2. Palmal Group of Industries
KM Monthly Knowledge Sharing Meeting-KSM
(Nov-21 To Jan-22)
Organized by:
Central-IE
Manufacturing Audit & Central Costing
1-1
3. Objectives of the Meeting:
1-2
To review factory last month performance
To understand our present position against
management expectation
To know about the scope of improvement
To set next month performance target
4. Key Discussion points:
1-3
1. Planning, Production & IE KPI:
Monthly Target Vs. achievement status
Monthly Efficiency %
Monthly PCD Hit rate status
Monthly NPT Analysis
Monthly Revenue status
Monthly Profit/Loss status
Monthly Machine utilization %
Operators Skill Matrix Analysis
Monthly Short/excess shipment status
3. Quality Assurance Department KPI:
Monthly Final inspection pass status
Monthly OQL% status
Monthly DHU% status
Monthly Top 5 Defects analysis
Fail report analysis against Top 5 Defect
2. Human Resource Department KPI:
Monthly worker absenteeism status
4. Set next month performance target
35. Factors influencing on efficiency %:
1-34
1. Style Analysis : Allocating the styles in such a way that
maximum line days can be achieved.
2. PCD hit Rate : Ensure PCD to ensure right style line feeding at
right time.
3. Set a standard Target : Target has to be as per feasibility
learning curve to get expected efficiency.
4. Production Monitoring : Ensure process wise production which
leads to target achievement of full line.
5. Line Balancing : Set right person at right place to get maximum
utilization of manpower and get output.
6. Operators Skill Matrix : Identify the right person as per process
& requirement.
7. Operators Availability : Reduction of absenteeism to ensure
operators availability as per requirement.
39. Meeting Agenda
• DHU% for the month of December
• Top 3 Defects: Root cause analysis and Action taken.
• Weekly Final Inspection Pass/Fail summary report.
• FRI Fail report submit for review.
• OQL summary report.
• CHO Quality Organogram.
• Factory Quality Organogram.
• GPQ Activities and the best way to detecting fabric defects at the initial
stage.
40. DHU DATA- JANUARY
Total Check 688049
QC Pass 638556
Alter 34614
AVG DHU % 5.03%
Uncut Thread 4294 pcs 12.4%
Broken Stitch 3544 pcs 10.2%
Point up-down 2762 pcs 8.9%
QC Pass Alter AVG DHU %
638556
34614 5.03%
Total Check Qty-688049
41. TOP 3 DEFECTS FOR THE MONTH OF JAN-22
•UNCUT THREAD
•BROKEN STITCH
•POINT UP-DOWN
43. Root cause & Action plan of Uncut thread
Root Cause Action Plan
• Operator didn’t clean his own process
threads properly.
• Should be operator trained and alert to
do proper trimming on own process.
Identified non perform operator and
make them understand the impotency.
• Used Manual Sewing Machine without
auto trimmer.
• Auto trimmer machine should be proper
utilized.
• Improper trained helper • Trained helper to proper trimming and
give a proper guideline with.
• No available compressor line with O/L
machine.
• Should be Set all compressor line with O/L
machine.
• Lack of attention. • Should be monitor each process and bring
attention relevant operator or helper to avoid
thread ends.
44. Root cause & Action plan of Broken stitch
Root Cause Action Plan
Lack of proper training of operator. Trained up operator for proper machine
controlling.
Poor Overlaping stitch. Should be carefully when given Overlaping
stitch.
Don’t use proper thread trimming method. Trained for proper trimming.
Poor thread quality. Should be check thread quality strength
before production according fabric base.
45. Root cause & Action plan of Point up-down
Root Cause Action Plan
Lack of Proper machine adjustment. Machine RPM adjusted properly as per IE target
and machine feed dog set base on operation to
avoid the misplacement as well as improve the
operator handling.
Operator Handling Problem Should be improve Operator handling.
52. Fabric GPQ Activities:
• Receiving Fabric booking sheet from the fabric audit/merchant team.
• Fabric quality follow-up at fabric mills (dyeing/finishing).
• From each color /combo (1st lot fabric/rib/collar/cuff) approval will be
provided by the concern merchandiser. Rest of the lots approval will be
done by fabric GPQ.
• GSM record (100% rolls) should be made by the fabric mill in front of fabric
GPQ.
• Fabric test report should be carried out from the fabric mill’s lab for each
lot.
• 4.0 Fabric inspection report should be carried out 20% rolls from each lot.
• Fabric check and test related all docs should be submitted to the cutting
units through the mail.