Agenda

Introduction


PPP in Central Eastern Europe – update


PPP in Poland


Summary
Agenda

Introduction


PPP in Central Eastern Europe – update


PPP in Poland


Summary
PPP in CEE in particularly needed due to:
•   Great scale of negligence in the field of public services during real socialism,

•   Strong and increasing public deficits and public budgets limitations,

•   Increasing expectations of the societies regarding the infrastructure and public

    services,

•   Poor qualifications of public officials in regarding the infrastructural projects

    management and operation,

•   Politicisation of privatisation process as a part of political games – negative

    connotations,

•   The challenges, which public authorities in EU countries are facing, regarding the

    consumption of EU funds.
Agenda

Introduction


PPP in Central Eastern Europe – update


PPP in Poland


Summary
Czech Republic



     • In September 2011 Ministry of Regional Development concluded a concession
       contract with 5 concessionaires who were commissioned with creating and
       operating the so-called electronic marketplaces (EMP) – first PPP project on
       the central level,
     • On municipal level, a number of PPP projects in operation phase – water
       management, football stadium, pool, bus-stops, city-lightning and three senior
       houses. Demand for PPP on the municipal level is increasing: e.g. PPP
       project of public transport in Pilsen are under preparation. Most of these projects
       are based on availability fee,
     • The only project under preparation on central level is 19 km long part of
       highway D3
     • Changes in the Public Procuement Act has been adopted by the Czech
       Parliament in November 2011. New rules on the transparency of contracts
       and subcontractors in the public tendering procedure entered into force 1st
       April 2012.




Special thanks to Mr. Vladimír Sloup, Asociace PPP, Czech Republic
Hungary


 There is no specific PPP legislation, PPP Projects are implemented through Public
  Procurement Act, Municipal Act and Civic Code,
 Public Finance Act determines if the value of the PPP project is exceeding 180 mln euro
  there has to be an acceptance from the Parliament, below 180 mln euro – acceptance
  form the Government is necessary,
 Update of the Public Finance Act in 2010 regulated the issue of off-the-balance sheet
  treatment of PPP projects,
 On the state level, PPP projects are implemented mainly by:
• Ministry of Economy and Transport (M5, M6 highways),
• Ministry of Justice (2 prisons),
• National Sports Office (swimming pools, sport halls),
• Ministry of Education and Culture (students' hostels, Palace of Arts).
Majority of the projects are implemented as DBFO model,
 Future PPP sectors:
• National railway network – high speed rail,
• National toll payment system,
• Education – secondary schools,
• Court buildings – reconstruction and operation,
• Healthcare – hospitals,
• Sport facilities – stadiums, watersport centre.
Bulgaria


   • A draft of a PPP Act was developed in 2011. The draft was approved by the
     Council of Ministers in September 2011 and is currently being considered by the
     National Parliament. By the end of April 2012 the PPP Act will be adopted,
   • The aim of the Act is to give clear definition and set clear rules for doing PPP,
   • 2007-2010 there was on average only one infrastructure concession contract
     signed per year – all of them for relatively small river ports,
   • One concession contract was signed in 2011 - for port infrastructure on the
     Black Sea - Concession for Port Bourgas East 2, contract period is 35 years,
     starting from 01.01.2012, the value of the project is app.100 mln euro,
   • The transport ministry, in cooperation with the ministry of finance, continues its
     work on preparation of several more concessions in the area of airports, sea
     and river ports as well as railway stations,
   • Pleven is currently undertaking a water PPP with IFC acting as transaction
     leader,
   • The EIB alongside a banking consortium (Societe Generale Expressbank,
     Elana Holding, Elana Investment, Balkan Advisors) has established a €56.4
     million Urban Development Fund to invest in PPPs and infrastructure in 6
     Bulgarian cities (Burgas, Pleven, Plovdiv, Ruse, Stara Zagora, Varna).

Special thanks to Mr. Galin Zhelev and the Ministry of Finance of Bulgaria, Real Sector Finance Directorate (PPP unit)
Romania


      •Till the end of 2010 – did not have any legal act dedicated directly to PPP,
      •PPP Act had been resolved by the Parliament in September 2010 and came into
   force in October 2010, however the European Commission was not satisfied with
   the framework as it did not mesh with European procurement laws and
   encouraged Romania to redraft it – necessary changes were introduced in October
   2011,
      •Central Unit for Coordination of the PPP was established in 2011,
      •Regardless the legislation, the National Strategy for PPP (in regarding PPP project
   pipeline, good practices, risk structures, mechanisms of payment, ect.) has been
   implemented by the Government, (the Strategy was prepared in cooperation with
   European PPP Expertise Centre JASPERS initiative),
      •EBRD has adopted a new 3-year strategy for Romania with a key objective being
   the greater use of PPP and privatisations in the country. Key sector interest: water,
   waste, roads, rail, district heating,
      •Implemented PPPs: road infrastructure, waste management, airport modernization,
   construction of Metroline 7 in Bucharest,
      •PPP opportunities in the following sectors: healthcare, prisons, energy,
   environment, transport, road infrastructure (Bucharest Bypass South Section &
   Comarnic-Brasov Motorway)

Special thanks to Mr.s. Antonina Petrescu, PPP Coordinator, Louis Berger - PPP Unit. Regional Office for Central and Eastern Europe
Slovak Republic

•    Slovakia’s centre-left opposition SMER stormed to an unprecedented (the best result for any party
     since the independence in 1993) victory in parliamentary elections in March 2012 and will rule alone,
•    The new goverment seems to be enthusiastic in terms of PPP and restart some of the PPP
     projects scrapped by the outgoing government,
•    One project is about to be finished on the central level – Highway R1,
•    On the municipal level: 2 water management projects in operational stage (Trencin and Banska
     Bystrica),
•    Plans for projects: construction of broad-gauge rail from Kosice to Bratislava. (probably it will be
     part of new governments program), road projects (many plans in the national level, but it depends
     on new government).


                                 Republic of Slovenia

       •Public-private partnerships are regulated by PPP Act adopted in 2006,
       •PPP has been used mainly at the local level (municipalities) in e.g. social housing,
    kindergartens, waste management, sports infrastructure, cultural buildings, parking garages,
    public lightning and photovoltaic,
       •step-by-step PPP good practice has been developed,
       •On the central level there have been no significant PPP projects,
       •PPP projects pipeline should be developed,
       •Due to a small size of PPP projects on local level and absence of central PPP projects,
    Slovenia has not been an interesting case for foreign investors so far.
Special thanks to Mr. Michal Považan, Slovak PPP Association, Slovak Republic and Mrs. Petra Ferk, Institute for PPP, Slovenia
Moldova


        •In 2008 the Law on public-private Partnership has been adopted,
        •PPP projects pipeline prepared by the goverment and PPP Unit is about to be
  introduced in the first half of 2012,
        •The National Council of PPP (deputy prime-minister, ministers, NGO’s,
  investment banks) first meeting is about to be organized in the first half of 2012,
        •The city of Chisinau has approved a €11.7 million loan from the EBRD to fund
  various PPP projects for the modernisation of the city's street infrastructure
  (roads, parkings, pavements, street lighting). The tender for the project is expected to
  begin after May 2012 with works planned for the second half of 2012,
        •Implemented PPP projects: 2 on central level (healthcare, ICT) and 12 on local
  level (healthcare, waste management, culture),
        •PPP projects in preparation: 33 on central level (carparks, social infrastructure,
  airport, sport infrastructure, ICT, road infrastructure) and 57 on local level
  (healthcare, waste management, road infrastructure).

