This corporate presentation from Rubicon Minerals provides an overview of their plans to build long-term shareholder value through advancing their Phoenix Gold Project, exploring additional targets near Phoenix, and exploring their large land package in Red Lake, Ontario. They have a strong balance sheet with $12.5 million cash and minimal debt. Institutional investors own over 70% of shares.
George Ogilvie, President and CEO of Rubicon Minerals Corporation, provides an overview of the company's goals and progress at the Phoenix Gold Project in Red Lake, Ontario. The company aims to advance the project to commercial production, explore additional targets on the property, and explore its large regional land package. Recent exploration work has led to a new geological model that indicates better continuity of mineralization. Highlights include a 2018 mineral resource estimate showing a 113% increase in measured and indicated ounces and an 80% increase in inferred ounces compared to 2016. Bulk sampling and additional drilling are planned to potentially increase confidence and resource size.
Rubicon Minerals is a Canadian mining company focused on advancing its Phoenix Gold Project in Red Lake, Ontario with the goal of becoming a mid-tier gold producer. It aims to achieve this through 1) advancing Phoenix to commercial production, 2) exploring organic growth opportunities within 2 km of Phoenix, and 3) exploring its large Red Lake land package. Rubicon has a strong balance sheet with approximately C$24 million in cash and nominal long-term debt, and institutional investors own over 70% of shares.
The document discusses Rubicon Minerals' Phoenix Gold Project and efforts to advance it towards commercial production. It provides the following key points:
- Rubicon released a new 2018 Mineral Resource Estimate in April 2018 that showed significant growth over previous estimates, with a 113% increase in Measured and Indicated resources and an 80% increase in Inferred resources.
- The re-interpretation of geological and structural controls on mineralization, along with recognizing potential for larger scale mining, resulted in broader mineral domains and improved grades in the 2018 estimate.
- Rubicon plans additional infill and step-out drilling, 25,000-30,000 tons of bulk sampling and test mining, and evaluation of
- Rubicon Minerals has infrastructure and permits in place at its Phoenix Gold Project site in Red Lake, Ontario, including a mill, tailings facility, camp, and 13km of underground development.
- In 2018, Rubicon updated the mineral resource estimate for its F2 Gold Deposit, showing a 113% increase in measured and indicated resources and an 80% increase in inferred resources compared to 2016.
- Rubicon plans 20,000m of infill drilling in 2018 aimed at converting inferred resources to indicated and improving resource classifications, as well as 25,000-30,000 tonnes of bulk sampling to validate the 2018 resource model.
The document provides an overview of Rubicon Minerals Corporation and its Phoenix Gold Project. Some key points:
- Rubicon aims to advance the Phoenix Gold Project to commercial production and grow its land package in Red Lake through exploration.
- Bulk sampling at the Phoenix Project validated the 2018 mineral resource estimate, with tonnes, grades, and ounces higher than modeled. Mill throughput was 70 tonnes per hour.
- The 2018 mineral resource estimate for the Phoenix Project reported measured and indicated resources of 1.37 million tonnes at 6.37 g/t gold for 281,000 ounces of contained gold, plus inferred resources of 3.88 million tonnes at 6.00 g/t gold for 749
Rubicon Minerals is advancing the Phoenix Gold Project in Red Lake, Ontario towards potential commercial production. The company has strengthened its management team and board with mining experts. A 2018 mineral resource estimate validated by a positive bulk sample reconciliation demonstrated significant growth in measured and indicated and inferred gold ounces at the project. Rubicon plans to deliver an updated resource estimate in the first half of 2019 and a new preliminary economic assessment by mid-late 2019 to further de-risk the Phoenix Gold Project.
This corporate presentation from Rubicon Minerals Corporation provides an overview of the company and its mining projects. It discloses forward-looking statements about Rubicon's exploration potential, plans to advance its Phoenix Gold Project, and objectives for planned drilling programs and resource estimates. It also outlines risks to the company's plans, including variations in mineralization, permitting delays, and uncertainties around future operations and economic evaluations. The presentation is intended to help investors understand Rubicon's goals but cautions that no production decision has been made and there is inherent risk involved with mining exploration.
The document provides an overview of Rubicon Minerals Corporation and its Phoenix Gold Project in Red Lake, Ontario. It discusses Rubicon's three-pronged approach to building shareholder value by advancing Phoenix to production, exploring nearby targets, and exploring its large regional land package. It also summarizes key infrastructure and permits in place at Phoenix, highlights encouraging drill results from 2017 exploration, and outlines Rubicon's plan to refine the geological model and resource estimate through additional drilling, mapping, and test mining in 2018.
George Ogilvie, President and CEO of Rubicon Minerals Corporation, provides an overview of the company's goals and progress at the Phoenix Gold Project in Red Lake, Ontario. The company aims to advance the project to commercial production, explore additional targets on the property, and explore its large regional land package. Recent exploration work has led to a new geological model that indicates better continuity of mineralization. Highlights include a 2018 mineral resource estimate showing a 113% increase in measured and indicated ounces and an 80% increase in inferred ounces compared to 2016. Bulk sampling and additional drilling are planned to potentially increase confidence and resource size.
Rubicon Minerals is a Canadian mining company focused on advancing its Phoenix Gold Project in Red Lake, Ontario with the goal of becoming a mid-tier gold producer. It aims to achieve this through 1) advancing Phoenix to commercial production, 2) exploring organic growth opportunities within 2 km of Phoenix, and 3) exploring its large Red Lake land package. Rubicon has a strong balance sheet with approximately C$24 million in cash and nominal long-term debt, and institutional investors own over 70% of shares.
The document discusses Rubicon Minerals' Phoenix Gold Project and efforts to advance it towards commercial production. It provides the following key points:
- Rubicon released a new 2018 Mineral Resource Estimate in April 2018 that showed significant growth over previous estimates, with a 113% increase in Measured and Indicated resources and an 80% increase in Inferred resources.
- The re-interpretation of geological and structural controls on mineralization, along with recognizing potential for larger scale mining, resulted in broader mineral domains and improved grades in the 2018 estimate.
- Rubicon plans additional infill and step-out drilling, 25,000-30,000 tons of bulk sampling and test mining, and evaluation of
- Rubicon Minerals has infrastructure and permits in place at its Phoenix Gold Project site in Red Lake, Ontario, including a mill, tailings facility, camp, and 13km of underground development.
- In 2018, Rubicon updated the mineral resource estimate for its F2 Gold Deposit, showing a 113% increase in measured and indicated resources and an 80% increase in inferred resources compared to 2016.
- Rubicon plans 20,000m of infill drilling in 2018 aimed at converting inferred resources to indicated and improving resource classifications, as well as 25,000-30,000 tonnes of bulk sampling to validate the 2018 resource model.
The document provides an overview of Rubicon Minerals Corporation and its Phoenix Gold Project. Some key points:
- Rubicon aims to advance the Phoenix Gold Project to commercial production and grow its land package in Red Lake through exploration.
- Bulk sampling at the Phoenix Project validated the 2018 mineral resource estimate, with tonnes, grades, and ounces higher than modeled. Mill throughput was 70 tonnes per hour.
- The 2018 mineral resource estimate for the Phoenix Project reported measured and indicated resources of 1.37 million tonnes at 6.37 g/t gold for 281,000 ounces of contained gold, plus inferred resources of 3.88 million tonnes at 6.00 g/t gold for 749
Rubicon Minerals is advancing the Phoenix Gold Project in Red Lake, Ontario towards potential commercial production. The company has strengthened its management team and board with mining experts. A 2018 mineral resource estimate validated by a positive bulk sample reconciliation demonstrated significant growth in measured and indicated and inferred gold ounces at the project. Rubicon plans to deliver an updated resource estimate in the first half of 2019 and a new preliminary economic assessment by mid-late 2019 to further de-risk the Phoenix Gold Project.
This corporate presentation from Rubicon Minerals Corporation provides an overview of the company and its mining projects. It discloses forward-looking statements about Rubicon's exploration potential, plans to advance its Phoenix Gold Project, and objectives for planned drilling programs and resource estimates. It also outlines risks to the company's plans, including variations in mineralization, permitting delays, and uncertainties around future operations and economic evaluations. The presentation is intended to help investors understand Rubicon's goals but cautions that no production decision has been made and there is inherent risk involved with mining exploration.
The document provides an overview of Rubicon Minerals Corporation and its Phoenix Gold Project in Red Lake, Ontario. It discusses Rubicon's three-pronged approach to building shareholder value by advancing Phoenix to production, exploring nearby targets, and exploring its large regional land package. It also summarizes key infrastructure and permits in place at Phoenix, highlights encouraging drill results from 2017 exploration, and outlines Rubicon's plan to refine the geological model and resource estimate through additional drilling, mapping, and test mining in 2018.
The document provides details on Rubicon Minerals' 2018 exploration program at its Phoenix Gold Project in Red Lake, Ontario. The program includes 10,000 meters of infill and step-out drilling, underground test mining of 15,000-25,000 tonnes between the 122-244 meter levels, and a new NI 43-101 resource estimate in the second half of 2018. The objectives are to validate the geological model and gather data to advance the project towards a potential feasibility study.
