SlideShare a Scribd company logo
1 of 3
Download to read offline
T
he oil and gas industry continues to confront
some of the most difficult valve application
challenges. Companies are required to address
environmental concerns regarding emissions,
human resource concerns around safety, as well as
increasingly demanding regulatory requirements, to name a
few. Out of these challenges comes greater demand for
high performance products, services and technical
expertise that ensures these concerns are first understood
and then addressed in the most reliable and cost effective
manner.
The following case studies highlight how innovative
valve solutions, technical expertise and experience, and a
total focus on the needs of the customer can help to
improve operations, address regulatory concerns and
ensure the safety of the plant and personnel in various
downstream and chemical processing industry
applications.
Case study: challenging refinery
processes
The delayed coker process is crucial to a refinery’s
profitability. Coking is one of the most hostile
environments in the refinery, with process temperatures
of 1000˚F/538˚C, that yields a very abrasive and erosive
coke byproduct. In this application, valves are cycled
more frequently than those in other parts of the refinery
and failure can cause complete unit shutdown. A refinery
in Canada realised these costs first hand when the
facility's plug valves were locking up on a routine basis. A
Julie Bodine,
ValvTechnologies, Inc.,
USA, explains how
effective and innovative
valve design and proper
implementation can
increase process safety,
reliability and efficiency.
A study in
solutions
A study in
solutions
Reprinted from November 2016 HYDROCARBON
ENGINEERING
unit shutdown was required to remove the upper bonnets
and steam internals in order to free the debris and allow
the valves to function properly. Unit shutdowns were
becoming routine and very costly.
The delayed coker process is a batch process – one of
a few in the refinery complex. The process of switching
from one drum to another requires a complex series of
events that must take place in perfect sequence in order
to avoid major equipment damage. The coker feed (a
liquid-vapour combination) is heated in a large furnace
and then directed into a preheated coke drum for
cracking and product separation. Delayed cokers are
designed as a pair of drums so that one drum can be
prepared for the next cycle while the other drum is in
operation. This critical application requires valves to cycle
on a regular basis, which necessitates high reliability.
Operating temperatures vary drastically and state change
(coke formation) can occur as the process flows through
the switch and various isolation valves. The main
challenge for this refinery was related to the existing
valves locking up and leaking due to their inability to
handle the abrasive feed.
The ValvTechnologies’ purge system is a preventative
solution that removes the heavy hydrocarbon from the
valve cavity before it has the opportunity to change state.
This purge system is recommended for coker valves above
8 in. ValvTechnologies was given the opportunity to
provide a test valve in the Canadian refiner’s coker unit.
However, the company was concerned about adding
steam to the process and chose not to incorporate the
purge system. Without it, there were some initial issues to
overcome to ensure the valve functioned as expected.
Even without the recommended purge system, the test
valve was outperforming all of the plug valves that were
in operation at that time. As a result of this test, six valves
were ordered to replace the other plug valves. The
company eventually incorporated the purge system, and
the valves continue to provide trouble free operation
today.
As a result of installing a reliable valve with the proper
purge system, the facility has realised an increase in
operational efficiency. In light of the cost savings
achieved as a result of the improved efficiency, the
company was awarded the next delayed coking project at
this location.
Case study: meeting unique
requirements
NatureWorks is the first company to offer a family of
commercially available, low carbon footprint IngeoTM
lactides and biopolymers derived from 100% annually
renewable resources, with performance and economics
that compete with oil-based intermediates, plastics and
fibres, and provide brand owners with new cradle to
cradle options after the use of their products.
NatureWorks contracted Plant Services, Inc., based in
Spring, Texas, which specialises in process engineering, to
specify and locate a suitable solution for an existing
control valve application. NatureWorks was experiencing
ongoing problems with its existing valve, which was
installed in 2008 and failed to meet process application
requirements due to galling on the ball and seats,
resulting in poor reliability.
NatureWorks required a valve that could be
modulated to control back pressure and provide tight
shut off when closed. The goal was to find a valve that
would meet the specifications and provide tight shut off.
Plant Services specialists researched numerous
manufacturers for a suitable valve for this extremely
severe service application and ValvTechnologies was
willing to produce a valve to the specifications required.
Figure 1. ValvTechnologies’ zero leakage high
