SlideShare a Scribd company logo
1 of 43
KEL224
MARK JEFFERY AND JOSEPH F. NORTON
Ariba Implementation at MED-X:
Managing Earned Value
Chris, what do you mean, we can’t deploy the system on time?
It’s a month before the
end of the project and now you’re telling me that we may not
deploy on time! Do you
know what this means? Don’t you understand what the
implications are? I don’t
understand what went wrong. This entire time I have been
reviewing the budget variance
and combined earned value reports and everything appeared to
be fine. How am I going
to explain this to the steering committee? I want to know what
went wrong with the
project and how you are going to fix it!
Terry Baker, CIO of MED-X Inc., a Fortune 500 pharmaceutical
company, was furious. The
e-procurement implementation she had been sponsoring was not
going according to plan and the
project manager had very few answers for her.
Christopher Martin, a consultant from Implementation
Technologies, was the project
manager for the $2 million Ariba e-procurement implementation
at MED-X Inc. This was
Martin’s first time managing a full-life-cycle e-procurement
implementation and he was having
problems figuring out what was delaying the project. He had
been aware of some potentially
troublesome events early in the project, but had not been
comfortable reporting them to his client.
Martin was very bright, had a great deal of technical
development experience, and knew
Ariba functionality well. He was just completing his MBA in
the manager’s program at the
Kellogg School of Management, and was looking forward to a
big raise when this project was
over. However, Martin knew very little about earned value and
had never seen it used in project
analysis before. His client Terry Baker was demanding answers
and Martin had to figure out what
was going wrong.
The Ariba implementation was broken up into several phases.
However, the critical path went
through two major components of the project: technical
infrastructure setup and software
customization. Looking at the project plan alone, Martin could
not figure out which component
was causing the delay.
MED-X Inc.
MED-X Inc. was a global pharmaceutical company
headquartered in Houston, Texas, with
fifty-four plants and more than 40,000 employees worldwide.
Founded by a genetic engineering
©2006 by the Kellogg School of Management, Northwestern
University. This case was prepared by Alex Gershbeyn ’03 and
Derek
Yung ’03 in collaboration with Joseph F. Norton, PMP, Senior
Fellow, Center for Research on Technology and Innovation,
Kellogg
School of Management, and Principal, SOCHIN Consulting
Group, under the supervision of Professor Mark Jeffery. Some
facts
within the case have been altered for confidentiality reasons.
Cases are developed solely as the basis for class discussion.
Cases are not
intended to serve as endorsements, sources of primary data, or
illustrations of effective or ineffective management. To order
copies or
request permission to reproduce materials, call 800-545-7685
(or 617-783-7600 outside the United States or Canada) or e-mail
[email protected] No part of this publication may be
reproduced, stored in a retrieval system, used in a spreadsheet,
or
transmitted in any form or by any means—electronic,
mechanical, photocopying, recording, or otherwise—without the
permission of
the Kellogg School of Management.
This document is authorized for use only by Lava Qurbani in
QSO-420-H5657 Integrated Cost/Sched Control 21EW5 at
Southern New Hampshire University, 2021.
ARIBA IMPLEMENTATION AT MED-X KEL224
scientist in 1972, MED-X had been growing rapidly ever since.
In 1985 MED-X’s research and
development team developed a blockbuster drug to treat skin
cancer. In addition to drug
development, MED-X established alliances with other
pharmaceutical companies whose drugs it
licensed and sold through retailers of over-the-counter
medication.
One of MED-X’s key strategic objectives was to transform its
procurement organization into
a decentralized purchasing model with a self-service
philosophy. MED-X was spending $3 billion
annually on indirect goods and services. Of this amount, $2
billion was sourceable and $1 billion
was spent on technology. MED-X estimated that a decentralized
procurement model would help
it save $200 million annually. By moving all its preferred
suppliers onto the Ariba e-procurement
platform, MED-X would reduce maverick spending, streamline
the procurement process, and
expedite user adoption.
In addition, MED-X would realize many other benefits from
implementing the Ariba Buyer
solution. The solution would encourage nationwide compliance
with negotiated agreements,
maximize the purchasing power of the organization, and reduce
processing costs and cycle times.
In addition, it would track purchasing behavior and retrieve
historical information, allowing
nonpurchasing employees to focus on mission-related
responsibilities. As a result of the
implementation, MED-X would realize a significant return on
investment.
Implementation Technologies
Headquartered in Chicago with branch offices in New York,
Dallas, Miami, and Seattle,
Implementation Technologies had more than five hundred
employees. Founded in 1995 by three
ex-“Big Five” partners, the organization had hired only the best
and brightest. The average
consultant had at least five years of experience in information
technology consulting, business
analysis, and project management.
Implementation Technologies’s mission was to be the premier
provider of global business-to-
business (B2B) e-commerce consulting services. It offered a full
range of consulting services,
including Ariba B2B commerce platform implementation,
supplier integration, and Ariba training
and support. Revenues for 2001 were expected to reach $80
million.
Implementation Technologies was the fastest-growing
organization in the dynamic
technology services sector and successfully competed with the
likes of Accenture and PWC. In
fact, MED-X had chosen Implementation Technologies over
Accenture because it had
successfully implemented Ariba for more than thirty clients,
five of which were other
pharmaceutical companies.
Implementation Technologies currently had other initiatives
underway and wanted to partner
with other enterprise resource planning (ERP) companies, such
as PeopleSoft and SAP, to
provide the best implementations for its worldwide
organization.
Ariba Inc.
Ariba (www.ariba.com) offered a powerful suite of e-
procurement solutions to help
companies manage spending so that expenses fell faster than
revenues in down times and grew
2 KELLOGG SCHOOL OF MANAGEMENT
This document is authorized for use only by Lava Qurbani in
QSO-420-H5657 Integrated Cost/Sched Control 21EW5 at
Southern New Hampshire University, 2021.
KEL224 ARIBA IMPLEMENTATION AT MED-X
more slowly than revenues in up times. The Ariba spend
management solution was designed to
significantly improve bottom-line results.
Since its founding in 1996, Ariba had remained at the forefront
of the Internet revolution,
providing easy-to-implement, robust online commerce solutions
for proven cost savings and
returns on investment. In 2002 Ariba led the enterprise spend
management (ESM) market. ESM
was a new class of solutions that focused on delivering a close d
loop of control and leverage over
a company’s spending. This included assessing spending
activities, conducting effective sourcing,
and capturing and reconciling spending enterprise-wide. The
Ariba spend management solution
delivered results quickly while providing a sustainable spend
management capability.
In 2001 a seasoned management team directed Ariba’s fast-
paced growth. Together, the team
had significant management experience in high-growth
organizations and the combined
experience of seven successful startups. The team members had
held senior management
positions at Digital Equipment Corporation, General Motors,
IBM, Lotus Corporation, NeXT
Computers, Parametric Technology Corporation, Rasna
Corporation, and SAP.
As the leading provider of spend management solutions and
services to leading companies
around the world—including forty of the Fortune 100—Ariba
brought companies together in
entirely new ways through powerful, easy-to-use Web
technologies that transparently overcame
differences in applications and business processes.
In 2002 Ariba products and solutions were enabling global
industry leaders, including Cisco
Systems, Chevron, Hewlett-Packard, Canadian Imperial Bank of
Commerce, and Phillips NV, to
save money, discover new revenue streams, and increase their
competitive advantage.
Business Case and Technology
E-procurement means obtaining or purchasing commodities and
services via the Internet. It
involves the use of an electronic catalog of items, automated
requisitioning, and an automated
approval process.
The Ariba network-centric approach to e-procurement and value
chain management linked
customers, suppliers, partners, and distribution channels on a
common platform for fast return on
investment and rapid cost savings. Value chain management
(VCM) enabled companies to
connect seamlessly to trading partners for all their inter -
enterprise commerce processes—from
analysis and planning to fulfillment and payment. Ariba
provided its customers with powerful
VCM solutions: Web-based applications that ran on a shared
technology platform, facilitating
inter-enterprise transactions over the Ariba Commerce Services
Network (Ariba CSN, Ariba’s
scalable B2B network).
The Ariba CSN provided a shared flexible infrastructure that
connected multiple enterprises
in an interactive community. Companies could use third-party
services to transact in real time
with buyers, partners, distribution channels, and more than
20,000 suppliers worldwide through a
single connection. Network-enabling the value chain allowed
companies to drive cost savings
through lower negotiated prices, employee and contract
compliance, reduced inventories, and
greater process efficiency.
KELLOGG SCHOOL OF MANAGEMENT 3
This document is authorized for use only by Lava Qurbani in
QSO-420-H5657 Integrated Cost/Sched Control 21EW5 at
Southern New Hampshire University, 2021.
ARIBA IMPLEMENTATION AT MED-X KEL224
The Ariba CSN provided a secure infrastructure of connectivity,
transaction management,
supplier enablement, and commerce services, and the Ariba
platform facilitated integration with
back-end systems. The platform and network worked together
with Ariba’s VCM applications for
core B2B commerce processes, from sourcing to payment.
See Exhibit 1 and Exhibit 2 for an overview of the Ariba Buyer
platform configuration and
the Ariba development environment, respectively.
Proposed Approach and Plan
The partnership between MED-X and Implementation
Technologies was designed to leverage
industry, business process, IT, and experience implementing the
Ariba Buyer solution. The
implementation methodology was modeled in accordance with
the AribaLive Methodology to
formulate a “best-of-breed” approach tailored to meet MED-X’s
project requirements.
A phased approach was taken to ensure project delivery by
October 1, 2001. This approach
would drive efficient, effective use of resources, promote reuse
of solutions across divisions, and
enable transfer of knowledge to MED-X in order to complete
the full deployment and supplier
enablement.
The original project timeline was as follows:
Approximate project start date: May 1, 2001
Conference room pilot (CRP): June 25, 2001
Live date: October 1, 2001
User groups: Home office (about 250 users)
Possible Suppliers: Boise Cascade, Corporate Express,
Grainger,
Fisher Scientific
Technical integration: ERP system—JDE
The original project timeline is shown schematically in Exhibit
3. The CRP had gone as
planned, but by September 1 it was clear the system was not
going to go live on October 1.
Project Management
Successful projects require a set of project management
processes in conjunction with project
development activities. These processes and activities should be
organized to provide a complete
set of tasks for starting the project, employing an iterative set of
tasks for managing the ongoing
work effort, and closing the project. The activities and
associated tasks within the management
processes are both linear and iterative in nature. They can be
performed on an as-needed basis
(daily, weekly, monthly), or they can be triggered by events and
run continually for a specific
period of time.
4 KELLOGG SCHOOL OF MANAGEMENT
This document is authorized for use only by Lava Qurbani in
QSO-420-H5657 Integrated Cost/Sched Control 21EW5 at
Southern New Hampshire University, 2021.
KEL224 ARIBA IMPLEMENTATION AT MED-X
An ideal project management approach for an Ariba
implementation promoted tight
integration of the business transformation and organizational
change. In addition, the
organizational issues had to be coordinated with the Ariba
configuration and IT infrastructure
aspects of the project and the associated parties conducting
these activities.
For a successful project, the project management team had to
foster effective communication
among project team members and between project teams, and
manage and track multiple projects
from an executive perspective. The team also had to manage
“scope creep” to meet stated project
goals and objectives and provide for faster and more effective
project decisions.
The project management team also needed to provide enhanced
focus on project issues/risks
and recommended actions, establish documentation standards
regarding quality and consistency,
manage workflow regarding review and approval of project
deliverables and work products, and
provide for better utilization of scarce project resources.
Finally, it had to provide for effective
knowledge transfer between consulting and client project teams,
provide a basis for an end-user
help desk, and ensure that the client was completely satisfied.
Project Plan
Implementation Technologies designed the plan, outlined below,
to roll out Ariba Buyer 7.0
to 250 users in MED-X’s home office. A thorough gap analysis
was conducted prior to the start
of the project that compared delivered Ariba functionality with
the “to be” process and identified
the differences for review. This analysis enabled
Implementation Technologies to understa nd the
gaps between MED-X’s current procurement system and an
ideal e-procurement solution.
The gap analysis team uncovered and documented the detailed
steps necessary to implement
the appropriate change management initiatives and effectively
roll out Ariba Buyer. The first
project phase culminated in a CRP in which MED-X was able to
