WHAT ARE THE PHASES OF THE SYSTEM
DEVELOPMENT CYCLE?
Phase 1. Planning
Phase 2. Analysis
Phase 3. Design
Phase 4. Implementation
Phase 5. Support
 Review project requests
 Prioritize project
requests
 Allocate resources
 Identify project
development team
 Conduct preliminary investigation
 Perform detailed analysis activities:
Study current system
Determine user requirements
Recommend solution
 Acquire hardware
and software, if
necessary
 Develop details of
system
 Develop programs, if necessary
 Install and test new system
 Train users
 Convert to new system
 Conduct post-implementation
system review
 Identify errors and enhancements
 Monitor system performance
WHO PARTICIPATES IN THE SDLC?
WHAT IS A SYSTEMS ANALYST?
Responsible for designing
and developing
information system
Liaison between users
and IT professionals
WHAT IS THE PROJECT TEAM?
Consists of users, systems analyst, and other IT professionals
Formed to work on project from beginning to end
Project leader—one member of the team who
manages and controls project budget and schedule
WHAT IS FEASIBILITY?
Measure of
how suitable
system
development
will be to the
company
Operational
feasibility
Schedule
feasibility
Four feasibility
tests:
Technical
feasibility
Economic
feasibility
(also called
cost/benefit
feasibility)
WHAT IS DOCUMENTATION?
Includes reports, diagrams,
programs, and other deliverables
Collection and summarization
of data and information
WHY CREATE (OR MODIFY) AN
INFORMATION SYSTEM?
Competition can
lead to change
To improve
existing system
Outside group may
mandate change
To correct problem
in existing system
WHAT IS A REQUEST FOR SYSTEM
SERVICES?
 Formal request for
new or modified
information system
 Also called
project request
PLANNING PHASE
Begins when steering committee receives project request
Steering
committee—
decision-making
body for the
company
Function of committee:
Review and
approve project
requests
Allocate
resources
Form project
development
team for each
approved
project
Prioritize
project requests
ANALYSIS PHASE
Conduct preliminary
investigation, also
called feasibility
study
Perform detailed
analysis
PRELIMINARY INVESTIGATION
 Determine exact nature of problem or improvement
and whether it is worth pursuing
 Findings are presented in feasibility report, also known as a feasibility study
DETAILED ANALYSIS
Sometimes called logical design
2. Determine user’s wants, needs,
and requirements
3. Recommend solution
1. Study how current system
works
SYSTEM PROPOSAL
Presented to
steering
committee,
which decides
how system will
be developed
Assesses
feasibility
of each
alternative
solution
Recommends
the most
feasible
solution for
the project
IDENTIFY POSSIBLE SOLUTIONS
Buy packaged software—prewritten
software available for purchase
Outsource—have outside source
develop software
Write own custom software—software
developed at user’s request
Vertical market
software—designed
for particular industry
Horizontal market
software—meets
needs of many
companies
DESIGN PHASE
Acquire hardware and software
Develop all details of new or
modified information system
Visit vendors’ stores
ACQUISITION
What is needed to acquire new hardware and software?
 Identify all hardware and software requirements of new
or modified system
Surf Web
Read print and online
trade journals,
newspapers, and
magazines
Talk with other
systems analysts
HOW TO TEST SOFTWARE PRODUCTS?
