SlideShare a Scribd company logo
1 of 5
Download to read offline
4 Indian Wind Power Dec. 2019 - Jan. 2020
1.	 Introduction
Forecasting and Scheduling (F&S) of solar and wind power
generation is required to manage the grid network for maximum
utilization of renewable energy. Hence the concept of forecasting
and scheduling (F&S) of renewable energy generators and the
commercial settlement was introduced in Indian context by
CERC through Indian Electricity Grid Code (IEGC), 20101 and
the Renewable Regulatory Fund mechanism2. Due to several
implementation issues, the mechanism was never made
operational. To formulate an implementable framework, CERC
also issued 2nd amendment to regulation for the Deviation
Settlement Mechanism (DSM) and other related matters3.
After CERC regulation, Forum of Regulators (FOR)4 and other
state regulators issued or drafted regulation related to the
forecasting and scheduling of wind and solar power generation.
Unlike DSM penalty of intrastate forecasting and scheduling of
wind and solar power generation, the ‘actual penalty’ and the
‘DSM penalty’ of wind and solar power generation in interstate
CERC regulation are different. This article briefly focuses on
the theoretical and evidence based understanding of ‘Actual
Penalty’ and ‘DSM Penalty’ in case of interstate regulation.
2.	 Theoretical Framework
In interstate regulation, the payment is on schedule generation,
unlike the intrastate in which the payment is on actual
generation. Hence, to calculate the actual penalty due F&S in
case of interstate regulation, we can state that,
Actual Penalty =
(Schedule Generation × PPA rate + DSM Penalty) -
Actual Generation × PPA rate	 (1)
Here DSM penalty is negative when payable to the pool by
the generators and positive when payable by the pool to the
RE generators. By simple algebraic manipulation (1) can be
written as,
Actual Penalty =
DSM Penalty - (Actual Generation - Schedule generation) ×
PPA rate	 (2)
Actual Penalty and Deviation
Settlement Mechanism (DSM)
Penalty in Interstate F&S
Regulation for RE Generators Abhik Kumar Das
Technical Director
del2infinity Energy Consulting
contact@del2infinity.xyz
Sandeep Suman
Assistant Manager (E&M)
Coal India Limited
Which transforms into,
Actual Penalty (P) =
DSM Penalty (∆) - Energy Deviation (δ) × PPA rate (p)	 (3)
i.e. P = ∆ - δp	(4)
Here (4) can be viewed as the fundamental equation to
calculate the actual penalty in interstate F&S regulation. Since
(4) is true for each of the time-block, for all time-blocks we
can state that,
∑P = ∑∆ - p∑δ
If we replace, ∑P as P, ∑∆ as ∆ and ∑δ as δ, (4) remains
same, and the total actual penalty (monthly or weekly) can be
calculated from the total DSM (monthly or weekly) and total
energy deviation (monthly or weekly). Interestingly, total DSM
and total energy deviation value (monthly or weekly) is readily
available at ERC sites, and the actual penalty can be calculated
if the PPA rate (p) is known.
Hence (4) can be viewed as a fundamental equation to
calculate the actual penalty in interstate regulation.
Since P = ∆ - δp , it is easy to state that the actual penalty due
to the deviation (P) is not the DSM penalty (∆).
Since the actual penalty (P) is always payable, it is always
negative. Hence DSM penalty (∆) and energy deviation (δ) are
of same sign, as shown in Table I.
Table I: DSM Penalty vs Energy Deviation
DSM
penalty
(∆)
Energy
deviation
(δ)
Comment
+ DSM
Receivable
+ Actual >
Schedule
Under-schedule
/ Over-injection
- DSM
Payable
- Actual <
Schedule
Over-schedule
/ Under-
injection
THE NEED
FOR SPEED
Learn more: WeKnowBlades.lmwindpower.com
Competition in the wind industry has never been fiercer.
Our customers require larger rotors, faster than ever.
Even with up to seven new blade developments every year,
we always deliver on time
As blade specialists, we know what it takes to:
• Ensure the fastest and safest product launch: Smooth and seamless
interaction with our customers’ development teams allows us to convert
numerous load iterations into tangible and competitive blade designs
• Deliver prototypes fast and on time: Our product development process has
been proven time and time again – it simply works. In-house testing andcertification
expertise give us the flexibility to respond quickly to customer demands
• Be a genuine global supplier: With 15 global factories, we are present in
all major wind markets, ensuring fast launches on time
6 Indian Wind Power Dec. 2019 - Jan. 2020
Table II: DSM for Inter-State Regulation and Mathematical Framework
Payment on Schedule Generation Payment on Schedule Generation
Abs Error For Under-Injection
(Actual < Schedule)
Deviation Charge payable by RE generators
∆
For Over-Injection
(Actual > Schedule)
Deviation Charge payable to RE generators
∆
0 – 15% At the Fixed Rate for the shortfall energy upto for
absolute error upto 15%
δp
At the Fixed Rate for the excess energy upto for
absolute error upto 15%
δp
15% - 25% At the Fixed Rate for the shortfall energy for
absolute error upto 15%
+
110% of the Fixed Rate for balance energy
beyond 15% and upto 25%
0.15 Ap
+
[δ - 0.15A ] X (1.1 p)
At the Fixed Rate for the excess energy for
absolute error upto 15%
+
90% of the Fixed Rate for balance energy
beyond 15% and upto 25%
0.15 Ap
+
[δ - 0.15A ] X (0.9 p)
25%-35% At the Fixed Rate for the shortfall energy for
absolute error upto 15%
+
110% of the Fixed Rate for balance energy
beyond 15% and upto 25%
+
120% of the Fixed Rate for balance energy
beyond 25% and upto 35%
0.15 Ap
+
0.1 A (1.1p)
+
[δ - 0.25A ] X (1.2 p)
At the Fixed Rate for the excess energy for
absolute error upto 15%
+
90% of the Fixed Rate for balance energy
beyond 15% and upto 25%
+
80% of the Fixed Rate for balance energy
beyond 25% and upto 35%
0.15 Ap
+
0.1 A (0.9p)
+
[δ - 0.25A ] X (0.8 p)
>35% At the Fixed Rate for the shortfall energy for
absolute error upto 15%
+
110% of the Fixed Rate for balance energy
beyond 15% and upto 25%
+
l20% of the Fixed Rate for balance energy
beyond 25% and upto 35%
+
l30% of the Fixed Rate for balance energy
beyond 35%
0.15 Ap
+
0.1 A (1.1p)
+
0.1 A (1.2p)
+
[δ - 0.35A ] X (1.3 p)
At the Fixed Rate for the excess energy for
absolute error upto 15%
+
90% of the Fixed Rate for balance energy
beyond 15% and upto 25%
+
80% of the Fixed Rate for balance energy
