Mn. Rs

 Month         April      May     June     July           Aug   Sept   Oct   Nov   Dec   Jan   Feb   Mar    Total



Total Sales 238.08       255.07   259.10




     Segment       Sales April Sales May Sales June

       OEM             207.63     228.10      229.91

      Retail           21.22       17.50          19.95

      Exports           7.42       7.23           8.14

       Fleet            1.81       2.25           1.10

       Total           238.08     255.07      259.10




                                                                                                             1
Mn Rs.

     Month          April    May     June   July     Aug   Sept   Oct   Nov   Dec   Jan   Feb   Mar   Total



Budgeted Material
                    44.70    46.06
  Consumption


 Actual Material
                    48.33
  Consumption               51.85




                                               PO:
Pelhar           April May     June July August   Sept   Oct   Nov   Dec   Jan   Feb   Mar
Installed
Capacity          0.76   0.83   0.83
( Million Sets)
Utilized
Capacity          0.33   0.45   0.50
(Million Sets)

% Utilization     43%    55%    61%




                                                                                         3
EXPORTS Projects
PROJECTS         Status on JUNE 2012

HONDA            A countermeasure was given to Honda ,where CSPL-TVF-3PLE-1 material is to be used. All the
                 materials available in Pelhar and Unit I were under deviation ,traced one roll at haridwar which was
                 without deviation and passes HES specs hence procured that from Haridwar, on which gloss
                 patches were printed . These patches passes in fuel oil resistance test where as fails in E10 and E20
                 solution for both Type 4 and Type 6 panels. Testing presently under process for original Honda Decal
                 for E10 and E20 solution reports will be submitted by July 1st week

MIO-PINK         Printing done with following combination and test conducted results found as under,
(Yamaha          Material used as
Indonesia)       1.PVC WB80 PA 10 11LLY
                 2.PVC WB80 PA T1 11LLY
                 3.CSPL-WVF-3P-1
                 4.CSPL-WVF-3P-2
                 Printed OC with following combination
                 1.V3 + 45% Non silicon 8228 OC
                 2.V3 + 8600 OC
                 3.V3 + SIEKO 5412 UV
                 All the material printed with V3 + Sieko 5412 UV fails in WOM after 400hrs,where as material printed
                 with other two OC passes in WOM till 400 hrs and is continued for 900hrs



KUBOTA           Approved Drawing submitted (K7564-65231,K7311-65206,K7721-65801,K2581-65205) on 14.6.2012
                 and 18.6.2012. Awaiting for the release of the P.O



     3/18/2013                                                                                                           4
Membrane Switch Projects
TYPE OF MEMBRANE             STATUS IN JUNE 2012
SWITCH
                             LG samples will be submitted by 11-07-12
               LG
                             LG quote submitted on 2.7.2012 ,awaiting feedback from
                             Mktg
                             Location finalized for MS assembling (In dial post curing
    Membrane switch          area) .Layout to be finalised
    production set-up

                             Testing equipments (MS tester, life tester & Hipot tester)
       Membrane Switch       ordered, expected by mid July 2012
         Equipments
                             Hot air oven will be ordered after positive feed back from LG

                             2 man power to be taken from production for involving in
              Manpower       MS start up production activities. Existing 2 persons


  3/18/2013                                                                               5
RAW MATERIAL TRACKING SHEET




3/18/2013                        6
Month
   2010-11
              Apr   May    Jun     Jul     Aug     Sep         Oct         Nov     Dec   Jan   Feb    Mar Average Target
No. of
Samples       67    40     44
dispatched
Development
            3.76    3.3    3.7
time (days)

   5

  4.5

   4
                                                                                                          TARGET 3.9 DAYS
  3.5

   3

  2.5

   2

  1.5

   1

  0.5

   0
        Apr   May    Jun     Jul     Aug     Sep         Oct         Nov         Dec     Jan    Feb     Mar
No. of samples     No. of production      No. of production
    Segments           Clients       dispatched      from this months sdr.   previous months sdr.   Ftr
OEM TWO WHEELERS        HERO               7                   0                      4              4
                        BAJAJ              4                   0                      0              0
                      YAMAHA               5                   0                      1              1
                       SUZUKI              1                   0                      0              0



                   MAH. & MAH.           8                    1                       2             3
                  M&M SWARAJ             2                    0                       1             1
                   JOHN DEERE            3                    0                       0             0
                      TAFE               10                   0                       2             2
                  MARUTI SUZUKI          1                    0                       0             0
OEM FOUR WHEELERS TATA MOTORS            4                    0                       0             0
     & OTHERS     ESCORT TRACT.          2                    0                       0             0
                     HAZARA              1                    1                       0             1
  AUTOGRAPHIX       ROYAL ENFIELD         1                   0                       0             0
                       OTHERS             4                   0                       1             2

                    AUTOGRAPHIX           4                   0                       4             4

                    SAUD BHAWAN           2                   0                       0             0
     EXPORT              ALJ              1                   0                       3             3

                    BANGLADESH            1                   0                       0             0

                       TOTAL             61                   2                      18             20
INTERNAL CUSTOMER   HERO HONDA                                                       15             15
Month
   2010-11
               Apr       May     Jun     Jul         Aug     Sep        Oct       Nov          Dec     Jan   Feb     Mar Actual Target
No. of
Samples        67        40      44
dispatched
FTR            67        40      44
% FTR
              100% 100% 94.4%
( days)

                                                                   % FTR
                          120%
                          100%
                           80%
                           60%
                           40%                                                                               % FTR
                           20%
                            0%
                                 Apr   May     Jun    Jul   Aug   Sep   Oct    Nov   Dec   Jan   Feb   Mar


                                                                              No. of production from this
               Clients                 No. of samples dispatched                      months sdr.                      Ftr

             MAH. & MAH.                                8                                  1                            1

               HAZARA                                   1                                  1                            1


                                                                                                                                  9
S. No
                       Dial Name                   Hand Over Date
 1
        HDT Daimler dial                  10 nos each
        NGC Dial & Diffuser               180 nos each

 2
        HDT Daimler dial                  10 nos each
 3
        Bajaj JL dial & John Deere dial   5 Nos each
 5
        TATA Prima dial (New option)      10 nos
 6
        TATA Prima dial (New option)      20 nos




                                                                    10
List of jobs of JUNE 2012
                                              Custom DATE                      Status
SR No.                   JOB                                                                       Things gone Right
                                                 er    Received             Sales status
  1    Classic Inshop- repeat order (2                                                          FTR approved
       artwork)
                                                ITC     2-Jun PRODUCTION DONE, 11-Jun
       repeat size ( 17.3" x 17")
       new size ( 22" x 14")
       Royal Onshop, 3'X6'                                                                      Clear and well file
  2                                             ITC     9-Jun Awaiting feedback
                                                                                                information
       Gold Flake red Onshop Vinyl, 3'X6'
                                                            Background : approved Brandboad :   Clear and well file
  3                                          ITC    1-Jun
                                                            approved                            information
       Gold Flake red Onshop PC, 3'X6'
                                                            Background : approved Brandboad :
  4                                          ITC    1-Jun                                       Clear and well file
                                                            approved                            information
       Flake Filter BRANDBOARD
       1) flake BB straight Printing                        Background : approved Brandboad :
  5    2) flake BB reverse Printing          ITC   19-Jun
                                                            approved                            Clear and well file
                                                                                                information
  6    NAVY CUT ACP, 59cmx 89cm              ITC   22-Jun Awaiting feedback
                                                          As per the instructions
                                                          received by Nandini
                                                          kindly stop all the sample
       NAVY CUT Reverse printing 17" x
                                                          developments on clear acrylic.
  7                                          ITC   22-Jun
       22"                                                We will not be using
                                                          3mm clear acrylic henceforth.
                                                          We are going to try some
                                                          alternate base material
                                                                                                                  11
Sr. No               JOB           Customer
                                                          Costing                 Sampling
         KUBOTA (225 RFQ)
                                                39 RFQ Submitted on PC
  1                                    KUBOTA   22 RFQ Submitted on PVC
                                                22 RFQ Submitted on PVC
                                                Total 83 RFQ Submitted
         KUBOTA (225 RFQ)
                                                39 RFQ Submitted on PC
  2                                    KUBOTA   22 RFQ Submitted on PVC
                                                30 RFQ Submitted on PVC
                                                Total 91 RFQ Submitted
  3      Sample Development   KUBOTA                                      30 pcs. Each submitted
                                                                          Dt. 28-06-2012
  4      Sample Development   KUBOTA
         Sample Development   KUBOTA
         Sample Development   KUBOTA                                      HOLD for Customer Inputs
         Sample Development   KUBOTA




                                                                                               12
In Lac

    Month
                 Apr     May    Jun          Jul     Aug         Sep         Oct     Nov    Dec     Jan         Feb     Mar     Total    Actual
   2010-11
Purchasing
                 817    1073    1122
Value
Target            57     75      79

Actual Savings    5.1    89     15.5

%                9%     118%    20%



         100
          90
          80
          70
          60
          50                                                                                                                  Actual Savings
          40                                                                                                                  Target
          30
          20
          10
          0
                 Apr    May    Jun     Jul         Aug     Sep         Oct     Nov    Dec     Jan         Feb     Mar

                                                            PO:
Inventory Analysis (Material Rx Vs Consumed)
                                 April to Mar 2013

                 May-                                                              Mar-
   Month   Apr-12 12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 13  Total
    Matl
 Recd(in L) 817     1073   1122                                                           3012
    Matl
Issued(in L) 1083   1363   1325                                                           3771




