Antalya su kayaği 04-02-2008 özet
- 1. ID WBS Task Name Duration Start Finish
1 1 ANTALYA SU KAYAĞI PROJESĐ 91,38 days? Fri 18.01.08 Thu 24.04.08
2 1.1 PROJE DĐZAYNI 29 days Fri 18.01.08 Mon 18.02.08
16 1.2 MALZEME ONAYLARI 34,38 days Fri 18.01.08 Sun 24.02.08
27 1.3 SATINALMA 55,38 days Fri 25.01.08 Mon 24.03.08
73 1.4 MOBĐLĐZASYON 7 days Mon 11.02.08 Mon 18.02.08
74 1.5 MONTAJ 40,38 days Mon 18.02.08 Mon 31.03.08
88 1.6 TEST VE DEVREYE ALMA 12 days? Tue 01.04.08 Sun 13.04.08
101 1.7 DEMOBĐLĐZASYON 6 days Sun 13.04.08 Sun 20.04.08
102 1.8 SAHA TEMĐZLĐĞĐ 4 days Sun 20.04.08 Thu 24.04.08
103 1.9 milestones 34,13 days Mon 25.02.08 Mon 31.03.08
Labor[8]
11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28
February 2008 March 2008 April 2008
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
ANTALYA KABLOLU SU KAYAĞI TESĐSĐ ELEKTRĐK TESĐSATI ĐŞ PLANI ANEL ELECTRICITY PROJECTS CONTRACTING & TRADE INC.