The document provides an overview of Rubicon Minerals Corporation and its Phoenix Gold Project in Red Lake, Ontario. Key points include:
- Rubicon is advancing the Phoenix Gold Project towards commercial production and exploring additional targets near the project and across its large land package in Red Lake.
- Over $770 million has already been spent developing infrastructure at Phoenix, including a mill, underground development, and permits. 2017 exploration returned high grade drill results.
- Rubicon plans further drilling, structural analysis, test mining and a new resource estimate in 2018 to increase confidence in the Phoenix Gold Project, with the goal of potential production.
- The company's assets have conceptual values comparable to its current market capitalization,
This corporate presentation from Rubicon Minerals Corporation provides an overview of the company and its mining projects. It discloses forward-looking statements about Rubicon's exploration potential, plans to advance its Phoenix Gold Project, and anticipated 2018 exploration programs. It also outlines risks and uncertainties inherent in forward-looking statements and mining exploration, including variations in mineralization, grade, recovery rates, as well as political, economic and regulatory risks.
George Ogilvie, President and CEO of Rubicon Minerals Corporation, presented at a 2018 Red Lake Community Information Session. Some key points:
- Rubicon completed 28,500m of underground drilling in 2017 to advance their understanding of the F2 Gold Deposit geology and identify new targets. Preliminary observations from drilling indicate discrepancies with the existing geological model and higher grades than expected.
- Underground development commenced in 2017 in preparation for test mining in 2018. Rubicon also raised $10 million for exploration activities.
- Health and safety continue to be a priority, with over 600 days since the last lost time incident. Environmental improvements in 2017 included ammonia management and an upgraded water treatment system.
This corporate presentation from Rubicon Minerals provides an overview of the company's projects and 2017 exploration program at its Phoenix Gold Project in Red Lake, Ontario. Some preliminary observations from the exploration program include discrepancies between the existing geological model and new data that indicate multiple quartz breccia units and orientations not previously captured. Higher gold grades were also encountered compared to the 2016 mineral resource block model, including from deeper drilling at the F2 Gold Deposit. Assay results from the structural and infill drilling programs returned several high-grade intercepts. Additional analysis is still needed, but initial results suggest the need to update the geological model.
This corporate presentation from Rubicon Minerals Corporation provides an overview of the company and discusses its exploration potential in Red Lake, Ontario, Canada. It notes plans to advance the Phoenix Gold Project to development and pre-production. However, it also emphasizes that any potential mine development decision would not be based on a feasibility study, which increases the risks. The presentation contains forward-looking statements about Rubicon's plans and expectations but also outlines several risks and uncertainties that could affect whether potential results are achieved.
The 2017 exploration program at Rubicon's Phoenix Gold Project in Red Lake, Ontario has yielded preliminary observations that indicate discrepancies between the existing geological model and new data collected from mapping, drilling and core re-logging. Highlight assay results from drilling include high grade intercepts. The program is ongoing and aims to improve the understanding of mineralization to potentially advance the project.
This 3 paragraph corporate presentation by TSX:RMX and OTC:RBYCF provides an overview of the company's exploration projects and discloses risks associated with forward-looking statements. It discusses Rubicon's Red Lake properties in Ontario which it aims to advance to development and production. It also outlines plans for exploration programs in 2017-2018 to further define resources and test targets. However, the presentation contains numerous cautionary statements regarding the speculative nature of mineral exploration and emphasizes that no certainty exists that a mine will be realized, as production decisions without feasibility studies have greater uncertainty of success.
The document provides an overview of Rubicon Minerals Corporation and its Phoenix Gold Project in Red Lake, Ontario. It discusses Rubicon's three-pronged approach to build shareholder value by potentially advancing Phoenix to production, organically growing its project pipeline near Phoenix, and exploring its regional land package. It provides details on Rubicon's 2018 exploration program, including 10,000m of drilling, test mining of 15-25kt of material, and an updated resource estimate. Preliminary results from 2017 exploration indicate discrepancies with the existing geological model that require further analysis.
This document provides an overview of Rubicon Minerals Corporation's 2017 Annual General and Special Meeting of Shareholders. It contains forward-looking statements regarding the exploration potential in Red Lake, plans to advance the Phoenix Gold Project, and anticipated exploration work. It cautions that forward-looking statements are based on certain assumptions and risks that could cause actual results to differ. It also notes the qualifications of the document and definitions of resource estimates under Canadian and U.S. standards.
Rubicon Minerals Corporation is a gold exploration company focused on its high-grade gold potential land package in Red Lake, Ontario. The company has over C$770 million in infrastructure and a strong balance sheet of C$29 million in cash. In 2018, Rubicon plans to undertake a 10,000 meter drilling program along with preliminary structural analysis and exploratory development to better understand the geology of its deposits and potentially increase mineral resources. The long-term vision is to build a mid-tier gold producer over the next 5-7 years through advancing its Phoenix Gold Project, organic growth opportunities near Phoenix, and exploring its extensive Red Lake land package.
This document summarizes exploration activities and mineral resource estimates for a high-grade gold project in Red Lake, Ontario owned by Rubicon Minerals Corporation. It provides details of the management team and board of directors. It outlines the 2018 exploration program including 20,000 meters of drilling, structural interpretation work, and underground test mining. It summarizes the results of a new 2018 mineral resource estimate which showed significant growth over the 2016 estimate, with increases in measured, indicated, and inferred ounces. Plans are outlined to further expand and upgrade the resources through additional exploration.
This document provides forward-looking statements regarding Romarco Minerals' Haile Gold project in South Carolina, including projections for mine life, production costs, capital costs, internal rate of return, and timing of permitting and construction. It qualifies all scientific and technical information as coming from a December 2014 technical report, and cautions that actual results may differ materially from the projections. The forward-looking statements are based on assumptions around factors like mineral reserves, receipt of permits and approvals, access to financing and markets, and ability to mine and sell minerals at favorable prices.
Ero Copper held a technical session to discuss its 2022 exploration program and recent results. The session provided an overview of exploration activities across Ero's portfolio, including near-mine exploration and regional programs at the MCSA Mining Complex, nickel exploration, and work at the Boa Esperança and NX Gold projects. Ero aims to unlock value across all timescales through ongoing life-of-mine planning and exploration, with a focus on generating high-margin growth projects delivering high returns on investment.
This document provides an overview of Plateau Energy Metals Inc., a company focused on developing lithium and uranium projects in Peru. Some key highlights include that Plateau has 100% control over a 930 square kilometer land package in Peru's Macusani Plateau, which hosts the world's largest underdeveloped lithium and uranium districts. The company's projects benefit from excellent local infrastructure and a supportive mining jurisdiction. Plateau also has a strong management team with experience advancing projects from exploration through development and financing. The document notes some preliminary economic assessments have been completed on the projects but additional work is required.
This document provides forward-looking statements regarding Romarco Minerals' Haile Gold project in South Carolina, including projections for mine life, production costs, capital costs, internal rate of return, and timing of permitting and construction. The statements are based on assumptions in a December 2014 technical report, but actual results may differ due to risks and uncertainties. Scientific information is qualified by the technical report, whose authors are qualified persons under Canadian regulations.
This document provides a summary of the 2019 Annual General Meeting for a mining company. It includes cautionary statements regarding forward-looking information in the presentation, such as production estimates, economic analyses, and assumptions underlying resource estimates. It notes that mineral resource and reserve estimates have been prepared according to Canadian standards which may not be comparable to US standards. The document also discusses non-IFRS financial measures presented and identifies the qualified persons who reviewed and approved the scientific and technical information in the presentation.
The document provides an overview of Ero Copper's April 2022 analyst site visit to their MCSA Mining Complex and Boa Esperança project in Brazil. It includes forward-looking statements and cautions that actual results may differ materially from projections. It also notes the qualifications of the experts who prepared technical reports on the company's properties and provides context around non-IFRS financial measures discussed. Key topics to be covered include health, safety and environment; performance and growth opportunities at MCSA and NX Gold; updates on the Boa Esperança project; and the company's balance sheet and financial position.
- American Lithium is a leading diversified lithium development company and was a top 50 company on the TSXV in May 2021.
- The presentation provides an overview of American Lithium and its subsidiaries, including their lithium projects in Nevada, USA and Peru.
- It discloses key details about the TLC, Falchani, and Macusani lithium projects, and summarizes preliminary economic assessments conducted for the projects.
The document discusses the 2018 Mineral Resource Estimate for the Phoenix Gold Project, which showed material growth over previous estimates. The 2018 estimate reported 1.374 million tonnes at 6.37 g/t gold for 281,000 ounces in the Measured and Indicated categories, along with 3.884 million tonnes at 6.00 g/t gold for 749,000 ounces in the Inferred category. This represented increases of 113% for Measured and Indicated and 80% for Inferred over previous estimates. The improved results were mainly attributed to a new geological and structural interpretation of the F2 Gold Deposit that recognized potential for larger scale mining.
The document provides an overview of Rubicon Minerals Corporation, including:
1) Rubicon aims to build shareholder value by advancing its Phoenix Gold Project in Red Lake, Ontario to commercial production and exploring its large land package in the region.
2) Rubicon has strengthened its management team and board with experts in geology, mining, finance, and law to advance the Phoenix Project.