see and test Ariba functionality
for the first time. Baker and other MED-X senior managers were
enthusiastic about the successful
pilot test.
Project Objectives
One of the early objectives was to design and configure the
initial Ariba solution that would
serve as both a “proof of concept” and learning tool to aid in the
establishment of an enterprise-
wide e-procurement solution and support structure. The CRP
was an integral component of the
production project as a first test of the solution.
Another objective was to provide MED-X with a low-risk and
controlled entrée into
leveraging Ariba e-procurement technology and evolving best
practices and to allow personnel to
start developing functional and technical expertise in the Ariba
Buyer application set.
In addition, Information Technologies aimed to further define
the requirements for elements
of scope not met by Ariba “out-of-the-box” functionality and
develop a strategy for developing
the associated solution. This required defining a holistic and
long-term integration strategy for
Ariba and MED-X’s enterprise systems. The ultimate goal
targeted for after October 1 was to roll
out the common baseline solution across the home office for
approximately 250 people.
KELLOGG SCHOOL OF MANAGEMENT 5
This document is authorized for use only by Lava Qurbani in
QSO-420-H5657 Integrated Cost/Sched Control 21EW5 at
Southern New Hampshire University, 2021.
ARIBA IMPLEMENTATION AT MED-X KEL224
Project Organization
Exhibit 4 details the resources and roles required from MED-X
and Implementation
Technologies to successfully staff the project. Implementation
Technologies estimated a six-
month timeline to successfull y deliver the customized MED-X
Ariba system.
MED-X provided eight individuals to staff the project. Some of
them assisted on an as-
needed basis. A MED-X project manager worked with
Christopher Martin to help manage issues
for the MED-X team. Most of the individuals provided by MED-
X were procurement specialists
who were responsible for working with the Implementation
Technologies team to ensure Ariba
worked as intended and to deploy the system to other business
users.
Implementation Technologies provided seven individuals to
staff the project. A project
quality advisor was staffed part-time to provide quality
management guidance throughout the
project. Martin was responsible for overall project management
and leadership. He was supported
by the technical, functional, and supplier leads.
The functional lead was primarily responsible for gathering
business requirements. The
technical lead was responsible for transforming MED-X
business requirements into Ariba Buyer
customizations. The supplier integration expert was responsible
for working with the Ariba Buyer
team and the suppliers that MED-X enabled. Finally, additional
technical staff were to assist with
specific customizations, such as writing business rules and
interface modifications.
Project Scope
From the following high-level scope activities, project tasks
were developed to support the
delivery and execution of the final Ariba e-procurement system
for MED-X.
Ariba Buyer 7.0 Configuration/Installation. Install and
configure server hardware, install third-
party software (e.g., Web server), and install four initial
instances of Ariba 7.0 (demo, test, CRP,
and development).
Business Process Design/Redesign. Validate “as is” and develop
“to be” requisition-to-check and
sourcing processes. Develop gap analysis to flag functional
requirements not addressed by Ariba.
Document end-to-end receiving requirements and commodity
code strategy and mapping.
Integration of Ariba Buyer 7.0 via TIBCO to MQ Series.
Implement needed push-and-pull
adapters.
Catalog Content On-Boarding. Implement four supplier
catalogs, configure catalog hierarchy to
support catalogs implemented, and adapt UN/Standard Products
and Services Code (UNSPSC).
Supplier Enablement. Work with Ariba-enabled and non-Ariba-
enabled suppliers. Plan and
coordinate the supplier summit.
Business Rules. Implement Ariba approval rules as stated in the
request for proposal and analyze
business rule requirements for the project.
Object Model and User Interface Modifications. Limit user
interface (UI) modifications for the
project to those essential for capturing additional data elements
not part of the standard Ariba
6 KELLOGG SCHOOL OF MANAGEMENT
This document is authorized for use only by Lava Qurbani in
QSO-420-H5657 Integrated Cost/Sched Control 21EW5 at
Southern New Hampshire University, 2021.
KEL224 ARIBA IMPLEMENTATION AT MED-X
object model and presenting a standard format on the HTML-
based requisition screens, printouts,
and vendor direct orders.
Source Data and Adapters. Manually load control data (e.g.,
unit of measure (UOM), currency,
user hierarchy, vendor information, purchase transactions) and
assist in the designing, building,
and testing of custom interfaces to the MQ Series.
Change Management. Includes end-user communication
planning, development and execution of
custom training curriculum for pilot end-user roll-out,
assistance with developing training
materials based upon knowledge repository, and a change
management toolkit for Ariba Buyer.
Reports. Use standard reporting functionality and begin
capturing requirements for custom
reports.
Custom Functionality. Capture custom requirements in a
functional gap analysis and research
offline with Ariba to identify potential solution approaches
(e.g., workarounds, customizations, or
inclusion in upcoming versions of Ariba software) for future
implementation.
PCards, Invoices, Matching, Receiving, Payments, and
Accounting. Implement Ariba Buyer with
PCard functionality and ensure that all interfaces and process
design enable efficient requisition
to payment processing.
System Testing
System testing plans were developed to validate that the system
architecture and software
associated with Ariba Buyer met MED-X’s requirements. The
system had to meet or exceed the
performance, reliability, maintainability, and availability
expectations of MED-X. The specific
scope of system testing was as follows:
• Database server processes
• Web server processes
• Server connection processes
• Client connection processes
• Middleware client module
• Middleware server module
• Workstation processes
• Client data entry modules
• Client printing services
• Interface processes
• Accounting data load
• Human resources data load
• General ledger (GL) data load
KELLOGG SCHOOL OF MANAGEMENT 7
This document is authorized for use only by Lava Qurbani in
QSO-420-H5657 Integrated Cost/Sched Control 21EW5 at
Southern New Hampshire University, 2021.
ARIBA IMPLEMENTATION AT MED-X KEL224
Technical Infrastructure
A schematic of the development environment for the Ariba
solution is shown in Exhibit 2. To
facilitate rapid development, no other production applications
could be running or were intended
to run on the Ariba servers.
Frequent Ariba server reboots were required during installation,
so no other access to these
servers could be active during the installation process.
Consultants needed full access
(console/physical) to the Ariba servers during installation. Full
administrative rights were given
to the consultants during the installation process and were
ongoing for development and test
environments (but not production).
System administrators were available for on-call support during
the installation of all
instances. Prerequisite database software, personal computer
hardware and software, server
hardware and software, and intranet proxy and e-mail
infrastructure had been installed,
configured, and tested prior to installation of all Ariba modules.
All necessary hardware and
software for the Ariba Buyer e-procurement solution were
installed prior to the project kickoff,
and the workspace was prepared and designated for the team.
Data Cleansing
For the completed project, Information Technologies required
MED-X to cleanse all source
data required to support the Ariba system. In addition, the
generation of all associated data
conversion files had to be completed by MED-X.
The original contract specifically stated:
Managing and performing all data extracts required from host
systems and the
modifications to host systems required to accept data from
Ariba will be completed by
MED-X. It is MED-X’s responsibility to work with Ariba for
any and all issues, should
they arise, relating to the integrity of Ariba software and
patches. MED-X will provide
project personnel with knowledge of company labs’
environment to fulfill the functional
roles and responsibilities. MED-X will provide the project team
with all documentation
relating to any process reengineering and strategic sourcing
initiatives.
So far in the project, MED-X had lived up to the contract and
had delivered on schedule.
Critical Success Factors
Critical success factors for this project included a plan for
organizational change
effectiveness, quick resolution for business decisions affecting
policy, and establishment of
clearly defined project objectives, since exact definitions of
project scope were key to keeping the
project on time and within budget. It was also important to
establish concise measures of success
and support with strong executive sponsorship so that
interdepartmental issues were addressed in
an efficient manner.
Other critical success factors included understanding MED-X’s
B2B strategy, understanding
current B2B projects underway, and determining methods of
leveraging the results (collaborate
rather than duplicate). Another important issue was to identify
and assign key individuals to assist
8 KELLOGG SCHOOL OF MANAGEMENT
This document is authorized for use only by Lava Qurbani in
QSO-420-H5657 Integrated Cost/Sched Control 21EW5 at
Southern New Hampshire University, 2021.
KEL224 ARIBA IMPLEMENTATION AT MED-X
in understanding current legacy systems and review and
challenge complex business processes to
reduce development and maintenance efforts. In addition, it was
important to identify and allocate
key resources that kept the project on schedule, since key
personnel losses could significantly
affect the delivery schedule.
It was also important to identify current ERP system and
process weaknesses, since staged
multiple development environments were crucial to support the
ability to implement changes
without disrupting other aspects of the project. For project
success, it was critical to use software
version control; this is essential in a distributed development
environment. Finally, the
management team had to build early consensus across the user
base and establish points of
escalation or parameters to keep the team on track and working
together.
Project Status to Date
After the meeting with Baker, Martin returned to his office.
“Wow, Terry was really upset,”
he thought. He knew he was on shaky ground, although his gut
told him the project was not
totally out of control.
The MED-X implementation had been running rather smoothly
to date, but some events had
impacted it. For instance, very early in the project, a part-time
MED-X staffer had been
repeatedly pulled off the project for other duties. At the end of
June, immediately after the
successful CRP, there was a slight delay as the Sun server
equipment showed up late. In July,
system testing of the development of legacy data interfaces was
scheduled late. In the testing,
Martin’s team uncovered several things that were not working
as designed. These events all
contributed to delaying unit testing and holding up the Ariba
integration with the PeopleSoft
purchasing module.
Martin studied the Microsoft Project Gantt chart on his
computer screen, but could not tell
exactly which component of the project was responsible for the
delay. Maybe Baker had a good
idea: check the earned value. Martin sent an e-mail to the
project staff to obtain the necessary
information.
The data Martin’s staff provided is given in Exhibit 5–Exhibit
7, and Exhibit 8 is the
standard Implementation Technologies earned value analysis
template. Martin was not exactly
sure what to do with the data now that he had it, but he figured
this was a good start.
KELLOGG SCHOOL OF MANAGEMENT 9
This document is authorized for use only by Lava Qurbani in
QSO-420-H5657 Integrated Cost/Sched Control 21EW5 at
Southern New Hampshire University, 2021.
ARIBA IMPLEMENTATION AT MED-X KEL224
Exhibit 1: Ariba Buyer Configuration
ERP 1
HRMS
ERP 2 Ariba Buyer
Commerce Services Network
Internet
End-User Buyers
The diagram above illustrates the Ariba Buyer configuration.
The Ariba B2B platform did the
following:
• Provided an infrastructure for e-commerce
• Provided an open, standards-based Internet service that
allowed Ariba Buyer to connect
buyers and sellers worldwide
• Simplified and streamlined order routing and catalog
management
• Promoted rapid supplier integration
• Enabled e-commerce technology such as Punchout and cXML
10 KELLOGG SCHOOL OF MANAGEMENT
This document is authorized for use only by Lava Qurbani in
QSO-420-H5657 Integrated Cost/Sched Control 21EW5 at
Southern New Hampshire University, 2021.
KEL224 ARIBA IMPLEMENTATION AT MED-X
Exhibit 2: Ariba Buyer Development Environment
De
velopment Instance
De lopment Instanceve
De lopment Instanceve
Test Instance
Ariba Buyer
Production System
Ongoing Development
C nges, Unit Test, and
Debug
Integration Test and
Debug
Final Test and
Debug
Final
Promotion
ha
This diagram illustrates a high-level approach to development.
Ariba recommended creating
three types of instances: development, test, and production (the
production instance was the Ariba
Buyer production system). Changes could be made first in
development instances and then
merged into a test instance, and finally moved into the Ariba
Buyer production system, although
these activities often took place concurrently.
Exhibit 3: Project Timeline
This chart outlines the project timeline for MED-X’s Ariba
implementation. The project
began in May and the go-live date was October 1, 2001. The
CRP was scheduled for June 25.
This was the first time that the Ariba e-procurement system,
customized for MED-X, was
functionally demonstrated.
May June July Aug Sep
October
Go-Live
Plan
CRP
Build
Deploy
Evolve
KELLOGG SCHOOL OF MANAGEMENT 11
This document is authorized for use only by Lava Qurbani in
QSO-420-H5657 Integrated Cost/Sched Control 21EW5 at
Southern New Hampshire University, 2021.
ARIBA IMPLEMENTATION AT MED-X KEL224
Exhibit 4: Project Organization
( A ) M E D - X R E S O U R C E R E Q U I R E M E N T S
MED-X would provide the appropriate resources with the
requisite level of commitment. The table below specifies the
