SlideShare a Scribd company logo
1 of 77
Download to read offline
USER CASE STUDY ABSTRACT
                  20th International Pump Users Symposium



TITLE:

Reliability Improvement of End Suction Pump in Severe Service
through Engineered Component Upgrade


ABSTRACT:

An end suction pump for amine service at an Ammonia plant was successfully
upgraded by improvement of its components.

Two 290 kW (390 HP) pumps, turbine/motor driven, rated for 262 m3/hr (1,153
gpm) and 271 m (889 ft), operate in severe service conditions due low NPSHA and
part-load operation. The equipment exhibited rough operation with high vibration
and an elevated repair frequency by recurrent fatigue failure of shaft, severe wear
ring rubs, impeller corrosion/erosion, mechanical seal leakage and bearing
damages..

After a catastrophic failure, involving pump and electric motor, that caused an
emergency plant shutdown, an upgrade for the pumps was engineered. The
objective was to overcome design weaknesses and incorporate features to
increase reliability. Impeller deficiencies were identified and corrected and its
metallurgy improved to endure severe cavitation/recirculation damage. The power
end was completely redesigned, incorporating larger shaft and bearing housing
stiffness, together with a material upgrade, oversized bearings and lubrication
enhancements.

As a result, a failure frequency as large as 9 a year has been eliminated since the
upgrade and the pump presently accumulates 3 years of continuous operation.
An outstanding improvement in reliability was obtained together with considerable
savings in investment & maintenance costs.

AUTHOR:

César A. Morales Casanova
Rotating Equipment Specialist
PDVSA – Pequiven
Morón Petrochemical Complex
Edo. Carabobo
Venezuela
®

       20th International Pump Users Symposium
       March 17-20, 2003. Houston, Texas




   RELIABILITY IMPROVEMENT
     OF END SUCTION PUMP
      IN SEVERE SERVICE
THROUGH ENGINEERED COMPONENT
           UPGRADE

                                           César A. Morales Casanova
                                           Rotating Equipment Specialist
                                           PDVSA - Pequiven
                                           Edo. Carabobo - Venezuela
CONTENTS
•   Objective
•   Conditions of service – Amine recovery system
•   Pump failures
       Experience of continued low reliability
       Problem areas – Original design
       Remedial actions – Historical review 1980 – 1997
       Catastrophic failure – 1998
•   Preliminary analysis – Recurrent pump failures
•   Problem analysis
       Factors associated to low reliability
       Correlation of causes for low reliability
•   Pump upgrade
       Objectives
       Areas of attention
       Summary of main improvements
•   Upgraded pump test
       Objectives
       Results of performance testing
       Test conclusions
•   Upgrade results
       Cost – lead time comparison
       Current upgrade progress – end 2002
       Reliability improvement
•   Conclusions
•   Lessons learned
•   References
OBJECTIVE


A successful experience of reliability
improvement of two process pumps,
through the application of a cost-effective,
“in-house” engineered component upgrade
is presented.
The solution can be used as a reference to
yield better mechanical performance of
existing equipment in similar services.
SITUATION OVERVIEW
                             AMINE RECOVERY SERVICE
               FCV
C-754                C-752       PUMP RATINGS:
             PCV

                             Q : 262 m3/hr (1,153 GPM)
                             H : 271 m (889 ft)
                              N : 3550 RPM
             PC-752A/B        P : 290 kW (390 HP)


                             MAIN PUMP “A”
                                  Turbine Driven

                             STAND-BY PUMP “B”
                                  Motor Driven
PUMP FAILURES
                          EXPERIENCE OF CONTINUED LOW RELIABILITY

                                         OPERATION PROBLEMS:
10
       PC-752B                                High Vibration
 9
 8     PC-752A                                Low Capacity
 7                                            Product Leakage
 6
 5
 4                                        FAILED COMPONENTS:
 3
 2                                            Impeller
 1                                            Wear Rings
 0                                            Shaft
     1995   1996   1997    1998   1999
                                              Bearings
                                              Mechanical Seal
PUMP FAILURES
      PROBLEM AREAS - ORIGINAL DESIGN
PUMP FAILURES
              PROBLEM AREAS - ORIGINAL DESIGN



WEAR
RINGS
PUMP FAILURES
                 PROBLEM AREAS - ORIGINAL DESIGN




SEVERE RUBBING AT WEAR RINGS - 1996
PUMP FAILURES
              PROBLEM AREAS - ORIGINAL DESIGN



WEAR
RINGS


SHAFT
PUMP FAILURES
                PROBLEM AREAS - ORIGINAL DESIGN




SHAFT FAILURE AT IMPELLER END - 1992
PUMP FAILURES
                 PROBLEM AREAS - ORIGINAL DESIGN



WEAR
RINGS


SHAFT




IMPELLER
PUMP FAILURES
                 PROBLEM AREAS - ORIGINAL DESIGN




EROSION                             W/R RUB




   SEVERE IMPELLER FAILURE - 1992
PUMP FAILURES
                 PROBLEM AREAS - ORIGINAL DESIGN



WEAR
RINGS


SHAFT




IMPELLER              MECH. SEAL
PUMP FAILURES
                 PROBLEM AREAS - ORIGINAL DESIGN



WEAR
RINGS                               BEARINGS



SHAFT




IMPELLER              MECH. SEAL
PUMP FAILURES
                    REMEDIAL ACTIONS – HYSTORICAL REVIEW

YEAR   COMPONENT                      ACTION
1980    Impeller     Installed pins between shrouds
1986     Shaft       Impeller capscrew replaced to fine thread

1991    Impeller     Local manufacture of impellers

1992     Shaft       Impeller capscrew replaced by a nut
1994   Wear Rings    Increase in wear ring clearances

1995    Impeller     Incorporation of 3 partial vanes

1996    Impeller     Impeller trim to pump “B”
1997    Impeller     Trimming of vanes at inlet

        Bearings     5313 thrust bearing replaced by 7313
PUMP FAILURES
                   REMEDIAL ACTIONS – HYSTORICAL REVIEW

YEAR   COMPONENT             DESCRIPTION
1980    Impeller   Installed pins between shrouds
PUMP FAILURES
            REMEDIAL ACTIONS – HYSTORICAL REVIEW
                                           1980




PINS INSTALLED BETWEEN IMPELLER SHROUDS
PUMP FAILURES
                   REMEDIAL ACTIONS – HYSTORICAL REVIEW

YEAR   COMPONENT              DESCRIPTION
1980    Impeller   Installed pins between shrouds

1986     Shaft     Impeller capscrew replaced to fine thread
PUMP FAILURES
                REMEDIAL ACTIONS – HYSTORICAL REVIEW
                                               1986




CAPSCREW M 24
   NC TO NF
PUMP FAILURES
                   REMEDIAL ACTIONS – HYSTORICAL REVIEW

YEAR   COMPONENT              DESCRIPTION
1980    Impeller   Installed pins between shrouds

1986     Shaft     Impeller capscrew replaced to fine thread

1991    Impeller   Local manufacture of impellers

1992     Shaft     Impeller capscrew replaced by a nut
PUMP FAILURES
                    REMEDIAL ACTIONS – HYSTORICAL REVIEW
                                                   1992
   IMPELLER NUT M 38 NF




CAPSCRW
 M 24 NF
PUMP FAILURES
           REMEDIAL ACTIONS – HYSTORICAL REVIEW
                                       Pump “B”




SHAFT FAILURE AT IMPELLER END - MAY 1999
PUMP FAILURES
                    REMEDIAL ACTIONS – HYSTORICAL REVIEW

YEAR   COMPONENT               DESCRIPTION
1980    Impeller    Installed pins between shrouds

1986     Shaft      Impeller capscrew replaced to fine thread

1991    Impeller    Local manufacture of impellers

1992     Shaft      Impeller capscrew replaced by a nut

1994   Wear Rings   Increase in wear rings running clearance

1995    Impeller    Incorporation of 3 partial vanes
PUMP FAILURES
                 REMEDIAL ACTIONS – HYSTORICAL REVIEW
                                                1995




IMPELLER PATTERN WITH 3
   PARTIAL VANES ADDED
                           EROSION CONTINUED
PUMP FAILURES
                    REMEDIAL ACTIONS – HYSTORICAL REVIEW

YEAR   COMPONENT               DESCRIPTION
1980    Impeller    Installed pins between shrouds

1986     Shaft      Impeller capscrew replaced to fine thread

1991    Impeller    Local manufacture of impellers

1992     Shaft      Impeller capscrew replaced by a nut

1994   Wear Rings   Increase in wear rings running clearance

1995    Impeller    Incorporation of 3 partial vanes

1996    Impeller    Impeller trim to pump “B”
PUMP FAILURES
                                              REMEDIAL ACTIONS – HYSTORICAL REVIEW
                                                                                                                              1996
               00       200
                         200       400
                                    400      600
                                              600        800
                                                          800          1000
                                                                        1000          1200
                                                                                       1200       1400
                                                                                                   1400    Q [GPM]
                                                                                                           Q [GPM]