Special thanks to Mr. Ion Potlog, Head of the PPP Unit, Public Property Agency, Ministry of Economy of Republic of Moldova
Lithuania


    Concession Law adopted in 1996, PPP Law in 2009, PPP Unit established in 2010,
    In 2010 there was a program introduced by the Government to boost PPP in priority sectors:
     transport, education, social housing, public order and safety,
    5 PPP Pilot Projects have been initiated in 2010 – social housing, education (secondary
     school), transport (bypass), safety (prison) and public order (police station). Pilot PPPs are
     slow in process, but they creates concrete background with minimum risk;
    More than 40 PPP projects so far (mainly service concessions),
    4 prison projects are under discussion to be procured as 25 year DBFOT contracts:
•    Vilnius              €34 million (£28m $45m)        holding 1,620 inmates
•    Klaipeda             €21 million (£17,5m $28m)      holding 800 inmates
•    Panevežys            €17 million (£14m $22,5m)      holding 400 inmates
•    Šiauliai             €35 million (£29m $46,5m)      holding 1,180 inmates
Each prison will be procured separately in the late 2012.
 The Capital, Vilnius is preparing tender documents to procure a €25 million upgrade,
  operation and maintenance for its street lighting through a PPP. 19-year DBFOM contract is to
  cover 691km of city streets. Project is supposed to be launched at the end of Q3 2012,
 Vilnius – Utena 61,8 km road reconstruction to launch IVQ 2012, DBFO, 35 mln EUR, 25 years,
 Expansion of 34,5 km of 1st Trans-European Corridor E65 to launch in I Q 2015,
  DBFO, 100 mln EUR 25 years,
 15 potential PFI-type projects for social infrastructure - scheduled for min 15 - max 25 years.

Special thanks to Mr. Tadas Jagminas, Invest Lithuania
Estonia

       There is no specific PPP Law, all PPP are done according to Public Procurment,
       Lack of clear PPP policy framework/strategy or PPP Project Pipeline,
       No centralized PPP development - public authority has autonomy to decide on PPP,
       PPP sectors of interest: education (project in Tallinn – 18 schools renovated), municipal
 administrative buildings, social housing.
   PPP project on the central level – headquaters for: State Tax Authority and Statistical
 Bureau,
   There have been discussion mainly from the private sector discussing opportunities
 associated with PPP in other sectors, but public authorities are rather passive in this issue


                                Latvia

      There was PPP Action Plan 2006-2009, created in 2005,
      PPP Law came into force in 2009,
      Latvia is currently emerging from the deepest recession,
      There have been few PPP projects but public authorities are prudent,
      Concessions are allowed but for other types of PPP there should be accept from Ministry
       of Finance,
      There have been more than 60 PPP agreements in force (80% concessions),
      Main PPP sectors: transport, education, healthcare, water/waste, justice/courts,
Special thanks to Mr. Lauri Henno, U.S. Real Estate Management, Estonia
Ukraine

 •     PPP Law was adopted in 2010 and the by-laws on its implementation – in 2011, but till present
       there were no project started using these procedures; In March 2012 the draft law on
       incorporation of changes to the PPP law was registered in the Ukrainian Parliament,
 •     Opportunity to initiate PPP projects by the private sector,
 •     PPP sectors: transport, social housing, water management, solid waste, sports & leisure,
 •     Most active regions: Kyiv region, Donetsk region, Zaporizhzhia, Mykolayiv,
 •     Competition between operators/investors is relatively low,
 •     Among the positive moments that witness about speeding up of PPP in Ukraine is announcement of
       competition for consultant selection for implementation of metro construction in form of PPP.



                                 Belarus

•     There is a clear message from the President and the Government to establish and develop
      effective PPP mechanism in the country,
•     Belarusian PPP Law had been drafted and it has been assessed by UNECE Experts of the UN
      Economic Commission for Europe, action plan will be prepared on a basis of preliminary
      report,
•     Necessary conditions for implementing PPP projects in Belarus are being considered, including the
      establishment of a center of PPP expertise and training of qualified experts,
•     Current needs in the economic and social sectors are enormous – PPP could be applied,
•     PPP Pilot Project is also considered to be introduced.

Special thanks to Mrs. Irina Zapatrina, Chairman of the Board at Ukrainian PPP Center and Mr. Dzmitry Berazouski, Executive Director of the Coordinating Unit for the
European Union's Tacis Programme in the Republic of Belarus
Croatia


   • Croatia hopes to gain full EU membership in 2013,
   • PPP projects implemented in road infrastructure, education, sports and utility,
   • Only one signed PPP project in last 4 years – Zagreb airport (200 mln euro),
   • Sector of interest: energy, healthcare, ports, energy efficiency in public buildings,
         justice,



                                 Kosovo


        •Infrastructure gap for approximately 3 billion euro (in the next 3-5 years),
        •Main sectors in which private sector could participate: transport, energy, ICT,
        •PPP Law is investor-friendly in accordance with intenrational PPP best practice,
        •PPP              Inter-ministerial                       Steering                Committee                     and           Centralized     PPP   Unit
   -Partnerships Kosovo have been created,

Special thanks to Mr. Saša Marenjak, Prof.dr.sc. at PPP Centar, Croatia and Mrs. Nora Bakali Legal Advisor, Public Private Partnership Unit, kosovo
Serbia


 • In 2011 there was a new Law on PPP and Concessions introduced, (e.g new
    law distinguishes between institutional and contractual PPP),
 • The Government seeks to attract €4 billion of investments into local
    infrastructure through PPP over the next decade.



               Macedonia


  •Special Law on PPP and Concessions adopted in 2007,
  •Few positive experiences with PPP in the past (e.g. airports under
concession),
  •Several PPP projects in Skopje: amusement park, administrative facility and car
park, waste facility.
Albania

•       EBRD alongside the city of Tirana in Albania is preparing a feasibility study on procuring a new
        public transport terminal on a DBFOT basis,
•       The terminal will be situated on an 85,000m2 plot provided by the city and will consist of: bus
        terminals, tram/train station, parking and retail,
•       The contract will have a 20-year plus concession and will be opened as an international tender.
        The EBRD will look to help finance the project with the winning bidder.


