This document outlines a work breakdown structure (WBS) for a project with a total budget of Rp 550,000,000 over 12 months. It includes costs for project management staff like a project manager, business analyst, and programmer totaling Rp 450,000,000. Hardware such as devices and servers will cost Rp 45,000,000. Software like Windows, Office, and SQL Server licenses are Rp 20,000,000. Testing is budgeted at Rp 17,500,000 across the months. A reserve of Rp 17,500,000 is also allocated to account for potential changes or issues. The monthly costs vary between Rp 101,450,000 to Rp 54,