SlideShare a Scribd company logo
1 of 20
Download to read offline
A I M : E M E D T S X : E M D
Presentation 21 March 2013 Presentation at Proactive Conference
2
DISCLAIMER
The information contained in this confidential document (“Presentation”) has been prepared by EMED Mining Public Limited (the “Company”). While the information
contained herein has been prepared in good faith, neither the Company nor any of its shareholders, directors, officers, agents, employees or advisers give, have given or
have authority to give, any representations or warranties (express or implied) as to, or in relation to, the accuracy, reliability or completeness of the information in this
Presentation, or any revision thereof, or of any other written or oral information made or to be made available to any interested party or its advisers (all such information
being referred to as “Information”) and liability therefore is expressly disclaimed. Accordingly, neither the Company nor any of its shareholders, directors, officers, agents,
employees or advisers take any responsibility for, or will accept any liability whether direct or indirect, express or implied, contractual, tortious, statutory or otherwise, in
respect of, the accuracy or completeness of the Information or for any of the opinions contained herein or for any errors, omissions or misstatements or for any loss,
howsoever arising, from the use of this Presentation.
Neither the issue of this Presentation nor any part of its contents is to be taken as any form of commitment on the part of the Company to proceed with any transaction and
the right is reserved to terminate any discussions or negotiations with any prospective investors. In no circumstances will the Company be responsible for any costs, losses or
expenses incurred in connection with any appraisal or investigation of the Company. In furnishing this Presentation, the Company does not undertake or agree to any
obligation to provide the recipient with access to any additional information or to update this Presentation or to correct any inaccuracies in, or omissions from, this
Presentation which may become apparent.
This Presentation should not be considered as the giving of investment advice by the Company or any of its shareholders, directors, officers, agents, employees or advisers.
In particular, this Presentation does not constitute an offer or invitation to subscribe for or purchase any securities and neither this Presentation nor anything contained
herein shall form the basis of any contract or commitment whatsoever. Each party to whom this Presentation is made available must make its own independent assessment
of the Company after making such investigations and taking such advice as may be deemed necessary. In particular, any estimates or projections or opinions contained
herein necessarily involve significant elements of subjective judgment, analysis and assumptions and each recipient should satisfy itself in relation to such matters.
This Presentation contains “forward looking information” which may include, but is not limited to, statements with respect to the future financial or operating performance
of the Company, its subsidiaries and its projects, the future price of metals, the estimation of ore reserves and resources, the conversion of estimated resources into
reserves, the realisation of ore reserve estimates, the timing and amount of estimated future production, costs of production, capital, operating and exploration
expenditures, costs and timing of the development of new deposits, costs and timing of future exploration, requirements for additional capital, government regulation of
mining operations, environmental risks, reclamation expenses, title disputes or claims, limitations of insurance coverage and the timing and possible outcome of pending
litigation and regulatory matters.
Forward looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the
Company and/or its subsidiaries to be materially different from any future results, performance or achievements expressed or implied by the forward looking statements.
Such factors include, among others, general business, economic, competitive, political and social uncertainties; the actual results of current exploration activities; actual
results of reclamation activities; conclusions of economic evaluations; changes in project parameters as plans continue to be refined; future prices of metals; the future
costs of capital to the Company; possible variations of ore grade or recovery rates; failure of plant, equipment or processes to operate as anticipated; accidents, labour
disputes and other risks of the mining industry; political instability, terrorist attacks, insurrection or war; delays in obtaining governmental approvals or financing or in the
completion of development or construction activities, as well as those factors discussed in the section entitled “Risk Factors” in the Company’s annual information form
dated 30 March 2012.
Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward
looking statements, there may be other factors that cause actions, events or results to differ from those anticipated, estimated or intended. Forward looking statements
contained herein are made as of the date of this Presentation and the Company disclaims any obligation to update any forward looking statements, whether as a result of
new information, future events or results or otherwise. There can be no assurance that forward looking statements will prove to be accurate, as actual results and future
events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward looking statements.
INVESTMENT HIGHLIGHTS
100% ownership of the Rio Tinto Copper Project.
World’s largest VMS system, no drilling for 25 years
Fully equipped site with operating history .
Est. start-up cost $252M with C3 costs of $1.90/lb
Cu for base case restart on the 0.5%/t Cu open pit.
Mandated $225M project financing package,
