SlideShare a Scribd company logo
Building the Next
Major Iron Ore Mine
in the Labrador Trough
Corporate Presentation
November 2013

Oct 19th,2013

19 November 2013

| championironmines.com

FSE: P02

CPMNF
FORWARD-LOOKING STATEMENTS
Certain information contained herein regarding Champion Iron Mines Ltd., including
management’s assessment of future plans & operations, may constitute forward-looking
statements under applicable securities law & necessarily involve risks, including but not limited
to risks associated with mining exploration, operating costs, production costs, volatility of share
prices, currency fluctuations, imprecision of resource & reserve estimates, environmental risks
& ability to access sufficient capital from internal & external sources.
As a consequence, actual results may differ materially from those anticipated in any forward
looking statements. Plans, intentions or expectations disclosed in any forward-looking
statements or information should not be read as guarantees of future results or events, & will
not necessarily be accurate indications of whether or when or by which such results or events
will be achieved.
Except as required by law, Champion Iron Mines Ltd., expressly disclaims any intention &
undertakes no obligation to update any forward looking statements or information as conditions
change.
The historical mineral resources mentioned are strictly historical in nature & are non-compliant
to National Instrument 43-101 mineral resources & mineral reserves standards, & should
therefore not be relied upon. A qualified person has not done sufficient work to upgrade or
classify the historical mineral resources as current National Instrument NI-43-101 compliant.

2
About Champion Iron Mines
Advanced iron ore exploration & development projects located in
Canada’s principal iron ore district, the Labrador Trough
Fermont Holdings (755 km2)
 121 projects in the Fermont Iron Ore District
 Flagship Consolidated Fire Lake North (“CFLN”) Project
Prefeasibility Study (“PFS”) announced Feb. 7, 2013
 5.1 billion tonnes of NI 43-101 compliant Mineral Resource
Estimates of iron ore



910 million tonnes of Measured + Indicated Resources
4,185 million tonnes of Inferred Mineral Resources

 100% direct interest; option to buy back 0.5% of the NSR
for C$1.5 million, resulting in a 2.5% NSR overall)

Attikamagen Project (310 km2)
 1.7 billion tonnes @ 31.3% FeT & a plan for a 2 Mtpa2 DSO project
 Champion retains a 2% NSR in the Attikamagen Project that is owned through
a joint venture between Century Iron Mines and Wuhan3
1. Champion signed a definitive option agreement with Cartier Iron to earn a 65% interest in 7 of its projects (Cluster 3)
2. As reported by Champion Iron’s JV Partner on Mar. 25, 2013 press release
3. As reported in Champion Iron’s October 3, 2013 press release

3
Québec’s Next
Major Iron Ore Mine
CFLN Prefeasibility Study




Feb. 7, 2013 PFS indicated an average production
rate of 9.3 Mtpa of iron concentrate for the 20 year
mine life
 First 5 year average: 9.8 Mtpa
Net Present Value of $3.3B at a discounted cash flow
rate of 8% with an Internal Rate of Return of 30.9% &
a payback period of 3.4 years

Established Fermont Iron Ore District


Canada produces 47 Mtpa of iron ore concentrate & this
is expected to increase to a total of 200 Mtpa over the
next 10 years if all proposed development projects are
realized



Established rail, power & port infrastructure
- Competitive power rates are available
- Port of Sept-Îles is building a world-class 50 Mtpa
multi-user wharf project for the iron ore industry
which is on schedule & on budget
4
Capital Structure
Share Data & Cash Position as of September 30, 2013.
Total Shares – Outstanding
Warrants

Options

137.4
Issued
7,000,000 at $3.00 (expire May 17, 2015) - Fancamp
15,000,000 at $0.25 (expire July 17, 2015) – Baotou

Outstanding
7,000,000
15,000,000
22,000,000

8.34 M @ C$1.00 (avg. exercise price)

Total Shares – Fully Diluted

168.0 M

Outstanding Share Market
Capitalization
(based on $0.25 share price)

C$34M

Cash & Receivables

C$15M

Management / Insiders Ownership

~ 26.7%

Analyst Coverage

5
Board of Directors
Over 200 years of combined exploration & mine operations experience
B OARD

OF

D IRECTORS

Tom Larsen*
Donald A. Sheldon, LLB., P.Eng.*
Alexander Horvath, P.Eng.*
William Harding
Francis Sauvé
Harry Burgess, P.Eng.
Paul Ankcorn
James Wang

PRESIDENT
DIRECTOR
DIRECTOR
DIRECTOR
DIRECTOR
DIRECTOR
DIRECTOR
DIRECTOR

M AN AGEM E NT T EAM
Tom Larsen
Miles Nagamatsu
Alexander Horvath, P.Eng.
Martin Bourgoin, P.Geo.
Beat Frei
Jeff Hussey, P.Geo.
Jean-Luc Chouinard, P.Eng., M.Sc.
Bruce Mitton, P.Geo.
Jorge Estepa
Katrina Chua

PRESIDENT & CEO
CHIEF FINANCIAL OFFICER
EXECUTIVE VICE PRESIDENT, EXPLORATION & PROJECT DEVELOPMENT
EXECUTIVE VICE PRESIDENT, OPERATIONS
SENIOR VICE PRESIDENT, PROJECT FINANCE
SENIOR VICE PRESIDENT, CORPORATE DEVELOPMENT
VICE PRESIDENT, PROJECT DEVELOPMENT
VICE PRESIDENT, EXPLORATION
VICE PRESIDENT, SECRETARY & TREASURER
DIRECTOR OF INVESTOR RELATIONS

CORPORATE ADVISORS

Doug Bache; Jérome Cliche

6
Why invest in Champion Iron Mines?
Favourable Operating
Environment
 October 7th 2013, Government
announce a pre-feasibity study for a
new multi-users rail – accessible to
all
 The forecast for Iron ore prices over
the mid to long term remain positive
 Favourable tax environment
(40% tax rebate on exploration
expenditures)

Champion Iron Mines
Competitive Advantage
 Fermont Holdings: 12 iron ore brownfield
projects (755 km2)
 CFLN Prefeasibility Study of coarse
grained specular hematite surficial
deposits
 Easier to liberate
 Deleterious elements in
concentrate are well below
industry specifications limits

 Access to low-cost power & close to
rail & port infrastructure

 Team with experience in mine start-ups
including construction and commissioning

 Québec is a very stable jurisdiction to
develop & operate mines

 Upside potential for short, mid, & long term
growth is high with 5.1 billion tonnes of
iron ore resources

 Skilled labor work force in Québec
 Environmental: Iron ore beneficiation
includes crushing & grinding to
liberate the iron; followed by gravity
& magnetic separation of iron ore
from gangue minerals rather than the
use of reagents

 Several de-risking initiatives underway
including a multi-user rail solution,
Environmental & Social Impact Study that
is near completion & permit applications
underway
 Closest t project development to the St.
Lawrence Seaway & electrical power
infrastructure

7
Global Mineral Resources
NI 43-101 Compliant Mineral Resource Estimates
Consolidated Fire Lake North Mineral Resource Estimates @ 15% FeT cut-off

Deposit
FLN - West*
FLN - East*
FLN - Don Lake
Bellechasse
Oil Can - Oxide
Oil Can - Mixed
Total
*Total Resource under Prefeasibility Study
Total Resource Tonnes (millions)

Measured
tonnes
(millions)
24
3
0

Grade
FeT%
35.4
34.2
21.4

Indicated
tonnes
(millions)
405
262
52

Grade
FeT%
32.6
29.6
26.5

-

-

-

-

27
1,215

35.0

719

31.0

Inferred
tonnes
(millions)
329
192
188
215
972
924
2,821

Grade
FeT%
30.9
28.7
25.3
28.7
33.2
24.1
28.8

3,567

Other Fermont Holdings Mineral Resource Estimates @ 15% FeT cut-off
Harvey-Tuttle
Moire Lake
Other Fermont Projects Total Resources Tonnes
(millions)
Total Fermont Holdings Mineral Resources Tonnes
(millions)

164
27

35.0

30.5

947
417

883

30.9

4,185

23.2
29.4
27.6

5,095

3.567 billion tonnes, out of the 5.1 billion tonnes of global resources, are within the confines of the
CFLN Project; the resource base has the potential to produce up to 35-40 Mtpa of iron concentrate;
that could support an independent rail solution, if necessary. Oil Can has the potential for 16-20 Mtpa.
8
Existing Rail Infrastructure
REGIONAL LOCATION MAP &
INFRASTRUCTURE

Québec North Shore & Labrador Railway
(“QNS&L”):


CFLN PEA Base Case connection to Bloom
Lake railway required 62 km of rail + 32 km of
loops and sidings including 14 km for the CFA1
railway for a total of 94 km of rail



New option under study: multi-user railway



QNS&L links to Sept-Îles & Pointe Noire



Bloom Lake & QNS&L railways are considered
common carriers



Common carriers allocate capacity on a firstcome, first-serve basis

Cartier Railway:



Privately owned by ArcelorMittal


Chemin de Fer Arnaud

Transports ore from ArcelorMittal’s Fire Lake
Mine northward to Mt. Wright concentrator



1

Links Mont Wright to Port-Cartier (Max 30Mtpa)

Within CFLN Project boundary
9
World Class Port of Sept-Îles Infrastructure
Expanding to Meet Demand
Pointe Noire Multi-Users Wharf
 Completion Mar. 31, 2014; 18 months prior
to “CFLN" startup
 Federal Government announced $55M
funding or 25% of project
 Phase 1: 50 Mtpa for $220M
 Phase 2: Planning for 100 Mtpa
Port of Sept-Iles
Pointe Noire

Port of Sept-Îles
Port of Sept-Iles

 RTZ-IOC shipping facility

Port-Cartier

Pointe Noire

 ArcelorMittal shipping facility
 $2.1B expansion is underway & will include
concentrator expansion with port & rail
infrastructure upgrades

China Max ship capacity 300kt

 Located 62 km west of Sept-Îles

Courtesy of the Port de Sept Îles

10
11
Site Layout of Consolidated Fire Lake North Project

12
Consolidated Fire Lake North Project
Prefeasibility Study – February 2013
Key Results

Pre-Tax Basis

Internal Rate of Return (IRR) (8% Discount Rate) 1

30.9%

Undiscounted Cash Flow

$9.0B

Net Present Value @ 5% Discounted Cash Flow

$4.7B

Net Present Value @ 8% Discounted Cash Flow

$3.3B

Net Present Value @ 10% Discounted Cash Flow

$2.6B

Payback Period (8% Discount Rate)

3.4 Years

Pre-production Capital Expenditures:
Direct Operating Costs2

US$1,394.4M (Fire Lake North & Pointe Noire)
US$34.58 per tonne (average 20 years);
US$27.99 per tonne (average years 1 to 5)

Iron Ore Spot Price Assumptions3

US$115 per tonne of concentrate at 62% Fe (years 1 -5)
US$110 per tonne of concentrate at 62% Fe (years 6-20)

Mine-Life

19.6 years

Exchange Rate

$1.00 USD to $1.00 CDN

Overall Stripping Ratio

2.74:1 for the current 20 year mine-life
1.56:1 (years 1-3 of production); 2.02:1 (years 1-5 of operation)

Mineral Resource Estimate (MRE)
East & West Pits

Measured & Indicated Resources 693.5 Mt grading 31.5% FeT (NI43-101)
Inferred Resources 521.6 Mt grading 30.1% FeT @ 15% FeT cut-off (NI43-101)

Proven & Probable Reserves
464.6 million tonnes grading 32.4% Fe at a 15% cut-off grade;
1. This includes railway capital repayment and interest
2. Direct operating costs excludes railway capital repayment & interest
3. Iron ore spot price assumption does not take into account that Champion will be producing a 66% FeTconcentrate and can command a $2-5 premium
per percentage above 62% FeT, for each tonne of ore.
13
Consolidated Fire Lake North Project
Prefeasibility Study – Feb. 2013
OPERATING EXPENDITURES (US$/TONNE OF CONCENTRATE)
COST PARAMETERS

AVERAGE 20 YEARS

AVERAGE YEARS 1 to 5

Mining

18.89

12.76

Concentrating, crushing & processing

4.38

3.89

Site infrastructure, sales & general administration

4.05

3.66

Environmental tailings & management

0.13

0.12

Rail transport including lease for rolling stock

4.80

5.42

Port facilities

2.34

2.14

34.58

27.99

Railway capital repayment ($1,133.6M)

6.22

7.40

Railway interest payment ($592.6M)

3.25

7.29

44.05

42.68

Total Direct Operating Cost

Total Operating Cost
PRE-PRODUCTION CAPITAL EXPENDITURES (US$ MILLIONS)
Fire Lake North & Pointe Noire

Railway
Total Capital
in
$ MILLIONS

Direct Costs

Mining
Concentrator & FLN Site Infrastructure

687.7

Pointe Noire

106.5

Project Indirect Costs

140.5

Contingency

Railway

200.0

Rolling Stock Leasing

13.4

53.2

Engineering, Procurement, Construction & Mgmt. (EPCM)

Total Capital in
$ MILLIONS

158.2

Owner’s Cost

COST AREA

133.7

Indirect Costs

COST AREA

114.6
Sub-total

1,394.4

Grand Total (100% of the project)

Sub-total
1,607.9

213.4

14
Consolidated Fire Lake North
Project Schedule
2011
2012
2013
2014
2015
2016
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
CFLN Definition Drilling
Scoping Study
Updated PEA
Metallurgical Results - CFLN, Moire
Lake, Oil Can
Pre-Feasibility Study
Environmental and Social Impact
Assessment (ongoing)
Community Consultation
Oil Can Definition Drilling Planned
Feasibility Study
Permitting
Construction
Production
Legend:
Critical point: Project Schedule will be revised and updated once the feasibility study of the railway solution is confirmed

Completed milestones
Consolidated Fire Lake North Project
Growth Through Development


Prefeasibility Study results released Feb. 7, 2013



Feasibility Study with 20 Mtpa production rate
scope underway



West Pit
Area
East Pit
Area

West (3500m) & East (2400m) Pits are both
synformal fold closures that are open at depth



Don Lake
Area

Mineral Resource Estimate (MRE) announced on
Jan. 9, 2013 (COG 15% FeT):
Measured & Indicated Resources
693.5 M tonnes grading 31.5% total iron (FeT)
Inferred Resources
521.6 M tonnes grading 30.1% total iron (FeT)



Several de-risking initiatives are underway
See www.championironmines.com for reports maps & assays

16
Consolidated Fire Lake North Metallurgy
Press Release, August 1, 2012





High quality sinter concentrate with very low deleterious elemental content
Weight recovery @ 39.9%; no magnetic separation required
Liberates at 850 micron (-20 mesh) & produces a 65-66% iron concentrate
Assuming a concentrate with 66% Fe ; No magnetic separation circuit required
 Alumina is 0.52% versus industry standard of 2%
 Silica content is < 5%
 Al2O3 : SiO2 ratio of 0.14 versus the upper industry specification limit of 1
 This very low alumina to silica ratio is an ideal blending product for steel mills

High Grade, Coarse Specular Hematite

Quartz Specular Hematite

17
Consolidated Fire Lake North Project
Economic Projections based on PFS Metrics
Assumptions: 1Projections of an expansion plan at CFLN for a second concentrator production line
are listed in the table below. This projection of an 18-20 Mtpa production rate of iron concentrate is
not NI 43-101 compliant but rather an estimation of mid term potential:
IRR = 34.7%

NPV (M$)

Payback (yrs)

0%

$18,441 M

3.9

5%

$9,400 M

4.1

8%

$6,465 M

4.32

10%

$5,081 M

4.4

Discount Rate

2Payback

period at an 8% discounted rate is estimated from the production start of the 1st
concentrator production line, the payback for the 2nd production line is 1.9 years after it starts based
on the additional CAPEX for the 2nd line of US$587M including indirect (mine and concentrator)
costs, railway capital repayment and interest.

Feasibility Study Objectives:
•
•
•
•

Potential to integrate a Multi-Users rail solution
Reduce CFLN sustaining capital in the economic model.
Continue metallurgical test work with the objective of eliminating the second AG mill ($100 million sustaining capital) in year.
Continue negotiations with Hydro-Québec to find ways to reduce the $217.5 million participation in sustaining capital for the
construction of a new 315 kV power line.
• Review iron ore deposits at both CFLN & Oil Can to increase Measured & Indicated Resources and reduce the overall strip ratio.
18
Fire Lake North Development Project

19
Fire Lake North Development Project

20
Oil Can Project
Initial Mineral Resource Estimate
 Potential for low strip ratio < 1–1.5
 972 Mt of iron oxide grading 33.2% at a
15% iron cut-off
 924 Mt of mixed iron oxide-silicate
mineralization
 This deposit is open at depth
 Orientation metallurgical tests indicate
a relatively coarse liberation grind size
 Commercial grade magnetite sinter feed
concentrate can be produced
 2011 drill program returned long
magnetite-hematite
iron
formation
intersections up to 545 metres in length
 Inferred Resources drilled on 400 metre
sections is completed
To view a larger more detailed version of this map please visit:
http://www.championironmines.com/vns-site/page-oil_can.html

21
Moiré Lake Project
Initial Mineral Resource Estimate: March 29, 2012
Mineral Resource Estimate:
Arcelor Mittal Property Boundary

Indicated Resources:
164 M tonnes grading 30.5% FeT
Inferred Resources:
417 M tonnes grading 29.4% FeT
 DDH LM11-12: 503 M @ 31% FeT

A’