1600
1400
1200
1000
 800
 600                                                                          Matl Recd(in L)
 400                                                                          Matl Issued(in L)
 200
  0




                                      PO:
Inventory Valuation
                                          April to Mar 2013

                     May-               Aug-               Nov-        Jan- Feb- Mar-
 Month      Apr-12        Jun-12 Jul-12      Sep-12 Oct-12      Dec-12                Total
                      12                 12                 12          13   13   13
  Local
&Import ( 1280       1365   1356                                                                    4001
  Lacs)
 Target      1527    1628   1845   2080    2228    2316                                            11624



2500

2000

1500
                                                                                     Local &Import ( Lacs)
1000                                                                                 Target

 500

   0
          April May June July      Aug    Sep    Oct   Nov   Dec   Jan   Feb   Mar


                                           PO:
Months      Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13

Inv Turns     10     12     12

 Target       11     11     11     11     11    11     11     11     11     11     11         11



 12.50

 12.00

 11.50

 11.00
                                                                                  Inv Turns
 10.50
                                                                                  Target
 10.00

  9.50

  9.00



                                        PO:
Total
Month               April   May    June   July    Aug         Sep         Oct     Nov    Dec    Jan   Feb     Mar
Last year ( 11-     2.40    1.78   0.0     0.0        0.0     1.9         0.0     0.3    0.0    0.0    1.9     2.35       10.6
12)
                    2.37    1.98    0.6                                                                                   4.95
This Year (12-13)
Target Rs in
Lakhs                4.0    4.0    4.0     4.0        4.0     4.0         4.0     4.0    4.0    4.0    4.0     4.0        48.0


 4.50
 4.00
 3.50
 3.00
 2.50                                                                                                 Last year ( 11-12)
 2.00                                                                                                 This Year (12-13)
 1.50                                                                                                 Target Rs in Lakhs
 1.00
 0.50
 0.00
         April May June July       Aug    Sep    Oct        Nov     Dec     Jan    Feb    Mar

                                                PO:
Description      Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13
      Base Film    49        49     49
  Application
                   32        31     31
     Film
         Ink       24        24     24

  Grand Total      105      104    104

       Target      105    102     101    98         95   93   91     88     85     81     78     75



120

100

 80

 60
                                                                                               Grand Total
 40
                                                                                               Target
 20

 0




                                              PO:
10
          12
          14
          16




           0
           2
           4
           6
           8
  Avg.                                                                         13.48
                                                                               13.66
(11-12)
                                                               9.48
Apr-12                                                         9.88
                                                               10.07
                                                                       10.22
May-12                                                                 10.70
                                                                       10.69
                                                                             10.92
Jun-12                                                                          13.44
                                                                              12.08

 Jul-12

Aug-12

Sep-12

Oct-12

Nov-12

Dec-12

Jan-13

Feb-13

Mar-13
          Sales (Rs.Crs.)
                            Actual Prod (Rs.Crs.)
                                                    Budget Prod (Rs. Crs.)
Target
         Actual




                                  99.56
                  99.35



                          99.23




                                          99.15
                   100



                           100



                                  100



                                           100



                                                  100




                                                                    100



                                                                          100



                                                                                100



                                                                                      100



                                                                                            100



                                                                                                   100
                                                        100



                                                              100
        100

         95

         90
% OTD




         85

         80

         75

         70
                Avg. Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-12 Feb-12 Mar-12
              (11-12)
New models AACA       New Models
                    & K06A           AANA & AAGA



                                  Target      Total Freight cost (%) on sale   Premium Freight (%) on sale

0.7              0.63     0.62
0.6    0.54
0.5                                  0.46

0.4
0.3
                   0.22     0.20
0.2
                                       0.10
0.1      0.07

 0
      Avg. 11- Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13
        12
Capacity Planning for July’ 12 to Sept’ 12


Capacity Planning - July' 12 to Sep' 12 - Pelhar Plant
Sales Budget
                        Jul-12            Aug-12         Sep-12
(Sets)                                                                   Total
HMCL                        389100            362625         387385        1139110
BAL                          90900              90400         90400         271700
Yamaha                       32700              45000         43600         121300
Suzuki                       30000              31500         31500              93000
M&M                            4200              4200             4500           12900
Total                       546900            533725         557385        1638010


Production
Budget (Sets)               601590            587098         613124        1801811
Planned
Utilization (%)                  78                 76             86              80
Dial Capacity Planning July’ 12 to Sept’ 12



                       Capacity Planning - Jul' 12 to Sep' 12 - Pelhar Plant
Sales Budget -
                         Jul-12              Aug-12               Sep-12
Dials                                                                           Total


PRICOL                   107850              132050               156150       396050

CONTI                    39300                45300               47300        131900

TOTAL                    147150              177350               203450       527950


Total Prod Budget        183938              221688               254313       659938


Capacity - Dials         452603              452603               417787       1322992


Planned %
                           41                   49                  61           50
Utilization
Sales & Production Plan – June ’12



                   Sales & Production Plan -Jul 12
                                      Actual Opening Stk
                          Stocking                         Product Schedule
Customer Sales Plan
                           Norms     BSR     Depot   Total ion Plan Value

HMCL           10.000       5.000    0.000   5.560   5.560   9.560    10.120
BAL            0.800        0.400    0.007   0.290   0.297   0.800    1.210
Yamaha         0.300        0.150    0.002   0.194   0.196   0.254    0.292
Suzuki         0.200        0.100    0.020   0.008   0.028   0.272    0.017
M&M            0.050        0.025    0.025   0.000   0.025   0.050    0.051
Godrej         0.020        0.010    0.000   0.000   0.000   0.035    0.025
Pricol/Conti
.              0.200        0.100    0.003   0.001   0.004   0.270    0.174
Export         1.150        0.000    0.000   0.000   0.000   1.150    0.530
Total          12.720       5.785    0.057   6.053   6.110   12.391   12.419




                                                                               24
60
                                   64
                                        66
                                              68
                                                   70
                                                             74
                                                                  76




                              62
                                                        72



                                             66
                                                             73
          Avg. (11-12)




                                        65
                                                                  75
               Apr-12




                                        65
                                                                  75



              May-12




                                        65
                                                                  75




               Jun-12
                                                                  75




                Jul-12
                                                                  75




              Aug-12




Target
                                                                  75




               Sep-12
                                                                  75




               Oct-12
Average
                                                                  75




              Nov-12
                                                                  75




               Dec-12
                                                                  75




               Jan-13
                                                                  75




               Feb-13
                                                                  75




              Mar-13
Avg. (11-                                         Sep-        Nov-   Dec-                 Mar-
                                   Apr-12 May-12 Jun-12    Jul-12 Aug-12        Oct-12             Jan-13 Feb-13
        Month              12)                                              12          12     12                   13

      Description

Total Loading Time (min.) 204595 162714 184178    201729


Total Down Time (min.)    61233   58657   59206   61105

  Total Down Time (%)     30.00   36.05   32.15   30.29

Reasons of Down Time


                          13681   20864   12757
  Planned Shut Down                               13638

                                          4568
                          4655    3609
    Screen Related                                3571

                                  30045   37828
                          38824
    Process Related                               39305

      Ink Related                 3474    3140
                          2894                    3561

  Maintenance Related     1180     665    913
                                                  1030

                                                                                                                    26
Traget         % OT Cost (Support) to Production (Production)
                                              % OT Cost           % OT Cost                           % OT Cost (Total)


         1.20    0.97
         1.00
         0.80
  % OT




         0.60                      0.59 0.39
                                 0.27
         0.40             0.13 0.14       0.20
         0.20               0.01     0.32 0.19
         0.00
                Avg. (11- Apr-12 May-12 Jun-12   Jul-12   Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13     Feb-13 Mar-13
                  12)
                                                                Month




• New Model AAGA – Super Splendor processed on short lead time.
• Increased changeovers in SPD due to Brand Migration at HMC
• M/C Allocation for ITC Sampling
                                                                                                                          27
Actual Target
  Machine       April   May   June   July   Aug   Sept   Oct   Nov   Dec   Jan   Feb   Mar
                                                                                             (Avg) (Avg)

REBOLINI -1      91     87    87
REBOLINI -2      82     82    94
BHARAT BIG -1    83     72    98

BHARAT BIG -2    89     89    81
BHARAT
SMALL -1
                 82     78    91

BHARAT
SMALL -2
                 76     76    70




                                                                                                     28
Rejection %




                                                                                                            10.00%




                                                                          6.00%
                                                                                            8.00%




                         0.00%
                                 1.00%
                                         2.00%
                                                 3.00%
                                                         4.00%
                                                                 5.00%
                                                                                    7.00%
                                                                                                    9.00%
             Avg. (11-
               12)




                                                                          5.96%
               Apr-12


              May-12                                                              6.85%




                                                                  5.10%
               Jun-12
                                                                  5.13%


               Jul-12


              Aug-12


              Sep-12




     Month
               Oct-12


              Nov-12


              Dec-12


               Jan-12


              Feb-12


              Mar-12
29
10.00
                           9.44
 9.00
 8.00        8.00                 8.13
 7.00               7.19
 6.00
 5.00                                                                                    Unit 1
 4.00                                                                                    Pelhar
 3.00                                                                                    Haridwar
 2.00
 1.00
 0.00
                                   Jul
        Target




                                         Aug




                                                           Nov


                                                                       Jan
                                                                             Feb
                                                                 Dec




