SlideShare a Scribd company logo
United States Government Accountability Office
Washington, DC 20548
Comptroller General
of the United States
Decision
Matter of: Latvian Connection, LLC
File: B-411489
Date: August 11, 2015
Keven L. Barnes, Latvian Connection, LLC, for the protester.
CPT Ahsan M. Nasar, and Scott N. Flesch, Esq., Department of the Army, for the
agency.
Katherine I. Riback, Esq., and Jonathan L. Kang, Esq., Office of the General
Counsel, GAO, participated in the preparation of the decision.
DIGEST
Protester’s contention that it did not have a reasonable amount of time to respond to
a solicitation amendment is sustained where the record shows that the protester did
not have constructive notice of the issuance of the amendment, and did not learn of
the amendment until less than 2 business days prior to the revised closing date.
DECISION
Latvian Connection, LLC, of Healdsburg, California, a small business, challenges
the terms of request for proposals (RFP) No. W912D1-15-R-0014, issued by the
Department of the Army to provide and install sunshade canopies at various sites in
Kuwait. Specifically, the protester argues that the agency did not provide it
adequate time to respond to an amendment to the RFP.
We sustain the protest.
BACKGROUND
The Army issued the solicitation on March 20, 2015, to procure sunshade canopies
of various dimensions. The RFP anticipates the award of a fixed-price contract with
a cost-reimbursement contract line item number (CLIN) for Defense Base Act
Page 2 B-411489
insurance.1
RFP at 6. The anticipated value of the contract exceeds $25,000.
Email from Agency to GAO (Aug. 4, 2015).
As relevant here, the RFP provides that “all offerors must submit an electronic
proposal to the Contracting Officer and Contract Specialist.” RFP at 57. The initial
solicitation listed an email address for the contract specialist in three places in the
solicitation, including “Contracting Office Points of Contact.” Id. at 40, 54, 56. The
initial solicitation also included an incorrect version of the contract specialist’s email
in a section regarding the site visit.2
Id. at 40. Before proposals were due, the
protester sent the agency a question via email about a Defense Federal Acquisition
Regulations Supplement (DFARS) § 252.236-7001 contract drawing. AR, Tab 8,
Email from Latvian Connection to the Army (Apr. 15, 2015). This email was
correctly addressed to the contracting officer and the contract specialist. Id.
Latvian Connection submitted its initial proposal on April 20. This proposal was
sent to the email address listed for the original contracting officer, and was also sent
to the incorrect address for the contract specialist. AR, Tab 10, Email from Latvian
Connection of Initial Proposal to Army (April 20, 2015). As the agency explains, the
original contracting officer was away on temporary duty at the time for receipt of
proposals, and was therefore not aware that Latvian Connection had submitted a
proposal. AR at 2. The contract specialist did not receive the proposal because of
the error in the email address used by the protester. Id.
Shortly before proposals were due, the record shows that on April 11, the agency
assigned a new contracting officer to the procurement; the agency, however, did not
update the solicitation to reflect the identity of the new contracting officer until
April 28. Id. at 3 n.1. On April 28, the agency issued RFP amendment No. 4, which
set forth the revised dimensions of the sunshades, provided revised instructions for
the submission of proposals, provided contact information for the new contracting
officer, and established a new deadline for the submission of proposals of 3 p.m.
Kuwait Local Time on May 4. AR, Tab 11, RFP amend. No. 4 (Apr. 28, 2015). The
agency states that although it provided copies of amendment No. 4 to the offerors
that submitted initial proposals, the agency did not provide a copy to Latvian
Connection. AR at 4. The agency explains that it did not provide a copy of the
1
While the agency states that it issued the original solicitation and amendments
using Federal Acquisition Regulation (FAR) part 13 simplified acquisition
procedures, and that its actions were consistent with such procedures, the agency
acknowledges that the solicitation was silent as to whether it followed FAR part 13
or part 15 procedures. Agency Report (AR) at 8.
2
The error was a second period in the email address, which resulted in an address
similar to the following: John..A.Doe.civ@mail.mil.
Page 3 B-411489
amendment to Latvian Connection because it was not aware that the protester had
submitted a proposal. The agency explains it was not aware because Latvian
Connection’s initial proposal was sent to the incorrect address for the contract
specialist, and because the original contracting officer was away on temporary duty
at the time the proposal was submitted and was not aware that he had received it.
AR at 4.
The agency also posted RFP amendment No. 4 on the Army Single Face to
Industry (ASFI) website on April 28. AR, Tab 13, Affidavit of Contract Specialist
(May 28, 2015). The protester states that it became aware of amendment No. 4 on
May 2 (Saturday)--two days before proposals were due on Monday, May 4--from
the posting on the ASFI website. Protester’s Email to GAO (July 5, 2015) at 3;
Protester’s Email to GAO (Aug. 3, 2014).
On Sunday, May 3, Latvian Connection submitted its protest to our Office,
complaining that the Army had failed to advise it of the change to the solicitation,
and failed to provide sufficient time for a response. The protest was docketed by
our Office on Monday, May 4, at 8:30 a.m., Eastern Time--which was 30 minutes
after the specified closing time of 3:00 p.m., local Kuwait time.3
On Monday, May 4, the protester submitted its revised proposal to the original
contracting officer (rather than the new contracting officer) and to the contract
specialist, using the same incorrect email address for this individual that had been
used to submit the protester’s initial proposal. AR, Tab 15, Email from Latvian
Connection to Army of Revised Proposal (May 4, 2015). The previous contracting
officer received Latvian Connection’s proposal at 3:02 p.m., Kuwait local time.
The Army requested that our Office dismiss the protest on the grounds that Latvian
Connection was not an interested party because it had not submitted a proposal in
response to the solicitation. Army Request for Dismissal (May 13, 2015). Latvian
Connection responded that it submitted its initial proposal on April 20, and provided
documentation reflecting its submission. Latvian Connection Response to Request
for Summary Dismissal (May 15, 2015). Our Office denied the agency’s request for
dismissal and asked the agency to submit a report that addressed the merits of the
protest. GAO Denial of Agency Request for Summary Dismissal (May 19, 2015).
3
Kuwait is located in the Arabia time zone, which is 7 hours ahead of the Eastern
Time zone. AR at 8.
Page 4 B-411489
DISCUSSION
Latvian Connection argues that it was not afforded sufficient time in which to
respond to amendment No. 4, specifically the requirement to submit a new proposal
addressing the revised sunshade canopy dimensions. Protest at 2; Protester’s
Comments at 12. Latvian Connection argues that its protest is timely because it
learned of amendment No. 4 on May 2, and filed a protest with our Office within less
than one business day. The protester also argues that the issuance of amendment
No. 4 was improper because the Army failed to restrict the procurement to the
offerors that submitted initial proposals, as required by FAR § 15.206. For the
reasons discussed below, we conclude that the protester was not provided a
reasonable amount of time to respond to RFP amendment No. 4, and we sustain
the protest on this basis.
The Army first argues that the protest is untimely because it was not filed prior to
the revised closing time of May 4 at 3:00 p.m., Kuwait local time--which was
8:00 a.m., Eastern Time. AR at 8. The Army notes that Latvian Connection’s
protest was time/date stamped by our Office on May 4 at 8:30 a.m., Eastern Time,
which was 30 minutes after the specified closing time of 3:00 p.m., local Kuwait
time. Id. For the reasons discussed below, we conclude that the protest is timely.
The Army is correct that our Bid Protest Regulations require that a protest based
upon alleged improprieties in a solicitation that are apparent prior to the closing time
for receipt of initial proposals must be filed before that time. 4 C.F.R. § 21.2(a)(1).
This rule includes protests that challenge alleged improprieties that did not exist in
the initial solicitation but which are subsequently incorporated into it; in such cases,
the solicitation must be protested not later than the next closing time for receipt of
proposals following the incorporation. Id.; see Cessna Aircraft Co., B-261953.5,
Feb. 5, 1996, 96-1 CPD ¶ 132 at 16. In this respect, our timeliness rules reflect the
dual requirements of giving parties a fair opportunity to present their cases and
resolving protests expeditiously without unduly disrupting or delaying the
procurement process. Dominion Aviation, Inc.--Recon., B-275419.4, Feb. 24, 1998,
98-1 CPD ¶ 62 at 3.
The Army is also correct that our Regulations provide that a document, including a
protest, is considered filed “on a particular day when it is received by GAO by
5:30 p.m., Eastern Time, on that day.” 4 C.F.R. § 21.0(f). Further, our Office has
explained that a document filed after 5:30 p.m. Eastern Time, on a particular day, is
considered filed at 8:30 a.m., Eastern Time, the next day our Office is open. Guam
Shipyard, B-294287, Sept. 16, 2004, 2004 CPD ¶ 181 at 3. For this reason, Latvian
