SlideShare a Scribd company logo
1 of 3
Background: Some executives prefer to micromanage projects
whereas other executives are fearful of making a decision
because, if they were to make the wrong decision, it could
impact their career. In this case study, the president of the
company assigned one of the vice presidents to act as the
project sponsor on a project designed to build tooling for a
client. The sponsor, however, was reluctant to make any
decisions.
Assigning the VP: Moreland Company was well-respected as a
tooling design-and-build company. Moreland was project-driven
because all of its income came from projects. Moreland was
also reasonably mature in project management. When the
previous VP for engineering retired, Moreland hired an
executive from a manufacturing company to replace him. The
new VP for engineering, Al Zink, had excellent engineering
knowledge about tooling but had worked for companies that
were not project-driven. Al had very little knowledge about
project management and had never functioned as a project
sponsor. Because of Al’s lack of experience as a sponsor, the
president decided that Al should “get his feet wet” as quickly as
possible and assigned him as the project sponsor on a
mediumsized project. The project manager on this project was
Fred Cutler. Fred was an engineer with more than twenty years
of experience in tooling design and manufacturing. Fred
reported directly to Al Zink administratively.
Fred's Dilemma: Fred understood the situation; he would have
to train Al Zink on how to function as a project sponsor. This
was a new experience for Fred because subordinates usually do
not train senior personnel on how to do their job. Would Al
Zink be receptive? Fred explained the role of the sponsor and
how there are certain project documents that require the
signatures of both the project manager and the project sponsor.
Everything seemed to be going well until Fred informed Al that
the project sponsor is the person that the president eventually
holds accountable for the success or failure of the project. Fred
could tell that Al was quite upset over this statement. Al
realized that the failure of a project where he was the sponsor
could damage his reputation and career. Al was now
uncomfortable about having to act as a sponsor but knew that he
might eventually be assigned as a sponsor on other projects. Al
also knew that this project was somewhat of a high risk. If Al
could function as an invisible sponsor, he could avoid making
any critical decisions. In the first meeting between Fred and Al
where Al was the sponsor, Al asked Fred for a copy of the
schedule for the project. Fred responded: I’m working on the
schedule right now. I cannot finish the schedule until you tell
me whether you want me to lay out the schedule based upon
best time, least cost, or least risk. Al stated that he would think
about it and get back to Fred as soon as possible. During the
middle of the next week, Fred and Al met in the company’s
cafeteria. Al asked Fred again, “How is the schedule coming
along?” and Fred responded as before: I cannot finish the
schedule until you tell me whether you want me to lay out the
schedule based upon best time, least cost, or least risk. Al was
furious, turned around, and walked away from Fred. Fred was
now getting nervous about how upset Al was and began
worrying if Al might remove him as the project manager. But
Fred decided to hold his ground and get Al to make a decision.
At the weekly sponsor meeting between Fred and Al, once again
Al asked the same question, and once again Fred gave the same
response as before. Al now became quite angry and yelled out:
Just give me a least time schedule. Fred had gotten Al to make
his first decision. Fred finalized his schedule and had it on Al’s
desk two days later awaiting Al’s signature. Once again, Al
procrastinated and refused to sign off on the schedule. Al
believed that, if he delayed making the decision, Fred would
take the initiative and begin working on the schedule without
Al’s signature. Fred kept sending e-mails to Al asking when he
intended to sign off on the schedule or, if something was not
correct, what changes needed to be made. As expected, Al did
not respond. Fred then decided that he had to pressure Al one
way or another into making timely decisions as the project
sponsor. Fred then sent an e-mail to Al that stated: I sent you
the project schedule last week. If the schedule is not signed by
this Friday, there could be an impact on the end date of the
project. If I do not hear from you, one way or another, by this
Friday, I will assume you approve the schedule and I can begin
implementation. The president’s e-mail address was also
included in the CC location on the e-mail. The next morning,
Fred found the schedule on his desk, signed by Al Zink.

More Related Content

More from kacie8xcheco

PronombresFill in the blanks with the correct words.Raúl y Val.docx
PronombresFill in the blanks with the correct words.Raúl y Val.docxPronombresFill in the blanks with the correct words.Raúl y Val.docx
PronombresFill in the blanks with the correct words.Raúl y Val.docxkacie8xcheco
 
Propose at least three techniques in which the color blind perspecti.docx
Propose at least three techniques in which the color blind perspecti.docxPropose at least three techniques in which the color blind perspecti.docx
Propose at least three techniques in which the color blind perspecti.docxkacie8xcheco
 
Provide a 150 word response to the below discussion question answer .docx
Provide a 150 word response to the below discussion question answer .docxProvide a 150 word response to the below discussion question answer .docx
Provide a 150 word response to the below discussion question answer .docxkacie8xcheco
 
