SlideShare a Scribd company logo
1 of 22
Download to read offline
CONFIDENTIAL



Defender Software Tools

Remedy Defender™
Portfolio Defender™
Due Diligence Defender™




                               Contact:

                         John Rosengard
                         (415) 982-3100

                          www.erci.com




               © 2012 Environmental Risk Communications, Inc.
ERCI and Defender Software

      ERCI incorporated in California in 1994
      Initial customers: US DOE, FMC, Chevron
      Software competence in:
            Microsoft Excel, Access, and Project
            Visual Basic for Applications (VBA)
            Crystal Ball and @Risk (Monte Carlo modeling for Excel and Project)

      17 portfolios, 300 users
      Remedy Defender: Single site analysis
      Portfolio Defender: Rollup reports of Remedy Defender
            Due Diligence Defender: Parametric models built for specific industries
            Midstream gas
            Sediments

      Counterparty Defender: Credit-weighted analysis of counterparties
       sharing future environmental costs




© 2012 Environmental Risk Communications, Inc.                                         2
Needs of the Typical Defender User

      GAAP Compliance / Audit Defense
            ASC 410-30-25 Recognition of Environmental Obligations
            ASTM E2137 for Estimating Environmental Liabilities
            ASTM E2173 for Disclosing Environmental Liabilities

      Performance Management
            Strategic consistency: Cost benchmarks, risks, remedial alternatives
            Challenge current strategy: New options, accelerate / defer
            Differentiate between reserve, asset retirement, OPEX, CAPEX spending

      Change Management
            Document site history, key assumptions
            Prepare for any team turnover: Project manager, lead consultant, regulator, external
             counsel

      Vendor Management
            Identify best practices, lessons learned
            Record cost benchmarks



© 2012 Environmental Risk Communications, Inc.                                                      3
What is Defender?
                                                                                                                  ENVIRONMENTAL BUSINESS PLAN                                                                                       RESERVE CASE:                              ($24,910,034)


      Software for environmental                                                                                     I. SITE SUMMARY

                                                                                                                                               Site Name            County Landfill                                                              Business Unit   1001

       liability teams                                                                                                                  Project Manager
                                                                                                                                            Project Code
                                                                                                                                                   Street
                                                                                                                                                                    Luke Vermeire
                                                                                                                                                                    01CLF
                                                                                                                                                                    475 Sansome Street
                                                                                                                                                                                                                                      Lead Internal Attorney
                                                                                                                                                                                                                                Additional Internal Attorney
                                                                                                                                                                                                                            Business Unit or Owner Contact
                                                                                                                                                                                                                                                                 Ryan Lafrenz
                                                                                                                                                                                                                                                                 n/a
                                                                                                                                                                                                                                                                 n/a
                                                                                                                                                       City         San Francisco                                                  Public Affairs Coordinator    n/a


             Measure
                                                                                                                                                     State          California                                                      Real Estate Coordinator      n/a
                                                                                                                                                 Zip Code
                                                                                                                                   Lead Regulatory Agency
                                                                                                                                                                    94111
                                                                                                                                                                    EPA
                                                                                                                                                                                                                                            External Counsel
                                                                                                                                                                                                                                           Offsite Landowner
                                                                                                                                                                                                                                                                 n/a
                                                                                                                                                                                                                                                                 n/a
                                                                                                                                     Superfund or NPL Site          CA123456789                                                                  Third Parties   n/a
                                                                                                                                            PRP Participant         Yes                                                                    Consultant (study)    URS

            Analyze                                                                                                                            PRP Share
                                                                                                                                 USEPA Regulatory Contact
                                                                                                                                                                    75%
                                                                                                                                                                    Jane Doe
                                                                                                                                                                                                                             Consultant (remediation/O&M)
                                                                                                                                                                                                                                         Property Tax Status
                                                                                                                                                                                                                                                                 SCS Engineers
                                                                                                                                                                                                                                                                 n/a
                                                                                                                                       USEPA Generator ID           n/a                                                          Adjoining Property Owners       Joe's tire shop
                                                                                                                                  State Regulatory Contact          n/a                                                                          Date Notified   5/12/2012

            Display                                                                                                                    State Generator ID
                                                                                                                                            US EPA Region
                                                                                                                                             Project Cause
                                                                                                                                                                    n/a
                                                                                                                                                                    9
                                                                                                                                                                    Landfill Operations
                                                                                                                                                                                                                                                  Date Added
                                                                                                                                                                                                                            Estimated Project Closure Date
                                                                                                                                                                                                                       Regulator's Contaminants of Concern
                                                                                                                                                                                                                                                                 6/29/2012
                                                                                                                                                                                                                                                                 7/4/2052
                                                                                                                                                                                                                                                                 CAM 17, VOCs, SVOCs, PCBs