 Kilometric synform with hematite &
magnetite outcrops at surface
 Adjacent to ArcelorMittal Mont-Wright mine

A
500
meters

22
Moiré Lake Project
Infrastructure: Adjacent to Bloom Lake Railway (8km), road, & power

442 Mt @ 30.1% FeT;
Zone B: 285 Mt @ 30.1% FeT

500
meters

23
Oil Can Project
Exploration Upside

South & East Zones
Section 9800N (Facing North)
South Zone
OC11-05

OC11-07

East Zone

OC11-08

OC11-19

OC11-02

OC11-01

Ovb

IF
OC11-07

OC11-019

IF

197.2m @ 26.8%
incl. 145.5 @
28.1%

163.1m @
30.5%
OC11-01

190.9m @
30.6%

OC11-05

303.4m @ 34.7%
incl. 130.8m @
36.5%

OC11-02

401.5m @ 30.7%
incl. 213.5 @
33.1%
OC11-08
545.7m @ 33.7%
incl. 442.3 @
36.4%
200 metres

24
Oil Can Project
Exploration Upside

Central Zone
(Facing Northwest)

OC11-14
OC11-16 OC11-03
OC11-10

Ovb

OC11-014

191.7m @
28.2%
OC11-016

311.4m @ 27.6%
incl. 269.0m @
29.2%

OC11-03

224.0m @ 28.1%
incl. 176.0m @
29.0%

IF

OC11-10

472.2m @ 28.0%
incl. 119.6m @
35.2%

200 metres

25
Oil Can Project
Exploration Upside

North Zone
Section 5800E (Facing East)
OC11-12

OC11-13

OC11-04

OC11-15

Ovb
OC11-09

OC11-012

221.2m @ 25.0%
incl. 128.9m @
28.7%

IF
OC11-15

OC11-09

292.5m @ 25.8%
incl. 113.8m @
30.4%

OC11-04

328.9m @ 31.5%
Incl. 111.1m @
32.9%

141.5m @ 29.2%
Incl. 179.5m @
OC11-13
32.8%
414.1m @ 25.1%
incl. 139.0m @
29.5%

200 metres

26
Why Invest in
Champion Iron Mines?


Robust Economics: (CFLN NPV, US$3.3B @ 8%
DCF (PFS Feb. 2013); IRR 30.9%; 3.4 year
payback period

 12 Projects (755 km2) near 5 operating mines;
 5.1 billion tonnes of NI 43-101 compliant
resource


Oil Can Deposit:
Initial Resource Estimate 1,896 Mt @ 28.7%



High-Quality CFLN concentrate @ 66%Fe, with low
impurity levels



Experienced team: Exploration, development,
construction, commissioning & operations
management



Financed through to feasibility; Favourable tax
regime; Political support; & known operating
environment

27
Fire Lake North Exploration Camp

Coarse Specular Hematite in Drill Core

Coarse Grained Specular Hematite

28
Thank You
www.championironmines.com
FSE: P02; OTCQX: CPMNF

20 Adelaide Street East, Suite 301, Toronto, ON M5C 2T6

| 416 866 2200

29
Global Steel Production Shows
Continued Demand for Iron Ore
1,600,000

China’s CAGR* is 9.88% over
the last 30 years vs. 2.30% for
total global steel production
over the same period.

1,400,000

Kilotonnes

1,200,000

1,000,000

China
800,000

Japan

600,000

Rest of the
World

400,000

200,000

1980

1985

Source: World Steel Association website
* CAGR: Compound Annual Growth Rate

1990

1995

2000

2005

2010

30
Labrador Trough Annual Production
Iron Ore Production Upside
Current Annual
Production

Future
Annual Forecast

IOC/RTZ

17 Mtpa + 6 Mtpa

23 Mtpa

ArcelorMittal

16 Mtpa + 8 Mtpa

24 Mtpa

Cliffs Natural Resources (Wuhan)

12 Mtpa + 8 Mtpa

20 Mtpa

2 Mtpa1

5 Mtpa1

0

50 Mtpa2

Company

Labrador Iron Mines
Adriana Resources (Wuhan)
New Millennium (Tata)

0

4 Mtpa1
24 Mtpa2
2 Mtpa1

Century Iron Mines (Wuhan)

0

Champion Iron Mines Limited

0

~20 Mtpa

Alderon Iron Ore Corp.

0

~16 Mtpa

47 + 22 Mtpa

~208 Mtpa

Total Current & Forecasted Production
1.
2.

Direct shipping ore
Taconite fine grained iron ore

20 Mtpa2

31
Fermont Iron Ore District
(“FIOD”)
Historically, before 2003, the Fermont &
Labrador mining camps produced 33 Mtpa.
RTZ/IOC = 17 Mtpa; increased now to 24
ArcelorMittal = 13 Mtpa; increased now to 24
Wabush = 3-4 Mtpa
Price
“ Marginal Era”:
For 30-40 years pre-2003
the price per tonne of concentrate
was $15- $30/tonne for 62% Fe,
costs per tonne were similar.
Current 3 year moving average is
$115/tonne (62% Fe)
Current Spot Price Average
~$130-135/tonne (Oct. 2013)
(62% Fe)
32
O’Keefe Purdy Project
Exploration Upside

33
Advanced Exploration
Bellechasse Deposit

Harvey Tuttle Project



Deposit located within CFLN





NI 43-101 Resource Estimate: Inferred Resources

estimate; 215 Mt @ 29% Fe; potential for more



Magnetite rich iron formation



Adjacent to Hwy 389



Synform geometry is favorable for open pit mining

NI 43-101 Inferred Resource Estimate:
717 Mt @ 25% Fe; magnetite rich iron formation
Intersected multiple significant iron formation
intervals in 2010 drill program



Total of 13,165 m of drilling completed



Less than 50% of the kilometric scale magnetic
anomalies have been tested



25 km W-NW of CFLN



Within conveying distance from CFLN planned
concentrator (20-30 km)

34

More Related Content

What's hot

RMC Corporate Presentation August 2014
RMC Corporate Presentation August 2014RMC Corporate Presentation August 2014
RMC Corporate Presentation August 2014
reservoirminerals
 
Corporate Presentation - November 2014
Corporate Presentation - November 2014Corporate Presentation - November 2014
Corporate Presentation - November 2014
reservoirminerals
 
Corporate Presentation - October 2014
Corporate Presentation - October 2014Corporate Presentation - October 2014
Corporate Presentation - October 2014
reservoirminerals
 
November Investor Presentation
November Investor PresentationNovember Investor Presentation
November Investor Presentation
reservoirminerals
 
160603 corporate presentation
160603 corporate presentation160603 corporate presentation
160603 corporate presentation
reservoirminerals
 
160530 corporate presentation
160530 corporate presentation160530 corporate presentation
160530 corporate presentation
reservoirminerals
 
Reservoir Minerals Presentation - March 2016
Reservoir Minerals Presentation - March 2016Reservoir Minerals Presentation - March 2016
Reservoir Minerals Presentation - March 2016
reservoirminerals
 
Reservoir Corporate PDAC
Reservoir Corporate PDACReservoir Corporate PDAC
Reservoir Corporate PDAC
reservoirminerals
 
Reservoir Minerals Presentation - August 2013
Reservoir Minerals Presentation - August 2013Reservoir Minerals Presentation - August 2013
Reservoir Minerals Presentation - August 2013
reservoirminerals
 
RMC November 2013 Corporate Presentation
RMC November 2013 Corporate PresentationRMC November 2013 Corporate Presentation
RMC November 2013 Corporate Presentation
reservoirminerals
 
150720 corporate presentation
150720 corporate presentation150720 corporate presentation
150720 corporate presentation
reservoirminerals
 
RMC Corporate Presentation - May 2014
RMC Corporate Presentation - May 2014RMC Corporate Presentation - May 2014
RMC Corporate Presentation - May 2014
reservoirminerals
 
Corporate Presentation - April 2015
Corporate Presentation - April 2015Corporate Presentation - April 2015
Corporate Presentation - April 2015
reservoirminerals
 
Corporate Presentation - June 2015
Corporate Presentation - June 2015Corporate Presentation - June 2015
Corporate Presentation - June 2015
reservoirminerals
 
Reservoir Minerals Presentation - June 2013
Reservoir Minerals Presentation - June 2013Reservoir Minerals Presentation - June 2013
Reservoir Minerals Presentation - June 2013
reservoirminerals
 
150825 corporate presentation
150825 corporate presentation150825 corporate presentation
150825 corporate presentation
reservoirminerals
 
Fortune Minerals - Investor Presentation - January 2014
Fortune Minerals -  Investor Presentation - January 2014Fortune Minerals -  Investor Presentation - January 2014
Fortune Minerals - Investor Presentation - January 2014
Company Spotlight
 
150928 corporate presentation
150928 corporate presentation150928 corporate presentation
150928 corporate presentation
reservoirminerals
 