 References from vendor
 Talk to current users of product
 Product demonstrations
 Trial version of software
 Benchmark test measures performance
DETAILED DESIGN
Includes several activities
Database
design
Input and
output design
Program
design
Detailed design specifications for components in proposed solution
PROTOTYPING TOOLS/METHODS:
MOCKUP
 Sample of input or output that contains actual data
PROTOTYPING TOOLS/METHODS:
PROTOTYPE
Working model of
proposed system
Beginning a prototype
too early may lead to
problems
PROTOTYPING TOOLS/METHODS:
CASE
 CASE (Computer-Aided Software Engineering) tools
support activities of the SDLC
Convert to new system
IMPLEMENTATION PHASE
 Purpose is to construct, or build, new or modified
system and then deliver it to users
Train users
Install and test new system
Develop programs
TESTING
Three kinds of tests performed by system developers:
Verifies application
works with other
applications
Systems test
Integration Test
Unit Test
Verifies each
individual program
works by itself
Verifies all programs
in application work
together
TRAINING
 Showing users exactly how they will use new
hardware and software in system
SUPPORT PHASE
Conduct post-implementation system review—meeting to find out if
information system is performing according to expectations
Identify errors
Identify enhancements
Monitor system performance
 Providing ongoing assistance after the system is
implemented
FEASIBILITY
 Every organization which performs system
development, or has it done for them, needs a way
to choose which projects are worth
the effort
 Feasibility study is a common approach to make
such decisions thoughtfully
 Basis for feasibility study is generally the problems
and opportunities analysis
PROBLEMS & OPPORTUNITIES
 We can look for problems and opportunities in
many parts of our organization, and the existing
systems which are supported
 Track maintenance costs for existing systems
 Measure existing processes to determine their cost, and
compare to industry standards
 Monitor availability of support for existing
system components
 Look for signs of unhappy employees
 Check quality of work products (outputs)
 Listen to customers, vendors, and suppliers
 Both complaints and suggestions
 Measure customer satisfaction
 Monitor competitor’s offerings and plans
 Monitor changes in technology which could help
 Don’t forget obvious measures of success, like sales,
profit, or number of contracts awarded
PROBLEMS & OPPORTUNITIES
PROJECT SELECTION
 Selection of projects is based on many factors –
cost, urgency, the systems
affected, etc.
 From the organization’s perspective, choosing
projects is kind of like shopping
 There’s generally a limited amount of funds
and people available to work on the possible projects,
and management needs to choose which projects to
support
 There are five typical requirements for a project to
be supported
 Management support for the project
 Appropriate timing of commitment to the project
 Relevance to helping meet organizational goals
 Project must be practical and feasible
 Project must be worthwhile compared to other possible
expenditures
 Are we getting enough ‘bang for our buck?’
PROJECT SELECTION
PROJECT OBJECTIVES
 Based on the problems and opportunities identified
for a project, we can set objectives for the project
 These not only help the feasibility study which follows,
but set goals against which we can later test the system
 Objectives should not only address the type of
improvement sought, but set a desired level of
improvement
 Examples of objectives might include
 Improve customer satisfaction 10% within 1 year
 Reduce the response time for customer complaints by
15%
 Get a new feature to market before competitors
 Reduce error rate for data entry from 2% to 0.5%
 Improve sales to new customers by 5%
 Reduce voluntary employee turnover by 10%
PROJECT OBJECTIVES
FEASIBILITY ANALYSIS
 Feasibility consists of several types we want to
assess for each candidate project
 Technical feasibility
 Can the project be done with existing technology?
 Are people available to use the technologies needed?
 Economic feasibility
 How much does the system cost to develop? Maintain? How
long will it be usable?
 Some add schedule feasibility – how long will it take
to create the system?
 Operational feasibility
 What impact will the new system have on how we do
business? Will there be changes to where or how processes
are performed?
 Will there be changes to employee skills needed? Changes to
employee training?
 Are existing users amenable to a new system?
 These types of feasibility can be measured for each
project, and compared to determine which is most
feasible
FEASIBILITY ANALYSIS
 Like voting or buying a car, feasibility analysis is
rarely completely logical or quantifiable
 Many other issues can also affect it
 Political climate
 State of the US and/or global economy
 Preferences of the decision makers – favored vendors,
technologies, types of projects, etc.