             Disclose
                                                                                                                                        Last Update Date                            8/31/2012                                      Budget Approval Date                     6/30/2012
                                                                                                                     II. ASC 410-30-25-15 Recognition Benchmarks

                                                                                                                      a. Identification and verification of                          1/16/1996                        Company recognized as PRP by EPA

      How Does Defender Work?                                                                                        an entity as a potentially
                                                                                                                      responsible party

                                                                                                   FINANCIAL SUMMARY
                                                                                                            b. Receipt of unilateral                                                 1/16/1999                        AO dated 1/16/1999 received by PRP group

             Cost forecasting / estimating
                                                                                                                      administrative order
                                                                                                                                                  Case                  Case                   Case                  Case




                                                                                                                                                   R
                                                                                                                      c. Participation, as a potentially
                                                                                                                                                                         1           5/12/2009
                                                                                                                                                                                                 2                    3
                                                                                                                                                                                                                      PRP group completed RI in 2009

             Alternative analysis
                                                                                                                      responsible party, in the remedial
                                                                                                                    investigation-feasibility study
                                                                                                              Strategy Description          Reserve Case          Delay Project 5 Years
                                                                                                                                                                                             Increased PRP
                                                                                                                                                                                               Recoveries
                                                                                                                                                                                                               Complete Coverage
                                                                                                                                                                                                                with Asphalt Cap

                                                                                                       FUTURE VALUE 5-YR (2011-2015)          ($9,967,590)            ($521,445)                       DISTRIBUTION CHARTS
                                                                                                                                                                                            ($10,409,933)    ($10,508,806)
                                                                                                                      d. Completion of feasibility study                             6/29/2012                        PRP group completed FS in 2012


             Monte Carlo modeling
                                                                                                       FUTURE VALUE 10-YR (2011-2020)         ($16,867,332)         ($11,554,072)           ($17,798,058)       ($19,075,710)
       
                                                                                                                                                                                                                R01

                                                                                                       FUTURE VALUE 30-YR (2011-2040)         ($24,910,034)         ($25,503,923)           ($25,840,760)       ($26,186,143)

                                                                                                                      e. Issuance of record of decision
                                                                                                       PRESENT VALUE 30-YR (2011-2040)    ($12,599,881)              ($8,963,293)           ($13,219,348)
                                                                                                                                                                                                                      Waiting for EPA to release ROD, expected 2013
                                                                                                                                                                                                                ($13,911,252)


            Project controls                                                                          COST RECOVERIES                         $6,098,722            $6,247,194              $8,863,965          $6,535,437

                                                                                                       OPERATING BUSINESS IMPACTS                   $0                    $0                     $0                    $0
                                                                                                                      f. Remedial design through                                                                      Expected 2016


             Audit support
                     pp
                                                                                                       PROJECT CASH operation
                                                                                                                    FLOWS NPV    and maintenance,
                                                                                                                                            ($9,458,030)             ($6,730,589)            ($8,603,942)       ($10,434,139)
                                                                                                                     including post-remediation
                                                                                                                      monitoring
                                                                                                                                         Financial Assumptions:          2.00%            In f lat io n
                                                                                                                                                                        10.00%            Disc o u n t rat e


                                                                                                                      III. STRATEGIC ALTERNATIVES                                                                                                       BUDGET VALUE

                                                                                                                  Reserve Case                                                    ($24,910,034)                       Reserve case, most likely
            Probablistic Cost Modeling (Monte Carlo)                                                              Delay Project 5 Years                                           ($25,503,923)
                                                                                                                                                                                                                R02
                                                                                                                                                                                                                      Same costs as Case R, delayed 5 years plus 5 years of PM, legal, etc. costs
                                                                                                                  Increased PRP Recoveries                                        ($25,840,760)                       Additional legal support to gain 10% more recovery from recalcitrant PRPs
                                                                                                                  Complete Coverage with Asphalt Cap                              ($26,186,143)                       Complete coverage with asphalt and reduced length of O&M by 5 years
                                                       p10             p50             p90         Expected Value           Chart #
                  Case R: Reserve Case
                  Remedial Costs                  $    1,000,000   $   1,500,000   $   2,500,000   $      1,649,019            R01
                  Capping Acres                          75             100             125              100.1                 R02
                  Capping Cost / Acre             $       70,000   $      85,000   $     100,000   $         85,043            R03
                  Material Cost                   $    1,000,000
                                                       1 000 000   $   1,500,000
                                                                       1 500 000   $   2,000,000
                                                                                       2 000 000   $      1,501,426
                                                                                                          1 501 426            R04
                  Yearly Monitoring Cost          $      125,000   $     150,000   $     225,000   $        165,085            R05
                                                                                                   Click to Add Row                        Rcase

