SlideShare a Scribd company logo
1 of 10
Download to read offline
PUNJAB GOVT. GAZ. (EXTRA), JANUARY 7, 2019 (PAUSA 17, 1940 SAKA)1966Regd. No. NW/CH-22 Regd. No. CHD/0092/2018-2020
EXTRAORDINARY
Published byAuthority
CHANDIGARH, MONDAY, JANUARY7, 2019 (PAUSA17, 1940 SAKA)
(1966)
THE PUNJAB STATE ELECTRICITY REGULATORY COMMISSION
NOTIFICATION
7th January, 2019
No.PSERC/Secy/Regu.135.- In exercise of the powers conferred under Section 181of the Electricity
Act, 2003 (CentralAct 36 of 2003), and all other powers enabling it in this behalf, and after previous publication,
the Punjab State Electricity Regulatory Commission hereby makes the following regulations, namely:
1.0 Short title and commencement
1.1 These regulations may be called the Punjab State Electricity Regulatory Commission (Forecasting,
Scheduling, Deviation Settlement and Related Matters of Solar and Wind Generation Sources) Regulations,
2019.
1.2 These regulations shall extend to whole of the State of Punjab.
1.3 These regulations shall come into force from the date of notification in the official Gazette of the State.
Provided that Forecasting and Scheduling in accordance with these Regulations shall come in to
force six months from the date of notification of these Regulations while the commercial mechanism
regarding Deviation Settlement specified in these Regulations shall come into force from the date to be
notified separately by the Commission.
2.0 Definitions and Interpretation
2.1 In these Regulations, unless the context otherwise requires –
(a) ‘Absolute Error’ means the absolute value of the error in actual generation of wind or solar generators
with reference to scheduled generation and the ‘Available Capacity (AvC), as calculated using the following
formula for each 15minute time block;
Absolute Error (%)= [Actual Generation-Scheduled Generation]X100
(AvC)
(b) ‘Act’ means the Electricity Act, 2003 (36 of 2003);
(c) ‘Actual drawal’ in a time-block means the electricity drawn by a buyer, as the case may be, as measured
by the interface meters;
(d) ‘Actual injection’ in a time-block means electricity generated or supplied by the seller, as the case may
be, measured by the Interface meters;
PUNJAB GOVT. GAZ. (EXTRA), JANUARY 7, 2019 (PAUSA 17, 1940 SAKA) 1967
(e) 'Available Capacity (AvC)' for wind or solar generators, which are State Entities, means the cumulative
rating of wind turbines or solar inverters that are capable of generating power in a given time-block;
(f) ‘Beneficiary’ means a person purchasing electricity generated from a generating station including a
captive generating station;
(g) ‘Buyer’ means a person, including beneficiary, distribution licensee or open access consumer, purchasing
electricity through a transaction scheduled in accordance with the regulations applicable for short-term
open access, medium-term open access and long-term access;
(h) ‘Central Commission (CERC)’ means Central Electricity Regulatory Commission referred to in sub-
section (1) of Section 76 of the Act;
(i) ‘Commission’ means Punjab State Electricity Regulatory Commission constituted under sub-section (1)
of section 82 of the Act;
(j) ‘Deviation’ in a time-block for a Seller means its total actual injection minus its total scheduled generation
and for a Buyer means its total actual drawal minus its total scheduled drawal,
(k) ‘Existing RE Generator’ shall mean Wind or Solar Generator that has been commissioned prior to the
date of notification of these Regulations;
(l) ‘Forecasting’ means the projection of likely future electricity generation based on scientific analysis of
meteorological data and other relevant parameters;
(m) ‘Gaming’ in relation to these regulations, shall mean an intentional mis-declaration of available capacity
or schedule by any seller in order to make an undue commercial gain through deviation charges;
(n) ‘Grid Code or State Grid Code’ means the Grid Code specified by the Commission under clause (h) of
sub-section (1) of Section 86 of the Act;
(o) ‘Indian Electricity Grid Code (IEGC)’ means the Grid Code specified by CERC under clause (h) of
sub-section (1) of section 79 of the Act;
(p) ‘Interface meter’means the interface meter as defined in Central Electricity Authority (Installation and
Operation of Meters) Regulations, 2006, as amended from time to time;
(q) ‘Interconnection/Interface Point’ means a point at which an individual wind/solar generating plant or
a group of such generating plants are connected to the transmission or distribution system, as the case
may be;
(r) ‘New RE Generator’ shall mean Wind or Solar Generator that has been commissioned subsequent to
the date of notification of these Regulations;
(s) ‘Open Access Regulations’ means Punjab State Electricity Regulatory Commission (Terms and
Conditions of Intra-State Open Access) Regulations, 2011, as amended from time to time;
(t) ‘Pooling Station’ means the sub-station where pooling of generation of individual wind or solar generators
is done for interfacing with the next higher voltage level:
Provided that where there is no separate pooling station for a wind/solar generator and the generating
station is connected through common/dedicated feeder and terminated at a Sub Station of distribution
company/STU, the sub-station of the distribution company/STU shall be considered as the pooling station
for such wind or solar generator, as the case may be;
(u) ‘Qualified Coordinating Agency (QCA)’ means the agency coordinating on behalf of wind/solar
generators connected to a pooling station to perform the functions and discharge the obligations as specified
in these regulations;
(v) ‘Scheduled Generation’ at any time or for a time block or any period means schedule of generation in
MW or MWh ex-bus given by the State Load Despatch Centre (SLDC);
PUNJAB GOVT. GAZ. (EXTRA), JANUARY 7, 2019 (PAUSA 17, 1940 SAKA)1968
(w) ‘Scheduled Drawal’ at any time or for a time block or any period time block means schedule of despatch
in MW or MWh ex-bus given by the State Load Despatch Centre (SLDC);
(x) ‘Seller’ means a person, including a generating station, supplying electricity through a transaction scheduled
in accordance with the regulations applicable for short-term open access, medium-term open access and
long-term access;
(y) ‘State Entity’ means an entity which is in the SLDC control area and whose metering and energy
accounting is done at the State level;
(z) ‘State Load Despatch Centre’ or ‘SLDC’ means the Load Despatch Centre of the State established
under sub section (1) of section 31 of theAct, responsible for co-ordinating scheduling of the state entities
in accordance with the provisions of State Grid Code;
(aa) ‘State Pool Account’ means a separate account to be maintained by SLDC for receipts and payments
on account of deviation, specified by the Commission;
(bb) ‘Time-Block’ means a time block of 15 minutes or such shorter duration, as may be specified by the
Commission, for which specified electrical parameters and quantities are recorded by Special Energy
Meter, with first time block starting at 00.00 hrs.
2.2 Save as aforesaid and unless repugnant to the context or the subject-matter otherwise required, words
and expressions used in these regulations and not defined, but defined in theAct, or the Grid Code or any
other regulations of this Commission shall have the meaning assigned to them respectively in the Act or
the Grid Code or any other regulation.
3.0 General
3.1 Objective
The objective of these regulations is to facilitate large scale grid integration of solar and wind generating
stations while maintaining grid stability and security as envisaged under the State Grid Code, through
Forecasting, Scheduling and Commercial Mechanism for Deviation Settlement of these generators.
3.2 Applicability
These Regulations shall be applicable to all wind and solar generators with individual capacity of 5 MW
and above connected to the State Transmission System or distribution system or wind and solar generators
of any capacity connected through pooling stations to the State Transmission System or distribution system
with combined capacity of 5 MW and above, supplying power to the distribution company (ies) or to the
third party through open access or for captive consumption through open access within or outside the
State.
4.0 Appointment of Qualified Coordinating Agency (QCA)
Qualified CoordinatingAgency (QCA) is an agency appointed by the wind/solar generators, connected to
a pooling station, for coordinating on their behalf with SLDC. Each pooling station shall have one QCA
who may be one of the generators or any other mutually agreed agency to perform the functions and
discharge the obligations as specified in these regulations. The QCA shall be treated as a State Entity
registered with SLDC in accordance with the Detailed Procedure prescribed in Regulation 5.9 of these
regulations. QCA shall be single point of contact between generators and SLDC. The QCA shall perform
the following functions;
• Coordinate for schedules with periodic revisions on behalf of all the Wind/Solar Generators connected to
a pooling station.
• Responsible for coordination with STU/SLDC for metering, data collection/ transmission, communication.
• Undertake commercial settlement on behalf of the generators of such charges pertaining to generation,
including payment of Deviation Charges to the State Pool Accounts through SLDC.
PUNJAB GOVT. GAZ. (EXTRA), JANUARY 7, 2019 (PAUSA 17, 1940 SAKA) 1969
• Undertake de-pooling of payments received/payable on behalf of the generators of the pooling station
from/to the State Pool Account and settling them with individual generators;
• Undertake commercial settlement of any other charges on behalf of the generators, as may be mandated
from time to time.
5.0 Forecasting and Scheduling Code
5.1 This Code specifies the methodology for Day-Ahead, Week ahead scheduling of wind and solar energy
generators, which are connected to the State Grid and re-scheduling them on one and half hourly basis
and methodology of handling deviations of such wind and solar energy generators.
5.2 Appropriate Interface meters shall be provided in accordance with CEA Metering Regulations for energy
accounting. Telemetry/Communication System and the Data Acquisition System shall also be provided
for transfer of information to the concerned SLDC by the generators or Qualified Coordinating Agency
(QCA) appointed by it.
5.3 Wind and solar generators, either by themselves or represented by QCAs, shall mandatorily provide to the
concerned SLDC, in a format prescribed by the SLDC, the technical specifications of the generating
units and all other associated equipment of wind/solar generator at the beginning and thereafter, whenever
there is any change in such technical specifications. The data relating to the power generation parameters
and weather related data, as applicable, shall also be mandatorily provided by such generators or QCA
appointed by it, to the concerned SLDC in real time.
5.4 Forecasting shall be done by every wind and solar generator connected to the Grid, either by itself or by
a QCA on its behalf. The SLDC is also mandated to undertake forecasting of wind and solar power that
is expected to be injected into the state grid, by engaging forecasting agency (ies), if required. The
forecast by the SLDC shall be with the objective of ensuring secured grid operation by planning for
requisite balancing resources. The forecast by a wind or solar generator or QCA, as the case may be,
shall be generator centric. The wind or solar generator or QCA will have the option of accepting the
SLDC’s forecast for preparing its schedule or provide the SLDC with a schedule based on its own
forecast. The SLDC shall recover the charges for such forecasting service, as may be approved by the
Commission and such amount shall be treated as ‘other income’in theAggregate Revenue Requirement”
of SLDC. The QCA shall coordinate the aggregation of schedules of all its generators connected to a
pooling station and communicate the same to the SLDC.
Provided that the existing wind and solar generators or QCA on their behalf shall establish the forecasting
tools and furnish day ahead, week-ahead forecasting and scheduling to SLDC within six months from the
date of coming into force of these regulations.
Provided further that all new wind and solar generators or QCA on their behalf, shall establish the forecasting
tools before commissioning of the plant and connecting to the State Transmission System or Distribution
system, as the case may be.
5.5 Every wind and solar generator or a QCA shall submit a day ahead and week ahead schedule for each
generating station or each pooling station, as the case may be. Day ahead schedule shall contain wind or
solar energy generation schedule at intervals of fifteen (15) minutes time-block for next day, starting from
00.00 hours of the day and prepared for all ninety six (96) time blocks of the day. Week-ahead schedule
shall contain the same information for next seven days.
5.6 The schedule of wind and solar generators connected to the State Grid, excluding collective transactions,
may be revised by giving advance notice to SLDC. Such revisions shall be effective from fourth (4th)
time block, the first being the time-block in which notice was given. There may be one revision for each
time slot of one and half hours starting from 00.00 hours of particular day subject to maximum of sixteen
(16) revisions during the day.
PUNJAB GOVT. GAZ. (EXTRA), JANUARY 7, 2019 (PAUSA 17, 1940 SAKA)1970
5.7 Any commercial impact on account of deviation from schedule based on forecast shall be borne by the
wind and solar electric generator, either directly or transacted via the representing QCA.
5.8 The plan for data telemetry, formats of forecast submission and other modalities and requirements shall
be stipulated in the Detailed Procedure to be submitted by the SLDC within three months, which the
Commission shall endeavor to approve within a month thereafter.
Provided that SLDC shall undertake stakeholder consultation by uploading the Draft Procedure on SLDC’s
website before submission to the Commission for approval.
5.9 The Detailed Procedure shall address the following aspects:
a) The procedure and requirements, including the payment of fees and penalties, for the registration
and de-registration of QCAs by the SLDC.
b) The information and data, and the formats on which the information/data is required by the SLDC
from the wind/solar generators or QCAs, as the case may be.
c) The mode and protocol of communication for exchange of information and data between the wind/
solar generators or QCAs and the SLDC.
d) The guidelines for energy and deviation accounting of Wind and Solar energy transactions under the
State energy accounting framework, with illustrative examples, in accordance with the principles
specified in these Regulations.
e) The mechanism for monitoring compliance of the Forecasting and Scheduling Code.
f) The default conditions in the State Deviation Pool Settlement by QCAs and their treatment.
5.10 Treatment for Gaming
Any intentional mis-declaration ofAvailable Capacity or schedule to the SLDC for its own undue commercial
gain through deviation charges or that of a generator shall be considered as gaming and shall be liable to
action under appropriate provisions of the Act or the Regulations.
6.0 Commercial and Deviation Settlement
6.1 Deviation Settlement of Intra-State Transactions:
(i) The wind or solar generators, which are state entities, connected to the State Grid and selling power