linked to product off-take to minimise equity dilution
Strong government and community support.
Strong shareholders, board and management
At execution stage for permitting & financing for
start construction H2-13 and production H2-14
Targeting progressive restart of the field
including higher-grade underground mines
3
EXCELLENCE IN
MINING, EXPLORATION AND DEVELOPMENT
• IPO 2005: to develop Cu-Au properties in Europe
• Assets:
– one of the largest Cu projects in Europe, within the largest VMS system in the world
– a large Au deposit in Slovakia
• Current Focus: to restart one of the mines at Rio Tinto Copper Project in Andalucia
• Next Projects: other mines at Rio Tinto in Spain, Slovakia & Cyprus
4
PROJECTS
5
CYPRUS
SPAIN
SLOVAKIA
RIO TINTO
Mediterranean Sea
Black Sea
Bay of Biscay
BIELY VRCH
KLIROU
SUMMARY AND STATUS
6
Market Cap
vs NPV
• Market cap US$234M (£151M) vs NPV10% US$286M-US$633M of Base Case
for the first mine restart at Rio Tinto Copper Project, at $3.00-4.00/lb Cu
2013 Inflection
Points
in Spain*
• Engineering: updated 43-101 in Feb 2013
• Financing: have mandated product-linked financings with Goldman
Sachs (debt) and Xiangguang + Red Kite (equity and debt)
• Permitting Timelines:
• H1: Environmental Plan (AAU) & Administrative Standing (AS)
• Allowing commencement of site preliminary works (Pre-Works)
• H2: Final Restoration Plan (FRP) & Project Approval (Mining Permit)
• Allowing full start-up works (refurbishment and commissioning)
Team in Place
• Shareholders, financiers, board, senior management
• Supportive mining communities, local contractors and consultants
Solid Platform
and Pipeline of
Growth Projects
• Base Case for near term start of cash flow
• Potential brownfields copper mines next to the main mine in Spain
• Slovak Gold deposit has received initial approval of Mining Lease Area
* Represents Company’s best estimate on timing
EMED MINING: 2005 TO 2012
$6M IPO on
AIM with initial
Cu exploration
program only
in Cyprus
Started gold
exploration in
Slovakia
Gold discovery in
Slovakia
Acquired an
option over Rio
Tinto Copper Mine
Overcame
litigation and
acquired 100%
of the Rio Tinto
Copper District
Managed
through the GFC
by refining
projects and
finance structure
Rio Tinto
permit
applications
for original
land footprint
Rio Tinto
permit
applications
adjusted for
enlarged land
footprint
7
2005 2006 2007 2008 2009 2010 2011
IPO
on TSX
2012
Completed
consolidation of all land
for restart and expansion
at Rio Tinto
Permit processes
for restart target
production H2-14
and base case
production at end-
2015
RIO TINTO: MAJOR COPPER MINING FIELD
• 100% ownership of assets, including the
Cerro Colorado deposit, processing
facilities and all project lands owned or
under option
• Last operated in 2001 and was put on
care and maintenance due to then-
prevailing low Cu prices
• Excellent infrastructure in place:
– Access to towns, roads, port, power & water
– Only 75 km from Freeport McMoRan’s
Atlantic Cu smelter
8
SPAIN
Rio Tinto
SPAIN
EXCELLENT INFRASTRUCTURE IN PLACE
9
TAILINGS DEPOSIT
PRIMARY CRUSHER
SECONDARY &
TERTIARY CRUSHING
GRINDING AREA
FLOTATION AREA THICKENER
RESERVES & RESOURCES
Cerro Colorado Open Pit
10
RESERVES Mt Cu% Cu ‘000t
Proved 39 0.38 148
Probable 84 0.54 458
TOTAL Ore Reserves 123 0.49 606
RESOURCES Mt Cu% Cu ‘000t
Measured 48 0.38 179
Indicated 155 0.49 754
TOTAL Measured &
Indicated Resources
203 0.46 933
Inferred 2 0.50 10
Source: Behre Dolbear NI 43-101 Technical Report issued February 2013 and based on a 0.2% cut-off grade
RIO TINTO MINE COPPER PROJECT
“GROWTH AGENDA” TASKS FOR 2013, SO AS TO
RE-ESTABLISH RIO TINTO AS A MINING DISTRICT
Cerro Colorado Pit, initial target increased reserves
Drilling programs commence on permitting. No drilling below 250 meters & open
San Dionisio & San Antonio Mines , evaluate these higher grade deposits
Validate and interpret database under today’s standards and economics
Tailings Reprocessing Joint Venture, evaluate treatment of precious metal
Metallurgical testing and engineering programs to commence in 2013
11
Rio Tinto is the world’s largest VMS system.
Historical production 1.7Mt Cu, 3.4Moz Au and 56Moz Ag.
No exploration for 25 years.
BASE CASE for first mine to be redeveloped –
Cerro Colorado Open Pit
Base Case $3.00/lb $3.50/lb $4.00/lb
Operating cash flow (pre-tax) $Mpa 106 135 173
Project NPV US$M at
- discount rate 10%
- discount rate 7.5%
286
378
427
545
633
786
12
1. Base Case assumes extraction of existing ore reserves at 9Mtpa only over 14 years. Target Case 15Mtpa.
2. NPV is after deducting project acquisition costs (which is $142M in the $3.50 case) paid out of future cash
flows and $91M of site improvement and closure costs.
3. Scenarios under $3.50/lb assume 50% of Base Case of years 2-7 are hedged at circa $3.50/lb.
4. Operating Costs (C1): assumed $1.56/lb
5. Capital, Operating and Closure Costs (C3): assumed $1.90/lb
6. Estimates independently reviewed in accordance with Behre Dolbear NI 43-101 Technical Report issued in
February 2013
STEPS TO START UP 9MTPA PRODUCTION
WHILST DRILLING TO EXPAND ORE RESERVES
13
Environmental Plans (AAU)
Administrative Standing of
Mineral Rights (AS)
Environmental Bonding
Project Finance and
Product Off take
Bankable Engineering &
Technical Studies
Production Planning and
Expansion Studies
Operations Development
Operating Licences
Phase 1 Project Execution
to start up at 5Mpta ***
Phase 2 Project Execution
& Commissioning to 9Mtpa
2012 2013 2014 2015
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Documentation, D. Diligence, Closing
Feasibility Studies
Capex, Opex, Schedule.
Production Planning to 9Mtpa , Drilling,
Expansion Studies beyond 9Mtpa
Systems, Contracting, Recruitment & Training
Operating Licenses are processed in parallel with project execution works
Phase 1: 3 months Pre-Works
and 9 months Refurbishment
Phase 2 Production commissioning and ramp-up
Final Restoration Plan (FRP)
Project (Mining Permit)