150918 corporate presentation
150918 corporate presentation150918 corporate presentation
150918 corporate presentation
reservoirminerals
 

What's hot (19)

RMC Corporate Presentation August 2014
RMC Corporate Presentation August 2014RMC Corporate Presentation August 2014
RMC Corporate Presentation August 2014
 
Corporate Presentation - November 2014
Corporate Presentation - November 2014Corporate Presentation - November 2014
Corporate Presentation - November 2014
 
Corporate Presentation - October 2014
Corporate Presentation - October 2014Corporate Presentation - October 2014
Corporate Presentation - October 2014
 
November Investor Presentation
November Investor PresentationNovember Investor Presentation
November Investor Presentation
 
160603 corporate presentation
160603 corporate presentation160603 corporate presentation
160603 corporate presentation
 
160530 corporate presentation
160530 corporate presentation160530 corporate presentation
160530 corporate presentation
 
Reservoir Minerals Presentation - March 2016
Reservoir Minerals Presentation - March 2016Reservoir Minerals Presentation - March 2016
Reservoir Minerals Presentation - March 2016
 
Reservoir Corporate PDAC
Reservoir Corporate PDACReservoir Corporate PDAC
Reservoir Corporate PDAC
 
Reservoir Minerals Presentation - August 2013
Reservoir Minerals Presentation - August 2013Reservoir Minerals Presentation - August 2013
Reservoir Minerals Presentation - August 2013
 
RMC November 2013 Corporate Presentation
RMC November 2013 Corporate PresentationRMC November 2013 Corporate Presentation
RMC November 2013 Corporate Presentation
 
150720 corporate presentation
150720 corporate presentation150720 corporate presentation
150720 corporate presentation
 
RMC Corporate Presentation - May 2014
RMC Corporate Presentation - May 2014RMC Corporate Presentation - May 2014
RMC Corporate Presentation - May 2014
 
Corporate Presentation - April 2015
Corporate Presentation - April 2015Corporate Presentation - April 2015
Corporate Presentation - April 2015
 
Corporate Presentation - June 2015
Corporate Presentation - June 2015Corporate Presentation - June 2015
Corporate Presentation - June 2015
 
Reservoir Minerals Presentation - June 2013
Reservoir Minerals Presentation - June 2013Reservoir Minerals Presentation - June 2013
Reservoir Minerals Presentation - June 2013
 
150825 corporate presentation
150825 corporate presentation150825 corporate presentation
150825 corporate presentation
 
Fortune Minerals - Investor Presentation - January 2014
Fortune Minerals -  Investor Presentation - January 2014Fortune Minerals -  Investor Presentation - January 2014
Fortune Minerals - Investor Presentation - January 2014
 
150928 corporate presentation
150928 corporate presentation150928 corporate presentation
150928 corporate presentation
 
150918 corporate presentation
150918 corporate presentation150918 corporate presentation
150918 corporate presentation
 

Similar to Nov. 2013 Champion Corporate Presentation - English

Reservoir Minerals Presentation - March 2016
Reservoir Minerals Presentation - March 2016Reservoir Minerals Presentation - March 2016
Reservoir Minerals Presentation - March 2016
reservoirminerals
 
Fortune Minerals June 2012 Investor Presentation
Fortune Minerals June 2012 Investor PresentationFortune Minerals June 2012 Investor Presentation
Fortune Minerals June 2012 Investor Presentation
Company Spotlight
 
Reservoir Minerals Corporate Presentation 2015
Reservoir Minerals Corporate Presentation 2015Reservoir Minerals Corporate Presentation 2015
Reservoir Minerals Corporate Presentation 2015
reservoirminerals
 
Fortune minerals march 2012 investor presentation
Fortune minerals march 2012 investor presentationFortune minerals march 2012 investor presentation
Fortune minerals march 2012 investor presentation
Company Spotlight
 
Huguenot Project Presentation
Huguenot Project PresentationHuguenot Project Presentation
Huguenot Project Presentation
ColonialCoal
 
Investor Presentation
Investor PresentationInvestor Presentation
Investor Presentation
Company Spotlight
 
12 champion iron mines oct. 25th
12 champion iron mines oct. 25th12 champion iron mines oct. 25th
12 champion iron mines oct. 25th
shosein2011
 
April 2012 Fortune Minerals Investor Presentation
April 2012 Fortune Minerals Investor PresentationApril 2012 Fortune Minerals Investor Presentation
April 2012 Fortune Minerals Investor Presentation
Company Spotlight
 
Investor presentationjul2013
Investor presentationjul2013Investor presentationjul2013
Investor presentationjul2013
Company Spotlight
 
Rmc december2013
Rmc december2013Rmc december2013
Rmc december2013
reservoirminerals
 
English champion iron_mines_october 9, 2012
English champion iron_mines_october 9, 2012English champion iron_mines_october 9, 2012
English champion iron_mines_october 9, 2012
shosein2011
 
English champion iron mines sept 18th 2012
English champion iron mines sept 18th 2012English champion iron mines sept 18th 2012
English champion iron mines sept 18th 2012
shosein2011
 
Fortune Minerals Investor Presentation - January 2014
Fortune Minerals Investor Presentation - January 2014Fortune Minerals Investor Presentation - January 2014
Fortune Minerals Investor Presentation - January 2014
Company Spotlight
 
Fortune Minerals Investor Presentation November 2013
Fortune Minerals  Investor Presentation November 2013Fortune Minerals  Investor Presentation November 2013
Fortune Minerals Investor Presentation November 2013
Company Spotlight
 
160111 corp presentation
160111 corp presentation160111 corp presentation
160111 corp presentation
reservoirminerals
 

Similar to Nov. 2013 Champion Corporate Presentation - English (15)

Reservoir Minerals Presentation - March 2016
Reservoir Minerals Presentation - March 2016Reservoir Minerals Presentation - March 2016
Reservoir Minerals Presentation - March 2016
 
Fortune Minerals June 2012 Investor Presentation
Fortune Minerals June 2012 Investor PresentationFortune Minerals June 2012 Investor Presentation
Fortune Minerals June 2012 Investor Presentation
 
Reservoir Minerals Corporate Presentation 2015
Reservoir Minerals Corporate Presentation 2015Reservoir Minerals Corporate Presentation 2015
Reservoir Minerals Corporate Presentation 2015
 
Fortune minerals march 2012 investor presentation
Fortune minerals march 2012 investor presentationFortune minerals march 2012 investor presentation
Fortune minerals march 2012 investor presentation
 
Huguenot Project Presentation
Huguenot Project PresentationHuguenot Project Presentation
Huguenot Project Presentation
 
Investor Presentation
Investor PresentationInvestor Presentation
Investor Presentation
 
12 champion iron mines oct. 25th
12 champion iron mines oct. 25th12 champion iron mines oct. 25th
12 champion iron mines oct. 25th
 
April 2012 Fortune Minerals Investor Presentation
April 2012 Fortune Minerals Investor PresentationApril 2012 Fortune Minerals Investor Presentation
April 2012 Fortune Minerals Investor Presentation
 
Investor presentationjul2013
Investor presentationjul2013Investor presentationjul2013
Investor presentationjul2013
 
Rmc december2013
Rmc december2013Rmc december2013
Rmc december2013
 
English champion iron_mines_october 9, 2012
English champion iron_mines_october 9, 2012English champion iron_mines_october 9, 2012
English champion iron_mines_october 9, 2012
 
English champion iron mines sept 18th 2012
English champion iron mines sept 18th 2012English champion iron mines sept 18th 2012
English champion iron mines sept 18th 2012
 
Fortune Minerals Investor Presentation - January 2014
Fortune Minerals Investor Presentation - January 2014Fortune Minerals Investor Presentation - January 2014
Fortune Minerals Investor Presentation - January 2014
 
Fortune Minerals Investor Presentation November 2013
Fortune Minerals  Investor Presentation November 2013Fortune Minerals  Investor Presentation November 2013
Fortune Minerals Investor Presentation November 2013
 
160111 corp presentation
160111 corp presentation160111 corp presentation
160111 corp presentation
 

More from ChampionMines

Champion & Mumba Business Combination Presentation
Champion & Mumba Business Combination PresentationChampion & Mumba Business Combination Presentation
Champion & Mumba Business Combination Presentation
ChampionMines
 
Feb. 2013 Champion Corporate Presentation - French
Feb. 2013 Champion Corporate Presentation - FrenchFeb. 2013 Champion Corporate Presentation - French
Feb. 2013 Champion Corporate Presentation - FrenchChampionMines
 
December - Champion and Mamba Merger - Corporate Presentation
December - Champion and Mamba Merger - Corporate PresentationDecember - Champion and Mamba Merger - Corporate Presentation
December - Champion and Mamba Merger - Corporate Presentation
ChampionMines
 
