MV Generator
earthing in large
cable networks
Jason Mayer
Aurecon Australasia
EESS November 2019
2
๏‚ง Private commercial and industrial medium voltage
networks commonly employ centralised, direct
connected medium voltage standby diesel
generators
Topic background
3
๏‚ง Can supply standby power to an entire MV network
using the existing network infrastructure
๏‚ง Using a MV generator eliminates step up transformer
๏‚ง No transformer oil containment issues to deal with
๏‚ง Eliminates large LV cables
๏‚ง More compact
๏‚ง Typically less expensive โ€“ maybe
๏‚ง Less maintenance than multiple de-centralised LV
generator systems
Why direct connected?
4
๏‚ง Neutral earthing is not trivial for direct connected
MV generators
โ€’ These generators need to be earthed when operating in
islanded mode to provide a system reference
โ€’ Conversely they should be unearthed when paralleled
with the grid to prevent interference with utility earth fault
protection
Generator neutral earthing
Utility
Transformer Generator
Customer
Network
Utility
Network
other
feeders
5
๏‚ง Typically generator X0 is lower than Xโ€d so you
need some sort of earthing impedance to limit
generator earth fault current to no more than three
phase fault current โ€“ (winding bracing strength)
๏‚ง Earth fault current limitation may also be required
for step/touch voltage safety reasons
๏‚ง Typically done with a neutral earthing resistor
Generator neutral earthing
6
๏‚ง Neutral earthing reactor could be used but certain
rules must be followed
โ€’ Earth fault current must be at least 25% (preferably 60%)
of three phase fault current to avoid serious transient
overvoltage issues
โ€’ X0 โ‰ค 10X1
Generator neutral earthing
7
Typical generator impedances
8
Typical MV network โ€“ normal operation
๏‚ง Intake substation
๏‚ง 11 kV feeders
๏‚ง Distribution transformers with
400/230V loads
๏‚ง Standby diesel generators normally
off-line
9
Typical network โ€“ loss of grid
๏‚ง Grid incoming feeders tripped
๏‚ง Diesel generators on-line
๏‚ง 11 kV system earth provided by
earthing one generator (typically
via neutral earthing resistor)
10
Simplified arrangement
๏‚ง Generator
supplying MV
distribution network
in islanded mode
Site MV cabling and
substations
Generator
NER
MV Switchgear
11
๏‚ง Generators do not produce pure
sinusoidal waveforms
๏‚ง Two common generator types
โ€’ 5/6 winding pitch
โ€’ 2/3 winding pitch
๏‚ง Both generate voltage harmonics
on their output waveform
๏‚ง 5/6 generates lower 5th and 7th but
medium 3rd
๏‚ง 2/3 generates no 3rd but 5th and 7th
Generator harmonics
5/6
2/3
12
Which choice?
๏‚ง 2/3rd Pitch
โ€’ Non-existent 3rd
harmonic
โ€’ Higher cost
โ€’ Larger machine
โ€’ Low Z0 (higher earth fault current)
๏‚ง 5/6th Pitch
โ€’ Increased power density
โ€’ Lower cost
โ€’ Lower weight
โ€’ Higher efficiency
โ€’ Lower 5th and 7th harmonic
โ€’ Higher 3rd harmonic
โ€’ Higher Z0 (lower earth fault current)
13
Testing conducted โ€“ harmonic voltages
0.00%
2.00%
4.00%
6.00%
8.00%
10.00%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Harmonic Voltages on grid supply
Harmonic Voltage (% of fundamental)
0.00%
2.00%
4.00%
6.00%
8.00%
10.00%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Harmonic voltages on generator
Harmonic Voltage (% of fundamental)
๏‚ง High levels of 3rd harmonic from 5/6th wound
generators
14
Circulating currents in the generator neutralโ€ฆ.
๏‚ง In some cases you can see significant circulating
current in the generator NER
โ€’ You need triplen harmonic voltage source โ€“ only 3rd and
multiples of 3rd can circulate in the neutral
โ€’ Need a zero sequence path from the network back to
the generator neutral
15
How can this happen?