beyond 25% and upto 35%
+
70% of the Fixed Rate for balance energy
beyond 35%
0.15 Ap
+
0.1 A (0.9)
+
0.1 A (0.8p)
+
[δ - 0.35A ] X (0.7 p)
7Indian Wind PowerDec. 2019 - Jan. 2020
(a) (b)
Figure 1: Shows the percentage of energy deviation vs (a) DSM penalty per unit capacity and
(b) Actual penalty per unit capacity as per the Interstate regulation using the equation in Table II.
Figure 2(a) shows the energy deviation (MW-Hr) vs (a)Weekly DSM Penalty and 2(b) Weekly Actual Penalty for
7 different generators at SRPC. The bold black curve in 2(b) shows the average trend line.
Since different RE generators are of different capacities, to
normalize the calculation, let divide (4) by the available capacity
(AvC), i.e.
= −
Where is the penalty per unit capacity, is DSM per unit
capacity and represents the percentage in energy deviation.
Hence, as per interstate F&S regulation, the equation relating
‘DSM penalty’ and ‘percentage in energy deviation’ can be
represented as Table II.
3.	 Results and Discussion
Using the equation in Table II, the percentage of energy
deviation vs DSM penalty per unit capacity for different PPA
rate (p) can be shown as Figure 1(a). As shown in figure
1(a), when the energy deviation is positive (negative), the
DSM penalty is positive (negative). It is interesting to see that
the curve representing DSM penalty vs. energy deviation is
continuous, though the function seems to be an odd function
(f(-x) = - f(x)), the curve is not an odd function, i.e. for same
energy deviation in the positive and negative direction the DSM
penalty for under-schedule and over-schedule are not same
( f (-δ) ≠ -f (δ) ).
8 Indian Wind Power Dec. 2019 - Jan. 2020
The Actual Penalty vs energy deviation is shown in figure 1(b)
for different values of PPA rate (p). Here it is interesting to see
that the curve is symmetric about the y-axis and it is an even
function (f(-x) = f(x)). Hence, for same energy deviation in the
positive and negative direction the Actual penalty for under-
schedule and over-schedule are same (f(-δ) = f(δ)). Hence,
as per interstate regulation, if the forecast is over-scheduled or
under-scheduled, the actual penalty remains same for same
energy deviation in positive or negative direction.
The theoretical structure of ‘Actual Penalty’ and ‘DSM Penalty’ is
validated by evidence based data of 7 different RE generators
of the Southern Regional Power Committee (SRPC) website5
where DSM data and energy deviation data are openly available.
As shown in figure 2(a), the DSM penalty data vs energy
deviation data has close match with the curve in figure 1(a).
Though it is expected that the actual penalty value in figure
2(b) will closely match the nature of curve in figure 1(b), the
‘actual penalty’ in figure 2(b) is very scattered due to the high
value of the penalty due to erroneous forecast. From Figure 2
(a) and (b), we can state that the tendency of over-schedule
the forecast is very high, though it is evident from Figure 1(b)
that the actual penalty for under-schedule and over-schedule is
same for the same amount of energy deviation.
4.	 Conclusion
This article shows a simple method of calculation the ‘actual
penalty’ as per DSM in the case of interstate regulation since
SnippetsonWindPower
	º Renewables Need to Double by 2030 to Reach Climate Goals – IRENA
The share of renewables in the global energy mix should more than double by 2030 to advance the global energy
transformation, achieve sustainable development goals and a pathway to climate safety, according to the International
Renewable Energy Agency (IRENA). Renewable electricity should supply 57% of the global power by the end of the
decade, up from 26% today. The Agency’s data shows that annual renewable energy investment needs to double from
around $330 billion today to close to $750 billion to deploy renewable energy at the speed required. Much of the
needed investment can be met by redirecting planned fossil fuel investment. Close to $10 trillion of non-renewables
related energy investments are planned to 2030, risking stranded assets and increasing the likelihood of exceeding the
world’s 1.5 degree carbon budget this decade.
Source: Smart Energy International, Jan 13, 2020
	º Electricity Act May Be Amended To Ensure Discoms Honour Power Pacts
The government is planning to introduce a bill to amend the Electricity Act to prevent states from reneging on power
pacts, particularly renewable energy contracts, and distribution companies from defaulting on bills. It wants to ensure
that renewable energy tariffs are not changed after execution of contracts, and electricity regulatory commissions have
more teeth to enforce power purchase agreements between projects and distribution companies (discom), a senior
government official said. The proposal comes after the new governments in Andhra Pradesh and Maharashtra refused
to honour power purchase agreements, leaving investors jittery.
Source: ET Bureau, January 17, 2020
the DSM penalty and ‘Actual Penalty’ are not same in case of
interstate regulation unlike to intrastate. The P = ∆ - δp rule is an
easy way to compute the actual penalty value since and values
are easily available at weekly or monthly bill of DSM settlement.
The article shows the theoretical structure for energy deviation
vs Actual Penalty curve from which we can state that the actual
penalty for under-schedule and over-schedule are same for the
same amount of energy deviation.
References
1.	 Indian Electricity Grid Code, Central Electricity Regulatory
Commission, 2010 (http://cercind.gov.in/2010/ORDER/
February2010/IEGC_Review_Proposal.pdf)
2.	 Procedure for implementation of the mechanism
of Renewable Regulatory Fund , Central Electricity
Regulatory Commission, 2011 (http://www.cercind.gov.in/
Regulations/Detailed_Procedure_IEGC.pdf)
3.	 Framework on Forecasting, Scheduling and Imbalance
Handling for Variable Renewable Energy Sources (Wind
and Solar), Central Electricity Regulatory Commission,
(http://www.cercind.gov.in/2015/regulation/SOR7.pdf)
4.	 Model Regulations on Forecasting, Scheduling and
Deviation Settlement of Wind and Solar Generating
Stations at the State level.http://www.forumofregulators.
gov.in/Data/study/MR.pdf)
5.	 http://www.srpc.kar.nic.in/html/all_uploads.html