performance metal seated ball valve for coking
applications.
Figure 2. Zero leakage valve solutions.
Figure 3. ValvTechnologies’ HVOF RiTech®, Robotically
Integrated Technology, for high performance valves.
Reprinted from November 2016HYDROCARBON
ENGINEERING
The company selected ValvTechnologies’ RiTech®coating
technology and V1-2 metal seated ball valve design, and
were very satisfied with the quality assurance/quality
control (QA/QC) and stringent zero leakage testing
performed.
A 24 in. 300 lb metal-seated V1-2 valve was designed
and manufactured by ValvTechnologies, and a hydraulic
Moog actuator, hydraulic power unit (HPU) system and
the automation were designed by Donald Marek and
fabricated by Control Fluids, Inc. of Beaumont, Texas. The
Eads Company, a ValvTechnologies distribution partner
and integrator, provided the package as a complete
system and facilitated the final product acceptance test
prior to delivery to NatureWorks.
Case study: teamwork builds success
Aftermarket service and repair is also crucial in the
effort to ensure customer’s concerns are addressed and
plants are properly maintained and continue to run
safely and reliably, ensuring lower total cost of
ownership.
During a scheduled outage, a large plant discovered a
valve that would not move. Upon further inspection the
customer found a damaged coupler on the valve’s
mounting bracket. Assuming this damaged coupler was
causing the valve to lock up, the company decided
against purchasing a new valve and instead simply
replaced the damaged mounting bracket. Preparing to go
back online, the company found that the valve would
still not function.
Planning for outage season can be difficult enough
without an unexpected setback or unplanned
costs. Unplanned shutdowns cost plants millions of
dollars; to prevent paying this high cost, an immediate
shipment of a ValvTechnologies' V1-1 zero leakage metal
seated ball valve was required to avoid extended plant
downtime.
The request was received on a Saturday and
ValvTechnologies assembled a cross-functional team to
provide the plant with an immediate solution.
Representatives across the entire organisation, including
the shipping, warehouse and service departments, were
called to the Houston office to solve the problem. The
team was able to identify, assemble, test and ship a
replacement V1-1 valve by the end of the day that the
emergency request was received. The plant received the
V1-1 valve on the Monday morning and immediately
installed it. The new valve functioned well and the
company was able to bring the plant up, saving thousands
of dollars in potential downtime and revenue loss.
Case study: service and repair
ValvTechnologies has supplied almost 250 000 severe
service isolation valves, which are expected to last
between 20 and 40 years of almost continuous
operation. Just like any machine, the valves should be
inspected and serviced to maintain their performance
throughout their operating life. The company's
Aftermarket Service & Repair Department plays an
important support role, providing inspection and
product servicing for companies.
One of these companies is a large refinery in the
Texas Gulf area. The refinery has several hundred valves
installed – many having been specially engineered
designs with unique construction materials. A large
number of these valves have been in service for more
than 15 years. ValvTechnologies began discussions with
the refinery managers about how the company could
help refurbish these valves during a large multi-unit
plant outage early in the following year. For many
months the companies held onsite inspections of the
equipment and organised numerous follow up planning
meetings with the personnel that were determining the
outage schedule. From these meetings, the refinery
developed a detailed valve list that consisted of several
dozen older valves designated for service and repair.
With this list, ValvTechnologies designed an outage
support plan to receive the used valves and restore
them to 'like new' condition. This plan was a major
challenge as there was only one week to turnaround
each valve, leaving little time for delay or error.
The company managed almost all of the pre-outage
and in-shop planning and work flows. The project was
watched around the clock, seven days a week to ensure
success. Numerous aftermarket service and repair
personnel assisted in the preparation and execution of
this large project, alongside several other departments.
In particular, assembly and test personnel from the
company's shops worked 12 hour days to ensure the
valves were repaired on time. Inspectors visited daily to
check on the status of the valves in-process and confirm
that progress was being made. The end result was that
all valves were successfully serviced and repaired and
returned to the refinery ahead of schedule.
Conclusion
As a result of supplying the right metal seated ball valves
in the most difficult severe service applications, oil and
gas companies can take advantage of higher reliability,
increased safety and additional plant efficiencies.
Recommendations and technical expertise ensures
companies in the oil and gas industry that face tough
challenges are able to achieve peace of mind.
Figure 4. Aftermarket service and repair is crucial to
support the industry’s most difficult challenges.

