DANIELI
Erection & Commissioning
Pre- Conditions and
procedure of Embedded
plate fixing.
Report Nr. 001
DATE: 04/12/2014
Page 1 of 5
Project Name: xxxxxxx Location: INDIA
From:- Rashmi Ranjan
Swain
Description: BM
Distribution to:-
Customer: JSW Job. Number: WP0G501
Pre-Condition Before Alignment
1. Arrange Steel Plugs for Axis Mark & Level Mark as per designs shown below in Picture 01 & 02.-
Not Done.
2. All vertical and horizontal stands bench mark to be fixed and certified by customer on steel plug.
Pass line and stand axis’s on below “Picture 01” type steel plug. Level/Elevation on below “Picture
02” type steel plug.- Not Done.
Picture 01 Picture 02
For axis mark. For level mark
3. Networking of bench mark to be done as per below picture in mill area.(Layout drawing to be
followed for the distance between stands).- Not Done
4. Machined plate’s deviation to be checked. Follow procedure as shown in pictures 1, 2 & 3. If no
deviations observed then proceed with the erection-alignment of plate.- Not Done.
5. As shown in the drawing sample below, top of the horizontal supporting plate has an indication of
+4590 mm above a symbol that stands for “Elevation for machinery resting”, means the plate to
be levelled at this level.
Drawing Reference:- DP0KZl-JD21-C0300-CD010(Rev. 00)
DANIELI
Erection & Commissioning
Pre- Conditions and
procedure of Embedded
plate fixing.
Report Nr. 001
DATE: 04/12/2014
Page 2 of 5
Note: - Holes displacement on the base plate is also important but minor displacement is acceptable. It is to be noted
that there is lot of available space between the anchor bolts and the holes: bolt size is M48 while holes on the base plate
are 100 mm and holes on the shimming plates is 80 mm as seen here below.
6. Manufacturing error allowed are specified in the embedded steel plate manufacturing drawing as
seen here below: Danieli standard 2.4.103 corresponding to a maximum error of +/- 2 mm in total
for all holes displacement while for the plate is +/- 0.5 mm in respect of the 260 mm distance
from the closest anchor bolt hole.
Note: - The purpose of bottom horizontal plate is, to be used as a stopper & jacking device for the base plate as seen here below.
DANIELI
Erection & Commissioning
Pre- Conditions and
procedure of Embedded
plate fixing.
Report Nr. 001
DATE: 04/12/2014
Page 3 of 5
Bigger tolerances on displacement of this plate can be accepted keeping tight the holes alignment referred to the described
installation targets. If this plate would be lower or higher a possible solution would be to replace the bolt used as jacking
screw/stopper or to reweld it in the right place.
7. After alignment of embedded plate through certified Pass line & certified Stand Axis, lock it
properly from front mounted temporary support. Locking should be strong enough to withstand
casting pressure. Prepare Alignment Protocols for Pre- Casting Survey readings.
8. Now lock this embedded plate properly from both sides as well to avoid any lateral movement
during concrete casting. (Refer Picture 07).
9. After Concrete casting is done, curing is done. Final Post-casting survey is to be done to check if
there is no deflection from Pass Line & Stand Axis.
Pictorial Representation
DANIELI
Erection & Commissioning
Pre- Conditions and
procedure of Embedded
plate fixing.
Report Nr. 001
DATE: 04/12/2014
Page 4 of 5
Photo:-1:-Embedded plate to be checked before
erection in two plane
Photo:-2:-Allowed deviation from one machined
to other is +/- 0.50mm.
Photo:-3:- Inspection of Embedded plate.
Photo:-4:- Temporary structure to support
embedded plate
Photo:-5:- Screw arrangement required between
vertical fixed member to the embedded plate for
adjustment.
Photo:-6:- Pre casting and post casting survey to
be done.
DANIELI
Erection & Commissioning
Pre- Conditions and
procedure of Embedded
plate fixing.
Report Nr. 001
DATE: 04/12/2014
Page 5 of 5
Photo:-7:-Vertical member required to hold align plate
and strong enough to hold the casting pressure.
DANIELI
Erection & Commissioning
Pre- Conditions and
procedure of Embedded
plate fixing.
Report Nr. 001
DATE: 04/12/2014
Page 5 of 5
Photo:-7:-Vertical member required to hold align plate
and strong enough to hold the casting pressure.