                                                                                   Mar
                       May




                                               Sep
                 Apr




                                                     Oct
                             Jun




                                                                                                    30
DIAL Rejection trend

                   Nov     Dec            Jan     Feb          Mar     April        May       June July Aug         Sept   Oct


  Pricol           16       15            20.71 10.54 14.58             9.5         9.56

Continental        50       24            52.38 30.83 34.08                 28      31.44

 Diffuser           0           0         41.82 64.77 43.04 27.94 39.25


              70

              60

              50

              40
                                                                                                         Pricol

              30                                                                                         Continental
                                                                                                         Diffuser
              20

              10

               0
                    Nov   Dec       Jan    Feb   Mar   April   May   June    July   Aug     Sept   Oct
8
 7
 6
 5
 4
 3
 2
 1
 0
         Apr




                                                        Oct
                          Jun




                                                                       Dec




                                                                                          Mar
                                  Jul




                                                               Nov




                                                                                                   A: 11-12

                                                                                                               A: 10-11
                                                                              Jan

                                                                                    Feb
                  May




                                         Aug

                                                Sep

                                               Pelhar         Target

 Internal                                                                                        Actual Actual
          April May June          July   Aug   Sept   Oct Nov Dec       Jan   Feb   Mar Target
Rejection                                                                                        11-12 10-11


Pelhar     4.05    3.63    3.85                                                           4.0%    4.0         5.7
13000
    12000
    11000                                       Line Rejection – BAL (2011-12)
    10000                                                                                                      W&C
     9000
     8000
     7000
     6000
     5000
     4000                                                                                                      Target
     3000
     2000
     1000
        0




                                                                            Nov
                        Apr




                                                        Aug




                                                                                  Dec
                                          Jun


                                                  Jul




                                                                                               Feb
                                 May
             Actual:




                                                                    Oct




                                                                                                      Mar
                                                                                         Jan
                                                              Sep
              11-12




Line rejection ppm from Varroc - Pantnagar
   TARGET    ACHIEVED TARGET APRIL MAY- JUNE-12 JULY-12 AUG-              SEP-12 OCT-12 NOV-12 DEC-12 JAN-13 FEB-13 MAR-
   2011-12    2011-12 2012-13 12    12                   12                                                          13


    3000        11909         3000     6001 11986




                                                                                                                   33
Vendor Rating - Bajaj



                             CSPL (Vendor) Rating from BAJAJ [2012-13]

           Standa
Customer           APRIL MAY     JUN     JUL   AUG    SEP    OCT   NOV   DEC   JAN   FEB   MAR
           rd
BAL – WC   < Level
(100487)   2         2    3       3

BAL –      < Level
Haridwar   2         2   2        2
(111407)




                                                                                            34
Line PPM feedback from M&M FES



                                                                                              Actual 2012-13
 Line ppm:
                Actual
  MM FES                        Apr                May         Jun         Jul      Aug         Sep         Oct         Nov   Dec   Jan   Feb   Mar
                11-12
TARGET LR
PPM <250         618            258                13
ppm

% GR
                  3                     0            0
Rejection = 0



                                                          M&M FES - Line ppm [12-13]
                                                              Target: 250 ppm
                  700
                  600
                  500
                  400
                  300
                  200
                  100
                      0
                          Actual 11-…




                                                                                        Nov
                                                                     Aug
                                            Apr




                                                               Jul
                                                   May




                                                                                                Dec
                                                                            Sep




                                                                                                            Feb
                                                                                  Oct




                                                                                                                  Mar
                                                         Jun




                                                                                                      Jan




                                                                                                                                                  35
Line PPM feedback from Tafe




 Line ppm:    Actual                                       Actual 2012-13
    Tafe      11-12     Apr     May      Jun   Jul      Aug Sep     Oct   Nov    Dec   Jan   Feb   Mar
TARGET <100
               865      250         0     0
ppm




               1000                              Past trend    Target   Actual
                900    865
                800
                700
                600
                500
                400
                300           250
                200
                100
                  0




                                                                                                     36
4. Summary of Complaints

                       Apr   May   Jun   Jul   Aug   Sep   Oct   Nov   Dec   Jan   Feb   Mar
No. of Complaints       3     2    6                                                           1

Nature of Complaints
low Gloss               1




Complaints by Customer
Varroc – Chakan        1




                                                                                               37
5. Summary of Corrective actions - June


Sr.No    Customer        Complaint Description                     Root Cause                                    Corrective Action
                                                                                                1] Work instruction amended for the method
           IYM-                                    Levelling of blade on one side of die
 1                 Graphic Cut in 1CK2                                                          of visual checking of deepcut,
          Surajpur                                 found out to be uneven.
                                                                                                2] job training provided to the inspectors.
                                                   Uncoated metallic particles have less
                                                                                                Coated metallic particles to be used. Bill of
           IYM-    Ink peel off in Yamaha          cohesive force as compared to coated
 2                                                                                              material amended and also the process
          Surajpur Emblem (5KAB CRUX)              metallic particles used in ink
                                                                                                routing changes in SAP.
                                                   preparation.
           IYM-                                    New material was used - inadequate           PPAP methodology to be followed for new
 3                 Air Bubbles in 1CK3
          Surajpur                                 validation                                   material introduction
                     Disc. 125 ST Shade
                                                   Variation in deposition of metallic
          Bajaj - Variation found in Flame red                                                  Uniform stirring during ink issue also stirring
 4                                                 partcile on base film during printing in
           Waluj     for batches 446052012 &                                                    prior to pouring ink on the screen.
                                                   single batch.
                     70062012
                     Smoke Variation found in                                                   Setup Sheets/Dials to be crossed completely
                                                   Setup sheet is not identified at printing
                     HDT Diamler in 1 pieces in                                                 using permanent marker in printing stage
                                                   stage before proceeding for further
        Continental- lot size of 300 of batch                                                   itself.
 5                                                 operation leading to mixing of setup
        Bengaluru number 2021211 at customer                                                    Illumination inspection to be done on Cluster
                                                   sheets/dials with Ok sheets/dials at final
                     assembly line at Continental,                                              instead of light table.
                                                   inspection.
                     Bangalore on 20/06/2012.
                     Green and white dots found                                                 Before commencing printing a pc sheet with
                                                   Leakage in screen due to removal of
                     in HDT Daimler in 59 pieces                                                lamination and/or rough pc sheet will be
                                                   emulsion coating from non image area
        Continental- in lot size of 300 of batch                                                printed and checked for ink leakage and
 6                                                 leading to green and grey ink transfer
        Bengaluru number 2021211 at customer                                                    same will be done after every 100th and for
                                                   on image area while printing 5th Colour
                     assembly line at Continental,                                              last sheet and leakages if any will be touched
                                                   and 6th colour respectively
                     Bangalore on 20/06/2012.                                                   up by PVA
HMC-G– Quality Failure Report
Plant SL     Material   Material    Problem Analysis Action Type   Reason            Counter Measures
      No.    Code       Description
HMC-G 1.     240512     CBZ Stripes Incomplete       -Samples      -Process lapse    -Yet to be
                                    back cut         sent to plant                   received



        2.   5940312=0 KWAH Front Incomplete        -Samples      -Process and       -Yet to be
             9         Cowl Blk   back cut(10-      sent to plant inspection lapse   received
                       Blue       12%)



             2470512=0 KVEG CVG -Incomplete         -Samples      -Process and       -Yet to be
             9                  back cut(25-        sent to plant inspection lapse   received
                                30%)



             3160612=0 KWAH Front -Incomplete    -Samples      -Process and          -Yet to be
             9         Cowl cover back cut(3-5%) sent to plant inspection lapse      received
                       BHG
HMC-D – Line feedback
Customer               Issue                  Batch No.      Observation               CAPA / Comments
HMC-D      1.Craters observed in model       5560412      -Observed after       -Yet to be received from plant
           splender plus AAEA                             lacquering process.   -IPA cleaning introduced prior to
                                                          -Reduces after        lacquering and after that no
                                                          cleaning with IPA.    problem has been reported.

           2.Skinning observed in stripes    2640512      -Observed in 10-      -Yet to be received from plant .
           of model AAEA SBK                              15% stripes
           -model AAEA P.maroon              0320120376   -obsd. In 20-25%                   -do-
                                                          pcs.