3) Recent drilling, a positive bulk sample reconciliation, and an updated mineral resource estimate have helped rebuild confidence in the Phoenix Project's potential.
The document provides details on Rubicon Minerals' 2018 exploration program at its Phoenix Gold Project in Red Lake, Ontario. The program includes 10,000 meters of infill and step-out drilling, underground test mining of 15,000-25,000 tonnes between the 122-244 meter levels, and a new NI 43-101 resource estimate in the second half of 2018. The objectives are to validate the geological model and gather data to advance the project towards a potential feasibility study.
The document provides an overview of Rubicon Minerals Corporation and its Phoenix Gold Project in Red Lake, Ontario. Key points include:
- Rubicon is advancing the Phoenix Gold Project towards commercial production and exploring additional targets near the project and across its large land package in Red Lake.
- Over $770 million has already been spent developing infrastructure at Phoenix, including a mill, underground development, and permits. 2017 exploration returned high grade drill results.
- Rubicon plans further drilling, structural analysis, test mining and a new resource estimate in 2018 to increase confidence in the Phoenix Gold Project, with the goal of potential production.
- The company's assets have conceptual values comparable to its current market capitalization,
This corporate presentation from Rubicon Minerals Corporation provides an overview of the company and its mining projects. It discloses forward-looking statements about Rubicon's exploration potential, plans to advance its Phoenix Gold Project, and anticipated 2018 exploration programs. It also outlines risks and uncertainties inherent in forward-looking statements and mining exploration, including variations in mineralization, grade, recovery rates, as well as political, economic and regulatory risks.
George Ogilvie, President and CEO of Rubicon Minerals Corporation, presented at a 2018 Red Lake Community Information Session. Some key points:
- Rubicon completed 28,500m of underground drilling in 2017 to advance their understanding of the F2 Gold Deposit geology and identify new targets. Preliminary observations from drilling indicate discrepancies with the existing geological model and higher grades than expected.
- Underground development commenced in 2017 in preparation for test mining in 2018. Rubicon also raised $10 million for exploration activities.
- Health and safety continue to be a priority, with over 600 days since the last lost time incident. Environmental improvements in 2017 included ammonia management and an upgraded water treatment system.
This corporate presentation from Rubicon Minerals provides an overview of the company's projects and 2017 exploration program at its Phoenix Gold Project in Red Lake, Ontario. Some preliminary observations from the exploration program include discrepancies between the existing geological model and new data that indicate multiple quartz breccia units and orientations not previously captured. Higher gold grades were also encountered compared to the 2016 mineral resource block model, including from deeper drilling at the F2 Gold Deposit. Assay results from the structural and infill drilling programs returned several high-grade intercepts. Additional analysis is still needed, but initial results suggest the need to update the geological model.
This corporate presentation from Rubicon Minerals Corporation provides an overview of the company and discusses its exploration potential in Red Lake, Ontario, Canada. It notes plans to advance the Phoenix Gold Project to development and pre-production. However, it also emphasizes that any potential mine development decision would not be based on a feasibility study, which increases the risks. The presentation contains forward-looking statements about Rubicon's plans and expectations but also outlines several risks and uncertainties that could affect whether potential results are achieved.
The 2017 exploration program at Rubicon's Phoenix Gold Project in Red Lake, Ontario has yielded preliminary observations that indicate discrepancies between the existing geological model and new data collected from mapping, drilling and core re-logging. Highlight assay results from drilling include high grade intercepts. The program is ongoing and aims to improve the understanding of mineralization to potentially advance the project.
This 3 paragraph corporate presentation by TSX:RMX and OTC:RBYCF provides an overview of the company's exploration projects and discloses risks associated with forward-looking statements. It discusses Rubicon's Red Lake properties in Ontario which it aims to advance to development and production. It also outlines plans for exploration programs in 2017-2018 to further define resources and test targets. However, the presentation contains numerous cautionary statements regarding the speculative nature of mineral exploration and emphasizes that no certainty exists that a mine will be realized, as production decisions without feasibility studies have greater uncertainty of success.
The document provides an overview of Rubicon Minerals Corporation and its Phoenix Gold Project in Red Lake, Ontario. It discusses Rubicon's three-pronged approach to build shareholder value by potentially advancing Phoenix to production, organically growing its project pipeline near Phoenix, and exploring its regional land package. It provides details on Rubicon's 2018 exploration program, including 10,000m of drilling, test mining of 15-25kt of material, and an updated resource estimate. Preliminary results from 2017 exploration indicate discrepancies with the existing geological model that require further analysis.
This document provides an overview of Rubicon Minerals Corporation's 2017 Annual General and Special Meeting of Shareholders. It contains forward-looking statements regarding the exploration potential in Red Lake, plans to advance the Phoenix Gold Project, and anticipated exploration work. It cautions that forward-looking statements are based on certain assumptions and risks that could cause actual results to differ. It also notes the qualifications of the document and definitions of resource estimates under Canadian and U.S. standards.
Rubicon Minerals Corporation is a gold exploration company focused on its high-grade gold potential land package in Red Lake, Ontario. The company has over C$770 million in infrastructure and a strong balance sheet of C$29 million in cash. In 2018, Rubicon plans to undertake a 10,000 meter drilling program along with preliminary structural analysis and exploratory development to better understand the geology of its deposits and potentially increase mineral resources. The long-term vision is to build a mid-tier gold producer over the next 5-7 years through advancing its Phoenix Gold Project, organic growth opportunities near Phoenix, and exploring its extensive Red Lake land package.
This document summarizes exploration activities and mineral resource estimates for a high-grade gold project in Red Lake, Ontario owned by Rubicon Minerals Corporation. It provides details of the management team and board of directors. It outlines the 2018 exploration program including 20,000 meters of drilling, structural interpretation work, and underground test mining. It summarizes the results of a new 2018 mineral resource estimate which showed significant growth over the 2016 estimate, with increases in measured, indicated, and inferred ounces. Plans are outlined to further expand and upgrade the resources through additional exploration.
This document provides forward-looking statements regarding Romarco Minerals' Haile Gold project in South Carolina, including projections for mine life, production costs, capital costs, internal rate of return, and timing of permitting and construction. It qualifies all scientific and technical information as coming from a December 2014 technical report, and cautions that actual results may differ materially from the projections. The forward-looking statements are based on assumptions around factors like mineral reserves, receipt of permits and approvals, access to financing and markets, and ability to mine and sell minerals at favorable prices.
Ero Copper held a technical session to discuss its 2022 exploration program and recent results. The session provided an overview of exploration activities across Ero's portfolio, including near-mine exploration and regional programs at the MCSA Mining Complex, nickel exploration, and work at the Boa Esperança and NX Gold projects. Ero aims to unlock value across all timescales through ongoing life-of-mine planning and exploration, with a focus on generating high-margin growth projects delivering high returns on investment.
This document provides an overview of Plateau Energy Metals Inc., a company focused on developing lithium and uranium projects in Peru. Some key highlights include that Plateau has 100% control over a 930 square kilometer land package in Peru's Macusani Plateau, which hosts the world's largest underdeveloped lithium and uranium districts. The company's projects benefit from excellent local infrastructure and a supportive mining jurisdiction. Plateau also has a strong management team with experience advancing projects from exploration through development and financing. The document notes some preliminary economic assessments have been completed on the projects but additional work is required.
This document provides forward-looking statements regarding Romarco Minerals' Haile Gold project in South Carolina, including projections for mine life, production costs, capital costs, internal rate of return, and timing of permitting and construction. The statements are based on assumptions in a December 2014 technical report, but actual results may differ due to risks and uncertainties. Scientific information is qualified by the technical report, whose authors are qualified persons under Canadian regulations.
This document provides a summary of the 2019 Annual General Meeting for a mining company. It includes cautionary statements regarding forward-looking information in the presentation, such as production estimates, economic analyses, and assumptions underlying resource estimates. It notes that mineral resource and reserve estimates have been prepared according to Canadian standards which may not be comparable to US standards. The document also discusses non-IFRS financial measures presented and identifies the qualified persons who reviewed and approved the scientific and technical information in the presentation.
The document provides an overview of Ero Copper's April 2022 analyst site visit to their MCSA Mining Complex and Boa Esperança project in Brazil. It includes forward-looking statements and cautions that actual results may differ materially from projections. It also notes the qualifications of the experts who prepared technical reports on the company's properties and provides context around non-IFRS financial measures discussed. Key topics to be covered include health, safety and environment; performance and growth opportunities at MCSA and NX Gold; updates on the Boa Esperança project; and the company's balance sheet and financial position.
- American Lithium is a leading diversified lithium development company and was a top 50 company on the TSXV in May 2021.
- The presentation provides an overview of American Lithium and its subsidiaries, including their lithium projects in Nevada, USA and Peru.
- It discloses key details about the TLC, Falchani, and Macusani lithium projects, and summarizes preliminary economic assessments conducted for the projects.
The document discusses the 2018 Mineral Resource Estimate for the Phoenix Gold Project, which showed material growth over previous estimates. The 2018 estimate reported 1.374 million tonnes at 6.37 g/t gold for 281,000 ounces in the Measured and Indicated categories, along with 3.884 million tonnes at 6.00 g/t gold for 749,000 ounces in the Inferred category. This represented increases of 113% for Measured and Indicated and 80% for Inferred over previous estimates. The improved results were mainly attributed to a new geological and structural interpretation of the F2 Gold Deposit that recognized potential for larger scale mining.