Nov. 2013 Champion Corporate Presentation - French
Nov. 2013 Champion Corporate Presentation - FrenchNov. 2013 Champion Corporate Presentation - French
Nov. 2013 Champion Corporate Presentation - FrenchChampionMines
 
Nov. 2013 Champion Corporate Presentation - German
Nov. 2013 Champion Corporate Presentation - GermanNov. 2013 Champion Corporate Presentation - German
Nov. 2013 Champion Corporate Presentation - GermanChampionMines
 
Nov. 2013 Champion Corporate Presentation - Chinese
Nov. 2013 Champion Corporate Presentation - ChineseNov. 2013 Champion Corporate Presentation - Chinese
Nov. 2013 Champion Corporate Presentation - ChineseChampionMines
 
Oct. 2013 Champion Corporate Presentation - Chinese
Oct. 2013 Champion Corporate Presentation - ChineseOct. 2013 Champion Corporate Presentation - Chinese
Oct. 2013 Champion Corporate Presentation - ChineseChampionMines
 
May 2013 Champion Corporate Presentation - German
May 2013 Champion Corporate Presentation - GermanMay 2013 Champion Corporate Presentation - German
May 2013 Champion Corporate Presentation - GermanChampionMines
 
May 2013 Champion Corporate Presentation - Chinese
May 2013 Champion Corporate Presentation - ChineseMay 2013 Champion Corporate Presentation - Chinese
May 2013 Champion Corporate Presentation - ChineseChampionMines
 
May 2013 Champion Corporate Presentation - French
May 2013 Champion Corporate Presentation - FrenchMay 2013 Champion Corporate Presentation - French
May 2013 Champion Corporate Presentation - FrenchChampionMines
 
April 2013 Champion Corporate Presentation - Chinese
April 2013 Champion Corporate Presentation - ChineseApril 2013 Champion Corporate Presentation - Chinese
April 2013 Champion Corporate Presentation - ChineseChampionMines
 
April 2013 Champion Corporate Presentation - German
April 2013 Champion Corporate Presentation - GermanApril 2013 Champion Corporate Presentation - German
April 2013 Champion Corporate Presentation - GermanChampionMines
 
April 2013 Champion Corporate Presentation - French
April 2013 Champion Corporate Presentation - FrenchApril 2013 Champion Corporate Presentation - French
April 2013 Champion Corporate Presentation - FrenchChampionMines
 
Mar. 2013 Champion Corporate Presentation - Chinese
Mar. 2013 Champion Corporate Presentation - ChineseMar. 2013 Champion Corporate Presentation - Chinese
Mar. 2013 Champion Corporate Presentation - ChineseChampionMines
 

More from ChampionMines (14)

Champion & Mumba Business Combination Presentation
Champion & Mumba Business Combination PresentationChampion & Mumba Business Combination Presentation
Champion & Mumba Business Combination Presentation
 
Feb. 2013 Champion Corporate Presentation - French
Feb. 2013 Champion Corporate Presentation - FrenchFeb. 2013 Champion Corporate Presentation - French
Feb. 2013 Champion Corporate Presentation - French
 
December - Champion and Mamba Merger - Corporate Presentation
December - Champion and Mamba Merger - Corporate PresentationDecember - Champion and Mamba Merger - Corporate Presentation
December - Champion and Mamba Merger - Corporate Presentation
 
Nov. 2013 Champion Corporate Presentation - French
Nov. 2013 Champion Corporate Presentation - FrenchNov. 2013 Champion Corporate Presentation - French
Nov. 2013 Champion Corporate Presentation - French
 
Nov. 2013 Champion Corporate Presentation - German
Nov. 2013 Champion Corporate Presentation - GermanNov. 2013 Champion Corporate Presentation - German
Nov. 2013 Champion Corporate Presentation - German
 
Nov. 2013 Champion Corporate Presentation - Chinese
Nov. 2013 Champion Corporate Presentation - ChineseNov. 2013 Champion Corporate Presentation - Chinese
Nov. 2013 Champion Corporate Presentation - Chinese
 
Oct. 2013 Champion Corporate Presentation - Chinese
Oct. 2013 Champion Corporate Presentation - ChineseOct. 2013 Champion Corporate Presentation - Chinese
Oct. 2013 Champion Corporate Presentation - Chinese
 
May 2013 Champion Corporate Presentation - German
May 2013 Champion Corporate Presentation - GermanMay 2013 Champion Corporate Presentation - German
May 2013 Champion Corporate Presentation - German
 
May 2013 Champion Corporate Presentation - Chinese
May 2013 Champion Corporate Presentation - ChineseMay 2013 Champion Corporate Presentation - Chinese
May 2013 Champion Corporate Presentation - Chinese
 
May 2013 Champion Corporate Presentation - French
May 2013 Champion Corporate Presentation - FrenchMay 2013 Champion Corporate Presentation - French
May 2013 Champion Corporate Presentation - French
 
April 2013 Champion Corporate Presentation - Chinese
April 2013 Champion Corporate Presentation - ChineseApril 2013 Champion Corporate Presentation - Chinese
April 2013 Champion Corporate Presentation - Chinese
 
April 2013 Champion Corporate Presentation - German
April 2013 Champion Corporate Presentation - GermanApril 2013 Champion Corporate Presentation - German
April 2013 Champion Corporate Presentation - German
 
April 2013 Champion Corporate Presentation - French
April 2013 Champion Corporate Presentation - FrenchApril 2013 Champion Corporate Presentation - French
April 2013 Champion Corporate Presentation - French
 
Mar. 2013 Champion Corporate Presentation - Chinese
Mar. 2013 Champion Corporate Presentation - ChineseMar. 2013 Champion Corporate Presentation - Chinese
Mar. 2013 Champion Corporate Presentation - Chinese
 

Recently uploaded

Corporate Presentation Probe June 2024.pdf
Corporate Presentation Probe June 2024.pdfCorporate Presentation Probe June 2024.pdf
Corporate Presentation Probe June 2024.pdf
Probe Gold
 
Collective Mining | Corporate Presentation - June 2024
Collective Mining | Corporate Presentation - June 2024Collective Mining | Corporate Presentation - June 2024
Collective Mining | Corporate Presentation - June 2024
CollectiveMining1
 
快速办理(CUBoulder毕业证书)科罗拉多大学博尔德分校毕业证录取通知书一模一样
快速办理(CUBoulder毕业证书)科罗拉多大学博尔德分校毕业证录取通知书一模一样快速办理(CUBoulder毕业证书)科罗拉多大学博尔德分校毕业证录取通知书一模一样
快速办理(CUBoulder毕业证书)科罗拉多大学博尔德分校毕业证录取通知书一模一样
f3wjr2q2
 
2024-deutsche-bank-global-consumer-conference.pdf
2024-deutsche-bank-global-consumer-conference.pdf2024-deutsche-bank-global-consumer-conference.pdf
2024-deutsche-bank-global-consumer-conference.pdf
Sysco_Investors
 
Cyberagent_For New Investors_EN_240424.pdf
Cyberagent_For New Investors_EN_240424.pdfCyberagent_For New Investors_EN_240424.pdf
Cyberagent_For New Investors_EN_240424.pdf
CyberAgent, Inc.
 
Osisko Development - Investor Presentation - June 24
Osisko Development - Investor Presentation - June 24Osisko Development - Investor Presentation - June 24
Osisko Development - Investor Presentation - June 24
Philip Rabenok
 
Understanding-the-E-Way-Bill-A-Digital-Transformation-in-Logistics.pptx
Understanding-the-E-Way-Bill-A-Digital-Transformation-in-Logistics.pptxUnderstanding-the-E-Way-Bill-A-Digital-Transformation-in-Logistics.pptx
Understanding-the-E-Way-Bill-A-Digital-Transformation-in-Logistics.pptx
cosmo-soil
 
Cleades robinson:The Diplomat is Blue
Cleades robinson:The Diplomat is BlueCleades robinson:The Diplomat is Blue
Cleades robinson:The Diplomat is Blue
Cleades Robinson
 
MUTUAL FUNDS (ICICI Prudential Mutual Fund) BY JAMES RODRIGUES
MUTUAL FUNDS (ICICI Prudential Mutual Fund) BY JAMES RODRIGUESMUTUAL FUNDS (ICICI Prudential Mutual Fund) BY JAMES RODRIGUES
MUTUAL FUNDS (ICICI Prudential Mutual Fund) BY JAMES RODRIGUES
WilliamRodrigues148
 
一比一原版(UW毕业证)华盛顿大学毕业证成绩单专业办理
一比一原版(UW毕业证)华盛顿大学毕业证成绩单专业办理一比一原版(UW毕业证)华盛顿大学毕业证成绩单专业办理
一比一原版(UW毕业证)华盛顿大学毕业证成绩单专业办理
ybout
 