Prompt Submit a draft of your implementation section. You will gi.docx
Prompt Submit a draft of your implementation section. You will gi.docxPrompt Submit a draft of your implementation section. You will gi.docx
Prompt Submit a draft of your implementation section. You will gi.docxkacie8xcheco
 
PROMPT Think about how 5 of the population of the South managed to.docx
PROMPT Think about how 5 of the population of the South managed to.docxPROMPT Think about how 5 of the population of the South managed to.docx
PROMPT Think about how 5 of the population of the South managed to.docxkacie8xcheco
 
Properties of LifeChapter 1 of the text highlights the nine proper.docx
Properties of LifeChapter 1 of the text highlights the nine proper.docxProperties of LifeChapter 1 of the text highlights the nine proper.docx
Properties of LifeChapter 1 of the text highlights the nine proper.docxkacie8xcheco
 
Prompt Write a short paper that describes a public health issue a.docx
Prompt Write a short paper that describes a public health issue a.docxPrompt Write a short paper that describes a public health issue a.docx
Prompt Write a short paper that describes a public health issue a.docxkacie8xcheco
 
PromptHow was St. Franciss message of empathy conveyed in the fr.docx
PromptHow was St. Franciss message of empathy conveyed in the fr.docxPromptHow was St. Franciss message of empathy conveyed in the fr.docx
PromptHow was St. Franciss message of empathy conveyed in the fr.docxkacie8xcheco
 
PromptOur readings from this unit engage with the topic of economi.docx
PromptOur readings from this unit engage with the topic of economi.docxPromptOur readings from this unit engage with the topic of economi.docx
PromptOur readings from this unit engage with the topic of economi.docxkacie8xcheco
 
PROMPT 1Reflecting on the CBS eye logo within the context of co.docx
PROMPT 1Reflecting on the CBS eye logo within the context of co.docxPROMPT 1Reflecting on the CBS eye logo within the context of co.docx
PROMPT 1Reflecting on the CBS eye logo within the context of co.docxkacie8xcheco
 
Project should include your revisions based on faculty feedback, pee.docx
Project should include your revisions based on faculty feedback, pee.docxProject should include your revisions based on faculty feedback, pee.docx
Project should include your revisions based on faculty feedback, pee.docxkacie8xcheco
 
Prompt 1Ethical ConsiderationsWhen using technology responsibly .docx
Prompt 1Ethical ConsiderationsWhen using technology responsibly .docxPrompt 1Ethical ConsiderationsWhen using technology responsibly .docx
Prompt 1Ethical ConsiderationsWhen using technology responsibly .docxkacie8xcheco
 
Prompt 1How did generational differences between white settlers a.docx
Prompt 1How did generational differences between white settlers a.docxPrompt 1How did generational differences between white settlers a.docx
Prompt 1How did generational differences between white settlers a.docxkacie8xcheco
 
Project   Assessing Self and Potential CandidatesPurpose In th.docx
Project   Assessing Self and Potential CandidatesPurpose In th.docxProject   Assessing Self and Potential CandidatesPurpose In th.docx
Project   Assessing Self and Potential CandidatesPurpose In th.docxkacie8xcheco
 
Project Schedule Due Week 6 and worth 150 pointsThis assignment .docx
Project Schedule Due Week 6 and worth 150 pointsThis assignment .docxProject Schedule Due Week 6 and worth 150 pointsThis assignment .docx
Project Schedule Due Week 6 and worth 150 pointsThis assignment .docxkacie8xcheco
 
Project Rolling out iPadseMenus for Bob RestaurantsProject S.docx
Project Rolling out iPadseMenus for Bob RestaurantsProject S.docxProject Rolling out iPadseMenus for Bob RestaurantsProject S.docx
Project Rolling out iPadseMenus for Bob RestaurantsProject S.docxkacie8xcheco
 
Project ScenarioYou are working for a company that provides c.docx
Project ScenarioYou are working for a company that provides c.docxProject ScenarioYou are working for a company that provides c.docx
Project ScenarioYou are working for a company that provides c.docxkacie8xcheco
 
Project Management Questions3. Do team members often report inco.docx
Project Management Questions3. Do team members often report inco.docxProject Management Questions3. Do team members often report inco.docx
Project Management Questions3. Do team members often report inco.docxkacie8xcheco
 
