How to approach complex remediation projects:
some European examples

       Guy Pomphrey – Area Manager USA
       Stany Pensaert – Research & Development Manager
Procuring a Complex Remediation Project

• Procurement of Complex Remediation Projects is
  often not given the attention it deserves
• Badly thought through procurement can lead to:
   •   Unsafe execution
   •   Delays
   •   Poor workmanship
   •   Cost overruns
• These outcomes can of course have far reaching
  consequences for you, your organisation and even
  the wider community



                                                     2
Procuring a Complex Remediation Project


Corby children win High Court birth defects claim

“A group of 18 young people born with deformed hands and
feet after their mothers were allegedly exposed to toxic
materials before their birth have won a group action lawsuit
against Corby Borough Council.”

Daily Telegraph Newspaper UK 29th July 2009




                                                               3
Content of this presentation


• Contractor selection

• New contract forms

• Public Liaison

• Case Studies




                                        4
Contractor selection
Preparing bids is costly – do not waste bidders’ time and money:

•   Preselect a shortlist of no more than 5 companies
•   Only select companies with proven track record
•   Try to use companies with experience and technologies available inhouse –
    too much subcontracting can lead to conflicts and lack of control
•   Provide sufficient information – obvious isn’t it?
•   Allow sufficient time for a meaningful proposal



However money isn’t everything!
Do not use price as the only factor in assessing proposals at least
give the technical proposal a similar weighting or higher – 60% is
common


                                                                           5
Form of Contract
The more risk you pass to the contractor the higher the average
outcome price
• Lump Sum Fixed Price – All risk on contractor and he will price
   accordingly unless he is desperate – then beware!
• Remeasurable priced bill of quantities – quantity risk taken by
   client
• Cost plus fee – all risk on client
• Cost plus fee with target price and risk reward sharing – our
   recommendation – is the best approach

Involve the contractor as early as possible in the remediation
design – with his experience he is the best person to optimise the
process



                                                                     6
NEC Engineering and Construction
              Contract

Design of a new contract form:

•   Simplified and clear structure to:
    • Framework for compensation events, avoiding open-ended claim situations.
    • Minimise incidence of disputes

•   Incentivisation:
     • Foresighted and cooperative management of the interactions between
        parties: collaborative employers-designers-contractors
    •   Reduced risk to employer (cost and time overruns, poor performance)
    •   Reduced risk to contractors (losses)
    •   Mechanism: unforeseen events: “early warning system” and compensation
        events: contractor prices various options to the project manager at the time
        the problem is identified => certainty for cost implications and planning
        implications



                                                                                       7
Public Liaison



Get the public onboard – what you are doing is good!

•   Regular community liaison meetings
•   Regular newsletters/press releases
•   Good quality up to date website
•   Contact person and appropriate respond if any complaints
•   Visitor Centre including viewing
•   Jobs for locals




                                                               8
CASE STUDY 1
Avenue Coking Works Site - United Kingdom
Case Study 1 – The Avenue Coking
Works, Chesterfield UK
               •   Former coking works, located in
                   Chesterfield (UK)

               •   Operated from 1956 to 1992
                    • Production of smokeless fuels
                    • Procession of by-products of
                       coal carbonisation (sulphuric
                       acid, ammonium sulphate, pure
                       benzene and toluene, xylene,
                       naphthalene and other acids
                       and organic compounds)

               •   Heavy contamination of site and
                   adjacent river “Rother”
                    • Surface of 98 ha around the
                       former coking works: saturation
                       with hydrocarbons and tar



                                                         10
Case Study 1 – The Avenue Coking
Works, Chesterfield UK




                  PLANT AREA




                                   11
Case Study 1 – The Avenue Coking
                     Works, Chesterfield UK
NEC Target Price Contract: three Stages; Bid, design and execute.
•   Stage 1 Bid - Design was not fixed at time of RFP

     •    Contractors priced based on a best guess quantity of contaminated soil and sludge taking into account
          the Client’s assumptions.
     •    Contractors had to select appropriate remediation design
     •    Bids were assessed 60% technical quality

•   Stage 2 Design - Successful bidder executed further site investigation and process
    design in order to establish the work scope and a target price in negotiation with Client.
    Risks to be covered by further site investigation and process design:
     •    Impact of lagoons and waste tip
     •    Depth of contamination
     •    Preliminary remediation criteria
     •    Complex pollutant mix and uncertainty on remediation technologies for soil and groundwater.
     •    Final landscaping profiles
     •    Planning applications



Specialised joint venture consortium: DEC – SITA Remediation – Volker Stevin



                                                                                                                  12
Case Study 1 – The Avenue Coking
                Works, Chesterfield UK

NEC Target Price Contract: three Stages; Bid, design and execute.