types and level of
resources needed from MED-X.
Functional Area Role Responsibilities
Full-Time
Equivalents
Procurement Procurement
professional
Provide input to project team concerning
procurement processes and procedures
1.0
Procurement Catalog manager/
supplier manager
Manage supplier processes 0.5
Procurement Training End-user training 0.5
Procurement/IT Ariba configuration/
development
Through knowledge transfer, learn the Ariba solution
set and configuration process and assume
deliverable responsibilities in subsequent phases
0.5
IT Network/system
administration
Administer Ariba servers As needed
IT Database
administration
Administer database server As needed
IT Integration expert Provide input to project team concerning
integration 1.0
Project Project manager Provide project management 1.0
( B ) C O N S U L T I N G F I R M R E S O U R C E S F O R
I M P L E M E N T A T I O N P R O J E C T
The consulting firm would need to bring the following resources
to MED-X for this implementation.
Consulting Partner Resources Responsibilities
Project advisor Available throughout project duration to
facilitate resolution of strategic issues and to
ensure that project is delivered on time and on budget.
Responsibilities include
monitoring workplan progress and quality assurance, aiding in
resolution of difficult
business issues and customer satisfaction, and maintenance of
client relationship.
Project manager Available throughout project duration to
manage implementation team and complete
project on time and on budget. Critical responsibilities include
managing customer
relationships, architecting project plan, identifying resource
requirements,
developing project infrastructure and management tools, and
providing primary
communication channel for all customer issues and feedback to
Ariba.
Functional lead Available during analysis, implementation, and
deployment phases for defining
business process requirements, business rules, and data
integration requirements.
Supplier integration expert Responsible for supplier
integration/enablement, catalog and commodity
management, and knowledge transfer to client supplier
integration analyst.
Technical lead Responsible for management of all development
and integration activities. Will also
have assigned development deliverables.
Rules/UI specialist Responsible for writing of business/approval
rules, UI/object model customizations,
Java code, and all supporting documentation.
Integration expert Responsible for configuration of delivered
integration events and development of
any custom interfaces to back-end systems.
( C ) A R I B A R E S O U R C E S F O R I M P L E M E N T
A T I O N P R O J E C T
Ariba Resource Responsibilities
Ariba GSD consultant Assist with implementation as product
expert. Also help facilitate communication
between implementation team and Ariba to resolve issues.
12 KELLOGG SCHOOL OF MANAGEMENT
This document is authorized for use only by Lava Qurbani in
QSO-420-H5657 Integrated Cost/Sched Control 21EW5 at
Southern New Hampshire University, 2021.
KEL224 ARIBA IMPLEMENTATION AT MED-X
Exhibit 5: Infrastructure and Software Customization Budgeted
Cost of Work
Scheduled
T E C H N I C A L I N F R A S T R U C T U R E P L A N
(a) The dollar amounts below represent the budgeted cost of
work scheduled (BCWS) to be done for the given time
period for the technical infrastructure component of the project
plan.
Month Dollar Amount
May $ 120,000
June $ 192,000
July $ 192,000
August $ 192,000
September $ 192,000
October $ 60,000
S O F T W A R E C U S T O M I Z A T I O N P L A N
(b) The dollar amounts below represent the budgeted cost of
work scheduled (BCWS) to be done for the given time
period for the software customization component of the project
plan.
Month Dollar Amount
May $ 120,000
June $ 192,000
July $ 192,000
August $ 192,000
September $ 192,000
October $ 60,000
Exhibit 6: Infrastructure and Software Customization Actual
Cash Burn
T E C H N I C A L I N F R A S T R U C T U R E A C T U A L
C A S H B U R N
(a) The dollar amounts below represent the actual cost of work
performed (ACWP) for the given time period for the
technical infrastructure component of the project plan.
Month Dollar Amount
May $ 120,000
June $ 215,000
July $ 192,000
August $ 216,500
September $ 170,000
S O F T W A R E C U S T O M I Z A T I O N A C T U A L C
A S H B U R N
(b) The dollar amounts below represent the actual cost of work
performed (ACWP) for the given time period for the
software customization component of the project plan.
Month Dollar Amount
May $ 119,000
June $ 187,000
July $ 165,000
August $ 189,000
September $ 186,000
KELLOGG SCHOOL OF MANAGEMENT 13
This document is authorized for use only by Lava Qurbani in
QSO-420-H5657 Integrated Cost/Sched Control 21EW5 at
Southern New Hampshire University, 2021.
ARIBA IMPLEMENTATION AT MED-X KEL224
Exhibit 7: Infrastructure and Software Customization Actual
Performance
T E C H N I C A L I N F R A S T R U C T U R E A C T U A L
P E R F O R M A N C E
(a) The dollar amounts below represent the budgeted cost of
work performed (BCWP) in the given time period for the
technical infrastructure component of the project plan.
Month Dollar Amount
May $ 120,000
June $ 170,000
July $ 173,000
August $ 190,000
September $ 185,000
S O F T W A R E C U S T O M I Z A T I O N A C T U A L P
E R F O R M A N C E
(b) The dollar amounts below represent the budgeted cost of
work performed (BCWP) in the given time period for the
software customization component of the project plan.
Month Dollar Amount
May $ 133,250
June $ 197,000
July $ 220,000
August $ 215,000
September $ 240,000
14 KELLOGG SCHOOL OF MANAGEMENT
This document is authorized for use only by Lava Qurbani in
QSO-420-H5657 Integrated Cost/Sched Control 21EW5 at
Southern New Hampshire University, 2021.
KEL224 ARIBA IMPLEMENTATION AT MED-X
Exhibit 8: Earned Value Analysis Template
The template below can be used to analyze earned value for the
MED-X Ariba
implementation. The accompanying electronic file has built-in
Excel formulas to help derive the
earned value ratios.
Software Customization Monthly Plan May Jun Jul Aug Sep
Oct
Monthly status Plan BCWS
Actual burn ACWP
Actual perform BCWP
Rolling status Plan BCWS
Actual burn ACWP
Actual perform BCWP
Rolling ratios Schedule impact SV = BCWP – BCWS
SPI = BCWP / BCWS
Cost impact CV = BCWP – ACWP
CPI = BCWP / ACWP
Control ratio CR = SPI × CPI
Technical Infrastructure May Jun Jul Aug Sep Oct
Monthly status Plan BCWS
Actual burn ACWP
Actual perform BCWP
Rolling status Plan BCWS
Actual burn ACWP
Actual perform BCWP
Rolling ratios Schedule impact SV = BCWP – BCWS
SPI = BCWP / BCWS
Cost impact CV = BCWP – ACWP
CPI = BCWP / ACWP
Control ratio CR = SPI × CPI
Combined Projects May Jun Jul Aug Sep Oct
Monthly status Plan BCWS
Actual burn ACWP
Actual perform BCWP
Rolling status Plan BCWS
Actual burn ACWP
Actual perform BCWP
Rolling ratios Schedule impact SV = BCWP – BCWS
SPI = BCWP / BCWS
Cost impact CV = BCWP – ACWP
CPI = BCWP / ACWP
Control ratio CR = SPI × CPI
KELLOGG SCHOOL OF MANAGEMENT 15
This document is authorized for use only by Lava Qurbani in
QSO-420-H5657 Integrated Cost/Sched Control 21EW5 at
Southern New Hampshire University, 2021.
MED-X Inc.Implementation TechnologiesAriba Inc.Business
Case and TechnologyProposed Approach and PlanProject
ManagementProject PlanProject ObjectivesProject
OrganizationProject ScopeSystem TestingTechnical
InfrastructureData CleansingCritical Success FactorsProject
Status to Date
2
BADM 627 Project Risk & Quality Management
Problem Set #5
Your Name
Date
Contents
Assignment Guidelines 3
Part I: Create a risk matrix in Excel 3
Identify the risks to be addressed with a rationale as to why you
have chosen these risks from the matrix? 3
Explain which of the four remediation methodologies you will
use for each risk and why? 3
Part II: 3
Define Quality? 3
What does Total Quality Management emphasize? 3
Sate the Deming philosophy. 3
What are the major steps for an organization to follow in
implementing TQM? 3
References 4
Assignment Guidelines
Overview: Over the past few decades, one of the most common
types of projects within a business is the development of a new
piece of software to facilitate a certain facet of business
operations. The assignment will entail a project concerned with
the creation of a new version of business expense software for
the entry of, tracking of, payment of business expenses accrued
by organizational members during normal business operations
as other related issues such as reimbursing employees for
expenses they personally paid for during their business-related
travel.Part I: Create a risk matrix in Excel (submit as a separate
file)
Identify the risks to be addressed with a rationale as to why you
have chosen these risks from the matrix?
Explain which of the four remediation methodologies you will
use for each risk and why?
Part II:
· Define Quality?
· What does Total Quality Management emphasize?
· State the Deming philosophy.
· What are the major steps for an organization to follow in
implementing TQM?
References
Edwards, P. J., Serra, P. V., & Edwards, M. (2019). Managing
project risks. Hoboken, NJ: Wiley-Blackwell.
Project Management Institute, A guide to the project
management body of knowledge (PMBOK® guide), Fifth
Edition, Project Management Institute Inc. 2013. [Vitalsource
version]. Retrieved from
https://online.vitalsource.com/#/books/9781935589815/cfi/0
QSO 420 Milestone Three Guidelines and Rubric
This assignment is the third step in the analysis of the company
for your final project. For this milestone, you will create a
presentation for a project manager
based on the assigned case study that reports the project’s
performance, including any current or potential deficiencies that
you have identified, as well as your
recommendations for improving project performance.
Specifically, the following critical elements must be addressed.
Use presentation notes (“speaker notes”) to articulate those
points that are not observable in the
presentation:
A. Explain the use of EVM statistics for identifying potential
project performance deficiencies.
B. Interpret the EVM statistics calculated for the project in the
case study in terms of current or potential deficiencies. Do the
statistics imply or identify any
deficiencies? If so, what are they? Be sure to support your
reasoning with research.
C. Discuss the role of EVM principles in achieving integrated
cost and schedule control. Be sure to substantiate your claims
with research.
D. Interpret the EVM statistics calculated for the project in the
case study. Do they lend themselves to the successful
integration of cost and schedule
control for this project? Be sure to cite research to justify your
position.
E. Make appropriate recommendations for improving integrated
cost and schedule control for the project in the case study. Be
sure to use research to
justify your recommendations.
Guidelines for Submission: Use Microsoft PowerPoint or a
similar presentation software to create four to five slides (not
including references slide), that will
report the project’s performance to the project manager. Be sure
to cite references using APA format.
Critical Elements Exemplary (100%) Proficient (85%) Needs
Improvement (55%) Not Evident (0%) Value
Interpretation: Use
of EVM Statistics
Meets “Proficient” criteria and
provides cogent examples to
detail the process of using EVM
to identify deficiencies
Comprehensively explains how
EVM statistics are used to
identify potential project
deficiencies
Explains how EVM statistics are
used to identify potential
project deficiencies, but with
gaps in detail
Does not explain how EVM
statistics are used to identify
potential project deficiencies
18
Interpretation:
Deficiencies
Meets “Proficient” criteria and
cites specific, relevant examples
to establish a robust context for
the interpretation
Accurately interprets EVM
statistics for the project in the
case study in terms of
deficiencies, and supports
reasoning with research
Interprets EVM statistics for the
project in the case study in
terms of deficiencies, but with
gaps in accuracy, or does not
support reasoning with research
Does not interpret EVM
statistics for the project in the
case study in terms of
deficiencies
18
Interpretation: Role
of EVM Principles
Meets “Proficient” criteria and
cites specific, relevant examples
to establish a robust context for
the discussion
Comprehensively discusses the
role of EVM principles in
achieving integrated cost and
schedule control and
substantiates claims with
research
Discusses the role of EVM
principles in achieving
integrated cost and schedule
control, but with gaps in detail,
or does not substantiate claims
with research
Does not discuss the role of
EVM principles in achieving
integrated cost and schedule
control
18
Interpretation:
Integrated Control
Meets “Proficient” criteria and
articulation is exceptionally clear
and logical
Accurately interprets EVM
statistics for the project in the
case study for the successful
integration of cost and schedule
control and justifies position
with research
Interprets EVM statistics for the
project in the case study for the
successful integration of cost
and schedule control, but with
gaps in accuracy, or does not
justify position with research
Does not interpret EVM
statistics for the project in the
case study for the successful
integration of cost and schedule
control
18
Interpretation:
Recommendations
for Improving
Meets “Proficient” criteria and
provides detailed examples of
how the recommendations will
support the improvement of
integrated cost and schedule
control
Makes appropriate
recommendations for improving
integrated cost and schedule
control for the project in the
case study and justifies
recommendations with research
Makes recommendations for
improving integrated cost and
schedule control, but
recommendations are not
appropriate, or does not justify
recommendations with research
Does not make
recommendations for improving
integrated cost and schedule
control
18
Articulation of
Response
Submission is free of errors
related to citations, grammar,
spelling, syntax, and
organization and is presented in
a professional and easy-to-read
format
Submission has no major errors
related to citations, grammar,
spelling, syntax, or organization
Submission has major errors
related to citations, grammar,
spelling, syntax, or organization
that negatively impact
readability and articulation of
main ideas
Submission has critical errors
related to citations, grammar,
spelling, syntax, or organization
that prevent understanding of
ideas
10
Earned Total 100%