More Related Content

What's hot

Boiler Water Circulation Pumps
Boiler Water Circulation PumpsBoiler Water Circulation Pumps
Boiler Water Circulation PumpsGerard B. Hawkins
 
TES Catalogue 2016_V3
TES Catalogue 2016_V3TES Catalogue 2016_V3
TES Catalogue 2016_V3Kelvin King
 
Shell and Tube Heat Exchangers Using Cooling Water
Shell and Tube Heat Exchangers Using Cooling WaterShell and Tube Heat Exchangers Using Cooling Water
Shell and Tube Heat Exchangers Using Cooling WaterGerard B. Hawkins
 
Adam Fabriwerk Processing Skids Presentation Sterile Processing
Adam Fabriwerk Processing Skids Presentation   Sterile ProcessingAdam Fabriwerk Processing Skids Presentation   Sterile Processing
Adam Fabriwerk Processing Skids Presentation Sterile ProcessingVishal Wagh
 
E Kranti PVT LTD 1000 LPH
E Kranti PVT LTD 1000 LPH E Kranti PVT LTD 1000 LPH
E Kranti PVT LTD 1000 LPH EKrantipvtltd
 
GTC's High Performance Tray Tower Solutions
GTC's High Performance Tray Tower SolutionsGTC's High Performance Tray Tower Solutions
GTC's High Performance Tray Tower SolutionsGTC Technology
 
Usage of Support Balls, Meshes & Hold Down Screens
Usage of Support Balls, Meshes & Hold Down ScreensUsage of Support Balls, Meshes & Hold Down Screens
Usage of Support Balls, Meshes & Hold Down ScreensGerard B. Hawkins
 
EMERGENCY ISOLATION OF CHEMICAL PLANTS
EMERGENCY ISOLATION OF CHEMICAL PLANTS EMERGENCY ISOLATION OF CHEMICAL PLANTS
EMERGENCY ISOLATION OF CHEMICAL PLANTS Gerard B. Hawkins
 
Catalogue ALMATEC
Catalogue ALMATECCatalogue ALMATEC
Catalogue ALMATECJamil DHIB
 
Case Study: Modular Distillation System to Recover Spent Solvents
Case Study: Modular Distillation System to Recover Spent SolventsCase Study: Modular Distillation System to Recover Spent Solvents
Case Study: Modular Distillation System to Recover Spent SolventsKoch Modular Process Systems, LLC.
 
WELL INTEGRITY MANAGEMENT
WELL INTEGRITY MANAGEMENTWELL INTEGRITY MANAGEMENT
WELL INTEGRITY MANAGEMENTpetroEDGE
 
Pipeline Design for Isothermal, Turbulent Flow of Non-Newtonian Fluids
Pipeline Design for Isothermal, Turbulent Flow of Non-Newtonian FluidsPipeline Design for Isothermal, Turbulent Flow of Non-Newtonian Fluids
Pipeline Design for Isothermal, Turbulent Flow of Non-Newtonian FluidsGerard B. Hawkins
 
IFM_Brochure-Reliability
IFM_Brochure-ReliabilityIFM_Brochure-Reliability
IFM_Brochure-ReliabilityJoelLeBlanc
 

What's hot (20)

Boiler Water Circulation Pumps
Boiler Water Circulation PumpsBoiler Water Circulation Pumps
Boiler Water Circulation Pumps
 
TES Catalogue 2016_V3
TES Catalogue 2016_V3TES Catalogue 2016_V3
TES Catalogue 2016_V3
 
Centrifugation
CentrifugationCentrifugation
Centrifugation
 
Shell and Tube Heat Exchangers Using Cooling Water
Shell and Tube Heat Exchangers Using Cooling WaterShell and Tube Heat Exchangers Using Cooling Water
Shell and Tube Heat Exchangers Using Cooling Water
 
Adam Fabriwerk Processing Skids Presentation Sterile Processing
Adam Fabriwerk Processing Skids Presentation   Sterile ProcessingAdam Fabriwerk Processing Skids Presentation   Sterile Processing
Adam Fabriwerk Processing Skids Presentation Sterile Processing
 