        340                                                                              Publ Head           1120
                                                                                                              1120
         340                                                                              Publ Head
                                                                                         Publ Head
                               3550 rpm φ 385 mm
                               3550 rpm φ 385 mm                                         Publ Head
                                                                                         Corr Head
                                                                                          Corr Head
                                                                                                             1060
                                                                                                              1060
        320
         320
                                                                               30%                           1000
                                                                                                              1000
        300
         300

                    PUMP “A” Imp φ385 mm                                              RATED
                                                                                       RATED
                                                                                                             940
                                                                                                              940




                                                                                                                     H [ft]
H [m]




        280             @ 3200 rpm                                                    POINT




                                                                                                                     H [ft]
H [m]




         280                                                                           POINT
                                                                                                             880
                                                                                                              880
                                                                                                 BEP
                                                                                                  BEP
        260
         260
                PUMP “B” Imp φ348 mm                                                                         820
                                                                                                              820
                    @ 3550 rpm
        240
         240                                                                                                 760
                                                                                                              760
                                            OPERATING

        220
                                             OPERATING
                                              RANGE
                                               RANGE                                                  PROCESS FLOW
         220                                                                                              700
                                                                                                       NOT700
                                                                                                            REACHED
        200
         200                                                                                                 640
                                                                                                              640
               00        50
                          50         100
                                      100       150
                                                 150            200
                                                                 200           250
                                                                                250            300
                                                                                                300       350
                                                                                                           350
                                                                                                            Q [m3/hr]
                                                                                                            Q [m3/hr]


                    IMPELLER TRIM OF STAND-BY PUMP “B”
PUMP FAILURES
                                              REMEDIAL ACTIONS – HYSTORICAL REVIEW
                                                                                                                              1996
               00       200
                         200       400
                                    400      600
                                              600        800
                                                          800          1000
                                                                        1000          1200
                                                                                       1200       1400
                                                                                                   1400    Q [GPM]
                                                                                                           Q [GPM]

        340                                                                              Publ Head           1120
                                                                                                              1120
         340                                                                             Publ Head
                               3550 rpm φ 385 mm
                               3550 rpm φ 385 mm                                         Corr Head
                                                                                         Corr Head
                                                                                                             1060
                                                                                                              1060
        320
         320

                                                                                                             1000
                                                                                                              1000
        300
         300
                                                                                                             940
                                                                                                              940
                                                                                      RATED
                                                                                       RATED




                                                                                                                     H [ft]
H [m]




        280




                                                                                                                     H [ft]
                                                                                      POINT
H [m]




         280                                                                           POINT
                    PUMP “B” Imp φ370 mm                                                                     880
                                                                                                              880
                        @ 3550 rpm                                                               BEP
                                                                                                  BEP
        260
         260
                                                                                                             820
                        CAVITATION                                                                            820

        240
         240
                                                                                                             760
                                                                                                              760
                                            OPERATING
                                             OPERATING
                                              RANGE
                                               RANGE
        220
         220                                                                                                 700
                                                                                                              700

        200
         200                                                                                                 640
                                                                                                              640
               00        50
                          50         100
                                      100       150
                                                 150            200
                                                                 200           250
                                                                                250            300
                                                                                                300       350
                                                                                                           350
                                                                                                            Q [m3/hr]
                                                                                                            Q [m3/hr]


                    IMPELLER TRIM OF STAND-BY PUMP “B”
PUMP FAILURES
                    REMEDIAL ACTIONS – HYSTORICAL REVIEW

YEAR   COMPONENT               DESCRIPTION
1980    Impeller    Installed pins between shrouds

1986     Shaft      Impeller capscrew replaced to fine thread

1991    Impeller    Local manufacture of impellers

1992     Shaft      Impeller capscrew replaced by a nut

1994   Wear Rings   Increase in wear rings running clearance

1995    Impeller    Incorporation of 3 partial vanes

1996    Impeller    Impeller trim to pump “B”

1997    Impeller    Trimming of vanes at inlet
PUMP FAILURES
                  REMEDIAL ACTIONS – HYSTORICAL REVIEW
                                                 1997




VANE TRIM AT IMPELLER
INLET TO REDUCE NPSHR
                           IMPROPERLY EFFECTED
PUMP FAILURES
                    REMEDIAL ACTIONS – HYSTORICAL REVIEW

YEAR   COMPONENT               DESCRIPTION
1980    Impeller    Installed pins between shrouds

1986     Shaft      Impeller capscrew replaced to fine thread

1991    Impeller    Local manufacture of impellers

1992     Shaft      Impeller capscrew replaced by a nut

1994   Wear Rings   Increase in wear rings running clearance

1995    Impeller    Incorporation of 3 partial vanes

1996    Impeller    Impeller trim to pump “B”

1997    Impeller    Trimming of vanes at inlet
        Bearings    5313 thrust bearing replaced by 7313 BG
PUMP FAILURES
              REMEDIAL ACTIONS – HYSTORICAL REVIEW
                                              1997




THRUST BEARING UPGRADE FROM 3313 TO 7313 BG
PUMP FAILURES
      CATASTROPHIC FAILURE – PUMP “B”
                          SEPT 1998
PRELIMINARY ANALYSIS
                            RECURRENT PUMP FAILURES
                                          SEPT 1999


Unsuccessful efforts to improve reliability.
Solutions mainly focused in the consequences
rather than the causes for the problems.
Improper procedures contribute to failures.
Complex problem with multiple correlated
causes and failure modes.
Global solution required.
PROBLEM ANALYSIS
           FACTORS ASSOCIATED TO LOW RELIABILTY
                                    SEPT 1999
OPERATIONAL
  • Low NPSHA
PROBLEM ANALYSIS
                       FACTORS ASSOCIATED TO LOW RELIABILTY
                                SUCTION CONDITIONS - 1999
                  PLUGGING OF
                 PLATE COOLER

                                      FCV
         C-754                                  C-752
                                    PCV
                                      INOP.
                                     FILTER




  TEMP INCREASE &                   PC-752A/B
REDUCTION OF SUCTION
     PRESSURE
                  MEA RECOVERY SYSTEM
PROBLEM ANALYSIS
                            FACTORS ASSOCIATED TO LOW RELIABILTY
                                         SUCTION CONDITIONS - 1999

                             DESIGN        REVISED 1997   MEASURED
   Fluid                     20% MEA         30% MEA      30% MEA
   Temp          [ºC]           92            95 – 99         99
    SG                        0.965           1.015
    VP         [kg/cm2 a]      0.78            1.05
Suct. Press.   [kg/cm2 g]      0.60            0.50       0.25 – 0.60
   Flow         [m3/hr]      228 – 262       200 – 220    200 – 220
  NPSH A          [m]          9.00            4.90       2.45 – 5.90
  NPSH R          [m]          6.50            4.00 ?       4.00 ?
NPSH MARGIN                    38%         INSUFFICIENT     NONE
PROBLEM ANALYSIS
                        FACTORS ASSOCIATED TO LOW RELIABILTY
                                      SUCTION CONDITIONS - 1999

                         DESIGN         REVISED 1997   MEASURED
   Fluid                 20% MEA          30% MEA      30% MEA
   Temp         [F]        198            203 – 210       210
    SG                     0.965           1.015
    VP         [psia]      11.1             14.9
Suct. Press.   [psia]       8.5              7.1        3.5 – 8.5
   Flow        [GPM]    1000 – 1153       880 – 970    880 – 970
  NPSH A        [ft]       29.5             16.0       8.0 – 19.3
  NPSH R        [ft]       21.3             13.1 ?       13.1 ?
NPSH MARGIN                38%          INSUFFICIENT     NONE
PROBLEM ANALYSIS
               FACTORS ASSOCIATED TO LOW RELIABILTY
                                        SEPT 1999
OPERATIONAL
  • Low NPSHA
  • Part load operation
PROBLEM ANALYSIS
             FACTORS ASSOCIATED TO LOW RELIABILTY
                    PART LOAD OPERATION - 1999




                  EROSION &
                    SHROUD
                  SEPARATION




EVIDENCES OF RECIRCULATION AT DISCHARGE
PROBLEM ANALYSIS
               FACTORS ASSOCIATED TO LOW RELIABILTY
                                        SEPT 1999
OPERATIONAL
  • Low NPSHA
  • Part load operation                   MAY
                                        CONTINUE
  • Process disturbances
    (flow/pressure surges)

MAINTENANCE
   • Inoperative pipe supports
       - Transmission of pipe forces
       - Excessive deflection
PROBLEM ANALYSIS
     FACTORS ASSOCIATED TO LOW RELIABILTY
          MAINTENANCE PROBLEMS - 1999




 INOPERATIVE PIPE SUPPORTS
PROBLEM ANALYSIS
               FACTORS ASSOCIATED TO LOW RELIABILTY
                                        SEPT 1999
OPERATIONAL
  • Low NPSHA
  • Part load operation                   MAY
                                        CONTINUE
  • Process disturbances
    (flow/pressure surges)

MAINTENANCE
   • Inoperative pipe supports
       - Transmission of pipe forces     EASILY
       - Excessive deflection          CORRECTED

   • Improper procedures
PROBLEM ANALYSIS
                FACTORS ASSOCIATED TO LOW RELIABILTY
                                         SEPT 1999


MANUFACTURING DEFICIENCIES
  • Shaft (own shop)
  • Impeller   (local mfr)