within the State shall be paid by the buyers as per actual generation whereas the Deviation Settlement
shall be undertaken as under;
(ii) In the event of actual generation of a Solar or Wind generating station or a pooling station, as the case
may be, being less or more than the scheduled generation, the deviation charges for shortfall or excess
generation shall be payable by the wind and solar generator or the QCA on its behalf, as the case may be,
to the State Pool Account, as given in Table–I below:
TABLE-I
Deviation Charges in case of under-injection or over injection, by Wind/Solar Generating Stations
for sale of power within State:
S. No. Absolute Error in the Deviation Charges payable by Wind/Solar Generating Stations to State
15-minute time block PoolAccount
1 <= 15% None
2 >15% but <=25% (At the Rs 0.50 per unit for shortfall or excess energy for Absolute Error
beyond 15% and upto 25%)
3 >25% but <=35% (At the Rs 0.50 per unit for shortfall or excess energy for Absolute Error
beyond 15% and upto 25%) + (At the Rs 1.00 per unit for balance energy
beyond 25% and up to 35%)
PUNJAB GOVT. GAZ. (EXTRA), JANUARY 7, 2019 (PAUSA 17, 1940 SAKA) 1971
4 >35% (At the Rs 0.50 per unit for shortfall or excess energy for Absolute Error
beyond 15% and upto 25%) + (At the Rs 1.00 per unit for shortfall or
excess energy beyond 25% and up to 35%) + (At the Rs 1.50 per unit for
balance energy beyond 35%)
(iii) State Load Despatch Centre or the Secretariat of State Power Committee, as the case may be, shall
maintain separate records and account of time-block wise schedules, actual generation and deviations for
all individual wind and solar generators connected directly to the grid and at the level of Pooling Station, if
RE generators are connected to State Transmission System or distribution system.
(iv) The QCA shall undertake de-pooling of the energy deviation as well as deviation charges to each generator
in proportion to actual generated units for each time block for each generator
6.2 Deviation Settlement for Inter-State Transactions:
The wind or solar generators, which are state entities undertaking inter-state transactions shall be paid as
per schedule generation in accordance with CERC (Deviation Settlement Mechanism & Related Matters)
Regulations, 2014, as amended from time to time, as under:
(i) In the event of actual generation being less than the scheduled generation, the deviation charges for
shortfall shall be payable by such wind or solar generator or QCA on their behalf , which are state entities
undertaking inter-state transactions into State Pool Account as given in Table–II of Appendix-1.
(ii) In the event of actual generation being more than the scheduled generation, the deviation charges for
excess generation shall be payable to such wind or solar generator or QCA on their behalf, which are
state entities undertaking inter-state transactions from the State Pool Account as given in Table–III of
Appendix-1.
6.3 Deviation Settlement for Inter-State and Intra-State Transactions
(i) The SLDC shall provide separate Energy and Deviation accounts for inter-state and intra-state transactions
to QCA or individual wind or solar generator, as the case may be.
(ii) The wind or solar generators, as state entities, undertaking intrastate transactions and inter-state transactions
shall be allowed provided that such generators are connected to separate feeders at LV side of the
Pooling Substation and metering, scheduling, energy accounting and deviation settlement account for
such wind or solar generators are maintained separately.
7.0 Implementation procedure
7.1 Metering
Interface Energy Meters (IEMs) shall be installed by STU/SPD as per CEA Metering Regulations.
Every Solar and Wind generating plant or a pooling station shall have a Special Energy Meter (SEM) at
the interface points capable of recording and storing all the load survey and billing parameters for every
15-minute time blocks or such shorter duration as may be specified by the Commission, in accordance
with the CEA Regulations governing metering. Automated Meter Reading (AMR) system shall be used
for communicating interface data at SLDC. Internal clock of the interface meter shall be time synchronised
with GPS. Weekly meter readings shall be forwarded to the SLDC in addition to data provided through
Supervisory ControlAnd DataAcquisition (SCADA) for energy accounting. The IEMs shall comply with
the provisions of Central Electricity Authority (Installation and Operation of Meters) Regulations, 2006,
as amended from time to time.
7.2 Telemetry
All Wind and Solar generators shall provide data telemetry at the Turbine/Inverter level to SLDC and
shall ensure the correctness of the real time data and undertake the corrective actions, if required.
PUNJAB GOVT. GAZ. (EXTRA), JANUARY 7, 2019 (PAUSA 17, 1940 SAKA)1972
Frequency of real time data updation to be shared with SLDC shall be 10 second or less as per prevailing
practice being followed by RLDCs. Further, turbine/inverter outage plan shall be forwarded to SLDC.
7.3 Communication
(i) All Solar and Wind generators or QCAs, as the case may be, whose scheduling is done by SLDC
shall follow Central Electricity Regulatory Commission (Communication Systems for Inter-state
Transmission of Electricity) Regulations, 2017 for Communication infrastructure to be used for data
communication, tele-protection of power system at the State level till the Commission notifies separate
regulations on Communication systems for State entities.
(ii) All Solar and Wind generators or the QCAs, as the case may be, shall abide by any guidelines,
technical standards, protocols for communication system etc which may be notified by CEA under
CERC (Communication Systems for Inter-state Transmission of Electricity) Regulations, 2017, as
applicable to them.
(iii) A preparatory window upto 6 months from the date of notification of these regulations has been
provided to wind and solar generator or their QCA to ensure installation of data measurement and
telemetry equipment and for the SLDC to prepare its systems and team for receipt of regular data.
During this period, SLDC shall evolve a detailed procedure for Data Telemetry and Communication
requirement, necessary formats for furnishing forecasts and scheduling data to SLDC, formats for
technical parameters and other details of Solar/Wind generators and solicit the comments of
stakeholders and seek the approval of the Commission as specified in Regulation 5.8.
8. Deviation Accounting and Settlement of Deviation Charges
The procedure for computation of Deviation Charges shall be as under:
8.1 The Deviation Charges (D) payable/receivable for the State as a whole at State periphery by distribution
licensee/OA consumers/conventional generators/RE generators (pooling station) shall be computed first
by SLDC in accordance with CERC (Deviation Settlement Mechanism and related matters) Regulations,
2014, as amended from time to time, read with Commission’s order dated 28.11.2014 in petition no. 27 of
2014, till Intra-State Deviation Settlement Mechanism Regulations are notified by the Commission.
8.2 The SLDC shall compute the Absolute Error, i.e. the difference between the scheduled and the actual
energy injected, in respect of each Pooling Sub-Station and each Generator with capacity more than 5
MW which feeds the energy directly to Sub-Station, and shall accordingly determine the deviation charges
payable by RE generators/pooling station (R1) in accordance with Regulations 6.
8.3 Deviation charges (D) shall be allocated amongst the distribution licensee/OA consumers/conventional
generators/RE generators (pooling station) in proportion to their respective deviation.Assuming the share
of the State level deviation charges for RE generators as D4 and receipt of deviation charges from RE
generators/pooling stations as R1, the actual commercial impact for the State as a result of deviation of
RE generation shall be D4-R1. At the end of the year, if this amount is greater than zero, the same can be
refunded to the State Pool Account from PSDF/NCEF or from the alternative funding mechanism, as
may be approved by the Commission.
8.4 The QCA shall pay the Deviation Charges to the SLDC, and collect it from the concerned Generators in
proportion to their actual generation as per regulation 6.1.
8.5 The Deviation Charges shall be paid in to State Pool Account by the generators or QCA, as the case may
be, within ten days from the issue of deviation charges statement by the SLDC. If the payments against
deviation charges are delayed beyond 12 days from the date of issue of deviation charges statement by
SLDC, then the defaulting generator shall pay simple interest @ 0.04% for each day of delay.
PUNJAB GOVT. GAZ. (EXTRA), JANUARY 7, 2019 (PAUSA 17, 1940 SAKA) 1973
8.6 All payments to the State entities on account of charges for deviation shall be made within 2 working days
of receipt of the payments in State Pool account.
8.7 In case the Wind or solar generator defaults in payment to QCAthen QCAshall inform SLDC about such
default and request SLDC to disconnect such defaulting generator from the grid.
9. Compliance with instructions of Load Despatch Centre or Curtailment of schedule
Notwithstanding anything specified in these Regulations, the sellers and the buyers shall strictly follow the
instructions of the State Load Despatch Centre on injection and drawal in the interest of grid security and
grid discipline. In the event of contingencies, transmission constraints, congestion in network, threat to
system security, the transaction of RE generators already scheduled by SLDC may be curtailed as per
the provisions of State Grid Code for ensuring secure and reliable system operation. Any curtailment
imposed on energy injection for reliable and secure grid operation in emergent situation shall be
communicated by SLDC to generators and QCAs. In case SLDC fails to communicate about the curtailment
to generators/QCAs, deviation charges shall not be levied.
10 Practice Directions
Subject to the provisions of the Act, the Commission may issue Practice Directions with regard to the
implementation of these Regulations.
11. Power to Relax
The Commission may by general or special order, for reasons to be recorded in writing, and after giving
an opportunity of hearing to the parties likely to be affected by grant of relaxation, may relax any of the
provisions of these Regulations on its own motion or on an application made before it by an interested
person.
12. Power to remove difficulties
If any difficulty arises in giving effect to the provisions of these Regulations, the Commission may, by
general or specific order, make such provisions not inconsistent with the provisions of the Act, as may
appear to be necessary for removing the difficulty.
Sd/-
Secretary
Punjab State Electricity Regulatory Commission
PUNJAB GOVT. GAZ. (EXTRA), JANUARY 7, 2019 (PAUSA 17, 1940 SAKA)1974
Appendix 1
Deviation Charges for under- or over-injection by Solar and Wind Generators connected to the
Intra-State Transmission network and supplying or consuming power outside Punjab
1. In the event of actual generation being lesser than the scheduled generation, the deviation charges for
shortfall shall be payable by such wind or solar generator which are state entities undertaking inter-state
transactions into State Deviation Pool Account as given in Table – II.
TABLE-II
Deviation Charges in case of under injection by Wind/Solar Generating Stations as State Entities
undertaking Inter-state transactions:
S Absolute Error in Deviation Charges payable by Wind/Solar Generating Stations
No. the 15-minute time to State Pool Account
block
1 <= 15% At the Fixed Rate for the shortfall energy for absolute error upto 15%
2 >15% but <=25% (At the Fixed Rate for the shortfall energy for absolute error upto 15%) +
(110% of the Fixed Rate for balance energy beyond 15% and upto 25%)
3 >25% but <=35% (At the Fixed Rate for the shortfall energy for absolute error upto 15%) +
(110% of the Fixed Rate for balance energy beyond 15% and upto 25%) + (120%
of the Fixed Rate for balance energy beyond 25% and upto 35%)
4 >35% (At the Fixed Rate for the shortfall energy for absolute error upto 15%) +
(110% of the Fixed Rate for balance energy beyond 15% and upto 25%) + (120%
of the Fixed Rate for balance energy beyond 25% and upto 35%) + (130% of the
Fixed Rate for balance energy beyond 35%)
2. In the event of the actual generation being more than the scheduled generation, the Deviation Charges for
excess generation shall be payable to the wind or solar generators which are state entities undertaking
inter-state transactions from State Deviation Pool Account as given in Table – III.
TABLE-III.
Deviation Charges in case of over injection by Wind/Solar Generating Stations as State Entities
undertaking Interstate transactions:
S. Absolute Error in Deviation Charges payable to Wind/Solar Generating Stations
No. the 15-minute time from State Pool Account
block
1 <= 15% At the Fixed Rate for the excess energy upto 15%
2 >15% but <=25% (At the Fixed Rate for the excess energy upto 15%) + (90% of the Fixed Rate
for balance energy beyond 15% and upto 25%)
3 >25% but <=35% (At the Fixed Rate for the excess energy upto 15%) + (90% of the Fixed Rate
for balance energy beyond 15% and upto 25%) + (80% of the Fixed Rate for
balance energy beyond 25% and upto 35%)
4 >35% (At the Fixed Rate for the excess energy upto 15%) + (90% of the Fixed Rate
for balance energy beyond 15% and upto 25%) + (80% of the Fixed Rate for
balance energy beyond 25% and upto 35%) + (70% of the Fixed Rate for balance
energy beyond 35%)
3. Where the Fixed Rate referred under Table-II and Table-III is the Power Purchase Agreement (PPA)
rate as determined by the Commission under section 62 of the Act or adopted by the Commission under
PUNJAB GOVT. GAZ. (EXTRA), JANUARY 7, 2019 (PAUSA 17, 1940 SAKA) 1975
section 63 of the Act. In case of multiple PPAs, the weighted average of the PPA rates shall be taken as
the Fixed Rate. The wind and solar generators shall furnish the PPA rates on affidavit for the purpose of
Deviation charge account preparation to SLDC supported by copy of the PPA.
4. The Fixed Rate for Solar and Wind captive power plants or OpenAccess generators selling power, which
is not accounted towards Renewal Purchase Obligation (RPO) compliance of the buyer, shall be the
Average Power Purchase Cost (APPC) rate at the National level, as may be determined by the Central
Commission from time to time.
5. With regard to inter-state wheeling transactions of Wind and Solar Generating stations as State Entities,
for balancing of deemed Renewable Purchase Obligation (RPO) compliance of buyers with respect to
schedule, deviations by all wind and solar generators, which are state entities, shall first be netted off for
the entire pool on a monthly basis and any remaining shortfall in renewable energy generation must be
balanced through purchase of equivalent solar and non-solar Renewable Energy Certificates (RECs), as
the case may be, by SLDC by utilising funds from the Pool Account. For positive balance of renewable
energy generation, equivalent notional RECs shall be credited to the DSM Pool and carried forward for
settlement in future.
6. State Load Despatch Centre or the Secretariat of State Power Committee, as the case may be, shall
maintain separate records and account of time-block wise schedules, actual generation and deviations for
all generators, including wind and solar generators.
1682/1-2019/Pb. Govt. Press, S.A.S. Nagar