More Related Content

More from MoseStaton39

(Monica)Gender rarely shapes individual experience in isolation bu
(Monica)Gender rarely shapes individual experience in isolation bu(Monica)Gender rarely shapes individual experience in isolation bu
(Monica)Gender rarely shapes individual experience in isolation bu
MoseStaton39
 
(Monica) A summary of my decision-making process starts with flipp
(Monica) A summary of my decision-making process starts with flipp(Monica) A summary of my decision-making process starts with flipp
(Monica) A summary of my decision-making process starts with flipp
MoseStaton39
 
(Note This case study is based on many actual cases. All the name
(Note This case study is based on many actual cases. All the name(Note This case study is based on many actual cases. All the name
(Note This case study is based on many actual cases. All the name
MoseStaton39
 
(Minimum 175 words)In your own words, explain class conflict the
(Minimum 175 words)In your own words, explain class conflict the(Minimum 175 words)In your own words, explain class conflict the
(Minimum 175 words)In your own words, explain class conflict the
MoseStaton39
 
(Individuals With Disabilities Act Transformation Over the Years)D
(Individuals With Disabilities Act Transformation Over the Years)D(Individuals With Disabilities Act Transformation Over the Years)D
(Individuals With Disabilities Act Transformation Over the Years)D
MoseStaton39
 
(Kaitlyn)To be very honest I know next to nothing about mythology,
(Kaitlyn)To be very honest I know next to nothing about mythology,(Kaitlyn)To be very honest I know next to nothing about mythology,
(Kaitlyn)To be very honest I know next to nothing about mythology,
MoseStaton39
 
(Harry)Dante’s Inferno is the first of the three-part epic poem, D
(Harry)Dante’s Inferno is the first of the three-part epic poem, D(Harry)Dante’s Inferno is the first of the three-part epic poem, D
(Harry)Dante’s Inferno is the first of the three-part epic poem, D
MoseStaton39
 
(Lucious)Many steps in the systems development process may cause a
(Lucious)Many steps in the systems development process may cause a(Lucious)Many steps in the systems development process may cause a
(Lucious)Many steps in the systems development process may cause a
MoseStaton39
 
(Eric)Technology always seems simple when it works and it is when
(Eric)Technology always seems simple when it works and it is when (Eric)Technology always seems simple when it works and it is when
(Eric)Technology always seems simple when it works and it is when
MoseStaton39
 
(ELI)At the time when I first had to take a sociology class in hig
(ELI)At the time when I first had to take a sociology class in hig(ELI)At the time when I first had to take a sociology class in hig
(ELI)At the time when I first had to take a sociology class in hig
MoseStaton39
 
(Click icon for citation) Theme Approaches to History
(Click icon for citation) Theme Approaches to History(Click icon for citation) Theme Approaches to History
(Click icon for citation) Theme Approaches to History
MoseStaton39
 
(Executive Summary)MedStar Health Inc, a leader in the healthc
(Executive Summary)MedStar Health Inc, a leader in the healthc(Executive Summary)MedStar Health Inc, a leader in the healthc
(Executive Summary)MedStar Health Inc, a leader in the healthc
MoseStaton39
 
(Diquan)Analog Transmission of Digital DataBefore describing the
(Diquan)Analog Transmission of Digital DataBefore describing the(Diquan)Analog Transmission of Digital DataBefore describing the
(Diquan)Analog Transmission of Digital DataBefore describing the
MoseStaton39
 
(Christopher)With packet-switched networks its services allow mult
(Christopher)With packet-switched networks its services allow mult(Christopher)With packet-switched networks its services allow mult
(Christopher)With packet-switched networks its services allow mult
MoseStaton39
 
(Chelsey)Das Bett, Katharina Grosse, 2004, Acrylic on various obje
(Chelsey)Das Bett, Katharina Grosse, 2004, Acrylic on various obje(Chelsey)Das Bett, Katharina Grosse, 2004, Acrylic on various obje
(Chelsey)Das Bett, Katharina Grosse, 2004, Acrylic on various obje
MoseStaton39
 