More Related Content

What's hot

421313805-MANUAL-ABB-SWITCHSYNC-F236-2-pdf.pdf
421313805-MANUAL-ABB-SWITCHSYNC-F236-2-pdf.pdf421313805-MANUAL-ABB-SWITCHSYNC-F236-2-pdf.pdf
421313805-MANUAL-ABB-SWITCHSYNC-F236-2-pdf.pdf
UNAC
 
Analysis of on Load Tap Changing Transformer for Substation
Analysis of on Load Tap Changing Transformer for SubstationAnalysis of on Load Tap Changing Transformer for Substation
Analysis of on Load Tap Changing Transformer for Substation
ijtsrd
 
Rail-net Indian railway internet
Rail-net Indian railway internetRail-net Indian railway internet
Rail-net Indian railway internet
Rahul Kumar
 
Transformer testing
Transformer testingTransformer testing
Transformer testing
ajayknows
 

What's hot (20)

Super Capacitor Buses in Shanghai
Super Capacitor Buses in ShanghaiSuper Capacitor Buses in Shanghai
Super Capacitor Buses in Shanghai
 
Mosfet power losses
Mosfet power lossesMosfet power losses
Mosfet power losses
 
Inf. de serv vlf puerta aragón
Inf. de serv vlf puerta aragónInf. de serv vlf puerta aragón
Inf. de serv vlf puerta aragón
 
Vacuum circuit breaker
Vacuum circuit breakerVacuum circuit breaker
Vacuum circuit breaker
 
Power quality 3
Power quality 3Power quality 3
Power quality 3
 
Tutorial on Distance and Over Current Protection
Tutorial on Distance and Over  Current ProtectionTutorial on Distance and Over  Current Protection
Tutorial on Distance and Over Current Protection
 
Sdcs 02 part1
Sdcs 02 part1Sdcs 02 part1
Sdcs 02 part1
 
421313805-MANUAL-ABB-SWITCHSYNC-F236-2-pdf.pdf
421313805-MANUAL-ABB-SWITCHSYNC-F236-2-pdf.pdf421313805-MANUAL-ABB-SWITCHSYNC-F236-2-pdf.pdf
421313805-MANUAL-ABB-SWITCHSYNC-F236-2-pdf.pdf
 
substation monitoring and control system
substation monitoring and control systemsubstation monitoring and control system
substation monitoring and control system
 
Electrical substation (one and half breaker scheme)
Electrical substation (one and half breaker scheme)Electrical substation (one and half breaker scheme)
Electrical substation (one and half breaker scheme)
 
Breakdown due to Internal Discharges and Surface Breakdown
Breakdown due to Internal Discharges and Surface BreakdownBreakdown due to Internal Discharges and Surface Breakdown
Breakdown due to Internal Discharges and Surface Breakdown
 
Analysis of on Load Tap Changing Transformer for Substation
Analysis of on Load Tap Changing Transformer for SubstationAnalysis of on Load Tap Changing Transformer for Substation
Analysis of on Load Tap Changing Transformer for Substation
 
Sop 6.6 kv switchboard
Sop 6.6 kv switchboardSop 6.6 kv switchboard
Sop 6.6 kv switchboard
 
Rail-net Indian railway internet
Rail-net Indian railway internetRail-net Indian railway internet
Rail-net Indian railway internet
 
presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.
 
Circuit Breaker: Part 2
Circuit Breaker: Part 2Circuit Breaker: Part 2
Circuit Breaker: Part 2
 
Flexible ac transmission system
Flexible ac transmission systemFlexible ac transmission system
Flexible ac transmission system
 
Insulators.pptx
Insulators.pptxInsulators.pptx
Insulators.pptx
 
Puentes de medición
Puentes de mediciónPuentes de medición
Puentes de medición
 
Transformer testing
Transformer testingTransformer testing
Transformer testing
 

Similar to Actual Penalty and Deviation Settlement Mechanism (DSM) Penalty in Interstate F&S Regulation for RE Generators

Task Force Pace Phone Confer Q&A 7 29 09
Task Force Pace Phone Confer Q&A 7 29 09Task Force Pace Phone Confer Q&A 7 29 09
Task Force Pace Phone Confer Q&A 7 29 09
Chris Smith
 
Estimating Project LCOE-an Analysis of Geothermal PPA Data
Estimating Project LCOE-an Analysis of Geothermal PPA DataEstimating Project LCOE-an Analysis of Geothermal PPA Data
Estimating Project LCOE-an Analysis of Geothermal PPA Data
Kevin Hernandez
 
MHK- Alex Pan FINAL (1)
MHK- Alex Pan FINAL (1)MHK- Alex Pan FINAL (1)
MHK- Alex Pan FINAL (1)
Yu-Lin Pan
 

Similar to Actual Penalty and Deviation Settlement Mechanism (DSM) Penalty in Interstate F&S Regulation for RE Generators (20)

Economic operation of power system
Economic operation of power systemEconomic operation of power system
Economic operation of power system
 
IRJET- Optimal Generation Scheduling for Thermal Units
IRJET-  	  Optimal Generation Scheduling for Thermal UnitsIRJET-  	  Optimal Generation Scheduling for Thermal Units
IRJET- Optimal Generation Scheduling for Thermal Units
 
IRJET- Optimal Generation Scheduling for Thermal Units
IRJET- Optimal Generation Scheduling for Thermal UnitsIRJET- Optimal Generation Scheduling for Thermal Units
IRJET- Optimal Generation Scheduling for Thermal Units
 
Verification process for DER modeling in interconnection-wide base case creation
Verification process for DER modeling in interconnection-wide base case creationVerification process for DER modeling in interconnection-wide base case creation
Verification process for DER modeling in interconnection-wide base case creation
 
Task Force Pace Phone Confer Q&A 7 29 09
Task Force Pace Phone Confer Q&A 7 29 09Task Force Pace Phone Confer Q&A 7 29 09
Task Force Pace Phone Confer Q&A 7 29 09
 
Estimating Project LCOE-an Analysis of Geothermal PPA Data
Estimating Project LCOE-an Analysis of Geothermal PPA DataEstimating Project LCOE-an Analysis of Geothermal PPA Data
Estimating Project LCOE-an Analysis of Geothermal PPA Data
 
del2infinity presents - cost of penalties under tnerc (forecasting & scheduli...
del2infinity presents - cost of penalties under tnerc (forecasting & scheduli...del2infinity presents - cost of penalties under tnerc (forecasting & scheduli...
del2infinity presents - cost of penalties under tnerc (forecasting & scheduli...
 