More Related Content

What's hot

New electricity market. How consumers will pay for the pas mistakes made at t...
New electricity market. How consumers will pay for the pas mistakes made at t...New electricity market. How consumers will pay for the pas mistakes made at t...
New electricity market. How consumers will pay for the pas mistakes made at t...НЕК Укренерго - NPC Ukrenergo
 
Renewable energy production at the new electricity market of Ukraine - Stanis...
Renewable energy production at the new electricity market of Ukraine - Stanis...Renewable energy production at the new electricity market of Ukraine - Stanis...
Renewable energy production at the new electricity market of Ukraine - Stanis...Stanislav Masevych
 
Protocol for submission of data to sldc for renewable energy certificate
Protocol for submission of data to sldc for renewable energy certificateProtocol for submission of data to sldc for renewable energy certificate
Protocol for submission of data to sldc for renewable energy certificateJay Ranvir
 
Concept desing of new electricity market of Ukraine
Concept desing of new electricity market of UkraineConcept desing of new electricity market of Ukraine
Concept desing of new electricity market of UkraineStanislav Masevych
 
tew (10.10.18) - Principles of regulatory setting prices for guaranteed suppl...
tew (10.10.18) - Principles of regulatory setting prices for guaranteed suppl...tew (10.10.18) - Principles of regulatory setting prices for guaranteed suppl...
tew (10.10.18) - Principles of regulatory setting prices for guaranteed suppl...Денис Киркач
 
Iskender Sahin, Energy Market Regulatory Authority of Turkey
Iskender Sahin, Energy Market Regulatory Authority of TurkeyIskender Sahin, Energy Market Regulatory Authority of Turkey
Iskender Sahin, Energy Market Regulatory Authority of TurkeyWEC Italia
 
CW / 18587 / 2018 INDIAN WIND POWER ASSOCIATION (RAJASTHAN STATE COUNCIL) Vs....
CW / 18587 / 2018 INDIAN WIND POWER ASSOCIATION (RAJASTHAN STATE COUNCIL) Vs....CW / 18587 / 2018 INDIAN WIND POWER ASSOCIATION (RAJASTHAN STATE COUNCIL) Vs....
CW / 18587 / 2018 INDIAN WIND POWER ASSOCIATION (RAJASTHAN STATE COUNCIL) Vs....Das A. K.
 
Επιστολή Ελληνικής Κυβέρνησης στην ΕΟΚ για τα swap
Επιστολή Ελληνικής Κυβέρνησης στην ΕΟΚ για τα swapΕπιστολή Ελληνικής Κυβέρνησης στην ΕΟΚ για τα swap
Επιστολή Ελληνικής Κυβέρνησης στην ΕΟΚ για τα swapKafeneio Megalopolis
 
2010 Amendments to the Polish Energy Law
2010 Amendments to the Polish Energy Law2010 Amendments to the Polish Energy Law
2010 Amendments to the Polish Energy LawMichal
 

What's hot (10)

Epira ra9136
Epira ra9136Epira ra9136
Epira ra9136
 
New electricity market. How consumers will pay for the pas mistakes made at t...
New electricity market. How consumers will pay for the pas mistakes made at t...New electricity market. How consumers will pay for the pas mistakes made at t...
New electricity market. How consumers will pay for the pas mistakes made at t...
 
Renewable energy production at the new electricity market of Ukraine - Stanis...
Renewable energy production at the new electricity market of Ukraine - Stanis...Renewable energy production at the new electricity market of Ukraine - Stanis...
Renewable energy production at the new electricity market of Ukraine - Stanis...
 
Protocol for submission of data to sldc for renewable energy certificate
Protocol for submission of data to sldc for renewable energy certificateProtocol for submission of data to sldc for renewable energy certificate
Protocol for submission of data to sldc for renewable energy certificate
 
Concept desing of new electricity market of Ukraine
Concept desing of new electricity market of UkraineConcept desing of new electricity market of Ukraine
Concept desing of new electricity market of Ukraine
 
tew (10.10.18) - Principles of regulatory setting prices for guaranteed suppl...
tew (10.10.18) - Principles of regulatory setting prices for guaranteed suppl...tew (10.10.18) - Principles of regulatory setting prices for guaranteed suppl...
tew (10.10.18) - Principles of regulatory setting prices for guaranteed suppl...
 
Iskender Sahin, Energy Market Regulatory Authority of Turkey
Iskender Sahin, Energy Market Regulatory Authority of TurkeyIskender Sahin, Energy Market Regulatory Authority of Turkey
Iskender Sahin, Energy Market Regulatory Authority of Turkey
 
CW / 18587 / 2018 INDIAN WIND POWER ASSOCIATION (RAJASTHAN STATE COUNCIL) Vs....
CW / 18587 / 2018 INDIAN WIND POWER ASSOCIATION (RAJASTHAN STATE COUNCIL) Vs....CW / 18587 / 2018 INDIAN WIND POWER ASSOCIATION (RAJASTHAN STATE COUNCIL) Vs....
CW / 18587 / 2018 INDIAN WIND POWER ASSOCIATION (RAJASTHAN STATE COUNCIL) Vs....
 
