This document shows a Gantt chart comparing the scheduled and actual completion dates for various milestones of a construction project from 2006 to 2008. The baseline schedule estimated substantial completion by November 13, 2006 but there were a number of delays pushing the completion dates back. The delays can be grouped into six periods and were caused by issues like start delays, production problems, design defects, fire rating impacts requiring rework, and slow drywall installation. The project was ultimately completed on June 6, 2008, over a year later than the original baseline schedule.