                      Bosnia and Herzegovina


    •    PPP Law adopted in 2009, the cooperation model between public and private sector is a
         relatively new model, where market is still in the early stages,
    •    PPP sectors of interest: power facilities, recycling facilities, water and waste management,
         education, healthcare,transport.


                      Montenegro

•       PPP is regulated by Law on participation of private sector in the procurement of public services and the
        Law on Concessions in 2009,
•       Sectors of interest: tourism, energy, roads.
•       Local municipalities interested in PPP: Podgorica, Budva,
Agenda

Introduction


PPP in Central Eastern Europe – update


PPP in Poland


Summary
First PPP Act

                            Public-Private Partnership Act

                                           June 2005
No PPP projects implemented!

Reasons for failure: bad political climate, lack of knowledge about PPP, strict regulations?




  New PPP regulations – came into force in February 2009

                      The Public-Private Partnership Act
                                     19 December 2008

          Concession for construction works and services Act
                                               ;


                                       9 January 2009
Number of PPPs and Concessions announcements in Poland 2009, 2010, 2011


                                              + 47 %
                                              +47%
               PPPs
                                                                         – 31 %




• The number of announcements, on a basis of PPP Act and concession for works and services Act,
  is 41 in 2009, 61 in 2010 and 42 in 2011 – summing up 144 announcements.

• The number of actual projects in 2009, 2010 and 2011 was 33, 51 i 36 – summing up 120
  projects.
PPP announcements 2009 – 2011
                                  + 47 %




 Municipal Elections at the end of 2010 could be the reason…
Number of announcements, number of projects and contract signed
                        PPP in Poland 2009 – 2011




                                                          number of announcements

                                                          number of actual projects

                                                          number of contracts signed




•   24 projects were commerially closed (agreement signed) during 2009-2011:
      18 out of 24 was also financially closed,
      Signed contracts accounts for app. 15-20% of the initial number of
         announcements.
     • Approximately 50% of the announcements were cancelled – often due to lack of
         oficially submitted bids by the private partners.
PPP announcements in sectors (2009-2011)




                              The most popular sectors:

                               Sports & Leisure (34%)

                                Communal infrastructure (15%)

                               Transport & Carparks (18%)

                                Education (5%)
PPP announcements in sectors (2009-2011)




Source: on a basis of Investment Suppor reports on polish PPP market in 2009, 2010 and 2011
PPP announcements in sectors with values (2009-2011)

                                                                  Estimated value of the project (mln PLN netto)
                    Sector
                                                                     2009             2010             2011
                     Education                                  17 500 000 – 29 369 032,5               b.d.              4 500 000,00 – 18 599 955,00

                           ICT                                           23 000 000                     b.d.                          b.d.

                    Healthcare                                   1 500 000 – 145 000 000      2 800 000 – 4 295 127,99           3 300 000,00

         Comunal infrastructure                                  29 369 032,5 – 70000000            25 000 000                        b.d.

                Sport & Leisure                                  12 406 720 – 375 000 000      600 000 – 220 000 000      320 000,00 – 300 000 000,00

             Water management                                    3 000 000 – 333 000 000      1 150 000 – 24 571 778,8                b.d.

                      Carparks                                                b.d.             570 000 – 52 500 000      18 599 955,00 – 115 000 000,00

            Waste management                                                  b.d.            16 500 000 – 17 500 000    8 929 514,00 – 700 000 000,00

                     Transport                                                b.d.                 20 287 732,56                      b.d.
           Public infrastructure                                              b.d.                  80 000 000                        b.d.
                        Culture                                               b.d.            6 461 396,63 – 24 400 00                b.d.
            Urban regeneration                                                b.d.                  215 000 000                       b.d.
                    Fuel sector                                               b.d.                  17 760 000                        b.d.
                        Energy                                                b.d.             3 250 000 – 3 750 000                  b.d.
                  Conferences                                                 b.d.                      b.d.                        671 825
                 Social housing                                               b.d.                      b.d.                      23 645 000
               Shopping centre                                                b.d.                      b.d.                      20 000 000




Source: on a basis of Investment Suppor reports on polish PPP market in 2009, 2010 and 2011
Value of PPP projects (in sectors) in Poland 2009 – 2011

•     The value of the polish PPP market for the last 3 years, taking into consideration
      announced projects, is estimated* to 5 bln PLN (app. 1,2 bln EUR),
•     Strong variation of PPP projects does not allow the use the term of average value ​-
      e.g. in Sports & Leisure projects 0,6 mln PLN - 375 mln PLN,
•     The highest vaule of PPP projects have been is the sectors: Sports & Leisure, waste
      management, water management and carparks,
•     In comparison to the european** PPP projects – polish PPPs are relatively small. It is
      mainly due to a fact that majority of PPP projects have been implemented by
      municipalities, which are resposible locally for activities in particular regions and as a
      consequence those projects are not that big,
•     One of the reasons of the PPP projects low value is the lack of the central government
      involvement in the implementation of PPPs. There are several central goverment
      projects that could and should be implemented using PPP: courts and prisons, road
      infrastructure (highways), rail infrastructure (High Speed Rail), air infrastructure (Airport
      and MRTT) and many many others…

* The vaule of the planned PPP projects in the next 2 years in Poland is estimated to 15 bln PLN (3,7 bln EUR)
** the average value of PPP project commercially and financially closed is 163 mln EUR in 2010 and 213 mln EUR in 2011
PPP announcements in regions (2009-2011)




•   PPP leaders in voievodships are: małopolskie (Cracov), wielkopolskie (Poznan), dolnośląskie
    (Wroclaw), mazowieckie (Warsaw) pomorskie (Gdansk, Sopot, Gdynia) i śląskie (Katowice).
Planned PPP projects 2012




   There have been more than 130 projects identified that are at the initial stage of
          development – in which PPP/concession has been considered.
             Some of the projects are about to be launched in 2012.