Επιστολή Ελληνικής Κυβέρνησης στην ΕΟΚ για τα swap
Επιστολή Ελληνικής Κυβέρνησης στην ΕΟΚ για τα swapΕπιστολή Ελληνικής Κυβέρνησης στην ΕΟΚ για τα swap
Επιστολή Ελληνικής Κυβέρνησης στην ΕΟΚ για τα swap
 
2010 Amendments to the Polish Energy Law
2010 Amendments to the Polish Energy Law2010 Amendments to the Polish Energy Law
2010 Amendments to the Polish Energy Law
 

Similar to Punjab State Electricity Regulatory Commission (Forecasting, Scheduling, Deviation Settlement and Related Matters of Solar and Wind Generation Sources) Regulations, 2019

GERC (Forecasting, Scheduling, Deviation Settlement and Related Matters of So...
GERC (Forecasting, Scheduling, Deviation Settlement and Related Matters of So...GERC (Forecasting, Scheduling, Deviation Settlement and Related Matters of So...
GERC (Forecasting, Scheduling, Deviation Settlement and Related Matters of So...Das A. K.
 
Forecasting, scheduling and imbalance handling for Solar Wind Energy
Forecasting, scheduling and imbalance handling for Solar Wind EnergyForecasting, scheduling and imbalance handling for Solar Wind Energy
Forecasting, scheduling and imbalance handling for Solar Wind EnergyJay Ranvir
 
RERC Net metering Regulations 2015
RERC Net metering Regulations 2015RERC Net metering Regulations 2015
RERC Net metering Regulations 2015Headway Solar
 
Draft MERC Net Metering for Solar Rooftop Regulations,2015
Draft MERC Net Metering for Solar Rooftop Regulations,2015Draft MERC Net Metering for Solar Rooftop Regulations,2015
Draft MERC Net Metering for Solar Rooftop Regulations,2015Headway Solar
 
Model ppa for renewable energy sources
Model ppa for renewable energy sourcesModel ppa for renewable energy sources
Model ppa for renewable energy sourcesJay Ranvir
 
Solar net metering policy
Solar net metering policySolar net metering policy
Solar net metering policyJay Ranvir
 
DERC Renewable energy Net Metering Regulations 2014
DERC Renewable energy Net Metering Regulations 2014DERC Renewable energy Net Metering Regulations 2014
DERC Renewable energy Net Metering Regulations 2014Headway Solar
 
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...Headway Solar
 
Telangana State Electricity Regulatory Commission (Forecasting, Scheduling, D...
Telangana State Electricity Regulatory Commission (Forecasting, Scheduling, D...Telangana State Electricity Regulatory Commission (Forecasting, Scheduling, D...
Telangana State Electricity Regulatory Commission (Forecasting, Scheduling, D...Das A. K.
 
Gujarat electricity regulatory commission
Gujarat electricity regulatory commissionGujarat electricity regulatory commission
Gujarat electricity regulatory commissionJay Ranvir
 
Issuance of Ministry of Energy and Mineral Resources Regulation No. 2 of 2024...
Issuance of Ministry of Energy and Mineral Resources Regulation No. 2 of 2024...Issuance of Ministry of Energy and Mineral Resources Regulation No. 2 of 2024...
Issuance of Ministry of Energy and Mineral Resources Regulation No. 2 of 2024...AHRP Law Firm
 
175-Notification.pdf
175-Notification.pdf175-Notification.pdf
175-Notification.pdfPinkesh Kumar
 
Power supply regulation_28.9
Power supply regulation_28.9Power supply regulation_28.9
Power supply regulation_28.9Manoj kumar Rana
 
Regulation No. 177.pdf
Regulation No. 177.pdfRegulation No. 177.pdf
Regulation No. 177.pdfpspclexchange
 
Cerc open access-in-inter-state-transmission-regulations-2008
Cerc open access-in-inter-state-transmission-regulations-2008Cerc open access-in-inter-state-transmission-regulations-2008
Cerc open access-in-inter-state-transmission-regulations-2008vikrantdesh
 
Ppa agreement draft
Ppa agreement draftPpa agreement draft
Ppa agreement draftJay Ranvir
 
Mo p electricity rules, 2005
Mo p electricity rules, 2005Mo p electricity rules, 2005
Mo p electricity rules, 2005Anil Kumar
 
Gujarat Wind Power Policy 2013
Gujarat Wind Power Policy 2013Gujarat Wind Power Policy 2013
Gujarat Wind Power Policy 2013Spark Network
 

Similar to Punjab State Electricity Regulatory Commission (Forecasting, Scheduling, Deviation Settlement and Related Matters of Solar and Wind Generation Sources) Regulations, 2019 (20)

GERC (Forecasting, Scheduling, Deviation Settlement and Related Matters of So...
GERC (Forecasting, Scheduling, Deviation Settlement and Related Matters of So...GERC (Forecasting, Scheduling, Deviation Settlement and Related Matters of So...
GERC (Forecasting, Scheduling, Deviation Settlement and Related Matters of So...
 
Forecasting, scheduling and imbalance handling for Solar Wind Energy
Forecasting, scheduling and imbalance handling for Solar Wind EnergyForecasting, scheduling and imbalance handling for Solar Wind Energy
Forecasting, scheduling and imbalance handling for Solar Wind Energy
 
RERC Net metering Regulations 2015
RERC Net metering Regulations 2015RERC Net metering Regulations 2015
RERC Net metering Regulations 2015
 
Draft MERC Net Metering for Solar Rooftop Regulations,2015
Draft MERC Net Metering for Solar Rooftop Regulations,2015Draft MERC Net Metering for Solar Rooftop Regulations,2015
Draft MERC Net Metering for Solar Rooftop Regulations,2015
 
Model ppa for renewable energy sources
Model ppa for renewable energy sourcesModel ppa for renewable energy sources
Model ppa for renewable energy sources
 
Solar net metering policy
Solar net metering policySolar net metering policy
Solar net metering policy
 
DERC Renewable energy Net Metering Regulations 2014
DERC Renewable energy Net Metering Regulations 2014DERC Renewable energy Net Metering Regulations 2014
DERC Renewable energy Net Metering Regulations 2014
 
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
 
Telangana State Electricity Regulatory Commission (Forecasting, Scheduling, D...
Telangana State Electricity Regulatory Commission (Forecasting, Scheduling, D...Telangana State Electricity Regulatory Commission (Forecasting, Scheduling, D...
Telangana State Electricity Regulatory Commission (Forecasting, Scheduling, D...
 
Cbte regulations2019
Cbte regulations2019Cbte regulations2019
Cbte regulations2019
 
1.Regulation 2019.pdf
1.Regulation 2019.pdf1.Regulation 2019.pdf
1.Regulation 2019.pdf
 
Gujarat electricity regulatory commission
Gujarat electricity regulatory commissionGujarat electricity regulatory commission
Gujarat electricity regulatory commission
 
Issuance of Ministry of Energy and Mineral Resources Regulation No. 2 of 2024...
Issuance of Ministry of Energy and Mineral Resources Regulation No. 2 of 2024...Issuance of Ministry of Energy and Mineral Resources Regulation No. 2 of 2024...
Issuance of Ministry of Energy and Mineral Resources Regulation No. 2 of 2024...
 
175-Notification.pdf
175-Notification.pdf175-Notification.pdf
175-Notification.pdf
 
Power supply regulation_28.9
Power supply regulation_28.9Power supply regulation_28.9
Power supply regulation_28.9
 
Regulation No. 177.pdf
Regulation No. 177.pdfRegulation No. 177.pdf
Regulation No. 177.pdf
 
Cerc open access-in-inter-state-transmission-regulations-2008
Cerc open access-in-inter-state-transmission-regulations-2008Cerc open access-in-inter-state-transmission-regulations-2008
Cerc open access-in-inter-state-transmission-regulations-2008
 
Ppa agreement draft
Ppa agreement draftPpa agreement draft
Ppa agreement draft
 
Mo p electricity rules, 2005
Mo p electricity rules, 2005Mo p electricity rules, 2005
Mo p electricity rules, 2005
 
Gujarat Wind Power Policy 2013
Gujarat Wind Power Policy 2013Gujarat Wind Power Policy 2013
Gujarat Wind Power Policy 2013
 

More from Das A. K.

Rajasthan SLDC - RE DSM Statement -Jan 2020
Rajasthan SLDC - RE DSM Statement -Jan 2020Rajasthan SLDC - RE DSM Statement -Jan 2020
Rajasthan SLDC - RE DSM Statement -Jan 2020Das A. K.
 
Rajasthan SLDC - RE DSM Statement -August 2019
Rajasthan SLDC - RE DSM Statement -August 2019Rajasthan SLDC - RE DSM Statement -August 2019
Rajasthan SLDC - RE DSM Statement -August 2019Das A. K.
 
Rajasthan SLDC - RE DSM Statement -July 2019
Rajasthan SLDC - RE DSM Statement -July 2019Rajasthan SLDC - RE DSM Statement -July 2019
Rajasthan SLDC - RE DSM Statement -July 2019Das A. K.
 
Rajasthan DSM April 2019
Rajasthan DSM April 2019Rajasthan DSM April 2019
Rajasthan DSM April 2019Das A. K.
 
Rajasthan DSM May 2019
Rajasthan DSM May 2019Rajasthan DSM May 2019
Rajasthan DSM May 2019Das A. K.
 
Rajasthan DSM June 2019
Rajasthan DSM June 2019Rajasthan DSM June 2019
Rajasthan DSM June 2019Das A. K.
 
Actual Penalty and Deviation Settlement Mechanism (DSM) Penalty in Interstate...
Actual Penalty and Deviation Settlement Mechanism (DSM) Penalty in Interstate...Actual Penalty and Deviation Settlement Mechanism (DSM) Penalty in Interstate...
Actual Penalty and Deviation Settlement Mechanism (DSM) Penalty in Interstate...Das A. K.
 
Statement Showing the RE DSM (Rajasthan SLDC) for the month of November-2019 ...
Statement Showing the RE DSM (Rajasthan SLDC) for the month of November-2019 ...Statement Showing the RE DSM (Rajasthan SLDC) for the month of November-2019 ...
Statement Showing the RE DSM (Rajasthan SLDC) for the month of November-2019 ...Das A. K.
 
Draft - Rajasthan - SLDC - Deviation Settlement Account (DSM) statement Octob...
Draft - Rajasthan - SLDC - Deviation Settlement Account (DSM) statement Octob...Draft - Rajasthan - SLDC - Deviation Settlement Account (DSM) statement Octob...
Draft - Rajasthan - SLDC - Deviation Settlement Account (DSM) statement Octob...Das A. K.
 
Gujarat SLDC - STATE DEVIATION SETTLEMENT ACCOUNT FOR THE WEEK 29-Jul-2019 ...
Gujarat SLDC - STATE DEVIATION SETTLEMENT ACCOUNT  FOR THE WEEK  29-Jul-2019 ...Gujarat SLDC - STATE DEVIATION SETTLEMENT ACCOUNT  FOR THE WEEK  29-Jul-2019 ...
Gujarat SLDC - STATE DEVIATION SETTLEMENT ACCOUNT FOR THE WEEK 29-Jul-2019 ...Das A. K.
 
