Refurbishment5*Inter-ContinentalHotel Madrid
The $40m project involved the full renovation of 300 guest rooms, Hotel facilities and all back of
house areas. Health and Safety was paramount in all phased construction activities. The
original building had been developed as 3 separate apartment buildings in 1940. A four phase
redevelopment plan was agreed consisting of mock up rooms, new lifts, enabling works and
then 3 separate room phases. The planning aimed to minimize operational disruption, utilize low
occupancy periods to maximize work and keep the hotel at minimum 65% occupancy
throughout the 3 year construction period.
Major risks were identified - change orders due to unknown base build condition, choice of
contractor/sub-trades, material delays, management of deficiencies, missing operational
windows (e.g. low summer occupancy), noise/vibration/dust, design coordination to meet
schedule requirements and importantly delays in client sign off. Risks were allocated, managed
and reported on and risk management came second on all meeting agendas after Health and
Safety.
Brief included the tender process and contract development for Architect, Engineers, Interior
Designer and Construction Manager.
All FF&E (over 50 suppliers) and OS&E was identified, procured, expedited and delivered to
local warehouse in Madrid. Sub trades installed as required.
Over 600 change orders were managed during the construction process, 25 provisional sum
items were identified at tender phase – as the project developed the provisional sum items were
reviewed and included in the ongoing scope growth, always maintaining the agreed overall
budget levels.
Daily site meetings with the Construction Manager and the Project Manager, weekly meetings
between the PM and Hotel Operations, the identification of the Hotel Representative all
contributed to the success of the project.
The project was the largest refurbishment in Inter-Continental’s history in Europe. It was
completed 2% under the approved CAPEX and all phases were completed on time to a
extremely high quality.
Inter-Continental Hotel
Madrid, Spain
Client: Bass Hotels & Resorts
Location: Madrid, Spain
Building Area: 259,000 SF
Project Cost: $40,000,000
Completion: 2004
Contract Type: CM / Stipulated Sum
Scope of Services:
Project Management
Cost Management
FF&E, OS&E Procurement

iNTERCONTINENTAL - PROJECT PAGE

  • 1.
    Refurbishment5*Inter-ContinentalHotel Madrid The $40mproject involved the full renovation of 300 guest rooms, Hotel facilities and all back of house areas. Health and Safety was paramount in all phased construction activities. The original building had been developed as 3 separate apartment buildings in 1940. A four phase redevelopment plan was agreed consisting of mock up rooms, new lifts, enabling works and then 3 separate room phases. The planning aimed to minimize operational disruption, utilize low occupancy periods to maximize work and keep the hotel at minimum 65% occupancy throughout the 3 year construction period. Major risks were identified - change orders due to unknown base build condition, choice of contractor/sub-trades, material delays, management of deficiencies, missing operational windows (e.g. low summer occupancy), noise/vibration/dust, design coordination to meet schedule requirements and importantly delays in client sign off. Risks were allocated, managed and reported on and risk management came second on all meeting agendas after Health and Safety. Brief included the tender process and contract development for Architect, Engineers, Interior Designer and Construction Manager. All FF&E (over 50 suppliers) and OS&E was identified, procured, expedited and delivered to local warehouse in Madrid. Sub trades installed as required. Over 600 change orders were managed during the construction process, 25 provisional sum items were identified at tender phase – as the project developed the provisional sum items were reviewed and included in the ongoing scope growth, always maintaining the agreed overall budget levels. Daily site meetings with the Construction Manager and the Project Manager, weekly meetings between the PM and Hotel Operations, the identification of the Hotel Representative all contributed to the success of the project. The project was the largest refurbishment in Inter-Continental’s history in Europe. It was completed 2% under the approved CAPEX and all phases were completed on time to a extremely high quality.
  • 2.
    Inter-Continental Hotel Madrid, Spain Client:Bass Hotels & Resorts Location: Madrid, Spain Building Area: 259,000 SF Project Cost: $40,000,000 Completion: 2004 Contract Type: CM / Stipulated Sum Scope of Services: Project Management Cost Management FF&E, OS&E Procurement