Environment Plans (AAU): await approval.
Everything has been submitted.
Project already cleared by IGME. CEDEX
requires further due diligence on tailings
Flows from Restoration Plan.
Administrative Standing: we
believe we have met the Legal,
Technical and EconomicTests
Flows from AAU Approval
Drilling to increase
Resource/Reserve
Target to Increase Reserves on Open Pit to trigger production higher than 9Mtpa
Target to report Resources on higher-grade underground mine/s
*** the triggering of Phase 1 depends on the timing of formal confirmation of permits and finance
THIS SYMBOL DENOTES THE EXPECTED TIMING
OF FINAL FORMAL APPROVAL.
FOR INSTANCE, WITH THE AAU THE PUBLIC
COMMENT PERIOD HAS BEEN CONCLUDED.
ALSO THE REGULATORS HAVE ADVISED DRAFT
CONDITIONS OF APPROVAL OF AS AND AAU
AND WE AWAIT THE GAZETTING OF APPROVALS.
SUBJECT TO FINANCE, PHASE 1 PRE-WORKS CAN
PROCEED AFTER FORMAL APPROVAL OF AAU
AND AS AND FULL PHASE 1 START-UP WORKS
CAN PROCEED UPON FORMAL APPROVAL OF
FRP AND MINING PERMIT.
FINANCE STRATEGY
14
USES OF FUNDS US$M
Repairs, plant improvements, contingency and activities prior to cash-flow generation 189
Bonding for environmental and social (this is finalised after approval of the FRP) 29
Counterparty Settlements 20
Working capital 14
TOTAL 252
All estimates in accordance with Behre Dolbear NI 43-101 Technical Report issued February 2013
Planned working capital together with finance facilities being designed with Goldman
Sachs, Xiangguang and Red Kite potentially covers $252M when “fully-bankable”.
This project start-up finance plan assumes $27M of additional capital is arranged
from non-debt (off-take-linked, royalty linked or ordinary equity) sources by mid-2013.
15
GROWTH PIPELINE
– To optimise open pit
resources for higher gold
prices
– To consider the impact of
potentially higher gold prices
on the economics of deeper
zones of mineralisation
– To keep testing Hodrusa Field
– To re-start drilling after
addressing higher
priorities elsewhere
Slovakia, plan to develop
1M oz gold discovery:
Cyprus, potential for
economic discoveries
DETVA
GROWTH
RIO TINTO
CYPRUS
– To optimise open pit reserves of 123 Mt
for copper price higher than $2/lb
– To convert more of 203 Mt open pit
resources to reserves
– To increase open pit resources of 203 Mt
– To test potential to recycle tailings
Spain, plan to restart the whole Rio Tinto mining field:
– To re-evaluate the San Dyonisio and San
Antonio higher-grade underground mines
– To test other deposits RTZ reported on the
company’s Rio Tinto Mine property
– To test targets on one or more of the
surrounding mineral concessions
Gold Project
100%
Copper Project
100%
Copper
95%
ONE OF BEST PERFORMING COPPER SECTOR
SHARES OVER THE LAST 2 YEARS
Relative Share Performance Since December 17, 2010 – Copper Developers and Producers
The sector performed poorly in 2012 in stock market terms
EMED has outperformed the majority of TSX and TSXV listed copper exploration, development and
producing companies since the TSX IPO in December 2010
Source: Capital IQ, as of February 21, 2013
-94%
-92%
-90%
-88%
-85%
-82%
-79%
-78%
-76%
-76%
-74%
-74%
-73%
-68%
-65%
-60%
-59%
-58%
-57%
-49%
-48%
-48%
-46%
-43%
-42%
-40%
-36%
-34%
-33%
-33%
-31%
-30%
-25%
-16%
-11%
-7%
7%
8%
37%
69%
110%
111%
Baja
AQM
Intrepid
Mercator
Hana
Coro
International PBX
Copper One
Northern Dynasty
CuOro
Constantine
Sarengeti
Ivanhoe
Thundermin
Candente
VMS Ventures
Los Andes
Duran
Western Copper
Copper Mountain
Capstone
Median
HudBay
Amerigo
Polymet
Taseko
Augusta
Yellowhead
Abacus
Lundin
Redhawk
Katanga
Duluth
First Quantum
Inmet
Nevada Copper
Copper Fox
Imperial
EMED
Panoro
Lumina
NGEx
SUMMARY REGISTER OF SHAREHOLDERS
FULLY-DILUTED 1,252M SHARES ON ISSUE AT 31 DECEMBER 2012
OVER 5% OF THE OWNERSHIP IS BASED IN ANDALUCIA, SPAIN
17
Board and Management 6%
Resource Capital Funds
(USA/Australia, mining investor)
13%
Yanggu Xiangguang Copper Co. Ltd.
(strategic investor and off-take customer)
11%
RBC Asset Management
(Canada, institutional investor)
8%
Rand Merchant Bank
(UK/Australia, mining bank)
5%
Red Kite
(USA, metals trader and financier)
5%
Rumbo 5 Cero
(Andalucia, Spain. Investment group)
4%
Astor Holdings, formerly MRI Group
(Switzerland, metals trader and financier)
3%
Approx. 25 other shareholders owning > 0.5% of shares 33%
Approx. 800 other shareholders owning < 0.5% of shares
Many of these holders are broker nominee accounts on behalf of others
12%
Ronnie Beevor - Non-Executive Chairman
Director of several mining companies
Former MD, investment banking, Rothschild Australia
DIRECTORS
18
NON-EXECUTIVE DIRECTORS
Harry Anagnostaras-Adams - Managing Director
John Leach - Finance Director
Jasper Bertisen
Principal of Resource Capital Funds and engineer
Roger Davey
Mining Company director and former Senior Mining Engineer at Rothschild
Bob Francis
Former senior partner of Deloitte & Touche specialising in mining
Harry Liu
Vice President Xiangguang responsible for corporate development
Ashwath Mehra
CEO of Astor Group and commodities trader
Jose Sierra
30 years minerals policy & regulation, Spain (Director-General Mines) and EU
DIRECTORS & SENIOR MANAGEMENT
Harry Anagnostaras-Adams - Managing Director
Founder of EMED Mining
Serves (or has served) as non-executive Director of many other
public and private companies
Demetrios Constantinides - External Relations
30 years experience in private and government roles in Europe
Ron Cunneen - Group Geologist
Over 25 years exploration, start-up and operational experience
Bill Enrico - Chief Operating Officer
20 years general management start-up and operational experience
John Leach - Finance Director
30 years experience in senior financial and executive positions
within the mining industry
Rob Williams - Group Development
20 years project start-up and management experience
19
SENIOR MANAGEMENT
A I M : E M E D T S X : E M D
Presentation 21 March 2013 Presentation at Proactive Conference

