- 1. REGISTRO ESTADO DEL PROYECTO
VALORES ACUMULADOS
PV AC EV PV AC EV CPI SPI
1 ) 06/07/2012 - 13/07/2012 50.00 25.00 35.00 50.00 25.00 35.00 1.40 0.70
2 ) 13/07/2012 - 20/07/2012 75.00 90.00 80.00 125.00 115.00 115.00 0.89 1.07
3 ) 20/07/2012 - 27/07/2012 70.00 120.00 60.00 195.00 235.00 175.00 0.50 0.86
4 ) 27/07/2012 - 03/08/2012 65.00 90.00 120.00 260.00 325.00 295.00 1.33 1.85
5 ) 03/08/2012 - 10/08/2012 200.00 90.00 120.00 460.00 415.00 415.00 1.33 0.60
6 ) 10/08/2012 - 17/08/2012 120.00 150.00 100.00 580.00 565.00 515.00 0.67 0.83
7 ) 17/08/2012 - 24/08/2012 150.00 250.00 150.00 730.00 815.00 665.00 0.60 1.00
8 ) 24/08/2012 - 31/08/2012 90.00 300.00 180.00 820.00 1,115.00 845.00 0.60 2.00
9 ) 31/08/2012 - 07/09/2012 120.00 940.00
10 ) 07/09/2012 - 14/09/2012 200.00 1,140.00
11 ) 14/09/2012 - 21/09/2012 150.00 1,290.00
12 ) 21/09/2012 - 28/09/2012 90.00 1,380.00
13 ) 28/09/2012 - 05/10/2012 60.00 1,440.00
14 ) 05/10/2012 - 12/10/2012 50.00 1,490.00
15 ) 12/10/2012 - 19/10/2012 60.00 1,550.00
16 ) 19/10/2012 45.00 1,595.00
1,595.00 1,115.00 845.00
( BAC ) : COSTO TOTAL DE PRESUPUESTO ( PV ) : MONTO VALOR PRESUPUESTADO ( CV ) : VARIACION DEL COSTO
( DPT ) : DURACION DEL PROYECTO ( AC ) : MONTO ACUMULADO GASTADO ( SV ) : VARIACION DEL CRONOGRAMA
( EV ) : MONTO VALOR GANADO (CPI) : INDICE DE VARIACION DEL COSTO
(SPI) : INDICE DE VAR. DEL CRONOGRAMA
AVANCE EN CURVAS S
1,800.00
1,600.00
1,400.00
1,200.00
1,000.00
800.00
600.00
400.00
200.00
0.00
0.00 2.00 4.00 6.00 8.00 10.00 12.00 14.00 16.00 18.00
CPTP - (PV) CRTR - (AC) CRTP - (EV)