Source: www.pppbaza.pl.
Results of announcements 2009-2010, Centrum PPP Survey

               In general                               with advisors                          without advisors




•       24% of the all announcements in which external advisors were involved, ended up with signing a
        contract, 31% was cancelled,
•       In announcements where external advisors were not involved – only 10% were signed contracts
        and more than 60% were cancelled,

    Including external advisors in PPP projects is even more important than in traditional procurement due to a fact that:
      PPP project are far more complicated than the traditional procurement,
      There is a need to secure public interest in PPP projects,
      PPP projects are long-term investments.
Common mistakes in preparing PPP projects in Poland:

 Lack of proper analysis (economic-financial, legal, technical),

 Improper way of selecting private partner (concession vs PPP –

 payment mechanism),

 Unrealistic expectations of public authority regarding private partner,

 Lack of market testing before the announcement,

 Improper criteria for selecting best bid,

 Lack of flexibility during the negotiations,

 Lack of knowledge in regarding PPP, Public Procurement and other

 Law.
Agenda

Introduction


PPP in Central Eastern Europe – update


PPP in Poland


Summary
PPP in various sectors across the Europe
          Sector                                              Social                                                                 Education                      Water
                        Town halls   Airports Defence                  Health care        ICT   Ports Prisons        Rail    Roads             Sport & Leisure
Country                                                      housing                                                                  Schools                     management
Austria                                                                                                                                                            
Belgium                                                                                                                                                            
Bulgaria                                                                                                                                                           
Croatia                                                                                                                                                            
Czech Republic                                                                                                                                                     
Denmark                                                                                                                                                            
Estonia                                                                                                                                                            
France                                                                                                                                                             
Greece                                                                                                                                                             
Spain                                                                                                                                                              
Netherlands                                                                                                                                                        
Ireland                                                                                                                                                            
North Ireland                                                                                                                                                      
Lithuania                                                                                                                                                          
Latvia                                                                                                                                                             
Malta                                                                                                                                                              
Germany                                                                                                                                                            
Poland                                                                                                                                                             
Portugal                                                                                                                                                           
Russia                                                                                                                                                             
Romania                                                                                                                                                            
Slovak Republic                                                                                                                                                    
Slovenia                                                                                                                                                           
Scotland                                                                                                                                                           
Switzerland                                                                                                                                                        
Hungary                                                                                                                                                            
United Kingdom                                                                                                                                                     
Italy                                                                                                                                                              



                   Executed,done                                                                           Under preparation
Conclusions
•   CEE PPP market has been still at the initial stage of development although
    there has been several PPP experiences across the region,
•   Financial crisis affected PPP market,
• There are few big projects on the horizon in the CEE region:
? A1 Highway and High-Speed Rail, Poland,
? D3, Czech Republic,
? D4, Slovak Republic,
? Bucharest Bypass and Comarnic – Brasov Motorway, Romania,
? Milot-Morine, Albania,
•   Costruction companies have become infrastructure operators,



•   Key International infrastructure operators move to CEE region.
Thank you
 for your attention


Bartosz Mysiorski                            Centrum PPP is an independent unit and its aim is to significantly
                                             accelerate private investments in meeting these public needs, for which
Bartosz Mysiorski, Chief Specialist in PPP   the state lacks financing. More investment in public infrastructure,
                                             together with simultaneous improvement in the quality of its positive
                                             impact on the economic growth will improve the quality of everyday life.
E-mail: bartosz.mysiorski@centrum-ppp.pl  
                                             Centrum PPP was founded in 2008 by more than 40 public and private
Mobile: +48 519 138 517                      entities including banks, law firms, consulting companies, firms,
                                             regional development agencies, foundations, associations, chambers
                                             and business agencies.


                                             The Centrum is given government support from Ministry of Finance,
                                             Ministry of Economy, Ministry of Infrastructure, as well as the local
                                             authorities.

                                             www.centrum-ppp.pl

                                             www.pppbaza.pl

                                             www.tep-ppp.eu

More Related Content

Similar to Current situation and future opportunities for PPP in CEE region

Projects and activities of the City of Pécs Concerning Sustainable Public Tra...
Projects and activities of the City of Pécs Concerning Sustainable Public Tra...Projects and activities of the City of Pécs Concerning Sustainable Public Tra...
Projects and activities of the City of Pécs Concerning Sustainable Public Tra...CSCP
 
20101020 Broadband in Europe - Internet Hungary conference
20101020 Broadband in Europe - Internet Hungary conference20101020 Broadband in Europe - Internet Hungary conference
20101020 Broadband in Europe - Internet Hungary conferencegaalnorb
 
Euro rail eng_full
Euro rail eng_fullEuro rail eng_full
Euro rail eng_fullinvestinlviv
 
Ukraine Early Recovery presentation 23 June 2015 ENG
Ukraine Early Recovery presentation 23 June 2015 ENGUkraine Early Recovery presentation 23 June 2015 ENG
Ukraine Early Recovery presentation 23 June 2015 ENGAndriy Demydenko
 
5. foreign players wwtp
5. foreign players wwtp5. foreign players wwtp
5. foreign players wwtpGilberte Delva
 
The european union and ukraine
The european union and ukraineThe european union and ukraine
The european union and ukraineENPI Info Centre
 
Participatory budgeting bratislava nove mesto
Participatory budgeting bratislava nove mestoParticipatory budgeting bratislava nove mesto
Participatory budgeting bratislava nove mestoGabriel Lachmann
 
Prezentare MLPS Comitet Director din 19 noiembrie 2012
Prezentare MLPS Comitet Director din 19 noiembrie 2012Prezentare MLPS Comitet Director din 19 noiembrie 2012
Prezentare MLPS Comitet Director din 19 noiembrie 2012GIZ Moldova
 
20150610-uitp-amm-pta-challenges-final
20150610-uitp-amm-pta-challenges-final20150610-uitp-amm-pta-challenges-final
20150610-uitp-amm-pta-challenges-finalStefan Roseanu
 
24.03.2014, Public Private Partnership in Mongolia: Now and Future Prospects,...
24.03.2014, Public Private Partnership in Mongolia: Now and Future Prospects,...24.03.2014, Public Private Partnership in Mongolia: Now and Future Prospects,...
24.03.2014, Public Private Partnership in Mongolia: Now and Future Prospects,...The Business Council of Mongolia
 
MSPL presentation of the steering committee session of 8 october 2015
MSPL presentation of the steering committee session of 8 october 2015MSPL presentation of the steering committee session of 8 october 2015
MSPL presentation of the steering committee session of 8 october 2015GIZ Moldova
 
Програма розвитку державно-приватного партнерства
Програма розвитку державно-приватного партнерстваПрограма розвитку державно-приватного партнерства
Програма розвитку державно-приватного партнерстваKukurudziak Ivan
 
AnthonyMilaneseCV-LinkedIn
AnthonyMilaneseCV-LinkedInAnthonyMilaneseCV-LinkedIn
AnthonyMilaneseCV-LinkedInTony Milanese
 
New developments in the infrastructure space in OECD countries - Martin Kelle...
New developments in the infrastructure space in OECD countries - Martin Kelle...New developments in the infrastructure space in OECD countries - Martin Kelle...
New developments in the infrastructure space in OECD countries - Martin Kelle...OECD Governance
 
MLPS Presentation for the Steering Committee Session from February 21, 2014
MLPS Presentation for the Steering Committee Session from February 21, 2014MLPS Presentation for the Steering Committee Session from February 21, 2014
MLPS Presentation for the Steering Committee Session from February 21, 2014GIZ Moldova
 

Similar to Current situation and future opportunities for PPP in CEE region (20)

Projects and activities of the City of Pécs Concerning Sustainable Public Tra...
Projects and activities of the City of Pécs Concerning Sustainable Public Tra...Projects and activities of the City of Pécs Concerning Sustainable Public Tra...
Projects and activities of the City of Pécs Concerning Sustainable Public Tra...
 