•   Stage 3 Execution - Payment of cost plus fees

    •   “Open book” accounting

    •   Contractor and client gain from savings
         • Savings split 50% Client – 50% Contractor

    •   Client has small cost overrun risk
         • Cost overrun up to 10% of target Client pays 50%
         • Further cost overruns all paid by Contractor’s JV




                                                                    13
Case Study 1 – The Avenue Coking
            Works, Chesterfield UK

Stage 1: Design phase
“Pragmatical” site investigation.




                                               14
Case Study 1 – The Avenue Coking
               Works, Chesterfield UK

Stage 1: Design phase
Process design




                                                  15
Case Study 1 – The Avenue Coking
                  Works, Chesterfield UK
•   2.6 million yd³ of soils to be excavated

•   Logistical challenge: synchronisation excavations –
    stockpiling – treatment – reuse of various qualities

•   Treatment of the contaminated soil with mobile
    treatment plants:
      • Thermal desorption treatment: 350 000 yd³
      • Separation and soil washing: 420 000 yd³
      • Bioremediation: 100 000 yd³

•   Treatment of the contaminated groundwater at 7500
    gallons/h with a bespoke water treatment plant:
     • Aerobic biologic degradation
     • Chemical oxidation
     • Adsorption



                                                           16
CASE STUDY 2
TOTAL Site - Belgium
Case Study 2: Acid Tar Total – Belgium
Design and Build contract

        Lagoon I:
        Liquid tars


        Lagoon II: Liquid-Paste
        tars and Filtercells




        Lagoon III: Solid and
        Paste tars, Filtercells




                                         18
Case Study 2: Acid Tar Total – Belgium
             Design and Build contract

Some boundary conditions for the remediation design:

•   High potential SO2-emissions from acid tars
•   Live piperack at the dykes of the lagoons
•   High pressure hydrogen and natural gas along the lagoons
•   Approximity of village at 100 meter
•   3 operational petrochemical plants within a radius of 500 m
•   Last but not least…




                                                                  19
Case Study 2: Acid Tar Total – Belgium
                Design and Build contract


Result driven contract
•   Stage 1 Bid - Tendering based on preliminary design by Total
    and Haskoning: Stabilisation/Solidification and on-site storage
    •   Limited knowledge on variability and composition of materials in the lagoons.
    •   Limited knowledge on risks: UXO, sulphur dioxide emissions,…


•   Stage 2 Lot A Design – Further sampling in order to finetune
    process design and manage risks

•   Stage 3 Lot B Full Scale Performance validation

•   Stage 4 Lot C Full scale works


                                                                                        20
Case Study 2: Acid Tar Total – Belgium
                    Design and Build contract
Design phase: lot A contract:

•   Thorough sampling of the acid tars, surface water,
    groundwater,…

•   Bench-scale testing for optimal
    Stabilisation/Solidification mix formulation for acid tar   Design of
    treatment.                                                  acid tar treatment
•   Full-scale pilot testing on small amounts of lagoon         process and plant
    materials for choice of equipment.

•   Bench-scale testing of various water treatment
    options.                                                    Design of
•   Pilot testing water treatment.                              Water treatment
                                                                process and plant
•   Assessment of emissions                Design of
                                           Excavation methodology and
•   Historical research on UXO             mitigation measures


