This document provides a sequence of work for a railway project including:
1. Removing an earlier installed temporary track and laying plain track to connect on line 10.
2. In a subsequent block, removing another earlier installed temporary track and plain track.
3. Continuing to lay permanent track on sections FL07, FL08 and FL09 to connect lines 11, 12 and 13.
M370-DTP-558_3 Rev A - Plan for Installing PB31- PB35 and PB37 - Padang Besar (Sheets 4 of 5)
1. N
4.759
FP
UPMAIN
DOWNMAIN
EM02
FL01
FL07
FL10
RELEASE LINE (RL)
EM03
TS04
RELEASE
LINE
(RL) 379m
EM01 (329m)
EM02 (357m)
EM03 (350m)
EM04 (350m)
AUTHORISED
W
ALKING
ROUTE
UPLOOP
(660m)
LINE 13
LINE 12
LINE 11
LINE 10
LINE
9
LINE
8
LINE
7
LINE
6
LINE
5
LINE
4
1.51
FP
FP
FP
FP
FP
FP
FP
(CAL 361 m)
(CAL 413 m)
(CAL 600 m)
(CAL 580 m)
(CAL 435 m)
(CAL 456 m)
(CAL 581 m)
(CAL 525 m)
(CAL 525 m)
FP
(13875-D)
MMC - GAMUDA JOINT VENTURE SDN BHD KERETAPI TANAH MELAYU BERHAD
(225943-T)(414492-M)
PROJEK LANDASAN KERETAPI BERKEMBAR ELEKTRIK
DARI IPOH KE PADANG BESAR
KERAJAAN MALAYSIA
SEQUENCE OF WORK:
1. REMOVE EARLIER INSTALLED TTO AT 1 ON LINE NO. 10 AND
PLAIN TRACK AND LAY PLAIN TRACK TO CONNECT.
2. IN SUBSEQUENCE BLOCK, REMOVE EARLIER INSTALLED TTO
AT 2 AND PLAIN TRACK.
3. CONTINUE LAY PERMANENT TRACK ON FL07, FL08 AND FL09 TO
CONNECT LINE NO. 11, 12 AND 13.