Mandalay Resouces June 2024 Investor Relations PPT
Mandalay Resouces June 2024 Investor Relations PPTMandalay Resouces June 2024 Investor Relations PPT
Mandalay Resouces June 2024 Investor Relations PPT
MandalayResources
 
ppt-namibia-worldeconomy-standardbank.ppt
ppt-namibia-worldeconomy-standardbank.pptppt-namibia-worldeconomy-standardbank.ppt
ppt-namibia-worldeconomy-standardbank.ppt
TestOrg1
 

Recently uploaded (12)

Corporate Presentation Probe June 2024.pdf
Corporate Presentation Probe June 2024.pdfCorporate Presentation Probe June 2024.pdf
Corporate Presentation Probe June 2024.pdf
 
Collective Mining | Corporate Presentation - June 2024
Collective Mining | Corporate Presentation - June 2024Collective Mining | Corporate Presentation - June 2024
Collective Mining | Corporate Presentation - June 2024
 
快速办理(CUBoulder毕业证书)科罗拉多大学博尔德分校毕业证录取通知书一模一样
快速办理(CUBoulder毕业证书)科罗拉多大学博尔德分校毕业证录取通知书一模一样快速办理(CUBoulder毕业证书)科罗拉多大学博尔德分校毕业证录取通知书一模一样
快速办理(CUBoulder毕业证书)科罗拉多大学博尔德分校毕业证录取通知书一模一样
 
2024-deutsche-bank-global-consumer-conference.pdf
2024-deutsche-bank-global-consumer-conference.pdf2024-deutsche-bank-global-consumer-conference.pdf
2024-deutsche-bank-global-consumer-conference.pdf
 
Cyberagent_For New Investors_EN_240424.pdf
Cyberagent_For New Investors_EN_240424.pdfCyberagent_For New Investors_EN_240424.pdf
Cyberagent_For New Investors_EN_240424.pdf
 
Osisko Development - Investor Presentation - June 24
Osisko Development - Investor Presentation - June 24Osisko Development - Investor Presentation - June 24
Osisko Development - Investor Presentation - June 24
 
Understanding-the-E-Way-Bill-A-Digital-Transformation-in-Logistics.pptx
Understanding-the-E-Way-Bill-A-Digital-Transformation-in-Logistics.pptxUnderstanding-the-E-Way-Bill-A-Digital-Transformation-in-Logistics.pptx
Understanding-the-E-Way-Bill-A-Digital-Transformation-in-Logistics.pptx
 
Cleades robinson:The Diplomat is Blue
Cleades robinson:The Diplomat is BlueCleades robinson:The Diplomat is Blue
Cleades robinson:The Diplomat is Blue
 
MUTUAL FUNDS (ICICI Prudential Mutual Fund) BY JAMES RODRIGUES
MUTUAL FUNDS (ICICI Prudential Mutual Fund) BY JAMES RODRIGUESMUTUAL FUNDS (ICICI Prudential Mutual Fund) BY JAMES RODRIGUES
MUTUAL FUNDS (ICICI Prudential Mutual Fund) BY JAMES RODRIGUES
 
一比一原版(UW毕业证)华盛顿大学毕业证成绩单专业办理
一比一原版(UW毕业证)华盛顿大学毕业证成绩单专业办理一比一原版(UW毕业证)华盛顿大学毕业证成绩单专业办理
一比一原版(UW毕业证)华盛顿大学毕业证成绩单专业办理
 
Mandalay Resouces June 2024 Investor Relations PPT
Mandalay Resouces June 2024 Investor Relations PPTMandalay Resouces June 2024 Investor Relations PPT
Mandalay Resouces June 2024 Investor Relations PPT
 
ppt-namibia-worldeconomy-standardbank.ppt
ppt-namibia-worldeconomy-standardbank.pptppt-namibia-worldeconomy-standardbank.ppt
ppt-namibia-worldeconomy-standardbank.ppt
 