MP-DSM Account of Wind and Solar Pooling Stations for the month of AUGUST, 2019
MP-DSM Account of Wind and Solar Pooling Stations for the month of AUGUST, 2019MP-DSM Account of Wind and Solar Pooling Stations for the month of AUGUST, 2019
MP-DSM Account of Wind and Solar Pooling Stations for the month of AUGUST, 2019Das A. K.
 
Adjudication of dispute regarding RERC (Forecasting, Scheduling, Deviation Se...
Adjudication of dispute regarding RERC (Forecasting, Scheduling, Deviation Se...Adjudication of dispute regarding RERC (Forecasting, Scheduling, Deviation Se...
Adjudication of dispute regarding RERC (Forecasting, Scheduling, Deviation Se...Das A. K.
 
MP-SLDC-DSM Account of Wind and Solar PSS for April, 2019
MP-SLDC-DSM Account of Wind and Solar PSS for April, 2019MP-SLDC-DSM Account of Wind and Solar PSS for April, 2019
MP-SLDC-DSM Account of Wind and Solar PSS for April, 2019Das A. K.
 
MP-DSM Account of Wind and Solar Pooling Stations for March, 2019
MP-DSM Account of Wind and Solar Pooling Stations for March, 2019MP-DSM Account of Wind and Solar Pooling Stations for March, 2019
MP-DSM Account of Wind and Solar Pooling Stations for March, 2019Das A. K.
 
Rajasthan SLDC - Statement Showing the RE DSM for the month of October-2018 Q...
Rajasthan SLDC - Statement Showing the RE DSM for the month of October-2018 Q...Rajasthan SLDC - Statement Showing the RE DSM for the month of October-2018 Q...
Rajasthan SLDC - Statement Showing the RE DSM for the month of October-2018 Q...Das A. K.
 
Rajasthan SLDC - Statement Showing the RE DSM for the month of November-2018 ...
Rajasthan SLDC - Statement Showing the RE DSM for the month of November-2018 ...Rajasthan SLDC - Statement Showing the RE DSM for the month of November-2018 ...
Rajasthan SLDC - Statement Showing the RE DSM for the month of November-2018 ...Das A. K.
 
Rajasthan SLDC - Statement Showing the RE DSM for the month of December-2018 ...
Rajasthan SLDC - Statement Showing the RE DSM for the month of December-2018 ...Rajasthan SLDC - Statement Showing the RE DSM for the month of December-2018 ...
Rajasthan SLDC - Statement Showing the RE DSM for the month of December-2018 ...Das A. K.
 
MP-SLDC-DSM Account of Wind and Solar Pooling Stations for the month of Febru...
MP-SLDC-DSM Account of Wind and Solar Pooling Stations for the month of Febru...MP-SLDC-DSM Account of Wind and Solar Pooling Stations for the month of Febru...
MP-SLDC-DSM Account of Wind and Solar Pooling Stations for the month of Febru...Das A. K.
 
MP_SLDC_RE_DSM_from-01-01-2019-to-31-01-2019_daily
MP_SLDC_RE_DSM_from-01-01-2019-to-31-01-2019_dailyMP_SLDC_RE_DSM_from-01-01-2019-to-31-01-2019_daily
MP_SLDC_RE_DSM_from-01-01-2019-to-31-01-2019_dailyDas A. K.
 
Reply to reconnect's defamation notice - One can love it or hate it, but we r...
Reply to reconnect's defamation notice - One can love it or hate it, but we r...Reply to reconnect's defamation notice - One can love it or hate it, but we r...
Reply to reconnect's defamation notice - One can love it or hate it, but we r...Das A. K.
 

More from Das A. K. (20)

Rajasthan SLDC - RE DSM Statement -Jan 2020
Rajasthan SLDC - RE DSM Statement -Jan 2020Rajasthan SLDC - RE DSM Statement -Jan 2020
Rajasthan SLDC - RE DSM Statement -Jan 2020
 
Rajasthan SLDC - RE DSM Statement -August 2019
Rajasthan SLDC - RE DSM Statement -August 2019Rajasthan SLDC - RE DSM Statement -August 2019
Rajasthan SLDC - RE DSM Statement -August 2019
 
Rajasthan SLDC - RE DSM Statement -July 2019
Rajasthan SLDC - RE DSM Statement -July 2019Rajasthan SLDC - RE DSM Statement -July 2019
Rajasthan SLDC - RE DSM Statement -July 2019
 
Rajasthan DSM April 2019
Rajasthan DSM April 2019Rajasthan DSM April 2019
Rajasthan DSM April 2019
 
Rajasthan DSM May 2019
Rajasthan DSM May 2019Rajasthan DSM May 2019
Rajasthan DSM May 2019
 
Rajasthan DSM June 2019
Rajasthan DSM June 2019Rajasthan DSM June 2019
Rajasthan DSM June 2019
 
Actual Penalty and Deviation Settlement Mechanism (DSM) Penalty in Interstate...
Actual Penalty and Deviation Settlement Mechanism (DSM) Penalty in Interstate...Actual Penalty and Deviation Settlement Mechanism (DSM) Penalty in Interstate...
Actual Penalty and Deviation Settlement Mechanism (DSM) Penalty in Interstate...
 
Statement Showing the RE DSM (Rajasthan SLDC) for the month of November-2019 ...
Statement Showing the RE DSM (Rajasthan SLDC) for the month of November-2019 ...Statement Showing the RE DSM (Rajasthan SLDC) for the month of November-2019 ...
Statement Showing the RE DSM (Rajasthan SLDC) for the month of November-2019 ...
 
Draft - Rajasthan - SLDC - Deviation Settlement Account (DSM) statement Octob...
Draft - Rajasthan - SLDC - Deviation Settlement Account (DSM) statement Octob...Draft - Rajasthan - SLDC - Deviation Settlement Account (DSM) statement Octob...
Draft - Rajasthan - SLDC - Deviation Settlement Account (DSM) statement Octob...
 
Gujarat SLDC - STATE DEVIATION SETTLEMENT ACCOUNT FOR THE WEEK 29-Jul-2019 ...
Gujarat SLDC - STATE DEVIATION SETTLEMENT ACCOUNT  FOR THE WEEK  29-Jul-2019 ...Gujarat SLDC - STATE DEVIATION SETTLEMENT ACCOUNT  FOR THE WEEK  29-Jul-2019 ...
Gujarat SLDC - STATE DEVIATION SETTLEMENT ACCOUNT FOR THE WEEK 29-Jul-2019 ...
 
MP-DSM Account of Wind and Solar Pooling Stations for the month of AUGUST, 2019
MP-DSM Account of Wind and Solar Pooling Stations for the month of AUGUST, 2019MP-DSM Account of Wind and Solar Pooling Stations for the month of AUGUST, 2019
MP-DSM Account of Wind and Solar Pooling Stations for the month of AUGUST, 2019
 
Adjudication of dispute regarding RERC (Forecasting, Scheduling, Deviation Se...
Adjudication of dispute regarding RERC (Forecasting, Scheduling, Deviation Se...Adjudication of dispute regarding RERC (Forecasting, Scheduling, Deviation Se...
Adjudication of dispute regarding RERC (Forecasting, Scheduling, Deviation Se...
 
MP-SLDC-DSM Account of Wind and Solar PSS for April, 2019
MP-SLDC-DSM Account of Wind and Solar PSS for April, 2019MP-SLDC-DSM Account of Wind and Solar PSS for April, 2019
MP-SLDC-DSM Account of Wind and Solar PSS for April, 2019
 
MP-DSM Account of Wind and Solar Pooling Stations for March, 2019
MP-DSM Account of Wind and Solar Pooling Stations for March, 2019MP-DSM Account of Wind and Solar Pooling Stations for March, 2019
MP-DSM Account of Wind and Solar Pooling Stations for March, 2019
 
Rajasthan SLDC - Statement Showing the RE DSM for the month of October-2018 Q...
Rajasthan SLDC - Statement Showing the RE DSM for the month of October-2018 Q...Rajasthan SLDC - Statement Showing the RE DSM for the month of October-2018 Q...
Rajasthan SLDC - Statement Showing the RE DSM for the month of October-2018 Q...
 
Rajasthan SLDC - Statement Showing the RE DSM for the month of November-2018 ...
Rajasthan SLDC - Statement Showing the RE DSM for the month of November-2018 ...Rajasthan SLDC - Statement Showing the RE DSM for the month of November-2018 ...
Rajasthan SLDC - Statement Showing the RE DSM for the month of November-2018 ...
 
Rajasthan SLDC - Statement Showing the RE DSM for the month of December-2018 ...
Rajasthan SLDC - Statement Showing the RE DSM for the month of December-2018 ...Rajasthan SLDC - Statement Showing the RE DSM for the month of December-2018 ...
Rajasthan SLDC - Statement Showing the RE DSM for the month of December-2018 ...
 
MP-SLDC-DSM Account of Wind and Solar Pooling Stations for the month of Febru...
MP-SLDC-DSM Account of Wind and Solar Pooling Stations for the month of Febru...MP-SLDC-DSM Account of Wind and Solar Pooling Stations for the month of Febru...
MP-SLDC-DSM Account of Wind and Solar Pooling Stations for the month of Febru...
 
MP_SLDC_RE_DSM_from-01-01-2019-to-31-01-2019_daily
MP_SLDC_RE_DSM_from-01-01-2019-to-31-01-2019_dailyMP_SLDC_RE_DSM_from-01-01-2019-to-31-01-2019_daily
MP_SLDC_RE_DSM_from-01-01-2019-to-31-01-2019_daily
 
Reply to reconnect's defamation notice - One can love it or hate it, but we r...
Reply to reconnect's defamation notice - One can love it or hate it, but we r...Reply to reconnect's defamation notice - One can love it or hate it, but we r...
Reply to reconnect's defamation notice - One can love it or hate it, but we r...
 