20101020 Broadband in Europe - Internet Hungary conference
20101020 Broadband in Europe - Internet Hungary conference20101020 Broadband in Europe - Internet Hungary conference
20101020 Broadband in Europe - Internet Hungary conference
 
Euro rail eng_full
Euro rail eng_fullEuro rail eng_full
Euro rail eng_full
 
Ukraine Early Recovery presentation 23 June 2015 ENG
Ukraine Early Recovery presentation 23 June 2015 ENGUkraine Early Recovery presentation 23 June 2015 ENG
Ukraine Early Recovery presentation 23 June 2015 ENG
 
5. foreign players wwtp
5. foreign players wwtp5. foreign players wwtp
5. foreign players wwtp
 
The european union and ukraine
The european union and ukraineThe european union and ukraine
The european union and ukraine
 
Serbia Presentation, PPO, Svetlana Razic, Serbian Practical Experience in PP ...
Serbia Presentation, PPO, Svetlana Razic, Serbian Practical Experience in PP ...Serbia Presentation, PPO, Svetlana Razic, Serbian Practical Experience in PP ...
Serbia Presentation, PPO, Svetlana Razic, Serbian Practical Experience in PP ...
 
Participatory budgeting bratislava nove mesto
Participatory budgeting bratislava nove mestoParticipatory budgeting bratislava nove mesto
Participatory budgeting bratislava nove mesto
 
Prezentare MLPS Comitet Director din 19 noiembrie 2012
Prezentare MLPS Comitet Director din 19 noiembrie 2012Prezentare MLPS Comitet Director din 19 noiembrie 2012
Prezentare MLPS Comitet Director din 19 noiembrie 2012
 
Wojciech Kutyla, The independence of the Court of Auditors, a guarantee of it...
Wojciech Kutyla, The independence of the Court of Auditors, a guarantee of it...Wojciech Kutyla, The independence of the Court of Auditors, a guarantee of it...
Wojciech Kutyla, The independence of the Court of Auditors, a guarantee of it...
 
Jiri Fiala: Nasi Politici o.s. - new media watchdog
Jiri Fiala: Nasi Politici o.s. - new media watchdogJiri Fiala: Nasi Politici o.s. - new media watchdog
Jiri Fiala: Nasi Politici o.s. - new media watchdog
 
20150610-uitp-amm-pta-challenges-final
20150610-uitp-amm-pta-challenges-final20150610-uitp-amm-pta-challenges-final
20150610-uitp-amm-pta-challenges-final
 
24.03.2014, Public Private Partnership in Mongolia: Now and Future Prospects,...
24.03.2014, Public Private Partnership in Mongolia: Now and Future Prospects,...24.03.2014, Public Private Partnership in Mongolia: Now and Future Prospects,...
24.03.2014, Public Private Partnership in Mongolia: Now and Future Prospects,...
 
MSPL presentation of the steering committee session of 8 october 2015
MSPL presentation of the steering committee session of 8 october 2015MSPL presentation of the steering committee session of 8 october 2015
MSPL presentation of the steering committee session of 8 october 2015
 
Montenegro Presentation, Sandra Skataric, PPA, Institutional set up, 7th Regi...
Montenegro Presentation, Sandra Skataric, PPA, Institutional set up, 7th Regi...Montenegro Presentation, Sandra Skataric, PPA, Institutional set up, 7th Regi...
Montenegro Presentation, Sandra Skataric, PPA, Institutional set up, 7th Regi...
 
Програма розвитку державно-приватного партнерства
Програма розвитку державно-приватного партнерстваПрограма розвитку державно-приватного партнерства
Програма розвитку державно-приватного партнерства
 
AnthonyMilaneseCV-LinkedIn
AnthonyMilaneseCV-LinkedInAnthonyMilaneseCV-LinkedIn
AnthonyMilaneseCV-LinkedIn
 
Donor meeting. Ministry of Infrastructure of Ukraine 6th of December
Donor meeting. Ministry of Infrastructure of Ukraine 6th of DecemberDonor meeting. Ministry of Infrastructure of Ukraine 6th of December
Donor meeting. Ministry of Infrastructure of Ukraine 6th of December
 
New developments in the infrastructure space in OECD countries - Martin Kelle...
New developments in the infrastructure space in OECD countries - Martin Kelle...New developments in the infrastructure space in OECD countries - Martin Kelle...
New developments in the infrastructure space in OECD countries - Martin Kelle...
 
MLPS Presentation for the Steering Committee Session from February 21, 2014
MLPS Presentation for the Steering Committee Session from February 21, 2014MLPS Presentation for the Steering Committee Session from February 21, 2014
MLPS Presentation for the Steering Committee Session from February 21, 2014
 

Recently uploaded

Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...lizamodels9
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdfOrient Homes
 
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | Delhi
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | DelhiFULL ENJOY - 9953040155 Call Girls in Chhatarpur | Delhi
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | DelhiMalviyaNagarCallGirl
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurSuhani Kapoor
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis UsageNeil Kimberley
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024christinemoorman
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Timedelhimodelshub1
 
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… AbridgedLean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… AbridgedKaiNexus
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfPaul Menig
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessAggregage
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Dipal Arora
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...lizamodels9
 
Pitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deckPitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deckHajeJanKamps
 
rishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfrishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfmuskan1121w
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 

Recently uploaded (20)

Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdf
 
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | Delhi
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | DelhiFULL ENJOY - 9953040155 Call Girls in Chhatarpur | Delhi
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | Delhi
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Time
 
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… AbridgedLean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdf
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for Success
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 
Best Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting PartnershipBest Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting Partnership
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
 
Pitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deckPitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deck
 
rishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfrishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdf
 
KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 

Current situation and future opportunities for PPP in CEE region

  • 1.
  • 2. Agenda Introduction PPP in Central Eastern Europe – update PPP in Poland Summary
  • 3. Agenda Introduction PPP in Central Eastern Europe – update PPP in Poland Summary
  • 4. PPP in CEE in particularly needed due to: • Great scale of negligence in the field of public services during real socialism, • Strong and increasing public deficits and public budgets limitations, • Increasing expectations of the societies regarding the infrastructure and public services, • Poor qualifications of public officials in regarding the infrastructural projects management and operation, • Politicisation of privatisation process as a part of political games – negative connotations, • The challenges, which public authorities in EU countries are facing, regarding the consumption of EU funds.
  • 5. Agenda Introduction PPP in Central Eastern Europe – update PPP in Poland Summary
  • 6. Czech Republic • In September 2011 Ministry of Regional Development concluded a concession contract with 5 concessionaires who were commissioned with creating and operating the so-called electronic marketplaces (EMP) – first PPP project on the central level, • On municipal level, a number of PPP projects in operation phase – water management, football stadium, pool, bus-stops, city-lightning and three senior houses. Demand for PPP on the municipal level is increasing: e.g. PPP project of public transport in Pilsen are under preparation. Most of these projects are based on availability fee, • The only project under preparation on central level is 19 km long part of highway D3 • Changes in the Public Procuement Act has been adopted by the Czech Parliament in November 2011. New rules on the transparency of contracts and subcontractors in the public tendering procedure entered into force 1st April 2012. Special thanks to Mr. Vladimír Sloup, Asociace PPP, Czech Republic
  • 7. Hungary  There is no specific PPP legislation, PPP Projects are implemented through Public Procurement Act, Municipal Act and Civic Code,  Public Finance Act determines if the value of the PPP project is exceeding 180 mln euro there has to be an acceptance from the Parliament, below 180 mln euro – acceptance form the Government is necessary,  Update of the Public Finance Act in 2010 regulated the issue of off-the-balance sheet treatment of PPP projects,  On the state level, PPP projects are implemented mainly by: • Ministry of Economy and Transport (M5, M6 highways), • Ministry of Justice (2 prisons), • National Sports Office (swimming pools, sport halls), • Ministry of Education and Culture (students' hostels, Palace of Arts). Majority of the projects are implemented as DBFO model,  Future PPP sectors: • National railway network – high speed rail, • National toll payment system, • Education – secondary schools, • Court buildings – reconstruction and operation, • Healthcare – hospitals, • Sport facilities – stadiums, watersport centre.
  • 8. Bulgaria • A draft of a PPP Act was developed in 2011. The draft was approved by the Council of Ministers in September 2011 and is currently being considered by the National Parliament. By the end of April 2012 the PPP Act will be adopted, • The aim of the Act is to give clear definition and set clear rules for doing PPP, • 2007-2010 there was on average only one infrastructure concession contract signed per year – all of them for relatively small river ports, • One concession contract was signed in 2011 - for port infrastructure on the Black Sea - Concession for Port Bourgas East 2, contract period is 35 years, starting from 01.01.2012, the value of the project is app.100 mln euro, • The transport ministry, in cooperation with the ministry of finance, continues its work on preparation of several more concessions in the area of airports, sea and river ports as well as railway stations, • Pleven is currently undertaking a water PPP with IFC acting as transaction leader, • The EIB alongside a banking consortium (Societe Generale Expressbank, Elana Holding, Elana Investment, Balkan Advisors) has established a €56.4 million Urban Development Fund to invest in PPPs and infrastructure in 6 Bulgarian cities (Burgas, Pleven, Plovdiv, Ruse, Stara Zagora, Varna). Special thanks to Mr. Galin Zhelev and the Ministry of Finance of Bulgaria, Real Sector Finance Directorate (PPP unit)
  • 9. Romania •Till the end of 2010 – did not have any legal act dedicated directly to PPP, •PPP Act had been resolved by the Parliament in September 2010 and came into force in October 2010, however the European Commission was not satisfied with the framework as it did not mesh with European procurement laws and encouraged Romania to redraft it – necessary changes were introduced in October 2011, •Central Unit for Coordination of the PPP was established in 2011, •Regardless the legislation, the National Strategy for PPP (in regarding PPP project pipeline, good practices, risk structures, mechanisms of payment, ect.) has been implemented by the Government, (the Strategy was prepared in cooperation with European PPP Expertise Centre JASPERS initiative), •EBRD has adopted a new 3-year strategy for Romania with a key objective being the greater use of PPP and privatisations in the country. Key sector interest: water, waste, roads, rail, district heating, •Implemented PPPs: road infrastructure, waste management, airport modernization, construction of Metroline 7 in Bucharest, •PPP opportunities in the following sectors: healthcare, prisons, energy, environment, transport, road infrastructure (Bucharest Bypass South Section & Comarnic-Brasov Motorway) Special thanks to Mr.s. Antonina Petrescu, PPP Coordinator, Louis Berger - PPP Unit. Regional Office for Central and Eastern Europe
  • 10. Slovak Republic • Slovakia’s centre-left opposition SMER stormed to an unprecedented (the best result for any party since the independence in 1993) victory in parliamentary elections in March 2012 and will rule alone, • The new goverment seems to be enthusiastic in terms of PPP and restart some of the PPP projects scrapped by the outgoing government, • One project is about to be finished on the central level – Highway R1, • On the municipal level: 2 water management projects in operational stage (Trencin and Banska Bystrica), • Plans for projects: construction of broad-gauge rail from Kosice to Bratislava. (probably it will be part of new governments program), road projects (many plans in the national level, but it depends on new government). Republic of Slovenia •Public-private partnerships are regulated by PPP Act adopted in 2006, •PPP has been used mainly at the local level (municipalities) in e.g. social housing, kindergartens, waste management, sports infrastructure, cultural buildings, parking garages, public lightning and photovoltaic, •step-by-step PPP good practice has been developed, •On the central level there have been no significant PPP projects, •PPP projects pipeline should be developed, •Due to a small size of PPP projects on local level and absence of central PPP projects, Slovenia has not been an interesting case for foreign investors so far. Special thanks to Mr. Michal Považan, Slovak PPP Association, Slovak Republic and Mrs. Petra Ferk, Institute for PPP, Slovenia
  • 11. Moldova •In 2008 the Law on public-private Partnership has been adopted, •PPP projects pipeline prepared by the goverment and PPP Unit is about to be introduced in the first half of 2012, •The National Council of PPP (deputy prime-minister, ministers, NGO’s, investment banks) first meeting is about to be organized in the first half of 2012, •The city of Chisinau has approved a €11.7 million loan from the EBRD to fund various PPP projects for the modernisation of the city's street infrastructure (roads, parkings, pavements, street lighting). The tender for the project is expected to begin after May 2012 with works planned for the second half of 2012, •Implemented PPP projects: 2 on central level (healthcare, ICT) and 12 on local level (healthcare, waste management, culture), •PPP projects in preparation: 33 on central level (carparks, social infrastructure, airport, sport infrastructure, ICT, road infrastructure) and 57 on local level (healthcare, waste management, road infrastructure). Special thanks to Mr. Ion Potlog, Head of the PPP Unit, Public Property Agency, Ministry of Economy of Republic of Moldova