SunBurn Test
SunBurn TestSunBurn Test
SunBurn Test
 
Cost of Penalties for deviation of Variable Renewable Power Forecasting consi...
Cost of Penalties for deviation of Variable Renewable Power Forecasting consi...Cost of Penalties for deviation of Variable Renewable Power Forecasting consi...
Cost of Penalties for deviation of Variable Renewable Power Forecasting consi...
 
Unit 5.pptx
Unit 5.pptxUnit 5.pptx
Unit 5.pptx
 
Economic Dispatch of Generated Power Using Modified Lambda-Iteration Method
Economic Dispatch of Generated Power Using Modified Lambda-Iteration MethodEconomic Dispatch of Generated Power Using Modified Lambda-Iteration Method
Economic Dispatch of Generated Power Using Modified Lambda-Iteration Method
 
Comparison between SAM and RETScreen
Comparison between SAM and RETScreenComparison between SAM and RETScreen
Comparison between SAM and RETScreen
 
Enmat details of each chart
Enmat details of each chartEnmat details of each chart
Enmat details of each chart
 
PaperLoad following in a deregulated power system with Thyristor Controlled S...
PaperLoad following in a deregulated power system with Thyristor Controlled S...PaperLoad following in a deregulated power system with Thyristor Controlled S...
PaperLoad following in a deregulated power system with Thyristor Controlled S...
 
Enmat details of each chart
Enmat details of each chartEnmat details of each chart
Enmat details of each chart
 
IRJET- Maximization of Net Profit by Optimal Placement and Sizing of DG in Di...
IRJET- Maximization of Net Profit by Optimal Placement and Sizing of DG in Di...IRJET- Maximization of Net Profit by Optimal Placement and Sizing of DG in Di...
IRJET- Maximization of Net Profit by Optimal Placement and Sizing of DG in Di...
 
R04601113118
R04601113118R04601113118
R04601113118
 
frequency regulation of deregulated power system having grc integrated with r...
frequency regulation of deregulated power system having grc integrated with r...frequency regulation of deregulated power system having grc integrated with r...
frequency regulation of deregulated power system having grc integrated with r...
 
Applicability of Error Limit in Forecasting & Scheduling of Wind & Solar Powe...
Applicability of Error Limit in Forecasting & Scheduling of Wind & Solar Powe...Applicability of Error Limit in Forecasting & Scheduling of Wind & Solar Powe...
Applicability of Error Limit in Forecasting & Scheduling of Wind & Solar Powe...
 
MHK- Alex Pan FINAL (1)
MHK- Alex Pan FINAL (1)MHK- Alex Pan FINAL (1)
MHK- Alex Pan FINAL (1)
 

More from Das A. K.

More from Das A. K. (20)

Rajasthan SLDC - RE DSM Statement -Jan 2020
Rajasthan SLDC - RE DSM Statement -Jan 2020Rajasthan SLDC - RE DSM Statement -Jan 2020
Rajasthan SLDC - RE DSM Statement -Jan 2020
 
Rajasthan SLDC - RE DSM Statement -August 2019
Rajasthan SLDC - RE DSM Statement -August 2019Rajasthan SLDC - RE DSM Statement -August 2019
Rajasthan SLDC - RE DSM Statement -August 2019
 
Rajasthan SLDC - RE DSM Statement -July 2019
Rajasthan SLDC - RE DSM Statement -July 2019Rajasthan SLDC - RE DSM Statement -July 2019
Rajasthan SLDC - RE DSM Statement -July 2019
 
Rajasthan DSM April 2019
Rajasthan DSM April 2019Rajasthan DSM April 2019
Rajasthan DSM April 2019
 
Rajasthan DSM May 2019
Rajasthan DSM May 2019Rajasthan DSM May 2019
Rajasthan DSM May 2019
 
Rajasthan DSM June 2019
Rajasthan DSM June 2019Rajasthan DSM June 2019
Rajasthan DSM June 2019
 
Statement Showing the RE DSM (Rajasthan SLDC) for the month of November-2019 ...
Statement Showing the RE DSM (Rajasthan SLDC) for the month of November-2019 ...Statement Showing the RE DSM (Rajasthan SLDC) for the month of November-2019 ...
Statement Showing the RE DSM (Rajasthan SLDC) for the month of November-2019 ...
 
Draft - Rajasthan - SLDC - Deviation Settlement Account (DSM) statement Octob...
Draft - Rajasthan - SLDC - Deviation Settlement Account (DSM) statement Octob...Draft - Rajasthan - SLDC - Deviation Settlement Account (DSM) statement Octob...
Draft - Rajasthan - SLDC - Deviation Settlement Account (DSM) statement Octob...
 
Gujarat SLDC - STATE DEVIATION SETTLEMENT ACCOUNT FOR THE WEEK 29-Jul-2019 ...
Gujarat SLDC - STATE DEVIATION SETTLEMENT ACCOUNT  FOR THE WEEK  29-Jul-2019 ...Gujarat SLDC - STATE DEVIATION SETTLEMENT ACCOUNT  FOR THE WEEK  29-Jul-2019 ...
Gujarat SLDC - STATE DEVIATION SETTLEMENT ACCOUNT FOR THE WEEK 29-Jul-2019 ...
 
MP-DSM Account of Wind and Solar Pooling Stations for the month of AUGUST, 2019
MP-DSM Account of Wind and Solar Pooling Stations for the month of AUGUST, 2019MP-DSM Account of Wind and Solar Pooling Stations for the month of AUGUST, 2019
MP-DSM Account of Wind and Solar Pooling Stations for the month of AUGUST, 2019
 
Adjudication of dispute regarding RERC (Forecasting, Scheduling, Deviation Se...
Adjudication of dispute regarding RERC (Forecasting, Scheduling, Deviation Se...Adjudication of dispute regarding RERC (Forecasting, Scheduling, Deviation Se...
Adjudication of dispute regarding RERC (Forecasting, Scheduling, Deviation Se...
 