More Related Content

What's hot

February 2015 investor presentation
February 2015 investor presentationFebruary 2015 investor presentation
February 2015 investor presentationFalcoCorporate
 
Mao marketing-presentation-june2013
Mao marketing-presentation-june2013Mao marketing-presentation-june2013
Mao marketing-presentation-june2013Company Spotlight
 
Corporate presentation-june-30-2016
Corporate presentation-june-30-2016Corporate presentation-june-30-2016
Corporate presentation-june-30-2016Adnet Communications
 
January 2015 Investor Presentation
January 2015 Investor PresentationJanuary 2015 Investor Presentation
January 2015 Investor PresentationFalcoCorporate
 
Corporate Presentation June 2013
Corporate Presentation June 2013Corporate Presentation June 2013
Corporate Presentation June 2013pacificcoal
 
Rambler Metals & Mining Investor Roadshow
Rambler Metals & Mining Investor RoadshowRambler Metals & Mining Investor Roadshow
Rambler Metals & Mining Investor Roadshowsparky263
 
Iberian Investors Presentation August 2009
Iberian Investors Presentation August 2009Iberian Investors Presentation August 2009
Iberian Investors Presentation August 2009Iberian Minerals Corp.
 
Kombat Copper AGM 2015 Presentation
Kombat Copper AGM 2015 PresentationKombat Copper AGM 2015 Presentation
Kombat Copper AGM 2015 PresentationKombat_Copper
 
30.2 falco presentation rbc august 2017 100dpi
30.2 falco presentation   rbc august 2017 100dpi30.2 falco presentation   rbc august 2017 100dpi
30.2 falco presentation rbc august 2017 100dpiFalcoCorporate
 
30.3 falco presentation osisko days - sept 2017 125dpi
30.3 falco presentation   osisko days - sept 2017 125dpi30.3 falco presentation   osisko days - sept 2017 125dpi
30.3 falco presentation osisko days - sept 2017 125dpiFalcoCorporate
 
Highbank Appoints Ivan Scott, P. Eng. to the Board of Directors
Highbank Appoints Ivan Scott, P. Eng. to the Board of DirectorsHighbank Appoints Ivan Scott, P. Eng. to the Board of Directors
Highbank Appoints Ivan Scott, P. Eng. to the Board of DirectorsFollow me on Twitter @Stockshaman
 
HEVI Oil Exploration and Production Presentation
HEVI Oil Exploration and Production PresentationHEVI Oil Exploration and Production Presentation
HEVI Oil Exploration and Production Presentationheavyearthresources
 
January 2015 - Corporate Presentation
January 2015 - Corporate PresentationJanuary 2015 - Corporate Presentation
January 2015 - Corporate PresentationFalcoCorporate
 
First mountain presentation
First mountain presentationFirst mountain presentation
First mountain presentationfizakousar
 
140724 rab sample short diff font
140724 rab sample short diff font140724 rab sample short diff font
140724 rab sample short diff fontsparky263
 
2015 Broken Hill Resources Investment Symposium - Broken Hill Prospecting (AS...
2015 Broken Hill Resources Investment Symposium - Broken Hill Prospecting (AS...2015 Broken Hill Resources Investment Symposium - Broken Hill Prospecting (AS...
2015 Broken Hill Resources Investment Symposium - Broken Hill Prospecting (AS...Symposium
 
Lion One Metals Presentation Jan 2022
Lion One Metals Presentation Jan 2022Lion One Metals Presentation Jan 2022
Lion One Metals Presentation Jan 2022Joe Gray
 

What's hot (18)

February 2015 investor presentation
February 2015 investor presentationFebruary 2015 investor presentation
February 2015 investor presentation
 
Mao marketing-presentation-june2013
Mao marketing-presentation-june2013Mao marketing-presentation-june2013
Mao marketing-presentation-june2013
 
Corporate presentation-june-30-2016
Corporate presentation-june-30-2016Corporate presentation-june-30-2016
Corporate presentation-june-30-2016
 
January 2015 Investor Presentation
January 2015 Investor PresentationJanuary 2015 Investor Presentation
January 2015 Investor Presentation
 
Corporate Presentation June 2013
Corporate Presentation June 2013Corporate Presentation June 2013
Corporate Presentation June 2013
 
Rambler Metals & Mining Investor Roadshow
Rambler Metals & Mining Investor RoadshowRambler Metals & Mining Investor Roadshow
Rambler Metals & Mining Investor Roadshow
 
Iberian Investors Presentation August 2009
Iberian Investors Presentation August 2009Iberian Investors Presentation August 2009
Iberian Investors Presentation August 2009
 
Kombat Copper AGM 2015 Presentation
Kombat Copper AGM 2015 PresentationKombat Copper AGM 2015 Presentation
Kombat Copper AGM 2015 Presentation
 
30.2 falco presentation rbc august 2017 100dpi
30.2 falco presentation   rbc august 2017 100dpi30.2 falco presentation   rbc august 2017 100dpi
30.2 falco presentation rbc august 2017 100dpi
 
Highbank Appoints Hans Smit, P. Geo. To Its Advisory Board
Highbank Appoints Hans Smit, P. Geo. To Its Advisory BoardHighbank Appoints Hans Smit, P. Geo. To Its Advisory Board
Highbank Appoints Hans Smit, P. Geo. To Its Advisory Board
 
30.3 falco presentation osisko days - sept 2017 125dpi
30.3 falco presentation   osisko days - sept 2017 125dpi30.3 falco presentation   osisko days - sept 2017 125dpi
30.3 falco presentation osisko days - sept 2017 125dpi
 
Highbank Appoints Ivan Scott, P. Eng. to the Board of Directors
Highbank Appoints Ivan Scott, P. Eng. to the Board of DirectorsHighbank Appoints Ivan Scott, P. Eng. to the Board of Directors
Highbank Appoints Ivan Scott, P. Eng. to the Board of Directors
 
HEVI Oil Exploration and Production Presentation
HEVI Oil Exploration and Production PresentationHEVI Oil Exploration and Production Presentation
HEVI Oil Exploration and Production Presentation
 
January 2015 - Corporate Presentation
January 2015 - Corporate PresentationJanuary 2015 - Corporate Presentation
January 2015 - Corporate Presentation
 
First mountain presentation
First mountain presentationFirst mountain presentation
First mountain presentation
 
140724 rab sample short diff font
140724 rab sample short diff font140724 rab sample short diff font
140724 rab sample short diff font
 
2015 Broken Hill Resources Investment Symposium - Broken Hill Prospecting (AS...
2015 Broken Hill Resources Investment Symposium - Broken Hill Prospecting (AS...2015 Broken Hill Resources Investment Symposium - Broken Hill Prospecting (AS...
2015 Broken Hill Resources Investment Symposium - Broken Hill Prospecting (AS...
 
Lion One Metals Presentation Jan 2022
Lion One Metals Presentation Jan 2022Lion One Metals Presentation Jan 2022
Lion One Metals Presentation Jan 2022
 

Viewers also liked

The Art of Responding to Reviews
The Art of Responding to ReviewsThe Art of Responding to Reviews
The Art of Responding to ReviewsGlassdoor
 
Paginas de matematicas
Paginas de matematicasPaginas de matematicas
Paginas de matematicasespanol
 
A Guide to SlideShare Analytics - Excerpts from Hubspot's Step by Step Guide ...
A Guide to SlideShare Analytics - Excerpts from Hubspot's Step by Step Guide ...A Guide to SlideShare Analytics - Excerpts from Hubspot's Step by Step Guide ...
A Guide to SlideShare Analytics - Excerpts from Hubspot's Step by Step Guide ...SlideShare
 
2015 Upload Campaigns Calendar - SlideShare
2015 Upload Campaigns Calendar - SlideShare2015 Upload Campaigns Calendar - SlideShare
2015 Upload Campaigns Calendar - SlideShareSlideShare
 
What to Upload to SlideShare
What to Upload to SlideShareWhat to Upload to SlideShare
What to Upload to SlideShareSlideShare
 
How to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & TricksHow to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & TricksSlideShare
 
Getting Started With SlideShare
Getting Started With SlideShareGetting Started With SlideShare
Getting Started With SlideShareSlideShare
 

Viewers also liked (7)

The Art of Responding to Reviews
The Art of Responding to ReviewsThe Art of Responding to Reviews
The Art of Responding to Reviews
 
Paginas de matematicas
Paginas de matematicasPaginas de matematicas
Paginas de matematicas
 
A Guide to SlideShare Analytics - Excerpts from Hubspot's Step by Step Guide ...
A Guide to SlideShare Analytics - Excerpts from Hubspot's Step by Step Guide ...A Guide to SlideShare Analytics - Excerpts from Hubspot's Step by Step Guide ...
A Guide to SlideShare Analytics - Excerpts from Hubspot's Step by Step Guide ...
 