           3.Top film removal hard           3100512      -Observed in 30-      -Yet to be received from plant.
           observed in stripes of model                   40% stripes
           AADA BLK Sil

           -Splendor pro color SBK           0520120425   -observed in 30-      -Yet to be received
                                                          40% stripes

           4.Hole punching in stripes            -        -Repeated problem     -Inform to all concerned with
                                                          & Observed in the     compiled data.
                                                          materials belonging
                                                          to march 12
           5.Incomplete back cut at tab
           location in side cover color      0520120425   -Observed in 30-      -Yet to be received.
           SBK                                            35% pcs.
Customer Line feedback-Yamaha SP

Customer                Issue               Batch No.           Observation             CAPA / Comments
IYM-SP     1.Ink peel off in yamaha                     -Ink peel off while removal    -Submitted on
               emblem model 5KA                         of top application film        23.04.2012


                                           5470412      -Problem repeated              -Submitted on
                                                                                       26.06.2012
                                                                                       -Fresh batch yet to
                                                                                       be delivered

           2.Craters in stripes of model   0120120743   -Problem observed at edges     -Submitted on
                1CK3                                    in different locations after   26.06.2012
                                                        lacquering                     -Fresh batch after
                                                                                       c/m yet to be
                                                                                       received
Major Highlights (Quarter-1)

• April12: First Surveillance Audit inline with
  TS:16949/2009 conducted by Bureau Veritas.
• May12: Supplier Surveillance Audit (QAV-1)
  conducted by Mahindra 2 Wheeler.
• May12: Visit of John Deere to Pelhar Plant.
• June12: Green Vendor Development Program
  (GVDP), certificate received by HMCL Gurgaon.
• June12: Supplier Development Audit conducted
  by Royal Enfield.
Ink Lab – Issues report for June
                                             OC Peeloff Problems

Job Details         Issue           Root Cause                            Corrective Action
AANA GLM CARB CB OC & Ink peel off Uncoted silver particles in CSPL 057   (CSPL 2285) New Accurate
RED ABS PART & KTRM                (accurate silver)                       Silver by Coated Stapa VK
Glm. FI CB RED ABS                                                        903/904 ECN raised
part ( HMCL)


KVEG CBZ EXTREME - OC & Ink peel off
                                              SG 700 Base coat            Eliminate
HMCL
                                             SG 700 Conc White            HD White
                                             CSPL 1007 (425 OC)           CSPL 2120 (8228 OC)
                                                                          ECN raised

                                       VK901 in CSPL 438 Pastel Gold
YAHAHA Emblem        OC & Ink peel off Shade                              Used Stapa 801 silver particles
                                       CSPL 1007 (OC 425)                 CSPL 1007 (OC 425)
                                                                          ECN raised




                                                                                                            43
Ink Lab – OC Wastage for June

                                                                                 Wastage   % Wastage
PO no.    Machine Description                                 Qty. 8600 OC                             Average
                                                                                 Qty.Kg       OC

100068194 SPS-XP   KWAH BLK H. GREY F/COWL (T-3) [4 SETS]     2000      8.8       1.781     20.20%

100068200 SPS-XP   BAJAJ DISC 125ST BLK RED SEAT/FR.COWL(1S   2000      16         3.6      22.50%

100068001 SPS-XP   KTPJ C.B.RED T-2 FUC 'A', BC 'A' (1SET)    2600     11.2       2.544     22.70%

100068691 SPS-XP   BAJAJ DISC 125ST BLK RED SEAT/FR.COWL(1S   1860      6.4       1.384     21.50%

100068615 ATMA-6   EXPORT                                     1000      5.8       1.19      20.50%

100070565 ATMA-6   EXPORT                                     500       4.5         1       22.20%     21.65%


                                                                     CSPL 2120   Wastage   % Wastage
PO no.    Machine Description                                 Qty.                                     Average
                                                                     of Nazdar   Qty.Kg       OC

100067055 SPS-XP   AACA PASSION PRO BLK H.GREY SC (2SETS)     2272     10.5       2.44      23.20%

100068298 SPS-XP   AAFA SPL.NXG BLK RED ABS PARTS(1SET)       3000     16.8       4.27      25.40%

100067415 SPS-XP   AACA[PASS.PRO]BLK H.GREY ABS (1SET)        2300     11.2        3.5      31.25%

100068271 SPS-XP   BAJAJ PULSAR 135 RED ABS(4SETS)            600       3.5        1.2      34.20%

100068001 SPS-XP   KTPJ C.B.RED T-2 FUC 'A', BC 'A' (1SET)    1100      5.6         1       17.80%

100068604 SPS-XP   KWAH BLK RED/BLUE /H.GREY R/COWL(5SETS)    2500     14.4        3.4      23.60%      26%


                                                                                                          44
Machine          Total Downtime      Avg. Downtime      Avg. MTBF        Avg. MTTR
                          (mins.)         per day (mins.)     (mins.)          (mins.)
    Sakurai-01             465                 18.6           21367.65           465
    Sakurai-02             115                  4.6             7408             38
      SPS-01               205                  8.2             8599            51.25
      SPS-02                60                  2.4            21570             60
      SPS-03                 0                  0              43200              0
      SPS-04                30                  1.2            14390             15
      SPS-XP               320                 12.8             8576             80
      Others               430                35.33           2177.62           57.63
 TOTAL (JUN’ 12)           1700               68.00           1507.73           95.86
 TOTAL (MAY’ 12)           1960               40.80           1579.80           42.70
  TOTAL (APR’ 12)          982                40.80           1579.80           42.70
 TOTAL (Mar’ 12)           2429               83.29            879.40           51.68
MTBF – Mean Time Between Failures; MTTR – Mean Time To Repair
Downtime for Rolt is not considered as there are some manufacturing defects which lead to
downtimes.
                                                                                            45
3500
                                                                               Downtime 2011-12
                                                    Monthly                     3147
                                                Downtime Limit                 Downtime 2012-13
3000                                             is 2000 mins.
                                        2580                                             2582
                                                         2448                                     2429
2500
               2201                                              2148
                                                1957
2000
                               1735
                                                                         1653
         1517          1506
1500

1000

 500

  0
                 May




                                 July




                                                                                                    Mar
                                                                         Dec
                        June




                                                                                   Jan


                                                                                           Feb
                                                           Oct


                                                                   Nov
                                                  Sept
       April




                                          Aug




                                                                                                      46
CYLINDER PRESS DOWNTIME FOR LAST 12 MONTHS (mins)

Machine/   SPS-01   SPS-02   SPS-03   SPS-04   SPS-XP   SK-01   SK-02
 Month
 June12     205      60        0        30      320      465     115
 May12       0       245       0       200       0       20      130
 Apr’12
             40      65        0        0        40       0      110
 Mar’12
             75      70        00      113      223      345     15
 Feb.’12
            144      155      128      337      200      200     30
 Jan’12     202      375       86      147      182      87      30
 Dec’11     130      192       30      405       90       0       0
 Nov’11      0       175      285      145      270      20      110
 Oct’11      5       428       20      198       80       5      220
 Sept’11    115       0       165       40      105       0      25
 Aug’11     110      119       30      125       30       0      75
 July’11     240     145       0        105      410     70      240
 TOTAL      1266    2029      759      1845     1950    1212    1100
Average    105.5    169.08   63.25    153.75   162.5     101    91.66
Electricity Units 2010-
800000                                                                                         11
                                                                     Sudden increase is due
                                                                     to increased HVAC load
700000
                                                                        and machine load.
                                                            589080
600000              560790   566430    564000    555180             547590                                  551910559709
         527070                                                       521501    504090
                                                          513840                                         506576
                                                                             493710   496020   492535
500000                475710
                                                                                          492390
                                                                                                   488250
            435450             430266    425790    437071

400000


300000


200000


100000


    0
                       May




                                          July




                                                                                                                     Mar
                                June




                                                                                         Dec


                                                                                                   Jan


                                                                                                             Feb
                                                                       Oct


                                                                                Nov
                                                             Sept
            April




                                                    Aug




                                                                                                                       48
MAINT. BREAKDOWNS & PREVENTIVE ACTIONS



           Breakdown       Down
Machine                            Corrective Action       Preventive Action
             Reason        Time
 SPS XP       Machine      320    Damaged Cable         PLC’s input ,output function
          wasnot running mins.    replaced with the     ‘Check Point’ will be
            due to faulty         New Cable.            checked in ‘Preventive
            cable of PLC                                Maintenance’.
          input Contacts..
  SK-1     Shear Key of   465     Shearkey replaced     Shear Key Check Point
           the Gear-box   mins.   with new Shearkey.    included in the ‘Preventive
            was broken.                                 Maintenance’.

  SK-2      Timer Belt    165     Timer Belt replaced   Timer Belt will be replaced
          damged of the   mins.   with new one.         once in a year.
          Vaccum Pump.
500
                                                           Sales (Rs.) per Electrical Unit
                                                           2011-12
450                                                        Sales (Rs.) per Electrical Unit
                                                           2012-13
400
                                  Monthly Target for
                                  Sales (Rs.) per Elec.
350                                 Unit is Rs. 300.

300

250

200

150

100

 50

 0
              May




                           July




                                                                                             Mar
                                                     Oct
                    June




                                                           Nov


                                                                    Dec


                                                                            Jan


                                                                                     Feb
                                           Sept
      April




                                  Aug




                                                                                             50
800000
                                                                          Electricity Units 2011-12
                               Sudden increase is due
700000                                                                    Electricity Units 2012-13
                               to increased HVAC load
                                  and machine load.
600000


500000


400000


300000


200000


100000


    0
                 May




                              July




                                                                                  Mar
                                                                    Jan
                                                              Dec
                       June




                                                  Oct

                                                        Nov




                                                                           Feb
                                           Sept
         April




                                     Aug




                                                                                                51
9000                                                       Units consumed by DG
        8200                                               Sets 2011-12
8000                            7657                       Units consumed by DG
                                                           Sets 2012-13
7000

6000
               5412                    5370

5000
                                                                                         4238
4000             3797


3000                                                                              2576
                                              2378
                        1836
2000
                                                                   1275
                                                                          998
1000   555                                           501
                          337
                                                             0
   0




                                                                                    11
                 2




                                  4
        1




                          3




                                         5


                                              6


                                                     7


                                                             8


                                                                    9


                                                                           10




                                                                                           12
                                                                                            52
As on As on
Sr. No      Description    March March April   May   June   July   Aug   Sept   Oct   Nov   Dec   Jan   Feb   Mar
                           2011 2012


  1      No. Of Staff       87   106    100    99    94


         No. Of Company
  2                         94   118    119    117   117
         Workmen

         No. of Contract
  3
         Workmen
                           423    432   381    405   398



         Total Manpower    604    656   600    621   609
Figures in Mn.Rs




   Description      April May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

Total Production.   98.8   107.0   106.9



Salary & Wages to
% of Production.  7.33%    8.59%   7.74%
Mn. Rs.