Connection’s protest, which was submitted to our Office via email on Sunday,
May 3, was considered filed at 8:30 a.m., Eastern Time, on Monday, May 4.
We nonetheless conclude that the protest was timely filed. The Army does not
dispute the protester’s representation that it received actual knowledge of the
Page 5 B-411489
amendment after our Office closed on Friday, May 1 (at 5:30 p.m., Eastern Time).
Because our Office was closed when Latvian Connection learned of amendment
No. 4, and because the solicitation’s closing date was prior to our Office reopening
on the following Monday (May 4, 8:30 a.m., Eastern Time), it was impossible for the
protester to file its protest prior to the time for receipt of revised proposals. Under
these circumstances, where the agency’s actions preclude the possibility of filing a
timely challenge to the terms of a solicitation, our Office has held that the timeliness
rule of 4 C.F.R. § 21.2(a)(1), which requires protests to be filed prior to the time for
receipt of proposals, does not apply; instead, the 10-day rule of 4 C.F.R.
§ 21.2(a)(2) applies. Immediate Systems Resources, Inc., B-292856, Dec. 9, 2003,
2003 CPD ¶ 227 at 4; Morrison Knudsen Corp., B-247160, Jan. 7, 1992, 92-1 CPD
¶ 35 at 2. Since Latvian Connection’s protest was filed 2 days after it became
aware of its basis of protest, in this case the short response time allowed by
amendment No. 4, we find that the protest is timely.
For the record, we also disagree with the Army’s argument that the protester had
constructive knowledge of amendment No. 4 as of April 28, the date the agency
posted amendment No. 4 on the AFSI website. The AFSI website is not a
government-wide point of entry (GPE) designated for the publication of solicitations.
Instead, FedBizOpps has been designated as the GPE--that is, the single point
where government business opportunities greater than $25,000 (such as the
solicitation here), including synopses of proposed contract actions, solicitations, and
associated information, can be accessed electronically by the public. FAR
§§ 5.101, 5.101(a)(1), 5.102.4
While offerors are charged with constructive notice
of procurement actions published on the GPE, Latvian Connection did not have
constructive notice in this instance because AFSI is not the GPE. See DBI Waste
Sys., Inc., B-400687, B-400687.2, Jan. 12, 2009, 2009 CPD ¶ 15 at 2.
We next consider whether Latvian Connection was afforded sufficient time in which
to prepare a proposal in response to amendment No. 4. The Competition in
Contracting Act of 1984 generally requires contracting agencies to obtain full and
open competition through the use of competitive procedures, 10 U.S.C.
§ 2304(a)(1)(A), the dual purpose of which is to ensure that a procurement is open
to all responsible sources and to provide the government with the opportunity to
receive fair and reasonable prices. Kendall Healthcare Prods. Co., B-289381,
Feb. 19, 2002, 2002 CPD ¶ 42 at 6. In pursuit of these goals, a contracting agency
must use reasonable methods to publicize its procurement needs and to timely
disseminate solicitation documents to those entitled to receive them. Id.
Additionally, agencies must provide potential offerors a reasonable opportunity to
respond. FAR §§ 5.203(b), 13.003(h)(2); see Sabreliner Corp., B-288030,
B-288030.2, Sept. 13, 2001, 2001 CPD ¶ 170 at 6-7. What constitutes a
4
The Army does not argue in response to the protest that this solicitation was
exempt from publication on the GPE.
Page 6 B-411489
reasonable opportunity to respond will depend on “the circumstances of the
individual acquisition, such as complexity, commerciality, availability, and urgency.”
FAR § 5.203(b).
As stated above, we find that the protester first became aware of amendment No. 4
on Saturday, May 2, when it spotted the amendment on the AFSI website. The
protester states that Friday and Saturday are considered non-business days in
Kuwait (where the protester’s representative was located), and that Sunday is
considered a business day. Protester’s Email to GAO (Aug. 3, 2014). This means
that the protester had less than 2 business days in which to respond to amendment
No. 4, specifically to prepare a revised proposal addressing the new sunshade
canopy dimensions.5
Under these circumstances, we find that Latvian Connection
was not provided sufficient time in which to submit a response to the amendment.6
See Information Ventures, Inc., B-293541, Apr. 9, 2004, 2004 CPD ¶ 81 at 4 (where
a December 31, 2003, announcement of the intended award established a
response period from potential sources of one-and-a-half business days (until
January 5, 2004), we held that the agency did not provide a sufficient time in which
to respond).
We next discuss whether Latvian Connection was prejudiced by the Army’s
actions.7
5
The Army itself characterizes these revisions as “substantial.” AR at 3 n.2
(“Because of substantial changes to some required canopy dimensions in
Amendment 0004, offerors that did not submit revised quotes in response to
Amendment 0004 risked having their original quotes deemed nonresponsive . . . .”)
In this regard, the Army acknowledges that it did not notify Latvian
Connection when it sent out an email containing a courtesy copy of amendment
No. 4 to the original offerors on April 28. AR at 5. The agency argues, however,
that Latvian Connection had constructive knowledge of amendment No. 4 by virtue
of the fact that the agency posted it on the ASFI website that same day. AR at 5-6.
Therefore, the agency contends that Latvian Connection was not prejudiced by the
failure of the agency to send it the email that was sent to the original offerors. Id.
at 9. Since as set forth above, we find that the protester had less than 2 business
6
The Army’s response to the protest did not specifically address whether the
amount of time available to the protester, based on its actual knowledge of the
amendment, was adequate to respond to RFP amendment. No. 4.
7
Our Office will not sustain a protest unless the protester demonstrates a
reasonable possibility that it was prejudiced by the agency’s actions, that is, unless
the protester demonstrates that, but for the agency’s actions, it would have had a
substantial chance of receiving the award. McDonald-Bradley, B-270126, Feb. 8,
1996, 96-1 CPD ¶ 54 at 3; see Statistica, Inc., v. Christopher, 102 F.3d 1577, 1581
(Fed. Cir. 1996).
Page 7 B-411489
days to respond to this amendment, we conclude that the protester was prejudiced
by the brief response time here.
The agency also argues that the protester “contributed” to its non-receipt of
amendment No. 4 by incorrectly typing the contract specialist’s email address when
it submitted its initial proposal. Id. at 5. As stated above, the Army failed to meet its
obligation to publicize the issuance of RFP amendment No. 4 through the GPE.
Thus, even if the protester contributed to the agency’s mistaken belief that the
protester had not submitted an initial proposal, the protester could have received
notice of the amendment through the GPE. For this reason, we conclude that any
errors on the part of the protester concerning the email addresses used to transmit
its initial proposal were superseded by the agency’s failure to properly publicize
RFP amendment No. 4.8
Finally, Latvian Connection argues that the issuance of RFP amendment No. 4 was
improper because the Army failed to restrict the procurement to the offerors that
submitted initial proposals, as required by FAR § 15.206. Protest at 1. As stated
above the solicitation did not specifically address whether the competition would
follow FAR part 13 or part 15 procedures. AR at 8. To the extent the protester
argues that the agency should have specified that FAR part 15 procedures applied,
this was an apparent solicitation impropriety that, to be timely, should have been
challenged before initial proposals were due, on April 20. See 4 C.F.R.
§ 21.2(a)(1). In any event the Army states that it did not receive proposals from any
offerors that had not already submitted a proposal in response to the original
solicitation. AR at 9; Declaration of Contract Specialist (May 28, 2015) at 2. We
therefore find no merit to this aspect of the protest.
CONCLUSION AND RECOMMENDATION
We find that the Army did not provide Latvian Connection a reasonable time in
which to respond to RFP amendment No. 4. We find that the agency’s actions here
prejudiced the protester, and contributed to the late receipt of the protester’s
proposal. We recommend that the agency reissue amendment No. 4, with sufficient
time for offerors to respond, and that the agency evaluate all timely proposals. We
8
Although the protester submitted a proposal in response to RFP amendment
No. 4, this proposal was not timely received by the Army. Here too, the agency’s
failure to provide Latvian Connection with a copy of the amendment, or to publicize
the amendment on the GPE, resulted in the protester lacking an adequate amount
of time to prepare its proposal. For this reason, the fact that Latvian Connection
submitted a late proposal in response to RFP amendment No. 4 does not affect our
conclusion that the Army’s actions here were improper, and that they prejudiced the
protester.
Page 8 B-411489
also recommend that the agency reimburse Latvian Connection its costs associated
with filing and pursuing the protest. Bid Protest Regulations, 4 C.F.R. § 21.8(d).
The protester’s certified claims for costs, detailing the time expended and costs
incurred, must be submitted to the agency within 60 days after the receipt of this
decision. Id. at § 21.8(f).
The protest is sustained
Susan A. Poling
General Counsel