                  Case 1: Delay Project 5 Years
                                                  $          -     $         -     $         -
                                                  $          -     $         -     $         -
                                                  $          -     $         -     $         -
                                                  $          -     $         -     $         -
                                                  $          -     $         -     $         -
                                                                                                   Click to Add Row                        1Case


© 2012 Environmental Risk Communications, Inc.                                                                                                                                                                                                                                                      4
Defender – Index




                                                                               User may select
                                                                            alternatives to update




                                           Navigation buttons
                                                for users
                                                                                  Allows user to save a PDF
                                                                                      copy for archiving



                                       Allows user to save a copy of file for audit
                                          that removes privileged information




© 2012 Environmental Risk Communications, Inc.                                                                5
Defender – Plan Page




  Site / project specific data,
   contact information, and
          critical dates




                                                 Information regarding compliance
                                                      with ASC 410-30-25-15
                                                      Recognition Benchmarks




© 2012 Environmental Risk Communications, Inc.                                      6
Defender – Plan Page (cont.)




                                                    Strategic alternatives
                                                         comparison




                                                 Historical notes and
                                                     summaries




© 2012 Environmental Risk Communications, Inc.                               7
Defender – Financial Summary & Site Narrative




                                                                             Comparison of alternative
                                                                                cases and financial
                                                                              summaries for analysis




                                                 User may store project manager notes,
                                                 regulator correspondence, additional
                                                     information or documentation
                                                     i f     ti     d         t ti
                                                       regarding the site / project



© 2012 Environmental Risk Communications, Inc.                                                           8
Defender – Modeling




                                             User inputs for ranges
                                                    p           g
                                                to be modeled




                                                 User inputs line items, unit
                                                 cost, or units for analysis




                                                   Modeled expected values flow
                                                    to individual case estimates




© 2012 Environmental Risk Communications, Inc.                                     9
Defender – Modeling (cont.)




                                                 Various options for
                                                 distribution charts
                                                  (Weibull shown)




                                                                     Distribution charts
                                                                 created for every modeled
                                                                          line item




© 2012 Environmental Risk Communications, Inc.                                               10
Defender – Case R




                                                                                  Main section for inputting
                                                                                       cost estimates




                                                 User selected subtasks
                                                    from pop-up list




                                                                Expected values from
                                                                   modeling sheet




© 2012 Environmental Risk Communications, Inc.                                                                 11
Defender – Case R (cont.)



                                                 Automatic WBS code lookup
                                                 from company-defined Work
                                                    Breakdown Structure
                                                     (ASTM WBS shown)




                                                      Cost recovery / PRP
                                                       share calculations




                                                                    Inputs for OPCO
                                                                        impacts




© 2012 Environmental Risk Communications, Inc.                                        12
Defender – Case R (cont.)



                                                    Inputs for OPCO
                                                    impacts (cont.)




                                                 Section for budgeting, reporting,
                                                       analysis, and display




© 2012 Environmental Risk Communications, Inc.                                       13
Report: “Bow Wave” Analysis

      Concern: $1 spent ≠ $1 liability work-down
                $120


                $110                                                                             2011

                $100


                 $90                                                                             2010
                                                                                                 2009
                 $80
                                                                                                 2008
                 $70
       ($ MM)




                 $60                                                                             2006
                                                                                                 2007
       (




                 $50


                 $40


                 $30

                           Cumulative spending
                 $20


                 $10


                  $0




                          Cumulative Spend       Budget Remaining   2006   2007   2008   2009   2010    2011

© 2012 Environmental Risk Communications, Inc.                                                                 14
Report: “Bow Wave” Analysis

      Goal: $1 spent ≈ $1 liability work-down
                $120


                $110


                $100


                 $90


                 $80


                 $70
       ($ MM)




                 $60                                                                            2006-2011
       (




                 $50


                 $40


                 $30

                           Cumulative spending
                 $20


                 $10


                  $0




                          Cumulative Spend       Budget Remaining   2006   2007   2008   2009      2010     2011

© 2012 Environmental Risk Communications, Inc.                                                                     15
Report: Scenario Comparison, 30-yr NPV, $MM
                   GW                 Liability
 Percentiles
                Protection             Work
     0%            $3.83                         $5.13
                                                                                                     100%
     10%           $5.04                         $7.63

     20%           $5.46                         $8.78
                                                                                                     90%
     30%           $5.79
                   $5 79                         $9.84
                                                 $9 84

     40%           $6.08                   $10.91

     50%           $6.37                   $12.06
                                                                                                     80%

     60%           $6.61                   $13.07

     70%           $6.89                   $14.15                                                    70%

     80%           $7.24                   $15.14

     90%           $7.77                   $16.44                                                    60%
    100%           $9.92                   $18.38
                                                                                                     50%
                                                                 ed
                                                   Reserve Propose
                              Reserve Original




                                                                                                     40%


                                                                                                     30%
                                    e:
                                                         e:




                                                                                                     20%


                                                                                                     10%


                                                                                                      0%
                    $0                                                $5   $10   $15               $20

                           Ordinarily, there is a gap between reserve levels and lifecycle (NPV)
© 2012 Environmental Risk Communications, Inc.                                                              16
Report: Reserve History

             Future reserves:
                                                                                                 10
             + $ 8.2 million
             Recognition criteria and                                                            9
             trigger date in Watch List
                                                                                                 8

                                                                                                 7




                                                                                                       $ million
                                                                                                 6

                                                                                                 5

                                                                                                 4
                                                               Actual spending
                                                               Typically lags reserves by        3
                                                               two to ten years
                                                                                                 2

                               Initial study                                                     1

                                                                                               0
                         2008             2010   2012         2014           2016           2018



                                                   Reserve History
                                                   A. $1.8M Costs to perform initial study [Reserved]
           Original reserve:                       B. $2 6M
                                                   B $2.6M Costs to conclude assessment, explore options, draft
                                                                                assessment          options
                                                       feasibility study or EE/CA (add in 2010)
           $ 1.8 million                           C. $4.0M Remedy implementation update (add in 2011)
                                                   D. $1.6M O&M cost update (add in 2013+)

© 2012 Environmental Risk Communications, Inc.                                                                     17
Recognition Triggers of Future Losses

        New tool for environmental remediation liability forecasting
             ASC 410-30-50-9 “Disclosures that Are Encouraged but Not Required”
             Displays to management – for potential disclosure – future reserve changes
             Site-specific
             Recognition trigger is specific and measurable
             Range of costs and timing noted
                 g                    g


  Site       Recognition Trigger                            Low Value      Mid Value     High Value      Timing
                                                           ($ millions)   ($ millions)   ($ millions)
Site 1       CAMU size and installation year                   1.0            1.5           2.25        3/31/2014
Site 2       Remedy selection: SVE for 10 years                1.5           2.25            4.5        2014-2015
Site 3       Remedy selection: P&T for 30 years                2.0            2.5            3.0        1/1/2015
Site 3       Source removal: 300,000 CY soil (lead)            2.5            3.0            3.5        1/1/2015
Site 4       Scope of investigation                            0.5            0.7            0.8        1/1/2014
Site 5       NRDA claim/damages                                0.5            1.0            2.0        2015-2018
Site 5       30% design of soil removal 20,000 MT (lead)       1.0            2.5            4.5        7/1/2016
Site 5       Remedy selection for 195,000 MT (solvents)         7             12             16         7/1/2016
Site 6       Building demo, redevelopment (ARO or CAPEX)       2.5            5.0            5.5         2013-14




© 2012 Environmental Risk Communications, Inc.                                                                      18
Uncertainty is Normal


         Expected Cost Estimate Accuracy Along the Superfund Pipeline




  Source: USEPA, A Guide to Developing and Documenting Cost Estimates During the Feasibility Study, July 2000


© 2012 Environmental Risk Communications, Inc.                                                                  19
Audit Experience

                                                                                   Fortune
                                                                                   Fo t ne 500
Company                               Division                                                       Auditor            Audits
                                                                                     (sales)
                                      Chevron Environmental Management Co.
                                      Chevron Pipe Line Co                                                            Annual, plus
Chevron                                                                                 3
                                      Chevron Canada, Ltd.                                                           quarterly items

                                      Texaco Downstream Properties, Inc.

Duke Energy                           Duke Energy Field Services
                                                                                       173                               Annual
Field Services                        Natural gas collection and pipelines

                                      Now part of KinderMorgan                                                        Annual, plus
El Paso Corp                                                                           488
                                      Diversified energy company                                                      special items
                                                                                                                       p

                                      Corporate-wide
FMC                                                                                    475                               Annual
                                      Diversified manufacturer

                                      Corporate-wide                                                                 Annual or less
Hewlett-Packard                                                                        10
                                      Computer and microelectronics manufacturer                                     (not material)

Northrop                              Corporate-wide
                                                                                       104                               Annual
Grumman                               Aerospace and defense                                         and DCAA

                                      Corporate-wide
Port of Seattle                                                                        NA                                Annual
                                      Regional airport and marine port authority                 and State Auditor

                                      Corporate-wide
                                      C      t   id                                                                   Annual, plus
Tesoro Petroleum                                                                       101
                                      Oil refinery and marketer                                                       special items

                                      Corporate-wide
TRW Automotive                                                                         161                               Annual
                                      Automotive parts
                                      Corporate-wide
Univar                                                                               Private                             Annual
                                      Chemical processor and distributor

                                      Corporate-wide                                                                  Annual, plus
Delphi                                                                                 163
                                      Automotive parts                                                               quarterly items

© 2012 Environmental Risk Communications, Inc.                                                                                         20
Defender Value Proposition

