The document outlines the production schedule for a film project. It lists dates from April to February and the tasks assigned on each date, such as drafting a presentation, finalizing planning details, filming on various dates, logging and capturing footage, continuing editing work, and creating posters. It also lists the crew members and actors involved on each date to complete the various tasks.
1. CREW MEMBERS/ACTORS
DATE TASK
INVOLVED
Ama
04/10/10 Presentation – First draft Frankie-Rose
Sonia
Ama
11/10/10 Group Meeting and delegation – Assigning pre-production and production roles Frankie-Rose
Sonia
Ama
Dennis
Frankie-Rose
18/10/10 – Magne
Finalise planning – location, actors, Shoot schedule, contact list
22/10/10 Michaella
Philippa
Sonia
Theresa
Ama
Dennis
Frankie-Rose
HALF TERM
Update blog Magne
25/10/10 –
START FILMING – More information in the shoot schedule Michaella
29/10/10
Philippa
Sonia
Theresa
Ama
Dennis
Frankie-Rose
03/11/10 – Magne
CONTINUE FILMING – More information in the shoot schedule
08/12/10 Michaella
Philippa
Sonia
Theresa
Ama
Dennis
Frankie-Rose
CONTINUE FILMING Magne
15/12/10
Log and capture footage so far Michaella
Philippa
Sonia
Theresa
Ama
Dennis
CHRISTMAS Frankie-Rose
HOLIDAYS Magne
CONTINUE FILMING
20/12/10 – Michaella
4/01/11 Philippa
Sonia
Theresa
Ama
Dennis
Frankie-Rose
5/01/11 – CONTINUE FILMING – Do photoshoot on location Magne
19/01/11 Log and capture footage so far Michaella
Philippa
Sonia
Theresa
Ama
Log and capture remaining footage
26/01/11 Frankie-Rose
START EDITING
Sonia
Ama
02/02/11 Continue editing Frankie-Rose
Sonia
Ama, Frankie-Rose and Sonia will
Continue editing
09/02/11 work individually on their posters,
Start working on the first draft of your poster
but as a group for their teaser.
Ama, Frankie-Rose and Sonia will
Continue editing
16/02/11 work individually on their posters,
Continue working on the first draft of your poster and hand in
but as a group for their teaser.