Recently uploaded

如何办理(SFSta文凭证书)美国旧金山州立大学毕业证学位证书
如何办理(SFSta文凭证书)美国旧金山州立大学毕业证学位证书如何办理(SFSta文凭证书)美国旧金山州立大学毕业证学位证书
如何办理(SFSta文凭证书)美国旧金山州立大学毕业证学位证书Fs Las
 
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书SD DS
 
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTSVIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTSDr. Oliver Massmann
 
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书Fir L
 
Constitutional Values & Fundamental Principles of the ConstitutionPPT.pptx
Constitutional Values & Fundamental Principles of the ConstitutionPPT.pptxConstitutional Values & Fundamental Principles of the ConstitutionPPT.pptx
Constitutional Values & Fundamental Principles of the ConstitutionPPT.pptxsrikarna235
 
An Introduction guidance of the European Union Law 2020_EU Seminar 4.pptx
An Introduction guidance of the European Union Law 2020_EU Seminar 4.pptxAn Introduction guidance of the European Union Law 2020_EU Seminar 4.pptx
An Introduction guidance of the European Union Law 2020_EU Seminar 4.pptxKUHANARASARATNAM1
 
如何办理(GWU毕业证书)乔治华盛顿大学毕业证学位证书
如何办理(GWU毕业证书)乔治华盛顿大学毕业证学位证书如何办理(GWU毕业证书)乔治华盛顿大学毕业证学位证书
如何办理(GWU毕业证书)乔治华盛顿大学毕业证学位证书SD DS
 
国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》
国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》
国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》o8wvnojp
 
如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书
如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书
如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书Fir L
 
POLICE ACT, 1861 the details about police system.pptx
POLICE ACT, 1861 the details about police system.pptxPOLICE ACT, 1861 the details about police system.pptx
POLICE ACT, 1861 the details about police system.pptxAbhishekchatterjee248859
 
昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书
昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书
昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书1k98h0e1
 
Model Call Girl in Haqiqat Nagar Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Haqiqat Nagar Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Haqiqat Nagar Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Haqiqat Nagar Delhi reach out to us at 🔝8264348440🔝soniya singh
 
如何办理伦敦南岸大学毕业证(本硕)LSBU学位证书
如何办理伦敦南岸大学毕业证(本硕)LSBU学位证书如何办理伦敦南岸大学毕业证(本硕)LSBU学位证书
如何办理伦敦南岸大学毕业证(本硕)LSBU学位证书FS LS
 
Arbitration, mediation and conciliation in India
Arbitration, mediation and conciliation in IndiaArbitration, mediation and conciliation in India
Arbitration, mediation and conciliation in IndiaNafiaNazim
 
Law360 - How Duty Of Candor Figures In USPTO AI Ethics Guidance
Law360 - How Duty Of Candor Figures In USPTO AI Ethics GuidanceLaw360 - How Duty Of Candor Figures In USPTO AI Ethics Guidance
Law360 - How Duty Of Candor Figures In USPTO AI Ethics GuidanceMichael Cicero
 
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.pptFINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.pptjudeplata
 
如何办理(uOttawa毕业证书)渥太华大学毕业证学位证书
如何办理(uOttawa毕业证书)渥太华大学毕业证学位证书如何办理(uOttawa毕业证书)渥太华大学毕业证学位证书
如何办理(uOttawa毕业证书)渥太华大学毕业证学位证书SD DS
 
如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
 如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书 如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书Sir Lt
 
John Hustaix - The Legal Profession: A History
John Hustaix - The Legal Profession:  A HistoryJohn Hustaix - The Legal Profession:  A History
John Hustaix - The Legal Profession: A HistoryJohn Hustaix
 
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书FS LS
 

Recently uploaded (20)

如何办理(SFSta文凭证书)美国旧金山州立大学毕业证学位证书
如何办理(SFSta文凭证书)美国旧金山州立大学毕业证学位证书如何办理(SFSta文凭证书)美国旧金山州立大学毕业证学位证书
如何办理(SFSta文凭证书)美国旧金山州立大学毕业证学位证书
 
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书
 
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTSVIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
 
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书
 
Constitutional Values & Fundamental Principles of the ConstitutionPPT.pptx
Constitutional Values & Fundamental Principles of the ConstitutionPPT.pptxConstitutional Values & Fundamental Principles of the ConstitutionPPT.pptx
Constitutional Values & Fundamental Principles of the ConstitutionPPT.pptx
 
An Introduction guidance of the European Union Law 2020_EU Seminar 4.pptx
An Introduction guidance of the European Union Law 2020_EU Seminar 4.pptxAn Introduction guidance of the European Union Law 2020_EU Seminar 4.pptx
An Introduction guidance of the European Union Law 2020_EU Seminar 4.pptx
 
如何办理(GWU毕业证书)乔治华盛顿大学毕业证学位证书
如何办理(GWU毕业证书)乔治华盛顿大学毕业证学位证书如何办理(GWU毕业证书)乔治华盛顿大学毕业证学位证书
如何办理(GWU毕业证书)乔治华盛顿大学毕业证学位证书
 
国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》
国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》
国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》
 
如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书
如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书
如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书
 
POLICE ACT, 1861 the details about police system.pptx
POLICE ACT, 1861 the details about police system.pptxPOLICE ACT, 1861 the details about police system.pptx
POLICE ACT, 1861 the details about police system.pptx
 
昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书
昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书
昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书
 
Model Call Girl in Haqiqat Nagar Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Haqiqat Nagar Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Haqiqat Nagar Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Haqiqat Nagar Delhi reach out to us at 🔝8264348440🔝
 
如何办理伦敦南岸大学毕业证(本硕)LSBU学位证书
如何办理伦敦南岸大学毕业证(本硕)LSBU学位证书如何办理伦敦南岸大学毕业证(本硕)LSBU学位证书
如何办理伦敦南岸大学毕业证(本硕)LSBU学位证书
 
Arbitration, mediation and conciliation in India
Arbitration, mediation and conciliation in IndiaArbitration, mediation and conciliation in India
Arbitration, mediation and conciliation in India
 
Law360 - How Duty Of Candor Figures In USPTO AI Ethics Guidance
Law360 - How Duty Of Candor Figures In USPTO AI Ethics GuidanceLaw360 - How Duty Of Candor Figures In USPTO AI Ethics Guidance
Law360 - How Duty Of Candor Figures In USPTO AI Ethics Guidance
 
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.pptFINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
 
如何办理(uOttawa毕业证书)渥太华大学毕业证学位证书
如何办理(uOttawa毕业证书)渥太华大学毕业证学位证书如何办理(uOttawa毕业证书)渥太华大学毕业证学位证书
如何办理(uOttawa毕业证书)渥太华大学毕业证学位证书
 
如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
 如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书 如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
 
John Hustaix - The Legal Profession: A History
John Hustaix - The Legal Profession:  A HistoryJohn Hustaix - The Legal Profession:  A History
John Hustaix - The Legal Profession: A History
 
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
 

Punjab State Electricity Regulatory Commission (Forecasting, Scheduling, Deviation Settlement and Related Matters of Solar and Wind Generation Sources) Regulations, 2019