More Related Content

Similar to Pre -conditions for fixing Embedded plate at DOLVI

Technical Instructions (FSAE)
Technical Instructions (FSAE)Technical Instructions (FSAE)
Technical Instructions (FSAE)Michael Walker
 
I0314064071
I0314064071I0314064071
I0314064071theijes
 
Various approaches to Eliminate MIG Welding and Defects occurring in DT cap F...
Various approaches to Eliminate MIG Welding and Defects occurring in DT cap F...Various approaches to Eliminate MIG Welding and Defects occurring in DT cap F...
Various approaches to Eliminate MIG Welding and Defects occurring in DT cap F...IRJET Journal
 
Quad-Lock Insulated Concrete Forms Installation Guide
Quad-Lock Insulated Concrete Forms Installation GuideQuad-Lock Insulated Concrete Forms Installation Guide
Quad-Lock Insulated Concrete Forms Installation GuideWestern-Building-Center
 
Section 4 tower-volume-ii_6
Section 4 tower-volume-ii_6Section 4 tower-volume-ii_6
Section 4 tower-volume-ii_6BUDDHADEV KORA
 
IRJET- Design and Development of Jig and Fixture for Tacho Bracket
IRJET- Design and Development of Jig and Fixture for Tacho BracketIRJET- Design and Development of Jig and Fixture for Tacho Bracket
IRJET- Design and Development of Jig and Fixture for Tacho BracketIRJET Journal
 
Enhancing productivity by elimination of hole offset rejection of an obj socke
Enhancing productivity by elimination of hole offset rejection of an obj sockeEnhancing productivity by elimination of hole offset rejection of an obj socke
Enhancing productivity by elimination of hole offset rejection of an obj sockeIAEME Publication
 
G901 05 2013a
G901 05 2013aG901 05 2013a
G901 05 2013aRAYL_2014
 
Construction using Precast technology
Construction using Precast technologyConstruction using Precast technology
Construction using Precast technologyShubham Arora
 
MFRH Erection & Commissioning Method.pdf
MFRH Erection & Commissioning Method.pdfMFRH Erection & Commissioning Method.pdf
MFRH Erection & Commissioning Method.pdfssuseref23d3
 
Toyota 02 5 fg40 forklift service repair manual
Toyota 02 5 fg40 forklift service repair manualToyota 02 5 fg40 forklift service repair manual
Toyota 02 5 fg40 forklift service repair manualfjsjjekdkme
 

Similar to Pre -conditions for fixing Embedded plate at DOLVI (13)

Technical Instructions (FSAE)
Technical Instructions (FSAE)Technical Instructions (FSAE)
Technical Instructions (FSAE)
 
Instalacion acople
Instalacion acopleInstalacion acople
Instalacion acople
 
I0314064071
I0314064071I0314064071
I0314064071
 
Various approaches to Eliminate MIG Welding and Defects occurring in DT cap F...
Various approaches to Eliminate MIG Welding and Defects occurring in DT cap F...Various approaches to Eliminate MIG Welding and Defects occurring in DT cap F...
Various approaches to Eliminate MIG Welding and Defects occurring in DT cap F...
 
Quad-Lock Insulated Concrete Forms Installation Guide
Quad-Lock Insulated Concrete Forms Installation GuideQuad-Lock Insulated Concrete Forms Installation Guide
Quad-Lock Insulated Concrete Forms Installation Guide
 
Section 4 tower-volume-ii_6
Section 4 tower-volume-ii_6Section 4 tower-volume-ii_6
Section 4 tower-volume-ii_6
 
IRJET- Design and Development of Jig and Fixture for Tacho Bracket
IRJET- Design and Development of Jig and Fixture for Tacho BracketIRJET- Design and Development of Jig and Fixture for Tacho Bracket
IRJET- Design and Development of Jig and Fixture for Tacho Bracket
 
99119 coach failure report
99119 coach failure report99119 coach failure report
99119 coach failure report
 
Enhancing productivity by elimination of hole offset rejection of an obj socke
Enhancing productivity by elimination of hole offset rejection of an obj sockeEnhancing productivity by elimination of hole offset rejection of an obj socke
Enhancing productivity by elimination of hole offset rejection of an obj socke
 
G901 05 2013a
G901 05 2013aG901 05 2013a
G901 05 2013a
 
Construction using Precast technology
Construction using Precast technologyConstruction using Precast technology
Construction using Precast technology
 
MFRH Erection & Commissioning Method.pdf
MFRH Erection & Commissioning Method.pdfMFRH Erection & Commissioning Method.pdf
MFRH Erection & Commissioning Method.pdf
 