Nov. 2013 Champion Corporate Presentation - English

  • 1. Building the Next Major Iron Ore Mine in the Labrador Trough Corporate Presentation November 2013 Oct 19th,2013 19 November 2013 | championironmines.com FSE: P02 CPMNF
  • 2. FORWARD-LOOKING STATEMENTS Certain information contained herein regarding Champion Iron Mines Ltd., including management’s assessment of future plans & operations, may constitute forward-looking statements under applicable securities law & necessarily involve risks, including but not limited to risks associated with mining exploration, operating costs, production costs, volatility of share prices, currency fluctuations, imprecision of resource & reserve estimates, environmental risks & ability to access sufficient capital from internal & external sources. As a consequence, actual results may differ materially from those anticipated in any forward looking statements. Plans, intentions or expectations disclosed in any forward-looking statements or information should not be read as guarantees of future results or events, & will not necessarily be accurate indications of whether or when or by which such results or events will be achieved. Except as required by law, Champion Iron Mines Ltd., expressly disclaims any intention & undertakes no obligation to update any forward looking statements or information as conditions change. The historical mineral resources mentioned are strictly historical in nature & are non-compliant to National Instrument 43-101 mineral resources & mineral reserves standards, & should therefore not be relied upon. A qualified person has not done sufficient work to upgrade or classify the historical mineral resources as current National Instrument NI-43-101 compliant. 2
  • 3. About Champion Iron Mines Advanced iron ore exploration & development projects located in Canada’s principal iron ore district, the Labrador Trough Fermont Holdings (755 km2)  121 projects in the Fermont Iron Ore District  Flagship Consolidated Fire Lake North (“CFLN”) Project Prefeasibility Study (“PFS”) announced Feb. 7, 2013  5.1 billion tonnes of NI 43-101 compliant Mineral Resource Estimates of iron ore   910 million tonnes of Measured + Indicated Resources 4,185 million tonnes of Inferred Mineral Resources  100% direct interest; option to buy back 0.5% of the NSR for C$1.5 million, resulting in a 2.5% NSR overall) Attikamagen Project (310 km2)  1.7 billion tonnes @ 31.3% FeT & a plan for a 2 Mtpa2 DSO project  Champion retains a 2% NSR in the Attikamagen Project that is owned through a joint venture between Century Iron Mines and Wuhan3 1. Champion signed a definitive option agreement with Cartier Iron to earn a 65% interest in 7 of its projects (Cluster 3) 2. As reported by Champion Iron’s JV Partner on Mar. 25, 2013 press release 3. As reported in Champion Iron’s October 3, 2013 press release 3
  • 4. Québec’s Next Major Iron Ore Mine CFLN Prefeasibility Study   Feb. 7, 2013 PFS indicated an average production rate of 9.3 Mtpa of iron concentrate for the 20 year mine life  First 5 year average: 9.8 Mtpa Net Present Value of $3.3B at a discounted cash flow rate of 8% with an Internal Rate of Return of 30.9% & a payback period of 3.4 years Established Fermont Iron Ore District  Canada produces 47 Mtpa of iron ore concentrate & this is expected to increase to a total of 200 Mtpa over the next 10 years if all proposed development projects are realized  Established rail, power & port infrastructure - Competitive power rates are available - Port of Sept-Îles is building a world-class 50 Mtpa multi-user wharf project for the iron ore industry which is on schedule & on budget 4
  • 5. Capital Structure Share Data & Cash Position as of September 30, 2013. Total Shares – Outstanding Warrants Options 137.4 Issued 7,000,000 at $3.00 (expire May 17, 2015) - Fancamp 15,000,000 at $0.25 (expire July 17, 2015) – Baotou Outstanding 7,000,000 15,000,000 22,000,000 8.34 M @ C$1.00 (avg. exercise price) Total Shares – Fully Diluted 168.0 M Outstanding Share Market Capitalization (based on $0.25 share price) C$34M Cash & Receivables C$15M Management / Insiders Ownership ~ 26.7% Analyst Coverage 5
  • 6. Board of Directors Over 200 years of combined exploration & mine operations experience B OARD OF D IRECTORS Tom Larsen* Donald A. Sheldon, LLB., P.Eng.* Alexander Horvath, P.Eng.* William Harding Francis Sauvé Harry Burgess, P.Eng. Paul Ankcorn James Wang PRESIDENT DIRECTOR DIRECTOR DIRECTOR DIRECTOR DIRECTOR DIRECTOR DIRECTOR M AN AGEM E NT T EAM Tom Larsen Miles Nagamatsu Alexander Horvath, P.Eng. Martin Bourgoin, P.Geo. Beat Frei Jeff Hussey, P.Geo. Jean-Luc Chouinard, P.Eng., M.Sc. Bruce Mitton, P.Geo. Jorge Estepa Katrina Chua PRESIDENT & CEO CHIEF FINANCIAL OFFICER EXECUTIVE VICE PRESIDENT, EXPLORATION & PROJECT DEVELOPMENT EXECUTIVE VICE PRESIDENT, OPERATIONS SENIOR VICE PRESIDENT, PROJECT FINANCE SENIOR VICE PRESIDENT, CORPORATE DEVELOPMENT VICE PRESIDENT, PROJECT DEVELOPMENT VICE PRESIDENT, EXPLORATION VICE PRESIDENT, SECRETARY & TREASURER DIRECTOR OF INVESTOR RELATIONS CORPORATE ADVISORS Doug Bache; Jérome Cliche 6
  • 7. Why invest in Champion Iron Mines? Favourable Operating Environment  October 7th 2013, Government announce a pre-feasibity study for a new multi-users rail – accessible to all  The forecast for Iron ore prices over the mid to long term remain positive  Favourable tax environment (40% tax rebate on exploration expenditures) Champion Iron Mines Competitive Advantage  Fermont Holdings: 12 iron ore brownfield projects (755 km2)  CFLN Prefeasibility Study of coarse grained specular hematite surficial deposits  Easier to liberate  Deleterious elements in concentrate are well below industry specifications limits  Access to low-cost power & close to rail & port infrastructure  Team with experience in mine start-ups including construction and commissioning  Québec is a very stable jurisdiction to develop & operate mines  Upside potential for short, mid, & long term growth is high with 5.1 billion tonnes of iron ore resources  Skilled labor work force in Québec  Environmental: Iron ore beneficiation includes crushing & grinding to liberate the iron; followed by gravity & magnetic separation of iron ore from gangue minerals rather than the use of reagents  Several de-risking initiatives underway including a multi-user rail solution, Environmental & Social Impact Study that is near completion & permit applications underway  Closest t project development to the St. Lawrence Seaway & electrical power infrastructure 7
  • 8. Global Mineral Resources NI 43-101 Compliant Mineral Resource Estimates Consolidated Fire Lake North Mineral Resource Estimates @ 15% FeT cut-off Deposit FLN - West* FLN - East* FLN - Don Lake Bellechasse Oil Can - Oxide Oil Can - Mixed Total *Total Resource under Prefeasibility Study Total Resource Tonnes (millions) Measured tonnes (millions) 24 3 0 Grade FeT% 35.4 34.2 21.4 Indicated tonnes (millions) 405 262 52 Grade FeT% 32.6 29.6 26.5 - - - - 27 1,215 35.0 719 31.0 Inferred tonnes (millions) 329 192 188 215 972 924 2,821 Grade FeT% 30.9 28.7 25.3 28.7 33.2 24.1 28.8 3,567 Other Fermont Holdings Mineral Resource Estimates @ 15% FeT cut-off Harvey-Tuttle Moire Lake Other Fermont Projects Total Resources Tonnes (millions) Total Fermont Holdings Mineral Resources Tonnes (millions) 164 27 35.0 30.5 947 417 883 30.9 4,185 23.2 29.4 27.6 5,095 3.567 billion tonnes, out of the 5.1 billion tonnes of global resources, are within the confines of the CFLN Project; the resource base has the potential to produce up to 35-40 Mtpa of iron concentrate; that could support an independent rail solution, if necessary. Oil Can has the potential for 16-20 Mtpa. 8
  • 9. Existing Rail Infrastructure REGIONAL LOCATION MAP & INFRASTRUCTURE Québec North Shore & Labrador Railway (“QNS&L”):  CFLN PEA Base Case connection to Bloom Lake railway required 62 km of rail + 32 km of loops and sidings including 14 km for the CFA1 railway for a total of 94 km of rail  New option under study: multi-user railway  QNS&L links to Sept-Îles & Pointe Noire  Bloom Lake & QNS&L railways are considered common carriers  Common carriers allocate capacity on a firstcome, first-serve basis Cartier Railway:   Privately owned by ArcelorMittal  Chemin de Fer Arnaud Transports ore from ArcelorMittal’s Fire Lake Mine northward to Mt. Wright concentrator  1 Links Mont Wright to Port-Cartier (Max 30Mtpa) Within CFLN Project boundary 9
  • 10. World Class Port of Sept-Îles Infrastructure Expanding to Meet Demand Pointe Noire Multi-Users Wharf  Completion Mar. 31, 2014; 18 months prior to “CFLN" startup  Federal Government announced $55M funding or 25% of project  Phase 1: 50 Mtpa for $220M  Phase 2: Planning for 100 Mtpa Port of Sept-Iles Pointe Noire Port of Sept-Îles Port of Sept-Iles  RTZ-IOC shipping facility Port-Cartier Pointe Noire  ArcelorMittal shipping facility  $2.1B expansion is underway & will include concentrator expansion with port & rail infrastructure upgrades China Max ship capacity 300kt  Located 62 km west of Sept-Îles Courtesy of the Port de Sept Îles 10
  • 11. 11
  • 12. Site Layout of Consolidated Fire Lake North Project 12
  • 13. Consolidated Fire Lake North Project Prefeasibility Study – February 2013 Key Results Pre-Tax Basis Internal Rate of Return (IRR) (8% Discount Rate) 1 30.9% Undiscounted Cash Flow $9.0B Net Present Value @ 5% Discounted Cash Flow $4.7B Net Present Value @ 8% Discounted Cash Flow $3.3B Net Present Value @ 10% Discounted Cash Flow $2.6B Payback Period (8% Discount Rate) 3.4 Years Pre-production Capital Expenditures: Direct Operating Costs2 US$1,394.4M (Fire Lake North & Pointe Noire) US$34.58 per tonne (average 20 years); US$27.99 per tonne (average years 1 to 5) Iron Ore Spot Price Assumptions3 US$115 per tonne of concentrate at 62% Fe (years 1 -5) US$110 per tonne of concentrate at 62% Fe (years 6-20) Mine-Life 19.6 years Exchange Rate $1.00 USD to $1.00 CDN Overall Stripping Ratio 2.74:1 for the current 20 year mine-life 1.56:1 (years 1-3 of production); 2.02:1 (years 1-5 of operation) Mineral Resource Estimate (MRE) East & West Pits Measured & Indicated Resources 693.5 Mt grading 31.5% FeT (NI43-101) Inferred Resources 521.6 Mt grading 30.1% FeT @ 15% FeT cut-off (NI43-101) Proven & Probable Reserves 464.6 million tonnes grading 32.4% Fe at a 15% cut-off grade; 1. This includes railway capital repayment and interest 2. Direct operating costs excludes railway capital repayment & interest 3. Iron ore spot price assumption does not take into account that Champion will be producing a 66% FeTconcentrate and can command a $2-5 premium per percentage above 62% FeT, for each tonne of ore. 13