Aquatis brochure A4-lowres
Aquatis brochure A4-lowresAquatis brochure A4-lowres
Aquatis brochure A4-lowres
 
E Kranti PVT LTD 1000 LPH
E Kranti PVT LTD 1000 LPH E Kranti PVT LTD 1000 LPH
E Kranti PVT LTD 1000 LPH
 
BFC (S) Presentation
BFC (S) PresentationBFC (S) Presentation
BFC (S) Presentation
 
GTC's High Performance Tray Tower Solutions
GTC's High Performance Tray Tower SolutionsGTC's High Performance Tray Tower Solutions
GTC's High Performance Tray Tower Solutions
 
Usage of Support Balls, Meshes & Hold Down Screens
Usage of Support Balls, Meshes & Hold Down ScreensUsage of Support Balls, Meshes & Hold Down Screens
Usage of Support Balls, Meshes & Hold Down Screens
 
EMERGENCY ISOLATION OF CHEMICAL PLANTS
EMERGENCY ISOLATION OF CHEMICAL PLANTS EMERGENCY ISOLATION OF CHEMICAL PLANTS
EMERGENCY ISOLATION OF CHEMICAL PLANTS
 
Catalogue ALMATEC
Catalogue ALMATECCatalogue ALMATEC
Catalogue ALMATEC
 
Case Study: Modular Distillation System to Recover Spent Solvents
Case Study: Modular Distillation System to Recover Spent SolventsCase Study: Modular Distillation System to Recover Spent Solvents
Case Study: Modular Distillation System to Recover Spent Solvents
 
Laboratory Distillation
Laboratory DistillationLaboratory Distillation
Laboratory Distillation
 
BTP Palamatic Process
BTP Palamatic ProcessBTP Palamatic Process
BTP Palamatic Process
 
WELL INTEGRITY MANAGEMENT
WELL INTEGRITY MANAGEMENTWELL INTEGRITY MANAGEMENT
WELL INTEGRITY MANAGEMENT
 
EnServ Profile
EnServ ProfileEnServ Profile
EnServ Profile
 
Pipeline Design for Isothermal, Turbulent Flow of Non-Newtonian Fluids
Pipeline Design for Isothermal, Turbulent Flow of Non-Newtonian FluidsPipeline Design for Isothermal, Turbulent Flow of Non-Newtonian Fluids
Pipeline Design for Isothermal, Turbulent Flow of Non-Newtonian Fluids
 
Chemical cleaning
Chemical cleaningChemical cleaning
Chemical cleaning
 
IFM_Brochure-Reliability
IFM_Brochure-ReliabilityIFM_Brochure-Reliability
IFM_Brochure-Reliability
 

Similar to 1407_A study in solutions_Hydrocarbon Engineering_November 2016

Winter Newsletter 1.12.16
Winter Newsletter 1.12.16Winter Newsletter 1.12.16
Winter Newsletter 1.12.16fidge72
 
Valve designing trends in 2022
Valve designing trends in 2022Valve designing trends in 2022
Valve designing trends in 2022Sowmiya Siva
 
Flexim Fluxus Ultrasonic Flow Meters - Flow Measurement In Refineries - Broch...
Flexim Fluxus Ultrasonic Flow Meters - Flow Measurement In Refineries - Broch...Flexim Fluxus Ultrasonic Flow Meters - Flow Measurement In Refineries - Broch...
Flexim Fluxus Ultrasonic Flow Meters - Flow Measurement In Refineries - Broch...Thorne & Derrick UK
 
Sealweld commissioning enhancement
Sealweld commissioning enhancementSealweld commissioning enhancement
Sealweld commissioning enhancementkokan007
 
Cov company presentation 2018
Cov company presentation 2018Cov company presentation 2018
Cov company presentation 2018nayeem7265840
 
Ravva Use Of Seal Tite To Control Leaks
Ravva Use Of Seal Tite To Control LeaksRavva Use Of Seal Tite To Control Leaks
Ravva Use Of Seal Tite To Control LeaksCairn India Limited
 
Alphatec Europe Flyer
Alphatec Europe FlyerAlphatec Europe Flyer
Alphatec Europe FlyerCarlos Aliaga
 
Preventive maintenance
Preventive maintenancePreventive maintenance
Preventive maintenancevijay oak
 