Contract Wage Bill
                   3.16% 3.11% 3.03%
% to sales

On Roll Overtime
Cost to % of        0.06% 0.15% 0.12%
Production


Contract Overtime
Cost to % of      0.07% 0.44% 0.34%
Production.



                                                                                                 54
Description    April   May-11 Jun-11   Jul-11   Aug-11   Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12   Total

ELECTRICITY/POWE
R EXPENSE -
                 2.81      2.88   2.85    3.96     5.44     5.29     5.40   5.90   6.17   5.99   5.60   5.76   58.06
MANUF

ACTUAL EXPENSES   4.25     2.91


FUEL EXPENSES -
                                   -        0.08    0.08      0.08                  -
MANUFACTURING       -      0.08                                       -     0.08          0.08    -     0.08   0.56



ACTUAL EXPENSES     -      0.12




REPAIRS & MAINT- 2.50      2.50   2.50    2.00     2.00     2.00     2.00   1.20   2.00   1.50   1.20   1.20   22.60
   MACHINERY

ACTUAL EXPENSES 2.45       0.71



                                                                                                               55
Description      April   May    Jun    Jul    Aug    Sep    Oct    Nov    Dec    Jan    Feb    Mar    Total

 CONSUMABLE
   SUPPLIES       0.92    0.93   1.05   1.43   1.73   1.76   1.91   1.98   2.16   2.20   2.45   2.69    21.20


ACTUAL EXPENSES   1.11    0.49

DIE PURCHASES &
 DEVELOPMENT      0.28    0.28   0.32   0.43   0.52   0.53   0.57   0.59   0.65   0.66   0.73   0.81    6.36


ACTUAL EXPENSES     -     0.31

  POSITIVE &
   NEGATIVE
                  0.07    0.07   0.08   0.11   0.14   0.14   0.15   0.16   0.17   0.18   0.20   0.22    1.70
  DEV.CHARGS

ACTUAL EXPENSES   0.02     -

   PRODUCT
 DEVELOPMENT
                  0.18    0.19   0.21   0.29   0.35   0.35   0.38   0.40   0.43   0.44   0.49   0.54    4.24
     CHGS

ACTUAL EXPENSES   0.21    0.06




                                                                                                       56
Description     April   May-11 Jun-11   Jul-11   Aug-11 Sep-11 Oct-11 Nov-11 Dec-11   Jan-12 Feb-12 Ma-12r   Total
SCREEN MAKING
   EXPENSES        1.01     1.02   1.16     1.57     1.90   1.93   2.10   2.17   2.38     2.42   2.69   2.96    23.32


ACTUAL EXPENSES    0.90     2.20


LABOUR CHARGES
                   4.46     4.46   4.48     4.83     5.35   5.99   6.02   6.50   6.85     6.77   6.99   7.04    69.73


ACTUAL EXPENSES    4.36     5.06

TRANSPORT
CHARGES BY ROAD-
                   0.17     0.18   0.20     0.27     0.33   0.33   0.36   0.38   0.41     0.42   0.47   0.51    4.03
OUTWARD

ACUTAL EXPENSES    0.03     0.11

TRANSPORT
CHARGES OTHERS-
                   0.55     0.56   0.63     0.86     1.04   1.06   1.15   1.19   1.30     1.32   1.47   1.61    12.72
OUTWARDS

ACTUAL EXPENSES    0.46     0.54




                                                                                                                57
Description     April   May-11 Jun-11   Jul-11   Aug-11 Sep-11 Oct-11 Nov-11 Dec-11   Jan-12 Feb-12 Mar-12   Total


REPAIRS & MAINT-
                   0.18     0.18   0.18    0.18      0.18   0.18   0.53   0.53   0.53     0.53   0.53   0.53    4.20
BUILDING

ACTUAL EXPENSES      -

MOTOR CAR /
CYCLE FUEL
                   0.20     0.20   0.20    0.20      0.20   0.20   0.20   0.20   0.20     0.20   0.20   0.20    2.40
EXPENSES
ACTUAL EXPENSES
                   0.12



SECURITY CHARGES   0.33     0.33   0.33    0.33      0.33   0.33   0.33   0.33   0.33     0.33   0.33   0.33    3.90

ACTUAL EXPENSES
                   0.24



GARDENING EXP      0.05     0.05   0.05    0.05      0.05   0.05   0.05   0.05   0.05     0.05   0.05   0.05    0.60

ACTUAL EXPENSES
                     -

HOUSE KEEPING
EXPENSES           0.35     0.35   0.35    0.35      0.35   0.35   0.35   0.35   0.35     0.35   0.35   0.35    4.20