                                         PUMP
                                          PUMP
DESIGN WEAKNESSES
                                        UPGRADE
                                        UPGRADE
   • Dated 1969
   • Hydraulics
   • Component Stiffness
   • Choice of Materials
PROBLEM ANALYSIS
                                    CORRELATION OF CAUSES FOR LOW RELIABILITY

                                      IMMEDIATE                              NOTICEABLE        EXPECTED
       MAIN CAUSES                                      CONSEQUENCES
                                        EFFECTS                               EFFECTS           FAILURE

OPERATION
• Plugged Filters / Coolers         • CAVITATION       • IMPELLER EROSION    • VIBRATION      • IMPELLER
• Too low NPSHA                     • INTERNAL         • IMBALANCE            INCREASE        • WEAR RINGS
• Part load operation                RECIRCULATION     • LARGE LOADS         • NOISE          • SHAFT
• Process disturbances              • TURBULENCE       • LARGE STRESSES      • LOSS OF        • BEARINGS
                                    • VIBRATION        • LARGE DEFLECTIONS    CAPACITY        • MECH. SEAL
MAINTENANCE                                                                  • SEAL LEAKAGE
                                    • INCREASE OF      • SEVERE RUBS
• Inoperative pipe supports          NPSHR             • LOSS OF RUNNING
• Improper wear ring materials      • PIPE FORCES       CLEARANCES
• Improper vane trim at inlet       • STRESS RISERS    • SHAFT FATIGUE
                                    • INSUFFICIENT     • LOSS OF FUNCTION
MANUFACTURE
                                     MAT PROPERTIES
• Improper part. vane position
                                    • MAT OF SIMILAR
• Insufficient shaft fillet radii    GALLING
                                     TENDENCY
DESIGN
• Deficiencies in hydraulics
• Insufficient stiffness
• Inadequate shaft end design
• Choice of materials
PUMP UPGRADE
                       IMPLEMENTATION OF SOLUTIONS

OBJECTIVES:
Identify & solve design weaknesses.
Correct component manufacturing deficiencies.
Incorporate modifications for improved
reliability.
Withstand tough operating conditions with low
NPSHA.
Manufacture of new parts, pump refurbishment,
stand testing & performance adjustment to
requirements by a qualified supplier.
PUMP UPGRADE
               AREAS OF ATTENTION
PUMP UPGRADE
                          AREAS OF ATTENTION



IMPELLER
PUMP UPGRADE
                  IMPELLER IMPROVEMENT




BEFORE                  AFTER

     VANE CORRECTIONS
PUMP UPGRADE
                             IMPELLER IMPROVEMENT




                      MANUFACTURING MATERIAL:

BEFORE                  ORIGINAL       NEW
                         AISI 304   18Cr-16Mn




AFTER

  VANE LEADING EDGE / MATERIAL IMPROVEMENT
PUMP UPGRADE
                          AREAS OF ATTENTION



IMPELLER




WEAR
RINGS
PUMP UPGRADE
                                   WEAR RINGS IMPROVEMENT




                  MANUFACTURING MATERIALS:

                         IN USE                 NEW
            DESIGN
                          (1999)        ALT 1          ALT 2
            AISI 304                  AISI 304 +
IMPELLER                 AISI 304                   18Cr-16Mn
            Stellitted                Cr. Plating

CASING      AISI 304     AISI 304     18Cr-16Mn       AISI 304


           WEAR RINGS MATERIALS
PUMP UPGRADE
                          AREAS OF ATTENTION



IMPELLER




WEAR                           SHAFT
RINGS
PUMP UPGRADE
                                                SHAFT IMPROVEMENT
                        L




                    D



                   DESIGN    SAME MFR   MFR 2     MFR 3
API 610 Ed.                                               APPLIED
                    (1969)      7th      8th       8th
   L       [in]     10.91      12.25    11.25     11.50    11.18
   D       [in]     2.480      2.937    2.625     2.440    2.953
L3 / D 4             34.3      24.7      30        43      18.4
Improvement             –      39%      14%       – 20%    86%
                  SHAFT FLEXIBILITY COMPARISON
PUMP UPGRADE
                                       SHAFT IMPROVEMENT

R 5/32”       R 1/4”



                             MANUFACTURING MATERIAL:

                               ORIGINAL       NEW
           INCREASED TO         AISI 304     AISI 420
          M48x2 FROM M38x2

    R 1/32”



     KEYWAY CORNER RADIUS

          SHAFT END / MATERIAL IMPROVEMENT
PUMP UPGRADE
                          AREAS OF ATTENTION

                     BEARING HOUSING

IMPELLER




WEAR                            SHAFT
RINGS
PUMP UPGRADE
       BEARING HOUSING IMPROVEMENT

                  ORIGINAL     NEW
      1” NEW
                 CAST IRON   A216 WCB




           5/8” ORIGINAL
PUMP UPGRADE
           BEARING HOUSING IMPROVEMENT




IMPROVED BEARING HOUSING
PUMP UPGRADE
                          AREAS OF ATTENTION

                     BEARING HOUSING

IMPELLER                       BEARINGS &
                               LUBRICATION




WEAR                            SHAFT
RINGS
PUMP UPGRADE
                      BEARINGS & LUBRICATION IMPROVEMENT
  6216 M                                    7314 BECBM
HSG BORE TOL:
                                             HSG BORE TOL:
+0,06 / +0,04 mm
                                            +0,045 / +0,025 mm
FINISH GROUND
PUMP UPGRADE
                            AREAS OF ATTENTION

                       BEARING HOUSING

IMPELLER                         BEARINGS &
                                 LUBRICATION




                   STUFF. BOX
WEAR                COOLING       SHAFT
RINGS
PUMP UPGRADE
                                            SUMMARY OF MAIN IMPROVEMENTS
                                                        BEFORE                          AFTER
              • PARTIAL VANES                         MISPOSITIONED             EXTENDED & CORRECTED

              • MAIN VANES AT INLET                   IMPROPER TRIM               TRIMMED IN PATTERN
 IMPELLER
              • VANE LEADING EDGES (ALL)                                    ROUNDED & THINNED IN PTRN

              • MATERIAL                                  AISI 304                    18 Cr – 16 Mn

                                                                            1      AISI 304 + Cr / 18Cr-16 Mn
WEAR RINGS    • IMPELLER / CASING                    AISI 304 / AISI 304
                                                                            2        18 Cr-16 Mn / AISI 304

              • L3/D4                                       34.3                           18.4

              • END THREAD SIZE / FILLET RADIUS    M38 + FILL. RAD. 3/32”       M48 + FILLET RADIUS 5/32”
  SHAFT
              • RADII AT SHOULDERS / CORNERS      3/32” AT END / SHARP KW       1/4” AT END / 1/32” AT KW

              • MATERIAL                                  AISI 304                       AISI 420

              • THICKNESS AT TRANSITION PIECE           16 mm (5/8”)                   25 mm (1.0”)
BEARING HSG
              • MATERIAL                                CAST IRON                CAST STEEL A216 WCB

 BEARINGS     • RADIAL / THRUST                        6215 / 7313 BG               6216 M / 7314 BGM

LUBRICATION                                                                     ENHANCED / CIRCULATING

MECH. SEAL    • STUFF. BOX COOLING                          NO                             YES

 COUPLING                                           GEAR/LUBRICATED              DISC PACK / NON-LUBR.
UPGRADED PUMP TEST
                     STAND-TESTING OF UPGRADED PUMP

OBJECTIVES:
Determine actual performance for modified
impeller.
Quantify actual NPSHR.
Reduce effects of adverse operating conditions:
    •   Trim impeller of pump “B” to reduce part
        load operation.
    •   Rework impeller, if required, to help
        prevent cavitation.
Guarantee trouble-free operation at the plant.
UPGRADED PUMP TEST
                                                      RESULTS OF PERFORMANCE TESTING

               00       200
                         200   400
                                400      600
                                          600        800
                                                      800          1000
                                                                    1000          1200
                                                                                   1200       1400
                                                                                               1400    Q [GPM]
                                                                                                       Q [GPM]

        340                                                                           Publ Head          1120
                                                                                                          1120
         340                                                                           Publ Head
                                                                                      Test Head
                                                                                       Test Head
                                                                                                         1060
                                                                                                          1060
        320
         320
                                                                                              BEP
                    3550 rpm φ 385 mm
                    3550 rpm φ 385 mm
                                                                                               BEP
                                                                                                         1000
                                                                                                          1000
        300
         300
                                                                                  ORIGINAL
                                                                                   ORIGINAL              940
                                                                                                          940
                                                                                   RATED
                                                                                    RATED




                                                                                                                 H [ft]
H [m]




        280




                                                                                                                 H [ft]
H [m]




         280                                                                        POINT
                                                                                     POINT
                                                                                                         880
                                                                                                          880
                                                                                              BEP
                                                                                               BEP
        260
         260                              REVISED
                                           REVISED                                                       820
                                                                                                          820
                                           RATED
                                            RATED
                                           POINT
                                            POINT
        240
         240
                                                                                                         760
                                                                                                          760
                                        OPERATING
                                         OPERATING
                                          RANGE
                                           RANGE
        220
         220                                                                                             700
                                                                                                          700