Preventive maintenance
Preventive maintenancePreventive maintenance
Preventive maintenancevijay oak
 
Preventive maintenance
Preventive maintenancePreventive maintenance
Preventive maintenancevijay oak
 
TMV3 Thermostatic Mixing Valves - Reliance Water Controls Brochure
TMV3 Thermostatic Mixing Valves - Reliance Water Controls BrochureTMV3 Thermostatic Mixing Valves - Reliance Water Controls Brochure
TMV3 Thermostatic Mixing Valves - Reliance Water Controls BrochureThorne & Derrick UK
 
CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016
CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016
CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016Mujahid Ali Akhtar
 
STM_Autumn2015 Article Publication
STM_Autumn2015 Article PublicationSTM_Autumn2015 Article Publication
STM_Autumn2015 Article PublicationEwart Cox
 
Kitec Plumbing Replacement : A Comprehensive Guide
Kitec Plumbing Replacement : A Comprehensive GuideKitec Plumbing Replacement : A Comprehensive Guide
Kitec Plumbing Replacement : A Comprehensive GuideSamantha Angel
 
Data Centers - Pipe Joining Solutions
Data Centers - Pipe Joining SolutionsData Centers - Pipe Joining Solutions
Data Centers - Pipe Joining SolutionsGraeme Simmers
 
Lining Track Records & Case Histories
Lining Track Records & Case HistoriesLining Track Records & Case Histories
Lining Track Records & Case HistoriesInternational Paint
 

Similar to 1407_A study in solutions_Hydrocarbon Engineering_November 2016 (20)

Winter Newsletter 1.12.16
Winter Newsletter 1.12.16Winter Newsletter 1.12.16
Winter Newsletter 1.12.16
 
Valve designing trends in 2022
Valve designing trends in 2022Valve designing trends in 2022
Valve designing trends in 2022
 
Flexim Fluxus Ultrasonic Flow Meters - Flow Measurement In Refineries - Broch...
Flexim Fluxus Ultrasonic Flow Meters - Flow Measurement In Refineries - Broch...Flexim Fluxus Ultrasonic Flow Meters - Flow Measurement In Refineries - Broch...
Flexim Fluxus Ultrasonic Flow Meters - Flow Measurement In Refineries - Broch...
 
Sealweld commissioning enhancement
Sealweld commissioning enhancementSealweld commissioning enhancement
Sealweld commissioning enhancement
 
11-IAGT-202_paper
11-IAGT-202_paper11-IAGT-202_paper
11-IAGT-202_paper
 
Cov company presentation 2018
Cov company presentation 2018Cov company presentation 2018
Cov company presentation 2018
 
Ravva Use Of Seal Tite To Control Leaks
Ravva Use Of Seal Tite To Control LeaksRavva Use Of Seal Tite To Control Leaks
Ravva Use Of Seal Tite To Control Leaks
 
Alphatec Europe Flyer
Alphatec Europe FlyerAlphatec Europe Flyer
Alphatec Europe Flyer
 
Preventive maintenance
Preventive maintenancePreventive maintenance
Preventive maintenance
 
Preventive maintenance
Preventive maintenancePreventive maintenance
Preventive maintenance
 
Preventive maintenance
Preventive maintenancePreventive maintenance
Preventive maintenance
 
TMV3 Thermostatic Mixing Valves - Reliance Water Controls Brochure
TMV3 Thermostatic Mixing Valves - Reliance Water Controls BrochureTMV3 Thermostatic Mixing Valves - Reliance Water Controls Brochure
TMV3 Thermostatic Mixing Valves - Reliance Water Controls Brochure
 
NK Energy Presentation
NK Energy PresentationNK Energy Presentation
NK Energy Presentation
 
CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016
CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016
CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016
 
STM_Autumn2015 Article Publication
STM_Autumn2015 Article PublicationSTM_Autumn2015 Article Publication
STM_Autumn2015 Article Publication
 
Kitec Plumbing Replacement : A Comprehensive Guide
Kitec Plumbing Replacement : A Comprehensive GuideKitec Plumbing Replacement : A Comprehensive Guide
Kitec Plumbing Replacement : A Comprehensive Guide
 