2015 Upload Campaigns Calendar - SlideShare
2015 Upload Campaigns Calendar - SlideShare2015 Upload Campaigns Calendar - SlideShare
2015 Upload Campaigns Calendar - SlideShare
 
What to Upload to SlideShare
What to Upload to SlideShareWhat to Upload to SlideShare
What to Upload to SlideShare
 
How to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & TricksHow to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & Tricks
 
Getting Started With SlideShare
Getting Started With SlideShareGetting Started With SlideShare
Getting Started With SlideShare
 

Similar to Emed presentation 21-march_at_proactive_conference

Corporate Presentation_June 21, 2013
Corporate Presentation_June 21, 2013Corporate Presentation_June 21, 2013
Corporate Presentation_June 21, 2013FirstQuantum
 
Corporate Presentation
Corporate PresentationCorporate Presentation
Corporate PresentationFirstQuantum
 
1 g goviex corporate presentation_feb2022_final
1 g goviex corporate presentation_feb2022_final1 g goviex corporate presentation_feb2022_final
1 g goviex corporate presentation_feb2022_finalAdnet Communications
 
Govi ex uranium corporate presentation sep2021
Govi ex uranium corporate presentation sep2021Govi ex uranium corporate presentation sep2021
Govi ex uranium corporate presentation sep2021Adnet Communications
 
GoviEx Corporate Presentation --- May 2021
GoviEx Corporate Presentation --- May 2021GoviEx Corporate Presentation --- May 2021
GoviEx Corporate Presentation --- May 2021Adnet Communications
 
Govi ex presentation february 2021 v4 - feb 23, 21
Govi ex presentation february 2021 v4 - feb 23, 21Govi ex presentation february 2021 v4 - feb 23, 21
Govi ex presentation february 2021 v4 - feb 23, 21AdnetNew
 
Govi ex presentation may 2021
Govi ex presentation may 2021Govi ex presentation may 2021
Govi ex presentation may 2021AdnetNew
 
Govi ex presentation may 19 2021
Govi ex presentation may 19 2021Govi ex presentation may 19 2021
Govi ex presentation may 19 2021AdnetNew
 
GoviEx Corporate Presentation (October 2021)
GoviEx Corporate Presentation (October 2021)GoviEx Corporate Presentation (October 2021)
GoviEx Corporate Presentation (October 2021)Adnet Communications
 
Govi ex presentation february 2021
Govi ex presentation february 2021Govi ex presentation february 2021
Govi ex presentation february 2021AdnetNew
 
GoviEx Uranium Corporate Presentation
GoviEx Uranium Corporate PresentationGoviEx Uranium Corporate Presentation
GoviEx Uranium Corporate PresentationAdnetNew
 
Govi ex presentation march 2021
Govi ex presentation march 2021Govi ex presentation march 2021
Govi ex presentation march 2021AdnetNew
 
Govi ex presentation march 2021
Govi ex presentation march 2021Govi ex presentation march 2021
Govi ex presentation march 2021AdnetNew
 
GoviEx Uranium October 2020 Presentation
GoviEx Uranium October 2020 PresentationGoviEx Uranium October 2020 Presentation
GoviEx Uranium October 2020 PresentationAdnet Communications
 
Govi ex corporate presentation november 2021after q3_fin
Govi ex corporate presentation november 2021after q3_finGovi ex corporate presentation november 2021after q3_fin
Govi ex corporate presentation november 2021after q3_finAdnetNew
 
Govi ex presentation january 2021
Govi ex presentation january 2021Govi ex presentation january 2021
Govi ex presentation january 2021AdnetNew
 
GoviEx Uranium June 2020 Presentation
GoviEx Uranium June 2020 PresentationGoviEx Uranium June 2020 Presentation
GoviEx Uranium June 2020 PresentationAdnet Communications
 
GoviEX Uranium Inc. - Corporate Presentation (February 2022)
GoviEX Uranium Inc. - Corporate Presentation (February 2022)GoviEX Uranium Inc. - Corporate Presentation (February 2022)
GoviEX Uranium Inc. - Corporate Presentation (February 2022)Adnet Communications
 
LEADING HYDRO SUSTAINABILITY THROUGH TECHNOLOGY
LEADING HYDRO SUSTAINABILITY THROUGH TECHNOLOGYLEADING HYDRO SUSTAINABILITY THROUGH TECHNOLOGY
LEADING HYDRO SUSTAINABILITY THROUGH TECHNOLOGYiQHub
 

Similar to Emed presentation 21-march_at_proactive_conference (20)

Corporate Presentation_June 21, 2013
Corporate Presentation_June 21, 2013Corporate Presentation_June 21, 2013
Corporate Presentation_June 21, 2013
 
Corporate Presentation
Corporate PresentationCorporate Presentation
Corporate Presentation
 
1 g goviex corporate presentation_feb2022_final
1 g goviex corporate presentation_feb2022_final1 g goviex corporate presentation_feb2022_final
1 g goviex corporate presentation_feb2022_final
 
Goviex presentation august_2021
Goviex presentation august_2021Goviex presentation august_2021
Goviex presentation august_2021
 
Govi ex uranium corporate presentation sep2021
Govi ex uranium corporate presentation sep2021Govi ex uranium corporate presentation sep2021
Govi ex uranium corporate presentation sep2021
 
GoviEx Corporate Presentation --- May 2021
GoviEx Corporate Presentation --- May 2021GoviEx Corporate Presentation --- May 2021
GoviEx Corporate Presentation --- May 2021
 
Govi ex presentation february 2021 v4 - feb 23, 21
Govi ex presentation february 2021 v4 - feb 23, 21Govi ex presentation february 2021 v4 - feb 23, 21
Govi ex presentation february 2021 v4 - feb 23, 21
 