  • 14. Consolidated Fire Lake North Project Prefeasibility Study – Feb. 2013 OPERATING EXPENDITURES (US$/TONNE OF CONCENTRATE) COST PARAMETERS AVERAGE 20 YEARS AVERAGE YEARS 1 to 5 Mining 18.89 12.76 Concentrating, crushing & processing 4.38 3.89 Site infrastructure, sales & general administration 4.05 3.66 Environmental tailings & management 0.13 0.12 Rail transport including lease for rolling stock 4.80 5.42 Port facilities 2.34 2.14 34.58 27.99 Railway capital repayment ($1,133.6M) 6.22 7.40 Railway interest payment ($592.6M) 3.25 7.29 44.05 42.68 Total Direct Operating Cost Total Operating Cost PRE-PRODUCTION CAPITAL EXPENDITURES (US$ MILLIONS) Fire Lake North & Pointe Noire Railway Total Capital in $ MILLIONS Direct Costs Mining Concentrator & FLN Site Infrastructure 687.7 Pointe Noire 106.5 Project Indirect Costs 140.5 Contingency Railway 200.0 Rolling Stock Leasing 13.4 53.2 Engineering, Procurement, Construction & Mgmt. (EPCM) Total Capital in $ MILLIONS 158.2 Owner’s Cost COST AREA 133.7 Indirect Costs COST AREA 114.6 Sub-total 1,394.4 Grand Total (100% of the project) Sub-total 1,607.9 213.4 14
  • 15. Consolidated Fire Lake North Project Schedule 2011 2012 2013 2014 2015 2016 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 CFLN Definition Drilling Scoping Study Updated PEA Metallurgical Results - CFLN, Moire Lake, Oil Can Pre-Feasibility Study Environmental and Social Impact Assessment (ongoing) Community Consultation Oil Can Definition Drilling Planned Feasibility Study Permitting Construction Production Legend: Critical point: Project Schedule will be revised and updated once the feasibility study of the railway solution is confirmed Completed milestones
  • 16. Consolidated Fire Lake North Project Growth Through Development  Prefeasibility Study results released Feb. 7, 2013  Feasibility Study with 20 Mtpa production rate scope underway  West Pit Area East Pit Area West (3500m) & East (2400m) Pits are both synformal fold closures that are open at depth  Don Lake Area Mineral Resource Estimate (MRE) announced on Jan. 9, 2013 (COG 15% FeT): Measured & Indicated Resources 693.5 M tonnes grading 31.5% total iron (FeT) Inferred Resources 521.6 M tonnes grading 30.1% total iron (FeT)  Several de-risking initiatives are underway See www.championironmines.com for reports maps & assays 16
  • 17. Consolidated Fire Lake North Metallurgy Press Release, August 1, 2012     High quality sinter concentrate with very low deleterious elemental content Weight recovery @ 39.9%; no magnetic separation required Liberates at 850 micron (-20 mesh) & produces a 65-66% iron concentrate Assuming a concentrate with 66% Fe ; No magnetic separation circuit required  Alumina is 0.52% versus industry standard of 2%  Silica content is < 5%  Al2O3 : SiO2 ratio of 0.14 versus the upper industry specification limit of 1  This very low alumina to silica ratio is an ideal blending product for steel mills High Grade, Coarse Specular Hematite Quartz Specular Hematite 17
  • 18. Consolidated Fire Lake North Project Economic Projections based on PFS Metrics Assumptions: 1Projections of an expansion plan at CFLN for a second concentrator production line are listed in the table below. This projection of an 18-20 Mtpa production rate of iron concentrate is not NI 43-101 compliant but rather an estimation of mid term potential: IRR = 34.7% NPV (M$) Payback (yrs) 0% $18,441 M 3.9 5% $9,400 M 4.1 8% $6,465 M 4.32 10% $5,081 M 4.4 Discount Rate 2Payback period at an 8% discounted rate is estimated from the production start of the 1st concentrator production line, the payback for the 2nd production line is 1.9 years after it starts based on the additional CAPEX for the 2nd line of US$587M including indirect (mine and concentrator) costs, railway capital repayment and interest. Feasibility Study Objectives: • • • • Potential to integrate a Multi-Users rail solution Reduce CFLN sustaining capital in the economic model. Continue metallurgical test work with the objective of eliminating the second AG mill ($100 million sustaining capital) in year. Continue negotiations with Hydro-Québec to find ways to reduce the $217.5 million participation in sustaining capital for the construction of a new 315 kV power line. • Review iron ore deposits at both CFLN & Oil Can to increase Measured & Indicated Resources and reduce the overall strip ratio. 18
  • 19. Fire Lake North Development Project 19
  • 20. Fire Lake North Development Project 20
  • 21. Oil Can Project Initial Mineral Resource Estimate  Potential for low strip ratio < 1–1.5  972 Mt of iron oxide grading 33.2% at a 15% iron cut-off  924 Mt of mixed iron oxide-silicate mineralization  This deposit is open at depth  Orientation metallurgical tests indicate a relatively coarse liberation grind size  Commercial grade magnetite sinter feed concentrate can be produced  2011 drill program returned long magnetite-hematite iron formation intersections up to 545 metres in length  Inferred Resources drilled on 400 metre sections is completed To view a larger more detailed version of this map please visit: http://www.championironmines.com/vns-site/page-oil_can.html 21
  • 22. Moiré Lake Project Initial Mineral Resource Estimate: March 29, 2012 Mineral Resource Estimate: Arcelor Mittal Property Boundary Indicated Resources: 164 M tonnes grading 30.5% FeT Inferred Resources: 417 M tonnes grading 29.4% FeT  DDH LM11-12: 503 M @ 31% FeT A’  Kilometric synform with hematite & magnetite outcrops at surface  Adjacent to ArcelorMittal Mont-Wright mine A 500 meters 22
  • 23. Moiré Lake Project Infrastructure: Adjacent to Bloom Lake Railway (8km), road, & power 442 Mt @ 30.1% FeT; Zone B: 285 Mt @ 30.1% FeT 500 meters 23
  • 24. Oil Can Project Exploration Upside South & East Zones Section 9800N (Facing North) South Zone OC11-05 OC11-07 East Zone OC11-08 OC11-19 OC11-02 OC11-01 Ovb IF OC11-07 OC11-019 IF 197.2m @ 26.8% incl. 145.5 @ 28.1% 163.1m @ 30.5% OC11-01 190.9m @ 30.6% OC11-05 303.4m @ 34.7% incl. 130.8m @ 36.5% OC11-02 401.5m @ 30.7% incl. 213.5 @ 33.1% OC11-08 545.7m @ 33.7% incl. 442.3 @ 36.4% 200 metres 24
  • 25. Oil Can Project Exploration Upside Central Zone (Facing Northwest) OC11-14 OC11-16 OC11-03 OC11-10 Ovb OC11-014 191.7m @ 28.2% OC11-016 311.4m @ 27.6% incl. 269.0m @ 29.2% OC11-03 224.0m @ 28.1% incl. 176.0m @ 29.0% IF OC11-10 472.2m @ 28.0% incl. 119.6m @ 35.2% 200 metres 25
  • 26. Oil Can Project Exploration Upside North Zone Section 5800E (Facing East) OC11-12 OC11-13 OC11-04 OC11-15 Ovb OC11-09 OC11-012 221.2m @ 25.0% incl. 128.9m @ 28.7% IF OC11-15 OC11-09 292.5m @ 25.8% incl. 113.8m @ 30.4% OC11-04 328.9m @ 31.5% Incl. 111.1m @ 32.9% 141.5m @ 29.2% Incl. 179.5m @ OC11-13 32.8% 414.1m @ 25.1% incl. 139.0m @ 29.5% 200 metres 26
  • 27. Why Invest in Champion Iron Mines?  Robust Economics: (CFLN NPV, US$3.3B @ 8% DCF (PFS Feb. 2013); IRR 30.9%; 3.4 year payback period  12 Projects (755 km2) near 5 operating mines;  5.1 billion tonnes of NI 43-101 compliant resource  Oil Can Deposit: Initial Resource Estimate 1,896 Mt @ 28.7%  High-Quality CFLN concentrate @ 66%Fe, with low impurity levels  Experienced team: Exploration, development, construction, commissioning & operations management  Financed through to feasibility; Favourable tax regime; Political support; & known operating environment 27
  • 28. Fire Lake North Exploration Camp Coarse Specular Hematite in Drill Core Coarse Grained Specular Hematite 28
  • 29. Thank You www.championironmines.com FSE: P02; OTCQX: CPMNF 20 Adelaide Street East, Suite 301, Toronto, ON M5C 2T6 | 416 866 2200 29
  • 30. Global Steel Production Shows Continued Demand for Iron Ore 1,600,000 China’s CAGR* is 9.88% over the last 30 years vs. 2.30% for total global steel production over the same period. 1,400,000 Kilotonnes 1,200,000 1,000,000 China 800,000 Japan 600,000 Rest of the World 400,000 200,000 1980 1985 Source: World Steel Association website * CAGR: Compound Annual Growth Rate 1990 1995 2000 2005 2010 30
  • 31. Labrador Trough Annual Production Iron Ore Production Upside Current Annual Production Future Annual Forecast IOC/RTZ 17 Mtpa + 6 Mtpa 23 Mtpa ArcelorMittal 16 Mtpa + 8 Mtpa 24 Mtpa Cliffs Natural Resources (Wuhan) 12 Mtpa + 8 Mtpa 20 Mtpa 2 Mtpa1 5 Mtpa1 0 50 Mtpa2 Company Labrador Iron Mines Adriana Resources (Wuhan) New Millennium (Tata) 0 4 Mtpa1 24 Mtpa2 2 Mtpa1 Century Iron Mines (Wuhan) 0 Champion Iron Mines Limited 0 ~20 Mtpa Alderon Iron Ore Corp. 0 ~16 Mtpa 47 + 22 Mtpa ~208 Mtpa Total Current & Forecasted Production 1. 2. Direct shipping ore Taconite fine grained iron ore 20 Mtpa2 31
  • 32. Fermont Iron Ore District (“FIOD”) Historically, before 2003, the Fermont & Labrador mining camps produced 33 Mtpa. RTZ/IOC = 17 Mtpa; increased now to 24 ArcelorMittal = 13 Mtpa; increased now to 24 Wabush = 3-4 Mtpa Price “ Marginal Era”: For 30-40 years pre-2003 the price per tonne of concentrate was $15- $30/tonne for 62% Fe, costs per tonne were similar. Current 3 year moving average is $115/tonne (62% Fe) Current Spot Price Average ~$130-135/tonne (Oct. 2013) (62% Fe) 32
  • 34. Advanced Exploration Bellechasse Deposit Harvey Tuttle Project  Deposit located within CFLN   NI 43-101 Resource Estimate: Inferred Resources  estimate; 215 Mt @ 29% Fe; potential for more  Magnetite rich iron formation  Adjacent to Hwy 389  Synform geometry is favorable for open pit mining NI 43-101 Inferred Resource Estimate: 717 Mt @ 25% Fe; magnetite rich iron formation Intersected multiple significant iron formation intervals in 2010 drill program  Total of 13,165 m of drilling completed  Less than 50% of the kilometric scale magnetic anomalies have been tested  25 km W-NW of CFLN  Within conveying distance from CFLN planned concentrator (20-30 km) 34