  • 12. Lithuania  Concession Law adopted in 1996, PPP Law in 2009, PPP Unit established in 2010,  In 2010 there was a program introduced by the Government to boost PPP in priority sectors: transport, education, social housing, public order and safety,  5 PPP Pilot Projects have been initiated in 2010 – social housing, education (secondary school), transport (bypass), safety (prison) and public order (police station). Pilot PPPs are slow in process, but they creates concrete background with minimum risk;  More than 40 PPP projects so far (mainly service concessions),  4 prison projects are under discussion to be procured as 25 year DBFOT contracts: • Vilnius €34 million (£28m $45m) holding 1,620 inmates • Klaipeda €21 million (£17,5m $28m) holding 800 inmates • Panevežys €17 million (£14m $22,5m) holding 400 inmates • Šiauliai €35 million (£29m $46,5m) holding 1,180 inmates Each prison will be procured separately in the late 2012.  The Capital, Vilnius is preparing tender documents to procure a €25 million upgrade, operation and maintenance for its street lighting through a PPP. 19-year DBFOM contract is to cover 691km of city streets. Project is supposed to be launched at the end of Q3 2012,  Vilnius – Utena 61,8 km road reconstruction to launch IVQ 2012, DBFO, 35 mln EUR, 25 years,  Expansion of 34,5 km of 1st Trans-European Corridor E65 to launch in I Q 2015, DBFO, 100 mln EUR 25 years,  15 potential PFI-type projects for social infrastructure - scheduled for min 15 - max 25 years. Special thanks to Mr. Tadas Jagminas, Invest Lithuania
  • 13. Estonia There is no specific PPP Law, all PPP are done according to Public Procurment, Lack of clear PPP policy framework/strategy or PPP Project Pipeline, No centralized PPP development - public authority has autonomy to decide on PPP, PPP sectors of interest: education (project in Tallinn – 18 schools renovated), municipal administrative buildings, social housing. PPP project on the central level – headquaters for: State Tax Authority and Statistical Bureau, There have been discussion mainly from the private sector discussing opportunities associated with PPP in other sectors, but public authorities are rather passive in this issue Latvia  There was PPP Action Plan 2006-2009, created in 2005,  PPP Law came into force in 2009,  Latvia is currently emerging from the deepest recession,  There have been few PPP projects but public authorities are prudent,  Concessions are allowed but for other types of PPP there should be accept from Ministry of Finance,  There have been more than 60 PPP agreements in force (80% concessions),  Main PPP sectors: transport, education, healthcare, water/waste, justice/courts, Special thanks to Mr. Lauri Henno, U.S. Real Estate Management, Estonia
  • 14. Ukraine • PPP Law was adopted in 2010 and the by-laws on its implementation – in 2011, but till present there were no project started using these procedures; In March 2012 the draft law on incorporation of changes to the PPP law was registered in the Ukrainian Parliament, • Opportunity to initiate PPP projects by the private sector, • PPP sectors: transport, social housing, water management, solid waste, sports & leisure, • Most active regions: Kyiv region, Donetsk region, Zaporizhzhia, Mykolayiv, • Competition between operators/investors is relatively low, • Among the positive moments that witness about speeding up of PPP in Ukraine is announcement of competition for consultant selection for implementation of metro construction in form of PPP. Belarus • There is a clear message from the President and the Government to establish and develop effective PPP mechanism in the country, • Belarusian PPP Law had been drafted and it has been assessed by UNECE Experts of the UN Economic Commission for Europe, action plan will be prepared on a basis of preliminary report, • Necessary conditions for implementing PPP projects in Belarus are being considered, including the establishment of a center of PPP expertise and training of qualified experts, • Current needs in the economic and social sectors are enormous – PPP could be applied, • PPP Pilot Project is also considered to be introduced. Special thanks to Mrs. Irina Zapatrina, Chairman of the Board at Ukrainian PPP Center and Mr. Dzmitry Berazouski, Executive Director of the Coordinating Unit for the European Union's Tacis Programme in the Republic of Belarus
  • 15. Croatia • Croatia hopes to gain full EU membership in 2013, • PPP projects implemented in road infrastructure, education, sports and utility, • Only one signed PPP project in last 4 years – Zagreb airport (200 mln euro), • Sector of interest: energy, healthcare, ports, energy efficiency in public buildings, justice, Kosovo •Infrastructure gap for approximately 3 billion euro (in the next 3-5 years), •Main sectors in which private sector could participate: transport, energy, ICT, •PPP Law is investor-friendly in accordance with intenrational PPP best practice, •PPP Inter-ministerial Steering Committee and Centralized PPP Unit -Partnerships Kosovo have been created, Special thanks to Mr. Saša Marenjak, Prof.dr.sc. at PPP Centar, Croatia and Mrs. Nora Bakali Legal Advisor, Public Private Partnership Unit, kosovo
  • 16. Serbia • In 2011 there was a new Law on PPP and Concessions introduced, (e.g new law distinguishes between institutional and contractual PPP), • The Government seeks to attract €4 billion of investments into local infrastructure through PPP over the next decade. Macedonia •Special Law on PPP and Concessions adopted in 2007, •Few positive experiences with PPP in the past (e.g. airports under concession), •Several PPP projects in Skopje: amusement park, administrative facility and car park, waste facility.
  • 17. Albania • EBRD alongside the city of Tirana in Albania is preparing a feasibility study on procuring a new public transport terminal on a DBFOT basis, • The terminal will be situated on an 85,000m2 plot provided by the city and will consist of: bus terminals, tram/train station, parking and retail, • The contract will have a 20-year plus concession and will be opened as an international tender. The EBRD will look to help finance the project with the winning bidder. Bosnia and Herzegovina • PPP Law adopted in 2009, the cooperation model between public and private sector is a relatively new model, where market is still in the early stages, • PPP sectors of interest: power facilities, recycling facilities, water and waste management, education, healthcare,transport. Montenegro • PPP is regulated by Law on participation of private sector in the procurement of public services and the Law on Concessions in 2009, • Sectors of interest: tourism, energy, roads. • Local municipalities interested in PPP: Podgorica, Budva,
  • 18. Agenda Introduction PPP in Central Eastern Europe – update PPP in Poland Summary
  • 19. First PPP Act  Public-Private Partnership Act June 2005 No PPP projects implemented! Reasons for failure: bad political climate, lack of knowledge about PPP, strict regulations? New PPP regulations – came into force in February 2009  The Public-Private Partnership Act 19 December 2008  Concession for construction works and services Act ; 9 January 2009
  • 20. Number of PPPs and Concessions announcements in Poland 2009, 2010, 2011 + 47 % +47% PPPs – 31 % • The number of announcements, on a basis of PPP Act and concession for works and services Act, is 41 in 2009, 61 in 2010 and 42 in 2011 – summing up 144 announcements. • The number of actual projects in 2009, 2010 and 2011 was 33, 51 i 36 – summing up 120 projects.
  • 21. PPP announcements 2009 – 2011 + 47 % Municipal Elections at the end of 2010 could be the reason…
