1. Activity a m b predecessors ET Variance ES EF LS LF
A 2 4 5 - 3.83 0.25 0 3.83 0 3.83
B 3 2 2 A 2.17 3.83 6 4 6.17
C 5 2 3 A 2.67 0.11 3.83 6.5 3.83 6.5
D 7 3 2 A 3.5 3.83 7.33 6.33 9.83
E 6 3 3 B 3.5 6 9.5 6.17 9.67
F 7 2 4 C,D 3.17 0.25 6.5 9.67 6.5 9.67
G 5 2 5 E,F 2.83 0 9.67 12.5 9.67 12.5
H 4 2 4 D 2.67 7.33 10 9.83 12.5
I 5 3 6 G,H 3.83 0.028 12.5 16.33 12.5 16.3
Total activity duration = 16.33 days = 17 days
Critical path is (A,C,F,G,I)
Z probability
= (34-16.3)/(0.25+0.11+0.25+0+0.028)
=27.74
If Z>5 so probabilityis 0.75/75%
A
B
C
D
E
F
H
G
I
2. Q2:
Productivity = Units produced/labor hours used
Current Labor Productivity (when no buyer) = Output / Input
So,
Output = 300 crates
Input = Material required + labor hours
One log requires 3 labor hours; therefore 200 logs require 600 labor hour.
Current Labor Productivity
= 300 crates / (200 logs * 3 hours/ log)
= 300 / 600 = 0.5 crates per labor hour
New Output = 160 crates
Increase in labor hours = 8
Labor Productivity:
= 160 crates / (120 logs * 3 hours/ log) + 8 hours
= 160 / 368
= 0.4348 crates per labor hour
Difference:
(0.43 – 0.5) / 0.5 * 100
= -14%
The productivity with professional buyer would decrease by 14%