Govi ex presentation may 2021
Govi ex presentation may 2021Govi ex presentation may 2021
Govi ex presentation may 2021
 
Govi ex presentation may 19 2021
Govi ex presentation may 19 2021Govi ex presentation may 19 2021
Govi ex presentation may 19 2021
 
GoviEx Corporate Presentation (October 2021)
GoviEx Corporate Presentation (October 2021)GoviEx Corporate Presentation (October 2021)
GoviEx Corporate Presentation (October 2021)
 
Govi ex presentation february 2021
Govi ex presentation february 2021Govi ex presentation february 2021
Govi ex presentation february 2021
 
GoviEx Uranium Corporate Presentation
GoviEx Uranium Corporate PresentationGoviEx Uranium Corporate Presentation
GoviEx Uranium Corporate Presentation
 
Govi ex presentation march 2021
Govi ex presentation march 2021Govi ex presentation march 2021
Govi ex presentation march 2021
 
Govi ex presentation march 2021
Govi ex presentation march 2021Govi ex presentation march 2021
Govi ex presentation march 2021
 
GoviEx Uranium October 2020 Presentation
GoviEx Uranium October 2020 PresentationGoviEx Uranium October 2020 Presentation
GoviEx Uranium October 2020 Presentation
 
Govi ex corporate presentation november 2021after q3_fin
Govi ex corporate presentation november 2021after q3_finGovi ex corporate presentation november 2021after q3_fin
Govi ex corporate presentation november 2021after q3_fin
 
Govi ex presentation january 2021
Govi ex presentation january 2021Govi ex presentation january 2021
Govi ex presentation january 2021
 
GoviEx Uranium June 2020 Presentation
GoviEx Uranium June 2020 PresentationGoviEx Uranium June 2020 Presentation
GoviEx Uranium June 2020 Presentation
 
GoviEX Uranium Inc. - Corporate Presentation (February 2022)
GoviEX Uranium Inc. - Corporate Presentation (February 2022)GoviEX Uranium Inc. - Corporate Presentation (February 2022)
GoviEX Uranium Inc. - Corporate Presentation (February 2022)
 
LEADING HYDRO SUSTAINABILITY THROUGH TECHNOLOGY
LEADING HYDRO SUSTAINABILITY THROUGH TECHNOLOGYLEADING HYDRO SUSTAINABILITY THROUGH TECHNOLOGY
LEADING HYDRO SUSTAINABILITY THROUGH TECHNOLOGY
 