Data Centers - Pipe Joining Solutions
Data Centers - Pipe Joining SolutionsData Centers - Pipe Joining Solutions
Data Centers - Pipe Joining Solutions
 
mcd_SOAR A
mcd_SOAR Amcd_SOAR A
mcd_SOAR A
 
Compressors
CompressorsCompressors
Compressors
 
Lining Track Records & Case Histories
Lining Track Records & Case HistoriesLining Track Records & Case Histories
Lining Track Records & Case Histories
 

1407_A study in solutions_Hydrocarbon Engineering_November 2016

  • 1. T he oil and gas industry continues to confront some of the most difficult valve application challenges. Companies are required to address environmental concerns regarding emissions, human resource concerns around safety, as well as increasingly demanding regulatory requirements, to name a few. Out of these challenges comes greater demand for high performance products, services and technical expertise that ensures these concerns are first understood and then addressed in the most reliable and cost effective manner. The following case studies highlight how innovative valve solutions, technical expertise and experience, and a total focus on the needs of the customer can help to improve operations, address regulatory concerns and ensure the safety of the plant and personnel in various downstream and chemical processing industry applications. Case study: challenging refinery processes The delayed coker process is crucial to a refinery’s profitability. Coking is one of the most hostile environments in the refinery, with process temperatures of 1000˚F/538˚C, that yields a very abrasive and erosive coke byproduct. In this application, valves are cycled more frequently than those in other parts of the refinery and failure can cause complete unit shutdown. A refinery in Canada realised these costs first hand when the facility's plug valves were locking up on a routine basis. A Julie Bodine, ValvTechnologies, Inc., USA, explains how effective and innovative valve design and proper implementation can increase process safety, reliability and efficiency. A study in solutions A study in solutions
  • 2. Reprinted from November 2016 HYDROCARBON ENGINEERING unit shutdown was required to remove the upper bonnets and steam internals in order to free the debris and allow the valves to function properly. Unit shutdowns were becoming routine and very costly. The delayed coker process is a batch process – one of a few in the refinery complex. The process of switching from one drum to another requires a complex series of events that must take place in perfect sequence in order to avoid major equipment damage. The coker feed (a liquid-vapour combination) is heated in a large furnace and then directed into a preheated coke drum for cracking and product separation. Delayed cokers are designed as a pair of drums so that one drum can be prepared for the next cycle while the other drum is in operation. This critical application requires valves to cycle on a regular basis, which necessitates high reliability. Operating temperatures vary drastically and state change (coke formation) can occur as the process flows through the switch and various isolation valves. The main challenge for this refinery was related to the existing valves locking up and leaking due to their inability to handle the abrasive feed. The ValvTechnologies’ purge system is a preventative solution that removes the heavy hydrocarbon from the valve cavity before it has the opportunity to change state. This purge system is recommended for coker valves above 8 in. ValvTechnologies was given the opportunity to provide a test valve in the Canadian refiner’s coker unit. However, the company was concerned about adding steam to the process and chose not to incorporate the purge system. Without it, there were some initial issues to overcome to ensure the valve functioned as expected. Even without the recommended purge system, the test valve was outperforming all of the plug valves that were in operation at that time. As a result of this test, six valves were ordered to replace the other plug valves. The company eventually incorporated the purge system, and the valves continue to provide trouble free operation today. As a result of installing a reliable valve with the proper purge system, the facility has realised an increase in operational efficiency. In light of the cost savings achieved as a result of the improved efficiency, the company was awarded the next delayed coking project at this location. Case study: meeting unique requirements NatureWorks is the first company to offer a family of commercially available, low carbon footprint IngeoTM lactides and biopolymers derived from 100% annually renewable resources, with performance and economics that compete with oil-based intermediates, plastics and fibres, and provide brand owners with new cradle to cradle options after the use of their products. NatureWorks contracted Plant Services, Inc., based in Spring, Texas, which specialises in process engineering, to specify and locate a suitable solution for an existing control valve application. NatureWorks was experiencing ongoing problems with its existing valve, which was installed in 2008 and failed to meet process application requirements due to galling on the ball and seats, resulting in poor reliability. NatureWorks required a valve that could be modulated to control back pressure and provide tight shut off when closed. The goal was to find a valve that would meet the specifications and provide tight shut off. Plant Services specialists researched numerous manufacturers for a suitable valve for this extremely severe service application and ValvTechnologies was willing to produce a valve to the specifications required. Figure 1. ValvTechnologies’ zero leakage high performance metal seated ball valve for coking applications. Figure 2. Zero leakage valve solutions. Figure 3. ValvTechnologies’ HVOF RiTech®, Robotically Integrated Technology, for high performance valves.
