT_Final.pptxGroup 2 PPP Workshop PPT_Final.pptx
Group 2 PPP Workshop PPT_Final.pptx
 
Future of Traffic Management and ITS
Future of Traffic Management and ITSFuture of Traffic Management and ITS
Future of Traffic Management and ITS
 
L1 Traffic Flow Parameters
L1 Traffic Flow ParametersL1 Traffic Flow Parameters
L1 Traffic Flow Parameters
 
IoT beneath your feet - building smart roads and networks
IoT beneath your feet - building smart roads and networksIoT beneath your feet - building smart roads and networks
IoT beneath your feet - building smart roads and networks
 
Overview of transnet port terminals
Overview of transnet port terminalsOverview of transnet port terminals
Overview of transnet port terminals
 

Tanga Regional Planning Presentation 1 [Autosaved]

  • 1.
  • 2. Due to the diverse projects within Tanga Region, the region will be divided into three operational areas Motivational Factors: To decrease the demand in the complexity of planning and to enhance and secure fluent logistics at all times To simplify the overall management of the various projects within the region into three confined areas and project boundaries To have better control and coordination over the reporting structures, movement of personnel, materials and equipment To identify the availability and utilization of specific resources within specific areas To optimize the use of all available resources in the region when and where needed, including “crossboundry” activities
  • 3. Team 1 Team 2 Team 3
  • 4. Project Statistics Total Estimated Line Material Lengths HV - 56Km 20% LV - 225Km 80% HV Poles - 542 LV Poles - 4467 Trfr's - 46
  • 5. Regional Organogram Regional Manager Local Local Local Supervisor Supervisor Supervisor Foreman Foreman Foreman Linesman Linesman Linesman (9) (9) (9) Driver Driver Driver Key: (2) (3) (3) Lushoto Team Korogwe Team Tanga City Team All teams to consist of HV and LV personnel
  • 6. Vehicles and Equipment Regional Manager 1 x D/Cab Pick-Up Local Supervisor Local Supervisor Local Supervisor 1 x Pick-Up 1 x Pick-Up 1 x Pick-Up 1 x Bedford 1 x Bedford 1 x Bedford truck with crane truck with crane truck with crane 2 x Compressors 1 x Line truck 1 x Line truck 1 x Wire Puller 1 x Bucket truck 1 x Bucket truck 1 x Tensioner 1 x Wire Trailer 1 x Wire Trailer 1 x Personnel 1 x Personnel 1 x Pole Trailer Carrier Carrier 1 x Wire Trailer Key: 1 x Tractor Lushoto Team Korogwe Team 1 x Personnel Tanga City Team Carrier
  • 7. Regional Issues and Concerns Communication Cellphone Service Providers in regional areas Internet availability for regional areas Safety of Public and property during construction in Tanga City Bush clearing and demolishing of buildings in rural areas Material Schedules – Dependant on suppliers Project commencement schedules
  • 8. Communication tools for region Phones  Cellphones with the option of three different Service Providers  Service providers - Airtel, Vodacom and Tigo  Cost = Tsh 90 000 for Nokia K7 and Tsh 1 000 per Sim card Internet  TCCL for office in Tanga  Vodacom Internet dongles for Lushoto and Korogwe  Cost = Tsh 25 000 per dongle and Tsh 30 000 for uncapped data per month
  • 9. Safety of public, property and staff during construction in Tanga City  Schedule road closures/diversions in conjunction with Traffic authorities when and where necessary  Maintain road closures if necessary  Secure road closures after hours when and where necessary with assistance of local police  Barricading of excavations/construction areas when and where necessary Schedule power outages with Tanesco locally for LV shutdowns Schedule power outages with Tanesco Control Room Scheduler for HV shutdowns
  • 10. Bush clearing and demolishing of buildings in rural areas Muheza District: Lot of bush clearing, including large trees to be done, as well as demolishing of structures in path of line Line access would not be an issue Korogwe District: Lot of bush clearing, including large trees to be done Line access would not be an issue  Lushoto District: Lot of bush clearing, including large trees to be done Line access is a major issue, especially Line 518, dual structure on top of mountain
  • 11. Outstanding tasks for Tanga region
  • 12. Completed tasks for Tanga region Meet with Tanesco Regional Manager Meet with MCAT Engineer Meet with Tanesco Manager for Muheza District Meet with Tanesco Supervisor for Muheza District Meet with Tanesco Manager for Korogwe District Meet with Tanesco Supervisor for Korogwe District Project priorities as set out by the client: 1. Muheza District 2. Korogwe District 3. Lushoto District 4. Handeni District 5. Kiringi District