      Calculating core business effects of environmental projects
            Assess, anticipate, price, and react to risks
            Apply reserve dollars, operating expenses (OPEX), capital expenditures (CAPEX) fairly
             and accurately
            Maintain strategic consistency

      Using standard financial terms
            Budget: 2-5 years
            Reserves: 3-30 years
            Cost-to-close (lifecycle)

      Expected value, future value, present value
      Documenting forecasts for audit defense
      Responding to changing sources of risk
            Time to regulator acceptance or NFA
            Viability of cost recovery source
            Permanence, effecti eness
             Pe manence effectiveness of remedy
                                          emed
            Regulator turnover

© 2012 Environmental Risk Communications, Inc.                                                       21
Defender Deployment

      Duration: 90 days
      Key Steps
            Define the Work Breakdown Structure (WBS)
                                                 (   )
            Import current budgets and reserves (with backup)
            Populate the history, issues / alternatives, and other narrative
            Adjust the budget vs. actual reporting process

      Key Performance Indicators
            Reduction of time spent on reserve updates / variances
            Reduction of time spent on project handoffs
            More time thinking critically about the reserve watch list
            Fewer reserve surprises
            Better t k h ld
             B tt stakeholder reactions t upcoming decisions
                                  ti    to     i   d i i
            Minimal time with auditors and improved auditor acceptance
            >90% of reserve adjustments (by $) come from the reserve watch list




© 2012 Environmental Risk Communications, Inc.                                     22

More Related Content

Viewers also liked (8)

M Moser Design Experience
M Moser Design ExperienceM Moser Design Experience
M Moser Design Experience
 
LinkedIn Squeaky Wheel
LinkedIn Squeaky WheelLinkedIn Squeaky Wheel
LinkedIn Squeaky Wheel
 
Erci apr2015 webinar counterparty risk
Erci apr2015 webinar  counterparty riskErci apr2015 webinar  counterparty risk
Erci apr2015 webinar counterparty risk
 
Erci mar2015 webinar 2014 10 k reports on environmental liabilities - trends
Erci mar2015 webinar   2014 10 k reports on environmental liabilities - trendsErci mar2015 webinar   2014 10 k reports on environmental liabilities - trends
Erci mar2015 webinar 2014 10 k reports on environmental liabilities - trends
 
Erci mar2015 webinar fair value measurement
Erci mar2015 webinar   fair value measurementErci mar2015 webinar   fair value measurement
Erci mar2015 webinar fair value measurement
 
Estimating and Disclosing Environmental Liabilities
Estimating and Disclosing Environmental LiabilitiesEstimating and Disclosing Environmental Liabilities
Estimating and Disclosing Environmental Liabilities
 
La marca
La marcaLa marca
La marca
 
PORTAFOLIS MARTINA
PORTAFOLIS MARTINAPORTAFOLIS MARTINA
PORTAFOLIS MARTINA
 

Similar to ERCI Defender Backgrounder (10)

Project Excellence Risk Management K
Project Excellence Risk Management KProject Excellence Risk Management K
Project Excellence Risk Management K
 
Lynton Aviation Performance management final
Lynton Aviation Performance management finalLynton Aviation Performance management final
Lynton Aviation Performance management final
 
2006 Downtown Ferndale Parking Study_Section 3
2006 Downtown Ferndale Parking Study_Section 32006 Downtown Ferndale Parking Study_Section 3
2006 Downtown Ferndale Parking Study_Section 3
 
Project Controls Expo, 18th Nov 2014 - "Enterprise Project & Risk Analysis in...
Project Controls Expo, 18th Nov 2014 - "Enterprise Project & Risk Analysis in...Project Controls Expo, 18th Nov 2014 - "Enterprise Project & Risk Analysis in...
Project Controls Expo, 18th Nov 2014 - "Enterprise Project & Risk Analysis in...
 
Decommissioning Report, 2012-13, Gulf of Mexico
Decommissioning Report, 2012-13, Gulf of MexicoDecommissioning Report, 2012-13, Gulf of Mexico
Decommissioning Report, 2012-13, Gulf of Mexico
 
Introducing lo cus for potential new partners
Introducing lo cus   for potential new partnersIntroducing lo cus   for potential new partners
Introducing lo cus for potential new partners
 
GoM Decommissioning Report Brochure
GoM Decommissioning Report BrochureGoM Decommissioning Report Brochure
GoM Decommissioning Report Brochure
 
Nrs Presentation
Nrs PresentationNrs Presentation
Nrs Presentation
 
RhiZone Energy Solutions
RhiZone Energy SolutionsRhiZone Energy Solutions
RhiZone Energy Solutions
 
Semjet international company profile 2012
Semjet international company profile 2012Semjet international company profile 2012
Semjet international company profile 2012
 

