The newsletter provides construction updates for blocks A through D. For block A, roofing is completed through the 12th floor and brickwork is finished through the 6th floor. Block B's roofing is done through the 12th floor and brickwork through the 6th floor. Roofing for block C goes through the 6th floor while brickwork is through the 5th floor. Roofing on block D reaches the 5th floor and brickwork the 2nd floor. The model flat is now open for viewing.