PMI® Project Management
Professional (PMP)® Workshop
PMI, PMP, PMBOK & PMI Talent Triangle are registered marksof
Project Management Institute, Inc.
About Project Management
Professional (PMP)®
2 © 2018 ExcelR Solutions. All RightsReserved
Why PMP®?
 To become a better project manager as the best
practices have been included procured from myriad
project managers across the globe.
 Increases the success rate of your project as you
become more organized.
 Minimizing resource utilization and making a
project cost effective .
 Changes how others look your abilities.
 To keep your job, promoted or get a job.
 Hike in your current salary (Help you to get ahead)
3 © 2018 ExcelR Solutions. All RightsReserved
Exam Eligibility Requirement
Category Eligibility of
Education
Formal
PMP®
training
hours
Hours
leading and
directing
project
One BachelorsDegree or global
equivalent
35Contact
Hours
4,500 hours
Two High school diploma,
associatedegreeor global
equivalent
35Contact
Hours
7,500 hours
 After paying the examination fee online, PMI® will send an authorizationletter
 Exam must be taken within one year of receiving the authorizationletter
 PMI may randomly choose to send your application for auditing
 You need to contact a prometric center to schedule a date for the exam
4 © 2018 ExcelR Solutions. All RightsReserved
Examination Pattern
Total 4 Hours duration
Out of 200, 25 are considered as pre-test questions (zero
marks) and only 175 are scored for the exam result
Grading system is followed to arrive at the result Pass or Fail.
Result is based on the individual grades on each processgroup.
Grades are
 Below proficient
 Proficient
 Moderately Proficient
 There is no negative marking.
5 © 2018 ExcelR Solutions. All RightsReserved
Distribution of Q’s across Process Groups
Process Group Percentage of Questions
Initiating 13
Planning 24
Executing 31
Monitoring & Controlling 25
Closing 7
Note: This % of distribution might vary as required by PMI®.
6 © 2018 ExcelR Solutions. All RightsReserved
Introduction to Project Management
7 © 2018 ExcelR Solutions. All RightsReserved
What is a Project?
 What is a Project?
 A project is a temporary endeavour undertaken to create a unique
product, service or result
 Projects drive change, enable business value creation and have an
initiation context
 A project can create:
A product that can be either a component of another item or an end
item in itself,
A capability to perform a serviceor,
A result such as an outcome or document.
8
© 2018 ExcelR Solutions. All Rights Reserved
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide)
- Sixth Edition, Project Management Institute, Inc., 2017, Page 4-6
Programs & Portfolio
Project Management exists in a broader context governedby:
 Program Management
 Portfolio Management
 Organizational project management (OPM) and strategies
Program Management:
It is a group of related projects managed in a coordinated way to obtain
benefits and control not available from managing them individually. It focuses
on project interdependencies and optimal approach for managingthem.
Programs and projects deliver results
For example,
New aircraft manufacturing program has multiple related projects. Project A –
manufacture cockpit; Project B – manufacture fuselage; Project C –
manufacture turbine engine etc.
9
© 2018 ExcelR Solutions. All Rights Reserved
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide)
- Sixth Edition, Project Management Institute, Inc., 2017, Page 14
Programs & Portfolio
 Portfolio Management:
It refers to a collection of projects or programs (may not be necessarily
related or interdependent) and other work that are grouped together to
facilitate effective management of that work to meet strategic business
objectives.
Portfolios make value decisions
For example,
Aircraft manufacturer may have business lines such as domestic aircraft
manufacturing, international aircraft manufacturing, warfare aircraft
manufacturing etc.
 Note: Organizational Project Management (OPM) - Integrates project,
program and portfolio management with organizational enablers to achieve
strategic objectives. In other words, do the right projects and allocate of
resources for them
10
© 2018 ExcelR Solutions. All Rights Reserved
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide)
- Sixth Edition, Project Management Institute, Inc., 2017, Page 15 -16
What is Project Management?
 It is the application of knowledge, skills, tools and techniques to project
activities,
 Using the 49 processes and 5 process groups i.e. Initiating, Planning,
Executing, Monitoring & Controlling and Closing with appropriate
application and integration, project management can be accomplished.