                                                                                     21
Case Study 2: Acid Tar Total – Belgium
               Design and Build contract

Stage 2: Lot A Design
Process design




                                                        22
Case Study 2: Acid Tar Total – Belgium
               Design and Build contract

Stage 2: Lot A Design
Process design




                                                        23
Case Study 2: Acid Tar Total – Belgium
               Design and Build contract

Stage 2: Lot A Design
Process design




                                                        24
Case Study 2: Acid Tar Total – Belgium
               Design and Build contract

Stage 2: Lot A Design
Process design




                                                        25
Case Study 2: Acid Tar Total – Belgium
               Design and Build contract

Stage 2: Lot A Design
Process design




                                                        26
Case Study 2: Acid Tar Total – Belgium
Design and Build contract




                                         27
Case Study 2: Acid Tar Total – Belgium
               Design and Build contract

Stage 2: Lot A Design
Process design




                                                        28
Case Study 2: Acid Tar Total – Belgium
                Design and Build contract

Stage 3: Lot B Full scale performance validation




                                                         29
Case Study 2: Acid Tar Total – Belgium
                Design and Build contract

Stage 4: Lot C Full scale works – April 2006




                                                         30
Case Study 2: Acid Tar Total – Belgium
               Design and Build contract

Stage 4: Lot C Full scale works – May 2007




                                                        31
Case Study 2: Acid Tar Total – Belgium
               Design and Build contract

Stage 4: Lot C Full scale works – March 2009




                                                        32
Case Study 2: Acid Tar Total – Belgium
               Design and Build contract

Stage 4: Lot C Full scale works – September 2009




                                                        33
Conclusions

• Complex remediations projects are a Pandora’s box: a good
   design however results in a flexible and safe working method.

• The best design is made by an expert group gathering various
   disciplines and expertise. “Hands-on” expertise is important.

• Contract forms do exist to formalize a flexible, cost-efficient, and
   optimal cooperation between

   CCC = Client + Consultant + Contractor
   CCC = Consolidated Competence Centre




                                                                         34
Thanks for your attention !




                              35

More Related Content

Similar to New Jersey Seminar

Presentation arcadis 2012 eng
Presentation arcadis 2012 engPresentation arcadis 2012 eng
Presentation arcadis 2012 engARCADIS
 
Présentation ARCADIS
Présentation ARCADISPrésentation ARCADIS
Présentation ARCADIS
mlvermeire
 
Jonathan Atkinson, Environment Agency
Jonathan Atkinson, Environment AgencyJonathan Atkinson, Environment Agency
Jonathan Atkinson, Environment Agency
IES / IAQM
 
RICS FLASH Presentation
RICS FLASH PresentationRICS FLASH Presentation
RICS FLASH Presentation
MarkBradbury
 
01Caroline-Leon-Gary
01Caroline-Leon-Gary01Caroline-Leon-Gary
01Caroline-Leon-GaryLeon Botham
 
Implementation of CE principles in the remediation of a former paper mill site
Implementation of CE principles in the remediation of a former paper mill siteImplementation of CE principles in the remediation of a former paper mill site
Implementation of CE principles in the remediation of a former paper mill site
IES / IAQM
 
Soil management at metrolinx
Soil management at metrolinx Soil management at metrolinx
Soil management at metrolinx
ONEIA
 
Programme Management challenges on the UK Governments Geological Disposal Fac...
Programme Management challenges on the UK Governments Geological Disposal Fac...Programme Management challenges on the UK Governments Geological Disposal Fac...
Programme Management challenges on the UK Governments Geological Disposal Fac...
Association for Project Management
 
CV_Fayle_Mark _Rev.1
CV_Fayle_Mark _Rev.1CV_Fayle_Mark _Rev.1
CV_Fayle_Mark _Rev.1Mark Fayle
 
Smart Construction by Leopardo
Smart Construction by LeopardoSmart Construction by Leopardo
Smart Construction by Leopardo
leobuild
 
Qm Company Presentation 2011 V2
Qm Company Presentation 2011 V2Qm Company Presentation 2011 V2
Qm Company Presentation 2011 V2
Robert Wagenveld
 
Co re skills gap research, andy ainsworth,room4 consulting
Co re skills gap research, andy ainsworth,room4 consultingCo re skills gap research, andy ainsworth,room4 consulting
Co re skills gap research, andy ainsworth,room4 consultingjennieplink
 
CoRE skills gap research - by Andy Ainsworth, room4 consulting
CoRE skills gap research - by Andy Ainsworth, room4 consultingCoRE skills gap research - by Andy Ainsworth, room4 consulting
CoRE skills gap research - by Andy Ainsworth, room4 consultingsustainableCoRE
 
Commercial sites and the delivery of sustainable drainage
Commercial sites and the delivery of sustainable drainageCommercial sites and the delivery of sustainable drainage
Commercial sites and the delivery of sustainable drainageACO Technologies plc
 
Healthcheck your workspace skanska go green low carbon workshop 25 july 2017
Healthcheck your workspace skanska go green low carbon workshop 25 july 2017Healthcheck your workspace skanska go green low carbon workshop 25 july 2017
Healthcheck your workspace skanska go green low carbon workshop 25 july 2017
The Future Economy Network
 
Breaking new ground – Farming and forestry providing new opportunities for Cl...
Breaking new ground – Farming and forestry providing new opportunities for Cl...Breaking new ground – Farming and forestry providing new opportunities for Cl...
Breaking new ground – Farming and forestry providing new opportunities for Cl...
EMEX
 