The document provides an overview of Rubicon Minerals Corporation, including:
1) Rubicon aims to build shareholder value by advancing its Phoenix Gold Project in Red Lake, Ontario to commercial production and exploring its large land package in the region.
2) Rubicon has strengthened its management team and board with experts in geology, mining, finance, and law to advance the Phoenix Project.
3) Recent drilling, a positive bulk sample reconciliation, and an updated mineral resource estimate have helped rebuild confidence in the Phoenix Project's potential.
This document provides an overview of Rubicon Minerals Corporation, a gold exploration company with properties in the Red Lake district of Ontario, Canada. It summarizes the company's leadership team, 2018 mineral resource estimate for its Phoenix Gold Project which showed significant growth compared to 2016, and plans for 2019 including further exploration drilling and an updated preliminary economic assessment. The company aims to advance the Phoenix project to commercial production while exploring additional targets on its large land package in Red Lake.
- The corporate presentation discusses Ero Copper's position for high-margin organic growth and provides cautionary statements regarding the use of forward-looking information and statements.
- It notes that forward-looking statements are based on a number of estimates and assumptions that are inherently subject to risks and uncertainties that could cause actual results to differ materially from expectations.
- The presentation contains cautionary notes for US investors regarding the use of inferred resources that are required by Canadian regulations but not recognized by the SEC, and that inferred resources do not have demonstrated economic viability.
The document summarizes Pretivm's 2019 Mineral Reserve update for its Brucejack Mine. Key points include:
- The Valley of Kings Reserves were updated using updated costs, stope design parameters, and net smelter return model. No changes were made to the West Zone reserves.
- Mining costs were updated based on projected costs for 3,800 tonnes per day production, and are greater than the life of mine costs. The net smelter return cut-off increased to $185/tonne from $165/tonne previously.
- Total mining costs increased to $127.20/tonne from $91.30/tonne previously due to factors like increased development and use of
- Osisko reported results for Q2 2018, with gold equivalent ounces earned of 20,506, an 89% increase over Q2 2017.
- Cash flows from operating activities were $19.7 million, up from $14.1 million in Q2 2017. Adjusted earnings were $3.7 million, down from $7.1 million in Q2 2017 due to higher finance costs.
- Osisko is on track to achieve its 2018 guidance of 77,500 to 82,500 gold equivalent ounces and expects strong production in the second half of the year with steady increases through 2019 and 2020.
This document outlines the agenda and resolutions for the 2018 Annual and Special Meeting of Shareholders. Resolution 1 is the election of 11 directors to the corporation's board. Resolution 2 is the appointment and compensation of PricewaterhouseCoopers LLP as the independent auditor for 2018. Resolutions 3 through 5 are approvals of amendments to various compensation plans for employees and executives. Resolution 6 is an advisory vote on the corporation's executive compensation approach.
BMO Capital Markets Global Metals & Mining Conference yamanagold2016
The document provides cautionary notes regarding forward-looking statements in a presentation for a metals and mining conference. It notes that forward-looking statements involve risks and uncertainties that could cause actual results to differ from expectations. It also cautions US investors that mineral resource classifications differ between Canadian and US standards. The document outlines non-GAAP financial measures used by the company and definitions of EBITDA and EBITDA margin. It states that all dollar amounts in the presentation are in US dollars unless otherwise indicated.
Osisko reported its Q3 2018 results with the following highlights:
- Produced 20,006 GEOs in Q3 2018, a 20% increase over Q3 2017.
- Generated $20.6 million in net cash flows from operating activities compared to $1.1 million in Q3 2017.
- Adjusted earnings were $5.7 million or $0.04 per share compared to $8 million or $0.06 per share in Q3 2017.
This document provides an overview of Guyana Goldfields Inc., a gold mining company with operations in Guyana. Some key points:
- Guyana Goldfields operates the high-grade Aurora gold mine in Guyana, which has over 16 years of reserve life and exploration potential across its 200,000-acre land package.
- In 2018, production guidance was revised down to 150,000-155,000 ounces due to lower than expected head grades, and the company has engaged an independent firm to review the resource model.
- The company has a strong balance sheet with $93 million in cash and $45 million in debt as of September 2018.
- Management changes and a mill expansion are expected
The document discusses Pretivm Resources' Brucejack Mine, a high-grade underground gold mine in British Columbia. It notes that the mine has consistently been profitable. It cautions readers that the presentation contains forward-looking statements regarding anticipated results, costs, plans, estimates, assumptions, and other projections that involve risks and uncertainties. It also provides notes to investors on the technical information sources, definitions of resource estimates, and explanations of non-IFRS financial metrics.
BMO Capital Markets 28th Global Metals & Mining ConferencePretiumR
1) The Brucejack Mine in British Columbia has consistently generated profits every quarter since start-up six quarters ago through high-grade underground gold production and low costs.
2) In 2018 the mine produced over 376,000 ounces of gold at a total cash cost of $764 per ounce on average and generated over $20 million in adjusted net earnings.
3) For 2019 the mine is targeting production of 390,000 to 420,000 ounces of gold at an all-in sustaining cost of $775 to $875 per ounce through continued ramp up to 3,800 tonnes per day.
- Osisko reported 20,005 GEOs earned in Q4 2018 and a record 80,553 GEOs earned for the full year 2018, up 37% from 2017.
- Revenues from royalties and streams were $30.7 million in Q4 2018 and a record $127.6 million for 2018, up 36% from 2017.
- Net loss attributable to shareholders was $113.9 million in Q4 2018 and $105.6 million for 2018, reflecting impairment charges. Excluding impairment charges, adjusted earnings were $13.0 million in Q4 2018.
This investor presentation provides an overview of Guyana Goldfields Inc. and its Aurora Gold Project. Key highlights include:
- The Aurora Project is expected to produce an average of 194,000 ounces of gold per year over its 17-year mine life at average cash costs of $527/oz, with total production of 3.3 million ounces.
- At a gold price of $1,300/oz, the Aurora Project has an after-tax NPV of $735 million and IRR of 31%, with payback of just over 4 years.
- Guyana Goldfields plans to use a staged approach to develop the Aurora Project, with initial open pit mining and a 5,000 tpd
- The document discusses Gold Terra Resource Corp.'s Yellowknife City Gold Project in the Northwest Territories of Canada, which covers a district-scale land package near the city of Yellowknife with potential for multi-million ounces of gold.
- In November 2019, an initial mineral resource estimate for the project outlined 735,000 ounces of inferred resources at two main deposits.
- The project has excellent exploration potential along strike and at depth at known deposits like Sam Otto and Crestaurum, as well as at other targets along the 65km mineralized trend that remains largely untested. Drilling in 2020 aims to expand resources and test new targets.
Similar to Rubicon Minerals October 2018 Corporate Presentation (16)
UnityNet World Environment Day Abraham Project 2024 Press ReleaseLHelferty
June 12, 2024 UnityNet International (#UNI) World Environment Day Abraham Project 2024 Press Release from Markham / Mississauga, Ontario in the, Greater Tkaronto Bioregion, Canada in the North American Great Lakes Watersheds of North America (Turtle Island).
Bienestar Financiero al servicio de su jubilación anticipada
Pago de su 🏡
Estudio de sus hijos
Directamente a tu cuenta bancaria
Con Tesorería Auditoria Jurídica comercial
Administración de carteras
Apalancamiento Financiero
Desarrollo de tu marca personal
Acceso a Desarrollo de varias industrias
Cuentas bancarias
Estructuras Físicas en USA y en América Central
Avalado por Bolcomer
Puesto de Bolsa Comercial
Turismo
Y mucho más
Link de registro
https://business.myinfinity.global/maurod8/
https://therusnetwork.com/
Contacto:
https://goo.su/pzm1fja
Rubicon Minerals October 2018 Corporate Presentation
1. TSX : RMX | OTCQX : RBYCF
Corporate Presentation
October 2018
Building Long-Term Shareholder Value
2. TSX : RMX | OTCQX : RBYCF
Cautionary Statement regarding Forward-Looking Statements and other Cautionary Notes
This corporate presentation contains statements that constitute “forward-looking statements” and “forward looking information” (collectively, “forward-looking statements”) within the meaning of applicable
Canadian and United States securities legislation. Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as “believes”, “intends”, “may”, “will”, “should”,
“plans”, “anticipates”, “potential”, “expects”, “estimates”, “forecasts”, “budget”, “likely”, “goal” and similar expressions or statements that certain actions, events or results may or may not be achieved or
occur in the future. In some cases, forward-looking information may be stated in the present tense, such as in respect of current matters that may be continuing, or that may have a future impact or effect.