MP-SLDC-DSM Account of Wind and Solar PSS for April, 2019
MP-SLDC-DSM Account of Wind and Solar PSS for April, 2019MP-SLDC-DSM Account of Wind and Solar PSS for April, 2019
MP-SLDC-DSM Account of Wind and Solar PSS for April, 2019
 
MP-DSM Account of Wind and Solar Pooling Stations for March, 2019
MP-DSM Account of Wind and Solar Pooling Stations for March, 2019MP-DSM Account of Wind and Solar Pooling Stations for March, 2019
MP-DSM Account of Wind and Solar Pooling Stations for March, 2019
 
Rajasthan SLDC - Statement Showing the RE DSM for the month of October-2018 Q...
Rajasthan SLDC - Statement Showing the RE DSM for the month of October-2018 Q...Rajasthan SLDC - Statement Showing the RE DSM for the month of October-2018 Q...
Rajasthan SLDC - Statement Showing the RE DSM for the month of October-2018 Q...
 
Rajasthan SLDC - Statement Showing the RE DSM for the month of November-2018 ...
Rajasthan SLDC - Statement Showing the RE DSM for the month of November-2018 ...Rajasthan SLDC - Statement Showing the RE DSM for the month of November-2018 ...
Rajasthan SLDC - Statement Showing the RE DSM for the month of November-2018 ...
 
Rajasthan SLDC - Statement Showing the RE DSM for the month of December-2018 ...
Rajasthan SLDC - Statement Showing the RE DSM for the month of December-2018 ...Rajasthan SLDC - Statement Showing the RE DSM for the month of December-2018 ...
Rajasthan SLDC - Statement Showing the RE DSM for the month of December-2018 ...
 
MP-SLDC-DSM Account of Wind and Solar Pooling Stations for the month of Febru...
MP-SLDC-DSM Account of Wind and Solar Pooling Stations for the month of Febru...MP-SLDC-DSM Account of Wind and Solar Pooling Stations for the month of Febru...
MP-SLDC-DSM Account of Wind and Solar Pooling Stations for the month of Febru...
 
MP_SLDC_RE_DSM_from-01-01-2019-to-31-01-2019_daily
MP_SLDC_RE_DSM_from-01-01-2019-to-31-01-2019_dailyMP_SLDC_RE_DSM_from-01-01-2019-to-31-01-2019_daily
MP_SLDC_RE_DSM_from-01-01-2019-to-31-01-2019_daily
 
Reply to reconnect's defamation notice - One can love it or hate it, but we r...
Reply to reconnect's defamation notice - One can love it or hate it, but we r...Reply to reconnect's defamation notice - One can love it or hate it, but we r...
Reply to reconnect's defamation notice - One can love it or hate it, but we r...
 
normalized parametric model for wind turbine power curve
normalized parametric model for wind turbine power curvenormalized parametric model for wind turbine power curve
normalized parametric model for wind turbine power curve
 

Recently uploaded

Simplify hybrid data integration at an enterprise scale. Integrate all your d...
Simplify hybrid data integration at an enterprise scale. Integrate all your d...Simplify hybrid data integration at an enterprise scale. Integrate all your d...
Simplify hybrid data integration at an enterprise scale. Integrate all your d...
varanasisatyanvesh
 
如何办理(WashU毕业证书)圣路易斯华盛顿大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(WashU毕业证书)圣路易斯华盛顿大学毕业证成绩单本科硕士学位证留信学历认证如何办理(WashU毕业证书)圣路易斯华盛顿大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(WashU毕业证书)圣路易斯华盛顿大学毕业证成绩单本科硕士学位证留信学历认证
acoha1
 
Reconciling Conflicting Data Curation Actions: Transparency Through Argument...
Reconciling Conflicting Data Curation Actions:  Transparency Through Argument...Reconciling Conflicting Data Curation Actions:  Transparency Through Argument...
Reconciling Conflicting Data Curation Actions: Transparency Through Argument...
Bertram Ludäscher
 
Abortion Clinic in Kempton Park +27791653574 WhatsApp Abortion Clinic Service...
Abortion Clinic in Kempton Park +27791653574 WhatsApp Abortion Clinic Service...Abortion Clinic in Kempton Park +27791653574 WhatsApp Abortion Clinic Service...
Abortion Clinic in Kempton Park +27791653574 WhatsApp Abortion Clinic Service...
mikehavy0
 
如何办理(Dalhousie毕业证书)达尔豪斯大学毕业证成绩单留信学历认证
如何办理(Dalhousie毕业证书)达尔豪斯大学毕业证成绩单留信学历认证如何办理(Dalhousie毕业证书)达尔豪斯大学毕业证成绩单留信学历认证
如何办理(Dalhousie毕业证书)达尔豪斯大学毕业证成绩单留信学历认证
zifhagzkk
 
Abortion pills in Doha {{ QATAR }} +966572737505) Get Cytotec
Abortion pills in Doha {{ QATAR }} +966572737505) Get CytotecAbortion pills in Doha {{ QATAR }} +966572737505) Get Cytotec
Abortion pills in Doha {{ QATAR }} +966572737505) Get Cytotec
Abortion pills in Riyadh +966572737505 get cytotec
 
Abortion pills in Jeddah | +966572737505 | Get Cytotec
Abortion pills in Jeddah | +966572737505 | Get CytotecAbortion pills in Jeddah | +966572737505 | Get Cytotec
Abortion pills in Jeddah | +966572737505 | Get Cytotec
Abortion pills in Riyadh +966572737505 get cytotec
 
Displacement, Velocity, Acceleration, and Second Derivatives
Displacement, Velocity, Acceleration, and Second DerivativesDisplacement, Velocity, Acceleration, and Second Derivatives
Displacement, Velocity, Acceleration, and Second Derivatives
23050636
 
Abortion pills in Riyadh Saudi Arabia| +966572737505 | Get Cytotec, Unwanted Kit
Abortion pills in Riyadh Saudi Arabia| +966572737505 | Get Cytotec, Unwanted KitAbortion pills in Riyadh Saudi Arabia| +966572737505 | Get Cytotec, Unwanted Kit
Abortion pills in Riyadh Saudi Arabia| +966572737505 | Get Cytotec, Unwanted Kit
Abortion pills in Riyadh +966572737505 get cytotec
 
如何办理澳洲拉筹伯大学毕业证(LaTrobe毕业证书)成绩单原件一模一样
如何办理澳洲拉筹伯大学毕业证(LaTrobe毕业证书)成绩单原件一模一样如何办理澳洲拉筹伯大学毕业证(LaTrobe毕业证书)成绩单原件一模一样
如何办理澳洲拉筹伯大学毕业证(LaTrobe毕业证书)成绩单原件一模一样
wsppdmt
 

Recently uploaded (20)

Simplify hybrid data integration at an enterprise scale. Integrate all your d...
Simplify hybrid data integration at an enterprise scale. Integrate all your d...Simplify hybrid data integration at an enterprise scale. Integrate all your d...
Simplify hybrid data integration at an enterprise scale. Integrate all your d...
 