More Related Content

What's hot

Sc order freedom of rel act
Sc order freedom of rel actSc order freedom of rel act
Sc order freedom of rel act
sabrangsabrang
 
Bsy order
Bsy orderBsy order
Bsy order
ZahidManiyar
 
PPH Pilot Program between japan and vietnam
PPH Pilot Program between japan and vietnamPPH Pilot Program between japan and vietnam
PPH Pilot Program between japan and vietnam
Nguyen Hoa Binh (Bill)
 
About secp the companies registration offices regulations,2003_5
About secp the companies  registration offices regulations,2003_5About secp the companies  registration offices regulations,2003_5
About secp the companies registration offices regulations,2003_5Ali Raza
 
20220311 gauhati hc order in hbs comments on eviction case
20220311 gauhati hc order in hbs comments on eviction case20220311 gauhati hc order in hbs comments on eviction case
20220311 gauhati hc order in hbs comments on eviction case
sabrangsabrang
 
Training Session: 1 Indian Patent Process: Study of Forms
Training Session: 1 Indian Patent Process: Study of FormsTraining Session: 1 Indian Patent Process: Study of Forms
Training Session: 1 Indian Patent Process: Study of Forms
BananaIP Counsels
 
61306823 common-law-case
61306823 common-law-case61306823 common-law-case
61306823 common-law-case
homeworkping4
 
Can covid vaccines be used or acquired by Government?
Can covid vaccines be used or acquired by Government?Can covid vaccines be used or acquired by Government?
Can covid vaccines be used or acquired by Government?
DVSResearchFoundatio
 

What's hot (9)

Sc order freedom of rel act
Sc order freedom of rel actSc order freedom of rel act
Sc order freedom of rel act
 
Bsy order
Bsy orderBsy order
Bsy order
 
PPH Pilot Program between japan and vietnam
PPH Pilot Program between japan and vietnamPPH Pilot Program between japan and vietnam
PPH Pilot Program between japan and vietnam
 
6002
60026002
6002
 
About secp the companies registration offices regulations,2003_5
About secp the companies  registration offices regulations,2003_5About secp the companies  registration offices regulations,2003_5
About secp the companies registration offices regulations,2003_5
 
20220311 gauhati hc order in hbs comments on eviction case
20220311 gauhati hc order in hbs comments on eviction case20220311 gauhati hc order in hbs comments on eviction case
20220311 gauhati hc order in hbs comments on eviction case
 
Training Session: 1 Indian Patent Process: Study of Forms
Training Session: 1 Indian Patent Process: Study of FormsTraining Session: 1 Indian Patent Process: Study of Forms
Training Session: 1 Indian Patent Process: Study of Forms
 
61306823 common-law-case
61306823 common-law-case61306823 common-law-case
61306823 common-law-case
 
Can covid vaccines be used or acquired by Government?
Can covid vaccines be used or acquired by Government?Can covid vaccines be used or acquired by Government?
Can covid vaccines be used or acquired by Government?
 

