ID Task Name Duration Start Finish
1 38 Avenue Road - Master Programme 41.4 wks 01 Oct '15 29 Jul '16
2 Key Milestones 2 wks 06 Oct '15 19 Oct '15
6 Construction Issue Drawings 0 wks 13 Oct '15 13 Oct '15
12 Key Procurement Items 30 wks 13 Oct '15 23 May '16
15 Construction Works 40.6 wks 01 Oct '15 25 Jul '16
16 Ground Floor Level 36.4 wks 01 Oct '15 24 Jun '16
17 Kitchen 28 wks 19 Oct '15 13 May '16
34 Entrance and Central Hall 32 wks 19 Oct '15 10 Jun '16
49 Drawing Room 28.4 wks 01 Oct '15 29 Apr '16
65 Dining Room 29.4 wks 08 Oct '15 13 May '16
87 Family Room 21.4 wks 15 Oct '15 25 Mar '16
100 Reading Room 21.4 wks 22 Oct '15 01 Apr '16
114 Cloakroom Area 3 wks 29 Oct '15 18 Nov '15
118 WC 2 wks 05 Nov '15 18 Nov '15
121 Study 15 wks 14 Dec '15 08 Apr '16
137 Stair 1 8 wks 07 Mar '16 29 Apr '16
145 Common Works 3 wks 06 Jun '16 24 Jun '16
148 2nd Floor Level 21 wks 04 Dec '15 12 May '16
149 Bedroom 3 (Charlie) 11 wks 04 Dec '15 03 Mar '16
166 Bedroom 4 (Louis) 12 wks 11 Dec '15 17 Mar '16
183 Bedroom 5 (Nanny) 11 wks 18 Dec '15 17 Mar '16
200 Bedroom 6 (Arthur) 11 wks 08 Jan '16 24 Mar '16
217 Children's TV Room 11 wks 15 Jan '16 31 Mar '16
231 Landing & Stairs 8 wks 26 Feb '16 21 Apr '16
238 Common Works 3 wks 22 Apr '16 12 May '16
241 1st Floor Level 24.8 wks 16 Nov '15 19 May '16
242 HIS Suite Dressing & Bathrooms Inc WC 19 wks 16 Nov '15 08 Apr '16
258 HER Suite Dressing & Bathrooms Inc WC 13 wks 23 Nov '15 04 Mar '16
273 Master Bedroom 13 wks 30 Nov '15 11 Mar '16
289 Guest Bedroom 13 wks 07 Dec '15 18 Mar '16
305 Stair 1 and Landing 10 wks 14 Dec '15 04 Mar '16
314 Guest Bath Room 1 wk 15 Feb '16 19 Feb '16
316 Lobby South 3 wks 29 Feb '16 18 Mar '16
320 Common Works 3 wks 29 Apr '16 19 May '16
323 Basement 25.8 wks 16 Nov '15 26 May '16
324 Cinema 18 wks 16 Nov '15 01 Apr '16
337 Stair 2 & 3 1 wk 07 Dec '15 11 Dec '15
339 Wet Leisure Corridor 2 wks 14 Dec '15 08 Jan '16
342 Football Ground 4 wks 14 Dec '15 22 Jan '16
345 Salon 4 wks 11 Jan '16 05 Feb '16
350 Staff Kitchen 3 wks 08 Feb '16 26 Feb '16
354 Laundry Area 3 wks 15 Feb '16 04 Mar '16
358 Hall 1 & 2 4 wks 15 Feb '16 11 Mar '16
362 Common Works 3 wks 06 May '16 26 May '16
365 Lower Ground Floor 18.8 wks 25 Jan '16 02 Jun '16
366 Children's Play Room 8 wks 25 Jan '16 18 Mar '16
376 Children's Music Room 7 wks 01 Feb '16 18 Mar '16
383 Hall 2 (upper & lower landing) & Stair 2 2 wks 08 Feb '16 19 Feb '16
386 Pool 2 wks 15 Feb '16 26 Feb '16
389 Stair 1 6 wks 22 Feb '16 01 Apr '16
397 GYM 9 wks 22 Feb '16 22 Apr '16
405 Hall 1 5 wks 29 Feb '16 01 Apr '16
411 Staff Flat 7 wks 07 Mar '16 22 Apr '16
419 Powder Room/WC1 2 wks 07 Mar '16 18 Mar '16