ACTUAL EXPENSES
                   0.33



                                                                                                                58

~0614607

  • 1.
    Mn. Rs Month April May June July Aug Sept Oct Nov Dec Jan Feb Mar Total Total Sales 238.08 255.07 259.10 Segment Sales April Sales May Sales June OEM 207.63 228.10 229.91 Retail 21.22 17.50 19.95 Exports 7.42 7.23 8.14 Fleet 1.81 2.25 1.10 Total 238.08 255.07 259.10 1
  • 2.
    Mn Rs. Month April May June July Aug Sept Oct Nov Dec Jan Feb Mar Total Budgeted Material 44.70 46.06 Consumption Actual Material 48.33 Consumption 51.85 PO:
  • 3.
    Pelhar April May June July August Sept Oct Nov Dec Jan Feb Mar Installed Capacity 0.76 0.83 0.83 ( Million Sets) Utilized Capacity 0.33 0.45 0.50 (Million Sets) % Utilization 43% 55% 61% 3
  • 4.
    EXPORTS Projects PROJECTS Status on JUNE 2012 HONDA A countermeasure was given to Honda ,where CSPL-TVF-3PLE-1 material is to be used. All the materials available in Pelhar and Unit I were under deviation ,traced one roll at haridwar which was without deviation and passes HES specs hence procured that from Haridwar, on which gloss patches were printed . These patches passes in fuel oil resistance test where as fails in E10 and E20 solution for both Type 4 and Type 6 panels. Testing presently under process for original Honda Decal for E10 and E20 solution reports will be submitted by July 1st week MIO-PINK Printing done with following combination and test conducted results found as under, (Yamaha Material used as Indonesia) 1.PVC WB80 PA 10 11LLY 2.PVC WB80 PA T1 11LLY 3.CSPL-WVF-3P-1 4.CSPL-WVF-3P-2 Printed OC with following combination 1.V3 + 45% Non silicon 8228 OC 2.V3 + 8600 OC 3.V3 + SIEKO 5412 UV All the material printed with V3 + Sieko 5412 UV fails in WOM after 400hrs,where as material printed with other two OC passes in WOM till 400 hrs and is continued for 900hrs KUBOTA Approved Drawing submitted (K7564-65231,K7311-65206,K7721-65801,K2581-65205) on 14.6.2012 and 18.6.2012. Awaiting for the release of the P.O 3/18/2013 4
  • 5.
    Membrane Switch Projects TYPEOF MEMBRANE STATUS IN JUNE 2012 SWITCH LG samples will be submitted by 11-07-12 LG LG quote submitted on 2.7.2012 ,awaiting feedback from Mktg Location finalized for MS assembling (In dial post curing Membrane switch area) .Layout to be finalised production set-up Testing equipments (MS tester, life tester & Hipot tester) Membrane Switch ordered, expected by mid July 2012 Equipments Hot air oven will be ordered after positive feed back from LG 2 man power to be taken from production for involving in Manpower MS start up production activities. Existing 2 persons 3/18/2013 5
  • 6.
    RAW MATERIAL TRACKINGSHEET 3/18/2013 6
  • 7.
    Month 2010-11 Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Average Target No. of Samples 67 40 44 dispatched Development 3.76 3.3 3.7 time (days) 5 4.5 4 TARGET 3.9 DAYS 3.5 3 2.5 2 1.5 1 0.5 0 Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
  • 8.
    No. of samples No. of production No. of production Segments Clients dispatched from this months sdr. previous months sdr. Ftr OEM TWO WHEELERS HERO 7 0 4 4 BAJAJ 4 0 0 0 YAMAHA 5 0 1 1 SUZUKI 1 0 0 0 MAH. & MAH. 8 1 2 3 M&M SWARAJ 2 0 1 1 JOHN DEERE 3 0 0 0 TAFE 10 0 2 2 MARUTI SUZUKI 1 0 0 0 OEM FOUR WHEELERS TATA MOTORS 4 0 0 0 & OTHERS ESCORT TRACT. 2 0 0 0 HAZARA 1 1 0 1 AUTOGRAPHIX ROYAL ENFIELD 1 0 0 0 OTHERS 4 0 1 2 AUTOGRAPHIX 4 0 4 4 SAUD BHAWAN 2 0 0 0 EXPORT ALJ 1 0 3 3 BANGLADESH 1 0 0 0 TOTAL 61 2 18 20 INTERNAL CUSTOMER HERO HONDA 15 15
  • 9.
    Month 2010-11 Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Actual Target No. of Samples 67 40 44 dispatched FTR 67 40 44 % FTR 100% 100% 94.4% ( days) % FTR 120% 100% 80% 60% 40% % FTR 20% 0% Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar No. of production from this Clients No. of samples dispatched months sdr. Ftr MAH. & MAH. 8 1 1 HAZARA 1 1 1 9
  • 10.
    S. No Dial Name Hand Over Date 1 HDT Daimler dial 10 nos each NGC Dial & Diffuser 180 nos each 2 HDT Daimler dial 10 nos each 3 Bajaj JL dial & John Deere dial 5 Nos each 5 TATA Prima dial (New option) 10 nos 6 TATA Prima dial (New option) 20 nos 10
  • 11.
    List of jobsof JUNE 2012 Custom DATE Status SR No. JOB Things gone Right er Received Sales status 1 Classic Inshop- repeat order (2 FTR approved artwork) ITC 2-Jun PRODUCTION DONE, 11-Jun repeat size ( 17.3" x 17") new size ( 22" x 14") Royal Onshop, 3'X6' Clear and well file 2 ITC 9-Jun Awaiting feedback information Gold Flake red Onshop Vinyl, 3'X6' Background : approved Brandboad : Clear and well file 3 ITC 1-Jun approved information Gold Flake red Onshop PC, 3'X6' Background : approved Brandboad : 4 ITC 1-Jun Clear and well file approved information Flake Filter BRANDBOARD 1) flake BB straight Printing Background : approved Brandboad : 5 2) flake BB reverse Printing ITC 19-Jun approved Clear and well file information 6 NAVY CUT ACP, 59cmx 89cm ITC 22-Jun Awaiting feedback As per the instructions received by Nandini kindly stop all the sample NAVY CUT Reverse printing 17" x developments on clear acrylic. 7 ITC 22-Jun 22" We will not be using 3mm clear acrylic henceforth. We are going to try some alternate base material 11
  • 12.
    Sr. No JOB Customer Costing Sampling KUBOTA (225 RFQ) 39 RFQ Submitted on PC 1 KUBOTA 22 RFQ Submitted on PVC 22 RFQ Submitted on PVC Total 83 RFQ Submitted KUBOTA (225 RFQ) 39 RFQ Submitted on PC 2 KUBOTA 22 RFQ Submitted on PVC 30 RFQ Submitted on PVC Total 91 RFQ Submitted 3 Sample Development KUBOTA 30 pcs. Each submitted Dt. 28-06-2012 4 Sample Development KUBOTA Sample Development KUBOTA Sample Development KUBOTA HOLD for Customer Inputs Sample Development KUBOTA 12
  • 13.
    In Lac Month Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Total Actual 2010-11 Purchasing 817 1073 1122 Value Target 57 75 79 Actual Savings 5.1 89 15.5 % 9% 118% 20% 100 90 80 70 60 50 Actual Savings 40 Target 30 20 10 0 Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar PO:
  • 14.
    Inventory Analysis (MaterialRx Vs Consumed) April to Mar 2013 May- Mar- Month Apr-12 12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 13 Total Matl Recd(in L) 817 1073 1122 3012 Matl Issued(in L) 1083 1363 1325 3771 1600 1400 1200 1000 800 600 Matl Recd(in L) 400 Matl Issued(in L) 200 0 PO:
  • 15.
    Inventory Valuation April to Mar 2013 May- Aug- Nov- Jan- Feb- Mar- Month Apr-12 Jun-12 Jul-12 Sep-12 Oct-12 Dec-12 Total 12 12 12 13 13 13 Local &Import ( 1280 1365 1356 4001 Lacs) Target 1527 1628 1845 2080 2228 2316 11624 2500 2000 1500 Local &Import ( Lacs) 1000 Target 500 0 April May June July Aug Sep Oct Nov Dec Jan Feb Mar PO:
  • 16.
    Months Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Inv Turns 10 12 12 Target 11 11 11 11 11 11 11 11 11 11 11 11 12.50 12.00 11.50 11.00 Inv Turns 10.50 Target 10.00 9.50 9.00 PO:
  • 17.
    Total Month April May June July Aug Sep Oct Nov Dec Jan Feb Mar Last year ( 11- 2.40 1.78 0.0 0.0 0.0 1.9 0.0 0.3 0.0 0.0 1.9 2.35 10.6 12) 2.37 1.98 0.6 4.95 This Year (12-13) Target Rs in Lakhs 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 48.0 4.50 4.00 3.50 3.00 2.50 Last year ( 11-12) 2.00 This Year (12-13) 1.50 Target Rs in Lakhs 1.00 0.50 0.00 April May June July Aug Sep Oct Nov Dec Jan Feb Mar PO:
  • 18.
    Description Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Base Film 49 49 49 Application 32 31 31 Film Ink 24 24 24 Grand Total 105 104 104 Target 105 102 101 98 95 93 91 88 85 81 78 75 120 100 80 60 Grand Total 40 Target 20 0 PO:
  • 19.
    10 12 14 16 0 2 4 6 8 Avg. 13.48 13.66 (11-12) 9.48 Apr-12 9.88 10.07 10.22 May-12 10.70 10.69 10.92 Jun-12 13.44 12.08 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Sales (Rs.Crs.) Actual Prod (Rs.Crs.) Budget Prod (Rs. Crs.)
  • 20.
    Target Actual 99.56 99.35 99.23 99.15 100 100 100 100 100 100 100 100 100 100 100 100 100 100 95 90 % OTD 85 80 75 70 Avg. Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-12 Feb-12 Mar-12 (11-12)
  • 21.
    New models AACA New Models & K06A AANA & AAGA Target Total Freight cost (%) on sale Premium Freight (%) on sale 0.7 0.63 0.62 0.6 0.54 0.5 0.46 0.4 0.3 0.22 0.20 0.2 0.10 0.1 0.07 0 Avg. 11- Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 12
  • 22.
    Capacity Planning forJuly’ 12 to Sept’ 12 Capacity Planning - July' 12 to Sep' 12 - Pelhar Plant Sales Budget Jul-12 Aug-12 Sep-12 (Sets) Total HMCL 389100 362625 387385 1139110 BAL 90900 90400 90400 271700 Yamaha 32700 45000 43600 121300 Suzuki 30000 31500 31500 93000 M&M 4200 4200 4500 12900 Total 546900 533725 557385 1638010 Production Budget (Sets) 601590 587098 613124 1801811 Planned Utilization (%) 78 76 86 80
