Project Charter
Our goals are to take an existing database center, and
move/upgrade it to a newer building. We are trying to
get bigger because we regrew out of our original size.
We want to use better equipment so we can get a
bigger customer base. This is part of a larger project.
Estimated Budget
Estimated Labor $0
Estimated Materials $10,000
Estimated Contractors $0
Estimated Equipment and Facilities $75,000
Estimated Travel $1,000
Total Estimated Cost $86,000
Business Needs
• We are doing this project due to our customer’s
demand for server space and an option of playing a
variety of games on our platforms.
• The upgrade will add new servers capable of hosting
multiple gaming servers at once.
• This will be a financial gain for the owner as well as a
better gaming experience for the owner.
• Word of mouth promotion will help the revenue for
the owner as well.
• This will be a financial gain for the owner as well as a
better gaming experience for the owner.
Milestones
• We are acquiring the building first, on 11/6/2015.
• We will spec out and order equipment on 11/9/2015 and on
11/9/2015 we are setting up a date for our metro Ethernet.
• we are getting the equipment needed on 11/13/2015.
• We start wiring up the servers on 11/14/2015 and we are getting
the installation of metro Ethernet.
• On 11/18/2015 we will be doing a stress test on the servers to make
sure they work well with high volume
• A beta testing invite to our customers will be on 11/20/15 to
11/22/15.
• On 11/25/15 we are doing an editing and reviewing/bug repair to
our servers.
• 12/07/2015 is the launch date of our servers.

More Related Content

Similar to final project

With Dedicated Server Hosting Experience Fast Speeds Scalability Stringent ...
With Dedicated Server Hosting  Experience Fast Speeds Scalability  Stringent ...With Dedicated Server Hosting  Experience Fast Speeds Scalability  Stringent ...
With Dedicated Server Hosting Experience Fast Speeds Scalability Stringent ...Go4hosting Web Hosting Provider
 
ASTQB washington-sept-2015
ASTQB washington-sept-2015ASTQB washington-sept-2015
ASTQB washington-sept-2015Dan Boutin
 
Case Study: A Complex SharePoint Migration
Case Study: A Complex SharePoint MigrationCase Study: A Complex SharePoint Migration
Case Study: A Complex SharePoint MigrationMatthew J. Bailey , MCT
 
Designing your API Server for mobile apps
Designing your API Server for mobile appsDesigning your API Server for mobile apps
Designing your API Server for mobile appsMugunth Kumar
 
Mark Interrante OpenStack Design Summit
Mark Interrante OpenStack Design SummitMark Interrante OpenStack Design Summit
Mark Interrante OpenStack Design SummitOpen Stack
 
Website Maintenance Service Proposal PowerPoint Presentation Slides
Website Maintenance Service Proposal PowerPoint Presentation SlidesWebsite Maintenance Service Proposal PowerPoint Presentation Slides
Website Maintenance Service Proposal PowerPoint Presentation SlidesSlideTeam
 
Nick-Walter-HOB_Migrating_Dinosaurs.pptx
Nick-Walter-HOB_Migrating_Dinosaurs.pptxNick-Walter-HOB_Migrating_Dinosaurs.pptx
Nick-Walter-HOB_Migrating_Dinosaurs.pptxAWS Chicago
 
Website hosting
Website hostingWebsite hosting
Website hostingaustintim
 
Online Store Website Design Proposal PowerPoint Presentation Slides
Online Store Website Design Proposal PowerPoint Presentation SlidesOnline Store Website Design Proposal PowerPoint Presentation Slides
Online Store Website Design Proposal PowerPoint Presentation SlidesSlideTeam
 
Assigment 2
Assigment 2Assigment 2
Assigment 2Umut5552
 
Geek Guide - Shared Hosting
Geek Guide - Shared HostingGeek Guide - Shared Hosting
Geek Guide - Shared Hostingwebhostingguy
 
The Fabric of the Future
The Fabric of the FutureThe Fabric of the Future
The Fabric of the FutureUniFabric
 
DevOpsDays Galway 2017 - Skypilot Project
DevOpsDays Galway 2017 - Skypilot ProjectDevOpsDays Galway 2017 - Skypilot Project
DevOpsDays Galway 2017 - Skypilot ProjectThomas Shaw
 
Continued Accomplishments during this position
Continued Accomplishments during this positionContinued Accomplishments during this position
Continued Accomplishments during this positionSandra Abadir
 
Simply Business - Near Real Time Event Processing
Simply Business - Near Real Time Event ProcessingSimply Business - Near Real Time Event Processing
Simply Business - Near Real Time Event Processingidan_by
 
Auckland SQLSaturday 2018 - Building a Modern Analytics Solution in the cloud...
Auckland SQLSaturday 2018 - Building a Modern Analytics Solution in the cloud...Auckland SQLSaturday 2018 - Building a Modern Analytics Solution in the cloud...
Auckland SQLSaturday 2018 - Building a Modern Analytics Solution in the cloud...Sergio Zenatti Filho
 

Similar to final project (20)

Sanjeev_Resume
Sanjeev_ResumeSanjeev_Resume
Sanjeev_Resume
 
With Dedicated Server Hosting Experience Fast Speeds Scalability Stringent ...
With Dedicated Server Hosting  Experience Fast Speeds Scalability  Stringent ...With Dedicated Server Hosting  Experience Fast Speeds Scalability  Stringent ...
With Dedicated Server Hosting Experience Fast Speeds Scalability Stringent ...
 