422 Storage Room 4 wks 14 Mar '16 08 Apr '16
426 Common Works 3 wks 13 May '16 02 Jun '16
429 External Works 32 wks 01 Dec '15 25 Jul '16
438 Testing & Commissioning 8 wks 16 May '16 08 Jul '16
441 Snagging & Handing Over 4 wks 04 Jul '16 29 Jul '16
38 Avenue Road - Master Progra
Key Milestones
13-10
Key Procurement Items
Construction Works
Ground Floor Level
Kitchen
Entrance and Central Hall
Drawing Room
Dining Room
Family Room
Reading Room
Cloakroom Area
WC
Study
Stair 1
Common Works
2nd Floor Level
Bedroom 3 (Charlie)
Bedroom 4 (Louis)
Bedroom 5 (Nanny)
Bedroom 6 (Arthur)
Children's TV Room
Landing & Stairs
Common Works
1st Floor Level
HIS Suite Dressing & Bathrooms Inc WC
HER Suite Dressing & Bathrooms Inc WC
Master Bedroom
Guest Bedroom
Stair 1 and Landing
Guest Bath Room
Lobby South
Common Works
Basement
Cinema
Stair 2 & 3
Wet Leisure Corridor
Football Ground
Salon
Staff Kitchen
Laundry Area
Hall 1 & 2
Common Works
Lower Ground Floor
Children's Play Room
Children's Music Room
Hall 2 (upper & lower landing) & Stair 2
Pool
Stair 1
GYM
Hall 1
Staff Flat
Powder Room/WC1
Storage Room
Common Works
External Works
Testing & Commissioning
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
2016
38 Avenue Road- Rev 1.mpp
Master Programme
Page 1 / 1

38 Avenue Road- Rev 1, Summary Programme

  • 1.
    ID Task NameDuration Start Finish 1 38 Avenue Road - Master Programme 41.4 wks 01 Oct '15 29 Jul '16 2 Key Milestones 2 wks 06 Oct '15 19 Oct '15 6 Construction Issue Drawings 0 wks 13 Oct '15 13 Oct '15 12 Key Procurement Items 30 wks 13 Oct '15 23 May '16 15 Construction Works 40.6 wks 01 Oct '15 25 Jul '16 16 Ground Floor Level 36.4 wks 01 Oct '15 24 Jun '16 17 Kitchen 28 wks 19 Oct '15 13 May '16 34 Entrance and Central Hall 32 wks 19 Oct '15 10 Jun '16 49 Drawing Room 28.4 wks 01 Oct '15 29 Apr '16 65 Dining Room 29.4 wks 08 Oct '15 13 May '16 87 Family Room 21.4 wks 15 Oct '15 25 Mar '16 100 Reading Room 21.4 wks 22 Oct '15 01 Apr '16 114 Cloakroom Area 3 wks 29 Oct '15 18 Nov '15 118 WC 2 wks 05 Nov '15 18 Nov '15 121 Study 15 wks 14 Dec '15 08 Apr '16 137 Stair 1 8 wks 07 Mar '16 29 Apr '16 145 Common Works 3 wks 06 Jun '16 24 Jun '16 148 2nd Floor Level 21 wks 04 Dec '15 12 May '16 149 Bedroom 3 (Charlie) 11 wks 04 Dec '15 03 Mar '16 166 Bedroom 4 (Louis) 12 wks 11 Dec '15 17 Mar '16 183 Bedroom 5 (Nanny) 11 wks 18 Dec '15 17 Mar '16 200 Bedroom 6 (Arthur) 11 wks 08 Jan '16 24 Mar '16 217 Children's TV Room 11 wks 15 Jan '16 31 Mar '16 231 Landing & Stairs 8 wks 26 Feb '16 21 Apr '16 238 Common Works 3 wks 22 Apr '16 12 May '16 241 1st Floor Level 24.8 wks 16 