FEASIBILITY ANALYSIS
PLANNING ACTIVITIES
 To help structure development activities, we use a
life cycle model to identify the major sets of
activities, called life cycle phases
 There are many kinds of life cycle models
 The Waterfall model is the oldest, and uses phases like
Requirements Analysis, High Level Design, Low Level
Design, Coding, and Testing
 The Rational Unified Process has Inception,
Elaboration, Construction, and Transition phases
 Each life cycle phase is broken down into more and
more specific activities, until
the time needed for each activity can be reliably
estimated
 Then the tasks are put into a Gantt chart or Pert
chart to show when they occur relative
to each other
 Tasks might occur sequentially, have to start
or end together, or wait for some other tasks
to be completed
PLANNING VIA THE SDLC
 Tasks for a project often include the acts of creating
specific documents or work products, approving things
or making decisions; such as
 ‘Prepare system test plan’
 ‘Approve system release’
 ‘Conduct user satisfaction survey’
 ‘Approve system requirements specification’
 So the life cycle model provides guidance on the
types of activities needed, but the tasks provide
authority for people to do them
PLANNING VIA THE SDLC
WATERFALL MODEL
FEATURES OF A WATERFALL MODEL
 A waterfall model is easy to follow.
 It can be implemented for any size project.
 Every stage has to be done separately at the right time
so you cannot jump stages.
 Documentation is produced at every stage of a waterfall
model allowing people to understand what has been
done.
 Testing is done at every stage.
ADVANTAGES OF A WATERFALL MODEL
 Easy to understand, easy to use
 Provides structure to inexperienced staff
 Milestones are well understood
 Sets requirements stability
 Good for management control (plan, staff, track)
 Works well when quality is more important than cost or
schedule
DISADVANTAGES OF A WATERFALL MODEL
 All requirements must be known up front
 Deliverables created for each phase are considered
frozen – inhibits flexibility
 Can give a false impression of progress
 Does not reflect problem-solving nature of software
development – iterations of phases
 Integration is one big bang at the end
 Little opportunity for customer to preview the system
(until it may be too late)
WHEN TO USE THE WATERFALL MODEL
 Requirements are very well known
 Product definition is stable
 Technology is understood
 New version of an existing product
 Porting an existing product to a new platform.
AGILE SDLCS
 Speed up or bypass one or more life cycle phases
 Usually less formal and reduced scope
 Used for time-critical applications
 Used in organizations that employ disciplined
methods
AGILE MANIFESTO
SOME AGILE METHODS
 Adaptive Software Development (ASD)
 Feature Driven Development (FDD)
 Crystal Clear
 Dynamic Software Development Method
(DSDM)
 Rapid Application Development (RAD)
 Scrum
 Extreme Programming (XP)
 Rational Unify Process (RUP)
EXTREME PROGRAMMING - XP
For small-to-medium-sized teams developing
software with vague or rapidly changing
requirements
Coding is the key activity throughout a software
project
 Communication among teammates is done with
code
 Life cycle and behavior of complex objects defined
in test cases – again in code
XP PRACTICES (1-6)
1. Planning game – determine scope of the next release
by combining business priorities and technical
estimates
2. Small releases – put a simple system into production,
then release new versions in very short cycle
3. Metaphor – all development is guided by a simple
shared story of how the whole system works
4. Simple design – system is designed as simply as
possible (extra complexity removed as soon as found)
5. Testing – programmers continuously write unit tests;
customers write tests for features
6. Refactoring – programmers continuously restructure
the system without changing its behavior to remove
duplication and simplify
XP Practices (7 – 12)
7. Pair-programming -- all production code is written with
two programmers at one machine
8. Collective ownership – anyone can change any code
anywhere in the system at any time.
9. Continuous integration – integrate and build the
system many times a day – every time a task is
completed.
10. 40-hour week – work no more than 40 hours a week
as a rule
11. On-site customer – a user is on the team and available
full-time to answer questions
12. Coding standards – programmers write all code in
accordance with rules emphasizing communication
through the code
XP is “extreme” because
Commonsense practices taken to extreme levels
 If code reviews are good, review code all the time (pair
programming)
 If testing is good, everybody will test all the time
 If simplicity is good, keep the system in the simplest design that
supports its current functionality. (simplest thing that works)
 If design is good, everybody will design daily (refactoring)
 If architecture is important, everybody will work at defining and
refining the architecture (metaphor)
 If integration testing is important, build and integrate test several
times a day (continuous integration)
 If short iterations are good, make iterations really, really short (hours
rather than weeks)
SUMMARY
 This has been a (very) quick tour through the life
cycle of a system.
 You will have to do—to some extent—all of these
activities for your project.

SDLC_Intro.ppt

  • 1.
