SlideShare a Scribd company logo
March 2013 April 2013 May 2013 June 2013 July 2013
Completion of Autoslate/CO
DEFINITION OF SUBSTANTIAL COMPLETION TO SUPPORT WET SHEET – JUNE 20, 2013.
FIRST OBSERVED WET SHEET RUNS JUNE 22, 2013. FEE MATRIX PROPOSAL MILESTONES PERFORMANCE.
85% INCREASE in WORK HOURS150% INCREASE in FEET of CONDUIT360% INCREASE in # of PANELS
AVERAGE OF 40 DAYS IN PUSH TO FINAL ISSUE TOTAL OF 61 REVISIONS ISSUED
SAFETY
1) 0 Recordables 5 Near miss 80 safety classes 850 safety
orientations, 3,000 SPA's . Max 1 day SPA's 57, 405 Hot
work permits, 300 parking permits, 4 safety lunches,
$2,000 in safety recognitions conducted, and 93,000 man
hours expended
2) Tremendous safety SPA and coordination between plant
and Construction ops. As stated above 3,000 SPA's and
405 hot work permits
3) TOP's submitted, System sign off sheets in place, no
issues
4) No damages to plant or assets
SCHEDULE
Construction work critical to wet sheet completed 6/20/13,
Wet sheet runs on June 25-26 and ongoing into qualified
production runs. 1 or 2 remaining shutdowns planned for
weekend of July 20-21 and July 27-28 to complete
Autoslate systems. All work to be completed by July 26
and subs to demobilize the site .
COST
(Total Indicated Cost - TIC - minus FEE)
1) Final target cost goal = $29.3mm
2) Cost per summary report WITHOUT incentive fee =
$27,774,583 (thru July 6). This includes 22 submitted
change notices including CM 109-Autoslate that was not
part of base job. All changes total $3.4mm. Total TIC
includes all PO data provided to JE since the start of the
job yet excludes CM 900 - these are third party
engineering costs that were excluded from cost model
estimate
PANEL DELIVERY WENT TO END OF PROJECT
BONUS JUSTIFICATION ANALYSIS
76 PANELS DELIVERED 1-6 WEEKS LATE

More Related Content

What's hot

Tugasan Sosioekonomi
Tugasan SosioekonomiTugasan Sosioekonomi
Tugasan Sosioekonomi
elizaelin
 
Affordable sector 104
Affordable sector 104Affordable sector 104
Affordable sector 104
Khushbu Aswani
 
lettre recommandation
lettre recommandationlettre recommandation
lettre recommandation
Guillermo G
 
12 Small mines report card 2020
12 Small mines report card 202012 Small mines report card 2020
12 Small mines report card 2020
NSW Environment and Planning
 
Why CFD is the answer when designing power plant ventilation schemes
Why CFD is the answer when designing power plant ventilation schemesWhy CFD is the answer when designing power plant ventilation schemes
Why CFD is the answer when designing power plant ventilation schemes
Colt UK
 
ENERCRET summary
ENERCRET summaryENERCRET summary
ENERCRET summary
Martyn Rose
 
Company profile Nayxa
Company profile NayxaCompany profile Nayxa
Company profile Nayxa
Jose Miguel Jauregui
 
GITA2002
GITA2002GITA2002
GITA2002
Gary Duplisea
 
Modis National Jobs Report Fast Facts
Modis National Jobs Report Fast FactsModis National Jobs Report Fast Facts
Modis National Jobs Report Fast Facts
Modis
 
Reliability
ReliabilityReliability
NYC Energy Benchmarking Checklist
NYC Energy Benchmarking ChecklistNYC Energy Benchmarking Checklist
NYC Energy Benchmarking Checklist
REBNY
 
Feb 2010 Hydrocarbon Processing
Feb 2010 Hydrocarbon ProcessingFeb 2010 Hydrocarbon Processing
Feb 2010 Hydrocarbon Processing
Peter Armstrong
 