๏‚ง NER circulating current
โ€’ has to be zero sequence/triplen current
โ€’ need a triplen harmonic voltage source
๏‚ง Generators
โ€’ direct connected at MV
โ€’ 5/6th winding pitch produces triplen harmonics
๏‚ง MV cable
โ€’ if you have long lengths of it you have a capacitive
path to earth
16
๏‚ง There is a relatively medium
capacitance from conductor to screen in
underground cable
๏‚ง The screens are connected to the site
earthing system which connects to the
NER earth point
๏‚ง Lots of cable gives quite low zero
sequence impedance to earth - Xc0
Where is our zero sequence path?
17
Our harmonic current circuit
3rd
Harmonic
Sources
RgjXc
jXc
jXc
-jXc
jXg(Xo)
3xRg
Io
V3
10% of
Vph-e
โˆ’๐‘—๐‘‹๐‘ =
1
2๐œ‹๐‘“๐ถ
18
Worked example
Parameter Value
Generator Rating 11 kV 2.87 MVA
Generator Winding 5/6th pitch (therefore 10% 3rd harmonic at full load)
Generator X0 9.1% on 2.87 MVA
Cable Size and Length 11 kV 240sqmm XLPE, 30 km, 0.458 uF/km
NER 31 ohms
19
Worked example
-jXc
jXg(Xo)
3xRg
Io
V3
10% or
635V
20
Worked example
๐‘‹0 =
9.1
100
ร—
112
2.87
= 3.84๐‘– ๐‘œโ„Ž๐‘š๐‘  ๐‘Ž๐‘ก 50 ๐ป๐‘
๐‘‹0 = 3.84๐‘– ร— 3 = 11.5๐‘– ๐‘œโ„Ž๐‘š๐‘  ๐‘Ž๐‘ก 150 ๐ป๐‘
๐‘… ๐‘”0 = 31 ร— 3 = 93 ๐‘œโ„Ž๐‘š๐‘ 
๐‘‹๐‘0 =
1
2 ร— ๐œ‹ ร— 150 ร— 0.458 ร— 10โˆ’6 ร— 30
= โˆ’77.2๐‘– ๐‘œโ„Ž๐‘š๐‘ 
๐ผ0 =
10% ร— 6350
93 + 11.5๐‘– โˆ’ 77.2๐‘–
= 5.57/35.2ยฐ ๐‘Ž๐‘š๐‘๐‘ 
๐ผ ๐‘Ž = 3 ร— ๐ผ0 = 16.7 ๐‘Ž๐‘š๐‘๐‘ 
๐‘ƒ๐‘œ๐‘ค๐‘’๐‘Ÿ ๐‘๐ธ๐‘… = ๐ผ2
ร— ๐‘… = 16.72
ร— 31 = 8.6 ๐‘˜๐‘Š
21
On-site validation testing
๏‚ง Aurecon and Safearth confident of the issue
๏‚ง Safearth engaged to perform validation testing
of theory
๏‚ง Using proprietary broad frequency current
injection equipment and calibrated meters
testing was carried out
22
๏‚ง Off power frequency
and off harmonic
frequency testing
performed
๏‚ง Meters and source
needed to be
reprogrammed to
frequency in the range
of 150Hz
23
๏‚ง Measured capacitive
impedance
correlated well with
modelled estimates
๏‚ง The harmonic
circulating current of
approximately 18A
was validated
24
Where can this go wrong?
๏‚ง Generator suppliers tend to recommend 5/6th
winding pitch generators (although there is evidence some of
them are changing)
๏‚ง However they donโ€™t often understand the context
of the site where they were being installed
๏‚ง The site designer needs to be the one fitting all
the pieces of the design together and checking
this
๏‚ง NERs typically donโ€™t have a continuous rating
25
๏‚ง Circulating current in generator NERs during
islanded operation of the network
๏‚ง Heating, smoke and paint damage
Getting it wrong
26
So what is the correct solution?
๏‚ง Use NERs with type tested continuous current
rating and install them outside
๏‚ง Use earthing transformers and leave generator
neutrals floating
๏‚ง Using LV generators with step up transformers
๏‚ง Use 2/3rd pitch machines
๏‚ง Third harmonic filters
๏‚ง Use NEXs instead of NERs (less I2R heating??)