ASTQB washington-sept-2015
ASTQB washington-sept-2015ASTQB washington-sept-2015
ASTQB washington-sept-2015
 
Case Study: A Complex SharePoint Migration
Case Study: A Complex SharePoint MigrationCase Study: A Complex SharePoint Migration
Case Study: A Complex SharePoint Migration
 
Designing your API Server for mobile apps
Designing your API Server for mobile appsDesigning your API Server for mobile apps
Designing your API Server for mobile apps
 
Mark Interrante OpenStack Design Summit
Mark Interrante OpenStack Design SummitMark Interrante OpenStack Design Summit
Mark Interrante OpenStack Design Summit
 
Website Maintenance Service Proposal PowerPoint Presentation Slides
Website Maintenance Service Proposal PowerPoint Presentation SlidesWebsite Maintenance Service Proposal PowerPoint Presentation Slides
Website Maintenance Service Proposal PowerPoint Presentation Slides
 
Nick-Walter-HOB_Migrating_Dinosaurs.pptx
Nick-Walter-HOB_Migrating_Dinosaurs.pptxNick-Walter-HOB_Migrating_Dinosaurs.pptx
Nick-Walter-HOB_Migrating_Dinosaurs.pptx
 
MySQL@king
MySQL@kingMySQL@king
MySQL@king
 
IPaaS
IPaaSIPaaS
IPaaS
 
Website hosting
Website hostingWebsite hosting
Website hosting
 
Online Store Website Design Proposal PowerPoint Presentation Slides
Online Store Website Design Proposal PowerPoint Presentation SlidesOnline Store Website Design Proposal PowerPoint Presentation Slides
Online Store Website Design Proposal PowerPoint Presentation Slides
 
The Great move finish
The Great move finishThe Great move finish
The Great move finish
 
Assigment 2
Assigment 2Assigment 2
Assigment 2
 
Geek Guide - Shared Hosting
Geek Guide - Shared HostingGeek Guide - Shared Hosting
Geek Guide - Shared Hosting
 
The Fabric of the Future
The Fabric of the FutureThe Fabric of the Future
The Fabric of the Future
 
DevOpsDays Galway 2017 - Skypilot Project
DevOpsDays Galway 2017 - Skypilot ProjectDevOpsDays Galway 2017 - Skypilot Project
DevOpsDays Galway 2017 - Skypilot Project
 
Continued Accomplishments during this position
Continued Accomplishments during this positionContinued Accomplishments during this position
Continued Accomplishments during this position
 
Simply Business - Near Real Time Event Processing
Simply Business - Near Real Time Event ProcessingSimply Business - Near Real Time Event Processing
Simply Business - Near Real Time Event Processing
 
Auckland SQLSaturday 2018 - Building a Modern Analytics Solution in the cloud...
Auckland SQLSaturday 2018 - Building a Modern Analytics Solution in the cloud...Auckland SQLSaturday 2018 - Building a Modern Analytics Solution in the cloud...
Auckland SQLSaturday 2018 - Building a Modern Analytics Solution in the cloud...
 

final project

  • 1. Project Charter Our goals are to take an existing database center, and move/upgrade it to a newer building. We are trying to get bigger because we regrew out of our original size. We want to use better equipment so we can get a bigger customer base. This is part of a larger project.
  • 2. Estimated Budget Estimated Labor $0 Estimated Materials $10,000 Estimated Contractors $0 Estimated Equipment and Facilities $75,000 Estimated Travel $1,000 Total Estimated Cost $86,000
  • 3. Business Needs • We are doing this project due to our customer’s demand for server space and an option of playing a variety of games on our platforms. • The upgrade will add new servers capable of hosting multiple gaming servers at once. • This will be a financial gain for the owner as well as a better gaming experience for the owner. • Word of mouth promotion will help the revenue for the owner as well. • This will be a financial gain for the owner as well as a better gaming experience for the owner.
  • 4. Milestones • We are acquiring the building first, on 11/6/2015. • We will spec out and order equipment on 11/9/2015 and on 11/9/2015 we are setting up a date for our metro Ethernet. • we are getting the equipment needed on 11/13/2015. • We start wiring up the servers on 11/14/2015 and we are getting the installation of metro Ethernet. • On 11/18/2015 we will be doing a stress test on the servers to make sure they work well with high volume • A beta testing invite to our customers will be on 11/20/15 to 11/22/15. • On 11/25/15 we are doing an editing and reviewing/bug repair to our servers. • 12/07/2015 is the launch date of our servers.