(1) See page 20 for a discussion of non-IFRS measures.(2
(1) See page 20 for a discussion of non-IFRS measures.(2(1) See page 20 for a discussion of non-IFRS measures.(2
(1) See page 20 for a discussion of non-IFRS measures.(2
MoseStaton39
 
(Adams) While a database may seem like the solution to all data st
(Adams) While a database may seem like the solution to all data st(Adams) While a database may seem like the solution to all data st
(Adams) While a database may seem like the solution to all data st
MoseStaton39
 
(Adam)In an example like the Odebrecht case study from the book, i
(Adam)In an example like the Odebrecht case study from the book, i(Adam)In an example like the Odebrecht case study from the book, i
(Adam)In an example like the Odebrecht case study from the book, i
MoseStaton39
 
(Alex)There are four phases of the systems development life cycle
(Alex)There are four phases of the systems development life cycle (Alex)There are four phases of the systems development life cycle
(Alex)There are four phases of the systems development life cycle
MoseStaton39
 

More from MoseStaton39 (20)

(Monica)Gender rarely shapes individual experience in isolation bu
(Monica)Gender rarely shapes individual experience in isolation bu(Monica)Gender rarely shapes individual experience in isolation bu
(Monica)Gender rarely shapes individual experience in isolation bu
 
(Monica) A summary of my decision-making process starts with flipp
(Monica) A summary of my decision-making process starts with flipp(Monica) A summary of my decision-making process starts with flipp
(Monica) A summary of my decision-making process starts with flipp
 
(Note This case study is based on many actual cases. All the name
(Note This case study is based on many actual cases. All the name(Note This case study is based on many actual cases. All the name
(Note This case study is based on many actual cases. All the name
 
(Minimum 175 words)In your own words, explain class conflict the
(Minimum 175 words)In your own words, explain class conflict the(Minimum 175 words)In your own words, explain class conflict the
(Minimum 175 words)In your own words, explain class conflict the
 
(Individuals With Disabilities Act Transformation Over the Years)D
(Individuals With Disabilities Act Transformation Over the Years)D(Individuals With Disabilities Act Transformation Over the Years)D
(Individuals With Disabilities Act Transformation Over the Years)D
 
(Kaitlyn)To be very honest I know next to nothing about mythology,
(Kaitlyn)To be very honest I know next to nothing about mythology,(Kaitlyn)To be very honest I know next to nothing about mythology,
(Kaitlyn)To be very honest I know next to nothing about mythology,
 
(Harry)Dante’s Inferno is the first of the three-part epic poem, D
(Harry)Dante’s Inferno is the first of the three-part epic poem, D(Harry)Dante’s Inferno is the first of the three-part epic poem, D
(Harry)Dante’s Inferno is the first of the three-part epic poem, D
 
(Lucious)Many steps in the systems development process may cause a
(Lucious)Many steps in the systems development process may cause a(Lucious)Many steps in the systems development process may cause a
(Lucious)Many steps in the systems development process may cause a
 
(Eric)Technology always seems simple when it works and it is when
(Eric)Technology always seems simple when it works and it is when (Eric)Technology always seems simple when it works and it is when
(Eric)Technology always seems simple when it works and it is when
 
(ELI)At the time when I first had to take a sociology class in hig
(ELI)At the time when I first had to take a sociology class in hig(ELI)At the time when I first had to take a sociology class in hig
(ELI)At the time when I first had to take a sociology class in hig
 
(Click icon for citation) Theme Approaches to History
(Click icon for citation) Theme Approaches to History(Click icon for citation) Theme Approaches to History
(Click icon for citation) Theme Approaches to History
 
(Executive Summary)MedStar Health Inc, a leader in the healthc
(Executive Summary)MedStar Health Inc, a leader in the healthc(Executive Summary)MedStar Health Inc, a leader in the healthc
(Executive Summary)MedStar Health Inc, a leader in the healthc
 
(Diquan)Analog Transmission of Digital DataBefore describing the
(Diquan)Analog Transmission of Digital DataBefore describing the(Diquan)Analog Transmission of Digital DataBefore describing the
(Diquan)Analog Transmission of Digital DataBefore describing the
 
(Christopher)With packet-switched networks its services allow mult
(Christopher)With packet-switched networks its services allow mult(Christopher)With packet-switched networks its services allow mult
(Christopher)With packet-switched networks its services allow mult
 
(Chelsey)Das Bett, Katharina Grosse, 2004, Acrylic on various obje
(Chelsey)Das Bett, Katharina Grosse, 2004, Acrylic on various obje(Chelsey)Das Bett, Katharina Grosse, 2004, Acrylic on various obje
(Chelsey)Das Bett, Katharina Grosse, 2004, Acrylic on various obje
 
(1) See page 20 for a discussion of non-IFRS measures.(2
(1) See page 20 for a discussion of non-IFRS measures.(2(1) See page 20 for a discussion of non-IFRS measures.(2
(1) See page 20 for a discussion of non-IFRS measures.(2
 
(Adams) While a database may seem like the solution to all data st
(Adams) While a database may seem like the solution to all data st(Adams) While a database may seem like the solution to all data st
(Adams) While a database may seem like the solution to all data st
 
(Adam)In an example like the Odebrecht case study from the book, i
(Adam)In an example like the Odebrecht case study from the book, i(Adam)In an example like the Odebrecht case study from the book, i
(Adam)In an example like the Odebrecht case study from the book, i
 
(Alex)There are four phases of the systems development life cycle
(Alex)There are four phases of the systems development life cycle (Alex)There are four phases of the systems development life cycle
(Alex)There are four phases of the systems development life cycle
 
(2) conditions for language and literacy developmentConditio
(2) conditions for language and literacy developmentConditio(2) conditions for language and literacy developmentConditio
(2) conditions for language and literacy developmentConditio
 