27
Option selection
Option Technical discussion
Type tested NER Doesnโ€™t eliminate circulating current but deals with
heat more effectively
Earthing transformer Excellent electrical solution but more civil works and
electrical works
Replace alternators Could increase 5th and 7th harmonics, larger machines
in generator hall โ€“ need to do some checks
LV generators with step up
transformers
Isolates zero sequence networks. Excellent solution
but more civil and electrical works
Harmonic Filters Not sure a technical solution can be found if there are
a number of switching configurations
Use NEX Due to flexible switching arrangements could cause
resonance issues
28
Type tested NER solution
29
Type tested NER solution
30
Earthing transformer solution
31
Step-up transformer solution
11 kV
32
NEX solution โ€“ not recommended
33
Issues with the NEX option - example
-jXc
jXg(Xo)
3jXg
Io
V3
10% or
635V
34
Lessons for large cable networks with generators
๏‚ง Consider the winding pitch carefully
๏‚ง Consider your earth fault limitation and the device best
suited to achieve that (typically NER)
๏‚ง Make sure you talk to the utility about paralleling
๏‚ง Could use LV generators with Dyn or YNd step up
transformers to isolate zero sequence networks between
generators and the cable network
๏‚ง Could use MV direct connected generators but with
earthing transformers on the MV busbar and un-earthed
generator neutrals
๏‚ง Calculate the circulating current and incorporate into
earthing device design and type test it
Follow us on
www.twitter.com/Aurecon
Join us on
www.facebook.com/Aurecon
Watch us on
www.youtube.com/user/AureconGroup
Follow us on
www.instagram.com/Aurecon
Follow us on
www.linkedin.com/company/Aurecon
Follow us on
www.slideshare.net/Aurecon
Questions?

Earthing of medium voltage generators in large cable networks

  • 1.
    MV Generator earthing inlarge cable networks Jason Mayer Aurecon Australasia EESS November 2019
  • 2.
    2 ๏‚ง Private commercialand industrial medium voltage networks commonly employ centralised, direct connected medium voltage standby diesel generators Topic background
  • 3.
    3 ๏‚ง Can supplystandby power to an entire MV network using the existing network infrastructure ๏‚ง Using a MV generator eliminates step up transformer ๏‚ง No transformer oil containment issues to deal with ๏‚ง Eliminates large LV cables ๏‚ง More compact ๏‚ง Typically less expensive โ€“ maybe ๏‚ง Less maintenance than multiple de-centralised LV generator systems Why direct connected?
  • 4.
    4 ๏‚ง Neutral earthingis not trivial for direct connected MV generators โ€’ These generators need to be earthed when operating in islanded mode to provide a system reference โ€’ Conversely they should be unearthed when paralleled with the grid to prevent interference with utility earth fault protection Generator neutral earthing Utility Transformer Generator Customer Network Utility Network other feeders
  • 5.
    5 ๏‚ง Typically generatorX0 is lower than Xโ€d so you need some sort of earthing impedance to limit generator earth fault current to no more than three phase fault current โ€“ (winding bracing strength) ๏‚ง Earth fault current limitation may also be required for step/touch voltage safety reasons ๏‚ง Typically done with a neutral earthing resistor Generator neutral earthing
  • 6.
    6 ๏‚ง Neutral earthingreactor could be used but certain rules must be followed โ€’ Earth fault current must be at least 25% (preferably 60%) of three phase fault current to avoid serious transient overvoltage issues โ€’ X0 โ‰ค 10X1 Generator neutral earthing
  • 7.
  • 8.
    8 Typical MV networkโ€“ normal operation ๏‚ง Intake substation ๏‚ง 11 kV feeders ๏‚ง Distribution transformers with 400/230V loads ๏‚ง Standby diesel generators normally off-line
  • 9.
    9 Typical network โ€“loss of grid ๏‚ง Grid incoming feeders tripped ๏‚ง Diesel generators on-line ๏‚ง 11 kV system earth provided by earthing one generator (typically via neutral earthing resistor)
  • 10.