Similar to B-411489_1__LATVIAN_CONNECTION__LLC__ ( OFFICIAL GPE IS FBO )

B-409627 NEGATIVE DETERMINATION AEROSAGE LLC (2)
B-409627   NEGATIVE DETERMINATION   AEROSAGE LLC (2)B-409627   NEGATIVE DETERMINATION   AEROSAGE LLC (2)
B-409627 NEGATIVE DETERMINATION AEROSAGE LLC (2)Keven Barnes
 
181100347 social-legislation-digested-cases
181100347 social-legislation-digested-cases181100347 social-legislation-digested-cases
181100347 social-legislation-digested-cases
homeworkping10
 
20150305 Verified Answer
20150305 Verified Answer20150305 Verified Answer
20150305 Verified AnswerKrystina Smith
 
Process of patent filling,patent infringement & its issues (1)
Process of patent filling,patent infringement & its issues (1)Process of patent filling,patent infringement & its issues (1)
Process of patent filling,patent infringement & its issues (1)
Ankit Puri
 
2011.05.06 Sagent Counterclaim Against Infusive
2011.05.06 Sagent Counterclaim Against Infusive2011.05.06 Sagent Counterclaim Against Infusive
2011.05.06 Sagent Counterclaim Against Infusive
Hindenburg Research
 
Aristocrat technologies 15 dec2008
Aristocrat technologies 15 dec2008Aristocrat technologies 15 dec2008
Aristocrat technologies 15 dec2008Sondhaya Sudhamasapa
 
Challenge to Administrative Authority
Challenge to Administrative AuthorityChallenge to Administrative Authority
Challenge to Administrative AuthorityTracie Groh, J.D.
 
Rio Grande LNG Opposition to Motions to Intervene
Rio Grande LNG Opposition to Motions to InterveneRio Grande LNG Opposition to Motions to Intervene
Rio Grande LNG Opposition to Motions to Intervene
Marcellus Drilling News
 
Patent bar practice questions april 2003
Patent bar practice questions   april 2003Patent bar practice questions   april 2003
Patent bar practice questions april 2003
Bradley Sands
 
Reissue 1400 questions
Reissue 1400 questionsReissue 1400 questions
Reissue 1400 questions
Leon Li
 
Opposition Proceedings under Trademarks Act, 1999
Opposition Proceedings under Trademarks Act, 1999Opposition Proceedings under Trademarks Act, 1999
Opposition Proceedings under Trademarks Act, 1999
DVSResearchFoundatio
 
Latest rti letters
Latest rti lettersLatest rti letters
Latest rti letters
bansi default
 
Order Fided 04 08-2016
Order Fided 04 08-2016Order Fided 04 08-2016
Order Fided 04 08-2016
Alvin Sutherlin, Jr
 
Income Tax Appellate Tribunal has no power to stay prosecution of taxpayers i...
Income Tax Appellate Tribunal has no power to stay prosecution of taxpayers i...Income Tax Appellate Tribunal has no power to stay prosecution of taxpayers i...
Income Tax Appellate Tribunal has no power to stay prosecution of taxpayers i...
D Murali ☆
 
Credit given for all answers
Credit given for all answersCredit given for all answers
Credit given for all answers
Leon Li
 
City Water International Inc. v. Great Canadian Oil Change
City Water International Inc. v. Great Canadian Oil ChangeCity Water International Inc. v. Great Canadian Oil Change
City Water International Inc. v. Great Canadian Oil ChangeMatthew Riddell
 
Processofpatentfilling
ProcessofpatentfillingProcessofpatentfilling
Processofpatentfilling
Yogeshvar Tyagi
 
Memorandum of Adjudicator-final1
Memorandum of Adjudicator-final1Memorandum of Adjudicator-final1
Memorandum of Adjudicator-final1Adnan Alam
 

Similar to B-411489_1__LATVIAN_CONNECTION__LLC__ ( OFFICIAL GPE IS FBO ) (20)

B-409627 NEGATIVE DETERMINATION AEROSAGE LLC (2)
B-409627   NEGATIVE DETERMINATION   AEROSAGE LLC (2)B-409627   NEGATIVE DETERMINATION   AEROSAGE LLC (2)
B-409627 NEGATIVE DETERMINATION AEROSAGE LLC (2)
 
181100347 social-legislation-digested-cases
181100347 social-legislation-digested-cases181100347 social-legislation-digested-cases
181100347 social-legislation-digested-cases
 
20150305 Verified Answer
20150305 Verified Answer20150305 Verified Answer
20150305 Verified Answer
 
Process of patent filling,patent infringement & its issues (1)
Process of patent filling,patent infringement & its issues (1)Process of patent filling,patent infringement & its issues (1)
Process of patent filling,patent infringement & its issues (1)
 
2011.05.06 Sagent Counterclaim Against Infusive
2011.05.06 Sagent Counterclaim Against Infusive2011.05.06 Sagent Counterclaim Against Infusive
2011.05.06 Sagent Counterclaim Against Infusive
 
Aristocrat technologies 15 dec2008
Aristocrat technologies 15 dec2008Aristocrat technologies 15 dec2008
Aristocrat technologies 15 dec2008
 
writing sample
writing samplewriting sample
writing sample
 
Challenge to Administrative Authority
Challenge to Administrative AuthorityChallenge to Administrative Authority
Challenge to Administrative Authority
 
Rio Grande LNG Opposition to Motions to Intervene
Rio Grande LNG Opposition to Motions to InterveneRio Grande LNG Opposition to Motions to Intervene
Rio Grande LNG Opposition to Motions to Intervene
 
Ca2 db241675 01
Ca2 db241675 01Ca2 db241675 01
Ca2 db241675 01
 
Patent bar practice questions april 2003
Patent bar practice questions   april 2003Patent bar practice questions   april 2003
Patent bar practice questions april 2003
 
Reissue 1400 questions
Reissue 1400 questionsReissue 1400 questions
Reissue 1400 questions
 
Opposition Proceedings under Trademarks Act, 1999
Opposition Proceedings under Trademarks Act, 1999Opposition Proceedings under Trademarks Act, 1999
Opposition Proceedings under Trademarks Act, 1999
 
Latest rti letters
Latest rti lettersLatest rti letters
Latest rti letters
 
Order Fided 04 08-2016
Order Fided 04 08-2016Order Fided 04 08-2016
Order Fided 04 08-2016
 
Income Tax Appellate Tribunal has no power to stay prosecution of taxpayers i...
Income Tax Appellate Tribunal has no power to stay prosecution of taxpayers i...Income Tax Appellate Tribunal has no power to stay prosecution of taxpayers i...
Income Tax Appellate Tribunal has no power to stay prosecution of taxpayers i...
 