KEL224 MARK JEFFERY AND JOSEPH F. NORTON Ariba Im

  • 1. KEL224 MARK JEFFERY AND JOSEPH F. NORTON Ariba Implementation at MED-X: Managing Earned Value Chris, what do you mean, we can’t deploy the system on time? It’s a month before the end of the project and now you’re telling me that we may not deploy on time! Do you know what this means? Don’t you understand what the implications are? I don’t understand what went wrong. This entire time I have been reviewing the budget variance and combined earned value reports and everything appeared to be fine. How am I going to explain this to the steering committee? I want to know what went wrong with the project and how you are going to fix it! Terry Baker, CIO of MED-X Inc., a Fortune 500 pharmaceutical company, was furious. The e-procurement implementation she had been sponsoring was not going according to plan and the project manager had very few answers for her. Christopher Martin, a consultant from Implementation Technologies, was the project manager for the $2 million Ariba e-procurement implementation
  • 2. at MED-X Inc. This was Martin’s first time managing a full-life-cycle e-procurement implementation and he was having problems figuring out what was delaying the project. He had been aware of some potentially troublesome events early in the project, but had not been comfortable reporting them to his client. Martin was very bright, had a great deal of technical development experience, and knew Ariba functionality well. He was just completing his MBA in the manager’s program at the Kellogg School of Management, and was looking forward to a big raise when this project was over. However, Martin knew very little about earned value and had never seen it used in project analysis before. His client Terry Baker was demanding answers and Martin had to figure out what was going wrong. The Ariba implementation was broken up into several phases. However, the critical path went through two major components of the project: technical infrastructure setup and software customization. Looking at the project plan alone, Martin could not figure out which component was causing the delay. MED-X Inc. MED-X Inc. was a global pharmaceutical company headquartered in Houston, Texas, with fifty-four plants and more than 40,000 employees worldwide. Founded by a genetic engineering ©2006 by the Kellogg School of Management, Northwestern
  • 3. University. This case was prepared by Alex Gershbeyn ’03 and Derek Yung ’03 in collaboration with Joseph F. Norton, PMP, Senior Fellow, Center for Research on Technology and Innovation, Kellogg School of Management, and Principal, SOCHIN Consulting Group, under the supervision of Professor Mark Jeffery. Some facts within the case have been altered for confidentiality reasons. Cases are developed solely as the basis for class discussion. Cases are not intended to serve as endorsements, sources of primary data, or illustrations of effective or ineffective management. To order copies or request permission to reproduce materials, call 800-545-7685 (or 617-783-7600 outside the United States or Canada) or e-mail [email protected] No part of this publication may be reproduced, stored in a retrieval system, used in a spreadsheet, or transmitted in any form or by any means—electronic, mechanical, photocopying, recording, or otherwise—without the permission of the Kellogg School of Management. This document is authorized for use only by Lava Qurbani in QSO-420-H5657 Integrated Cost/Sched Control 21EW5 at Southern New Hampshire University, 2021. ARIBA IMPLEMENTATION AT MED-X KEL224 scientist in 1972, MED-X had been growing rapidly ever since. In 1985 MED-X’s research and development team developed a blockbuster drug to treat skin cancer. In addition to drug
  • 4. development, MED-X established alliances with other pharmaceutical companies whose drugs it licensed and sold through retailers of over-the-counter medication. One of MED-X’s key strategic objectives was to transform its procurement organization into a decentralized purchasing model with a self-service philosophy. MED-X was spending $3 billion annually on indirect goods and services. Of this amount, $2 billion was sourceable and $1 billion was spent on technology. MED-X estimated that a decentralized procurement model would help it save $200 million annually. By moving all its preferred suppliers onto the Ariba e-procurement platform, MED-X would reduce maverick spending, streamline the procurement process, and expedite user adoption. In addition, MED-X would realize many other benefits from implementing the Ariba Buyer solution. The solution would encourage nationwide compliance with negotiated agreements, maximize the purchasing power of the organization, and reduce processing costs and cycle times. In addition, it would track purchasing behavior and retrieve historical information, allowing nonpurchasing employees to focus on mission-related responsibilities. As a result of the implementation, MED-X would realize a significant return on investment. Implementation Technologies Headquartered in Chicago with branch offices in New York, Dallas, Miami, and Seattle,
  • 5. Implementation Technologies had more than five hundred employees. Founded in 1995 by three ex-“Big Five” partners, the organization had hired only the best and brightest. The average consultant had at least five years of experience in information technology consulting, business analysis, and project management. Implementation Technologies’s mission was to be the premier provider of global business-to- business (B2B) e-commerce consulting services. It offered a full range of consulting services, including Ariba B2B commerce platform implementation, supplier integration, and Ariba training and support. Revenues for 2001 were expected to reach $80 million. Implementation Technologies was the fastest-growing organization in the dynamic technology services sector and successfully competed with the likes of Accenture and PWC. In fact, MED-X had chosen Implementation Technologies over Accenture because it had successfully implemented Ariba for more than thirty clients, five of which were other pharmaceutical companies. Implementation Technologies currently had other initiatives underway and wanted to partner with other enterprise resource planning (ERP) companies, such as PeopleSoft and SAP, to provide the best implementations for its worldwide organization. Ariba Inc.
  • 6. Ariba (www.ariba.com) offered a powerful suite of e- procurement solutions to help companies manage spending so that expenses fell faster than revenues in down times and grew 2 KELLOGG SCHOOL OF MANAGEMENT This document is authorized for use only by Lava Qurbani in QSO-420-H5657 Integrated Cost/Sched Control 21EW5 at Southern New Hampshire University, 2021. KEL224 ARIBA IMPLEMENTATION AT MED-X more slowly than revenues in up times. The Ariba spend management solution was designed to significantly improve bottom-line results. Since its founding in 1996, Ariba had remained at the forefront of the Internet revolution, providing easy-to-implement, robust online commerce solutions for proven cost savings and returns on investment. In 2002 Ariba led the enterprise spend management (ESM) market. ESM was a new class of solutions that focused on delivering a close d loop of control and leverage over a company’s spending. This included assessing spending activities, conducting effective sourcing, and capturing and reconciling spending enterprise-wide. The Ariba spend management solution delivered results quickly while providing a sustainable spend management capability. In 2001 a seasoned management team directed Ariba’s fast- paced growth. Together, the team had significant management experience in high-growth
  • 7. organizations and the combined experience of seven successful startups. The team members had held senior management positions at Digital Equipment Corporation, General Motors, IBM, Lotus Corporation, NeXT Computers, Parametric Technology Corporation, Rasna Corporation, and SAP. As the leading provider of spend management solutions and services to leading companies around the world—including forty of the Fortune 100—Ariba brought companies together in entirely new ways through powerful, easy-to-use Web technologies that transparently overcame differences in applications and business processes. In 2002 Ariba products and solutions were enabling global industry leaders, including Cisco Systems, Chevron, Hewlett-Packard, Canadian Imperial Bank of Commerce, and Phillips NV, to save money, discover new revenue streams, and increase their competitive advantage. Business Case and Technology E-procurement means obtaining or purchasing commodities and services via the Internet. It involves the use of an electronic catalog of items, automated requisitioning, and an automated approval process. The Ariba network-centric approach to e-procurement and value chain management linked customers, suppliers, partners, and distribution channels on a common platform for fast return on investment and rapid cost savings. Value chain management
  • 8. (VCM) enabled companies to connect seamlessly to trading partners for all their inter - enterprise commerce processes—from analysis and planning to fulfillment and payment. Ariba provided its customers with powerful VCM solutions: Web-based applications that ran on a shared technology platform, facilitating inter-enterprise transactions over the Ariba Commerce Services Network (Ariba CSN, Ariba’s scalable B2B network). The Ariba CSN provided a shared flexible infrastructure that connected multiple enterprises in an interactive community. Companies could use third-party services to transact in real time with buyers, partners, distribution channels, and more than 20,000 suppliers worldwide through a single connection. Network-enabling the value chain allowed companies to drive cost savings through lower negotiated prices, employee and contract compliance, reduced inventories, and greater process efficiency. KELLOGG SCHOOL OF MANAGEMENT 3 This document is authorized for use only by Lava Qurbani in QSO-420-H5657 Integrated Cost/Sched Control 21EW5 at Southern New Hampshire University, 2021. ARIBA IMPLEMENTATION AT MED-X KEL224 The Ariba CSN provided a secure infrastructure of connectivity, transaction management, supplier enablement, and commerce services, and the Ariba platform facilitated integration with
  • 9. back-end systems. The platform and network worked together with Ariba’s VCM applications for core B2B commerce processes, from sourcing to payment. See Exhibit 1 and Exhibit 2 for an overview of the Ariba Buyer platform configuration and the Ariba development environment, respectively. Proposed Approach and Plan The partnership between MED-X and Implementation Technologies was designed to leverage industry, business process, IT, and experience implementing the Ariba Buyer solution. The implementation methodology was modeled in accordance with the AribaLive Methodology to formulate a “best-of-breed” approach tailored to meet MED-X’s project requirements. A phased approach was taken to ensure project delivery by October 1, 2001. This approach would drive efficient, effective use of resources, promote reuse of solutions across divisions, and enable transfer of knowledge to MED-X in order to complete the full deployment and supplier enablement. The original project timeline was as follows: Approximate project start date: May 1, 2001 Conference room pilot (CRP): June 25, 2001 Live date: October 1, 2001 User groups: Home office (about 250 users) Possible Suppliers: Boise Cascade, Corporate Express, Grainger,
  • 10. Fisher Scientific Technical integration: ERP system—JDE The original project timeline is shown schematically in Exhibit 3. The CRP had gone as planned, but by September 1 it was clear the system was not going to go live on October 1. Project Management Successful projects require a set of project management processes in conjunction with project development activities. These processes and activities should be organized to provide a complete set of tasks for starting the project, employing an iterative set of tasks for managing the ongoing work effort, and closing the project. The activities and associated tasks within the management processes are both linear and iterative in nature. They can be performed on an as-needed basis (daily, weekly, monthly), or they can be triggered by events and run continually for a specific period of time. 4 KELLOGG SCHOOL OF MANAGEMENT This document is authorized for use only by Lava Qurbani in QSO-420-H5657 Integrated Cost/Sched Control 21EW5 at Southern New Hampshire University, 2021. KEL224 ARIBA IMPLEMENTATION AT MED-X An ideal project management approach for an Ariba implementation promoted tight integration of the business transformation and organizational
  • 11. change. In addition, the organizational issues had to be coordinated with the Ariba configuration and IT infrastructure aspects of the project and the associated parties conducting these activities. For a successful project, the project management team had to foster effective communication among project team members and between project teams, and manage and track multiple projects from an executive perspective. The team also had to manage “scope creep” to meet stated project goals and objectives and provide for faster and more effective project decisions. The project management team also needed to provide enhanced focus on project issues/risks and recommended actions, establish documentation standards regarding quality and consistency, manage workflow regarding review and approval of project deliverables and work products, and provide for better utilization of scarce project resources. Finally, it had to provide for effective knowledge transfer between consulting and client project teams, provide a basis for an end-user help desk, and ensure that the client was completely satisfied. Project Plan Implementation Technologies designed the plan, outlined below, to roll out Ariba Buyer 7.0 to 250 users in MED-X’s home office. A thorough gap analysis was conducted prior to the start of the project that compared delivered Ariba functionality with the “to be” process and identified the differences for review. This analysis enabled