    10 Simplified arrangement ๏‚ง Generator supplyingMV distribution network in islanded mode Site MV cabling and substations Generator NER MV Switchgear
  • 11.
    11 ๏‚ง Generators donot produce pure sinusoidal waveforms ๏‚ง Two common generator types โ€’ 5/6 winding pitch โ€’ 2/3 winding pitch ๏‚ง Both generate voltage harmonics on their output waveform ๏‚ง 5/6 generates lower 5th and 7th but medium 3rd ๏‚ง 2/3 generates no 3rd but 5th and 7th Generator harmonics 5/6 2/3
  • 12.
    12 Which choice? ๏‚ง 2/3rdPitch โ€’ Non-existent 3rd harmonic โ€’ Higher cost โ€’ Larger machine โ€’ Low Z0 (higher earth fault current) ๏‚ง 5/6th Pitch โ€’ Increased power density โ€’ Lower cost โ€’ Lower weight โ€’ Higher efficiency โ€’ Lower 5th and 7th harmonic โ€’ Higher 3rd harmonic โ€’ Higher Z0 (lower earth fault current)
  • 13.
    13 Testing conducted โ€“harmonic voltages 0.00% 2.00% 4.00% 6.00% 8.00% 10.00% 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Harmonic Voltages on grid supply Harmonic Voltage (% of fundamental) 0.00% 2.00% 4.00% 6.00% 8.00% 10.00% 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Harmonic voltages on generator Harmonic Voltage (% of fundamental) ๏‚ง High levels of 3rd harmonic from 5/6th wound generators
  • 14.
    14 Circulating currents inthe generator neutralโ€ฆ. ๏‚ง In some cases you can see significant circulating current in the generator NER โ€’ You need triplen harmonic voltage source โ€“ only 3rd and multiples of 3rd can circulate in the neutral โ€’ Need a zero sequence path from the network back to the generator neutral
  • 15.
    15 How can thishappen? ๏‚ง NER circulating current โ€’ has to be zero sequence/triplen current โ€’ need a triplen harmonic voltage source ๏‚ง Generators โ€’ direct connected at MV โ€’ 5/6th winding pitch produces triplen harmonics ๏‚ง MV cable โ€’ if you have long lengths of it you have a capacitive path to earth
  • 16.
    16 ๏‚ง There isa relatively medium capacitance from conductor to screen in underground cable ๏‚ง The screens are connected to the site earthing system which connects to the NER earth point ๏‚ง Lots of cable gives quite low zero sequence impedance to earth - Xc0 Where is our zero sequence path?
  • 17.
    17 Our harmonic currentcircuit 3rd Harmonic Sources RgjXc jXc jXc -jXc jXg(Xo) 3xRg Io V3 10% of Vph-e โˆ’๐‘—๐‘‹๐‘ = 1 2๐œ‹๐‘“๐ถ
  • 18.
    18 Worked example Parameter Value GeneratorRating 11 kV 2.87 MVA Generator Winding 5/6th pitch (therefore 10% 3rd harmonic at full load) Generator X0 9.1% on 2.87 MVA Cable Size and Length 11 kV 240sqmm XLPE, 30 km, 0.458 uF/km NER 31 ohms
  • 19.
  • 20.
    20 Worked example ๐‘‹0 = 9.1 100 ร— 112 2.87 =3.84๐‘– ๐‘œโ„Ž๐‘š๐‘  ๐‘Ž๐‘ก 50 ๐ป๐‘ ๐‘‹0 = 3.84๐‘– ร— 3 = 11.5๐‘– ๐‘œโ„Ž๐‘š๐‘  ๐‘Ž๐‘ก 150 ๐ป๐‘ ๐‘… ๐‘”0 = 31 ร— 3 = 93 ๐‘œโ„Ž๐‘š๐‘  ๐‘‹๐‘0 = 1 2 ร— ๐œ‹ ร— 150 ร— 0.458 ร— 10โˆ’6 ร— 30 = โˆ’77.2๐‘– ๐‘œโ„Ž๐‘š๐‘  ๐ผ0 = 10% ร— 6350 93 + 11.5๐‘– โˆ’ 77.2๐‘– = 5.57/35.2ยฐ ๐‘Ž๐‘š๐‘๐‘  ๐ผ ๐‘Ž = 3 ร— ๐ผ0 = 16.7 ๐‘Ž๐‘š๐‘๐‘  ๐‘ƒ๐‘œ๐‘ค๐‘’๐‘Ÿ ๐‘๐ธ๐‘… = ๐ผ2 ร— ๐‘… = 16.72 ร— 31 = 8.6 ๐‘˜๐‘Š
  • 21.