Project Management Financial AssessmentsThursday, 608167.docx
Project Management Financial AssessmentsThursday, 608167.docxProject Management Financial AssessmentsThursday, 608167.docx
Project Management Financial AssessmentsThursday, 608167.docxkacie8xcheco
 
project Kitchen Remodel (commercial) and a brief description about.docx
project Kitchen Remodel (commercial) and a brief description about.docxproject Kitchen Remodel (commercial) and a brief description about.docx
project Kitchen Remodel (commercial) and a brief description about.docxkacie8xcheco
 

More from kacie8xcheco (20)

PronombresFill in the blanks with the correct words.Raúl y Val.docx
PronombresFill in the blanks with the correct words.Raúl y Val.docxPronombresFill in the blanks with the correct words.Raúl y Val.docx
PronombresFill in the blanks with the correct words.Raúl y Val.docx
 
Propose at least three techniques in which the color blind perspecti.docx
Propose at least three techniques in which the color blind perspecti.docxPropose at least three techniques in which the color blind perspecti.docx
Propose at least three techniques in which the color blind perspecti.docx
 
Provide a 150 word response to the below discussion question answer .docx
Provide a 150 word response to the below discussion question answer .docxProvide a 150 word response to the below discussion question answer .docx
Provide a 150 word response to the below discussion question answer .docx
 
Prompt Submit a draft of your implementation section. You will gi.docx
Prompt Submit a draft of your implementation section. You will gi.docxPrompt Submit a draft of your implementation section. You will gi.docx
Prompt Submit a draft of your implementation section. You will gi.docx
 
PROMPT Think about how 5 of the population of the South managed to.docx
PROMPT Think about how 5 of the population of the South managed to.docxPROMPT Think about how 5 of the population of the South managed to.docx
PROMPT Think about how 5 of the population of the South managed to.docx
 
Properties of LifeChapter 1 of the text highlights the nine proper.docx
Properties of LifeChapter 1 of the text highlights the nine proper.docxProperties of LifeChapter 1 of the text highlights the nine proper.docx
Properties of LifeChapter 1 of the text highlights the nine proper.docx
 
Prompt Write a short paper that describes a public health issue a.docx
Prompt Write a short paper that describes a public health issue a.docxPrompt Write a short paper that describes a public health issue a.docx
Prompt Write a short paper that describes a public health issue a.docx
 
PromptHow was St. Franciss message of empathy conveyed in the fr.docx
PromptHow was St. Franciss message of empathy conveyed in the fr.docxPromptHow was St. Franciss message of empathy conveyed in the fr.docx
PromptHow was St. Franciss message of empathy conveyed in the fr.docx
 
PromptOur readings from this unit engage with the topic of economi.docx
PromptOur readings from this unit engage with the topic of economi.docxPromptOur readings from this unit engage with the topic of economi.docx
PromptOur readings from this unit engage with the topic of economi.docx
 
PROMPT 1Reflecting on the CBS eye logo within the context of co.docx
PROMPT 1Reflecting on the CBS eye logo within the context of co.docxPROMPT 1Reflecting on the CBS eye logo within the context of co.docx
PROMPT 1Reflecting on the CBS eye logo within the context of co.docx
 
Project should include your revisions based on faculty feedback, pee.docx
Project should include your revisions based on faculty feedback, pee.docxProject should include your revisions based on faculty feedback, pee.docx
Project should include your revisions based on faculty feedback, pee.docx
 
Prompt 1Ethical ConsiderationsWhen using technology responsibly .docx
Prompt 1Ethical ConsiderationsWhen using technology responsibly .docxPrompt 1Ethical ConsiderationsWhen using technology responsibly .docx
Prompt 1Ethical ConsiderationsWhen using technology responsibly .docx
 
Prompt 1How did generational differences between white settlers a.docx
Prompt 1How did generational differences between white settlers a.docxPrompt 1How did generational differences between white settlers a.docx
Prompt 1How did generational differences between white settlers a.docx
 
Project   Assessing Self and Potential CandidatesPurpose In th.docx
Project   Assessing Self and Potential CandidatesPurpose In th.docxProject   Assessing Self and Potential CandidatesPurpose In th.docx
Project   Assessing Self and Potential CandidatesPurpose In th.docx
 
Project Schedule Due Week 6 and worth 150 pointsThis assignment .docx
Project Schedule Due Week 6 and worth 150 pointsThis assignment .docxProject Schedule Due Week 6 and worth 150 pointsThis assignment .docx
Project Schedule Due Week 6 and worth 150 pointsThis assignment .docx
 
Project Rolling out iPadseMenus for Bob RestaurantsProject S.docx
Project Rolling out iPadseMenus for Bob RestaurantsProject S.docxProject Rolling out iPadseMenus for Bob RestaurantsProject S.docx
Project Rolling out iPadseMenus for Bob RestaurantsProject S.docx
 