Programme of Activities (PoA's)
Programme of Activities (PoA's) Programme of Activities (PoA's)
Programme of Activities (PoA's)
ACX
 
Project ppt riverside condo
Project ppt riverside condoProject ppt riverside condo
Project ppt riverside condo
SAIFULLAH MAHMUD
 
Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...
Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...
Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...
irvan septyan mulyana
 

Similar to New Jersey Seminar (20)

Presentation arcadis 2012 eng
Presentation arcadis 2012 engPresentation arcadis 2012 eng
Presentation arcadis 2012 eng
 
Présentation ARCADIS
Présentation ARCADISPrésentation ARCADIS
Présentation ARCADIS
 
Jonathan Atkinson, Environment Agency
Jonathan Atkinson, Environment AgencyJonathan Atkinson, Environment Agency
Jonathan Atkinson, Environment Agency
 
RICS FLASH Presentation
RICS FLASH PresentationRICS FLASH Presentation
RICS FLASH Presentation
 
01Caroline-Leon-Gary
01Caroline-Leon-Gary01Caroline-Leon-Gary
01Caroline-Leon-Gary
 
Implementation of CE principles in the remediation of a former paper mill site
Implementation of CE principles in the remediation of a former paper mill siteImplementation of CE principles in the remediation of a former paper mill site
Implementation of CE principles in the remediation of a former paper mill site
 
Soil management at metrolinx
Soil management at metrolinx Soil management at metrolinx
Soil management at metrolinx
 
Programme Management challenges on the UK Governments Geological Disposal Fac...
Programme Management challenges on the UK Governments Geological Disposal Fac...Programme Management challenges on the UK Governments Geological Disposal Fac...
Programme Management challenges on the UK Governments Geological Disposal Fac...
 
CV_Fayle_Mark _Rev.1
CV_Fayle_Mark _Rev.1CV_Fayle_Mark _Rev.1
CV_Fayle_Mark _Rev.1
 
Kestrel pres feb 13, 13
Kestrel pres feb 13, 13Kestrel pres feb 13, 13
Kestrel pres feb 13, 13
 
Smart Construction by Leopardo
Smart Construction by LeopardoSmart Construction by Leopardo
Smart Construction by Leopardo
 
Qm Company Presentation 2011 V2
Qm Company Presentation 2011 V2Qm Company Presentation 2011 V2
Qm Company Presentation 2011 V2
 
Co re skills gap research, andy ainsworth,room4 consulting
Co re skills gap research, andy ainsworth,room4 consultingCo re skills gap research, andy ainsworth,room4 consulting
Co re skills gap research, andy ainsworth,room4 consulting
 
CoRE skills gap research - by Andy Ainsworth, room4 consulting
CoRE skills gap research - by Andy Ainsworth, room4 consultingCoRE skills gap research - by Andy Ainsworth, room4 consulting
CoRE skills gap research - by Andy Ainsworth, room4 consulting
 
Commercial sites and the delivery of sustainable drainage
Commercial sites and the delivery of sustainable drainageCommercial sites and the delivery of sustainable drainage
Commercial sites and the delivery of sustainable drainage
 
Healthcheck your workspace skanska go green low carbon workshop 25 july 2017
Healthcheck your workspace skanska go green low carbon workshop 25 july 2017Healthcheck your workspace skanska go green low carbon workshop 25 july 2017
Healthcheck your workspace skanska go green low carbon workshop 25 july 2017
 
Breaking new ground – Farming and forestry providing new opportunities for Cl...
Breaking new ground – Farming and forestry providing new opportunities for Cl...Breaking new ground – Farming and forestry providing new opportunities for Cl...
Breaking new ground – Farming and forestry providing new opportunities for Cl...
 
Programme of Activities (PoA's)
Programme of Activities (PoA's) Programme of Activities (PoA's)
Programme of Activities (PoA's)
 
Project ppt riverside condo
Project ppt riverside condoProject ppt riverside condo
Project ppt riverside condo
 
Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...
Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...
Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...
 

