Construction Management Assignment
We’re going to build an extension to existing building, shown in Fig 1 to 4.
Fig 5 shows the expansion plans.
1. I want you to create a sequence list of 25 activities that will be required to
complete the work. For example asphalt demolition.
Consider tasks that have to do with: Demolition, Site utilities, Roofing, Masonry,
Carpentry, Steel erection, Doors, frames and windows, etc.
2. Determine exactly the manpower, equipment, and material required for each
task.
3. Sequence the tasks to obtain the greatest efficiency.
 Minimize material handling
 Minimize traveling for both labor and equipment
 Keep equipment constantly in motion
So you have to provide a thorough analysis with the 25 activities required to
complete the task and describe how it can be done in a safe manner, and then
complete the table below for the 25 activities.
Activity Crew Equipment Material Notes (if needed)
Figure1
Figure2
Figure3
Figure4
Figure5

Construction management assignment 1

  • 1.
    Construction Management Assignment We’regoing to build an extension to existing building, shown in Fig 1 to 4. Fig 5 shows the expansion plans. 1. I want you to create a sequence list of 25 activities that will be required to complete the work. For example asphalt demolition. Consider tasks that have to do with: Demolition, Site utilities, Roofing, Masonry, Carpentry, Steel erection, Doors, frames and windows, etc. 2. Determine exactly the manpower, equipment, and material required for each task. 3. Sequence the tasks to obtain the greatest efficiency.  Minimize material handling  Minimize traveling for both labor and equipment  Keep equipment constantly in motion So you have to provide a thorough analysis with the 25 activities required to complete the task and describe how it can be done in a safe manner, and then complete the table below for the 25 activities. Activity Crew Equipment Material Notes (if needed)
  • 2.
  • 3.
  • 4.
  • 5.
  • 6.