Forward-looking statements reflect our current expectations and assumptions, and are subject to a number of known and unknown risks, uncertainties and other factors which may cause our actual results,
performance or achievements to be materially different from any anticipated future results, performance or achievements expressed or implied by the forward-looking statements. Forward-looking statements
include, but are not limited to statements regarding the anticipated 2018 Exploration Program timeline, observations from the 2018 infill drilling and underground development samples from test mining, the
potential advancement of the Phoenix Gold Project to a viable commercial operation, the potential value of the Company’s tax loss pools, the potential resale value of the equipment and hard assets of the
Phoenix Gold Project, the potential to improve the quantities and classification of the 2018 Mineral Resource Estimate, the impact of the new 2018 geological model and information on the Company’s
understanding of the F2 Gold Deposit and evaluation of mining methods for the Phoenix Gold Project, the additional exploration work required to further improve and reconcile the geological model for the F2
Gold Deposit, the further steps necessary to potentially improve upon the 2018 Mineral Resource Estimates, including targeted infill and step-out drilling to potentially convert Inferred Resources to Indicated
Resources, using the results from the bulk sampling program for reconciliation and validation purposes, the evaluation of the McFinley Deposit and other close proximity targets for potential inclusion in a
future Mineral Resources Estimate, and follow-up drilling of the F2 Gold Deposit at depth and along strike.
Forward-looking statements are based on the opinions and estimates of management as of the date such statements are made and represent management’s best judgment based on facts and assumptions that
management considers reasonable. If such opinions and estimates prove to be incorrect, actual and future results may be materially different than expressed in the forward-looking statements.
Forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of Rubicon to be materially different from any
future results, performance or achievements expressed or implied by the forward-looking statements. Such factors include, among others: possible variations in mineralization, grade or recovery or throughput
rates; uncertainty of mineral resources, inability to realize exploration potential, mineral grades and mineral recovery estimates; actual results of current exploration activities; actual results of reclamation
activities; uncertainty of future operations, delays in completion of exploration plans for any reason including insufficient capital, delays in permitting, and labour issues; conclusions of future economic or
geological evaluations; changes in project parameters as plans continue to be refined; failure of equipment or processes to operate as anticipated; accidents and other risks of the mining industry; delays and
other risks related to operations; timing and receipt of regulatory approvals; the ability of Rubicon and other relevant parties to satisfy regulatory requirements; the ability of Rubicon to comply with its
obligations under material agreements including financing agreements; the availability of financing for proposed programs and working capital requirements on reasonable terms; the ability of third-party service
providers to deliver services on reasonable terms and in a timely manner; risks associated with the ability to retain key executives and key operating personnel; cost of environmental expenditures and
potential environmental liabilities; dissatisfaction or disputes with local communities or First Nations or Aboriginal Communities; failure of plant, equipment or processes to operate as anticipated; market
conditions and general business, economic, competitive, political and social conditions; our ability to generate sufficient cash flow from operations or obtain adequate financing to fund our capital expenditures
and working capital needs and meet our other obligations; the volatility of our stock price, and the ability of our common stock to remain listed and traded on the TSX.
Cautionary Statements Regarding Forward-Looking
Statements and Cautionary Notes
2
3. TSX : RMX | OTCQX : RBYCF
Forward-looking statements contained herein are made as of the date of this corporate presentation and Rubicon disclaims any obligation to update any forward-looking statements, whether as a result of
new information, future events or results or otherwise, except as required by applicable securities laws. Readers are advised to carefully review and consider the risk factors identified in the Company’s
annual information form dated March 22, 2018 under the heading “Risk Factors” and in other continuous disclosure documents of the Company filed at www.sedar.com for a discussion of the factors that
could cause Rubicon’s actual results, performance and achievements to be materially different from any anticipated future results, performance or achievements expressed or implied by the forward-looking
statements. Readers are further cautioned that the foregoing list of assumptions and risk factors is not exhaustive and it is recommended that prospective investors consult the more complete discussion of
Rubicon’s business, financial condition and prospects that is included in this corporate presentation. The forward-looking statements contained herein are expressly qualified by this cautionary statement.
Qualified Person
The content of this corporate presentation relating to geology and exploration has been read and approved by George Ogilvie, P.Eng., President, CEO, and Director, who is a Qualified Person as defined by
NI 43-101.
Cautionary Note to U.S. Readers Regarding Estimates of Measured, Indicated and Inferred Resources
This corporate presentation uses the terms “Measured” and “Indicated” Mineral Resources and “Inferred” Mineral Resources. The Company advises U.S. investors that while these terms are recognized and
required by Canadian securities administrators, they are not recognized by the SEC. The estimation of “Measured” and “Indicated” Mineral Resources involves greater uncertainty as to their existence and
economic feasibility than the estimation of Proven and Probable Reserves. The estimation of “Inferred” resources involves far greater uncertainty as to their existence and economic viability than the
estimation of other categories of resources. It cannot be assumed that all or any part of a “Measured”, “Inferred” or “Indicated” mineral resource will ever be upgraded to a higher category.
Under Canadian rules, estimates of “inferred mineral resources” may not form the basis of feasibility studies, pre-feasibility studies or other economic studies, except in prescribed cases, such as in a
preliminary economic assessment under certain circumstances. The SEC normally only permits issuers to report mineralization that does not constitute “reserves” as in-place tonnage and grade without
reference to unit measures. Under U.S. standards, mineralization may not be classified as a “reserve” unless the determination has been made that the mineralization could be economically and legally
produced or extracted at the time the reserve determination is made. U.S. investors are cautioned not to assume that any part or all of a “measured”, “indicated” or “inferred” mineral resource exists or
is economically or legally mineable. Information concerning descriptions of mineralization and resources contained herein may not be comparable to information made public by U.S. companies subject to
the reporting and disclosure requirements of the SEC.
Cautionary Statements Regarding Forward-Looking
Statements and Cautionary Notes
3
4. TSX : RMX | OTCQX : RBYCF
Corporate Vision
Three-pronged approach to build long-term shareholder value
4
Potentially building a mid-tier gold Company:
1. Advancement of the Phoenix Gold Project to commercial
production;
2. Organic growth opportunities with exploration targets
within 2 km of the Phoenix Gold Project; and
3. Exploring our vast Red Lake Properties land package.
5. TSX : RMX | OTCQX : RBYCF
Capital Structure and Shareholder Info
Strong balance sheet and institutional support
Balance Sheet and Capital Structure
Approximate cash balance: ~C$12.5 M
Nominal long-term debt outstanding
(December 31, 2020):
C$12.0 M
Lease liabilities C$2.5 M
Shares outstanding: 65,853,092
Options outstanding: 4,199,703
Institutional
Investors
70.72%
George
Ogilvie
0.72%
CPPIB
Credit
15.19%
Retail
8.24%
Royal
Gold
5.13%
Equity ownership breakdown*
5
Analyst Coverage
BMO Andrew Mikitchook
TD Securities Daniel Earle
Laurentian Bank Ryan Hanley
Mackie Research Stuart McDougall
Industrial Alliance George Topping
Canaccord Genuity Tom Gallo
Market Data (October 9, 2018)**
RMX share price: C$1.28
Market capitalization: C$84.5 M
Avg. 30-day daily trading volume
(TSX & OTC markets)
40,671
*Numbers may not add due to rounding
**Source: TSX and OTC markets, as of October 9, 2018
Institutional shareholders include:
Mackenzie Financial Ninepoint (Sprott)
Donald Smith & Co. Greywolf
Sentry Investments Sun Valley Gold
Franklin Templeton U.S. Global
(475,940 shares)
6. TSX : RMX | OTCQX : RBYCF
Board and Management Team Strengthened
Expertise in geology, underground mining, finance and law
6
Technical Management Team
George Ogilvie, P.Eng., President and CEO • Led the successful turnaround of Kirkland Lake Gold and its acquisition of St.
Andrew Goldfields
• Grew Rambler Metals from grassroots exploration to profitable junior producer
Mike Willett, P.Eng., Director of Projects • Led the increase in mineral resources and permitting as President and CEO of
Tamerlane Ventures Inc.
• Held senior roles with March Consulting Associates/Hudbay.
Board of Directors
Julian Kemp, BBA, CPA, CA, C.Dir (Chair) • Led Rubicon through a successful strategic review and CCAA process
• Former CFO Fortune Minerals
Peter R. Jones, P.Eng. • Led the successful IPO of Hudbay Minerals Inc. and its turnaround
• Former Chair and CEO of Adanac Molybdenum, Chair of Medusa Mining and
Augyva Mining Resources
Dr. David A.S. Palmer, PhD, P.Geo. • Led the discovery of the Borden Deposit as President and CEO of Probe Mines and
the sale of the company to Goldcorp in 2015
• Current President and CEO of Probe Metals
Daniel Burns, JD, MBA, CPA, CMA, ICD.D, ACC • Experienced director in fields of financial services
• President and CEO of NDC Solutions Inc.
• Current Chair of World Council of Credit Unions
Sasha Bukacheva, CFA, MSc. • Previously a top-ranked base metals Equity Research Analyst for BMO
• Former Vice President, Finance and Administration for Stans Energy Corp.
7. TSX : RMX | OTCQX : RBYCF
• Head frame and hoist
commissioned
• 13 km of U/G development;
Shaft completed to 730 m
below surface
200-person camp
Tailings management
facility completed
• Surface roads, earth and civil works in place
• Power line and substation on site
7
Infrastructure and Permits in Place
>C$770 million spent on infrastructure and development
Item: Capital spent/Tax pools (C$)
Mill construction ~$150 M
Surface construction ~$95 M
Underground exploration,
development, sampling, etc.