        200
         200                                                                                             640
                                                                                                          640
               00        50
                          50     100
                                  100       150
                                             150            200
                                                             200           250
                                                                            250           300
                                                                                           300        350
                                                                                                       350
                                                                                                        Q [m3/hr]
                                                                                                        Q [m3/hr]


                     HEAD VS FLOW – FULL SIZE IMPELLER
UPGRADED PUMP TEST
                                                              RESULTS OF PERFORMANCE TESTING

                    00       200
                              200      400
                                        400        600
                                                    600      800
                                                              800          1000
                                                                            1000          1200
                                                                                           1200      1400
                                                                                                      1400      Q [GPM]
                                                                                                                Q [GPM]
             500
              500
                            Publ Pwr
                            Publ Pwr          Test Pwr
                                               Test Pwr                                                         140
                                                                                                                 140
                            Publ Eff
                            Publ Eff          Test Eff
                                               Test Eff
             400
              400                                                                                               120
                                                                                                                 120
                     AVAILABLE MOTOR POWER
                      AVAILABLE MOTOR POWER

                                                                                                                100
                                                                                                                 100
Power [HP]




             300
Power [HP]




              300
                                                                                                                80
                                                                                                                 80




                                                                                                                      η (%)
                                                                                                                      η (%)
             200
              200                                                                                               60
                                                                                                                 60


                                                                                                                40
                                                                                                                 40
             100
              100
                                                                                                                20
                                                                                                                 20
                                                                                     OPERATING
                                                                                      OPERATING
                                                                                       RANGE
                                                                                        RANGE
               00                                                                                               00
                    00        50
                               50        100
                                          100         150
                                                       150          200
                                                                     200           250
                                                                                    250           300
                                                                                                   300       350
                                                                                                              350
                                                                                                                Q [m3/hr]
                                                                                                                Q [m3/hr]



                    PWR & EFF VS FLOW – FULL SIZE IMPELLER
UPGRADED PUMP TEST
                                                        RESULTS OF PERFORMANCE TESTING

               00        200
                          200    400
                                  400      600
                                            600        800
                                                        800          1000
                                                                      1000          1200
                                                                                     1200       1400
                                                                                                 1400    Q [GPM]
                                                                                                         Q [GPM]

        340                                                                             Publ Head          1120
                                                                                                            1120
         340                                                                             Publ Head
                    3550 rpm φ 385 mm
                    3550 rpm φ 385 mm                                                   Test Head
                                                                                         Test Head
                                                                                                           1060
                                                                                                            1060
        320
         320

                                                                                                           1000
                                                                                                            1000
        300
         300
                                                                                    ORIGINAL
                                                                                     ORIGINAL              940
                    3550 rpm φ 350 mm                                                                       940
                    3550 rpm φ 350 mm                                                RATED
                                                                                      RATED




                                                                                                                   H [ft]
H [m]




        280




                                                                                                                   H [ft]
H [m]




         280                                                                          POINT
                                                                                       POINT
                                                                                                           880
                                                                                                            880
                                                                                                BEP
                                                                                                 BEP
        260
         260                                REVISED
                                             REVISED                                                       820
                                                                                                            820
                                             RATED
                                              RATED
                                             POINT
                                              POINT
        240
         240
                                                                                                           760
                                                                                                            760
                                          OPERATING
                                           OPERATING
                                            RANGE
                                             RANGE
        220
         220                                                                                               700
                                                                                                            700

        200
         200                                                                                               640
                                                                                                            640
               00         50
                           50      100
                                    100       150
                                               150            200
                                                               200           250
                                                                              250           300
                                                                                             300        350
                                                                                                         350
                                                                                                          Q [m3/hr]
                                                                                                          Q [m3/hr]


                       HEAD VS FLOW – TRIMMED IMPELLER
UPGRADED PUMP TEST
                                                       RESULTS OF PERFORMANCE TESTING

          6,5
          6,5               11,5
                            11,5         16,5
                                         16,5           21,5
                                                        21,5        26,5
                                                                    26,5                 31,5 NPSH [ft]
                                                                                         31,5 NPSH [ft]
        260
        260
                                                                           Test NPSH
                                                                           Test NPSH            1,4
                                                                                                1,4
                                                3550 rpm φ 350 mm
                                                3550 rpm φ 350 mm




                                                                                                      Suction press @ oper. cond. [kgf/cm² g]
                                                                           Suct Press
                                                                           Suct Press
        255
        255
                                                                                                1,2
                                                                                                1,2


        250
        250                                                                                     1,0
                                                                                                1,0
                  3% DROP
                  3% DROP
                                                                                                0,8
H [m]




                                                                                                0,8
        245
        245

                                                                                                0,6
                                                                                                0,6
                                                         MIN REQ'D = 0,50 kgf/cm² g
                                                         MIN REQ'D = 0,50 kgf/cm² g
        240
        240
                                                                        (( 7,1 psig ))
                                                                           7,1 psig             0,4
                                                                                                0,4

        235
        235
                               60% MARGIN
                               60% MARGIN                                                       0,2
                                                                                                0,2


        230
        230                                                                                     0,0
                                                                                                0,0
              2
              2       3
                      3            4
                                   4     5
                                         5         6
                                                   6       7
                                                           7        8
                                                                    8         9
                                                                              9            10
                                                                                           10
              NPSHR 3% = 3,4 m (11 ft)
              NPSHR 3% = 3,4 m (11 ft)                                                      NPSH [m]
                                                                                            NPSH [m]



         NPSHR @ 220 m3/h (970 GPM) – TRIMMED IMPELLER
UPGRADED PUMP TEST
                                       TEST CONCLUSIONS


Performance of modified impeller was determined
  Head:         Larger due to partial vanes
  BEP:          Coincident at 300 m3/hr (1320 GPM)
  Efficiency:   Coincident with original
  NPSHR:        15% lower than expected

Adjustments for revised conditions of service:
  Pump “A”:     Full-size impeller @ 3150 rpm
  Pump “B”:     91% dia impeller @ 3550 rpm
                Min suct. press.: 0.5 kgf/cm² g (7.1 psig)
                Required NPSH Margin: 60%
UPGRADED PUMP “A”
                 PUMP IN SERVICE – MAY 2000




MAIN PUMP INSTALLED SEPT 1999
UPGRADED PUMP “A”
               PUMP IN SERVICE – MARCH 2002




MAIN PUMP INSTALLED SEPT 1999
UPGRADE RESULTS
                               COST – LEAD TIME COMPARISON

              PROS - CONS           COST & LEAD TIME

                                • ENGINEERING           $ 3,0 K
               Field work       • 1 PUMP & DRIVER     $ 90,0 K
    PUMP       required         • 2 YR SPARE PARTS      $ 5,0 K
REPLACEMENT    Larger cost      • FOUND. & PIPING      $10,0 K
                                         TOTAL:      $ 108 K
                                    11 MONTH ON SITE

                                • ENGINEERING          $ 5,0 K

               No field work
                                • BRG HSG PATTERN      $ 5,0 K
   PUMP                         • MAIN PARTS          $ 17,0 K
               required
 UPGRADE                        • MFG, ASSY & TEST    $ 12,0 K
               Less cost
                                          TOTAL:      $ 39 K
                                   11 MONTH FINISHED
UPGRADE RESULTS
                 CURRENT UPGRADE PROGRESS – END 2002

MAIN PUMP “A”
  Fully upgraded

STAND-BY PUMP “B”
  Partially upgraded
   •   Impeller & wear rings
   •   Shaft end design & material

  Impeller size increased from 91% to 96% (370 mm)
   •   Flow requirement not reached
   •   Measured suct. press.: ≈ 0.25 kgf/cm² g (3.6 psig)
   •   Full cavitation, NPSH margin < 0
UPGRADE RESULTS
                                        RELIABILITY IMPROVEMENT – END 2002


10
10                                                         MAIN PUMP “A”
 9
 9     PC-752B
       PC-752B
                                        UPGRADE "A"
                                        UPGRADE "A"
8
8      PC-752A
       PC-752A                                               Fully upgraded
7
7
6
                                                             No failures
6
5
5
4
4                                                          STAND-BY PUMP “B”
3
3
2
                                                             Partially upgraded
2
1
1                                                            Failures at brgs &
0
0                                                            seal only
     1995
     1995   1996
            1996   1997
                   1997   1998 1999
                          1998 1999   2000
                                      2000   2001
                                             2001   2002
                                                    2002


                   Projected savings over 10 years: US$ 900 K

      FAILURE HISTORY BEFORE AND AFTER THE UPGRADE
CONCLUSIONS

Pump upgrade objectives were successfully
achieved.
Upgrade of existing pump was the best choice
for a cost-effective solution.
In-house engineering allowed a custom design
with some features exceeding current mfr. specs.
Impeller revised configuration is not an optimum
solution, but provided a remarkable service life
improvement.
Detected design deficiencies played an important
role on low reliability, but not on catastrophic
failures.
LESSONS LEARNED



In general, improvement of existing equipment
represents lower investment and lead time.
Check your equipment for upgrade opportunities,
specially if they exhibit low reliability.
REFERENCES
        RELIABILITY IMPROVEMENT OF END SUCTION PUMP IN SEVERE SERVICE
                                THRU ENGINEERED COMPONENT UPGRADE



Mc. Caul, Colin. An Advanced Cavitation Resistant Austenitic Steel for
Pumps. Corrosion 96, The NACE International Annual Conference and
Exposition. Paper Nº 415, 1996.