New Jersey Seminar

  • 1. Mid-Atlantic Contaminated Sediment/Soils Symposium March 24, 2010 Liberty Harbor Restaurant, Jersey City, NJ How to approach complex remediation projects: some European examples Guy Pomphrey – Area Manager USA Stany Pensaert – Research & Development Manager
  • 2. Procuring a Complex Remediation Project • Procurement of Complex Remediation Projects is often not given the attention it deserves • Badly thought through procurement can lead to: • Unsafe execution • Delays • Poor workmanship • Cost overruns • These outcomes can of course have far reaching consequences for you, your organisation and even the wider community 2
  • 3. Procuring a Complex Remediation Project Corby children win High Court birth defects claim “A group of 18 young people born with deformed hands and feet after their mothers were allegedly exposed to toxic materials before their birth have won a group action lawsuit against Corby Borough Council.” Daily Telegraph Newspaper UK 29th July 2009 3
  • 4. Content of this presentation • Contractor selection • New contract forms • Public Liaison • Case Studies 4
  • 5. Contractor selection Preparing bids is costly – do not waste bidders’ time and money: • Preselect a shortlist of no more than 5 companies • Only select companies with proven track record • Try to use companies with experience and technologies available inhouse – too much subcontracting can lead to conflicts and lack of control • Provide sufficient information – obvious isn’t it? • Allow sufficient time for a meaningful proposal However money isn’t everything! Do not use price as the only factor in assessing proposals at least give the technical proposal a similar weighting or higher – 60% is common 5
  • 6. Form of Contract The more risk you pass to the contractor the higher the average outcome price • Lump Sum Fixed Price – All risk on contractor and he will price accordingly unless he is desperate – then beware! • Remeasurable priced bill of quantities – quantity risk taken by client • Cost plus fee – all risk on client • Cost plus fee with target price and risk reward sharing – our recommendation – is the best approach Involve the contractor as early as possible in the remediation design – with his experience he is the best person to optimise the process 6
  • 7. NEC Engineering and Construction Contract Design of a new contract form: • Simplified and clear structure to: • Framework for compensation events, avoiding open-ended claim situations. • Minimise incidence of disputes • Incentivisation: • Foresighted and cooperative management of the interactions between parties: collaborative employers-designers-contractors • Reduced risk to employer (cost and time overruns, poor performance) • Reduced risk to contractors (losses) • Mechanism: unforeseen events: “early warning system” and compensation events: contractor prices various options to the project manager at the time the problem is identified => certainty for cost implications and planning implications 7
  • 8. Public Liaison Get the public onboard – what you are doing is good! • Regular community liaison meetings • Regular newsletters/press releases • Good quality up to date website • Contact person and appropriate respond if any complaints • Visitor Centre including viewing • Jobs for locals 8
  • 9. CASE STUDY 1 Avenue Coking Works Site - United Kingdom
  • 10. Case Study 1 – The Avenue Coking Works, Chesterfield UK • Former coking works, located in Chesterfield (UK) • Operated from 1956 to 1992 • Production of smokeless fuels • Procession of by-products of coal carbonisation (sulphuric acid, ammonium sulphate, pure benzene and toluene, xylene, naphthalene and other acids and organic compounds) • Heavy contamination of site and adjacent river “Rother” • Surface of 98 ha around the former coking works: saturation with hydrocarbons and tar 10
  • 11. Case Study 1 – The Avenue Coking Works, Chesterfield UK PLANT AREA 11
  • 12. Case Study 1 – The Avenue Coking Works, Chesterfield UK NEC Target Price Contract: three Stages; Bid, design and execute. • Stage 1 Bid - Design was not fixed at time of RFP • Contractors priced based on a best guess quantity of contaminated soil and sludge taking into account the Client’s assumptions. • Contractors had to select appropriate remediation design • Bids were assessed 60% technical quality • Stage 2 Design - Successful bidder executed further site investigation and process design in order to establish the work scope and a target price in negotiation with Client. Risks to be covered by further site investigation and process design: • Impact of lagoons and waste tip • Depth of contamination • Preliminary remediation criteria • Complex pollutant mix and uncertainty on remediation technologies for soil and groundwater. • Final landscaping profiles • Planning applications Specialised joint venture consortium: DEC – SITA Remediation – Volker Stevin 12