    21 On-site validation testing ๏‚งAurecon and Safearth confident of the issue ๏‚ง Safearth engaged to perform validation testing of theory ๏‚ง Using proprietary broad frequency current injection equipment and calibrated meters testing was carried out
  • 22.
    22 ๏‚ง Off powerfrequency and off harmonic frequency testing performed ๏‚ง Meters and source needed to be reprogrammed to frequency in the range of 150Hz
  • 23.
    23 ๏‚ง Measured capacitive impedance correlatedwell with modelled estimates ๏‚ง The harmonic circulating current of approximately 18A was validated
  • 24.
    24 Where can thisgo wrong? ๏‚ง Generator suppliers tend to recommend 5/6th winding pitch generators (although there is evidence some of them are changing) ๏‚ง However they donโ€™t often understand the context of the site where they were being installed ๏‚ง The site designer needs to be the one fitting all the pieces of the design together and checking this ๏‚ง NERs typically donโ€™t have a continuous rating
  • 25.
    25 ๏‚ง Circulating currentin generator NERs during islanded operation of the network ๏‚ง Heating, smoke and paint damage Getting it wrong
  • 26.
    26 So what isthe correct solution? ๏‚ง Use NERs with type tested continuous current rating and install them outside ๏‚ง Use earthing transformers and leave generator neutrals floating ๏‚ง Using LV generators with step up transformers ๏‚ง Use 2/3rd pitch machines ๏‚ง Third harmonic filters ๏‚ง Use NEXs instead of NERs (less I2R heating??)
  • 27.
    27 Option selection Option Technicaldiscussion Type tested NER Doesnโ€™t eliminate circulating current but deals with heat more effectively Earthing transformer Excellent electrical solution but more civil works and electrical works Replace alternators Could increase 5th and 7th harmonics, larger machines in generator hall โ€“ need to do some checks LV generators with step up transformers Isolates zero sequence networks. Excellent solution but more civil and electrical works Harmonic Filters Not sure a technical solution can be found if there are a number of switching configurations Use NEX Due to flexible switching arrangements could cause resonance issues
  • 28.
  • 29.
  • 30.
  • 31.
  • 32.
    32 NEX solution โ€“not recommended
  • 33.
    33 Issues with theNEX option - example -jXc jXg(Xo) 3jXg Io V3 10% or 635V
  • 34.
    34 Lessons for largecable networks with generators ๏‚ง Consider the winding pitch carefully ๏‚ง Consider your earth fault limitation and the device best suited to achieve that (typically NER) ๏‚ง Make sure you talk to the utility about paralleling ๏‚ง Could use LV generators with Dyn or YNd step up transformers to isolate zero sequence networks between generators and the cable network ๏‚ง Could use MV direct connected generators but with earthing transformers on the MV busbar and un-earthed generator neutrals ๏‚ง Calculate the circulating current and incorporate into earthing device design and type test it
  • 35.
    Follow us on www.twitter.com/Aurecon Joinus on www.facebook.com/Aurecon Watch us on www.youtube.com/user/AureconGroup Follow us on www.instagram.com/Aurecon Follow us on www.linkedin.com/company/Aurecon Follow us on www.slideshare.net/Aurecon Questions?

Editor's Notes

  • #3ย What do I mean by direct connected โ€“ I mean medium voltage generator connected straight to the medium voltage network without transformers in between. In the past scattered LV generators but more and more CEPโ€™s
  • #4ย Donโ€™t need multiple LV machines at each building, you can create a central energy plant of sorts. For larger machine sizes, LV cables become cumbersome. MV generator is more expensive than LV and depending on project or site, the MV option may or may not be less expensive overall depending on what other equipment you need to buy. Certainly need a transformer and some LV switchgear. If you have to build a giant CEP building then maybe not.