  • 12. Implementation Technologies to understa nd the gaps between MED-X’s current procurement system and an ideal e-procurement solution. The gap analysis team uncovered and documented the detailed steps necessary to implement the appropriate change management initiatives and effectively roll out Ariba Buyer. The first project phase culminated in a CRP in which MED-X was able to see and test Ariba functionality for the first time. Baker and other MED-X senior managers were enthusiastic about the successful pilot test. Project Objectives One of the early objectives was to design and configure the initial Ariba solution that would serve as both a “proof of concept” and learning tool to aid in the establishment of an enterprise- wide e-procurement solution and support structure. The CRP was an integral component of the production project as a first test of the solution. Another objective was to provide MED-X with a low-risk and controlled entrée into leveraging Ariba e-procurement technology and evolving best practices and to allow personnel to start developing functional and technical expertise in the Ariba Buyer application set. In addition, Information Technologies aimed to further define the requirements for elements of scope not met by Ariba “out-of-the-box” functionality and develop a strategy for developing the associated solution. This required defining a holistic and
  • 13. long-term integration strategy for Ariba and MED-X’s enterprise systems. The ultimate goal targeted for after October 1 was to roll out the common baseline solution across the home office for approximately 250 people. KELLOGG SCHOOL OF MANAGEMENT 5 This document is authorized for use only by Lava Qurbani in QSO-420-H5657 Integrated Cost/Sched Control 21EW5 at Southern New Hampshire University, 2021. ARIBA IMPLEMENTATION AT MED-X KEL224 Project Organization Exhibit 4 details the resources and roles required from MED-X and Implementation Technologies to successfully staff the project. Implementation Technologies estimated a six- month timeline to successfull y deliver the customized MED-X Ariba system. MED-X provided eight individuals to staff the project. Some of them assisted on an as- needed basis. A MED-X project manager worked with Christopher Martin to help manage issues for the MED-X team. Most of the individuals provided by MED- X were procurement specialists who were responsible for working with the Implementation Technologies team to ensure Ariba worked as intended and to deploy the system to other business users. Implementation Technologies provided seven individuals to
  • 14. staff the project. A project quality advisor was staffed part-time to provide quality management guidance throughout the project. Martin was responsible for overall project management and leadership. He was supported by the technical, functional, and supplier leads. The functional lead was primarily responsible for gathering business requirements. The technical lead was responsible for transforming MED-X business requirements into Ariba Buyer customizations. The supplier integration expert was responsible for working with the Ariba Buyer team and the suppliers that MED-X enabled. Finally, additional technical staff were to assist with specific customizations, such as writing business rules and interface modifications. Project Scope From the following high-level scope activities, project tasks were developed to support the delivery and execution of the final Ariba e-procurement system for MED-X. Ariba Buyer 7.0 Configuration/Installation. Install and configure server hardware, install third- party software (e.g., Web server), and install four initial instances of Ariba 7.0 (demo, test, CRP, and development). Business Process Design/Redesign. Validate “as is” and develop “to be” requisition-to-check and sourcing processes. Develop gap analysis to flag functional requirements not addressed by Ariba. Document end-to-end receiving requirements and commodity
  • 15. code strategy and mapping. Integration of Ariba Buyer 7.0 via TIBCO to MQ Series. Implement needed push-and-pull adapters. Catalog Content On-Boarding. Implement four supplier catalogs, configure catalog hierarchy to support catalogs implemented, and adapt UN/Standard Products and Services Code (UNSPSC). Supplier Enablement. Work with Ariba-enabled and non-Ariba- enabled suppliers. Plan and coordinate the supplier summit. Business Rules. Implement Ariba approval rules as stated in the request for proposal and analyze business rule requirements for the project. Object Model and User Interface Modifications. Limit user interface (UI) modifications for the project to those essential for capturing additional data elements not part of the standard Ariba 6 KELLOGG SCHOOL OF MANAGEMENT This document is authorized for use only by Lava Qurbani in QSO-420-H5657 Integrated Cost/Sched Control 21EW5 at Southern New Hampshire University, 2021. KEL224 ARIBA IMPLEMENTATION AT MED-X object model and presenting a standard format on the HTML- based requisition screens, printouts, and vendor direct orders.
  • 16. Source Data and Adapters. Manually load control data (e.g., unit of measure (UOM), currency, user hierarchy, vendor information, purchase transactions) and assist in the designing, building, and testing of custom interfaces to the MQ Series. Change Management. Includes end-user communication planning, development and execution of custom training curriculum for pilot end-user roll-out, assistance with developing training materials based upon knowledge repository, and a change management toolkit for Ariba Buyer. Reports. Use standard reporting functionality and begin capturing requirements for custom reports. Custom Functionality. Capture custom requirements in a functional gap analysis and research offline with Ariba to identify potential solution approaches (e.g., workarounds, customizations, or inclusion in upcoming versions of Ariba software) for future implementation. PCards, Invoices, Matching, Receiving, Payments, and Accounting. Implement Ariba Buyer with PCard functionality and ensure that all interfaces and process design enable efficient requisition to payment processing. System Testing System testing plans were developed to validate that the system architecture and software associated with Ariba Buyer met MED-X’s requirements. The
  • 17. system had to meet or exceed the performance, reliability, maintainability, and availability expectations of MED-X. The specific scope of system testing was as follows: • Database server processes • Web server processes • Server connection processes • Client connection processes • Middleware client module • Middleware server module • Workstation processes • Client data entry modules • Client printing services • Interface processes • Accounting data load • Human resources data load • General ledger (GL) data load KELLOGG SCHOOL OF MANAGEMENT 7 This document is authorized for use only by Lava Qurbani in QSO-420-H5657 Integrated Cost/Sched Control 21EW5 at Southern New Hampshire University, 2021.
  • 18. ARIBA IMPLEMENTATION AT MED-X KEL224 Technical Infrastructure A schematic of the development environment for the Ariba solution is shown in Exhibit 2. To facilitate rapid development, no other production applications could be running or were intended to run on the Ariba servers. Frequent Ariba server reboots were required during installation, so no other access to these servers could be active during the installation process. Consultants needed full access (console/physical) to the Ariba servers during installation. Full administrative rights were given to the consultants during the installation process and were ongoing for development and test environments (but not production). System administrators were available for on-call support during the installation of all instances. Prerequisite database software, personal computer hardware and software, server hardware and software, and intranet proxy and e-mail infrastructure had been installed, configured, and tested prior to installation of all Ariba modules. All necessary hardware and software for the Ariba Buyer e-procurement solution were installed prior to the project kickoff, and the workspace was prepared and designated for the team. Data Cleansing
  • 19. For the completed project, Information Technologies required MED-X to cleanse all source data required to support the Ariba system. In addition, the generation of all associated data conversion files had to be completed by MED-X. The original contract specifically stated: Managing and performing all data extracts required from host systems and the modifications to host systems required to accept data from Ariba will be completed by MED-X. It is MED-X’s responsibility to work with Ariba for any and all issues, should they arise, relating to the integrity of Ariba software and patches. MED-X will provide project personnel with knowledge of company labs’ environment to fulfill the functional roles and responsibilities. MED-X will provide the project team with all documentation relating to any process reengineering and strategic sourcing initiatives. So far in the project, MED-X had lived up to the contract and had delivered on schedule. Critical Success Factors Critical success factors for this project included a plan for organizational change effectiveness, quick resolution for business decisions affecting policy, and establishment of clearly defined project objectives, since exact definitions of project scope were key to keeping the project on time and within budget. It was also important to establish concise measures of success
  • 20. and support with strong executive sponsorship so that interdepartmental issues were addressed in an efficient manner. Other critical success factors included understanding MED-X’s B2B strategy, understanding current B2B projects underway, and determining methods of leveraging the results (collaborate rather than duplicate). Another important issue was to identify and assign key individuals to assist 8 KELLOGG SCHOOL OF MANAGEMENT This document is authorized for use only by Lava Qurbani in QSO-420-H5657 Integrated Cost/Sched Control 21EW5 at Southern New Hampshire University, 2021. KEL224 ARIBA IMPLEMENTATION AT MED-X in understanding current legacy systems and review and challenge complex business processes to reduce development and maintenance efforts. In addition, it was important to identify and allocate key resources that kept the project on schedule, since key personnel losses could significantly affect the delivery schedule. It was also important to identify current ERP system and process weaknesses, since staged multiple development environments were crucial to support the ability to implement changes without disrupting other aspects of the project. For project success, it was critical to use software version control; this is essential in a distributed development environment. Finally, the
  • 21. management team had to build early consensus across the user base and establish points of escalation or parameters to keep the team on track and working together. Project Status to Date After the meeting with Baker, Martin returned to his office. “Wow, Terry was really upset,” he thought. He knew he was on shaky ground, although his gut told him the project was not totally out of control. The MED-X implementation had been running rather smoothly to date, but some events had impacted it. For instance, very early in the project, a part-time MED-X staffer had been repeatedly pulled off the project for other duties. At the end of June, immediately after the successful CRP, there was a slight delay as the Sun server equipment showed up late. In July, system testing of the development of legacy data interfaces was scheduled late. In the testing, Martin’s team uncovered several things that were not working as designed. These events all contributed to delaying unit testing and holding up the Ariba integration with the PeopleSoft purchasing module. Martin studied the Microsoft Project Gantt chart on his computer screen, but could not tell exactly which component of the project was responsible for the delay. Maybe Baker had a good idea: check the earned value. Martin sent an e-mail to the project staff to obtain the necessary information.
  • 22. The data Martin’s staff provided is given in Exhibit 5–Exhibit 7, and Exhibit 8 is the standard Implementation Technologies earned value analysis template. Martin was not exactly sure what to do with the data now that he had it, but he figured this was a good start. KELLOGG SCHOOL OF MANAGEMENT 9 This document is authorized for use only by Lava Qurbani in QSO-420-H5657 Integrated Cost/Sched Control 21EW5 at Southern New Hampshire University, 2021. ARIBA IMPLEMENTATION AT MED-X KEL224 Exhibit 1: Ariba Buyer Configuration ERP 1 HRMS ERP 2 Ariba Buyer Commerce Services Network Internet End-User Buyers
  • 23. The diagram above illustrates the Ariba Buyer configuration. The Ariba B2B platform did the following: • Provided an infrastructure for e-commerce • Provided an open, standards-based Internet service that allowed Ariba Buyer to connect buyers and sellers worldwide • Simplified and streamlined order routing and catalog management • Promoted rapid supplier integration • Enabled e-commerce technology such as Punchout and cXML 10 KELLOGG SCHOOL OF MANAGEMENT This document is authorized for use only by Lava Qurbani in QSO-420-H5657 Integrated Cost/Sched Control 21EW5 at Southern New Hampshire University, 2021. KEL224 ARIBA IMPLEMENTATION AT MED-X
  • 24. Exhibit 2: Ariba Buyer Development Environment De velopment Instance De lopment Instanceve De lopment Instanceve Test Instance Ariba Buyer Production System Ongoing Development C nges, Unit Test, and Debug Integration Test and Debug Final Test and Debug Final Promotion
  • 25. ha This diagram illustrates a high-level approach to development. Ariba recommended creating three types of instances: development, test, and production (the production instance was the Ariba Buyer production system). Changes could be made first in development instances and then merged into a test instance, and finally moved into the Ariba Buyer production system, although these activities often took place concurrently. Exhibit 3: Project Timeline This chart outlines the project timeline for MED-X’s Ariba implementation. The project began in May and the go-live date was October 1, 2001. The CRP was scheduled for June 25. This was the first time that the Ariba e-procurement system, customized for MED-X, was functionally demonstrated. May June July Aug Sep October Go-Live Plan CRP Build Deploy Evolve
  • 26. KELLOGG SCHOOL OF MANAGEMENT 11 This document is authorized for use only by Lava Qurbani in QSO-420-H5657 Integrated Cost/Sched Control 21EW5 at Southern New Hampshire University, 2021. ARIBA IMPLEMENTATION AT MED-X KEL224 Exhibit 4: Project Organization ( A ) M E D - X R E S O U R C E R E Q U I R E M E N T S MED-X would provide the appropriate resources with the requisite level of commitment. The table below specifies the types and level of resources needed from MED-X. Functional Area Role Responsibilities Full-Time Equivalents Procurement Procurement professional Provide input to project team concerning procurement processes and procedures 1.0 Procurement Catalog manager/ supplier manager Manage supplier processes 0.5 Procurement Training End-user training 0.5
