Group Innovation




                   12/01/12
Project modify




         Change Legs to Base




Before                         After
Table Information


No     Part         Detail          Mat.        Process         Req.   Cost/   Cost
      name                                                             Part    total
1     Upper       The gap for      Bamboo Cut,Scrub,drill,wax    1     24.75
      body         branches

2     Lower     The pivot point    Bamboo    Cut,scrub,wax       1      2.5
      body      of upper body
                                                                               52.75
3    Branches   Hanging shirts     Wood      Cut,scrub,wax       4     4.192


4     Base      Fix to the lower   Wood      Cut,scrub,wax       1     8.73
                      body
Develop your first prototype

- Record the number of hours spent in each
manufacturing process.

1. Cut
    - Upper Body      5 minutes
    - Lower Body      4 minutes
    - Branches        4 minutes
2. Drill
    - Upper Body      4 minutes
3. Scrub              10 minutes
4. Wax                30 minutes
Develop your first prototype


- Provide difficulties and problems
encountered during the prototype
development.
= -The body of bamboo is not straight.
   -The pivot point have friction.

- Provide the solutions for your second
prototype.
= -Fine the body of bamboo that straight.
   -Coating by Jarabi.
Thank you

Project First Prototype

  • 1.
  • 2.
    Project modify Change Legs to Base Before After
  • 3.
    Table Information No Part Detail Mat. Process Req. Cost/ Cost name Part total 1 Upper The gap for Bamboo Cut,Scrub,drill,wax 1 24.75 body branches 2 Lower The pivot point Bamboo Cut,scrub,wax 1 2.5 body of upper body 52.75 3 Branches Hanging shirts Wood Cut,scrub,wax 4 4.192 4 Base Fix to the lower Wood Cut,scrub,wax 1 8.73 body
  • 6.
    Develop your firstprototype - Record the number of hours spent in each manufacturing process. 1. Cut - Upper Body 5 minutes - Lower Body 4 minutes - Branches 4 minutes 2. Drill - Upper Body 4 minutes 3. Scrub 10 minutes 4. Wax 30 minutes
  • 7.
    Develop your firstprototype - Provide difficulties and problems encountered during the prototype development. = -The body of bamboo is not straight. -The pivot point have friction. - Provide the solutions for your second prototype. = -Fine the body of bamboo that straight. -Coating by Jarabi.