MINUTES OF MEETING<br />MOM BETWEEN PARAMOUNT CABLE AND KAPIL MOHAN & ASSOCIETES REGARDING CABLE FAILURE & <br />                 LAYING FROM BASHANI TO MALORA IR LINE ON DATED 08, O9-09-2011<br />               PARAMOUNT CABLES PVT LTD                                                              KMA<br />                       Dinesh Kumar Yadav                                                            Parveen Thakur<br />The following points observe after checking the site:-<br />Cable is not proper earthling & recommended  proper earthling  with  all three cupper tape connected with8-10 meter grounded  cupper rod and connect using  lugs, thimble.

Complaint

  • 1.
    MINUTES OF MEETING<br />MOM BETWEEN PARAMOUNT CABLE AND KAPIL MOHAN & ASSOCIETES REGARDING CABLE FAILURE & <br /> LAYING FROM BASHANI TO MALORA IR LINE ON DATED 08, O9-09-2011<br /> PARAMOUNT CABLES PVT LTD KMA<br /> Dinesh Kumar Yadav Parveen Thakur<br />The following points observe after checking the site:-<br />Cable is not proper earthling & recommended proper earthling with all three cupper tape connected with8-10 meter grounded cupper rod and connect using lugs, thimble.
  • 2.
    Cablelying found not properly.
  • 3.
    Cable hanging isnot properly recommended that hanged with pole with proper acerreries with messenger.
  • 4.
    Soldering is providing/ used in case of cable jointing for earthling purpose.
  • 5.
    Do not leaveany loose connection b/w conductor and cupper tapeDinesh kumar Yadav Parveen thakur <br />