Republic of the Philippines
                                                Province of Ilocos Sur
                                                   City of Vigan

                              CITY PLANNING AND DEVELOPMENT OFFICE
                              APPROVED PROJECT MONITORING REPORT
                              Date Covered: January 01 – December 31, 2010

No.             Description of                       Project          Contract          Source of      Name of
                   Work                             Location            Cost              Fund        Contractor
                                                                       (Php)
 1    Road Concreting                           Pantay Laud            171,382.20         LGU       739 Builders
 2    Concrete Topping @ Brgy. Plaza            Purok A Bassit         171,837.60         LGU       739 Builders
 3    Repainting of Stage, Basketball           Plaza Burgos            95,968.00         LGU       Bonifacio Pugal
      Court, Bleachers and Path walk
 4    Road Concreting                           San Julian Sur –        497,964.72        LGU       739 Builders
                                                Cabaroan Laud
 5    Concreting of Farm to Market Road         Camangaan               998,055.67        LGU       MBB Const.
      @ Sitio Nalasin
 6    Fabrication and Installation of Boat       Beddeng Laud           267,405.60        LGU       739 Builders
      Shed and Wooden Flooring @ Vigan
      River Cruise
 7    Const. of Tanod Outpost and MP            Pong-ol                 474,018.39      LGU/BRGY.   HEAF Consul.
      Bldg
 8    Brgy. Raod Concreting                     Beddeng Laud            320,055.12      LGU/BRGY.   739 Builders
 9    Concreting of Farm to Market Road         Pons Road                98,981.34        LGU       MBB Const.
                                                Nagsangalan
10    Fabrication & Installation of             Mindoro                 991,584.00        LGU       739 Builders
      Hexapods
11    Construction of Stone Masonry Wall        San Julian Norte        822,465.65        LGU       MBB Const.
      @ Vigan Shelterville
12    Landscaping of Senior Citizen Bldg.       Ayusan Sur              248,477.10        LGU       Francisco Flores
      & Installation of Perimeter Fence
13    Construction of CHB Lined Canal           Capangpangan            235,903.80        LGU       739 Builders
      (Open) & Rehab. Of Culvert
14    Const. of Skills Training Inst. Bldg.     VPM Annex               219,106.80        LGU       739 Builders
15    Const. & Install. Of Steel & Conc.        Barangay II              99,000.00        LGU       739 Builders
      Cover
16    Const. of Waiting Shed/Tanod              Raois                       98,362.63     LGU       MBB Const.
      Outpost
17    Rehab. Of Drainage Canal w/ Cover         Barangay VIII           134,541.00        LGU       739 Builders
18    Const. of CHB Lined Canal w/ Cover        Barangay IV             218,103.60        LGU       739 Builders
19    Construction of Perimeter Fence           Barangay VII            246,644.00      LGU/BRGY.   739 Builders
20    Concreting of Farm to Market Road         Nagsangalan –           478,887.40        LGU       HEAF
                                                San Julian Sur                                      Consultancy
21    Const. of Covered CHB Lined Canal         Salcedo St.,            439,956.00        LGU       739 Builders
      Elevated Sidewalk                         Barangay I
22    Improvement of Module II (Wet             Vigan Comm’l.         2,027,522.64        LGU       739 Builders
      Section) @                                Center
23    Const. of Drainage Canal Phase IV
      including Septic Tank w/ Spillway @       San Julian Sur        1,994,822.45        LGU       739 Builders
      Discharge Point
24    Const. of Water System @ PNP              Rivero St.               12,000.00        LGU       Artemio Pacleb
      Station                                   Barangay IX,          (Labor Only)