Emed presentation 21-march_at_proactive_conference

  • 1. A I M : E M E D T S X : E M D Presentation 21 March 2013 Presentation at Proactive Conference
  • 2. 2 DISCLAIMER The information contained in this confidential document (“Presentation”) has been prepared by EMED Mining Public Limited (the “Company”). While the information contained herein has been prepared in good faith, neither the Company nor any of its shareholders, directors, officers, agents, employees or advisers give, have given or have authority to give, any representations or warranties (express or implied) as to, or in relation to, the accuracy, reliability or completeness of the information in this Presentation, or any revision thereof, or of any other written or oral information made or to be made available to any interested party or its advisers (all such information being referred to as “Information”) and liability therefore is expressly disclaimed. Accordingly, neither the Company nor any of its shareholders, directors, officers, agents, employees or advisers take any responsibility for, or will accept any liability whether direct or indirect, express or implied, contractual, tortious, statutory or otherwise, in respect of, the accuracy or completeness of the Information or for any of the opinions contained herein or for any errors, omissions or misstatements or for any loss, howsoever arising, from the use of this Presentation. Neither the issue of this Presentation nor any part of its contents is to be taken as any form of commitment on the part of the Company to proceed with any transaction and the right is reserved to terminate any discussions or negotiations with any prospective investors. In no circumstances will the Company be responsible for any costs, losses or expenses incurred in connection with any appraisal or investigation of the Company. In furnishing this Presentation, the Company does not undertake or agree to any obligation to provide the recipient with access to any additional information or to update this Presentation or to correct any inaccuracies in, or omissions from, this Presentation which may become apparent. This Presentation should not be considered as the giving of investment advice by the Company or any of its shareholders, directors, officers, agents, employees or advisers. In particular, this Presentation does not constitute an offer or invitation to subscribe for or purchase any securities and neither this Presentation nor anything contained herein shall form the basis of any contract or commitment whatsoever. Each party to whom this Presentation is made available must make its own independent assessment of the Company after making such investigations and taking such advice as may be deemed necessary. In particular, any estimates or projections or opinions contained herein necessarily involve significant elements of subjective judgment, analysis and assumptions and each recipient should satisfy itself in relation to such matters. This Presentation contains “forward looking information” which may include, but is not limited to, statements with respect to the future financial or operating performance of the Company, its subsidiaries and its projects, the future price of metals, the estimation of ore reserves and resources, the conversion of estimated resources into reserves, the realisation of ore reserve estimates, the timing and amount of estimated future production, costs of production, capital, operating and exploration expenditures, costs and timing of the development of new deposits, costs and timing of future exploration, requirements for additional capital, government regulation of mining operations, environmental risks, reclamation expenses, title disputes or claims, limitations of insurance coverage and the timing and possible outcome of pending litigation and regulatory matters. Forward looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company and/or its subsidiaries to be materially different from any future results, performance or achievements expressed or implied by the forward looking statements. Such factors include, among others, general business, economic, competitive, political and social uncertainties; the actual results of current exploration activities; actual results of reclamation activities; conclusions of economic evaluations; changes in project parameters as plans continue to be refined; future prices of metals; the future costs of capital to the Company; possible variations of ore grade or recovery rates; failure of plant, equipment or processes to operate as anticipated; accidents, labour disputes and other risks of the mining industry; political instability, terrorist attacks, insurrection or war; delays in obtaining governmental approvals or financing or in the completion of development or construction activities, as well as those factors discussed in the section entitled “Risk Factors” in the Company’s annual information form dated 30 March 2012. Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward looking statements, there may be other factors that cause actions, events or results to differ from those anticipated, estimated or intended. Forward looking statements contained herein are made as of the date of this Presentation and the Company disclaims any obligation to update any forward looking statements, whether as a result of new information, future events or results or otherwise. There can be no assurance that forward looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward looking statements.
  • 3. INVESTMENT HIGHLIGHTS 100% ownership of the Rio Tinto Copper Project. World’s largest VMS system, no drilling for 25 years Fully equipped site with operating history . Est. start-up cost $252M with C3 costs of $1.90/lb Cu for base case restart on the 0.5%/t Cu open pit. Mandated $225M project financing package, linked to product off-take to minimise equity dilution Strong government and community support. Strong shareholders, board and management At execution stage for permitting & financing for start construction H2-13 and production H2-14 Targeting progressive restart of the field including higher-grade underground mines 3
  • 4. EXCELLENCE IN MINING, EXPLORATION AND DEVELOPMENT • IPO 2005: to develop Cu-Au properties in Europe • Assets: – one of the largest Cu projects in Europe, within the largest VMS system in the world – a large Au deposit in Slovakia • Current Focus: to restart one of the mines at Rio Tinto Copper Project in Andalucia • Next Projects: other mines at Rio Tinto in Spain, Slovakia & Cyprus 4
  • 6. SUMMARY AND STATUS 6 Market Cap vs NPV • Market cap US$234M (£151M) vs NPV10% US$286M-US$633M of Base Case for the first mine restart at Rio Tinto Copper Project, at $3.00-4.00/lb Cu 2013 Inflection Points in Spain* • Engineering: updated 43-101 in Feb 2013 • Financing: have mandated product-linked financings with Goldman Sachs (debt) and Xiangguang + Red Kite (equity and debt) • Permitting Timelines: • H1: Environmental Plan (AAU) & Administrative Standing (AS) • Allowing commencement of site preliminary works (Pre-Works) • H2: Final Restoration Plan (FRP) & Project Approval (Mining Permit) • Allowing full start-up works (refurbishment and commissioning) Team in Place • Shareholders, financiers, board, senior management • Supportive mining communities, local contractors and consultants Solid Platform and Pipeline of Growth Projects • Base Case for near term start of cash flow • Potential brownfields copper mines next to the main mine in Spain • Slovak Gold deposit has received initial approval of Mining Lease Area * Represents Company’s best estimate on timing
  • 7. EMED MINING: 2005 TO 2012 $6M IPO on AIM with initial Cu exploration program only in Cyprus Started gold exploration in Slovakia Gold discovery in Slovakia Acquired an option over Rio Tinto Copper Mine Overcame litigation and acquired 100% of the Rio Tinto Copper District Managed through the GFC by refining projects and finance structure Rio Tinto permit applications for original land footprint Rio Tinto permit applications adjusted for enlarged land footprint 7 2005 2006 2007 2008 2009 2010 2011 IPO on TSX 2012 Completed consolidation of all land for restart and expansion at Rio Tinto Permit processes for restart target production H2-14 and base case production at end- 2015
  • 8. RIO TINTO: MAJOR COPPER MINING FIELD • 100% ownership of assets, including the Cerro Colorado deposit, processing facilities and all project lands owned or under option • Last operated in 2001 and was put on care and maintenance due to then- prevailing low Cu prices • Excellent infrastructure in place: – Access to towns, roads, port, power & water – Only 75 km from Freeport McMoRan’s Atlantic Cu smelter 8 SPAIN Rio Tinto SPAIN
  • 9. EXCELLENT INFRASTRUCTURE IN PLACE 9 TAILINGS DEPOSIT PRIMARY CRUSHER SECONDARY & TERTIARY CRUSHING GRINDING AREA FLOTATION AREA THICKENER