~$525 M
Total $770 M
Tax loss pools (April 2018)
$687 M
$387M – Phoenix Gold Project
$300M – can be used externally
7
• 1,250 tpd mill
• 91.5% recoveries during 2015
• Substantially permitted
8. TSX : RMX | OTCQX : RBYCF 8
Conceptual Asset Values Mitigate Downside Risk
Assets carry conceptual values comparable to the Company’s market cap
8
Red Lake Properties (28,266 ha):
Based on precedent land transactions in Red Lake,
Rubicon’s Red Lake Properties could have a
conceptual value of between C$30-50 M
Hard assets and equipment at site:
More than ~C$300 M of equipment and hard assets
could potentially have a resale value of ~C$30 M
Tax loss pools and end working capital:
Potential value of C$10-15 M
Current cash balance:
~C$12.5 M
Red Lake Properties
~C$30-50M
Hard assets and
equipment
~C$30M
Financial assets
~C$20-25M
Rubicon current market
capitalization: C$84.5 M
Long-term debt
(~C$15M)
CPPIB Credit LT Debt:
C$12 M with 5% coupon (payment-in-kind)
9. TSX : RMX | OTCQX : RBYCF
Milestones to Bring Confidence Back to the
Phoenix Gold Project
9
• Hired reputable consultant and peer reviewer from the start: Golder Associates and T. Maunula &
Associates have been working with Rubicon since early 2017.
• Focus on structural geology: 3,500 m structural oriented drilling, 10,000 m historical core re-logged, and extensive
underground mapping shows discrepancies with the 2016 geological model.
• 2017 infill and step out drilling showing higher grades compared to 2016 block model: 25,000 m
drilled in 2017 and 20,000 m planned for 2018
• Structural Interpretation shows better continuity: Simplified interpretation allows for the evaluation of bulk
mining methods
• 2018 Mineral Resource Estimate demonstrates significant growth
• 25,000-30,000 tonnes of test mining/bulk sampling in 2018: Test mining and bulk sampling
activities completed in October 2018; Mill cleanout underway
• Block model reconciliation to be completed in Q4/18: Golder Associates will be conducting
reconciliation
• Potential to significantly enhance the quantities and classifications of the 2018 Mineral Resource
Estimate
10. TSX : RMX | OTCQX : RBYCF
Structural Interpretation10
Comparison of structural interpretations of the F2 Gold Deposit
10
• Riedel vein system:
System of mineralized
quartz-actinolite veins that
appear to be primary
structural controls on gold
mineralization at the F2
Gold Deposit
• More continuity of gold
mineralization within the
HiTi Basalt Units (main host
rock) compared to the 2016
geological model
• Evaluating bulk mining
methods: Test mining
sublevel longhole method
on current test stopes
Historical drill holes
HiTi Basalt Units
Ultramafic Flow Units
High-grade domain
D1 N-S structures
D2 E-W structures
Quartz-Breccia Zones
(higher grade)
Mineralized
Riedel veins
(orientations):
R’ veins
R veins
P veins
D2 dextral transpresion
2013 Structural
Interpretation
(1.1Moz Indicated;
2.2Moz Inferred)
2016 Structural
Interpretation
(0.1Moz Indicated;
0.3Moz Inferred)
2018 Structural
Interpretation
(0.28Moz M+I;
0.75Moz Inferred)
North
(mine-grid)
(10) Refer to endnote #10
Plan Views
11. TSX : RMX | OTCQX : RBYCF 11
Material Growth in 2018 Mineral Resources11
Consideration for potential bulk mining methods
Resource
Category
Quantity
(000'tonnes)
Grade
(g/t Au)
Contained
Gold Ounces
Measured (M) 188 6.80 41,000
Indicated (I) 1,186 6.30 240,000
M + I 1,374 6.37 281,000
Inferred 3,884 6.00 749,000
2018 Mineral Resource Estimate – April 30, 2018*
@ 3.0 g/t Au Cut-off
• 113% increase in M+I Resources*;
80% increase in Inferred Resources*;
improved grades: Mainly attributed
to a re-interpretation of geological
and structural controls on
mineralization along with recognizing
the potential for larger scale mining
which resulted in broader mineral
domains
• Golder (lead) & T. Maunula (peer
reviewer): More than 12 months of
collaboration with Rubicon
• Encouraging results: Initial
observations from test mining
consistent with 2018 Mineral
Resources; too early to draw
conclusions
• Effective date for this Mineral Resource is April 30, 2018
• Mineral Resource Estimate uses a break-even economic cut-off grade of 3.0 g/t Au based on assumptions
of a gold price of US$1,300 per ounce, an exchange rate of US$/C$ 0.77, mining cash costs of C$97/t,
processing costs of C$20/t, G&A of C$5/t, sustaining capital C$10/t, refining, transport and royalty costs
of C$53/oz, and average gold recoverability of 92%
• Mineral Resources are not Mineral Reserves and do not demonstrate economic viability
• There is no certainty that all or any part of this Mineral Resource will be converted into Mineral Reserve
• All figures are rounded to reflect the relative accuracy of the estimates and totals may not add correctly
*There is no certainty that the Inferred Mineral Resources will be converted to the Measured and Indicated Mineral Resource categories, that the
Measured and Indicated Mineral Resources will be converted to the Proven and Probable Mineral Reserve categories and there is no certainty that
the updated Mineral Resource statement will be realized. Mineral Resources that are not Mineral Reserves do not have demonstrated economic
viability; the estimate of Mineral Resources in the updated Mineral Resource statement may be materially affected by environmental, permitting,
legal, title, taxation, socio-political, marketing, or other relevant issues.
(11) Refer to endnote #11
12. TSX : RMX | OTCQX : RBYCF 12
Material Growth in 2018 Mineral Resources
Potential to enhance quantities and classifications
• 20,000 m of infill/step-out
drilling: To Potentially improve
the classification of Inferred
Resources; potential to grow
resources
• Block model reconciliation will
be based on 25,000-30,000t
bulk sampling: To increase
confidence and validate a future
Mineral Resource Estimate
• F2 Gold Deposit open at depth
and along strike: High-grade
intercepts at 1,600 m, below
current bottom of 2018 Mineral
Resource Estimate
2018 Mineral Resource Block Model Diagram Zone 2
(Hanging Wall and West Limb Basalts)
Section View Looking West (Mine-Grid)
Exploration Target potential:
500-800kt @ 5.0-7.0 g/t Au 200 m
Infill drilling
target areas
13. TSX : RMX | OTCQX : RBYCF
2018 Exploration Program
Conceptual underground section diagram looking north
13
Surface
Fresh air
raise
337-metre loading pocket
685-metre
loading pocket
Shaft
610-metre haulage level
305-metre haulage level
Diagram looking north (not to scale)
Conveyer system
Ore and
waste
passes
Main F2 Gold Deposit
Completed development Drilling platforms
More than 13km of
U/G development
Conceptual ramp
to surface
25,000-30,000t of test mining
between the 122- and 244-
metre levels; up to 4,000 m
of bazooka drilling at the
stope faces
20,000 m of infill/step-out
drilling at the 305-, 610- and
685-metre levels;
Building exploration drift at
610-metre level
Planned development
200-metre exploration
drift, parallel to the strike
of the F2 Gold Deposit
14. TSX : RMX | OTCQX : RBYCF
122-metre level
244-metre level
305-metre level
183-metre level
161 test stope
977 test stope
015 test stope
Existing underground
development
60 m
2018 planned
test stopes
Previously mined
test stopes
997 mined test stope
030 mined test stope
994 mined test stope
2018 Test Mining – Conceptual Diagram9
>35,000 tonne bulk sample processing completed
Long section looking west
• Block model reconciliation
anticipated in Q4/18
• Test trial mining and bulk sample
processing activities completed;
gold sales used to mill cleanout
underway
• Test stopes are previously well
developed and drilled, allowing the
Company to take advantage of
sunk capital for reduced costs and
timelines
Please refer to the Cautionary Statements Regarding Forward-Looking Statements and Cautionary Notes at the
beginning of this presentation with respect of the Company’s Qualified Person.