ERCI Defender Backgrounder

  • 1. CONFIDENTIAL Defender Software Tools Remedy Defender™ Portfolio Defender™ Due Diligence Defender™ Contact: John Rosengard (415) 982-3100 www.erci.com © 2012 Environmental Risk Communications, Inc.
  • 2. ERCI and Defender Software  ERCI incorporated in California in 1994  Initial customers: US DOE, FMC, Chevron  Software competence in:  Microsoft Excel, Access, and Project  Visual Basic for Applications (VBA)  Crystal Ball and @Risk (Monte Carlo modeling for Excel and Project)  17 portfolios, 300 users  Remedy Defender: Single site analysis  Portfolio Defender: Rollup reports of Remedy Defender  Due Diligence Defender: Parametric models built for specific industries  Midstream gas  Sediments  Counterparty Defender: Credit-weighted analysis of counterparties sharing future environmental costs © 2012 Environmental Risk Communications, Inc. 2
  • 3. Needs of the Typical Defender User  GAAP Compliance / Audit Defense  ASC 410-30-25 Recognition of Environmental Obligations  ASTM E2137 for Estimating Environmental Liabilities  ASTM E2173 for Disclosing Environmental Liabilities  Performance Management  Strategic consistency: Cost benchmarks, risks, remedial alternatives  Challenge current strategy: New options, accelerate / defer  Differentiate between reserve, asset retirement, OPEX, CAPEX spending  Change Management  Document site history, key assumptions  Prepare for any team turnover: Project manager, lead consultant, regulator, external counsel  Vendor Management  Identify best practices, lessons learned  Record cost benchmarks © 2012 Environmental Risk Communications, Inc. 3
  • 4. What is Defender? ENVIRONMENTAL BUSINESS PLAN RESERVE CASE: ($24,910,034)  Software for environmental I. SITE SUMMARY Site Name County Landfill Business Unit 1001 liability teams Project Manager Project Code Street Luke Vermeire 01CLF 475 Sansome Street Lead Internal Attorney Additional Internal Attorney Business Unit or Owner Contact Ryan Lafrenz n/a n/a City San Francisco Public Affairs Coordinator n/a Measure State California Real Estate Coordinator n/a  Zip Code Lead Regulatory Agency 94111 EPA External Counsel Offsite Landowner n/a n/a Superfund or NPL Site CA123456789 Third Parties n/a PRP Participant Yes Consultant (study) URS  Analyze PRP Share USEPA Regulatory Contact 75% Jane Doe Consultant (remediation/O&M) Property Tax Status SCS Engineers n/a USEPA Generator ID n/a Adjoining Property Owners Joe's tire shop State Regulatory Contact n/a Date Notified 5/12/2012  Display State Generator ID US EPA Region Project Cause n/a 9 Landfill Operations Date Added Estimated Project Closure Date Regulator's Contaminants of Concern 6/29/2012 7/4/2052 CAM 17, VOCs, SVOCs, PCBs Disclose Last Update Date 8/31/2012 Budget Approval Date 6/30/2012  II. ASC 410-30-25-15 Recognition Benchmarks a. Identification and verification of 1/16/1996 Company recognized as PRP by EPA  How Does Defender Work? an entity as a potentially responsible party FINANCIAL SUMMARY b. Receipt of unilateral 1/16/1999 AO dated 1/16/1999 received by PRP group Cost forecasting / estimating administrative order  Case Case Case Case R c. Participation, as a potentially 1 5/12/2009 2 3 PRP group completed RI in 2009 Alternative analysis responsible party, in the remedial  investigation-feasibility study Strategy Description Reserve Case Delay Project 5 Years Increased PRP Recoveries Complete Coverage with Asphalt Cap FUTURE VALUE 5-YR (2011-2015) ($9,967,590) ($521,445) DISTRIBUTION CHARTS ($10,409,933) ($10,508,806) d. Completion of feasibility study 6/29/2012 PRP group completed FS in 2012 Monte Carlo modeling FUTURE VALUE 10-YR (2011-2020) ($16,867,332) ($11,554,072) ($17,798,058) ($19,075,710)  R01 FUTURE VALUE 30-YR (2011-2040) ($24,910,034) ($25,503,923) ($25,840,760) ($26,186,143) e. Issuance of record of decision PRESENT VALUE 30-YR (2011-2040) ($12,599,881) ($8,963,293) ($13,219,348) Waiting for EPA to release ROD, expected 2013 ($13,911,252)  Project controls COST RECOVERIES $6,098,722 $6,247,194 $8,863,965 $6,535,437 OPERATING BUSINESS IMPACTS $0 $0 $0 $0 f. Remedial design through Expected 2016 Audit support pp PROJECT CASH operation FLOWS NPV and maintenance, ($9,458,030) ($6,730,589) ($8,603,942) ($10,434,139)  including post-remediation monitoring Financial Assumptions: 2.00% In f lat