  • 10. RESERVES & RESOURCES Cerro Colorado Open Pit 10 RESERVES Mt Cu% Cu ‘000t Proved 39 0.38 148 Probable 84 0.54 458 TOTAL Ore Reserves 123 0.49 606 RESOURCES Mt Cu% Cu ‘000t Measured 48 0.38 179 Indicated 155 0.49 754 TOTAL Measured & Indicated Resources 203 0.46 933 Inferred 2 0.50 10 Source: Behre Dolbear NI 43-101 Technical Report issued February 2013 and based on a 0.2% cut-off grade RIO TINTO MINE COPPER PROJECT
  • 11. “GROWTH AGENDA” TASKS FOR 2013, SO AS TO RE-ESTABLISH RIO TINTO AS A MINING DISTRICT Cerro Colorado Pit, initial target increased reserves Drilling programs commence on permitting. No drilling below 250 meters & open San Dionisio & San Antonio Mines , evaluate these higher grade deposits Validate and interpret database under today’s standards and economics Tailings Reprocessing Joint Venture, evaluate treatment of precious metal Metallurgical testing and engineering programs to commence in 2013 11 Rio Tinto is the world’s largest VMS system. Historical production 1.7Mt Cu, 3.4Moz Au and 56Moz Ag. No exploration for 25 years.
  • 12. BASE CASE for first mine to be redeveloped – Cerro Colorado Open Pit Base Case $3.00/lb $3.50/lb $4.00/lb Operating cash flow (pre-tax) $Mpa 106 135 173 Project NPV US$M at - discount rate 10% - discount rate 7.5% 286 378 427 545 633 786 12 1. Base Case assumes extraction of existing ore reserves at 9Mtpa only over 14 years. Target Case 15Mtpa. 2. NPV is after deducting project acquisition costs (which is $142M in the $3.50 case) paid out of future cash flows and $91M of site improvement and closure costs. 3. Scenarios under $3.50/lb assume 50% of Base Case of years 2-7 are hedged at circa $3.50/lb. 4. Operating Costs (C1): assumed $1.56/lb 5. Capital, Operating and Closure Costs (C3): assumed $1.90/lb 6. Estimates independently reviewed in accordance with Behre Dolbear NI 43-101 Technical Report issued in February 2013
  • 13. STEPS TO START UP 9MTPA PRODUCTION WHILST DRILLING TO EXPAND ORE RESERVES 13 Environmental Plans (AAU) Administrative Standing of Mineral Rights (AS) Environmental Bonding Project Finance and Product Off take Bankable Engineering & Technical Studies Production Planning and Expansion Studies Operations Development Operating Licences Phase 1 Project Execution to start up at 5Mpta *** Phase 2 Project Execution & Commissioning to 9Mtpa 2012 2013 2014 2015 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Documentation, D. Diligence, Closing Feasibility Studies Capex, Opex, Schedule. Production Planning to 9Mtpa , Drilling, Expansion Studies beyond 9Mtpa Systems, Contracting, Recruitment & Training Operating Licenses are processed in parallel with project execution works Phase 1: 3 months Pre-Works and 9 months Refurbishment Phase 2 Production commissioning and ramp-up Final Restoration Plan (FRP) Project (Mining Permit) Environment Plans (AAU): await approval. Everything has been submitted. Project already cleared by IGME. CEDEX requires further due diligence on tailings Flows from Restoration Plan. Administrative Standing: we believe we have met the Legal, Technical and EconomicTests Flows from AAU Approval Drilling to increase Resource/Reserve Target to Increase Reserves on Open Pit to trigger production higher than 9Mtpa Target to report Resources on higher-grade underground mine/s *** the triggering of Phase 1 depends on the timing of formal confirmation of permits and finance THIS SYMBOL DENOTES THE EXPECTED TIMING OF FINAL FORMAL APPROVAL. FOR INSTANCE, WITH THE AAU THE PUBLIC COMMENT PERIOD HAS BEEN CONCLUDED. ALSO THE REGULATORS HAVE ADVISED DRAFT CONDITIONS OF APPROVAL OF AS AND AAU AND WE AWAIT THE GAZETTING OF APPROVALS. SUBJECT TO FINANCE, PHASE 1 PRE-WORKS CAN PROCEED AFTER FORMAL APPROVAL OF AAU AND AS AND FULL PHASE 1 START-UP WORKS CAN PROCEED UPON FORMAL APPROVAL OF FRP AND MINING PERMIT.
  • 14. FINANCE STRATEGY 14 USES OF FUNDS US$M Repairs, plant improvements, contingency and activities prior to cash-flow generation 189 Bonding for environmental and social (this is finalised after approval of the FRP) 29 Counterparty Settlements 20 Working capital 14 TOTAL 252 All estimates in accordance with Behre Dolbear NI 43-101 Technical Report issued February 2013 Planned working capital together with finance facilities being designed with Goldman Sachs, Xiangguang and Red Kite potentially covers $252M when “fully-bankable”. This project start-up finance plan assumes $27M of additional capital is arranged from non-debt (off-take-linked, royalty linked or ordinary equity) sources by mid-2013.
  • 15. 15 GROWTH PIPELINE – To optimise open pit resources for higher gold prices – To consider the impact of potentially higher gold prices on the economics of deeper zones of mineralisation – To keep testing Hodrusa Field – To re-start drilling after addressing higher priorities elsewhere Slovakia, plan to develop 1M oz gold discovery: Cyprus, potential for economic discoveries DETVA GROWTH RIO TINTO CYPRUS – To optimise open pit reserves of 123 Mt for copper price higher than $2/lb – To convert more of 203 Mt open pit resources to reserves – To increase open pit resources of 203 Mt – To test potential to recycle tailings Spain, plan to restart the whole Rio Tinto mining field: – To re-evaluate the San Dyonisio and San Antonio higher-grade underground mines – To test other deposits RTZ reported on the company’s Rio Tinto Mine property – To test targets on one or more of the surrounding mineral concessions Gold Project 100% Copper Project 100% Copper 95%
  • 16. ONE OF BEST PERFORMING COPPER SECTOR SHARES OVER THE LAST 2 YEARS Relative Share Performance Since December 17, 2010 – Copper Developers and Producers The sector performed poorly in 2012 in stock market terms EMED has outperformed the majority of TSX and TSXV listed copper exploration, development and producing companies since the TSX IPO in December 2010 Source: Capital IQ, as of February 21, 2013 -94% -92% -90% -88% -85% -82% -79% -78% -76% -76% -74% -74% -73% -68% -65% -60% -59% -58% -57% -49% -48% -48% -46% -43% -42% -40% -36% -34% -33% -33% -31% -30% -25% -16% -11% -7% 7% 8% 37% 69% 110% 111% Baja AQM Intrepid Mercator Hana Coro International PBX Copper One Northern Dynasty CuOro Constantine Sarengeti Ivanhoe Thundermin Candente VMS Ventures Los Andes Duran Western Copper Copper Mountain Capstone Median HudBay Amerigo Polymet Taseko Augusta Yellowhead Abacus Lundin Redhawk Katanga Duluth First Quantum Inmet Nevada Copper Copper Fox Imperial EMED Panoro Lumina NGEx
  • 17. SUMMARY REGISTER OF SHAREHOLDERS FULLY-DILUTED 1,252M SHARES ON ISSUE AT 31 DECEMBER 2012 OVER 5% OF THE OWNERSHIP IS BASED IN ANDALUCIA, SPAIN 17 Board and Management 6% Resource Capital Funds (USA/Australia, mining investor) 13% Yanggu Xiangguang Copper Co. Ltd. (strategic investor and off-take customer) 11% RBC Asset Management (Canada, institutional investor) 8% Rand Merchant Bank (UK/Australia, mining bank) 5% Red Kite (USA, metals trader and financier) 5% Rumbo 5 Cero (Andalucia, Spain. Investment group) 4% Astor Holdings, formerly MRI Group (Switzerland, metals trader and financier) 3% Approx. 25 other shareholders owning > 0.5% of shares 33% Approx. 800 other shareholders owning < 0.5% of shares Many of these holders are broker nominee accounts on behalf of others 12%
  • 18. Ronnie Beevor - Non-Executive Chairman Director of several mining companies Former MD, investment banking, Rothschild Australia DIRECTORS 18 NON-EXECUTIVE DIRECTORS Harry Anagnostaras-Adams - Managing Director John Leach - Finance Director Jasper Bertisen Principal of Resource Capital Funds and engineer Roger Davey Mining Company director and former Senior Mining Engineer at Rothschild Bob Francis Former senior partner of Deloitte & Touche specialising in mining Harry Liu Vice President Xiangguang responsible for corporate development Ashwath Mehra CEO of Astor Group and commodities trader Jose Sierra 30 years minerals policy & regulation, Spain (Director-General Mines) and EU
  • 19. DIRECTORS & SENIOR MANAGEMENT Harry Anagnostaras-Adams - Managing Director Founder of EMED Mining Serves (or has served) as non-executive Director of many other public and private companies Demetrios Constantinides - External Relations 30 years experience in private and government roles in Europe Ron Cunneen - Group Geologist Over 25 years exploration, start-up and operational experience Bill Enrico - Chief Operating Officer 20 years general management start-up and operational experience John Leach - Finance Director 30 years experience in senior financial and executive positions within the mining industry Rob Williams - Group Development 20 years project start-up and management experience 19 SENIOR MANAGEMENT
  • 20. A I M : E M E D T S X : E M D Presentation 21 March 2013 Presentation at Proactive Conference