(9) Refer to endnote #9
14
First bar poured from bulk sample program
15. TSX : RMX | OTCQX : RBYCF
2018 Exploration Program:
24,000 m of infill and step-out drilling
Structural Interpretation
Exploratory development
in the main F2 Gold Deposit
Test mining, bulk sampling,
and bazooka drilling
2018 Mineral Resource Estimate
Results from bulk sampling/reconciliation
Decision on feasibility study
2018
H1 H2
Anticipated 2018 Exploration Program Timeline
15
19,000 m completed;
drilling ongoing
Bulk sampling
completed;
Mill cleanout
underway
16. TSX : RMX | OTCQX : RBYCF
Cochenour (G)
Red Lake Gold Mines (G)
Phoenix Gold Project (RMX)
D2 Structures
Red Lake, ON
N
RMX claims: 28,776 hectares ~40% of claims in Red Lake
Goldcorp (G) claims
Ultramafic units
F2 folds
Gold projects in active exploration
Existing gold mines
RMX prospective exploration targets
Slate Bay
(RMX)
DMC
(RMX)
Adams Lake
(RMX)
East Bay
(RMX)
Prolific Red Lake Gold District:
Camp has produced more than 29 million ounces of gold
16
Rahill-Bonanza (PG/G)
H.G. Young (G)
Hasaga (PG)
McCuaig
(RMX)
17. TSX : RMX | OTCQX : RBYCF
Recent Land Transactions in Red Lake
Rubicon owns a sizeable land package in Red Lake
Date Property
Size
(ha)
Seller Buyer Sale price* Price/ha
Additional
info
Nov 2017 McCuaig (40%) 50 Golden Tag Rubicon C$0.7 M C$14,630/ha
Land
transaction
Mar 2017
Derlak (near
Madsen)
219 Orefinders Pure Gold C$1.2 M C$5,465/ha
Land
transaction
Dec 2015
Buffalo claims
(near Hasaga)
513 Pure Gold
Premier
Gold
~C$5.0 M C$9,747/ha
Land
transaction;
Pure Gold
gets 1.0%
NSR
Nov 2015 Springpole 32,448 Gold Canyon
First Mining
Finance
~C$56.2 M C$1,732/ha
Company
acquisition;
MRE
Jun 2014
Newman-
Madsen
>807
Sabina Gold
& Silver
Pure Gold ~C$2.8 M C$3,463/ha
Land
transaction
Mar 2014 Madsen 4,193
Claude
Resources
Pure Gold ~C$8.8 M C$2,087/ha
Asset
transaction
500 tpd mill,
MRE
Rubicon Red Lake Exploration Land Package
(excluding Phoenix Gold Project claim)
28,266 ha
Source: Company reports and Rubicon estimates 17
*Total consideration of cash and share
values at the time of acquisition
18. TSX : RMX | OTCQX : RBYCF
1000 m
244-metre level
exploration drift
Shaft
Island Zone
CARZ
Northern
Peninsula
F2 Gold Deposit
McFinleyCamp
F2 North
• 5-6 close proximity targets within 2 km of the Phoenix Gold Project
• All are potentially accessible from underground
• In-house modelling of the mineralized zones and generate
conceptual tonnes and grade for the zones; rank each zone as to
potential to fit in pipeline
• Build “Rubicon Red Lake” model to look at bigger picture
(structural and lithological model)
• Evaluating the resource potential of Historic McFinley,
Northern Peninsula, CARZ, and Island Zone
18
Close Proximity Targets
Potential LOM incremental feed of the Phoenix Gold Project
Long section looking north west
McFinley
Deep
19. TSX : RMX | OTCQX : RBYCF
Main F2 Gold
Deposit
Shaft
Historic
McFinley
Deposit
“B Zone”
Structure
“C Zone”
Structure
244-17-C02:
2.66 g/t Au over 0.5 m
1.05 g/t Au over 0.6 m
244-17-C03:
4.87 g/t Au over 0.4 m
2.31 g/t Au over 0.5 m
244-17-C03:
3.60 g/t Au over 0.5 m
1.53 g/t Au over 0.9 m
Scale: 200 m
Drill hole
U/G development
Close Proximity Targets – McFinley
Plan View
19
Historic McFinley Deposit (2002)1
Inferred: 66,801 oz Au
(303,006 tonnes grading 6.86 g/t Au)
1Not compiled according to NI 43-101
20. TSX : RMX | OTCQX : RBYCF
685-17-C04:
3.66 g/t Au over 0.4 m
2.93 g/t Au over 0.7 m
3.48 g/t Au over 1.0 m
5.55 g/t Au over 0.7 m
More than 550 m
deep from the
bottom of the
historic McFinley
Deposit mineral
resource
Scale: 200 m
Drill hole
U/G development
122-metre
level
183-metre
level
244-metre
level
305-metre
level
610-metre
level
685-metre
level
Main F2
Gold
Deposit
Shaft
Close Proximity Targets – McFinley Deep
Potential LOM incremental feed of the Phoenix Gold Project
Historic McFinley Deposit (2002)
Inferred: 66,801 oz Au
(303,006 tonnes grading 6.86 g/t Au)
• Drilling intersected gold-
bearing quartz veins and
sulphides through four
zones, similar to the
lithological sequence in
the historic McFinley
Deposit
• Drill hole ended in HiTi
basalts, suggesting that
mineralization remains
open to the west (mine
grid)
Isometric view looking northwest
20
21. TSX : RMX | OTCQX : RBYCF
Close Proximity Targets
Northern Peninsula, CARZ & Island Zone
21
• Historical high-grade intercepts along strike and
adjacent to the F2 Gold Deposit warrant follow up
drilling
• Compiling dataset and evaluating mineral
resource potential for eventual drill program
Select historical high-grade intercepts:
Island Zone (not true widths)
• PZ-23: 70.1 g/t Au over 3.1 m
• PZ-12: 28.7 g/t Au over 1.4 m
• PZ-47: 22.2 g/t Au over 1.7 m
• PZ-25: 15.8 g/t Au over 3.5 m
• PZ-03: 15.5 g/t Au over 4.8 m
• PZ-02: 15.0 g/t Au over 2.8 m
Carbonate Zone (“CARZ”)(not true widths)
• PR-15-11: 24.17 g/t Au over 2.00 m
• PR-15-11: 4.88 g/t Au over 10.50 m (incl. 6.43 g/t Au over 7.00 m)
• PR-15-16: 8.48 g/t Au over 3.25 m (incl. 11.10 g/t Au over 2.25 m)
• PR-15-19: 8.43 g/t Au over 1.05 m
• PR-15-19: 2.30 g/t Au over 12.00 m (incl. 5.76 g/t Au over 2.00 m)
• PR-15-06: 10.77 g/t Au over 2.65 m
• PR-15-09: 7.84 g/t Au over 1.50 m
Plan view
F2 North
22. TSX : RMX | OTCQX : RBYCF
Red Lake Regional Properties
Highly-prospective exploration targets
22
• Several highly-prospective
grassroots exploration targets
• Potential exploration work will
commence if the Phoenix Gold
Project’s advancement is on
the right path
• Targets were evaluated and
prioritized by an exploration
consultant with +20 years of
experience in Red Lake
3# Sidace
1# McCuaig
2# East Bay
4# Slate Bay
23. TSX : RMX | OTCQX : RBYCF
Key Takeaways to the Rubicon Story
Advanced exploration. Red Lake. High-grade gold potential
23
• Sunk Capital: Mine substantially built and permitted in safe and friendly
jurisdiction
• Block Model Reconciliation: A successful reconciliation exercise could
potentially validate and give credibility to the new 43-101 Mineral
Resource Estimate
• Potential Mineral Resource Growth: 20,000 m of additional infill,
oriented drilling couple potentially grow the 43-101 Mineral Resource
Estimate
• Economic Studies: Potential to advance Project to feasibility-level study
in 2019
• Short Timeline: Assuming a fully-funded positive feasibility-level study,
timeline to potential production would be roughly 12-18 months
• Vast Regional Land Package: Excellent exploration potential with
McFinley Deep, Close Proximity targets, and regional targets in Red Lake,
Ontario.
25. TSX : RMX | OTCQX : RBYCF
Structural Interpretation10
Conceptual diagram of F2 Gold Deposit local geology; Plan View
25
N
50 m
Shaft
West Limb
BasaltHanging Wall
Basalt
F2 Basalt
Historic McFinley
Deposit area
HiTi Basalt Units
Drill hole intersecting
Ultramafic Flow Units
Drill hole intersecting
Felsic Intrusive Units
Underground
development
Drill hole intersecting
HiTi Basalt Units
Remains open
along strike
Remains open
along strike
(10) Refer to endnote #10
26. TSX : RMX | OTCQX : RBYCF
Structural Interpretation10
Conceptual diagram of F2 Gold Deposit local geology
26
50 m
Historic
McFinley
Deposit area
Hanging
Wall Basalt
West Limb
Basalt
F2 Basalt
610-metre
level
305-metre level
HiTi Basalt Units
Drill hole intersecting
Ultramafic Flow Units
Drill hole intersecting Felsic
Intrusive Units
Underground
development
Drill hole intersecting
HiTi Basalt Units
• Three HiTi Basalt lenses:
Zone 1 (domain): F2 Basalt (horizontal widths of
20-30 m without felsic dykes; around 8 m with
felsic intrusions)
Zone 2 (domain): West Limb Basalt (horizontal
widths of 8 m), and Hanging Wall Basalt
(horizontal widths of 4-6 m; larger zones at depth)
• Mineralization encountered at 1,600 m below
surface: Current Mineral Resource Estimate is down
to the 1,325 m below surface
• Structural Interpretation will continue to be refined,
enhanced, and supported with data and
observations collected from the 2018 Exploration
Program
Section view
looking north
(10) Refer to endnote #10
27. TSX : RMX | OTCQX : RBYCF 27
Material Growth in 2018 Mineral Resources11
Increased tonnes, grade and ounces at all cut-offs and categories
Quantity (000’ tonnes) Grade (g/t Au) Contained Gold Ounces
2018 2016** Change 2018 2016** Change 2018 2016** Change
3.0 g/t Au
Measured (M) 188 0 N/A 6.80 0 N/A 41,000 0 N/A
Indicated (I) 1,186 719 65% 6.30 5.71 10.3% 240,000 132,000 81.8%
Total M+I 1,374 719 91% 6.37 5.71 11.6% 281,000 132,000 112.9%
Inferred 3,884 2,491 56% 6.00 5.18 15.8% 749,000 415,000 80.5%
3.5 g/t Au
Measured (M) 155 0 N/A 7.54 0 N/A 38,000 0 N/A
Indicated (I) 964 601 60% 7.01 6.19 13% 217,000 120,000 81%
Total M+I 1,119 601 86% 7.08 6.19 14.4% 255,000 120,000 113%
Inferred 3,146 1,959 61% 6.64 5.71 16.3% 672,000 360,000 87%
4.0 g/t Au
Measured (M) 129 0 N/A 8.29 0 N/A 35,000 0 N/A
Indicated (I) 779 492 58% 7.78 6.73 16% 195,000 106,000 84%
Total M+I 909 492 85% 7.86 6.73 17% 230,000 106,000 117%
Inferred 2,556 1,519 68% 7.31 6.28 16% 601,000 307,000 96%
Comparison between 2018* and 2016** Estimated Quantities
at Reported Cut-Off Grades
(11) Refer to endnote #11
*There is no certainty that the Inferred Mineral Resources will be converted to the Measured and Indicated Mineral Resource categories, that the
Measured and Indicated Mineral Resources will be converted to the Proven and Probable Mineral Reserve categories and there is no certainty that
the updated Mineral Resource statement will be realized. Mineral Resources that are not Mineral Reserves do not have demonstrated economic
viability; the estimate of Mineral Resources in the updated Mineral Resource statement may be materially affected by environmental, permitting,
legal, title, taxation, socio-political, marketing, or other relevant issues.