Identify Rules that Predict Patient’s Heart Disease - An Application of Decis...
Identify Rules that Predict Patient’s Heart Disease - An Application of Decis...Identify Rules that Predict Patient’s Heart Disease - An Application of Decis...
Identify Rules that Predict Patient’s Heart Disease - An Application of Decis...
 
Ranking and Scoring Exercises for Research
Ranking and Scoring Exercises for ResearchRanking and Scoring Exercises for Research
Ranking and Scoring Exercises for Research
 
如何办理(WashU毕业证书)圣路易斯华盛顿大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(WashU毕业证书)圣路易斯华盛顿大学毕业证成绩单本科硕士学位证留信学历认证如何办理(WashU毕业证书)圣路易斯华盛顿大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(WashU毕业证书)圣路易斯华盛顿大学毕业证成绩单本科硕士学位证留信学历认证
 
Reconciling Conflicting Data Curation Actions: Transparency Through Argument...
Reconciling Conflicting Data Curation Actions:  Transparency Through Argument...Reconciling Conflicting Data Curation Actions:  Transparency Through Argument...
Reconciling Conflicting Data Curation Actions: Transparency Through Argument...
 
DAA Assignment Solution.pdf is the best1
DAA Assignment Solution.pdf is the best1DAA Assignment Solution.pdf is the best1
DAA Assignment Solution.pdf is the best1
 
社内勉強会資料_Object Recognition as Next Token Prediction
社内勉強会資料_Object Recognition as Next Token Prediction社内勉強会資料_Object Recognition as Next Token Prediction
社内勉強会資料_Object Recognition as Next Token Prediction
 
Abortion Clinic in Kempton Park +27791653574 WhatsApp Abortion Clinic Service...
Abortion Clinic in Kempton Park +27791653574 WhatsApp Abortion Clinic Service...Abortion Clinic in Kempton Park +27791653574 WhatsApp Abortion Clinic Service...
Abortion Clinic in Kempton Park +27791653574 WhatsApp Abortion Clinic Service...
 
如何办理(Dalhousie毕业证书)达尔豪斯大学毕业证成绩单留信学历认证
如何办理(Dalhousie毕业证书)达尔豪斯大学毕业证成绩单留信学历认证如何办理(Dalhousie毕业证书)达尔豪斯大学毕业证成绩单留信学历认证
如何办理(Dalhousie毕业证书)达尔豪斯大学毕业证成绩单留信学历认证
 
Abortion pills in Doha {{ QATAR }} +966572737505) Get Cytotec
Abortion pills in Doha {{ QATAR }} +966572737505) Get CytotecAbortion pills in Doha {{ QATAR }} +966572737505) Get Cytotec
Abortion pills in Doha {{ QATAR }} +966572737505) Get Cytotec
 
Abortion pills in Jeddah | +966572737505 | Get Cytotec
Abortion pills in Jeddah | +966572737505 | Get CytotecAbortion pills in Jeddah | +966572737505 | Get Cytotec
Abortion pills in Jeddah | +966572737505 | Get Cytotec
 
Displacement, Velocity, Acceleration, and Second Derivatives
Displacement, Velocity, Acceleration, and Second DerivativesDisplacement, Velocity, Acceleration, and Second Derivatives
Displacement, Velocity, Acceleration, and Second Derivatives
 
SAC 25 Final National, Regional & Local Angel Group Investing Insights 2024 0...
SAC 25 Final National, Regional & Local Angel Group Investing Insights 2024 0...SAC 25 Final National, Regional & Local Angel Group Investing Insights 2024 0...
SAC 25 Final National, Regional & Local Angel Group Investing Insights 2024 0...
 
Credit Card Fraud Detection: Safeguarding Transactions in the Digital Age
Credit Card Fraud Detection: Safeguarding Transactions in the Digital AgeCredit Card Fraud Detection: Safeguarding Transactions in the Digital Age
Credit Card Fraud Detection: Safeguarding Transactions in the Digital Age
 
Las implicancias del memorándum de entendimiento entre Codelco y SQM según la...
Las implicancias del memorándum de entendimiento entre Codelco y SQM según la...Las implicancias del memorándum de entendimiento entre Codelco y SQM según la...
Las implicancias del memorándum de entendimiento entre Codelco y SQM según la...
 
Abortion pills in Riyadh Saudi Arabia| +966572737505 | Get Cytotec, Unwanted Kit
Abortion pills in Riyadh Saudi Arabia| +966572737505 | Get Cytotec, Unwanted KitAbortion pills in Riyadh Saudi Arabia| +966572737505 | Get Cytotec, Unwanted Kit
Abortion pills in Riyadh Saudi Arabia| +966572737505 | Get Cytotec, Unwanted Kit
 
DATA SUMMIT 24 Building Real-Time Pipelines With FLaNK
DATA SUMMIT 24  Building Real-Time Pipelines With FLaNKDATA SUMMIT 24  Building Real-Time Pipelines With FLaNK
DATA SUMMIT 24 Building Real-Time Pipelines With FLaNK
 
如何办理澳洲拉筹伯大学毕业证(LaTrobe毕业证书)成绩单原件一模一样
如何办理澳洲拉筹伯大学毕业证(LaTrobe毕业证书)成绩单原件一模一样如何办理澳洲拉筹伯大学毕业证(LaTrobe毕业证书)成绩单原件一模一样
如何办理澳洲拉筹伯大学毕业证(LaTrobe毕业证书)成绩单原件一模一样
 