11 © 2018 ExcelR Solutions. All RightsReserved
Project Constraints
Scope
Quality
Schedule
Budget
Resources
Risk
12 © 2018 ExcelR Solutions. All RightsReserved
Project Vs Operations
 Operations are an organizational function performing the ongoing execution
of activities that produce the same product or provide a repetitiveservice
Value is realized in operations
Examples: Manufacturing, Production operations etc…
 Though temporary in nature Projects can help achieve the organization goals
when they are aligned with the organization’s strategy.
13 © 2018 ExcelR Solutions. All RightsReserved
Project Life Cycle
Project life cycle - A collection of sequentially (typical – and sometimes
overlapping) project phases determined by management and needs of the
organization
Phase – A number of relatedactivities
resulting in deliverable(s)
Types of project life cycle:
 Predictive
 Adaptive (Agile)
Characteristics of the project life cycle:
 Starting the project
 Organizing and preparing
 Carrying out project work
 Closing the project
14 © 2018 ExcelR Solutions. All Rights Reserved
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) -
Sixth Edition, Project Management Institute, Inc., 2017, Page 18,19 & Fig 1-2 Page 548
Development Life Cycle & Phase Gate
15 © 2018 ExcelR Solutions. All Rights Reserved
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) -
Sixth Edition, Project Management Institute, Inc., 2017, Page 19,21
Development life cycles – Those phases of the project lifecycle where product
development happens
Types of development life cycle
 Predictive (waterfall)
 Iterative
 Incremental
 Adaptive (Agile)
 Hybrid (mix of predictive and adaptive)
Phase gate – Aphase-end review with a decision to
 Continue to next phase as is or with modification
 Remain in the same phase or repeat some of the phase work
 End the project
www.excelr.com
enquiry@excelr.com
Toll FREE : 1800-212-2120 (India)
0044-203-514-6638 (UK)
006-128-520-3240 (Australia)
001-844-392-3571 (USA)
+2348181496946 (Nigeria)
THANK YOU
CONTACT US

Pmp pmbok6 -2018

  • 1.
    PMI® Project Management Professional(PMP)® Workshop PMI, PMP, PMBOK & PMI Talent Triangle are registered marksof Project Management Institute, Inc.
  • 2.
    About Project Management Professional(PMP)® 2 © 2018 ExcelR Solutions. All RightsReserved
  • 3.
    Why PMP®?  Tobecome a better project manager as the best practices have been included procured from myriad project managers across the globe.  Increases the success rate of your project as you become more organized.  Minimizing resource utilization and making a project cost effective .  Changes how others look your abilities.  To keep your job, promoted or get a job.  Hike in your current salary (Help you to get ahead) 3 © 2018 ExcelR Solutions. All RightsReserved
  • 4.
    Exam Eligibility Requirement CategoryEligibility of Education Formal PMP® training hours Hours leading and directing project One BachelorsDegree or global equivalent 35Contact Hours 4,500 hours Two High school diploma, associatedegreeor global equivalent 35Contact Hours 7,500 hours  After paying the examination fee online, PMI® will send an authorizationletter  Exam must be taken within one year of receiving the authorizationletter  PMI may randomly choose to send your application for auditing  You need to contact a prometric center to schedule a date for the exam 4 © 2018 ExcelR Solutions. All RightsReserved
  • 5.
    Examination Pattern Total 4Hours duration Out of 200, 25 are considered as pre-test questions (zero marks) and only 175 are scored for the exam result Grading system is followed to arrive at the result Pass or Fail. Result is based on the individual grades on each processgroup. Grades are  Below proficient  Proficient  Moderately Proficient  There is no negative marking. 5 © 2018 ExcelR Solutions. All RightsReserved
  • 6.
    Distribution of Q’sacross Process Groups Process Group Percentage of Questions Initiating 13 Planning 24 Executing 31 Monitoring & Controlling 25 Closing 7 Note: This % of distribution might vary as required by PMI®. 6 © 2018 ExcelR Solutions. All RightsReserved
  • 7.