  • 2.
    WHAT IS ANINFORMATION SYSTEM (IS)? Hardware, software, data, people, and procedures that work together to produce quality information System—Set of components that interact to achieve common goal Businesses use many types of systems
  • 3.
    WHAT ARE THEPHASES OF THE SYSTEM DEVELOPMENT CYCLE? Phase 1. Planning Phase 2. Analysis Phase 3. Design Phase 4. Implementation Phase 5. Support  Review project requests  Prioritize project requests  Allocate resources  Identify project development team  Conduct preliminary investigation  Perform detailed analysis activities: Study current system Determine user requirements Recommend solution  Acquire hardware and software, if necessary  Develop details of system  Develop programs, if necessary  Install and test new system  Train users  Convert to new system  Conduct post-implementation system review  Identify errors and enhancements  Monitor system performance
  • 4.
  • 5.
    WHAT IS ASYSTEMS ANALYST? Responsible for designing and developing information system Liaison between users and IT professionals
  • 6.
    WHAT IS THEPROJECT TEAM? Consists of users, systems analyst, and other IT professionals Formed to work on project from beginning to end Project leader—one member of the team who manages and controls project budget and schedule
  • 7.
    WHAT IS FEASIBILITY? Measureof how suitable system development will be to the company Operational feasibility Schedule feasibility Four feasibility tests: Technical feasibility Economic feasibility (also called cost/benefit feasibility)
  • 8.
    WHAT IS DOCUMENTATION? Includesreports, diagrams, programs, and other deliverables Collection and summarization of data and information
  • 9.
    WHY CREATE (ORMODIFY) AN INFORMATION SYSTEM? Competition can lead to change To improve existing system Outside group may mandate change To correct problem in existing system
  • 10.
    WHAT IS AREQUEST FOR SYSTEM SERVICES?  Formal request for new or modified information system  Also called project request
  • 11.
    PLANNING PHASE Begins whensteering committee receives project request Steering committee— decision-making body for the company Function of committee: Review and approve project requests Allocate resources Form project development team for each approved project Prioritize project requests
  • 12.
    ANALYSIS PHASE Conduct preliminary investigation,also called feasibility study Perform detailed analysis
  • 13.
    PRELIMINARY INVESTIGATION  Determineexact nature of problem or improvement and whether it is worth pursuing  Findings are presented in feasibility report, also known as a feasibility study
  • 14.
    DETAILED ANALYSIS Sometimes calledlogical design 2. Determine user’s wants, needs, and requirements 3. Recommend solution 1. Study how current system works
  • 15.
    SYSTEM PROPOSAL Presented to steering committee, whichdecides how system will be developed Assesses feasibility of each alternative solution Recommends the most feasible solution for the project
  • 16.
    IDENTIFY POSSIBLE SOLUTIONS Buypackaged software—prewritten software available for purchase Outsource—have outside source develop software Write own custom software—software developed at user’s request Vertical market software—designed for particular industry Horizontal market software—meets needs of many companies
  • 17.
    DESIGN PHASE Acquire hardwareand software Develop all details of new or modified information system
  • 18.
    Visit vendors’ stores ACQUISITION Whatis needed to acquire new hardware and software?  Identify all hardware and software requirements of new or modified system Surf Web Read print and online trade journals, newspapers, and magazines Talk with other systems analysts
  • 19.
    HOW TO TESTSOFTWARE PRODUCTS?  References from vendor  Talk to current users of product  Product demonstrations  Trial version of software  Benchmark test measures performance
  • 20.
    DETAILED DESIGN Includes severalactivities Database design Input and output design Program design Detailed design specifications for components in proposed solution
  • 21.
    PROTOTYPING TOOLS/METHODS: MOCKUP  Sampleof input or output that contains actual data
  • 22.
    PROTOTYPING TOOLS/METHODS: PROTOTYPE Working modelof proposed system Beginning a prototype too early may lead to problems
  • 23.
    PROTOTYPING TOOLS/METHODS: CASE  CASE(Computer-Aided Software Engineering) tools support activities of the SDLC
  • 24.