SCI8-Q4-MOD11.pdfwrwujrrjfaajerjrajrrarj
SCI8-Q4-MOD11.pdfwrwujrrjfaajerjrajrrarjSCI8-Q4-MOD11.pdfwrwujrrjfaajerjrajrrarj
SCI8-Q4-MOD11.pdfwrwujrrjfaajerjrajrrarj
 
DS Lecture-1 about discrete structure .ppt
DS Lecture-1 about discrete structure .pptDS Lecture-1 about discrete structure .ppt
DS Lecture-1 about discrete structure .ppt
 

Actual Penalty and Deviation Settlement Mechanism (DSM) Penalty in Interstate F&S Regulation for RE Generators

  • 1. 4 Indian Wind Power Dec. 2019 - Jan. 2020 1. Introduction Forecasting and Scheduling (F&S) of solar and wind power generation is required to manage the grid network for maximum utilization of renewable energy. Hence the concept of forecasting and scheduling (F&S) of renewable energy generators and the commercial settlement was introduced in Indian context by CERC through Indian Electricity Grid Code (IEGC), 20101 and the Renewable Regulatory Fund mechanism2. Due to several implementation issues, the mechanism was never made operational. To formulate an implementable framework, CERC also issued 2nd amendment to regulation for the Deviation Settlement Mechanism (DSM) and other related matters3. After CERC regulation, Forum of Regulators (FOR)4 and other state regulators issued or drafted regulation related to the forecasting and scheduling of wind and solar power generation. Unlike DSM penalty of intrastate forecasting and scheduling of wind and solar power generation, the ‘actual penalty’ and the ‘DSM penalty’ of wind and solar power generation in interstate CERC regulation are different. This article briefly focuses on the theoretical and evidence based understanding of ‘Actual Penalty’ and ‘DSM Penalty’ in case of interstate regulation. 2. Theoretical Framework In interstate regulation, the payment is on schedule generation, unlike the intrastate in which the payment is on actual generation. Hence, to calculate the actual penalty due F&S in case of interstate regulation, we can state that, Actual Penalty = (Schedule Generation × PPA rate + DSM Penalty) - Actual Generation × PPA rate (1) Here DSM penalty is negative when payable to the pool by the generators and positive when payable by the pool to the RE generators. By simple algebraic manipulation (1) can be written as, Actual Penalty = DSM Penalty - (Actual Generation - Schedule generation) × PPA rate (2) Actual Penalty and Deviation Settlement Mechanism (DSM) Penalty in Interstate F&S Regulation for RE Generators Abhik Kumar Das Technical Director del2infinity Energy Consulting contact@del2infinity.xyz Sandeep Suman Assistant Manager (E&M) Coal India Limited Which transforms into, Actual Penalty (P) = DSM Penalty (∆) - Energy Deviation (δ) × PPA rate (p) (3) i.e. P = ∆ - δp (4) Here (4) can be viewed as the fundamental equation to calculate the actual penalty in interstate F&S regulation. Since (4) is true for each of the time-block, for all time-blocks we can state that, ∑P = ∑∆ - p∑δ If we replace, ∑P as P, ∑∆ as ∆ and ∑δ as δ, (4) remains same, and the total actual penalty (monthly or weekly) can be calculated from the total DSM (monthly or weekly) and total energy deviation (monthly or weekly). Interestingly, total DSM and total energy deviation value (monthly or weekly) is readily available at ERC sites, and the actual penalty can be calculated if the PPA rate (p) is known. Hence (4) can be viewed as a fundamental equation to calculate the actual penalty in interstate regulation. Since P = ∆ - δp , it is easy to state that the actual penalty due to the deviation (P) is not the DSM penalty (∆). Since the actual penalty (P) is always payable, it is always negative. Hence DSM penalty (∆) and energy deviation (δ) are of same sign, as shown in Table I. Table I: DSM Penalty vs Energy Deviation DSM penalty (∆) Energy deviation (δ) Comment + DSM Receivable + Actual > Schedule Under-schedule / Over-injection - DSM Payable - Actual < Schedule Over-schedule / Under- injection
  • 2. THE NEED FOR SPEED Learn more: WeKnowBlades.lmwindpower.com Competition in the wind industry has never been fiercer. Our customers require larger rotors, faster than ever. Even with up to seven new blade developments every year, we always deliver on time As blade specialists, we know what it takes to: • Ensure the fastest and safest product launch: Smooth and seamless interaction with our customers’ development teams allows us to convert numerous load iterations into tangible and competitive blade designs • Deliver prototypes fast and on time: Our product development process has been proven time and time again – it simply works. In-house testing andcertification expertise give us the flexibility to respond quickly to customer demands • Be a genuine global supplier: With 15 global factories, we are present in all major wind markets, ensuring fast launches on time
  • 3. 6 Indian Wind Power Dec. 2019 - Jan. 2020 Table II: DSM for Inter-State Regulation and Mathematical Framework Payment on Schedule Generation Payment on Schedule Generation Abs Error For Under-Injection (Actual < Schedule) Deviation Charge payable by RE generators ∆ For Over-Injection (Actual > Schedule) Deviation Charge payable to RE generators ∆ 0 – 15% At the Fixed Rate for the shortfall energy upto for absolute error upto 15% δp At the Fixed Rate for the excess energy upto for absolute error upto 15% δp 15% - 25% At the Fixed Rate for the shortfall energy for absolute error upto 15% + 110% of the Fixed Rate for balance energy beyond 15% and upto 25% 0.15 Ap + [δ - 0.15A ] X (1.1 p) At the Fixed Rate for the excess energy for absolute error upto 15% + 90% of the Fixed Rate for balance energy beyond 15% and upto 25% 0.15 Ap + [δ - 0.15A ] X (0.9 p) 25%-35% At the Fixed Rate for the shortfall energy for absolute error upto 15% + 110% of the Fixed Rate for balance energy beyond 15% and upto 25% + 120% of the Fixed Rate for balance energy beyond 25% and upto 35% 0.15 Ap + 0.1 A (1.1p) + [δ - 0.25A ] X (1.2 p) At the Fixed Rate for the excess energy for absolute error upto 15% + 90% of the Fixed Rate for balance energy beyond 15% and upto 25% + 80% of the Fixed Rate for balance energy beyond 25% and upto 35% 0.15 Ap + 0.1 A (0.9p) + [δ - 0.25A ] X (0.8 p) >35% At the Fixed Rate for the shortfall energy for absolute error upto 15% + 110% of the Fixed Rate for balance energy beyond 15% and upto 25% + l20% of the Fixed Rate for balance energy beyond 25% and upto 35% + l30% of the Fixed Rate for balance energy beyond 35% 0.15 Ap + 0.1 A (1.1p) + 0.1 A (1.2p) + [δ - 0.35A ] X (1.3 p) At the Fixed Rate for the excess energy for absolute error upto 15% + 90% of the Fixed Rate for balance energy beyond 15% and upto 25% + 80% of the Fixed Rate for balance energy beyond 25% and upto 35% + 70% of the Fixed Rate for balance energy beyond 35% 0.15 Ap + 0.1 A (0.9) + 0.1 A (0.8p) + [δ - 0.35A ] X (0.7 p)