  • 1. PUNJAB GOVT. GAZ. (EXTRA), JANUARY 7, 2019 (PAUSA 17, 1940 SAKA)1966Regd. No. NW/CH-22 Regd. No. CHD/0092/2018-2020 EXTRAORDINARY Published byAuthority CHANDIGARH, MONDAY, JANUARY7, 2019 (PAUSA17, 1940 SAKA) (1966) THE PUNJAB STATE ELECTRICITY REGULATORY COMMISSION NOTIFICATION 7th January, 2019 No.PSERC/Secy/Regu.135.- In exercise of the powers conferred under Section 181of the Electricity Act, 2003 (CentralAct 36 of 2003), and all other powers enabling it in this behalf, and after previous publication, the Punjab State Electricity Regulatory Commission hereby makes the following regulations, namely: 1.0 Short title and commencement 1.1 These regulations may be called the Punjab State Electricity Regulatory Commission (Forecasting, Scheduling, Deviation Settlement and Related Matters of Solar and Wind Generation Sources) Regulations, 2019. 1.2 These regulations shall extend to whole of the State of Punjab. 1.3 These regulations shall come into force from the date of notification in the official Gazette of the State. Provided that Forecasting and Scheduling in accordance with these Regulations shall come in to force six months from the date of notification of these Regulations while the commercial mechanism regarding Deviation Settlement specified in these Regulations shall come into force from the date to be notified separately by the Commission. 2.0 Definitions and Interpretation 2.1 In these Regulations, unless the context otherwise requires – (a) ‘Absolute Error’ means the absolute value of the error in actual generation of wind or solar generators with reference to scheduled generation and the ‘Available Capacity (AvC), as calculated using the following formula for each 15minute time block; Absolute Error (%)= [Actual Generation-Scheduled Generation]X100 (AvC) (b) ‘Act’ means the Electricity Act, 2003 (36 of 2003); (c) ‘Actual drawal’ in a time-block means the electricity drawn by a buyer, as the case may be, as measured by the interface meters; (d) ‘Actual injection’ in a time-block means electricity generated or supplied by the seller, as the case may be, measured by the Interface meters;
  • 2. PUNJAB GOVT. GAZ. (EXTRA), JANUARY 7, 2019 (PAUSA 17, 1940 SAKA) 1967 (e) 'Available Capacity (AvC)' for wind or solar generators, which are State Entities, means the cumulative rating of wind turbines or solar inverters that are capable of generating power in a given time-block; (f) ‘Beneficiary’ means a person purchasing electricity generated from a generating station including a captive generating station; (g) ‘Buyer’ means a person, including beneficiary, distribution licensee or open access consumer, purchasing electricity through a transaction scheduled in accordance with the regulations applicable for short-term open access, medium-term open access and long-term access; (h) ‘Central Commission (CERC)’ means Central Electricity Regulatory Commission referred to in sub- section (1) of Section 76 of the Act; (i) ‘Commission’ means Punjab State Electricity Regulatory Commission constituted under sub-section (1) of section 82 of the Act; (j) ‘Deviation’ in a time-block for a Seller means its total actual injection minus its total scheduled generation and for a Buyer means its total actual drawal minus its total scheduled drawal, (k) ‘Existing RE Generator’ shall mean Wind or Solar Generator that has been commissioned prior to the date of notification of these Regulations; (l) ‘Forecasting’ means the projection of likely future electricity generation based on scientific analysis of meteorological data and other relevant parameters; (m) ‘Gaming’ in relation to these regulations, shall mean an intentional mis-declaration of available capacity or schedule by any seller in order to make an undue commercial gain through deviation charges; (n) ‘Grid Code or State Grid Code’ means the Grid Code specified by the Commission under clause (h) of sub-section (1) of Section 86 of the Act; (o) ‘Indian Electricity Grid Code (IEGC)’ means the Grid Code specified by CERC under clause (h) of sub-section (1) of section 79 of the Act; (p) ‘Interface meter’means the interface meter as defined in Central Electricity Authority (Installation and Operation of Meters) Regulations, 2006, as amended from time to time; (q) ‘Interconnection/Interface Point’ means a point at which an individual wind/solar generating plant or a group of such generating plants are connected to the transmission or distribution system, as the case may be; (r) ‘New RE Generator’ shall mean Wind or Solar Generator that has been commissioned subsequent to the date of notification of these Regulations; (s) ‘Open Access Regulations’ means Punjab State Electricity Regulatory Commission (Terms and Conditions of Intra-State Open Access) Regulations, 2011, as amended from time to time; (t) ‘Pooling Station’ means the sub-station where pooling of generation of individual wind or solar generators is done for interfacing with the next higher voltage level: Provided that where there is no separate pooling station for a wind/solar generator and the generating station is connected through common/dedicated feeder and terminated at a Sub Station of distribution company/STU, the sub-station of the distribution company/STU shall be considered as the pooling station for such wind or solar generator, as the case may be; (u) ‘Qualified Coordinating Agency (QCA)’ means the agency coordinating on behalf of wind/solar generators connected to a pooling station to perform the functions and discharge the obligations as specified in these regulations; (v) ‘Scheduled Generation’ at any time or for a time block or any period means schedule of generation in MW or MWh ex-bus given by the State Load Despatch Centre (SLDC);
  • 3. PUNJAB GOVT. GAZ. (EXTRA), JANUARY 7, 2019 (PAUSA 17, 1940 SAKA)1968 (w) ‘Scheduled Drawal’ at any time or for a time block or any period time block means schedule of despatch in MW or MWh ex-bus given by the State Load Despatch Centre (SLDC); (x) ‘Seller’ means a person, including a generating station, supplying electricity through a transaction scheduled in accordance with the regulations applicable for short-term open access, medium-term open access and long-term access; (y) ‘State Entity’ means an entity which is in the SLDC control area and whose metering and energy accounting is done at the State level; (z) ‘State Load Despatch Centre’ or ‘SLDC’ means the Load Despatch Centre of the State established under sub section (1) of section 31 of theAct, responsible for co-ordinating scheduling of the state entities in accordance with the provisions of State Grid Code; (aa) ‘State Pool Account’ means a separate account to be maintained by SLDC for receipts and payments on account of deviation, specified by the Commission; (bb) ‘Time-Block’ means a time block of 15 minutes or such shorter duration, as may be specified by the Commission, for which specified electrical parameters and quantities are recorded by Special Energy Meter, with first time block starting at 00.00 hrs. 2.2 Save as aforesaid and unless repugnant to the context or the subject-matter otherwise required, words and expressions used in these regulations and not defined, but defined in theAct, or the Grid Code or any other regulations of this Commission shall have the meaning assigned to them respectively in the Act or the Grid Code or any other regulation. 3.0 General 3.1 Objective The objective of these regulations is to facilitate large scale grid integration of solar and wind generating stations while maintaining grid stability and security as envisaged under the State Grid Code, through Forecasting, Scheduling and Commercial Mechanism for Deviation Settlement of these generators. 3.2 Applicability These Regulations shall be applicable to all wind and solar generators with individual capacity of 5 MW and above connected to the State Transmission System or distribution system or wind and solar generators of any capacity connected through pooling stations to the State Transmission System or distribution system with combined capacity of 5 MW and above, supplying power to the distribution company (ies) or to the third party through open access or for captive consumption through open access within or outside the State. 4.0 Appointment of Qualified Coordinating Agency (QCA) Qualified CoordinatingAgency (QCA) is an agency appointed by the wind/solar generators, connected to a pooling station, for coordinating on their behalf with SLDC. Each pooling station shall have one QCA who may be one of the generators or any other mutually agreed agency to perform the functions and discharge the obligations as specified in these regulations. The QCA shall be treated as a State Entity registered with SLDC in accordance with the Detailed Procedure prescribed in Regulation 5.9 of these regulations. QCA shall be single point of contact between generators and SLDC. The QCA shall perform the following functions; • Coordinate for schedules with periodic revisions on behalf of all the Wind/Solar Generators connected to a pooling station. • Responsible for coordination with STU/SLDC for metering, data collection/ transmission, communication. • Undertake commercial settlement on behalf of the generators of such charges pertaining to generation, including payment of Deviation Charges to the State Pool Accounts through SLDC.
  • 4. PUNJAB GOVT. GAZ. (EXTRA), JANUARY 7, 2019 (PAUSA 17, 1940 SAKA) 1969 • Undertake de-pooling of payments received/payable on behalf of the generators of the pooling station from/to the State Pool Account and settling them with individual generators; • Undertake commercial settlement of any other charges on behalf of the generators, as may be mandated from time to time. 5.0 Forecasting and Scheduling Code 5.1 This Code specifies the methodology for Day-Ahead, Week ahead scheduling of wind and solar energy generators, which are connected to the State Grid and re-scheduling them on one and half hourly basis and methodology of handling deviations of such wind and solar energy generators. 5.2 Appropriate Interface meters shall be provided in accordance with CEA Metering Regulations for energy accounting. Telemetry/Communication System and the Data Acquisition System shall also be provided for transfer of information to the concerned SLDC by the generators or Qualified Coordinating Agency (QCA) appointed by it. 5.3 Wind and solar generators, either by themselves or represented by QCAs, shall mandatorily provide to the concerned SLDC, in a format prescribed by the SLDC, the technical specifications of the generating units and all other associated equipment of wind/solar generator at the beginning and thereafter, whenever there is any change in such technical specifications. The data relating to the power generation parameters and weather related data, as applicable, shall also be mandatorily provided by such generators or QCA appointed by it, to the concerned SLDC in real time. 5.4 Forecasting shall be done by every wind and solar generator connected to the Grid, either by itself or by a QCA on its behalf. The SLDC is also mandated to undertake forecasting of wind and solar power that is expected to be injected into the state grid, by engaging forecasting agency (ies), if required. The forecast by the SLDC shall be with the objective of ensuring secured grid operation by planning for requisite balancing resources. The forecast by a wind or solar generator or QCA, as the case may be, shall be generator centric. The wind or solar generator or QCA will have the option of accepting the SLDC’s forecast for preparing its schedule or provide the SLDC with a schedule based on its own forecast. The SLDC shall recover the charges for such forecasting service, as may be approved by the Commission and such amount shall be treated as ‘other income’in theAggregate Revenue Requirement” of SLDC. The QCA shall coordinate the aggregation of schedules of all its generators connected to a pooling station and communicate the same to the SLDC. Provided that the existing wind and solar generators or QCA on their behalf shall establish the forecasting tools and furnish day ahead, week-ahead forecasting and scheduling to SLDC within six months from the date of coming into force of these regulations. Provided further that all new wind and solar generators or QCA on their behalf, shall establish the forecasting tools before commissioning of the plant and connecting to the State Transmission System or Distribution system, as the case may be. 5.5 Every wind and solar generator or a QCA shall submit a day ahead and week ahead schedule for each generating station or each pooling station, as the case may be. Day ahead schedule shall contain wind or solar energy generation schedule at intervals of fifteen (15) minutes time-block for next day, starting from 00.00 hours of the day and prepared for all ninety six (96) time blocks of the day. Week-ahead schedule shall contain the same information for next seven days. 5.6 The schedule of wind and solar generators connected to the State Grid, excluding collective transactions, may be revised by giving advance notice to SLDC. Such revisions shall be effective from fourth (4th) time block, the first being the time-block in which notice was given. There may be one revision for each time slot of one and half hours starting from 00.00 hours of particular day subject to maximum of sixteen (16) revisions during the day.
  • 5. PUNJAB GOVT. GAZ. (EXTRA), JANUARY 7, 2019 (PAUSA 17, 1940 SAKA)1970 5.7 Any commercial impact on account of deviation from schedule based on forecast shall be borne by the wind and solar electric generator, either directly or transacted via the representing QCA. 5.8 The plan for data telemetry, formats of forecast submission and other modalities and requirements shall be stipulated in the Detailed Procedure to be submitted by the SLDC within three months, which the Commission shall endeavor to approve within a month thereafter. Provided that SLDC shall undertake stakeholder consultation by uploading the Draft Procedure on SLDC’s website before submission to the Commission for approval. 5.9 The Detailed Procedure shall address the following aspects: a) The procedure and requirements, including the payment of fees and penalties, for the registration and de-registration of QCAs by the SLDC. b) The information and data, and the formats on which the information/data is required by the SLDC from the wind/solar generators or QCAs, as the case may be. c) The mode and protocol of communication for exchange of information and data between the wind/ solar generators or QCAs and the SLDC. d) The guidelines for energy and deviation accounting of Wind and Solar energy transactions under the State energy accounting framework, with illustrative examples, in accordance with the principles specified in these Regulations. e) The mechanism for monitoring compliance of the Forecasting and Scheduling Code. f) The default conditions in the State Deviation Pool Settlement by QCAs and their treatment. 5.10 Treatment for Gaming Any intentional mis-declaration ofAvailable Capacity or schedule to the SLDC for its own undue commercial gain through deviation charges or that of a generator shall be considered as gaming and shall be liable to action under appropriate provisions of the Act or the Regulations. 6.0 Commercial and Deviation Settlement 6.1 Deviation Settlement of Intra-State Transactions: (i) The wind or solar generators, which are state entities, connected to the State Grid and selling power within the State shall be paid by the buyers as per actual generation whereas the Deviation Settlement shall be undertaken as under; (ii) In the event of actual generation of a Solar or Wind generating station or a pooling station, as the case may be, being less or more than the scheduled generation, the deviation charges for shortfall or excess generation shall be payable by the wind and solar generator or the QCA on its behalf, as the case may be, to the State Pool Account, as given in Table–I below: TABLE-I Deviation Charges in case of under-injection or over injection, by Wind/Solar Generating Stations for sale of power within State: S. No. Absolute Error in the Deviation Charges payable by Wind/Solar Generating Stations to State 15-minute time block PoolAccount 1 <= 15% None 2 >15% but <=25% (At the Rs 0.50 per unit for shortfall or excess energy for Absolute Error beyond 15% and upto 25%) 3 >25% but <=35% (At the Rs 0.50 per unit for shortfall or excess energy for Absolute Error beyond 15% and upto 25%) + (At the Rs 1.00 per unit for balance energy beyond 25% and up to 35%)