    Convert to newsystem IMPLEMENTATION PHASE  Purpose is to construct, or build, new or modified system and then deliver it to users Train users Install and test new system Develop programs
  • 25.
    TESTING Three kinds oftests performed by system developers: Verifies application works with other applications Systems test Integration Test Unit Test Verifies each individual program works by itself Verifies all programs in application work together
  • 26.
    TRAINING  Showing usersexactly how they will use new hardware and software in system
  • 27.
    SUPPORT PHASE Conduct post-implementationsystem review—meeting to find out if information system is performing according to expectations Identify errors Identify enhancements Monitor system performance  Providing ongoing assistance after the system is implemented
  • 28.
    FEASIBILITY  Every organizationwhich performs system development, or has it done for them, needs a way to choose which projects are worth the effort  Feasibility study is a common approach to make such decisions thoughtfully  Basis for feasibility study is generally the problems and opportunities analysis
  • 29.
    PROBLEMS & OPPORTUNITIES We can look for problems and opportunities in many parts of our organization, and the existing systems which are supported  Track maintenance costs for existing systems  Measure existing processes to determine their cost, and compare to industry standards  Monitor availability of support for existing system components  Look for signs of unhappy employees
  • 30.
     Check qualityof work products (outputs)  Listen to customers, vendors, and suppliers  Both complaints and suggestions  Measure customer satisfaction  Monitor competitor’s offerings and plans  Monitor changes in technology which could help  Don’t forget obvious measures of success, like sales, profit, or number of contracts awarded PROBLEMS & OPPORTUNITIES
  • 31.
    PROJECT SELECTION  Selectionof projects is based on many factors – cost, urgency, the systems affected, etc.  From the organization’s perspective, choosing projects is kind of like shopping  There’s generally a limited amount of funds and people available to work on the possible projects, and management needs to choose which projects to support
  • 32.
     There arefive typical requirements for a project to be supported  Management support for the project  Appropriate timing of commitment to the project  Relevance to helping meet organizational goals  Project must be practical and feasible  Project must be worthwhile compared to other possible expenditures  Are we getting enough ‘bang for our buck?’ PROJECT SELECTION
  • 33.
    PROJECT OBJECTIVES  Basedon the problems and opportunities identified for a project, we can set objectives for the project  These not only help the feasibility study which follows, but set goals against which we can later test the system  Objectives should not only address the type of improvement sought, but set a desired level of improvement
  • 34.
     Examples ofobjectives might include  Improve customer satisfaction 10% within 1 year  Reduce the response time for customer complaints by 15%  Get a new feature to market before competitors  Reduce error rate for data entry from 2% to 0.5%  Improve sales to new customers by 5%  Reduce voluntary employee turnover by 10% PROJECT OBJECTIVES
  • 35.
    FEASIBILITY ANALYSIS  Feasibilityconsists of several types we want to assess for each candidate project  Technical feasibility  Can the project be done with existing technology?  Are people available to use the technologies needed?  Economic feasibility  How much does the system cost to develop? Maintain? How long will it be usable?  Some add schedule feasibility – how long will it take to create the system?
  • 36.
     Operational feasibility What impact will the new system have on how we do business? Will there be changes to where or how processes are performed?  Will there be changes to employee skills needed? Changes to employee training?  Are existing users amenable to a new system?  These types of feasibility can be measured for each project, and compared to determine which is most feasible FEASIBILITY ANALYSIS
  • 37.
     Like votingor buying a car, feasibility analysis is rarely completely logical or quantifiable  Many other issues can also affect it  Political climate  State of the US and/or global economy  Preferences of the decision makers – favored vendors, technologies, types of projects, etc. FEASIBILITY ANALYSIS
  • 38.
    PLANNING ACTIVITIES  Tohelp structure development activities, we use a life cycle model to identify the major sets of activities, called life cycle phases  There are many kinds of life cycle models  The Waterfall model is the oldest, and uses phases like Requirements Analysis, High Level Design, Low Level Design, Coding, and Testing  The Rational Unified Process has Inception, Elaboration, Construction, and Transition phases
  • 39.