  • 3. Reprinted from November 2016HYDROCARBON ENGINEERING The company selected ValvTechnologies’ RiTech®coating technology and V1-2 metal seated ball valve design, and were very satisfied with the quality assurance/quality control (QA/QC) and stringent zero leakage testing performed. A 24 in. 300 lb metal-seated V1-2 valve was designed and manufactured by ValvTechnologies, and a hydraulic Moog actuator, hydraulic power unit (HPU) system and the automation were designed by Donald Marek and fabricated by Control Fluids, Inc. of Beaumont, Texas. The Eads Company, a ValvTechnologies distribution partner and integrator, provided the package as a complete system and facilitated the final product acceptance test prior to delivery to NatureWorks. Case study: teamwork builds success Aftermarket service and repair is also crucial in the effort to ensure customer’s concerns are addressed and plants are properly maintained and continue to run safely and reliably, ensuring lower total cost of ownership. During a scheduled outage, a large plant discovered a valve that would not move. Upon further inspection the customer found a damaged coupler on the valve’s mounting bracket. Assuming this damaged coupler was causing the valve to lock up, the company decided against purchasing a new valve and instead simply replaced the damaged mounting bracket. Preparing to go back online, the company found that the valve would still not function. Planning for outage season can be difficult enough without an unexpected setback or unplanned costs. Unplanned shutdowns cost plants millions of dollars; to prevent paying this high cost, an immediate shipment of a ValvTechnologies' V1-1 zero leakage metal seated ball valve was required to avoid extended plant downtime. The request was received on a Saturday and ValvTechnologies assembled a cross-functional team to provide the plant with an immediate solution. Representatives across the entire organisation, including the shipping, warehouse and service departments, were called to the Houston office to solve the problem. The team was able to identify, assemble, test and ship a replacement V1-1 valve by the end of the day that the emergency request was received. The plant received the V1-1 valve on the Monday morning and immediately installed it. The new valve functioned well and the company was able to bring the plant up, saving thousands of dollars in potential downtime and revenue loss. Case study: service and repair ValvTechnologies has supplied almost 250 000 severe service isolation valves, which are expected to last between 20 and 40 years of almost continuous operation. Just like any machine, the valves should be inspected and serviced to maintain their performance throughout their operating life. The company's Aftermarket Service & Repair Department plays an important support role, providing inspection and product servicing for companies. One of these companies is a large refinery in the Texas Gulf area. The refinery has several hundred valves installed – many having been specially engineered designs with unique construction materials. A large number of these valves have been in service for more than 15 years. ValvTechnologies began discussions with the refinery managers about how the company could help refurbish these valves during a large multi-unit plant outage early in the following year. For many months the companies held onsite inspections of the equipment and organised numerous follow up planning meetings with the personnel that were determining the outage schedule. From these meetings, the refinery developed a detailed valve list that consisted of several dozen older valves designated for service and repair. With this list, ValvTechnologies designed an outage support plan to receive the used valves and restore them to 'like new' condition. This plan was a major challenge as there was only one week to turnaround each valve, leaving little time for delay or error. The company managed almost all of the pre-outage and in-shop planning and work flows. The project was watched around the clock, seven days a week to ensure success. Numerous aftermarket service and repair personnel assisted in the preparation and execution of this large project, alongside several other departments. In particular, assembly and test personnel from the company's shops worked 12 hour days to ensure the valves were repaired on time. Inspectors visited daily to check on the status of the valves in-process and confirm that progress was being made. The end result was that all valves were successfully serviced and repaired and returned to the refinery ahead of schedule. Conclusion As a result of supplying the right metal seated ball valves in the most difficult severe service applications, oil and gas companies can take advantage of higher reliability, increased safety and additional plant efficiencies. Recommendations and technical expertise ensures companies in the oil and gas industry that face tough challenges are able to achieve peace of mind. Figure 4. Aftermarket service and repair is crucial to support the industry’s most difficult challenges.