  • 6. PUNJAB GOVT. GAZ. (EXTRA), JANUARY 7, 2019 (PAUSA 17, 1940 SAKA) 1971 4 >35% (At the Rs 0.50 per unit for shortfall or excess energy for Absolute Error beyond 15% and upto 25%) + (At the Rs 1.00 per unit for shortfall or excess energy beyond 25% and up to 35%) + (At the Rs 1.50 per unit for balance energy beyond 35%) (iii) State Load Despatch Centre or the Secretariat of State Power Committee, as the case may be, shall maintain separate records and account of time-block wise schedules, actual generation and deviations for all individual wind and solar generators connected directly to the grid and at the level of Pooling Station, if RE generators are connected to State Transmission System or distribution system. (iv) The QCA shall undertake de-pooling of the energy deviation as well as deviation charges to each generator in proportion to actual generated units for each time block for each generator 6.2 Deviation Settlement for Inter-State Transactions: The wind or solar generators, which are state entities undertaking inter-state transactions shall be paid as per schedule generation in accordance with CERC (Deviation Settlement Mechanism & Related Matters) Regulations, 2014, as amended from time to time, as under: (i) In the event of actual generation being less than the scheduled generation, the deviation charges for shortfall shall be payable by such wind or solar generator or QCA on their behalf , which are state entities undertaking inter-state transactions into State Pool Account as given in Table–II of Appendix-1. (ii) In the event of actual generation being more than the scheduled generation, the deviation charges for excess generation shall be payable to such wind or solar generator or QCA on their behalf, which are state entities undertaking inter-state transactions from the State Pool Account as given in Table–III of Appendix-1. 6.3 Deviation Settlement for Inter-State and Intra-State Transactions (i) The SLDC shall provide separate Energy and Deviation accounts for inter-state and intra-state transactions to QCA or individual wind or solar generator, as the case may be. (ii) The wind or solar generators, as state entities, undertaking intrastate transactions and inter-state transactions shall be allowed provided that such generators are connected to separate feeders at LV side of the Pooling Substation and metering, scheduling, energy accounting and deviation settlement account for such wind or solar generators are maintained separately. 7.0 Implementation procedure 7.1 Metering Interface Energy Meters (IEMs) shall be installed by STU/SPD as per CEA Metering Regulations. Every Solar and Wind generating plant or a pooling station shall have a Special Energy Meter (SEM) at the interface points capable of recording and storing all the load survey and billing parameters for every 15-minute time blocks or such shorter duration as may be specified by the Commission, in accordance with the CEA Regulations governing metering. Automated Meter Reading (AMR) system shall be used for communicating interface data at SLDC. Internal clock of the interface meter shall be time synchronised with GPS. Weekly meter readings shall be forwarded to the SLDC in addition to data provided through Supervisory ControlAnd DataAcquisition (SCADA) for energy accounting. The IEMs shall comply with the provisions of Central Electricity Authority (Installation and Operation of Meters) Regulations, 2006, as amended from time to time. 7.2 Telemetry All Wind and Solar generators shall provide data telemetry at the Turbine/Inverter level to SLDC and shall ensure the correctness of the real time data and undertake the corrective actions, if required.
  • 7. PUNJAB GOVT. GAZ. (EXTRA), JANUARY 7, 2019 (PAUSA 17, 1940 SAKA)1972 Frequency of real time data updation to be shared with SLDC shall be 10 second or less as per prevailing practice being followed by RLDCs. Further, turbine/inverter outage plan shall be forwarded to SLDC. 7.3 Communication (i) All Solar and Wind generators or QCAs, as the case may be, whose scheduling is done by SLDC shall follow Central Electricity Regulatory Commission (Communication Systems for Inter-state Transmission of Electricity) Regulations, 2017 for Communication infrastructure to be used for data communication, tele-protection of power system at the State level till the Commission notifies separate regulations on Communication systems for State entities. (ii) All Solar and Wind generators or the QCAs, as the case may be, shall abide by any guidelines, technical standards, protocols for communication system etc which may be notified by CEA under CERC (Communication Systems for Inter-state Transmission of Electricity) Regulations, 2017, as applicable to them. (iii) A preparatory window upto 6 months from the date of notification of these regulations has been provided to wind and solar generator or their QCA to ensure installation of data measurement and telemetry equipment and for the SLDC to prepare its systems and team for receipt of regular data. During this period, SLDC shall evolve a detailed procedure for Data Telemetry and Communication requirement, necessary formats for furnishing forecasts and scheduling data to SLDC, formats for technical parameters and other details of Solar/Wind generators and solicit the comments of stakeholders and seek the approval of the Commission as specified in Regulation 5.8. 8. Deviation Accounting and Settlement of Deviation Charges The procedure for computation of Deviation Charges shall be as under: 8.1 The Deviation Charges (D) payable/receivable for the State as a whole at State periphery by distribution licensee/OA consumers/conventional generators/RE generators (pooling station) shall be computed first by SLDC in accordance with CERC (Deviation Settlement Mechanism and related matters) Regulations, 2014, as amended from time to time, read with Commission’s order dated 28.11.2014 in petition no. 27 of 2014, till Intra-State Deviation Settlement Mechanism Regulations are notified by the Commission. 8.2 The SLDC shall compute the Absolute Error, i.e. the difference between the scheduled and the actual energy injected, in respect of each Pooling Sub-Station and each Generator with capacity more than 5 MW which feeds the energy directly to Sub-Station, and shall accordingly determine the deviation charges payable by RE generators/pooling station (R1) in accordance with Regulations 6. 8.3 Deviation charges (D) shall be allocated amongst the distribution licensee/OA consumers/conventional generators/RE generators (pooling station) in proportion to their respective deviation.Assuming the share of the State level deviation charges for RE generators as D4 and receipt of deviation charges from RE generators/pooling stations as R1, the actual commercial impact for the State as a result of deviation of RE generation shall be D4-R1. At the end of the year, if this amount is greater than zero, the same can be refunded to the State Pool Account from PSDF/NCEF or from the alternative funding mechanism, as may be approved by the Commission. 8.4 The QCA shall pay the Deviation Charges to the SLDC, and collect it from the concerned Generators in proportion to their actual generation as per regulation 6.1. 8.5 The Deviation Charges shall be paid in to State Pool Account by the generators or QCA, as the case may be, within ten days from the issue of deviation charges statement by the SLDC. If the payments against deviation charges are delayed beyond 12 days from the date of issue of deviation charges statement by SLDC, then the defaulting generator shall pay simple interest @ 0.04% for each day of delay.
  • 8. PUNJAB GOVT. GAZ. (EXTRA), JANUARY 7, 2019 (PAUSA 17, 1940 SAKA) 1973 8.6 All payments to the State entities on account of charges for deviation shall be made within 2 working days of receipt of the payments in State Pool account. 8.7 In case the Wind or solar generator defaults in payment to QCAthen QCAshall inform SLDC about such default and request SLDC to disconnect such defaulting generator from the grid. 9. Compliance with instructions of Load Despatch Centre or Curtailment of schedule Notwithstanding anything specified in these Regulations, the sellers and the buyers shall strictly follow the instructions of the State Load Despatch Centre on injection and drawal in the interest of grid security and grid discipline. In the event of contingencies, transmission constraints, congestion in network, threat to system security, the transaction of RE generators already scheduled by SLDC may be curtailed as per the provisions of State Grid Code for ensuring secure and reliable system operation. Any curtailment imposed on energy injection for reliable and secure grid operation in emergent situation shall be communicated by SLDC to generators and QCAs. In case SLDC fails to communicate about the curtailment to generators/QCAs, deviation charges shall not be levied. 10 Practice Directions Subject to the provisions of the Act, the Commission may issue Practice Directions with regard to the implementation of these Regulations. 11. Power to Relax The Commission may by general or special order, for reasons to be recorded in writing, and after giving an opportunity of hearing to the parties likely to be affected by grant of relaxation, may relax any of the provisions of these Regulations on its own motion or on an application made before it by an interested person. 12. Power to remove difficulties If any difficulty arises in giving effect to the provisions of these Regulations, the Commission may, by general or specific order, make such provisions not inconsistent with the provisions of the Act, as may appear to be necessary for removing the difficulty. Sd/- Secretary Punjab State Electricity Regulatory Commission
  • 9. PUNJAB GOVT. GAZ. (EXTRA), JANUARY 7, 2019 (PAUSA 17, 1940 SAKA)1974 Appendix 1 Deviation Charges for under- or over-injection by Solar and Wind Generators connected to the Intra-State Transmission network and supplying or consuming power outside Punjab 1. In the event of actual generation being lesser than the scheduled generation, the deviation charges for shortfall shall be payable by such wind or solar generator which are state entities undertaking inter-state transactions into State Deviation Pool Account as given in Table – II. TABLE-II Deviation Charges in case of under injection by Wind/Solar Generating Stations as State Entities undertaking Inter-state transactions: S Absolute Error in Deviation Charges payable by Wind/Solar Generating Stations No. the 15-minute time to State Pool Account block 1 <= 15% At the Fixed Rate for the shortfall energy for absolute error upto 15% 2 >15% but <=25% (At the Fixed Rate for the shortfall energy for absolute error upto 15%) + (110% of the Fixed Rate for balance energy beyond 15% and upto 25%) 3 >25% but <=35% (At the Fixed Rate for the shortfall energy for absolute error upto 15%) + (110% of the Fixed Rate for balance energy beyond 15% and upto 25%) + (120% of the Fixed Rate for balance energy beyond 25% and upto 35%) 4 >35% (At the Fixed Rate for the shortfall energy for absolute error upto 15%) + (110% of the Fixed Rate for balance energy beyond 15% and upto 25%) + (120% of the Fixed Rate for balance energy beyond 25% and upto 35%) + (130% of the Fixed Rate for balance energy beyond 35%) 2. In the event of the actual generation being more than the scheduled generation, the Deviation Charges for excess generation shall be payable to the wind or solar generators which are state entities undertaking inter-state transactions from State Deviation Pool Account as given in Table – III. TABLE-III. Deviation Charges in case of over injection by Wind/Solar Generating Stations as State Entities undertaking Interstate transactions: S. Absolute Error in Deviation Charges payable to Wind/Solar Generating Stations No. the 15-minute time from State Pool Account block 1 <= 15% At the Fixed Rate for the excess energy upto 15% 2 >15% but <=25% (At the Fixed Rate for the excess energy upto 15%) + (90% of the Fixed Rate for balance energy beyond 15% and upto 25%) 3 >25% but <=35% (At the Fixed Rate for the excess energy upto 15%) + (90% of the Fixed Rate for balance energy beyond 15% and upto 25%) + (80% of the Fixed Rate for balance energy beyond 25% and upto 35%) 4 >35% (At the Fixed Rate for the excess energy upto 15%) + (90% of the Fixed Rate for balance energy beyond 15% and upto 25%) + (80% of the Fixed Rate for balance energy beyond 25% and upto 35%) + (70% of the Fixed Rate for balance energy beyond 35%) 3. Where the Fixed Rate referred under Table-II and Table-III is the Power Purchase Agreement (PPA) rate as determined by the Commission under section 62 of the Act or adopted by the Commission under
  • 10. PUNJAB GOVT. GAZ. (EXTRA), JANUARY 7, 2019 (PAUSA 17, 1940 SAKA) 1975 section 63 of the Act. In case of multiple PPAs, the weighted average of the PPA rates shall be taken as the Fixed Rate. The wind and solar generators shall furnish the PPA rates on affidavit for the purpose of Deviation charge account preparation to SLDC supported by copy of the PPA. 4. The Fixed Rate for Solar and Wind captive power plants or OpenAccess generators selling power, which is not accounted towards Renewal Purchase Obligation (RPO) compliance of the buyer, shall be the Average Power Purchase Cost (APPC) rate at the National level, as may be determined by the Central Commission from time to time. 5. With regard to inter-state wheeling transactions of Wind and Solar Generating stations as State Entities, for balancing of deemed Renewable Purchase Obligation (RPO) compliance of buyers with respect to schedule, deviations by all wind and solar generators, which are state entities, shall first be netted off for the entire pool on a monthly basis and any remaining shortfall in renewable energy generation must be balanced through purchase of equivalent solar and non-solar Renewable Energy Certificates (RECs), as the case may be, by SLDC by utilising funds from the Pool Account. For positive balance of renewable energy generation, equivalent notional RECs shall be credited to the DSM Pool and carried forward for settlement in future. 6. State Load Despatch Centre or the Secretariat of State Power Committee, as the case may be, shall maintain separate records and account of time-block wise schedules, actual generation and deviations for all generators, including wind and solar generators. 1682/1-2019/Pb. Govt. Press, S.A.S. Nagar