25    Installation of Roof Ventilator @         Vigan Comm’l.            39,000.00        LGU       Alein Aldana
      Module I                                  Center               (Direct Labor)
26    Construction of Drainage Open Canal       Ilocos Sur Nat’l.        33,671.00        LGU       Hector Etalin
                                                High School           (Labor Only)
27    Improvement of Syquia Mansion             Quirino Blvd.            88,924.00        LGU       Bonifacio Pugal
Brgy. V             (Labor Only)
 28   Fabrication of Citizen’ Charter         Vigan City Hall          9,017.00     LGU       Rory Fenis
      Framing                                                    (Direct Labor)
 29   Conc. Topping @ Wet Section,            Vigan Public          146,388.00      LGU       E. Pajaro
      Module II                               Market,             (Labor Only)
 30   Painting of Flooring, Offal Sinks       Vigan Public          159,016.00      LGU       Bonifacio Pugal
      Wall, Per. Wall and all Stairs @ Wet    Market              (Labor Only)
      Section, Module II
 31   Improvement of Stage                    Bongtolan              31,954.00      LGU       Rudy Pajas
                                                                  (Labor Only)
 32   Bridge Approach Concreting              Paoa                  118,765.68      LGU       Batch 81 Const.
 33   Construction of CHB Lined Canal         Capangpangan          142,843.80      LGU       739 Builders
 34   Road Concreting                         Brgy. II               98,046.96      LGU       739 Builders
 35   Improvement of BJMP Building            Ayusan Sur            127,160.88      LGU       Batch 81 Const.
 36   Construction of Slope Protection        Pantay Daya            99,052.80      LGU       739 Builders
 37   Installation of Streetlights            Capangpangan           99,580.80      LGU       ELKAN Eng.
                                                                                              Services
 38   Concreting of Brgy. Road                Bulala                 99,185.58      LGU       MBB
                                                                                              Construction
 39   Const. of Reading Room                  Brgy. VIII            470,062.40      LGU       HEAF
      @ Mira Hills                                                                            Consultancy
 40   Construction of VCC Module IV           Alcantara St.       2,525,971.44      LGU       MBB Const.
      Phase VII
 41   Improvement of Health Center            Cabaroan Laud         118,108.53    LGU/BRGY.   HEAF
                                                                                              Consultancy
 42   Improvement of Two Storey               Purok A Bassit        136,842.14    LGU/BRGY.   HEAF
      Multi-Purpose Bldg                                                                      Consultancy
 43   Rehabilitation of Perimeter Fence       Paratong               99,409.20      LGU       Batch 81 Const.
 44   Installation of Streetlights            San Pedro              99,300.00      LGU       ELKAN Eng’g.
                                                                                              Services
 45   Const. of Two Storey Tanod Outpost      Pong-ol                99,184.80      LGU       Batch 81 Const.
 46   Construction of Canopy                  San Julian Sur        199,176.12    LGU/BRGY.   Batch 81 Const.
 47   Improvement of Day Care Center          Brgy. VIII            129,109.20    LGU/BRGY.   Batch 81 Const.
      and Const. of CHB Lined Canal
 48   Const. of Covered Court (MPB)           Cabaroan Daya       1,266,678.60    LGU/BRGY.   739 Builders
 49   Const. of Covered Court (MPB)           San Julian Norte      886,743.00      LGU       739 Builders
 50   Const. of Female Quarters, Toilet and   Vigan Fire             96,767.00      LGU       Rogelio Alejon
      Office Extension w/ Open Shelves        Station
 51   Installation of Streetlights            Ayusan Norte,          99,500.00      LGU       ELKAN Eng’g.
                                                                                              Services
 52   Construction of Seawall Phase VI        Mindoro               996,554.45      LGU       MBB Const.
 53   Completion of Multi-Purpose Bldg        Tamag                 348,047.00      CDF       739 Builders
 54   Construction of R.C. Canal              Tamag                 270,180.00      CDF       739 Builders
 55   Completion of Multi-Purpose Bldg        Brgy. VI              554,854.00      CDF       739 Builders
 56   Restoration of Post Office Bldg.        Brgy. I               559,574.40      LGU       Hector Etalin
 57   Construction of Multi-Purpose Bldg.     San Jose            1,892,060.94      CDF       739 Builders



Prepared by:                                                                Noted by:



(Sgd.) JUANITO B. BAÑAGA                                                    (Sgd.) VICTOR F. FIELDAD
        PDA I                                                                       CPDO