Toyota 02 5 fg40 forklift service repair manual
Toyota 02 5 fg40 forklift service repair manualToyota 02 5 fg40 forklift service repair manual
Toyota 02 5 fg40 forklift service repair manual
 

Pre -conditions for fixing Embedded plate at DOLVI

  • 1. DANIELI Erection & Commissioning Pre- Conditions and procedure of Embedded plate fixing. Report Nr. 001 DATE: 04/12/2014 Page 1 of 5 Project Name: xxxxxxx Location: INDIA From:- Rashmi Ranjan Swain Description: BM Distribution to:- Customer: JSW Job. Number: WP0G501 Pre-Condition Before Alignment 1. Arrange Steel Plugs for Axis Mark & Level Mark as per designs shown below in Picture 01 & 02.- Not Done. 2. All vertical and horizontal stands bench mark to be fixed and certified by customer on steel plug. Pass line and stand axis’s on below “Picture 01” type steel plug. Level/Elevation on below “Picture 02” type steel plug.- Not Done. Picture 01 Picture 02 For axis mark. For level mark 3. Networking of bench mark to be done as per below picture in mill area.(Layout drawing to be followed for the distance between stands).- Not Done 4. Machined plate’s deviation to be checked. Follow procedure as shown in pictures 1, 2 & 3. If no deviations observed then proceed with the erection-alignment of plate.- Not Done. 5. As shown in the drawing sample below, top of the horizontal supporting plate has an indication of +4590 mm above a symbol that stands for “Elevation for machinery resting”, means the plate to be levelled at this level. Drawing Reference:- DP0KZl-JD21-C0300-CD010(Rev. 00)
  • 2. DANIELI Erection & Commissioning Pre- Conditions and procedure of Embedded plate fixing. Report Nr. 001 DATE: 04/12/2014 Page 2 of 5 Note: - Holes displacement on the base plate is also important but minor displacement is acceptable. It is to be noted that there is lot of available space between the anchor bolts and the holes: bolt size is M48 while holes on the base plate are 100 mm and holes on the shimming plates is 80 mm as seen here below. 6. Manufacturing error allowed are specified in the embedded steel plate manufacturing drawing as seen here below: Danieli standard 2.4.103 corresponding to a maximum error of +/- 2 mm in total for all holes displacement while for the plate is +/- 0.5 mm in respect of the 260 mm distance from the closest anchor bolt hole. Note: - The purpose of bottom horizontal plate is, to be used as a stopper & jacking device for the base plate as seen here below.
  • 3. DANIELI Erection & Commissioning Pre- Conditions and procedure of Embedded plate fixing. Report Nr. 001 DATE: 04/12/2014 Page 3 of 5 Bigger tolerances on displacement of this plate can be accepted keeping tight the holes alignment referred to the described installation targets. If this plate would be lower or higher a possible solution would be to replace the bolt used as jacking screw/stopper or to reweld it in the right place. 7. After alignment of embedded plate through certified Pass line & certified Stand Axis, lock it properly from front mounted temporary support. Locking should be strong enough to withstand casting pressure. Prepare Alignment Protocols for Pre- Casting Survey readings. 8. Now lock this embedded plate properly from both sides as well to avoid any lateral movement during concrete casting. (Refer Picture 07). 9. After Concrete casting is done, curing is done. Final Post-casting survey is to be done to check if there is no deflection from Pass Line & Stand Axis. Pictorial Representation
  • 4. DANIELI Erection & Commissioning Pre- Conditions and procedure of Embedded plate fixing. Report Nr. 001 DATE: 04/12/2014 Page 4 of 5 Photo:-1:-Embedded plate to be checked before erection in two plane Photo:-2:-Allowed deviation from one machined to other is +/- 0.50mm. Photo:-3:- Inspection of Embedded plate. Photo:-4:- Temporary structure to support embedded plate Photo:-5:- Screw arrangement required between vertical fixed member to the embedded plate for adjustment. Photo:-6:- Pre casting and post casting survey to be done.
  • 5. DANIELI Erection & Commissioning Pre- Conditions and procedure of Embedded plate fixing. Report Nr. 001 DATE: 04/12/2014 Page 5 of 5 Photo:-7:-Vertical member required to hold align plate and strong enough to hold the casting pressure.
  • 6. DANIELI Erection & Commissioning Pre- Conditions and procedure of Embedded plate fixing. Report Nr. 001 DATE: 04/12/2014 Page 5 of 5 Photo:-7:-Vertical member required to hold align plate and strong enough to hold the casting pressure.