  • 22. Number of announcements, number of projects and contract signed PPP in Poland 2009 – 2011 number of announcements number of actual projects number of contracts signed • 24 projects were commerially closed (agreement signed) during 2009-2011:  18 out of 24 was also financially closed,  Signed contracts accounts for app. 15-20% of the initial number of announcements. • Approximately 50% of the announcements were cancelled – often due to lack of oficially submitted bids by the private partners.
  • 23. PPP announcements in sectors (2009-2011) The most popular sectors: Sports & Leisure (34%) Communal infrastructure (15%) Transport & Carparks (18%) Education (5%)
  • 24. PPP announcements in sectors (2009-2011) Source: on a basis of Investment Suppor reports on polish PPP market in 2009, 2010 and 2011
  • 25. PPP announcements in sectors with values (2009-2011) Estimated value of the project (mln PLN netto) Sector 2009 2010 2011 Education 17 500 000 – 29 369 032,5 b.d. 4 500 000,00 – 18 599 955,00 ICT 23 000 000 b.d. b.d. Healthcare 1 500 000 – 145 000 000 2 800 000 – 4 295 127,99 3 300 000,00 Comunal infrastructure 29 369 032,5 – 70000000 25 000 000 b.d. Sport & Leisure 12 406 720 – 375 000 000 600 000 – 220 000 000 320 000,00 – 300 000 000,00 Water management 3 000 000 – 333 000 000 1 150 000 – 24 571 778,8 b.d. Carparks b.d. 570 000 – 52 500 000 18 599 955,00 – 115 000 000,00 Waste management b.d. 16 500 000 – 17 500 000 8 929 514,00 – 700 000 000,00 Transport b.d. 20 287 732,56 b.d. Public infrastructure b.d. 80 000 000 b.d. Culture b.d. 6 461 396,63 – 24 400 00 b.d. Urban regeneration b.d. 215 000 000 b.d. Fuel sector b.d. 17 760 000 b.d. Energy b.d. 3 250 000 – 3 750 000 b.d. Conferences b.d. b.d. 671 825 Social housing b.d. b.d. 23 645 000 Shopping centre b.d. b.d. 20 000 000 Source: on a basis of Investment Suppor reports on polish PPP market in 2009, 2010 and 2011
  • 26. Value of PPP projects (in sectors) in Poland 2009 – 2011 • The value of the polish PPP market for the last 3 years, taking into consideration announced projects, is estimated* to 5 bln PLN (app. 1,2 bln EUR), • Strong variation of PPP projects does not allow the use the term of average value ​- e.g. in Sports & Leisure projects 0,6 mln PLN - 375 mln PLN, • The highest vaule of PPP projects have been is the sectors: Sports & Leisure, waste management, water management and carparks, • In comparison to the european** PPP projects – polish PPPs are relatively small. It is mainly due to a fact that majority of PPP projects have been implemented by municipalities, which are resposible locally for activities in particular regions and as a consequence those projects are not that big, • One of the reasons of the PPP projects low value is the lack of the central government involvement in the implementation of PPPs. There are several central goverment projects that could and should be implemented using PPP: courts and prisons, road infrastructure (highways), rail infrastructure (High Speed Rail), air infrastructure (Airport and MRTT) and many many others… * The vaule of the planned PPP projects in the next 2 years in Poland is estimated to 15 bln PLN (3,7 bln EUR) ** the average value of PPP project commercially and financially closed is 163 mln EUR in 2010 and 213 mln EUR in 2011
  • 27. PPP announcements in regions (2009-2011) • PPP leaders in voievodships are: małopolskie (Cracov), wielkopolskie (Poznan), dolnośląskie (Wroclaw), mazowieckie (Warsaw) pomorskie (Gdansk, Sopot, Gdynia) i śląskie (Katowice).
  • 28. Planned PPP projects 2012 There have been more than 130 projects identified that are at the initial stage of development – in which PPP/concession has been considered. Some of the projects are about to be launched in 2012. Source: www.pppbaza.pl.
  • 29. Results of announcements 2009-2010, Centrum PPP Survey In general with advisors without advisors • 24% of the all announcements in which external advisors were involved, ended up with signing a contract, 31% was cancelled, • In announcements where external advisors were not involved – only 10% were signed contracts and more than 60% were cancelled, Including external advisors in PPP projects is even more important than in traditional procurement due to a fact that: PPP project are far more complicated than the traditional procurement, There is a need to secure public interest in PPP projects, PPP projects are long-term investments.
  • 30. Common mistakes in preparing PPP projects in Poland: Lack of proper analysis (economic-financial, legal, technical), Improper way of selecting private partner (concession vs PPP – payment mechanism), Unrealistic expectations of public authority regarding private partner, Lack of market testing before the announcement, Improper criteria for selecting best bid, Lack of flexibility during the negotiations, Lack of knowledge in regarding PPP, Public Procurement and other Law.
  • 31. Agenda Introduction PPP in Central Eastern Europe – update PPP in Poland Summary
  • 32. PPP in various sectors across the Europe Sector Social Education Water Town halls Airports Defence Health care ICT Ports Prisons Rail Roads Sport & Leisure Country housing Schools management Austria                                        Belgium                                        Bulgaria                                        Croatia                                        Czech Republic                                        Denmark                                        Estonia                                        France                                        Greece                                        Spain                                        Netherlands                                        Ireland                                        North Ireland                                        Lithuania                                        Latvia                                        Malta                                        Germany                                        Poland                                        Portugal                                        Russia                                        Romania                                        Slovak Republic                                        Slovenia                                        Scotland                                        Switzerland                                        Hungary                                        United Kingdom                                        Italy                                        Executed,done Under preparation
  • 33. Conclusions • CEE PPP market has been still at the initial stage of development although there has been several PPP experiences across the region, • Financial crisis affected PPP market, • There are few big projects on the horizon in the CEE region: ? A1 Highway and High-Speed Rail, Poland, ? D3, Czech Republic, ? D4, Slovak Republic, ? Bucharest Bypass and Comarnic – Brasov Motorway, Romania, ? Milot-Morine, Albania, • Costruction companies have become infrastructure operators, • Key International infrastructure operators move to CEE region.
  • 34. Thank you for your attention Bartosz Mysiorski Centrum PPP is an independent unit and its aim is to significantly accelerate private investments in meeting these public needs, for which Bartosz Mysiorski, Chief Specialist in PPP the state lacks financing. More investment in public infrastructure, together with simultaneous improvement in the quality of its positive impact on the economic growth will improve the quality of everyday life. E-mail: bartosz.mysiorski@centrum-ppp.pl   Centrum PPP was founded in 2008 by more than 40 public and private Mobile: +48 519 138 517 entities including banks, law firms, consulting companies, firms, regional development agencies, foundations, associations, chambers and business agencies. The Centrum is given government support from Ministry of Finance, Ministry of Economy, Ministry of Infrastructure, as well as the local authorities. www.centrum-ppp.pl www.pppbaza.pl www.tep-ppp.eu