**2016 Estimates are no longer current and should not be relied upon.
28. TSX : RMX | OTCQX : RBYCF 28
Material Growth in 2018 Mineral Resources11
Potential to enhance quantities and classifications
2018 Mineral Resource Block Model Diagram
– Plan View, 244-Metre Level
2018 Mineral Resource Block Model Diagram Zone 1
– Section View Looking West (Mine-Grid)
(11) Refer to endnote #11
29. TSX : RMX | OTCQX : RBYCF
History of Mineral Resource Estimates
Historical estimates are not current and should no be relied upon
GEOEX – Amended2,6
(2011)
AMC3,6
(2011)
SRK4,6
(2013)
SRK5,6,7
(2016)
Grade
(g/t Au)
17.3 (inferred, capped) 14.5 (indicated)
17.0 (inferred)
8.5 (indicated)
9.3 (inferred)
6.7 (indicated)
6.3 (inferred)
Ounces 3.1 M (inferred) 0.5 M (indicated)
2.3 M (inferred)
1.1 M (indicated)
2.2 M (inferred)
0.1 M (indicated)
0.3 M (inferred)
Tonnes (t) 5.500 M (inferred) 1.028 M (indicated)
4.230 M (inferred)
4.120 M (indicated)
7.452 M (inferred)
0.492 M (indicated)
1.519 M (inferred)
Grade
interpolation
polygonal inverse distance
cubed
ordinary kriging ordinary kriging
Grade capping 10-5-2 oz
(311-155.5-62.2 g/t Au)
270 g/t Au 200 g/t Au (Main)
150 g/t (HW), 30 g/t (Ext)
10–120 g/t Au (HG domains)
5–45 g/t Au (LG domains)
Cut-off grade
(g/t Au)
5.0 5.0 4.0 4.0
Metres drilled at
F2 Gold Deposit
166,886 m 259,000 m +
2,000t bulk sample
355,611 m 450,175 m + trial stoping
Metrics from PEA
Grade to the mill
(g/t Au)
n/a 13.9 8.1 n/a
Average stope
width
n/a 2.0 m 7.8 m n/a
Overall dilution n/a 18% 44% n/a
29
(2) Refer to endnote #2, (3) Refer to endnote #3, (4) Refer to endnote #4, (5) Refer to endnote #5, (6) Refer to endnote #6 (7) Refer to endnote #7
Please refer to the Cautionary Statements Regarding Forward-Looking Statements and Cautionary Notes at
the beginning of this presentation with respect of the Company’s Qualified Person.
30. TSX : RMX | OTCQX : RBYCF
Close Proximity Targets – McFinley Deep
Cross Sections of “B” and “C” Zone Structures
30
244-17-C02:
2.66 g/t Au over 0.5 m
1.05 g/t Au over 0.6 m
244-17-C03:
3.60 g/t Au over 0.5 m
1.53 g/t Au over 0.9 m
Historic McFinley
Deposit
122-metre level
183-metre level
244-metre level
305-metre level
122-metre level
183-metre level
244-metre level
305-metre level
244-17-C03:
4.87 g/t Au over 0.4 m
2.31 g/t Au over 0.5 m
Drill hole
U/G development
Potential gold-bearing structure
Historic McFinley Deposit (2002)1
Inferred: 66,801 oz Au
(303,006 tonnes grading 6.86 g/t Au)
1Not compiled according to NI 43-101
31. TSX : RMX | OTCQX : RBYCF
Board and Management Team Strengthened
Expertise in geology, underground mining, finance and law
31
Management Team Additions
George Ogilvie, P.Eng., President and CEO • Led the successful turnaround of Kirkland Lake Gold and its acquisition of St.
Andrew Goldfields
• Grew Rambler Metals from grassroots exploration to profitable junior producer
Mike Willett, P.Eng., Director of Projects • Led the increase in mineral resources and permitting as President and CEO of
Tamerlane Ventures Inc.
• Held senior roles with March Consulting Associates/Hudbay.
Board of Directors
Julian Kemp, BBA, CPA, CA, C.Dir (Chair) • Led Rubicon through a successful strategic review and CCAA process
• Former CFO Fortune Minerals
Peter R. Jones, P.Eng. • Led the successful IPO of Hudbay Minerals Inc. and its turnaround
• Former Chair and CEO of Adanac Molybdenum, Chair of Medusa Mining and
Augyva Mining Resources
Dr. David A.S. Palmer, PhD, P.Geo. • Led the discovery of the Borden Deposit as President and CEO of Probe Mines and
the sale of the company to Goldcorp in 2015
• Current President and CEO of Probe Metals
Daniel Burns, JD, MBA, CPA, CMA, ICD.D, ACC • Experienced director in fields of financial services
• President and CEO of NDC Solutions Inc.
• Current Chair of World Council of Credit Unions
Sasha Bukacheva, CFA, MSc. • Previously a top-ranked base metals Equity Research Analyst for BMO
• Former Vice President, Finance and Administration for Stans Energy Corp.
32. TSX : RMX | OTCQX : RBYCF
1. For more information regarding 2017 Exploration program drilling results, please refer to the news releases dated
September 18, 2017, November 16, 2017, December 14, 2017, and February 20, 2018, which are available on our website at
www.rubiconminerals.com.
2. For more information regarding the amended inferred mineral resource and geological potential estimates prepared by
Geoex Ltd. please refer to the news release dated March 31, 2011, which is available on our website at
www.rubiconminerals.com and the Technical Report dated April 11, 2011 available on under Rubicon’s profile in SEDAR at
www.sedar.com.
3. For more information regarding the 2011 PEA study prepared by AMC Mining Consultants, please refer to the news release
dated June 29, 2011, which is available on our website at www.rubiconminerals.com and the Technical Report dated August
11, 2011 available on under Rubicon’s profile in SEDAR at www.sedar.com.
4. For more information regarding the 2013 PEA study prepared by SRK Consulting (Canada) Inc., please refer to the news
release dated June 25, 2013, which is available on our website at www.rubiconminerals.com and the Amended & Restated
Technical Report dated February 28, 2014 available under Rubicon’s profile in SEDAR at www.sedar.com.
5. For more information regarding the 2016 SRK mineral resource estimate prepared by SRK Consulting (Canada) Inc., please
refer to the news release dated January 11, 2016, which is available on our website at www.rubiconminerals.com and the
Technical Report filed on February 25, 2016 available under Rubicon’s profile at www.sedar.com.
6. Mineral resources are not mineral reserves and have not demonstrated economic viability. All figures are rounded to reflect
the relative accuracy of the estimate. Samples have been capped where appropriate.
7. Underground mineral resources reported at a cut-off grade of 4.0 g/t Au of gold per tonne assuming a gold price of
US$1,125/oz. and a gold recovery of 92.5%.
8. For more information regarding the first trial stope reconciliation, please refer to the news release dated November 3,
2015, which is available on our website at www.rubiconminerals.com.
9. For more information regarding 2018 Exploration program please refer to the news release dated January 23, 2018 which is
available on our website at www.rubiconminerals.com.
10. For more information regarding the Structural Interpretation, please refer to the news release dated March 12, 2018 which
is available on our website at www.rubiconminerals.com.
11. For more information regarding the 2018 Mineral Resource Estimate, please refer to the news release dated April 30, 2018
which is available on our website at www.rubiconminerals.com.
32
Endnotes
33. TSX : RMX | OTCQX : RBYCF
For more information, please contact:
Allan Candelario, CFA
Director, Investor Relations and Corporate Development
416-766-2804
acandelario@rubiconminerals.com
33