  • 13. Case Study 1 – The Avenue Coking Works, Chesterfield UK NEC Target Price Contract: three Stages; Bid, design and execute. • Stage 3 Execution - Payment of cost plus fees • “Open book” accounting • Contractor and client gain from savings • Savings split 50% Client – 50% Contractor • Client has small cost overrun risk • Cost overrun up to 10% of target Client pays 50% • Further cost overruns all paid by Contractor’s JV 13
  • 14. Case Study 1 – The Avenue Coking Works, Chesterfield UK Stage 1: Design phase “Pragmatical” site investigation. 14
  • 15. Case Study 1 – The Avenue Coking Works, Chesterfield UK Stage 1: Design phase Process design 15
  • 16. Case Study 1 – The Avenue Coking Works, Chesterfield UK • 2.6 million yd³ of soils to be excavated • Logistical challenge: synchronisation excavations – stockpiling – treatment – reuse of various qualities • Treatment of the contaminated soil with mobile treatment plants: • Thermal desorption treatment: 350 000 yd³ • Separation and soil washing: 420 000 yd³ • Bioremediation: 100 000 yd³ • Treatment of the contaminated groundwater at 7500 gallons/h with a bespoke water treatment plant: • Aerobic biologic degradation • Chemical oxidation • Adsorption 16
  • 17. CASE STUDY 2 TOTAL Site - Belgium
  • 18. Case Study 2: Acid Tar Total – Belgium Design and Build contract Lagoon I: Liquid tars Lagoon II: Liquid-Paste tars and Filtercells Lagoon III: Solid and Paste tars, Filtercells 18
  • 19. Case Study 2: Acid Tar Total – Belgium Design and Build contract Some boundary conditions for the remediation design: • High potential SO2-emissions from acid tars • Live piperack at the dykes of the lagoons • High pressure hydrogen and natural gas along the lagoons • Approximity of village at 100 meter • 3 operational petrochemical plants within a radius of 500 m • Last but not least… 19
  • 20. Case Study 2: Acid Tar Total – Belgium Design and Build contract Result driven contract • Stage 1 Bid - Tendering based on preliminary design by Total and Haskoning: Stabilisation/Solidification and on-site storage • Limited knowledge on variability and composition of materials in the lagoons. • Limited knowledge on risks: UXO, sulphur dioxide emissions,… • Stage 2 Lot A Design – Further sampling in order to finetune process design and manage risks • Stage 3 Lot B Full Scale Performance validation • Stage 4 Lot C Full scale works 20
  • 21. Case Study 2: Acid Tar Total – Belgium Design and Build contract Design phase: lot A contract: • Thorough sampling of the acid tars, surface water, groundwater,… • Bench-scale testing for optimal Stabilisation/Solidification mix formulation for acid tar Design of treatment. acid tar treatment • Full-scale pilot testing on small amounts of lagoon process and plant materials for choice of equipment. • Bench-scale testing of various water treatment options. Design of • Pilot testing water treatment. Water treatment process and plant • Assessment of emissions Design of Excavation methodology and • Historical research on UXO mitigation measures 21
  • 22. Case Study 2: Acid Tar Total – Belgium Design and Build contract Stage 2: Lot A Design Process design 22
  • 23. Case Study 2: Acid Tar Total – Belgium Design and Build contract Stage 2: Lot A Design Process design 23
  • 24. Case Study 2: Acid Tar Total – Belgium Design and Build contract Stage 2: Lot A Design Process design 24
  • 25. Case Study 2: Acid Tar Total – Belgium Design and Build contract Stage 2: Lot A Design Process design 25
  • 26. Case Study 2: Acid Tar Total – Belgium Design and Build contract Stage 2: Lot A Design Process design 26
  • 27. Case Study 2: Acid Tar Total – Belgium Design and Build contract 27
  • 28. Case Study 2: Acid Tar Total – Belgium Design and Build contract Stage 2: Lot A Design Process design 28
  • 29. Case Study 2: Acid Tar Total – Belgium Design and Build contract Stage 3: Lot B Full scale performance validation 29
  • 30. Case Study 2: Acid Tar Total – Belgium Design and Build contract Stage 4: Lot C Full scale works – April 2006 30
  • 31. Case Study 2: Acid Tar Total – Belgium Design and Build contract Stage 4: Lot C Full scale works – May 2007 31
  • 32. Case Study 2: Acid Tar Total – Belgium Design and Build contract Stage 4: Lot C Full scale works – March 2009 32
  • 33. Case Study 2: Acid Tar Total – Belgium Design and Build contract Stage 4: Lot C Full scale works – September 2009 33
  • 34. Conclusions • Complex remediations projects are a Pandora’s box: a good design however results in a flexible and safe working method. • The best design is made by an expert group gathering various disciplines and expertise. “Hands-on” expertise is important. • Contract forms do exist to formalize a flexible, cost-efficient, and optimal cooperation between CCC = Client + Consultant + Contractor CCC = Consolidated Competence Centre 34