  • 23.
    Dial Capacity PlanningJuly’ 12 to Sept’ 12 Capacity Planning - Jul' 12 to Sep' 12 - Pelhar Plant Sales Budget - Jul-12 Aug-12 Sep-12 Dials Total PRICOL 107850 132050 156150 396050 CONTI 39300 45300 47300 131900 TOTAL 147150 177350 203450 527950 Total Prod Budget 183938 221688 254313 659938 Capacity - Dials 452603 452603 417787 1322992 Planned % 41 49 61 50 Utilization
  • 24.
    Sales & ProductionPlan – June ’12 Sales & Production Plan -Jul 12 Actual Opening Stk Stocking Product Schedule Customer Sales Plan Norms BSR Depot Total ion Plan Value HMCL 10.000 5.000 0.000 5.560 5.560 9.560 10.120 BAL 0.800 0.400 0.007 0.290 0.297 0.800 1.210 Yamaha 0.300 0.150 0.002 0.194 0.196 0.254 0.292 Suzuki 0.200 0.100 0.020 0.008 0.028 0.272 0.017 M&M 0.050 0.025 0.025 0.000 0.025 0.050 0.051 Godrej 0.020 0.010 0.000 0.000 0.000 0.035 0.025 Pricol/Conti . 0.200 0.100 0.003 0.001 0.004 0.270 0.174 Export 1.150 0.000 0.000 0.000 0.000 1.150 0.530 Total 12.720 5.785 0.057 6.053 6.110 12.391 12.419 24
  • 25.
    60 64 66 68 70 74 76 62 72 66 73 Avg. (11-12) 65 75 Apr-12 65 75 May-12 65 75 Jun-12 75 Jul-12 75 Aug-12 Target 75 Sep-12 75 Oct-12 Average 75 Nov-12 75 Dec-12 75 Jan-13 75 Feb-13 75 Mar-13
  • 26.
    Avg. (11- Sep- Nov- Dec- Mar- Apr-12 May-12 Jun-12 Jul-12 Aug-12 Oct-12 Jan-13 Feb-13 Month 12) 12 12 12 13 Description Total Loading Time (min.) 204595 162714 184178 201729 Total Down Time (min.) 61233 58657 59206 61105 Total Down Time (%) 30.00 36.05 32.15 30.29 Reasons of Down Time 13681 20864 12757 Planned Shut Down 13638 4568 4655 3609 Screen Related 3571 30045 37828 38824 Process Related 39305 Ink Related 3474 3140 2894 3561 Maintenance Related 1180 665 913 1030 26
  • 27.
    Traget % OT Cost (Support) to Production (Production) % OT Cost % OT Cost % OT Cost (Total) 1.20 0.97 1.00 0.80 % OT 0.60 0.59 0.39 0.27 0.40 0.13 0.14 0.20 0.20 0.01 0.32 0.19 0.00 Avg. (11- Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 12) Month • New Model AAGA – Super Splendor processed on short lead time. • Increased changeovers in SPD due to Brand Migration at HMC • M/C Allocation for ITC Sampling 27
  • 28.
    Actual Target Machine April May June July Aug Sept Oct Nov Dec Jan Feb Mar (Avg) (Avg) REBOLINI -1 91 87 87 REBOLINI -2 82 82 94 BHARAT BIG -1 83 72 98 BHARAT BIG -2 89 89 81 BHARAT SMALL -1 82 78 91 BHARAT SMALL -2 76 76 70 28
  • 29.
    Rejection % 10.00% 6.00% 8.00% 0.00% 1.00% 2.00% 3.00% 4.00% 5.00% 7.00% 9.00% Avg. (11- 12) 5.96% Apr-12 May-12 6.85% 5.10% Jun-12 5.13% Jul-12 Aug-12 Sep-12 Month Oct-12 Nov-12 Dec-12 Jan-12 Feb-12 Mar-12 29
  • 30.
    10.00 9.44 9.00 8.00 8.00 8.13 7.00 7.19 6.00 5.00 Unit 1 4.00 Pelhar 3.00 Haridwar 2.00 1.00 0.00 Jul Target Aug Nov Jan Feb Dec Mar May Sep Apr Oct Jun 30
  • 31.
    DIAL Rejection trend Nov Dec Jan Feb Mar April May June July Aug Sept Oct Pricol 16 15 20.71 10.54 14.58 9.5 9.56 Continental 50 24 52.38 30.83 34.08 28 31.44 Diffuser 0 0 41.82 64.77 43.04 27.94 39.25 70 60 50 40 Pricol 30 Continental Diffuser 20 10 0 Nov Dec Jan Feb Mar April May June July Aug Sept Oct
  • 32.
    8 7 6 5 4 3 2 1 0 Apr Oct Jun Dec Mar Jul Nov A: 11-12 A: 10-11 Jan Feb May Aug Sep Pelhar Target Internal Actual Actual April May June July Aug Sept Oct Nov Dec Jan Feb Mar Target Rejection 11-12 10-11 Pelhar 4.05 3.63 3.85 4.0% 4.0 5.7
  • 33.
    13000 12000 11000 Line Rejection – BAL (2011-12) 10000 W&C 9000 8000 7000 6000 5000 4000 Target 3000 2000 1000 0 Nov Apr Aug Dec Jun Jul Feb May Actual: Oct Mar Jan Sep 11-12 Line rejection ppm from Varroc - Pantnagar TARGET ACHIEVED TARGET APRIL MAY- JUNE-12 JULY-12 AUG- SEP-12 OCT-12 NOV-12 DEC-12 JAN-13 FEB-13 MAR- 2011-12 2011-12 2012-13 12 12 12 13 3000 11909 3000 6001 11986 33
  • 34.
    Vendor Rating -Bajaj CSPL (Vendor) Rating from BAJAJ [2012-13] Standa Customer APRIL MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR rd BAL – WC < Level (100487) 2 2 3 3 BAL – < Level Haridwar 2 2 2 2 (111407) 34
  • 35.
    Line PPM feedbackfrom M&M FES Actual 2012-13 Line ppm: Actual MM FES Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar 11-12 TARGET LR PPM <250 618 258 13 ppm % GR 3 0 0 Rejection = 0 M&M FES - Line ppm [12-13] Target: 250 ppm 700 600 500 400 300 200 100 0 Actual 11-… Nov Aug Apr Jul May Dec Sep Feb Oct Mar Jun Jan 35
  • 36.
    Line PPM feedbackfrom Tafe Line ppm: Actual Actual 2012-13 Tafe 11-12 Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar TARGET <100 865 250 0 0 ppm 1000 Past trend Target Actual 900 865 800 700 600 500 400 300 250 200 100 0 36
  • 37.
    4. Summary ofComplaints Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar No. of Complaints 3 2 6 1 Nature of Complaints low Gloss 1 Complaints by Customer Varroc – Chakan 1 37
  • 38.
    5. Summary ofCorrective actions - June Sr.No Customer Complaint Description Root Cause Corrective Action 1] Work instruction amended for the method IYM- Levelling of blade on one side of die 1 Graphic Cut in 1CK2 of visual checking of deepcut, Surajpur found out to be uneven. 2] job training provided to the inspectors. Uncoated metallic particles have less Coated metallic particles to be used. Bill of IYM- Ink peel off in Yamaha cohesive force as compared to coated 2 material amended and also the process Surajpur Emblem (5KAB CRUX) metallic particles used in ink routing changes in SAP. preparation. IYM- New material was used - inadequate PPAP methodology to be followed for new 3 Air Bubbles in 1CK3 Surajpur validation material introduction Disc. 125 ST Shade Variation in deposition of metallic Bajaj - Variation found in Flame red Uniform stirring during ink issue also stirring 4 partcile on base film during printing in Waluj for batches 446052012 & prior to pouring ink on the screen. single batch. 70062012 Smoke Variation found in Setup Sheets/Dials to be crossed completely Setup sheet is not identified at printing HDT Diamler in 1 pieces in using permanent marker in printing stage stage before proceeding for further Continental- lot size of 300 of batch itself. 5 operation leading to mixing of setup Bengaluru number 2021211 at customer Illumination inspection to be done on Cluster sheets/dials with Ok sheets/dials at final assembly line at Continental, instead of light table. inspection. Bangalore on 20/06/2012. Green and white dots found Before commencing printing a pc sheet with Leakage in screen due to removal of in HDT Daimler in 59 pieces lamination and/or rough pc sheet will be emulsion coating from non image area Continental- in lot size of 300 of batch printed and checked for ink leakage and 6 leading to green and grey ink transfer Bengaluru number 2021211 at customer same will be done after every 100th and for on image area while printing 5th Colour assembly line at Continental, last sheet and leakages if any will be touched and 6th colour respectively Bangalore on 20/06/2012. up by PVA
  • 39.
    HMC-G– Quality FailureReport Plant SL Material Material Problem Analysis Action Type Reason Counter Measures No. Code Description HMC-G 1. 240512 CBZ Stripes Incomplete -Samples -Process lapse -Yet to be back cut sent to plant received 2. 5940312=0 KWAH Front Incomplete -Samples -Process and -Yet to be 9 Cowl Blk back cut(10- sent to plant inspection lapse received Blue 12%) 2470512=0 KVEG CVG -Incomplete -Samples -Process and -Yet to be 9 back cut(25- sent to plant inspection lapse received 30%) 3160612=0 KWAH Front -Incomplete -Samples -Process and -Yet to be 9 Cowl cover back cut(3-5%) sent to plant inspection lapse received BHG
  • 40.
    HMC-D – Linefeedback Customer Issue Batch No. Observation CAPA / Comments HMC-D 1.Craters observed in model 5560412 -Observed after -Yet to be received from plant splender plus AAEA lacquering process. -IPA cleaning introduced prior to -Reduces after lacquering and after that no cleaning with IPA. problem has been reported. 2.Skinning observed in stripes 2640512 -Observed in 10- -Yet to be received from plant . of model AAEA SBK 15% stripes -model AAEA P.maroon 0320120376 -obsd. In 20-25% -do- pcs. 3.Top film removal hard 3100512 -Observed in 30- -Yet to be received from plant. observed in stripes of model 40% stripes AADA BLK Sil -Splendor pro color SBK 0520120425 -observed in 30- -Yet to be received 40% stripes 4.Hole punching in stripes - -Repeated problem -Inform to all concerned with & Observed in the compiled data. materials belonging to march 12 5.Incomplete back cut at tab location in side cover color 0520120425 -Observed in 30- -Yet to be received. SBK 35% pcs.