Nov '15 19 May '16 242 HIS Suite Dressing & Bathrooms Inc WC 19 wks 16 Nov '15 08 Apr '16 258 HER Suite Dressing & Bathrooms Inc WC 13 wks 23 Nov '15 04 Mar '16 273 Master Bedroom 13 wks 30 Nov '15 11 Mar '16 289 Guest Bedroom 13 wks 07 Dec '15 18 Mar '16 305 Stair 1 and Landing 10 wks 14 Dec '15 04 Mar '16 314 Guest Bath Room 1 wk 15 Feb '16 19 Feb '16 316 Lobby South 3 wks 29 Feb '16 18 Mar '16 320 Common Works 3 wks 29 Apr '16 19 May '16 323 Basement 25.8 wks 16 Nov '15 26 May '16 324 Cinema 18 wks 16 Nov '15 01 Apr '16 337 Stair 2 & 3 1 wk 07 Dec '15 11 Dec '15 339 Wet Leisure Corridor 2 wks 14 Dec '15 08 Jan '16 342 Football Ground 4 wks 14 Dec '15 22 Jan '16 345 Salon 4 wks 11 Jan '16 05 Feb '16 350 Staff Kitchen 3 wks 08 Feb '16 26 Feb '16 354 Laundry Area 3 wks 15 Feb '16 04 Mar '16 358 Hall 1 & 2 4 wks 15 Feb '16 11 Mar '16 362 Common Works 3 wks 06 May '16 26 May '16 365 Lower Ground Floor 18.8 wks 25 Jan '16 02 Jun '16 366 Children's Play Room 8 wks 25 Jan '16 18 Mar '16 376 Children's Music Room 7 wks 01 Feb '16 18 Mar '16 383 Hall 2 (upper & lower landing) & Stair 2 2 wks 08 Feb '16 19 Feb '16 386 Pool 2 wks 15 Feb '16 26 Feb '16 389 Stair 1 6 wks 22 Feb '16 01 Apr '16 397 GYM 9 wks 22 Feb '16 22 Apr '16 405 Hall 1 5 wks 29 Feb '16 01 Apr '16 411 Staff Flat 7 wks 07 Mar '16 22 Apr '16 419 Powder Room/WC1 2 wks 07 Mar '16 18 Mar '16 422 Storage Room 4 wks 14 Mar '16 08 Apr '16 426 Common Works 3 wks 13 May '16 02 Jun '16 429 External Works 32 wks 01 Dec '15 25 Jul '16 438 Testing & Commissioning 8 wks 16 May '16 08 Jul '16 441 Snagging & Handing Over 4 wks 04 Jul '16 29 Jul '16 38 Avenue Road - Master Progra Key Milestones 13-10 Key Procurement Items Construction Works Ground Floor Level Kitchen Entrance and Central Hall Drawing Room Dining Room Family Room Reading Room Cloakroom Area WC Study Stair 1 Common Works 2nd Floor Level Bedroom 3 (Charlie) Bedroom 4 (Louis) Bedroom 5 (Nanny) Bedroom 6 (Arthur) Children's TV Room Landing & Stairs Common Works 1st Floor Level HIS Suite Dressing & Bathrooms Inc WC HER Suite Dressing & Bathrooms Inc WC Master Bedroom Guest Bedroom Stair 1 and Landing Guest Bath Room Lobby South Common Works Basement Cinema Stair 2 & 3 Wet Leisure Corridor Football Ground Salon Staff Kitchen Laundry Area Hall 1 & 2 Common Works Lower Ground Floor Children's Play Room Children's Music Room Hall 2 (upper & lower landing) & Stair 2 Pool Stair 1 GYM Hall 1 Staff Flat Powder Room/WC1 Storage Room Common Works External Works Testing & Commissioning Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep 2016 38 Avenue Road- Rev 1.mpp Master Programme Page 1 / 1