Credit given for all answers
Credit given for all answersCredit given for all answers
Credit given for all answers
 
City Water International Inc. v. Great Canadian Oil Change
City Water International Inc. v. Great Canadian Oil ChangeCity Water International Inc. v. Great Canadian Oil Change
City Water International Inc. v. Great Canadian Oil Change
 
Processofpatentfilling
ProcessofpatentfillingProcessofpatentfilling
Processofpatentfilling
 
Memorandum of Adjudicator-final1
Memorandum of Adjudicator-final1Memorandum of Adjudicator-final1
Memorandum of Adjudicator-final1
 

More from Keven Barnes

USF DIPLOMA - KEVEN L. BARNES
USF DIPLOMA - KEVEN L. BARNESUSF DIPLOMA - KEVEN L. BARNES
USF DIPLOMA - KEVEN L. BARNESKeven Barnes
 
ATTCH 4 GAO ATTORNY BURRIS - LATVIAN IS INTERESTED BIDDER
ATTCH 4   GAO ATTORNY BURRIS - LATVIAN IS INTERESTED BIDDERATTCH 4   GAO ATTORNY BURRIS - LATVIAN IS INTERESTED BIDDER
ATTCH 4 GAO ATTORNY BURRIS - LATVIAN IS INTERESTED BIDDERKeven Barnes
 
Report Number ISP-C-10-23, February 2010 ( SBU - FEDBID )
Report Number ISP-C-10-23, February 2010  ( SBU  - FEDBID )Report Number ISP-C-10-23, February 2010  ( SBU  - FEDBID )
Report Number ISP-C-10-23, February 2010 ( SBU - FEDBID )Keven Barnes
 
Key Army commander accused of steering a contract to ex-classmates - The Wash...
Key Army commander accused of steering a contract to ex-classmates - The Wash...Key Army commander accused of steering a contract to ex-classmates - The Wash...
Key Army commander accused of steering a contract to ex-classmates - The Wash...Keven Barnes
 
ATTCH 15 11-032redacted ( $ 1 BILLION WRONGLY GIVEN TO DYNCORP SOLE SOURCE )
ATTCH 15  11-032redacted  ( $ 1 BILLION WRONGLY GIVEN TO DYNCORP SOLE SOURCE )ATTCH 15  11-032redacted  ( $ 1 BILLION WRONGLY GIVEN TO DYNCORP SOLE SOURCE )
ATTCH 15 11-032redacted ( $ 1 BILLION WRONGLY GIVEN TO DYNCORP SOLE SOURCE )Keven Barnes
 
Executive Office of the President OBAMA June 6, 2012 memo
Executive Office of the President OBAMA   June 6, 2012 memoExecutive Office of the President OBAMA   June 6, 2012 memo
Executive Office of the President OBAMA June 6, 2012 memoKeven Barnes
 
B-407391 LatvianRedacted SBA LEGAL OPINION
B-407391   LatvianRedacted   SBA LEGAL OPINIONB-407391   LatvianRedacted   SBA LEGAL OPINION
B-407391 LatvianRedacted SBA LEGAL OPINIONKeven Barnes
 
SENIOR SBA ATTORNEY Latvian - SBA INTERPRETS FAR FOR STATE DEPARTMENT, GA...
SENIOR SBA ATTORNEY   Latvian   - SBA INTERPRETS FAR FOR STATE DEPARTMENT, GA...SENIOR SBA ATTORNEY   Latvian   - SBA INTERPRETS FAR FOR STATE DEPARTMENT, GA...
SENIOR SBA ATTORNEY Latvian - SBA INTERPRETS FAR FOR STATE DEPARTMENT, GA...Keven Barnes
 
SBA COMMENTS B-408633
SBA   COMMENTS   B-408633SBA   COMMENTS   B-408633
SBA COMMENTS B-408633Keven Barnes
 
DD FORM 2579 REVISED AUG 2015
DD FORM 2579 REVISED AUG 2015DD FORM 2579 REVISED AUG 2015
DD FORM 2579 REVISED AUG 2015Keven Barnes
 
Federal Register _ Small Business Mentor Protégé Programs LATVIAN SBA FINAL ...
Federal Register _ Small Business Mentor Protégé Programs LATVIAN  SBA FINAL ...Federal Register _ Small Business Mentor Protégé Programs LATVIAN  SBA FINAL ...
Federal Register _ Small Business Mentor Protégé Programs LATVIAN SBA FINAL ...Keven Barnes
 
GAO Doubles Down On FedBid_COC Ruling B-410947 B-410981
GAO Doubles Down On FedBid_COC Ruling   B-410947   B-410981GAO Doubles Down On FedBid_COC Ruling   B-410947   B-410981
GAO Doubles Down On FedBid_COC Ruling B-410947 B-410981Keven Barnes
 
Small Business's FedBid Suspension Was Improper - SmallGovCon
Small Business's FedBid Suspension Was Improper - SmallGovConSmall Business's FedBid Suspension Was Improper - SmallGovCon
Small Business's FedBid Suspension Was Improper - SmallGovConKeven Barnes
 
ATTCH 2 LatvianB-410947Final ( SBA OPINION )
ATTCH 2   LatvianB-410947Final  ( SBA OPINION )ATTCH 2   LatvianB-410947Final  ( SBA OPINION )
ATTCH 2 LatvianB-410947Final ( SBA OPINION )Keven Barnes
 
SDVOSB LATVIAN CONNECTION LLC STATEMENT
SDVOSB LATVIAN CONNECTION LLC    STATEMENTSDVOSB LATVIAN CONNECTION LLC    STATEMENT
SDVOSB LATVIAN CONNECTION LLC STATEMENTKeven Barnes
 

More from Keven Barnes (15)

USF DIPLOMA - KEVEN L. BARNES
USF DIPLOMA - KEVEN L. BARNESUSF DIPLOMA - KEVEN L. BARNES
USF DIPLOMA - KEVEN L. BARNES
 
ATTCH 4 GAO ATTORNY BURRIS - LATVIAN IS INTERESTED BIDDER
ATTCH 4   GAO ATTORNY BURRIS - LATVIAN IS INTERESTED BIDDERATTCH 4   GAO ATTORNY BURRIS - LATVIAN IS INTERESTED BIDDER
ATTCH 4 GAO ATTORNY BURRIS - LATVIAN IS INTERESTED BIDDER
 
Report Number ISP-C-10-23, February 2010 ( SBU - FEDBID )
Report Number ISP-C-10-23, February 2010  ( SBU  - FEDBID )Report Number ISP-C-10-23, February 2010  ( SBU  - FEDBID )
Report Number ISP-C-10-23, February 2010 ( SBU - FEDBID )
 
Key Army commander accused of steering a contract to ex-classmates - The Wash...
Key Army commander accused of steering a contract to ex-classmates - The Wash...Key Army commander accused of steering a contract to ex-classmates - The Wash...
Key Army commander accused of steering a contract to ex-classmates - The Wash...
 