2018 China Gas Fields Map
2018 China Gas Fields Map2018 China Gas Fields Map
2018 China Gas Fields Map
arapublication
 
Eia notif2020 panel discussion
Eia notif2020 panel discussionEia notif2020 panel discussion
Eia notif2020 panel discussion
Dr. Ashok Rathoure
 

What's hot (14)

Tugasan Sosioekonomi
Tugasan SosioekonomiTugasan Sosioekonomi
Tugasan Sosioekonomi
 
Affordable sector 104
Affordable sector 104Affordable sector 104
Affordable sector 104
 
lettre recommandation
lettre recommandationlettre recommandation
lettre recommandation
 
12 Small mines report card 2020
12 Small mines report card 202012 Small mines report card 2020
12 Small mines report card 2020
 
Why CFD is the answer when designing power plant ventilation schemes
Why CFD is the answer when designing power plant ventilation schemesWhy CFD is the answer when designing power plant ventilation schemes
Why CFD is the answer when designing power plant ventilation schemes
 
ENERCRET summary
ENERCRET summaryENERCRET summary
ENERCRET summary
 
Company profile Nayxa
Company profile NayxaCompany profile Nayxa
Company profile Nayxa
 
GITA2002
GITA2002GITA2002
GITA2002
 
Modis National Jobs Report Fast Facts
Modis National Jobs Report Fast FactsModis National Jobs Report Fast Facts
Modis National Jobs Report Fast Facts
 
Reliability
ReliabilityReliability
Reliability
 
NYC Energy Benchmarking Checklist
NYC Energy Benchmarking ChecklistNYC Energy Benchmarking Checklist
NYC Energy Benchmarking Checklist
 
Feb 2010 Hydrocarbon Processing
Feb 2010 Hydrocarbon ProcessingFeb 2010 Hydrocarbon Processing
Feb 2010 Hydrocarbon Processing
 
2018 China Gas Fields Map
2018 China Gas Fields Map2018 China Gas Fields Map
2018 China Gas Fields Map
 
Eia notif2020 panel discussion
Eia notif2020 panel discussionEia notif2020 panel discussion
Eia notif2020 panel discussion
 

Similar to Bonus Justification Presentation

Presentation 95
Presentation 95Presentation 95
Presentation 95
Tarek Fagal
 
Solarlightsystems
SolarlightsystemsSolarlightsystems
Solarlightsystems
Motoor Mohammed Muzammil
 
Khubaib Khan_CV Instrument
Khubaib Khan_CV InstrumentKhubaib Khan_CV Instrument
Khubaib Khan_CV Instrument
Khubaib Khan
 
SUNSHINE short overview of the project and its objectives
SUNSHINE short overview of the project and its objectives SUNSHINE short overview of the project and its objectives
SUNSHINE short overview of the project and its objectives
Raffaele de Amicis
 
ajay cv new (3)
ajay cv new (3)ajay cv new (3)
ajay cv new (3)
Ajay Gautam
 
Session B2 - Project Cost Control
Session B2 - Project Cost ControlSession B2 - Project Cost Control
Session B2 - Project Cost Control
Project Controls Expo
 
khalid mowafy CV
khalid mowafy CVkhalid mowafy CV
khalid mowafy CV
khalid elmowafy
 
Epc proposal 3x660 mw with cost analysis
Epc proposal 3x660 mw with cost analysisEpc proposal 3x660 mw with cost analysis
Epc proposal 3x660 mw with cost analysis
Nikhil Kumar Rai
 
IRJET- A Case Study Approach of Quality Tools in Manufacturing Industry
IRJET- A Case Study Approach of Quality Tools in Manufacturing IndustryIRJET- A Case Study Approach of Quality Tools in Manufacturing Industry
IRJET- A Case Study Approach of Quality Tools in Manufacturing Industry
IRJET Journal
 
Anwar Morsi _________July 2015
Anwar Morsi _________July 2015Anwar Morsi _________July 2015
Anwar Morsi _________July 2015
Anwar El-Sanafawey
 
Resume-up-Aug-16
Resume-up-Aug-16Resume-up-Aug-16
Resume-up-Aug-16
SUNIL KUMAR JENA
 