     Each lifecycle phase is broken down into more and more specific activities, until the time needed for each activity can be reliably estimated  Then the tasks are put into a Gantt chart or Pert chart to show when they occur relative to each other  Tasks might occur sequentially, have to start or end together, or wait for some other tasks to be completed PLANNING VIA THE SDLC
  • 40.
     Tasks fora project often include the acts of creating specific documents or work products, approving things or making decisions; such as  ‘Prepare system test plan’  ‘Approve system release’  ‘Conduct user satisfaction survey’  ‘Approve system requirements specification’  So the life cycle model provides guidance on the types of activities needed, but the tasks provide authority for people to do them PLANNING VIA THE SDLC
  • 41.
  • 42.
    FEATURES OF AWATERFALL MODEL  A waterfall model is easy to follow.  It can be implemented for any size project.  Every stage has to be done separately at the right time so you cannot jump stages.  Documentation is produced at every stage of a waterfall model allowing people to understand what has been done.  Testing is done at every stage.
  • 43.
    ADVANTAGES OF AWATERFALL MODEL  Easy to understand, easy to use  Provides structure to inexperienced staff  Milestones are well understood  Sets requirements stability  Good for management control (plan, staff, track)  Works well when quality is more important than cost or schedule
  • 44.
    DISADVANTAGES OF AWATERFALL MODEL  All requirements must be known up front  Deliverables created for each phase are considered frozen – inhibits flexibility  Can give a false impression of progress  Does not reflect problem-solving nature of software development – iterations of phases  Integration is one big bang at the end  Little opportunity for customer to preview the system (until it may be too late)
  • 45.
    WHEN TO USETHE WATERFALL MODEL  Requirements are very well known  Product definition is stable  Technology is understood  New version of an existing product  Porting an existing product to a new platform.
  • 46.
    AGILE SDLCS  Speedup or bypass one or more life cycle phases  Usually less formal and reduced scope  Used for time-critical applications  Used in organizations that employ disciplined methods
  • 47.
  • 48.
    SOME AGILE METHODS Adaptive Software Development (ASD)  Feature Driven Development (FDD)  Crystal Clear  Dynamic Software Development Method (DSDM)  Rapid Application Development (RAD)  Scrum  Extreme Programming (XP)  Rational Unify Process (RUP)
  • 49.
    EXTREME PROGRAMMING -XP For small-to-medium-sized teams developing software with vague or rapidly changing requirements Coding is the key activity throughout a software project  Communication among teammates is done with code  Life cycle and behavior of complex objects defined in test cases – again in code
  • 50.
    XP PRACTICES (1-6) 1.Planning game – determine scope of the next release by combining business priorities and technical estimates 2. Small releases – put a simple system into production, then release new versions in very short cycle 3. Metaphor – all development is guided by a simple shared story of how the whole system works 4. Simple design – system is designed as simply as possible (extra complexity removed as soon as found) 5. Testing – programmers continuously write unit tests; customers write tests for features 6. Refactoring – programmers continuously restructure the system without changing its behavior to remove duplication and simplify
  • 51.
    XP Practices (7– 12) 7. Pair-programming -- all production code is written with two programmers at one machine 8. Collective ownership – anyone can change any code anywhere in the system at any time. 9. Continuous integration – integrate and build the system many times a day – every time a task is completed. 10. 40-hour week – work no more than 40 hours a week as a rule 11. On-site customer – a user is on the team and available full-time to answer questions 12. Coding standards – programmers write all code in accordance with rules emphasizing communication through the code
  • 52.
    XP is “extreme”because Commonsense practices taken to extreme levels  If code reviews are good, review code all the time (pair programming)  If testing is good, everybody will test all the time  If simplicity is good, keep the system in the simplest design that supports its current functionality. (simplest thing that works)  If design is good, everybody will design daily (refactoring)  If architecture is important, everybody will work at defining and refining the architecture (metaphor)  If integration testing is important, build and integrate test several times a day (continuous integration)  If short iterations are good, make iterations really, really short (hours rather than weeks)
  • 53.
    SUMMARY  This hasbeen a (very) quick tour through the life cycle of a system.  You will have to do—to some extent—all of these activities for your project.