Project ScenarioYou are working for a company that provides c.docx
Project ScenarioYou are working for a company that provides c.docxProject ScenarioYou are working for a company that provides c.docx
Project ScenarioYou are working for a company that provides c.docx
 
Project Management Questions3. Do team members often report inco.docx
Project Management Questions3. Do team members often report inco.docxProject Management Questions3. Do team members often report inco.docx
Project Management Questions3. Do team members often report inco.docx
 
Project Management Financial AssessmentsThursday, 608167.docx
Project Management Financial AssessmentsThursday, 608167.docxProject Management Financial AssessmentsThursday, 608167.docx
Project Management Financial AssessmentsThursday, 608167.docx
 
project Kitchen Remodel (commercial) and a brief description about.docx
project Kitchen Remodel (commercial) and a brief description about.docxproject Kitchen Remodel (commercial) and a brief description about.docx
project Kitchen Remodel (commercial) and a brief description about.docx
 

Background Some executives prefer to micromanage projects whereas o

  • 1. Background: Some executives prefer to micromanage projects whereas other executives are fearful of making a decision because, if they were to make the wrong decision, it could impact their career. In this case study, the president of the company assigned one of the vice presidents to act as the project sponsor on a project designed to build tooling for a client. The sponsor, however, was reluctant to make any decisions. Assigning the VP: Moreland Company was well-respected as a tooling design-and-build company. Moreland was project-driven because all of its income came from projects. Moreland was also reasonably mature in project management. When the previous VP for engineering retired, Moreland hired an executive from a manufacturing company to replace him. The new VP for engineering, Al Zink, had excellent engineering knowledge about tooling but had worked for companies that were not project-driven. Al had very little knowledge about project management and had never functioned as a project sponsor. Because of Al’s lack of experience as a sponsor, the president decided that Al should “get his feet wet” as quickly as possible and assigned him as the project sponsor on a mediumsized project. The project manager on this project was Fred Cutler. Fred was an engineer with more than twenty years of experience in tooling design and manufacturing. Fred reported directly to Al Zink administratively. Fred's Dilemma: Fred understood the situation; he would have to train Al Zink on how to function as a project sponsor. This was a new experience for Fred because subordinates usually do not train senior personnel on how to do their job. Would Al Zink be receptive? Fred explained the role of the sponsor and how there are certain project documents that require the
  • 2. signatures of both the project manager and the project sponsor. Everything seemed to be going well until Fred informed Al that the project sponsor is the person that the president eventually holds accountable for the success or failure of the project. Fred could tell that Al was quite upset over this statement. Al realized that the failure of a project where he was the sponsor could damage his reputation and career. Al was now uncomfortable about having to act as a sponsor but knew that he might eventually be assigned as a sponsor on other projects. Al also knew that this project was somewhat of a high risk. If Al could function as an invisible sponsor, he could avoid making any critical decisions. In the first meeting between Fred and Al where Al was the sponsor, Al asked Fred for a copy of the schedule for the project. Fred responded: I’m working on the schedule right now. I cannot finish the schedule until you tell me whether you want me to lay out the schedule based upon best time, least cost, or least risk. Al stated that he would think about it and get back to Fred as soon as possible. During the middle of the next week, Fred and Al met in the company’s cafeteria. Al asked Fred again, “How is the schedule coming along?” and Fred responded as before: I cannot finish the schedule until you tell me whether you want me to lay out the schedule based upon best time, least cost, or least risk. Al was furious, turned around, and walked away from Fred. Fred was now getting nervous about how upset Al was and began worrying if Al might remove him as the project manager. But Fred decided to hold his ground and get Al to make a decision. At the weekly sponsor meeting between Fred and Al, once again Al asked the same question, and once again Fred gave the same response as before. Al now became quite angry and yelled out: Just give me a least time schedule. Fred had gotten Al to make his first decision. Fred finalized his schedule and had it on Al’s desk two days later awaiting Al’s signature. Once again, Al procrastinated and refused to sign off on the schedule. Al believed that, if he delayed making the decision, Fred would take the initiative and begin working on the schedule without
  • 3. Al’s signature. Fred kept sending e-mails to Al asking when he intended to sign off on the schedule or, if something was not correct, what changes needed to be made. As expected, Al did not respond. Fred then decided that he had to pressure Al one way or another into making timely decisions as the project sponsor. Fred then sent an e-mail to Al that stated: I sent you the project schedule last week. If the schedule is not signed by this Friday, there could be an impact on the end date of the project. If I do not hear from you, one way or another, by this Friday, I will assume you approve the schedule and I can begin implementation. The president’s e-mail address was also included in the CC location on the e-mail. The next morning, Fred found the schedule on his desk, signed by Al Zink.