    Introduction to ProjectManagement 7 © 2018 ExcelR Solutions. All RightsReserved
  • 8.
    What is aProject?  What is a Project?  A project is a temporary endeavour undertaken to create a unique product, service or result  Projects drive change, enable business value creation and have an initiation context  A project can create: A product that can be either a component of another item or an end item in itself, A capability to perform a serviceor, A result such as an outcome or document. 8 © 2018 ExcelR Solutions. All Rights Reserved Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) - Sixth Edition, Project Management Institute, Inc., 2017, Page 4-6
  • 9.
    Programs & Portfolio ProjectManagement exists in a broader context governedby:  Program Management  Portfolio Management  Organizational project management (OPM) and strategies Program Management: It is a group of related projects managed in a coordinated way to obtain benefits and control not available from managing them individually. It focuses on project interdependencies and optimal approach for managingthem. Programs and projects deliver results For example, New aircraft manufacturing program has multiple related projects. Project A – manufacture cockpit; Project B – manufacture fuselage; Project C – manufacture turbine engine etc. 9 © 2018 ExcelR Solutions. All Rights Reserved Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) - Sixth Edition, Project Management Institute, Inc., 2017, Page 14
  • 10.
    Programs & Portfolio Portfolio Management: It refers to a collection of projects or programs (may not be necessarily related or interdependent) and other work that are grouped together to facilitate effective management of that work to meet strategic business objectives. Portfolios make value decisions For example, Aircraft manufacturer may have business lines such as domestic aircraft manufacturing, international aircraft manufacturing, warfare aircraft manufacturing etc.  Note: Organizational Project Management (OPM) - Integrates project, program and portfolio management with organizational enablers to achieve strategic objectives. In other words, do the right projects and allocate of resources for them 10 © 2018 ExcelR Solutions. All Rights Reserved Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) - Sixth Edition, Project Management Institute, Inc., 2017, Page 15 -16
  • 11.
    What is ProjectManagement?  It is the application of knowledge, skills, tools and techniques to project activities,  Using the 49 processes and 5 process groups i.e. Initiating, Planning, Executing, Monitoring & Controlling and Closing with appropriate application and integration, project management can be accomplished. 11 © 2018 ExcelR Solutions. All RightsReserved
  • 12.
  • 13.
    Project Vs Operations Operations are an organizational function performing the ongoing execution of activities that produce the same product or provide a repetitiveservice Value is realized in operations Examples: Manufacturing, Production operations etc…  Though temporary in nature Projects can help achieve the organization goals when they are aligned with the organization’s strategy. 13 © 2018 ExcelR Solutions. All RightsReserved
  • 14.
    Project Life Cycle Projectlife cycle - A collection of sequentially (typical – and sometimes overlapping) project phases determined by management and needs of the organization Phase – A number of relatedactivities resulting in deliverable(s) Types of project life cycle:  Predictive  Adaptive (Agile) Characteristics of the project life cycle:  Starting the project  Organizing and preparing  Carrying out project work  Closing the project 14 © 2018 ExcelR Solutions. All Rights Reserved Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) - Sixth Edition, Project Management Institute, Inc., 2017, Page 18,19 & Fig 1-2 Page 548
  • 15.
    Development Life Cycle& Phase Gate 15 © 2018 ExcelR Solutions. All Rights Reserved Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) - Sixth Edition, Project Management Institute, Inc., 2017, Page 19,21 Development life cycles – Those phases of the project lifecycle where product development happens Types of development life cycle  Predictive (waterfall)  Iterative  Incremental  Adaptive (Agile)  Hybrid (mix of predictive and adaptive) Phase gate – Aphase-end review with a decision to  Continue to next phase as is or with modification  Remain in the same phase or repeat some of the phase work  End the project
  • 16.
    www.excelr.com enquiry@excelr.com Toll FREE :1800-212-2120 (India) 0044-203-514-6638 (UK) 006-128-520-3240 (Australia) 001-844-392-3571 (USA) +2348181496946 (Nigeria) THANK YOU CONTACT US