Bloch, Heinz P. Improving Machinery Reliability. 2nd Edition. 1988. Gulf
Publishing Company
Bloch, Heinz P. Pump Reliability Improvement Program. Pump Failure
Reduction Programs. PRIME Seminar notes
J.F. Gülich. Selection criteria for suction impellers of centrifugal pumps.
Part 1: The suction specific speed – a criterion for flow recirculation
and pump reliability ?, Sulzer Pumps Ltd, PO Box, CH-8400 Winterthur,
Switzerland.
Summers-Smith, J.D. A Tribology Casebook. P.83. Mechanical Engineering
Publications London and Bury St. Edmunds, 1997.
Pfleiderer, Carl. Bombas Centrífugas y Turbocompresores. Editorial
Labor, 1960.
®

    20th International Pump Users Symposium
    March 17-20, 2003. Houston, Texas




THANK YOU !

More Related Content

Similar to Reliability Improvement of End-Suction Pump through Engineered Component Upgrade

Rebowl Upgrade of Vertical-Turbine Pumps Proven Effective
Rebowl Upgrade of Vertical-Turbine Pumps Proven EffectiveRebowl Upgrade of Vertical-Turbine Pumps Proven Effective
Rebowl Upgrade of Vertical-Turbine Pumps Proven EffectiveCésar Augusto Morales Casanova
 
Degree Work Overview (Katja Maslova)
Degree Work Overview (Katja Maslova)Degree Work Overview (Katja Maslova)
Degree Work Overview (Katja Maslova)Katja Maslova
 
John deere 9500 and sidehill9500 maximaizer combines parts catalog
John deere 9500 and sidehill9500 maximaizer combines parts catalogJohn deere 9500 and sidehill9500 maximaizer combines parts catalog
John deere 9500 and sidehill9500 maximaizer combines parts catalogPartCatalogs Net
 
John deere 9410 maximaizer combine parts catalog
John deere 9410 maximaizer combine parts catalogJohn deere 9410 maximaizer combine parts catalog
John deere 9410 maximaizer combine parts catalogPartCatalogs Net
 
Modification Of Bb1 Pump Vibration Characteristics To Meet ISO 13709 2nd Edit...
Modification Of Bb1 Pump Vibration Characteristics To Meet ISO 13709 2nd Edit...Modification Of Bb1 Pump Vibration Characteristics To Meet ISO 13709 2nd Edit...
Modification Of Bb1 Pump Vibration Characteristics To Meet ISO 13709 2nd Edit...sbradsha1
 
Case 9010 excavator service repair manual
Case 9010 excavator service repair manualCase 9010 excavator service repair manual
Case 9010 excavator service repair manualfjkskekkemmmd
 
Case 9010 excavator service repair manual
Case 9010 excavator service repair manualCase 9010 excavator service repair manual
Case 9010 excavator service repair manualfjskefkemms
 
Cub cadet 7360 ss compact tractor service repair manual
Cub cadet 7360 ss compact tractor service repair manualCub cadet 7360 ss compact tractor service repair manual
Cub cadet 7360 ss compact tractor service repair manualfjjskekkdkoepll
 
Cub cadet 7360 ss compact tractor service repair manual
Cub cadet 7360 ss compact tractor service repair manualCub cadet 7360 ss compact tractor service repair manual
Cub cadet 7360 ss compact tractor service repair manualfujdjjksekmem
 

Similar to Reliability Improvement of End-Suction Pump through Engineered Component Upgrade (9)

Rebowl Upgrade of Vertical-Turbine Pumps Proven Effective
Rebowl Upgrade of Vertical-Turbine Pumps Proven EffectiveRebowl Upgrade of Vertical-Turbine Pumps Proven Effective
Rebowl Upgrade of Vertical-Turbine Pumps Proven Effective
 
Degree Work Overview (Katja Maslova)
Degree Work Overview (Katja Maslova)Degree Work Overview (Katja Maslova)
Degree Work Overview (Katja Maslova)
 
John deere 9500 and sidehill9500 maximaizer combines parts catalog
John deere 9500 and sidehill9500 maximaizer combines parts catalogJohn deere 9500 and sidehill9500 maximaizer combines parts catalog
John deere 9500 and sidehill9500 maximaizer combines parts catalog
 
John deere 9410 maximaizer combine parts catalog
John deere 9410 maximaizer combine parts catalogJohn deere 9410 maximaizer combine parts catalog
John deere 9410 maximaizer combine parts catalog
 
Modification Of Bb1 Pump Vibration Characteristics To Meet ISO 13709 2nd Edit...
Modification Of Bb1 Pump Vibration Characteristics To Meet ISO 13709 2nd Edit...Modification Of Bb1 Pump Vibration Characteristics To Meet ISO 13709 2nd Edit...
Modification Of Bb1 Pump Vibration Characteristics To Meet ISO 13709 2nd Edit...
 
Case 9010 excavator service repair manual
Case 9010 excavator service repair manualCase 9010 excavator service repair manual
Case 9010 excavator service repair manual
 
Case 9010 excavator service repair manual
Case 9010 excavator service repair manualCase 9010 excavator service repair manual
Case 9010 excavator service repair manual
 
Cub cadet 7360 ss compact tractor service repair manual
Cub cadet 7360 ss compact tractor service repair manualCub cadet 7360 ss compact tractor service repair manual
Cub cadet 7360 ss compact tractor service repair manual
 
Cub cadet 7360 ss compact tractor service repair manual
Cub cadet 7360 ss compact tractor service repair manualCub cadet 7360 ss compact tractor service repair manual
Cub cadet 7360 ss compact tractor service repair manual
 