  • 4. 7Indian Wind PowerDec. 2019 - Jan. 2020 (a) (b) Figure 1: Shows the percentage of energy deviation vs (a) DSM penalty per unit capacity and (b) Actual penalty per unit capacity as per the Interstate regulation using the equation in Table II. Figure 2(a) shows the energy deviation (MW-Hr) vs (a)Weekly DSM Penalty and 2(b) Weekly Actual Penalty for 7 different generators at SRPC. The bold black curve in 2(b) shows the average trend line. Since different RE generators are of different capacities, to normalize the calculation, let divide (4) by the available capacity (AvC), i.e. = − Where is the penalty per unit capacity, is DSM per unit capacity and represents the percentage in energy deviation. Hence, as per interstate F&S regulation, the equation relating ‘DSM penalty’ and ‘percentage in energy deviation’ can be represented as Table II. 3. Results and Discussion Using the equation in Table II, the percentage of energy deviation vs DSM penalty per unit capacity for different PPA rate (p) can be shown as Figure 1(a). As shown in figure 1(a), when the energy deviation is positive (negative), the DSM penalty is positive (negative). It is interesting to see that the curve representing DSM penalty vs. energy deviation is continuous, though the function seems to be an odd function (f(-x) = - f(x)), the curve is not an odd function, i.e. for same energy deviation in the positive and negative direction the DSM penalty for under-schedule and over-schedule are not same ( f (-δ) ≠ -f (δ) ).
  • 5. 8 Indian Wind Power Dec. 2019 - Jan. 2020 The Actual Penalty vs energy deviation is shown in figure 1(b) for different values of PPA rate (p). Here it is interesting to see that the curve is symmetric about the y-axis and it is an even function (f(-x) = f(x)). Hence, for same energy deviation in the positive and negative direction the Actual penalty for under- schedule and over-schedule are same (f(-δ) = f(δ)). Hence, as per interstate regulation, if the forecast is over-scheduled or under-scheduled, the actual penalty remains same for same energy deviation in positive or negative direction. The theoretical structure of ‘Actual Penalty’ and ‘DSM Penalty’ is validated by evidence based data of 7 different RE generators of the Southern Regional Power Committee (SRPC) website5 where DSM data and energy deviation data are openly available. As shown in figure 2(a), the DSM penalty data vs energy deviation data has close match with the curve in figure 1(a). Though it is expected that the actual penalty value in figure 2(b) will closely match the nature of curve in figure 1(b), the ‘actual penalty’ in figure 2(b) is very scattered due to the high value of the penalty due to erroneous forecast. From Figure 2 (a) and (b), we can state that the tendency of over-schedule the forecast is very high, though it is evident from Figure 1(b) that the actual penalty for under-schedule and over-schedule is same for the same amount of energy deviation. 4. Conclusion This article shows a simple method of calculation the ‘actual penalty’ as per DSM in the case of interstate regulation since SnippetsonWindPower º Renewables Need to Double by 2030 to Reach Climate Goals – IRENA The share of renewables in the global energy mix should more than double by 2030 to advance the global energy transformation, achieve sustainable development goals and a pathway to climate safety, according to the International Renewable Energy Agency (IRENA). Renewable electricity should supply 57% of the global power by the end of the decade, up from 26% today. The Agency’s data shows that annual renewable energy investment needs to double from around $330 billion today to close to $750 billion to deploy renewable energy at the speed required. Much of the needed investment can be met by redirecting planned fossil fuel investment. Close to $10 trillion of non-renewables related energy investments are planned to 2030, risking stranded assets and increasing the likelihood of exceeding the world’s 1.5 degree carbon budget this decade. Source: Smart Energy International, Jan 13, 2020 º Electricity Act May Be Amended To Ensure Discoms Honour Power Pacts The government is planning to introduce a bill to amend the Electricity Act to prevent states from reneging on power pacts, particularly renewable energy contracts, and distribution companies from defaulting on bills. It wants to ensure that renewable energy tariffs are not changed after execution of contracts, and electricity regulatory commissions have more teeth to enforce power purchase agreements between projects and distribution companies (discom), a senior government official said. The proposal comes after the new governments in Andhra Pradesh and Maharashtra refused to honour power purchase agreements, leaving investors jittery. Source: ET Bureau, January 17, 2020 the DSM penalty and ‘Actual Penalty’ are not same in case of interstate regulation unlike to intrastate. The P = ∆ - δp rule is an easy way to compute the actual penalty value since and values are easily available at weekly or monthly bill of DSM settlement. The article shows the theoretical structure for energy deviation vs Actual Penalty curve from which we can state that the actual penalty for under-schedule and over-schedule are same for the same amount of energy deviation. References 1. Indian Electricity Grid Code, Central Electricity Regulatory Commission, 2010 (http://cercind.gov.in/2010/ORDER/ February2010/IEGC_Review_Proposal.pdf) 2. Procedure for implementation of the mechanism of Renewable Regulatory Fund , Central Electricity Regulatory Commission, 2011 (http://www.cercind.gov.in/ Regulations/Detailed_Procedure_IEGC.pdf) 3. Framework on Forecasting, Scheduling and Imbalance Handling for Variable Renewable Energy Sources (Wind and Solar), Central Electricity Regulatory Commission, (http://www.cercind.gov.in/2015/regulation/SOR7.pdf) 4. Model Regulations on Forecasting, Scheduling and Deviation Settlement of Wind and Solar Generating Stations at the State level.http://www.forumofregulators. gov.in/Data/study/MR.pdf) 5. http://www.srpc.kar.nic.in/html/all_uploads.html