  • 41.
    Customer Line feedback-YamahaSP Customer Issue Batch No. Observation CAPA / Comments IYM-SP 1.Ink peel off in yamaha -Ink peel off while removal -Submitted on emblem model 5KA of top application film 23.04.2012 5470412 -Problem repeated -Submitted on 26.06.2012 -Fresh batch yet to be delivered 2.Craters in stripes of model 0120120743 -Problem observed at edges -Submitted on 1CK3 in different locations after 26.06.2012 lacquering -Fresh batch after c/m yet to be received
  • 42.
    Major Highlights (Quarter-1) •April12: First Surveillance Audit inline with TS:16949/2009 conducted by Bureau Veritas. • May12: Supplier Surveillance Audit (QAV-1) conducted by Mahindra 2 Wheeler. • May12: Visit of John Deere to Pelhar Plant. • June12: Green Vendor Development Program (GVDP), certificate received by HMCL Gurgaon. • June12: Supplier Development Audit conducted by Royal Enfield.
  • 43.
    Ink Lab –Issues report for June OC Peeloff Problems Job Details Issue Root Cause Corrective Action AANA GLM CARB CB OC & Ink peel off Uncoted silver particles in CSPL 057 (CSPL 2285) New Accurate RED ABS PART & KTRM (accurate silver) Silver by Coated Stapa VK Glm. FI CB RED ABS 903/904 ECN raised part ( HMCL) KVEG CBZ EXTREME - OC & Ink peel off SG 700 Base coat Eliminate HMCL SG 700 Conc White HD White CSPL 1007 (425 OC) CSPL 2120 (8228 OC) ECN raised VK901 in CSPL 438 Pastel Gold YAHAHA Emblem OC & Ink peel off Shade Used Stapa 801 silver particles CSPL 1007 (OC 425) CSPL 1007 (OC 425) ECN raised 43
  • 44.
    Ink Lab –OC Wastage for June Wastage % Wastage PO no. Machine Description Qty. 8600 OC Average Qty.Kg OC 100068194 SPS-XP KWAH BLK H. GREY F/COWL (T-3) [4 SETS] 2000 8.8 1.781 20.20% 100068200 SPS-XP BAJAJ DISC 125ST BLK RED SEAT/FR.COWL(1S 2000 16 3.6 22.50% 100068001 SPS-XP KTPJ C.B.RED T-2 FUC 'A', BC 'A' (1SET) 2600 11.2 2.544 22.70% 100068691 SPS-XP BAJAJ DISC 125ST BLK RED SEAT/FR.COWL(1S 1860 6.4 1.384 21.50% 100068615 ATMA-6 EXPORT 1000 5.8 1.19 20.50% 100070565 ATMA-6 EXPORT 500 4.5 1 22.20% 21.65% CSPL 2120 Wastage % Wastage PO no. Machine Description Qty. Average of Nazdar Qty.Kg OC 100067055 SPS-XP AACA PASSION PRO BLK H.GREY SC (2SETS) 2272 10.5 2.44 23.20% 100068298 SPS-XP AAFA SPL.NXG BLK RED ABS PARTS(1SET) 3000 16.8 4.27 25.40% 100067415 SPS-XP AACA[PASS.PRO]BLK H.GREY ABS (1SET) 2300 11.2 3.5 31.25% 100068271 SPS-XP BAJAJ PULSAR 135 RED ABS(4SETS) 600 3.5 1.2 34.20% 100068001 SPS-XP KTPJ C.B.RED T-2 FUC 'A', BC 'A' (1SET) 1100 5.6 1 17.80% 100068604 SPS-XP KWAH BLK RED/BLUE /H.GREY R/COWL(5SETS) 2500 14.4 3.4 23.60% 26% 44
  • 45.
    Machine Total Downtime Avg. Downtime Avg. MTBF Avg. MTTR (mins.) per day (mins.) (mins.) (mins.) Sakurai-01 465 18.6 21367.65 465 Sakurai-02 115 4.6 7408 38 SPS-01 205 8.2 8599 51.25 SPS-02 60 2.4 21570 60 SPS-03 0 0 43200 0 SPS-04 30 1.2 14390 15 SPS-XP 320 12.8 8576 80 Others 430 35.33 2177.62 57.63 TOTAL (JUN’ 12) 1700 68.00 1507.73 95.86 TOTAL (MAY’ 12) 1960 40.80 1579.80 42.70 TOTAL (APR’ 12) 982 40.80 1579.80 42.70 TOTAL (Mar’ 12) 2429 83.29 879.40 51.68 MTBF – Mean Time Between Failures; MTTR – Mean Time To Repair Downtime for Rolt is not considered as there are some manufacturing defects which lead to downtimes. 45
  • 46.
    3500 Downtime 2011-12 Monthly 3147 Downtime Limit Downtime 2012-13 3000 is 2000 mins. 2580 2582 2448 2429 2500 2201 2148 1957 2000 1735 1653 1517 1506 1500 1000 500 0 May July Mar Dec June Jan Feb Oct Nov Sept April Aug 46
  • 47.
    CYLINDER PRESS DOWNTIMEFOR LAST 12 MONTHS (mins) Machine/ SPS-01 SPS-02 SPS-03 SPS-04 SPS-XP SK-01 SK-02 Month June12 205 60 0 30 320 465 115 May12 0 245 0 200 0 20 130 Apr’12 40 65 0 0 40 0 110 Mar’12 75 70 00 113 223 345 15 Feb.’12 144 155 128 337 200 200 30 Jan’12 202 375 86 147 182 87 30 Dec’11 130 192 30 405 90 0 0 Nov’11 0 175 285 145 270 20 110 Oct’11 5 428 20 198 80 5 220 Sept’11 115 0 165 40 105 0 25 Aug’11 110 119 30 125 30 0 75 July’11 240 145 0 105 410 70 240 TOTAL 1266 2029 759 1845 1950 1212 1100 Average 105.5 169.08 63.25 153.75 162.5 101 91.66
  • 48.
    Electricity Units 2010- 800000 11 Sudden increase is due to increased HVAC load 700000 and machine load. 589080 600000 560790 566430 564000 555180 547590 551910559709 527070 521501 504090 513840 506576 493710 496020 492535 500000 475710 492390 488250 435450 430266 425790 437071 400000 300000 200000 100000 0 May July Mar June Dec Jan Feb Oct Nov Sept April Aug 48
  • 49.
    MAINT. BREAKDOWNS &PREVENTIVE ACTIONS Breakdown Down Machine Corrective Action Preventive Action Reason Time SPS XP Machine 320 Damaged Cable PLC’s input ,output function wasnot running mins. replaced with the ‘Check Point’ will be due to faulty New Cable. checked in ‘Preventive cable of PLC Maintenance’. input Contacts.. SK-1 Shear Key of 465 Shearkey replaced Shear Key Check Point the Gear-box mins. with new Shearkey. included in the ‘Preventive was broken. Maintenance’. SK-2 Timer Belt 165 Timer Belt replaced Timer Belt will be replaced damged of the mins. with new one. once in a year. Vaccum Pump.
  • 50.
    500 Sales (Rs.) per Electrical Unit 2011-12 450 Sales (Rs.) per Electrical Unit 2012-13 400 Monthly Target for Sales (Rs.) per Elec. 350 Unit is Rs. 300. 300 250 200 150 100 50 0 May July Mar Oct June Nov Dec Jan Feb Sept April Aug 50
  • 51.
    800000 Electricity Units 2011-12 Sudden increase is due 700000 Electricity Units 2012-13 to increased HVAC load and machine load. 600000 500000 400000 300000 200000 100000 0 May July Mar Jan Dec June Oct Nov Feb Sept April Aug 51
  • 52.
    9000 Units consumed by DG 8200 Sets 2011-12 8000 7657 Units consumed by DG Sets 2012-13 7000 6000 5412 5370 5000 4238 4000 3797 3000 2576 2378 1836 2000 1275 998 1000 555 501 337 0 0 11 2 4 1 3 5 6 7 8 9 10 12 52
  • 53.
    As on Ason Sr. No Description March March April May June July Aug Sept Oct Nov Dec Jan Feb Mar 2011 2012 1 No. Of Staff 87 106 100 99 94 No. Of Company 2 94 118 119 117 117 Workmen No. of Contract 3 Workmen 423 432 381 405 398 Total Manpower 604 656 600 621 609
  • 54.
    Figures in Mn.Rs Description April May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Total Production. 98.8 107.0 106.9 Salary & Wages to % of Production. 7.33% 8.59% 7.74% Mn. Rs. Contract Wage Bill 3.16% 3.11% 3.03% % to sales On Roll Overtime Cost to % of 0.06% 0.15% 0.12% Production Contract Overtime Cost to % of 0.07% 0.44% 0.34% Production. 54
  • 55.
    Description April May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Total ELECTRICITY/POWE R EXPENSE - 2.81 2.88 2.85 3.96 5.44 5.29 5.40 5.90 6.17 5.99 5.60 5.76 58.06 MANUF ACTUAL EXPENSES 4.25 2.91 FUEL EXPENSES - - 0.08 0.08 0.08 - MANUFACTURING - 0.08 - 0.08 0.08 - 0.08 0.56 ACTUAL EXPENSES - 0.12 REPAIRS & MAINT- 2.50 2.50 2.50 2.00 2.00 2.00 2.00 1.20 2.00 1.50 1.20 1.20 22.60 MACHINERY ACTUAL EXPENSES 2.45 0.71 55
  • 56.
    Description April May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Total CONSUMABLE SUPPLIES 0.92 0.93 1.05 1.43 1.73 1.76 1.91 1.98 2.16 2.20 2.45 2.69 21.20 ACTUAL EXPENSES 1.11 0.49 DIE PURCHASES & DEVELOPMENT 0.28 0.28 0.32 0.43 0.52 0.53 0.57 0.59 0.65 0.66 0.73 0.81 6.36 ACTUAL EXPENSES - 0.31 POSITIVE & NEGATIVE 0.07 0.07 0.08 0.11 0.14 0.14 0.15 0.16 0.17 0.18 0.20 0.22 1.70 DEV.CHARGS ACTUAL EXPENSES 0.02 - PRODUCT DEVELOPMENT 0.18 0.19 0.21 0.29 0.35 0.35 0.38 0.40 0.43 0.44 0.49 0.54 4.24 CHGS ACTUAL EXPENSES 0.21 0.06 56
  • 57.
    Description April May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Ma-12r Total SCREEN MAKING EXPENSES 1.01 1.02 1.16 1.57 1.90 1.93 2.10 2.17 2.38 2.42 2.69 2.96 23.32 ACTUAL EXPENSES 0.90 2.20 LABOUR CHARGES 4.46 4.46 4.48 4.83 5.35 5.99 6.02 6.50 6.85 6.77 6.99 7.04 69.73 ACTUAL EXPENSES 4.36 5.06 TRANSPORT CHARGES BY ROAD- 0.17 0.18 0.20 0.27 0.33 0.33 0.36 0.38 0.41 0.42 0.47 0.51 4.03 OUTWARD ACUTAL EXPENSES 0.03 0.11 TRANSPORT CHARGES OTHERS- 0.55 0.56 0.63 0.86 1.04 1.06 1.15 1.19 1.30 1.32 1.47 1.61 12.72 OUTWARDS ACTUAL EXPENSES 0.46 0.54 57
  • 58.
    Description April May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Total REPAIRS & MAINT- 0.18 0.18 0.18 0.18 0.18 0.18 0.53 0.53 0.53 0.53 0.53 0.53 4.20 BUILDING ACTUAL EXPENSES - MOTOR CAR / CYCLE FUEL 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 2.40 EXPENSES ACTUAL EXPENSES 0.12 SECURITY CHARGES 0.33 0.33 0.33 0.33 0.33 0.33 0.33 0.33 0.33 0.33 0.33 0.33 3.90 ACTUAL EXPENSES 0.24 GARDENING EXP 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.60 ACTUAL EXPENSES - HOUSE KEEPING EXPENSES 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 4.20 ACTUAL EXPENSES 0.33 58