ANACOSTIA GATEWAY report
ANACOSTIA GATEWAY reportANACOSTIA GATEWAY report
ANACOSTIA GATEWAY report
Ngo Quan
 
05. HSSE HCML-DMPT Monthly Coordination Meeting May 2024 (1).pptx
05. HSSE HCML-DMPT Monthly Coordination Meeting May 2024 (1).pptx05. HSSE HCML-DMPT Monthly Coordination Meeting May 2024 (1).pptx
05. HSSE HCML-DMPT Monthly Coordination Meeting May 2024 (1).pptx
GunawanWibisono429926
 
IRJET - Productivity Improvement by Time Study and Motion Study
IRJET - Productivity Improvement by Time Study and Motion StudyIRJET - Productivity Improvement by Time Study and Motion Study
IRJET - Productivity Improvement by Time Study and Motion Study
IRJET Journal
 
MAR,23.pptx
MAR,23.pptxMAR,23.pptx
MAR,23.pptx
vishal laddha
 
Hossam CV-FEB2016
Hossam CV-FEB2016Hossam CV-FEB2016
Hossam CV-FEB2016
Hossam Rabie
 
CV of Instrumentation Consultant_Rashesh Shah_32 years plus exp
CV of Instrumentation Consultant_Rashesh Shah_32 years plus expCV of Instrumentation Consultant_Rashesh Shah_32 years plus exp
CV of Instrumentation Consultant_Rashesh Shah_32 years plus exp
Rashesh Shah
 
Oil & Gas technical training courses
Oil & Gas technical training coursesOil & Gas technical training courses
Oil & Gas technical training courses
Dasline Sinta
 
IRJET - Recovery of Energy from Exhaust Air of Textile Industry with the ...
IRJET -  	  Recovery of Energy from Exhaust Air of Textile Industry with the ...IRJET -  	  Recovery of Energy from Exhaust Air of Textile Industry with the ...
IRJET - Recovery of Energy from Exhaust Air of Textile Industry with the ...
IRJET Journal
 
Almoustafa_-2015_CV2nn
Almoustafa_-2015_CV2nnAlmoustafa_-2015_CV2nn
Almoustafa_-2015_CV2nn
Moustafa Gouda
 

Similar to Bonus Justification Presentation (20)

Presentation 95
Presentation 95Presentation 95
Presentation 95
 
Solarlightsystems
SolarlightsystemsSolarlightsystems
Solarlightsystems
 
Khubaib Khan_CV Instrument
Khubaib Khan_CV InstrumentKhubaib Khan_CV Instrument
Khubaib Khan_CV Instrument
 
SUNSHINE short overview of the project and its objectives
SUNSHINE short overview of the project and its objectives SUNSHINE short overview of the project and its objectives
SUNSHINE short overview of the project and its objectives
 
ajay cv new (3)
ajay cv new (3)ajay cv new (3)
ajay cv new (3)
 
Session B2 - Project Cost Control
Session B2 - Project Cost ControlSession B2 - Project Cost Control
Session B2 - Project Cost Control
 
khalid mowafy CV
khalid mowafy CVkhalid mowafy CV
khalid mowafy CV
 
Epc proposal 3x660 mw with cost analysis
Epc proposal 3x660 mw with cost analysisEpc proposal 3x660 mw with cost analysis
Epc proposal 3x660 mw with cost analysis
 
IRJET- A Case Study Approach of Quality Tools in Manufacturing Industry
IRJET- A Case Study Approach of Quality Tools in Manufacturing IndustryIRJET- A Case Study Approach of Quality Tools in Manufacturing Industry
IRJET- A Case Study Approach of Quality Tools in Manufacturing Industry
 
Anwar Morsi _________July 2015
Anwar Morsi _________July 2015Anwar Morsi _________July 2015
Anwar Morsi _________July 2015
 
Resume-up-Aug-16
Resume-up-Aug-16Resume-up-Aug-16
Resume-up-Aug-16
 
ANACOSTIA GATEWAY report
ANACOSTIA GATEWAY reportANACOSTIA GATEWAY report
ANACOSTIA GATEWAY report
 