io n 10.00% Disc o u n t rat e III. STRATEGIC ALTERNATIVES BUDGET VALUE Reserve Case ($24,910,034) Reserve case, most likely Probablistic Cost Modeling (Monte Carlo) Delay Project 5 Years ($25,503,923) R02 Same costs as Case R, delayed 5 years plus 5 years of PM, legal, etc. costs Increased PRP Recoveries ($25,840,760) Additional legal support to gain 10% more recovery from recalcitrant PRPs Complete Coverage with Asphalt Cap ($26,186,143) Complete coverage with asphalt and reduced length of O&M by 5 years p10 p50 p90 Expected Value Chart # Case R: Reserve Case Remedial Costs $ 1,000,000 $ 1,500,000 $ 2,500,000 $ 1,649,019 R01 Capping Acres 75 100 125 100.1 R02 Capping Cost / Acre $ 70,000 $ 85,000 $ 100,000 $ 85,043 R03 Material Cost $ 1,000,000 1 000 000 $ 1,500,000 1 500 000 $ 2,000,000 2 000 000 $ 1,501,426 1 501 426 R04 Yearly Monitoring Cost $ 125,000 $ 150,000 $ 225,000 $ 165,085 R05 Click to Add Row Rcase Case 1: Delay Project 5 Years $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - Click to Add Row 1Case © 2012 Environmental Risk Communications, Inc. 4
  • 5. Defender – Index User may select alternatives to update Navigation buttons for users Allows user to save a PDF copy for archiving Allows user to save a copy of file for audit that removes privileged information © 2012 Environmental Risk Communications, Inc. 5
  • 6. Defender – Plan Page Site / project specific data, contact information, and critical dates Information regarding compliance with ASC 410-30-25-15 Recognition Benchmarks © 2012 Environmental Risk Communications, Inc. 6
  • 7. Defender – Plan Page (cont.) Strategic alternatives comparison Historical notes and summaries © 2012 Environmental Risk Communications, Inc. 7
  • 8. Defender – Financial Summary & Site Narrative Comparison of alternative cases and financial summaries for analysis User may store project manager notes, regulator correspondence, additional information or documentation i f ti d t ti regarding the site / project © 2012 Environmental Risk Communications, Inc. 8
  • 9. Defender – Modeling User inputs for ranges p g to be modeled User inputs line items, unit cost, or units for analysis Modeled expected values flow to individual case estimates © 2012 Environmental Risk Communications, Inc. 9
  • 10. Defender – Modeling (cont.) Various options for distribution charts (Weibull shown) Distribution charts created for every modeled line item © 2012 Environmental Risk Communications, Inc. 10
  • 11. Defender – Case R Main section for inputting cost estimates User selected subtasks from pop-up list Expected values from modeling sheet © 2012 Environmental Risk Communications, Inc. 11
  • 12. Defender – Case R (cont.) Automatic WBS code lookup from company-defined Work Breakdown Structure (ASTM WBS shown) Cost recovery / PRP share calculations Inputs for OPCO impacts © 2012 Environmental Risk Communications, Inc. 12
  • 13. Defender – Case R (cont.) Inputs for OPCO impacts (cont.) Section for budgeting, reporting, analysis, and display © 2012 Environmental Risk Communications, Inc. 13
  • 14. Report: “Bow Wave” Analysis  Concern: $1 spent ≠ $1 liability work-down $120 $110 2011 $100 $90 2010 2009 $80 2008 $70 ($ MM) $60 2006 2007 ( $50 $40 $30 Cumulative spending $20 $10 $0 Cumulative Spend Budget Remaining 2006 2007 2008 2009 2010 2011 © 2012 Environmental Risk Communications, Inc. 14
  • 15. Report: “Bow Wave” Analysis  Goal: $1 spent ≈ $1 liability work-down $120 $110 $100 $90 $80 $70 ($ MM) $60 2006-2011 ( $50 $40 $30 Cumulative spending $20 $10 $0 Cumulative Spend Budget Remaining 2006 2007 2008 2009 2010 2011 © 2012 Environmental Risk Communications, Inc. 15
  • 16. Report: Scenario Comparison, 30-yr NPV, $MM GW Liability Percentiles Protection Work 0% $3.83 $5.13 100% 10% $5.04 $7.63 20% $5.46 $8.78 90% 30% $5.79 $5 79 $9.84 $9 84 40% $6.08 $10.91 50% $6.37 $12.06 80% 60% $6.61 $13.07 70% $6.89 $14.15 70% 80% $7.24 $15.14 90% $7.77 $16.44 60% 100% $9.92 $18.38 50% ed Reserve Propose Reserve Original 40% 30% e: e: 20% 10% 0% $0 $5 $10 $15 $20 Ordinarily, there is a gap between reserve levels and lifecycle (NPV) © 2012 Environmental Risk Communications, Inc. 16