Reliability Improvement of End-Suction Pump through Engineered Component Upgrade

  • 1. USER CASE STUDY ABSTRACT 20th International Pump Users Symposium TITLE: Reliability Improvement of End Suction Pump in Severe Service through Engineered Component Upgrade ABSTRACT: An end suction pump for amine service at an Ammonia plant was successfully upgraded by improvement of its components. Two 290 kW (390 HP) pumps, turbine/motor driven, rated for 262 m3/hr (1,153 gpm) and 271 m (889 ft), operate in severe service conditions due low NPSHA and part-load operation. The equipment exhibited rough operation with high vibration and an elevated repair frequency by recurrent fatigue failure of shaft, severe wear ring rubs, impeller corrosion/erosion, mechanical seal leakage and bearing damages.. After a catastrophic failure, involving pump and electric motor, that caused an emergency plant shutdown, an upgrade for the pumps was engineered. The objective was to overcome design weaknesses and incorporate features to increase reliability. Impeller deficiencies were identified and corrected and its metallurgy improved to endure severe cavitation/recirculation damage. The power end was completely redesigned, incorporating larger shaft and bearing housing stiffness, together with a material upgrade, oversized bearings and lubrication enhancements. As a result, a failure frequency as large as 9 a year has been eliminated since the upgrade and the pump presently accumulates 3 years of continuous operation. An outstanding improvement in reliability was obtained together with considerable savings in investment & maintenance costs. AUTHOR: César A. Morales Casanova Rotating Equipment Specialist PDVSA – Pequiven Morón Petrochemical Complex Edo. Carabobo Venezuela
  • 2. ® 20th International Pump Users Symposium March 17-20, 2003. Houston, Texas RELIABILITY IMPROVEMENT OF END SUCTION PUMP IN SEVERE SERVICE THROUGH ENGINEERED COMPONENT UPGRADE César A. Morales Casanova Rotating Equipment Specialist PDVSA - Pequiven Edo. Carabobo - Venezuela
  • 3. CONTENTS • Objective • Conditions of service – Amine recovery system • Pump failures Experience of continued low reliability Problem areas – Original design Remedial actions – Historical review 1980 – 1997 Catastrophic failure – 1998 • Preliminary analysis – Recurrent pump failures • Problem analysis Factors associated to low reliability Correlation of causes for low reliability • Pump upgrade Objectives Areas of attention Summary of main improvements • Upgraded pump test Objectives Results of performance testing Test conclusions • Upgrade results Cost – lead time comparison Current upgrade progress – end 2002 Reliability improvement • Conclusions • Lessons learned • References
  • 4. OBJECTIVE A successful experience of reliability improvement of two process pumps, through the application of a cost-effective, “in-house” engineered component upgrade is presented. The solution can be used as a reference to yield better mechanical performance of existing equipment in similar services.
  • 5. SITUATION OVERVIEW AMINE RECOVERY SERVICE FCV C-754 C-752 PUMP RATINGS: PCV Q : 262 m3/hr (1,153 GPM) H : 271 m (889 ft) N : 3550 RPM PC-752A/B P : 290 kW (390 HP) MAIN PUMP “A” Turbine Driven STAND-BY PUMP “B” Motor Driven
  • 6. PUMP FAILURES EXPERIENCE OF CONTINUED LOW RELIABILITY OPERATION PROBLEMS: 10 PC-752B High Vibration 9 8 PC-752A Low Capacity 7 Product Leakage 6 5 4 FAILED COMPONENTS: 3 2 Impeller 1 Wear Rings 0 Shaft 1995 1996 1997 1998 1999 Bearings Mechanical Seal
  • 7. PUMP FAILURES PROBLEM AREAS - ORIGINAL DESIGN
  • 8. PUMP FAILURES PROBLEM AREAS - ORIGINAL DESIGN WEAR RINGS
  • 9. PUMP FAILURES PROBLEM AREAS - ORIGINAL DESIGN SEVERE RUBBING AT WEAR RINGS - 1996
  • 10. PUMP FAILURES PROBLEM AREAS - ORIGINAL DESIGN WEAR RINGS SHAFT
  • 11. PUMP FAILURES PROBLEM AREAS - ORIGINAL DESIGN SHAFT FAILURE AT IMPELLER END - 1992
  • 12. PUMP FAILURES PROBLEM AREAS - ORIGINAL DESIGN WEAR RINGS SHAFT IMPELLER
  • 13. PUMP FAILURES PROBLEM AREAS - ORIGINAL DESIGN EROSION W/R RUB SEVERE IMPELLER FAILURE - 1992
  • 14. PUMP FAILURES PROBLEM AREAS - ORIGINAL DESIGN WEAR RINGS SHAFT IMPELLER MECH. SEAL
  • 15. PUMP FAILURES PROBLEM AREAS - ORIGINAL DESIGN WEAR RINGS BEARINGS SHAFT IMPELLER MECH. SEAL
  • 16. PUMP FAILURES REMEDIAL ACTIONS – HYSTORICAL REVIEW YEAR COMPONENT ACTION 1980 Impeller Installed pins between shrouds 1986 Shaft Impeller capscrew replaced to fine thread 1991 Impeller Local manufacture of impellers 1992 Shaft Impeller capscrew replaced by a nut 1994 Wear Rings Increase in wear ring clearances 1995 Impeller Incorporation of 3 partial vanes 1996 Impeller Impeller trim to pump “B” 1997 Impeller Trimming of vanes at inlet Bearings 5313 thrust bearing replaced by 7313
  • 17. PUMP FAILURES REMEDIAL ACTIONS – HYSTORICAL REVIEW YEAR COMPONENT DESCRIPTION 1980 Impeller Installed pins between shrouds
  • 18. PUMP FAILURES REMEDIAL ACTIONS – HYSTORICAL REVIEW 1980 PINS INSTALLED BETWEEN IMPELLER SHROUDS
  • 19. PUMP FAILURES REMEDIAL ACTIONS – HYSTORICAL REVIEW YEAR COMPONENT DESCRIPTION 1980 Impeller Installed pins between shrouds 1986 Shaft Impeller capscrew replaced to fine thread
  • 20. PUMP FAILURES REMEDIAL ACTIONS – HYSTORICAL REVIEW 1986 CAPSCREW M 24 NC TO NF
  • 21. PUMP FAILURES REMEDIAL ACTIONS – HYSTORICAL REVIEW YEAR COMPONENT DESCRIPTION 1980 Impeller Installed pins between shrouds 1986 Shaft Impeller capscrew replaced to fine thread 1991 Impeller Local manufacture of impellers 1992 Shaft Impeller capscrew replaced by a nut
  • 22. PUMP FAILURES REMEDIAL ACTIONS – HYSTORICAL REVIEW 1992 IMPELLER NUT M 38 NF CAPSCRW M 24 NF
  • 23. PUMP FAILURES REMEDIAL ACTIONS – HYSTORICAL REVIEW Pump “B” SHAFT FAILURE AT IMPELLER END - MAY 1999
  • 24. PUMP FAILURES REMEDIAL ACTIONS – HYSTORICAL REVIEW YEAR COMPONENT DESCRIPTION 1980 Impeller Installed pins between shrouds 1986 Shaft Impeller capscrew replaced to fine thread 1991 Impeller Local manufacture of impellers 1992 Shaft Impeller capscrew replaced by a nut 1994 Wear Rings Increase in wear rings running clearance 1995 Impeller Incorporation of 3 partial vanes
  • 25. PUMP FAILURES REMEDIAL ACTIONS – HYSTORICAL REVIEW 1995 IMPELLER PATTERN WITH 3 PARTIAL VANES ADDED EROSION CONTINUED
  • 26. PUMP FAILURES REMEDIAL ACTIONS – HYSTORICAL REVIEW YEAR COMPONENT DESCRIPTION 1980 Impeller Installed pins between shrouds 1986 Shaft Impeller capscrew replaced to fine thread 1991 Impeller Local manufacture of impellers 1992 Shaft Impeller capscrew replaced by a nut 1994 Wear Rings Increase in wear rings running clearance 1995 Impeller Incorporation of 3 partial vanes 1996 Impeller Impeller trim to pump “B”
  • 27. PUMP FAILURES REMEDIAL ACTIONS – HYSTORICAL REVIEW 1996 00 200 200 400 400 600 600 800 800 1000 1000 1200 1200 1400 1400 Q [GPM] Q [GPM] 340 Publ Head 1120 1120 340 Publ Head Publ Head 3550 rpm φ 385 mm 3550 rpm φ 385 mm Publ Head Corr Head Corr Head 1060 1060 320 320 30% 1000 1000 300 300 PUMP “A” Imp φ385 mm RATED RATED 940 940 H [ft] H [m] 280 @ 3200 rpm POINT H [ft] H [m] 280 POINT 880 880 BEP BEP 260 260 PUMP “B” Imp φ348 mm 820 820 @ 3550 rpm 240 240 760 760 OPERATING 220 OPERATING RANGE RANGE PROCESS FLOW 220 700 NOT700 REACHED 200 200 640 640 00 50 50 100 100 150 150 200 200 250 250 300 300 350 350 Q [m3/hr] Q [m3/hr] IMPELLER TRIM OF STAND-BY PUMP “B”