Project monitoring report (jan dec. 2010) vigan

  • 1.
    Republic of thePhilippines Province of Ilocos Sur City of Vigan CITY PLANNING AND DEVELOPMENT OFFICE APPROVED PROJECT MONITORING REPORT Date Covered: January 01 – December 31, 2010 No. Description of Project Contract Source of Name of Work Location Cost Fund Contractor (Php) 1 Road Concreting Pantay Laud 171,382.20 LGU 739 Builders 2 Concrete Topping @ Brgy. Plaza Purok A Bassit 171,837.60 LGU 739 Builders 3 Repainting of Stage, Basketball Plaza Burgos 95,968.00 LGU Bonifacio Pugal Court, Bleachers and Path walk 4 Road Concreting San Julian Sur – 497,964.72 LGU 739 Builders Cabaroan Laud 5 Concreting of Farm to Market Road Camangaan 998,055.67 LGU MBB Const. @ Sitio Nalasin 6 Fabrication and Installation of Boat Beddeng Laud 267,405.60 LGU 739 Builders Shed and Wooden Flooring @ Vigan River Cruise 7 Const. of Tanod Outpost and MP Pong-ol 474,018.39 LGU/BRGY. HEAF Consul. Bldg 8 Brgy. Raod Concreting Beddeng Laud 320,055.12 LGU/BRGY. 739 Builders 9 Concreting of Farm to Market Road Pons Road 98,981.34 LGU MBB Const. Nagsangalan 10 Fabrication & Installation of Mindoro 991,584.00 LGU 739 Builders Hexapods 11 Construction of Stone Masonry Wall San Julian Norte 822,465.65 LGU MBB Const. @ Vigan Shelterville 12 Landscaping of Senior Citizen Bldg. Ayusan Sur 248,477.10 LGU Francisco Flores & Installation of Perimeter Fence 13 Construction of CHB Lined Canal Capangpangan 235,903.80 LGU 739 Builders (Open) & Rehab. Of Culvert 14 Const. of Skills Training Inst. Bldg. VPM Annex 219,106.80 LGU 739 Builders 15 Const. & Install. Of Steel & Conc. Barangay II 99,000.00 LGU 739 Builders Cover 16 Const. of Waiting Shed/Tanod Raois 98,362.63 LGU MBB Const. Outpost 17 Rehab. Of Drainage Canal w/ Cover Barangay VIII 134,541.00 LGU 739 Builders 18 Const. of CHB Lined Canal w/ Cover Barangay IV 218,103.60 LGU 739 Builders 19 Construction of Perimeter Fence Barangay VII 246,644.00 LGU/BRGY. 739 Builders 20 Concreting of Farm to Market Road Nagsangalan – 478,887.40 LGU HEAF San Julian Sur Consultancy 21 Const. of Covered CHB Lined Canal Salcedo St., 439,956.00 LGU 739 Builders Elevated Sidewalk Barangay I 22 Improvement of Module II (Wet Vigan Comm’l. 2,027,522.64 LGU 739 Builders Section) @ Center 23 Const. of Drainage Canal Phase IV including Septic Tank w/ Spillway @ San Julian Sur 1,994,822.45 LGU 739 Builders Discharge Point 24 Const. of Water System @ PNP Rivero St. 12,000.00 LGU Artemio Pacleb Station Barangay IX, (Labor Only) 25 Installation of Roof Ventilator @ Vigan Comm’l. 39,000.00 LGU Alein Aldana Module I Center (Direct Labor) 26 Construction of Drainage Open Canal Ilocos Sur Nat’l. 33,671.00 LGU Hector Etalin High School (Labor Only) 27 Improvement of Syquia Mansion Quirino Blvd. 88,924.00 LGU Bonifacio Pugal
  • 2.
    Brgy. V (Labor Only) 28 Fabrication of Citizen’ Charter Vigan City Hall 9,017.00 LGU Rory Fenis Framing (Direct Labor) 29 Conc. Topping @ Wet Section, Vigan Public 146,388.00 LGU E. Pajaro Module II Market, (Labor Only) 30 Painting of Flooring, Offal Sinks Vigan Public 159,016.00 LGU Bonifacio Pugal Wall, Per. Wall and all Stairs @ Wet Market (Labor Only) Section, Module II 31 Improvement of Stage Bongtolan 31,954.00 LGU Rudy Pajas (Labor Only) 32 Bridge Approach Concreting Paoa 118,765.68 LGU Batch 81 Const. 33 Construction of CHB Lined Canal Capangpangan 142,843.80 LGU 739 Builders 34 Road Concreting Brgy. II 98,046.96 LGU 739 Builders 35 Improvement of BJMP Building Ayusan Sur 127,160.88 LGU Batch 81 Const. 36 Construction of Slope Protection Pantay Daya 99,052.80 LGU 739 Builders 37 Installation of Streetlights Capangpangan 99,580.80 LGU ELKAN Eng. Services 38 Concreting of Brgy. Road Bulala 99,185.58 LGU MBB Construction 39 Const. of Reading Room Brgy. VIII 470,062.40 LGU HEAF @ Mira Hills Consultancy 40 Construction of VCC Module IV Alcantara St. 2,525,971.44 LGU MBB Const. Phase VII 41 Improvement of Health Center Cabaroan Laud 118,108.53 LGU/BRGY. HEAF Consultancy 42 Improvement of Two Storey Purok A Bassit 136,842.14 LGU/BRGY. HEAF Multi-Purpose Bldg Consultancy 43 Rehabilitation of Perimeter Fence Paratong 99,409.20 LGU Batch 81 Const. 44 Installation of Streetlights San Pedro 99,300.00 LGU ELKAN Eng’g. Services 45 Const. of Two Storey Tanod Outpost Pong-ol 99,184.80 LGU Batch 81 Const. 46 Construction of Canopy San Julian Sur 199,176.12 LGU/BRGY. Batch 81 Const. 47 Improvement of Day Care Center Brgy. VIII 129,109.20 LGU/BRGY. Batch 81 Const. and Const. of CHB Lined Canal 48 Const. of Covered Court (MPB) Cabaroan Daya 1,266,678.60 LGU/BRGY. 739 Builders 49 Const. of Covered Court (MPB) San Julian Norte 886,743.00 LGU 739 Builders 50 Const. of Female Quarters, Toilet and Vigan Fire 96,767.00 LGU Rogelio Alejon Office Extension w/ Open Shelves Station 51 Installation of Streetlights Ayusan Norte, 99,500.00 LGU ELKAN Eng’g. Services 52 Construction of Seawall Phase VI Mindoro 996,554.45 LGU MBB Const. 53 Completion of Multi-Purpose Bldg Tamag 348,047.00 CDF 739 Builders 54 Construction of R.C. Canal Tamag 270,180.00 CDF 739 Builders 55 Completion of Multi-Purpose Bldg Brgy. VI 554,854.00 CDF 739 Builders 56 Restoration of Post Office Bldg. Brgy. I 559,574.40 LGU Hector Etalin 57 Construction of Multi-Purpose Bldg. San Jose 1,892,060.94 CDF 739 Builders Prepared by: Noted by: (Sgd.) JUANITO B. BAÑAGA (Sgd.) VICTOR F. FIELDAD PDA I CPDO