  • 17. Report: Reserve History Future reserves: 10 + $ 8.2 million Recognition criteria and 9 trigger date in Watch List 8 7 $ million 6 5 4 Actual spending Typically lags reserves by 3 two to ten years 2 Initial study 1 0 2008 2010 2012 2014 2016 2018 Reserve History A. $1.8M Costs to perform initial study [Reserved] Original reserve: B. $2 6M B $2.6M Costs to conclude assessment, explore options, draft assessment options feasibility study or EE/CA (add in 2010) $ 1.8 million C. $4.0M Remedy implementation update (add in 2011) D. $1.6M O&M cost update (add in 2013+) © 2012 Environmental Risk Communications, Inc. 17
  • 18. Recognition Triggers of Future Losses  New tool for environmental remediation liability forecasting  ASC 410-30-50-9 “Disclosures that Are Encouraged but Not Required”  Displays to management – for potential disclosure – future reserve changes  Site-specific  Recognition trigger is specific and measurable  Range of costs and timing noted g g Site Recognition Trigger Low Value Mid Value High Value Timing ($ millions) ($ millions) ($ millions) Site 1 CAMU size and installation year 1.0 1.5 2.25 3/31/2014 Site 2 Remedy selection: SVE for 10 years 1.5 2.25 4.5 2014-2015 Site 3 Remedy selection: P&T for 30 years 2.0 2.5 3.0 1/1/2015 Site 3 Source removal: 300,000 CY soil (lead) 2.5 3.0 3.5 1/1/2015 Site 4 Scope of investigation 0.5 0.7 0.8 1/1/2014 Site 5 NRDA claim/damages 0.5 1.0 2.0 2015-2018 Site 5 30% design of soil removal 20,000 MT (lead) 1.0 2.5 4.5 7/1/2016 Site 5 Remedy selection for 195,000 MT (solvents) 7 12 16 7/1/2016 Site 6 Building demo, redevelopment (ARO or CAPEX) 2.5 5.0 5.5 2013-14 © 2012 Environmental Risk Communications, Inc. 18
  • 19. Uncertainty is Normal Expected Cost Estimate Accuracy Along the Superfund Pipeline Source: USEPA, A Guide to Developing and Documenting Cost Estimates During the Feasibility Study, July 2000 © 2012 Environmental Risk Communications, Inc. 19
  • 20. Audit Experience Fortune Fo t ne 500 Company Division Auditor Audits (sales) Chevron Environmental Management Co. Chevron Pipe Line Co Annual, plus Chevron 3 Chevron Canada, Ltd. quarterly items Texaco Downstream Properties, Inc. Duke Energy Duke Energy Field Services 173 Annual Field Services Natural gas collection and pipelines Now part of KinderMorgan Annual, plus El Paso Corp 488 Diversified energy company special items p Corporate-wide FMC 475 Annual Diversified manufacturer Corporate-wide Annual or less Hewlett-Packard 10 Computer and microelectronics manufacturer (not material) Northrop Corporate-wide 104 Annual Grumman Aerospace and defense and DCAA Corporate-wide Port of Seattle NA Annual Regional airport and marine port authority and State Auditor Corporate-wide C t id Annual, plus Tesoro Petroleum 101 Oil refinery and marketer special items Corporate-wide TRW Automotive 161 Annual Automotive parts Corporate-wide Univar Private Annual Chemical processor and distributor Corporate-wide Annual, plus Delphi 163 Automotive parts quarterly items © 2012 Environmental Risk Communications, Inc. 20
  • 21. Defender Value Proposition  Calculating core business effects of environmental projects  Assess, anticipate, price, and react to risks  Apply reserve dollars, operating expenses (OPEX), capital expenditures (CAPEX) fairly and accurately  Maintain strategic consistency  Using standard financial terms  Budget: 2-5 years  Reserves: 3-30 years  Cost-to-close (lifecycle)  Expected value, future value, present value  Documenting forecasts for audit defense  Responding to changing sources of risk  Time to regulator acceptance or NFA  Viability of cost recovery source  Permanence, effecti eness Pe manence effectiveness of remedy emed  Regulator turnover © 2012 Environmental Risk Communications, Inc. 21
  • 22. Defender Deployment  Duration: 90 days  Key Steps  Define the Work Breakdown Structure (WBS) ( )  Import current budgets and reserves (with backup)  Populate the history, issues / alternatives, and other narrative  Adjust the budget vs. actual reporting process  Key Performance Indicators  Reduction of time spent on reserve updates / variances  Reduction of time spent on project handoffs  More time thinking critically about the reserve watch list  Fewer reserve surprises  Better t k h ld B tt stakeholder reactions t upcoming decisions ti to i d i i  Minimal time with auditors and improved auditor acceptance  >90% of reserve adjustments (by $) come from the reserve watch list © 2012 Environmental Risk Communications, Inc. 22