  • 28. PUMP FAILURES REMEDIAL ACTIONS – HYSTORICAL REVIEW 1996 00 200 200 400 400 600 600 800 800 1000 1000 1200 1200 1400 1400 Q [GPM] Q [GPM] 340 Publ Head 1120 1120 340 Publ Head 3550 rpm φ 385 mm 3550 rpm φ 385 mm Corr Head Corr Head 1060 1060 320 320 1000 1000 300 300 940 940 RATED RATED H [ft] H [m] 280 H [ft] POINT H [m] 280 POINT PUMP “B” Imp φ370 mm 880 880 @ 3550 rpm BEP BEP 260 260 820 CAVITATION 820 240 240 760 760 OPERATING OPERATING RANGE RANGE 220 220 700 700 200 200 640 640 00 50 50 100 100 150 150 200 200 250 250 300 300 350 350 Q [m3/hr] Q [m3/hr] IMPELLER TRIM OF STAND-BY PUMP “B”
  • 29. PUMP FAILURES REMEDIAL ACTIONS – HYSTORICAL REVIEW YEAR COMPONENT DESCRIPTION 1980 Impeller Installed pins between shrouds 1986 Shaft Impeller capscrew replaced to fine thread 1991 Impeller Local manufacture of impellers 1992 Shaft Impeller capscrew replaced by a nut 1994 Wear Rings Increase in wear rings running clearance 1995 Impeller Incorporation of 3 partial vanes 1996 Impeller Impeller trim to pump “B” 1997 Impeller Trimming of vanes at inlet
  • 30. PUMP FAILURES REMEDIAL ACTIONS – HYSTORICAL REVIEW 1997 VANE TRIM AT IMPELLER INLET TO REDUCE NPSHR IMPROPERLY EFFECTED
  • 31. PUMP FAILURES REMEDIAL ACTIONS – HYSTORICAL REVIEW YEAR COMPONENT DESCRIPTION 1980 Impeller Installed pins between shrouds 1986 Shaft Impeller capscrew replaced to fine thread 1991 Impeller Local manufacture of impellers 1992 Shaft Impeller capscrew replaced by a nut 1994 Wear Rings Increase in wear rings running clearance 1995 Impeller Incorporation of 3 partial vanes 1996 Impeller Impeller trim to pump “B” 1997 Impeller Trimming of vanes at inlet Bearings 5313 thrust bearing replaced by 7313 BG
  • 32. PUMP FAILURES REMEDIAL ACTIONS – HYSTORICAL REVIEW 1997 THRUST BEARING UPGRADE FROM 3313 TO 7313 BG
  • 33. PUMP FAILURES CATASTROPHIC FAILURE – PUMP “B” SEPT 1998
  • 34. PRELIMINARY ANALYSIS RECURRENT PUMP FAILURES SEPT 1999 Unsuccessful efforts to improve reliability. Solutions mainly focused in the consequences rather than the causes for the problems. Improper procedures contribute to failures. Complex problem with multiple correlated causes and failure modes. Global solution required.
  • 35. PROBLEM ANALYSIS FACTORS ASSOCIATED TO LOW RELIABILTY SEPT 1999 OPERATIONAL • Low NPSHA
  • 36. PROBLEM ANALYSIS FACTORS ASSOCIATED TO LOW RELIABILTY SUCTION CONDITIONS - 1999 PLUGGING OF PLATE COOLER FCV C-754 C-752 PCV INOP. FILTER TEMP INCREASE & PC-752A/B REDUCTION OF SUCTION PRESSURE MEA RECOVERY SYSTEM
  • 37. PROBLEM ANALYSIS FACTORS ASSOCIATED TO LOW RELIABILTY SUCTION CONDITIONS - 1999 DESIGN REVISED 1997 MEASURED Fluid 20% MEA 30% MEA 30% MEA Temp [ºC] 92 95 – 99 99 SG 0.965 1.015 VP [kg/cm2 a] 0.78 1.05 Suct. Press. [kg/cm2 g] 0.60 0.50 0.25 – 0.60 Flow [m3/hr] 228 – 262 200 – 220 200 – 220 NPSH A [m] 9.00 4.90 2.45 – 5.90 NPSH R [m] 6.50 4.00 ? 4.00 ? NPSH MARGIN 38% INSUFFICIENT NONE
  • 38. PROBLEM ANALYSIS FACTORS ASSOCIATED TO LOW RELIABILTY SUCTION CONDITIONS - 1999 DESIGN REVISED 1997 MEASURED Fluid 20% MEA 30% MEA 30% MEA Temp [F] 198 203 – 210 210 SG 0.965 1.015 VP [psia] 11.1 14.9 Suct. Press. [psia] 8.5 7.1 3.5 – 8.5 Flow [GPM] 1000 – 1153 880 – 970 880 – 970 NPSH A [ft] 29.5 16.0 8.0 – 19.3 NPSH R [ft] 21.3 13.1 ? 13.1 ? NPSH MARGIN 38% INSUFFICIENT NONE
  • 39. PROBLEM ANALYSIS FACTORS ASSOCIATED TO LOW RELIABILTY SEPT 1999 OPERATIONAL • Low NPSHA • Part load operation
  • 40. PROBLEM ANALYSIS FACTORS ASSOCIATED TO LOW RELIABILTY PART LOAD OPERATION - 1999 EROSION & SHROUD SEPARATION EVIDENCES OF RECIRCULATION AT DISCHARGE
  • 41. PROBLEM ANALYSIS FACTORS ASSOCIATED TO LOW RELIABILTY SEPT 1999 OPERATIONAL • Low NPSHA • Part load operation MAY CONTINUE • Process disturbances (flow/pressure surges) MAINTENANCE • Inoperative pipe supports - Transmission of pipe forces - Excessive deflection
  • 42. PROBLEM ANALYSIS FACTORS ASSOCIATED TO LOW RELIABILTY MAINTENANCE PROBLEMS - 1999 INOPERATIVE PIPE SUPPORTS
  • 43. PROBLEM ANALYSIS FACTORS ASSOCIATED TO LOW RELIABILTY SEPT 1999 OPERATIONAL • Low NPSHA • Part load operation MAY CONTINUE • Process disturbances (flow/pressure surges) MAINTENANCE • Inoperative pipe supports - Transmission of pipe forces EASILY - Excessive deflection CORRECTED • Improper procedures
  • 44. PROBLEM ANALYSIS FACTORS ASSOCIATED TO LOW RELIABILTY SEPT 1999 MANUFACTURING DEFICIENCIES • Shaft (own shop) • Impeller (local mfr) PUMP PUMP DESIGN WEAKNESSES UPGRADE UPGRADE • Dated 1969 • Hydraulics • Component Stiffness • Choice of Materials
  • 45. PROBLEM ANALYSIS CORRELATION OF CAUSES FOR LOW RELIABILITY IMMEDIATE NOTICEABLE EXPECTED MAIN CAUSES CONSEQUENCES EFFECTS EFFECTS FAILURE OPERATION • Plugged Filters / Coolers • CAVITATION • IMPELLER EROSION • VIBRATION • IMPELLER • Too low NPSHA • INTERNAL • IMBALANCE INCREASE • WEAR RINGS • Part load operation RECIRCULATION • LARGE LOADS • NOISE • SHAFT • Process disturbances • TURBULENCE • LARGE STRESSES • LOSS OF • BEARINGS • VIBRATION • LARGE DEFLECTIONS CAPACITY • MECH. SEAL MAINTENANCE • SEAL LEAKAGE • INCREASE OF • SEVERE RUBS • Inoperative pipe supports NPSHR • LOSS OF RUNNING • Improper wear ring materials • PIPE FORCES CLEARANCES • Improper vane trim at inlet • STRESS RISERS • SHAFT FATIGUE • INSUFFICIENT • LOSS OF FUNCTION MANUFACTURE MAT PROPERTIES • Improper part. vane position • MAT OF SIMILAR • Insufficient shaft fillet radii GALLING TENDENCY DESIGN • Deficiencies in hydraulics • Insufficient stiffness • Inadequate shaft end design • Choice of materials
  • 46. PUMP UPGRADE IMPLEMENTATION OF SOLUTIONS OBJECTIVES: Identify & solve design weaknesses. Correct component manufacturing deficiencies. Incorporate modifications for improved reliability. Withstand tough operating conditions with low NPSHA. Manufacture of new parts, pump refurbishment, stand testing & performance adjustment to requirements by a qualified supplier.
  • 47. PUMP UPGRADE AREAS OF ATTENTION
  • 48. PUMP UPGRADE AREAS OF ATTENTION IMPELLER
  • 49. PUMP UPGRADE IMPELLER IMPROVEMENT BEFORE AFTER VANE CORRECTIONS
  • 50. PUMP UPGRADE IMPELLER IMPROVEMENT MANUFACTURING MATERIAL: BEFORE ORIGINAL NEW AISI 304 18Cr-16Mn AFTER VANE LEADING EDGE / MATERIAL IMPROVEMENT
  • 51. PUMP UPGRADE AREAS OF ATTENTION IMPELLER WEAR RINGS
  • 52. PUMP UPGRADE WEAR RINGS IMPROVEMENT MANUFACTURING MATERIALS: IN USE NEW DESIGN (1999) ALT 1 ALT 2 AISI 304 AISI 304 + IMPELLER AISI 304 18Cr-16Mn Stellitted Cr. Plating CASING AISI 304 AISI 304 18Cr-16Mn AISI 304 WEAR RINGS MATERIALS
  • 53. PUMP UPGRADE AREAS OF ATTENTION IMPELLER WEAR SHAFT RINGS
  • 54. PUMP UPGRADE SHAFT IMPROVEMENT L D DESIGN SAME MFR MFR 2 MFR 3 API 610 Ed. APPLIED (1969) 7th 8th 8th L [in] 10.91 12.25 11.25 11.50 11.18 D [in] 2.480 2.937 2.625 2.440 2.953 L3 / D 4 34.3 24.7 30 43 18.4 Improvement – 39% 14% – 20% 86% SHAFT FLEXIBILITY COMPARISON
  • 55. PUMP UPGRADE SHAFT IMPROVEMENT R 5/32” R 1/4” MANUFACTURING MATERIAL: ORIGINAL NEW INCREASED TO AISI 304 AISI 420 M48x2 FROM M38x2 R 1/32” KEYWAY CORNER RADIUS SHAFT END / MATERIAL IMPROVEMENT
  • 56. PUMP UPGRADE AREAS OF ATTENTION BEARING HOUSING IMPELLER WEAR SHAFT RINGS
  • 57. PUMP UPGRADE BEARING HOUSING IMPROVEMENT ORIGINAL NEW 1” NEW CAST IRON A216 WCB 5/8” ORIGINAL
  • 58. PUMP UPGRADE BEARING HOUSING IMPROVEMENT IMPROVED BEARING HOUSING
  • 59. PUMP UPGRADE AREAS OF ATTENTION BEARING HOUSING IMPELLER BEARINGS & LUBRICATION WEAR SHAFT RINGS