ATTCH 15 11-032redacted ( $ 1 BILLION WRONGLY GIVEN TO DYNCORP SOLE SOURCE )
ATTCH 15  11-032redacted  ( $ 1 BILLION WRONGLY GIVEN TO DYNCORP SOLE SOURCE )ATTCH 15  11-032redacted  ( $ 1 BILLION WRONGLY GIVEN TO DYNCORP SOLE SOURCE )
ATTCH 15 11-032redacted ( $ 1 BILLION WRONGLY GIVEN TO DYNCORP SOLE SOURCE )
 
Executive Office of the President OBAMA June 6, 2012 memo
Executive Office of the President OBAMA   June 6, 2012 memoExecutive Office of the President OBAMA   June 6, 2012 memo
Executive Office of the President OBAMA June 6, 2012 memo
 
B-407391 LatvianRedacted SBA LEGAL OPINION
B-407391   LatvianRedacted   SBA LEGAL OPINIONB-407391   LatvianRedacted   SBA LEGAL OPINION
B-407391 LatvianRedacted SBA LEGAL OPINION
 
SENIOR SBA ATTORNEY Latvian - SBA INTERPRETS FAR FOR STATE DEPARTMENT, GA...
SENIOR SBA ATTORNEY   Latvian   - SBA INTERPRETS FAR FOR STATE DEPARTMENT, GA...SENIOR SBA ATTORNEY   Latvian   - SBA INTERPRETS FAR FOR STATE DEPARTMENT, GA...
SENIOR SBA ATTORNEY Latvian - SBA INTERPRETS FAR FOR STATE DEPARTMENT, GA...
 
SBA COMMENTS B-408633
SBA   COMMENTS   B-408633SBA   COMMENTS   B-408633
SBA COMMENTS B-408633
 
DD FORM 2579 REVISED AUG 2015
DD FORM 2579 REVISED AUG 2015DD FORM 2579 REVISED AUG 2015
DD FORM 2579 REVISED AUG 2015
 
Federal Register _ Small Business Mentor Protégé Programs LATVIAN SBA FINAL ...
Federal Register _ Small Business Mentor Protégé Programs LATVIAN  SBA FINAL ...Federal Register _ Small Business Mentor Protégé Programs LATVIAN  SBA FINAL ...
Federal Register _ Small Business Mentor Protégé Programs LATVIAN SBA FINAL ...
 
GAO Doubles Down On FedBid_COC Ruling B-410947 B-410981
GAO Doubles Down On FedBid_COC Ruling   B-410947   B-410981GAO Doubles Down On FedBid_COC Ruling   B-410947   B-410981
GAO Doubles Down On FedBid_COC Ruling B-410947 B-410981
 
Small Business's FedBid Suspension Was Improper - SmallGovCon
Small Business's FedBid Suspension Was Improper - SmallGovConSmall Business's FedBid Suspension Was Improper - SmallGovCon
Small Business's FedBid Suspension Was Improper - SmallGovCon
 
ATTCH 2 LatvianB-410947Final ( SBA OPINION )
ATTCH 2   LatvianB-410947Final  ( SBA OPINION )ATTCH 2   LatvianB-410947Final  ( SBA OPINION )
ATTCH 2 LatvianB-410947Final ( SBA OPINION )
 
SDVOSB LATVIAN CONNECTION LLC STATEMENT
SDVOSB LATVIAN CONNECTION LLC    STATEMENTSDVOSB LATVIAN CONNECTION LLC    STATEMENT
SDVOSB LATVIAN CONNECTION LLC STATEMENT
 

B-411489_1__LATVIAN_CONNECTION__LLC__ ( OFFICIAL GPE IS FBO )