  • #5ย This will be part of any connection agreement. See what happens when an earth fault occurs you will get zero sequence current contribution from both the transformer and the generator and it could cause grading issues or increased fault levels. Without an earth reference in islanded mode you will not be able to detect MV earth faults.
  • #6ย Windings are braced for 3 phase fault current and no higher. Lower Xo means earth fault will be higher than 3 phase fault for a typical generator.
  • #9ย Lets talk a bit about a typical site distribution network. This is a simplified diagram.
  • #10ย During a grid failure the generators are on line and the grid feeders are tripped. So you lose your network earth reference which is at the network utility zone substation transformer upstream. The generators each typically have a NER with contactor. One of them is switched into service so that one machine provides the system earth reference. In this case the resistor provides earth fault current limitation which limits earth potential rise and prevents generator winding damage during unbalanced faults. Annual duty cycle might only be 12 hours per year but depends on outages.
  • #11ย For analysis just consider the standby arrangement via a single generator
  • #12ย There are others but these two are common choices. But here we have a possible source of 3rd harmonic and triplen harmonics voltage directly at MV. This is all to do with how the manufacturer lays the overlaps the windings in the stator slots.
  • #13ย Z0 influences earth fault levels 5th and 7th are normally more concerning at MV. 3rd harmonic is not normally a worry. So here is a source of 3rd harmonic on the MV networkโ€ฆ..
  • #14ย Actual case study example Point out normal 3, 5, 7 Point out 5, 7 goes up on generation due to lower fault levels Point out 3, 9
  • #15ย What conditions do you need to set up circulating currents in the generator neutral to earth connection
  • #16ย NER current on generator supply โ€“ so that has to be a zero sequence current (3 or multiple) Direct connected generators with no step up transformers, directly earthed through NER Lots of cable it is a very large site. Typical residential and commercial loads so there are 3rd harmonics in the load current (but that is kind of irrelevent). Captured by the delta winding of the Dyn transformers. Letโ€™s look one by one.
  • #17ย An earth fault will generally propagate into a solid fault and trip the protection. Cable capacitance is the hidden factor that many people do not give consideration to. If you have lots of cable at the same voltage as the generator then you have a zero sequence path back to the generator neutral.
  • #18ย Use 2pifL and 1/2pifC formulae to explain what is happening. Lots of C means low โ€“jWc, particularly at 3rd and triplen harmonics.
  • #20ย Of course there are other impedances such as cable zero sequence impedance but it is small so we can ignore that for the moment.
  • #22ย Methodology: - Event Tree - Root Cause Analysis Methodology probably less important than the findings.
  • #25ย All of this combined in a perfect storm that resulted in excessive 3rd harmonic circulating current in the NER
  • #26ย The current can cause heat and smoke or NER open circuit failure and loss of your earth reference in extreme cases. NERโ€™s only normally have a short time rating not a continuous current rating, so the ultimate temperature can be exceeded if an earth fault occurs after pre-heating. The enclosures are not designed to expel continuous heat.
  • #27ย Discuss options
  • #28ย NEX seems like a good idea because heat = I2Rโ€ฆ..NEX has very low R. However if you read the paper you will see that selecting the right NEX impedance is very tricky because you need enough earth fault current to avoid transient overvoltages if you limit current too much. However there is a chance of resonance of the NEX with the cable capacitance.
  • #29ย Significantly larger cubicle with large ventilation openings. Type tested to 20A continuous current followed by 200A 10 second fault limiting to 760K absolute temperature rise. Show vent openings
  • #30ย Large vents, more space to the walls, mediumer roof to allow hot air to pool.
  • #34ย Can get a resonant circuit which causes huge circulating currents if just the right amount of cabling is switched onto the generator switchboard. This is certainly possible if they only supply half the site on generators (remember there are two intake substations)
  • #35ย Last one is not the best option in my opinion but we did it because we were dealing with an already constructed site with large thick concrete paving all around so civil works to modify were expensive.