  • 60. PUMP UPGRADE BEARINGS & LUBRICATION IMPROVEMENT 6216 M 7314 BECBM HSG BORE TOL: HSG BORE TOL: +0,06 / +0,04 mm +0,045 / +0,025 mm FINISH GROUND
  • 61. PUMP UPGRADE AREAS OF ATTENTION BEARING HOUSING IMPELLER BEARINGS & LUBRICATION STUFF. BOX WEAR COOLING SHAFT RINGS
  • 62. PUMP UPGRADE SUMMARY OF MAIN IMPROVEMENTS BEFORE AFTER • PARTIAL VANES MISPOSITIONED EXTENDED & CORRECTED • MAIN VANES AT INLET IMPROPER TRIM TRIMMED IN PATTERN IMPELLER • VANE LEADING EDGES (ALL) ROUNDED & THINNED IN PTRN • MATERIAL AISI 304 18 Cr – 16 Mn 1 AISI 304 + Cr / 18Cr-16 Mn WEAR RINGS • IMPELLER / CASING AISI 304 / AISI 304 2 18 Cr-16 Mn / AISI 304 • L3/D4 34.3 18.4 • END THREAD SIZE / FILLET RADIUS M38 + FILL. RAD. 3/32” M48 + FILLET RADIUS 5/32” SHAFT • RADII AT SHOULDERS / CORNERS 3/32” AT END / SHARP KW 1/4” AT END / 1/32” AT KW • MATERIAL AISI 304 AISI 420 • THICKNESS AT TRANSITION PIECE 16 mm (5/8”) 25 mm (1.0”) BEARING HSG • MATERIAL CAST IRON CAST STEEL A216 WCB BEARINGS • RADIAL / THRUST 6215 / 7313 BG 6216 M / 7314 BGM LUBRICATION ENHANCED / CIRCULATING MECH. SEAL • STUFF. BOX COOLING NO YES COUPLING GEAR/LUBRICATED DISC PACK / NON-LUBR.
  • 63. UPGRADED PUMP TEST STAND-TESTING OF UPGRADED PUMP OBJECTIVES: Determine actual performance for modified impeller. Quantify actual NPSHR. Reduce effects of adverse operating conditions: • Trim impeller of pump “B” to reduce part load operation. • Rework impeller, if required, to help prevent cavitation. Guarantee trouble-free operation at the plant.
  • 64. UPGRADED PUMP TEST RESULTS OF PERFORMANCE TESTING 00 200 200 400 400 600 600 800 800 1000 1000 1200 1200 1400 1400 Q [GPM] Q [GPM] 340 Publ Head 1120 1120 340 Publ Head Test Head Test Head 1060 1060 320 320 BEP 3550 rpm φ 385 mm 3550 rpm φ 385 mm BEP 1000 1000 300 300 ORIGINAL ORIGINAL 940 940 RATED RATED H [ft] H [m] 280 H [ft] H [m] 280 POINT POINT 880 880 BEP BEP 260 260 REVISED REVISED 820 820 RATED RATED POINT POINT 240 240 760 760 OPERATING OPERATING RANGE RANGE 220 220 700 700 200 200 640 640 00 50 50 100 100 150 150 200 200 250 250 300 300 350 350 Q [m3/hr] Q [m3/hr] HEAD VS FLOW – FULL SIZE IMPELLER
  • 65. UPGRADED PUMP TEST RESULTS OF PERFORMANCE TESTING 00 200 200 400 400 600 600 800 800 1000 1000 1200 1200 1400 1400 Q [GPM] Q [GPM] 500 500 Publ Pwr Publ Pwr Test Pwr Test Pwr 140 140 Publ Eff Publ Eff Test Eff Test Eff 400 400 120 120 AVAILABLE MOTOR POWER AVAILABLE MOTOR POWER 100 100 Power [HP] 300 Power [HP] 300 80 80 η (%) η (%) 200 200 60 60 40 40 100 100 20 20 OPERATING OPERATING RANGE RANGE 00 00 00 50 50 100 100 150 150 200 200 250 250 300 300 350 350 Q [m3/hr] Q [m3/hr] PWR & EFF VS FLOW – FULL SIZE IMPELLER
  • 66. UPGRADED PUMP TEST RESULTS OF PERFORMANCE TESTING 00 200 200 400 400 600 600 800 800 1000 1000 1200 1200 1400 1400 Q [GPM] Q [GPM] 340 Publ Head 1120 1120 340 Publ Head 3550 rpm φ 385 mm 3550 rpm φ 385 mm Test Head Test Head 1060 1060 320 320 1000 1000 300 300 ORIGINAL ORIGINAL 940 3550 rpm φ 350 mm 940 3550 rpm φ 350 mm RATED RATED H [ft] H [m] 280 H [ft] H [m] 280 POINT POINT 880 880 BEP BEP 260 260 REVISED REVISED 820 820 RATED RATED POINT POINT 240 240 760 760 OPERATING OPERATING RANGE RANGE 220 220 700 700 200 200 640 640 00 50 50 100 100 150 150 200 200 250 250 300 300 350 350 Q [m3/hr] Q [m3/hr] HEAD VS FLOW – TRIMMED IMPELLER
  • 67. UPGRADED PUMP TEST RESULTS OF PERFORMANCE TESTING 6,5 6,5 11,5 11,5 16,5 16,5 21,5 21,5 26,5 26,5 31,5 NPSH [ft] 31,5 NPSH [ft] 260 260 Test NPSH Test NPSH 1,4 1,4 3550 rpm φ 350 mm 3550 rpm φ 350 mm Suction press @ oper. cond. [kgf/cm² g] Suct Press Suct Press 255 255 1,2 1,2 250 250 1,0 1,0 3% DROP 3% DROP 0,8 H [m] 0,8 245 245 0,6 0,6 MIN REQ'D = 0,50 kgf/cm² g MIN REQ'D = 0,50 kgf/cm² g 240 240 (( 7,1 psig )) 7,1 psig 0,4 0,4 235 235 60% MARGIN 60% MARGIN 0,2 0,2 230 230 0,0 0,0 2 2 3 3 4 4 5 5 6 6 7 7 8 8 9 9 10 10 NPSHR 3% = 3,4 m (11 ft) NPSHR 3% = 3,4 m (11 ft) NPSH [m] NPSH [m] NPSHR @ 220 m3/h (970 GPM) – TRIMMED IMPELLER
  • 68. UPGRADED PUMP TEST TEST CONCLUSIONS Performance of modified impeller was determined Head: Larger due to partial vanes BEP: Coincident at 300 m3/hr (1320 GPM) Efficiency: Coincident with original NPSHR: 15% lower than expected Adjustments for revised conditions of service: Pump “A”: Full-size impeller @ 3150 rpm Pump “B”: 91% dia impeller @ 3550 rpm Min suct. press.: 0.5 kgf/cm² g (7.1 psig) Required NPSH Margin: 60%
  • 69. UPGRADED PUMP “A” PUMP IN SERVICE – MAY 2000 MAIN PUMP INSTALLED SEPT 1999
  • 70. UPGRADED PUMP “A” PUMP IN SERVICE – MARCH 2002 MAIN PUMP INSTALLED SEPT 1999
  • 71. UPGRADE RESULTS COST – LEAD TIME COMPARISON PROS - CONS COST & LEAD TIME • ENGINEERING $ 3,0 K Field work • 1 PUMP & DRIVER $ 90,0 K PUMP required • 2 YR SPARE PARTS $ 5,0 K REPLACEMENT Larger cost • FOUND. & PIPING $10,0 K TOTAL: $ 108 K 11 MONTH ON SITE • ENGINEERING $ 5,0 K No field work • BRG HSG PATTERN $ 5,0 K PUMP • MAIN PARTS $ 17,0 K required UPGRADE • MFG, ASSY & TEST $ 12,0 K Less cost TOTAL: $ 39 K 11 MONTH FINISHED
  • 72. UPGRADE RESULTS CURRENT UPGRADE PROGRESS – END 2002 MAIN PUMP “A” Fully upgraded STAND-BY PUMP “B” Partially upgraded • Impeller & wear rings • Shaft end design & material Impeller size increased from 91% to 96% (370 mm) • Flow requirement not reached • Measured suct. press.: ≈ 0.25 kgf/cm² g (3.6 psig) • Full cavitation, NPSH margin < 0
  • 73. UPGRADE RESULTS RELIABILITY IMPROVEMENT – END 2002 10 10 MAIN PUMP “A” 9 9 PC-752B PC-752B UPGRADE "A" UPGRADE "A" 8 8 PC-752A PC-752A Fully upgraded 7 7 6 No failures 6 5 5 4 4 STAND-BY PUMP “B” 3 3 2 Partially upgraded 2 1 1 Failures at brgs & 0 0 seal only 1995 1995 1996 1996 1997 1997 1998 1999 1998 1999 2000 2000 2001 2001 2002 2002 Projected savings over 10 years: US$ 900 K FAILURE HISTORY BEFORE AND AFTER THE UPGRADE
  • 74. CONCLUSIONS Pump upgrade objectives were successfully achieved. Upgrade of existing pump was the best choice for a cost-effective solution. In-house engineering allowed a custom design with some features exceeding current mfr. specs. Impeller revised configuration is not an optimum solution, but provided a remarkable service life improvement. Detected design deficiencies played an important role on low reliability, but not on catastrophic failures.
  • 75. LESSONS LEARNED In general, improvement of existing equipment represents lower investment and lead time. Check your equipment for upgrade opportunities, specially if they exhibit low reliability.
  • 76. REFERENCES RELIABILITY IMPROVEMENT OF END SUCTION PUMP IN SEVERE SERVICE THRU ENGINEERED COMPONENT UPGRADE Mc. Caul, Colin. An Advanced Cavitation Resistant Austenitic Steel for Pumps. Corrosion 96, The NACE International Annual Conference and Exposition. Paper Nº 415, 1996. Bloch, Heinz P. Improving Machinery Reliability. 2nd Edition. 1988. Gulf Publishing Company Bloch, Heinz P. Pump Reliability Improvement Program. Pump Failure Reduction Programs. PRIME Seminar notes J.F. Gülich. Selection criteria for suction impellers of centrifugal pumps. Part 1: The suction specific speed – a criterion for flow recirculation and pump reliability ?, Sulzer Pumps Ltd, PO Box, CH-8400 Winterthur, Switzerland. Summers-Smith, J.D. A Tribology Casebook. P.83. Mechanical Engineering Publications London and Bury St. Edmunds, 1997. Pfleiderer, Carl. Bombas Centrífugas y Turbocompresores. Editorial Labor, 1960.
  • 77. ® 20th International Pump Users Symposium March 17-20, 2003. Houston, Texas THANK YOU !