  • 1. United States Government Accountability Office Washington, DC 20548 Comptroller General of the United States Decision Matter of: Latvian Connection, LLC File: B-411489 Date: August 11, 2015 Keven L. Barnes, Latvian Connection, LLC, for the protester. CPT Ahsan M. Nasar, and Scott N. Flesch, Esq., Department of the Army, for the agency. Katherine I. Riback, Esq., and Jonathan L. Kang, Esq., Office of the General Counsel, GAO, participated in the preparation of the decision. DIGEST Protester’s contention that it did not have a reasonable amount of time to respond to a solicitation amendment is sustained where the record shows that the protester did not have constructive notice of the issuance of the amendment, and did not learn of the amendment until less than 2 business days prior to the revised closing date. DECISION Latvian Connection, LLC, of Healdsburg, California, a small business, challenges the terms of request for proposals (RFP) No. W912D1-15-R-0014, issued by the Department of the Army to provide and install sunshade canopies at various sites in Kuwait. Specifically, the protester argues that the agency did not provide it adequate time to respond to an amendment to the RFP. We sustain the protest. BACKGROUND The Army issued the solicitation on March 20, 2015, to procure sunshade canopies of various dimensions. The RFP anticipates the award of a fixed-price contract with a cost-reimbursement contract line item number (CLIN) for Defense Base Act
  • 2. Page 2 B-411489 insurance.1 RFP at 6. The anticipated value of the contract exceeds $25,000. Email from Agency to GAO (Aug. 4, 2015). As relevant here, the RFP provides that “all offerors must submit an electronic proposal to the Contracting Officer and Contract Specialist.” RFP at 57. The initial solicitation listed an email address for the contract specialist in three places in the solicitation, including “Contracting Office Points of Contact.” Id. at 40, 54, 56. The initial solicitation also included an incorrect version of the contract specialist’s email in a section regarding the site visit.2 Id. at 40. Before proposals were due, the protester sent the agency a question via email about a Defense Federal Acquisition Regulations Supplement (DFARS) § 252.236-7001 contract drawing. AR, Tab 8, Email from Latvian Connection to the Army (Apr. 15, 2015). This email was correctly addressed to the contracting officer and the contract specialist. Id. Latvian Connection submitted its initial proposal on April 20. This proposal was sent to the email address listed for the original contracting officer, and was also sent to the incorrect address for the contract specialist. AR, Tab 10, Email from Latvian Connection of Initial Proposal to Army (April 20, 2015). As the agency explains, the original contracting officer was away on temporary duty at the time for receipt of proposals, and was therefore not aware that Latvian Connection had submitted a proposal. AR at 2. The contract specialist did not receive the proposal because of the error in the email address used by the protester. Id. Shortly before proposals were due, the record shows that on April 11, the agency assigned a new contracting officer to the procurement; the agency, however, did not update the solicitation to reflect the identity of the new contracting officer until April 28. Id. at 3 n.1. On April 28, the agency issued RFP amendment No. 4, which set forth the revised dimensions of the sunshades, provided revised instructions for the submission of proposals, provided contact information for the new contracting officer, and established a new deadline for the submission of proposals of 3 p.m. Kuwait Local Time on May 4. AR, Tab 11, RFP amend. No. 4 (Apr. 28, 2015). The agency states that although it provided copies of amendment No. 4 to the offerors that submitted initial proposals, the agency did not provide a copy to Latvian Connection. AR at 4. The agency explains that it did not provide a copy of the 1 While the agency states that it issued the original solicitation and amendments using Federal Acquisition Regulation (FAR) part 13 simplified acquisition procedures, and that its actions were consistent with such procedures, the agency acknowledges that the solicitation was silent as to whether it followed FAR part 13 or part 15 procedures. Agency Report (AR) at 8. 2 The error was a second period in the email address, which resulted in an address similar to the following: John..A.Doe.civ@mail.mil.
  • 3. Page 3 B-411489 amendment to Latvian Connection because it was not aware that the protester had submitted a proposal. The agency explains it was not aware because Latvian Connection’s initial proposal was sent to the incorrect address for the contract specialist, and because the original contracting officer was away on temporary duty at the time the proposal was submitted and was not aware that he had received it. AR at 4. The agency also posted RFP amendment No. 4 on the Army Single Face to Industry (ASFI) website on April 28. AR, Tab 13, Affidavit of Contract Specialist (May 28, 2015). The protester states that it became aware of amendment No. 4 on May 2 (Saturday)--two days before proposals were due on Monday, May 4--from the posting on the ASFI website. Protester’s Email to GAO (July 5, 2015) at 3; Protester’s Email to GAO (Aug. 3, 2014). On Sunday, May 3, Latvian Connection submitted its protest to our Office, complaining that the Army had failed to advise it of the change to the solicitation, and failed to provide sufficient time for a response. The protest was docketed by our Office on Monday, May 4, at 8:30 a.m., Eastern Time--which was 30 minutes after the specified closing time of 3:00 p.m., local Kuwait time.3 On Monday, May 4, the protester submitted its revised proposal to the original contracting officer (rather than the new contracting officer) and to the contract specialist, using the same incorrect email address for this individual that had been used to submit the protester’s initial proposal. AR, Tab 15, Email from Latvian Connection to Army of Revised Proposal (May 4, 2015). The previous contracting officer received Latvian Connection’s proposal at 3:02 p.m., Kuwait local time. The Army requested that our Office dismiss the protest on the grounds that Latvian Connection was not an interested party because it had not submitted a proposal in response to the solicitation. Army Request for Dismissal (May 13, 2015). Latvian Connection responded that it submitted its initial proposal on April 20, and provided documentation reflecting its submission. Latvian Connection Response to Request for Summary Dismissal (May 15, 2015). Our Office denied the agency’s request for dismissal and asked the agency to submit a report that addressed the merits of the protest. GAO Denial of Agency Request for Summary Dismissal (May 19, 2015). 3 Kuwait is located in the Arabia time zone, which is 7 hours ahead of the Eastern Time zone. AR at 8.
  • 4. Page 4 B-411489 DISCUSSION Latvian Connection argues that it was not afforded sufficient time in which to respond to amendment No. 4, specifically the requirement to submit a new proposal addressing the revised sunshade canopy dimensions. Protest at 2; Protester’s Comments at 12. Latvian Connection argues that its protest is timely because it learned of amendment No. 4 on May 2, and filed a protest with our Office within less than one business day. The protester also argues that the issuance of amendment No. 4 was improper because the Army failed to restrict the procurement to the offerors that submitted initial proposals, as required by FAR § 15.206. For the reasons discussed below, we conclude that the protester was not provided a reasonable amount of time to respond to RFP amendment No. 4, and we sustain the protest on this basis. The Army first argues that the protest is untimely because it was not filed prior to the revised closing time of May 4 at 3:00 p.m., Kuwait local time--which was 8:00 a.m., Eastern Time. AR at 8. The Army notes that Latvian Connection’s protest was time/date stamped by our Office on May 4 at 8:30 a.m., Eastern Time, which was 30 minutes after the specified closing time of 3:00 p.m., local Kuwait time. Id. For the reasons discussed below, we conclude that the protest is timely. The Army is correct that our Bid Protest Regulations require that a protest based upon alleged improprieties in a solicitation that are apparent prior to the closing time for receipt of initial proposals must be filed before that time. 4 C.F.R. § 21.2(a)(1). This rule includes protests that challenge alleged improprieties that did not exist in the initial solicitation but which are subsequently incorporated into it; in such cases, the solicitation must be protested not later than the next closing time for receipt of proposals following the incorporation. Id.; see Cessna Aircraft Co., B-261953.5, Feb. 5, 1996, 96-1 CPD ¶ 132 at 16. In this respect, our timeliness rules reflect the dual requirements of giving parties a fair opportunity to present their cases and resolving protests expeditiously without unduly disrupting or delaying the procurement process. Dominion Aviation, Inc.--Recon., B-275419.4, Feb. 24, 1998, 98-1 CPD ¶ 62 at 3. The Army is also correct that our Regulations provide that a document, including a protest, is considered filed “on a particular day when it is received by GAO by 5:30 p.m., Eastern Time, on that day.” 4 C.F.R. § 21.0(f). Further, our Office has explained that a document filed after 5:30 p.m. Eastern Time, on a particular day, is considered filed at 8:30 a.m., Eastern Time, the next day our Office is open. Guam Shipyard, B-294287, Sept. 16, 2004, 2004 CPD ¶ 181 at 3. For this reason, Latvian Connection’s protest, which was submitted to our Office via email on Sunday, May 3, was considered filed at 8:30 a.m., Eastern Time, on Monday, May 4. We nonetheless conclude that the protest was timely filed. The Army does not dispute the protester’s representation that it received actual knowledge of the