05. HSSE HCML-DMPT Monthly Coordination Meeting May 2024 (1).pptx
05. HSSE HCML-DMPT Monthly Coordination Meeting May 2024 (1).pptx05. HSSE HCML-DMPT Monthly Coordination Meeting May 2024 (1).pptx
05. HSSE HCML-DMPT Monthly Coordination Meeting May 2024 (1).pptx
 
IRJET - Productivity Improvement by Time Study and Motion Study
IRJET - Productivity Improvement by Time Study and Motion StudyIRJET - Productivity Improvement by Time Study and Motion Study
IRJET - Productivity Improvement by Time Study and Motion Study
 
MAR,23.pptx
MAR,23.pptxMAR,23.pptx
MAR,23.pptx
 
Hossam CV-FEB2016
Hossam CV-FEB2016Hossam CV-FEB2016
Hossam CV-FEB2016
 
CV of Instrumentation Consultant_Rashesh Shah_32 years plus exp
CV of Instrumentation Consultant_Rashesh Shah_32 years plus expCV of Instrumentation Consultant_Rashesh Shah_32 years plus exp
CV of Instrumentation Consultant_Rashesh Shah_32 years plus exp
 
Oil & Gas technical training courses
Oil & Gas technical training coursesOil & Gas technical training courses
Oil & Gas technical training courses
 
IRJET - Recovery of Energy from Exhaust Air of Textile Industry with the ...
IRJET -  	  Recovery of Energy from Exhaust Air of Textile Industry with the ...IRJET -  	  Recovery of Energy from Exhaust Air of Textile Industry with the ...
IRJET - Recovery of Energy from Exhaust Air of Textile Industry with the ...
 
Almoustafa_-2015_CV2nn
Almoustafa_-2015_CV2nnAlmoustafa_-2015_CV2nn
Almoustafa_-2015_CV2nn
 

Bonus Justification Presentation

  • 1. March 2013 April 2013 May 2013 June 2013 July 2013 Completion of Autoslate/CO DEFINITION OF SUBSTANTIAL COMPLETION TO SUPPORT WET SHEET – JUNE 20, 2013. FIRST OBSERVED WET SHEET RUNS JUNE 22, 2013. FEE MATRIX PROPOSAL MILESTONES PERFORMANCE. 85% INCREASE in WORK HOURS150% INCREASE in FEET of CONDUIT360% INCREASE in # of PANELS AVERAGE OF 40 DAYS IN PUSH TO FINAL ISSUE TOTAL OF 61 REVISIONS ISSUED SAFETY 1) 0 Recordables 5 Near miss 80 safety classes 850 safety orientations, 3,000 SPA's . Max 1 day SPA's 57, 405 Hot work permits, 300 parking permits, 4 safety lunches, $2,000 in safety recognitions conducted, and 93,000 man hours expended 2) Tremendous safety SPA and coordination between plant and Construction ops. As stated above 3,000 SPA's and 405 hot work permits 3) TOP's submitted, System sign off sheets in place, no issues 4) No damages to plant or assets SCHEDULE Construction work critical to wet sheet completed 6/20/13, Wet sheet runs on June 25-26 and ongoing into qualified production runs. 1 or 2 remaining shutdowns planned for weekend of July 20-21 and July 27-28 to complete Autoslate systems. All work to be completed by July 26 and subs to demobilize the site . COST (Total Indicated Cost - TIC - minus FEE) 1) Final target cost goal = $29.3mm 2) Cost per summary report WITHOUT incentive fee = $27,774,583 (thru July 6). This includes 22 submitted change notices including CM 109-Autoslate that was not part of base job. All changes total $3.4mm. Total TIC includes all PO data provided to JE since the start of the job yet excludes CM 900 - these are third party engineering costs that were excluded from cost model estimate PANEL DELIVERY WENT TO END OF PROJECT BONUS JUSTIFICATION ANALYSIS 76 PANELS DELIVERED 1-6 WEEKS LATE