  • 27. Procurement/IT Ariba configuration/ development Through knowledge transfer, learn the Ariba solution set and configuration process and assume deliverable responsibilities in subsequent phases 0.5 IT Network/system administration Administer Ariba servers As needed IT Database administration Administer database server As needed IT Integration expert Provide input to project team concerning integration 1.0 Project Project manager Provide project management 1.0 ( B ) C O N S U L T I N G F I R M R E S O U R C E S F O R I M P L E M E N T A T I O N P R O J E C T The consulting firm would need to bring the following resources to MED-X for this implementation. Consulting Partner Resources Responsibilities Project advisor Available throughout project duration to facilitate resolution of strategic issues and to ensure that project is delivered on time and on budget. Responsibilities include
  • 28. monitoring workplan progress and quality assurance, aiding in resolution of difficult business issues and customer satisfaction, and maintenance of client relationship. Project manager Available throughout project duration to manage implementation team and complete project on time and on budget. Critical responsibilities include managing customer relationships, architecting project plan, identifying resource requirements, developing project infrastructure and management tools, and providing primary communication channel for all customer issues and feedback to Ariba. Functional lead Available during analysis, implementation, and deployment phases for defining business process requirements, business rules, and data integration requirements. Supplier integration expert Responsible for supplier integration/enablement, catalog and commodity management, and knowledge transfer to client supplier integration analyst. Technical lead Responsible for management of all development and integration activities. Will also have assigned development deliverables. Rules/UI specialist Responsible for writing of business/approval rules, UI/object model customizations, Java code, and all supporting documentation. Integration expert Responsible for configuration of delivered integration events and development of
  • 29. any custom interfaces to back-end systems. ( C ) A R I B A R E S O U R C E S F O R I M P L E M E N T A T I O N P R O J E C T Ariba Resource Responsibilities Ariba GSD consultant Assist with implementation as product expert. Also help facilitate communication between implementation team and Ariba to resolve issues. 12 KELLOGG SCHOOL OF MANAGEMENT This document is authorized for use only by Lava Qurbani in QSO-420-H5657 Integrated Cost/Sched Control 21EW5 at Southern New Hampshire University, 2021. KEL224 ARIBA IMPLEMENTATION AT MED-X Exhibit 5: Infrastructure and Software Customization Budgeted Cost of Work Scheduled T E C H N I C A L I N F R A S T R U C T U R E P L A N (a) The dollar amounts below represent the budgeted cost of work scheduled (BCWS) to be done for the given time period for the technical infrastructure component of the project plan. Month Dollar Amount May $ 120,000 June $ 192,000 July $ 192,000 August $ 192,000
  • 30. September $ 192,000 October $ 60,000 S O F T W A R E C U S T O M I Z A T I O N P L A N (b) The dollar amounts below represent the budgeted cost of work scheduled (BCWS) to be done for the given time period for the software customization component of the project plan. Month Dollar Amount May $ 120,000 June $ 192,000 July $ 192,000 August $ 192,000 September $ 192,000 October $ 60,000 Exhibit 6: Infrastructure and Software Customization Actual Cash Burn T E C H N I C A L I N F R A S T R U C T U R E A C T U A L C A S H B U R N (a) The dollar amounts below represent the actual cost of work performed (ACWP) for the given time period for the technical infrastructure component of the project plan. Month Dollar Amount May $ 120,000 June $ 215,000 July $ 192,000 August $ 216,500 September $ 170,000 S O F T W A R E C U S T O M I Z A T I O N A C T U A L C
  • 31. A S H B U R N (b) The dollar amounts below represent the actual cost of work performed (ACWP) for the given time period for the software customization component of the project plan. Month Dollar Amount May $ 119,000 June $ 187,000 July $ 165,000 August $ 189,000 September $ 186,000 KELLOGG SCHOOL OF MANAGEMENT 13 This document is authorized for use only by Lava Qurbani in QSO-420-H5657 Integrated Cost/Sched Control 21EW5 at Southern New Hampshire University, 2021. ARIBA IMPLEMENTATION AT MED-X KEL224 Exhibit 7: Infrastructure and Software Customization Actual Performance T E C H N I C A L I N F R A S T R U C T U R E A C T U A L P E R F O R M A N C E (a) The dollar amounts below represent the budgeted cost of work performed (BCWP) in the given time period for the technical infrastructure component of the project plan. Month Dollar Amount May $ 120,000 June $ 170,000 July $ 173,000 August $ 190,000
  • 32. September $ 185,000 S O F T W A R E C U S T O M I Z A T I O N A C T U A L P E R F O R M A N C E (b) The dollar amounts below represent the budgeted cost of work performed (BCWP) in the given time period for the software customization component of the project plan. Month Dollar Amount May $ 133,250 June $ 197,000 July $ 220,000 August $ 215,000 September $ 240,000 14 KELLOGG SCHOOL OF MANAGEMENT This document is authorized for use only by Lava Qurbani in QSO-420-H5657 Integrated Cost/Sched Control 21EW5 at Southern New Hampshire University, 2021. KEL224 ARIBA IMPLEMENTATION AT MED-X Exhibit 8: Earned Value Analysis Template The template below can be used to analyze earned value for the MED-X Ariba implementation. The accompanying electronic file has built-in Excel formulas to help derive the earned value ratios. Software Customization Monthly Plan May Jun Jul Aug Sep Oct
  • 33. Monthly status Plan BCWS Actual burn ACWP Actual perform BCWP Rolling status Plan BCWS Actual burn ACWP Actual perform BCWP Rolling ratios Schedule impact SV = BCWP – BCWS SPI = BCWP / BCWS Cost impact CV = BCWP – ACWP CPI = BCWP / ACWP Control ratio CR = SPI × CPI Technical Infrastructure May Jun Jul Aug Sep Oct Monthly status Plan BCWS Actual burn ACWP Actual perform BCWP Rolling status Plan BCWS Actual burn ACWP Actual perform BCWP Rolling ratios Schedule impact SV = BCWP – BCWS SPI = BCWP / BCWS Cost impact CV = BCWP – ACWP CPI = BCWP / ACWP Control ratio CR = SPI × CPI Combined Projects May Jun Jul Aug Sep Oct Monthly status Plan BCWS Actual burn ACWP
  • 34. Actual perform BCWP Rolling status Plan BCWS Actual burn ACWP Actual perform BCWP Rolling ratios Schedule impact SV = BCWP – BCWS SPI = BCWP / BCWS Cost impact CV = BCWP – ACWP CPI = BCWP / ACWP Control ratio CR = SPI × CPI KELLOGG SCHOOL OF MANAGEMENT 15 This document is authorized for use only by Lava Qurbani in QSO-420-H5657 Integrated Cost/Sched Control 21EW5 at Southern New Hampshire University, 2021. MED-X Inc.Implementation TechnologiesAriba Inc.Business Case and TechnologyProposed Approach and PlanProject ManagementProject PlanProject ObjectivesProject OrganizationProject ScopeSystem TestingTechnical InfrastructureData CleansingCritical Success FactorsProject Status to Date 2
  • 35. BADM 627 Project Risk & Quality Management Problem Set #5 Your Name Date Contents Assignment Guidelines 3 Part I: Create a risk matrix in Excel 3 Identify the risks to be addressed with a rationale as to why you have chosen these risks from the matrix? 3 Explain which of the four remediation methodologies you will use for each risk and why? 3 Part II: 3 Define Quality? 3 What does Total Quality Management emphasize? 3 Sate the Deming philosophy. 3 What are the major steps for an organization to follow in implementing TQM? 3 References 4 Assignment Guidelines Overview: Over the past few decades, one of the most common types of projects within a business is the development of a new
  • 36. piece of software to facilitate a certain facet of business operations. The assignment will entail a project concerned with the creation of a new version of business expense software for the entry of, tracking of, payment of business expenses accrued by organizational members during normal business operations as other related issues such as reimbursing employees for expenses they personally paid for during their business-related travel.Part I: Create a risk matrix in Excel (submit as a separate file) Identify the risks to be addressed with a rationale as to why you have chosen these risks from the matrix? Explain which of the four remediation methodologies you will use for each risk and why? Part II: · Define Quality? · What does Total Quality Management emphasize? · State the Deming philosophy. · What are the major steps for an organization to follow in implementing TQM? References Edwards, P. J., Serra, P. V., & Edwards, M. (2019). Managing project risks. Hoboken, NJ: Wiley-Blackwell. Project Management Institute, A guide to the project management body of knowledge (PMBOK® guide), Fifth Edition, Project Management Institute Inc. 2013. [Vitalsource version]. Retrieved from https://online.vitalsource.com/#/books/9781935589815/cfi/0
  • 37. QSO 420 Milestone Three Guidelines and Rubric This assignment is the third step in the analysis of the company for your final project. For this milestone, you will create a presentation for a project manager based on the assigned case study that reports the project’s performance, including any current or potential deficiencies that you have identified, as well as your recommendations for improving project performance. Specifically, the following critical elements must be addressed. Use presentation notes (“speaker notes”) to articulate those points that are not observable in the presentation: A. Explain the use of EVM statistics for identifying potential project performance deficiencies. B. Interpret the EVM statistics calculated for the project in the case study in terms of current or potential deficiencies. Do the statistics imply or identify any deficiencies? If so, what are they? Be sure to support your reasoning with research. C. Discuss the role of EVM principles in achieving integrated cost and schedule control. Be sure to substantiate your claims with research. D. Interpret the EVM statistics calculated for the project in the case study. Do they lend themselves to the successful integration of cost and schedule control for this project? Be sure to cite research to justify your
  • 38. position. E. Make appropriate recommendations for improving integrated cost and schedule control for the project in the case study. Be sure to use research to justify your recommendations. Guidelines for Submission: Use Microsoft PowerPoint or a similar presentation software to create four to five slides (not including references slide), that will report the project’s performance to the project manager. Be sure to cite references using APA format. Critical Elements Exemplary (100%) Proficient (85%) Needs Improvement (55%) Not Evident (0%) Value Interpretation: Use of EVM Statistics Meets “Proficient” criteria and provides cogent examples to detail the process of using EVM to identify deficiencies Comprehensively explains how EVM statistics are used to identify potential project deficiencies Explains how EVM statistics are used to identify potential project deficiencies, but with gaps in detail
  • 39. Does not explain how EVM statistics are used to identify potential project deficiencies 18 Interpretation: Deficiencies Meets “Proficient” criteria and cites specific, relevant examples to establish a robust context for the interpretation Accurately interprets EVM statistics for the project in the case study in terms of deficiencies, and supports reasoning with research Interprets EVM statistics for the project in the case study in terms of deficiencies, but with gaps in accuracy, or does not support reasoning with research Does not interpret EVM statistics for the project in the case study in terms of deficiencies 18 Interpretation: Role of EVM Principles
  • 40. Meets “Proficient” criteria and cites specific, relevant examples to establish a robust context for the discussion Comprehensively discusses the role of EVM principles in achieving integrated cost and schedule control and substantiates claims with research Discusses the role of EVM principles in achieving integrated cost and schedule control, but with gaps in detail, or does not substantiate claims with research Does not discuss the role of EVM principles in achieving integrated cost and schedule control 18 Interpretation: Integrated Control Meets “Proficient” criteria and articulation is exceptionally clear
  • 41. and logical Accurately interprets EVM statistics for the project in the case study for the successful integration of cost and schedule control and justifies position with research Interprets EVM statistics for the project in the case study for the successful integration of cost and schedule control, but with gaps in accuracy, or does not justify position with research Does not interpret EVM statistics for the project in the case study for the successful integration of cost and schedule control 18 Interpretation: Recommendations for Improving Meets “Proficient” criteria and provides detailed examples of how the recommendations will support the improvement of integrated cost and schedule control
  • 42. Makes appropriate recommendations for improving integrated cost and schedule control for the project in the case study and justifies recommendations with research Makes recommendations for improving integrated cost and schedule control, but recommendations are not appropriate, or does not justify recommendations with research Does not make recommendations for improving integrated cost and schedule control 18 Articulation of Response Submission is free of errors related to citations, grammar, spelling, syntax, and organization and is presented in a professional and easy-to-read format Submission has no major errors related to citations, grammar, spelling, syntax, or organization Submission has major errors
  • 43. related to citations, grammar, spelling, syntax, or organization that negatively impact readability and articulation of main ideas Submission has critical errors related to citations, grammar, spelling, syntax, or organization that prevent understanding of ideas 10 Earned Total 100%