  • 5. Page 5 B-411489 amendment after our Office closed on Friday, May 1 (at 5:30 p.m., Eastern Time). Because our Office was closed when Latvian Connection learned of amendment No. 4, and because the solicitation’s closing date was prior to our Office reopening on the following Monday (May 4, 8:30 a.m., Eastern Time), it was impossible for the protester to file its protest prior to the time for receipt of revised proposals. Under these circumstances, where the agency’s actions preclude the possibility of filing a timely challenge to the terms of a solicitation, our Office has held that the timeliness rule of 4 C.F.R. § 21.2(a)(1), which requires protests to be filed prior to the time for receipt of proposals, does not apply; instead, the 10-day rule of 4 C.F.R. § 21.2(a)(2) applies. Immediate Systems Resources, Inc., B-292856, Dec. 9, 2003, 2003 CPD ¶ 227 at 4; Morrison Knudsen Corp., B-247160, Jan. 7, 1992, 92-1 CPD ¶ 35 at 2. Since Latvian Connection’s protest was filed 2 days after it became aware of its basis of protest, in this case the short response time allowed by amendment No. 4, we find that the protest is timely. For the record, we also disagree with the Army’s argument that the protester had constructive knowledge of amendment No. 4 as of April 28, the date the agency posted amendment No. 4 on the AFSI website. The AFSI website is not a government-wide point of entry (GPE) designated for the publication of solicitations. Instead, FedBizOpps has been designated as the GPE--that is, the single point where government business opportunities greater than $25,000 (such as the solicitation here), including synopses of proposed contract actions, solicitations, and associated information, can be accessed electronically by the public. FAR §§ 5.101, 5.101(a)(1), 5.102.4 While offerors are charged with constructive notice of procurement actions published on the GPE, Latvian Connection did not have constructive notice in this instance because AFSI is not the GPE. See DBI Waste Sys., Inc., B-400687, B-400687.2, Jan. 12, 2009, 2009 CPD ¶ 15 at 2. We next consider whether Latvian Connection was afforded sufficient time in which to prepare a proposal in response to amendment No. 4. The Competition in Contracting Act of 1984 generally requires contracting agencies to obtain full and open competition through the use of competitive procedures, 10 U.S.C. § 2304(a)(1)(A), the dual purpose of which is to ensure that a procurement is open to all responsible sources and to provide the government with the opportunity to receive fair and reasonable prices. Kendall Healthcare Prods. Co., B-289381, Feb. 19, 2002, 2002 CPD ¶ 42 at 6. In pursuit of these goals, a contracting agency must use reasonable methods to publicize its procurement needs and to timely disseminate solicitation documents to those entitled to receive them. Id. Additionally, agencies must provide potential offerors a reasonable opportunity to respond. FAR §§ 5.203(b), 13.003(h)(2); see Sabreliner Corp., B-288030, B-288030.2, Sept. 13, 2001, 2001 CPD ¶ 170 at 6-7. What constitutes a 4 The Army does not argue in response to the protest that this solicitation was exempt from publication on the GPE.
  • 6. Page 6 B-411489 reasonable opportunity to respond will depend on “the circumstances of the individual acquisition, such as complexity, commerciality, availability, and urgency.” FAR § 5.203(b). As stated above, we find that the protester first became aware of amendment No. 4 on Saturday, May 2, when it spotted the amendment on the AFSI website. The protester states that Friday and Saturday are considered non-business days in Kuwait (where the protester’s representative was located), and that Sunday is considered a business day. Protester’s Email to GAO (Aug. 3, 2014). This means that the protester had less than 2 business days in which to respond to amendment No. 4, specifically to prepare a revised proposal addressing the new sunshade canopy dimensions.5 Under these circumstances, we find that Latvian Connection was not provided sufficient time in which to submit a response to the amendment.6 See Information Ventures, Inc., B-293541, Apr. 9, 2004, 2004 CPD ¶ 81 at 4 (where a December 31, 2003, announcement of the intended award established a response period from potential sources of one-and-a-half business days (until January 5, 2004), we held that the agency did not provide a sufficient time in which to respond). We next discuss whether Latvian Connection was prejudiced by the Army’s actions.7 5 The Army itself characterizes these revisions as “substantial.” AR at 3 n.2 (“Because of substantial changes to some required canopy dimensions in Amendment 0004, offerors that did not submit revised quotes in response to Amendment 0004 risked having their original quotes deemed nonresponsive . . . .”) In this regard, the Army acknowledges that it did not notify Latvian Connection when it sent out an email containing a courtesy copy of amendment No. 4 to the original offerors on April 28. AR at 5. The agency argues, however, that Latvian Connection had constructive knowledge of amendment No. 4 by virtue of the fact that the agency posted it on the ASFI website that same day. AR at 5-6. Therefore, the agency contends that Latvian Connection was not prejudiced by the failure of the agency to send it the email that was sent to the original offerors. Id. at 9. Since as set forth above, we find that the protester had less than 2 business 6 The Army’s response to the protest did not specifically address whether the amount of time available to the protester, based on its actual knowledge of the amendment, was adequate to respond to RFP amendment. No. 4. 7 Our Office will not sustain a protest unless the protester demonstrates a reasonable possibility that it was prejudiced by the agency’s actions, that is, unless the protester demonstrates that, but for the agency’s actions, it would have had a substantial chance of receiving the award. McDonald-Bradley, B-270126, Feb. 8, 1996, 96-1 CPD ¶ 54 at 3; see Statistica, Inc., v. Christopher, 102 F.3d 1577, 1581 (Fed. Cir. 1996).
  • 7. Page 7 B-411489 days to respond to this amendment, we conclude that the protester was prejudiced by the brief response time here. The agency also argues that the protester “contributed” to its non-receipt of amendment No. 4 by incorrectly typing the contract specialist’s email address when it submitted its initial proposal. Id. at 5. As stated above, the Army failed to meet its obligation to publicize the issuance of RFP amendment No. 4 through the GPE. Thus, even if the protester contributed to the agency’s mistaken belief that the protester had not submitted an initial proposal, the protester could have received notice of the amendment through the GPE. For this reason, we conclude that any errors on the part of the protester concerning the email addresses used to transmit its initial proposal were superseded by the agency’s failure to properly publicize RFP amendment No. 4.8 Finally, Latvian Connection argues that the issuance of RFP amendment No. 4 was improper because the Army failed to restrict the procurement to the offerors that submitted initial proposals, as required by FAR § 15.206. Protest at 1. As stated above the solicitation did not specifically address whether the competition would follow FAR part 13 or part 15 procedures. AR at 8. To the extent the protester argues that the agency should have specified that FAR part 15 procedures applied, this was an apparent solicitation impropriety that, to be timely, should have been challenged before initial proposals were due, on April 20. See 4 C.F.R. § 21.2(a)(1). In any event the Army states that it did not receive proposals from any offerors that had not already submitted a proposal in response to the original solicitation. AR at 9; Declaration of Contract Specialist (May 28, 2015) at 2. We therefore find no merit to this aspect of the protest. CONCLUSION AND RECOMMENDATION We find that the Army did not provide Latvian Connection a reasonable time in which to respond to RFP amendment No. 4. We find that the agency’s actions here prejudiced the protester, and contributed to the late receipt of the protester’s proposal. We recommend that the agency reissue amendment No. 4, with sufficient time for offerors to respond, and that the agency evaluate all timely proposals. We 8 Although the protester submitted a proposal in response to RFP amendment No. 4, this proposal was not timely received by the Army. Here too, the agency’s failure to provide Latvian Connection with a copy of the amendment, or to publicize the amendment on the GPE, resulted in the protester lacking an adequate amount of time to prepare its proposal. For this reason, the fact that Latvian Connection submitted a late proposal in response to RFP amendment No. 4 does not affect our conclusion that the Army’s actions here were improper, and that they prejudiced the protester.
  • 8. Page 8 B-411489 also recommend that the agency reimburse Latvian Connection its costs associated with filing and pursuing the protest. Bid Protest Regulations, 4 C.F.R. § 21.8(d). The protester’s certified claims for costs, detailing the time expended and costs incurred, must be submitted to the agency within 60 days after the receipt of this decision. Id. at § 21.8(f). The protest is sustained Susan A. Poling General Counsel