Caterpillar Cat 257D MULTI TERRAIN LOADER (Prefix FMR) Service Repair Manual ...
Manpower optimization_2nd_0407_Eng
1. 對外秘
No ITEM SITE F/F cost H/C DATE Writer
1
[WP special – 10] Removal classifying scrap
screw with shape
D2E 2.5” - 3 April CH.KIM
To-BeTo-BeTo-BeTo-BeAs-IsAs-IsAs-IsAs-Is
effective
■ Removal this duty base on GUMI’s process
- It doesn’t need classifying the scrap screw
because it will be destroyed
1. H/C optimization_SUB[T6]
■ operator’s role of this duty
- Classifying the scrap screw with shape
. 3 operators are allocated (D2D 1F, 2F, D2E)
Removal of
classifying
3men/shift can be reduced
- this duty is extra activity for WP’s profit.
so shouldn’t include on H/C list
2. 對外秘
No ITEM SITE F/F cost H/C DATE Writer
2 [SUB - 11] removal duty what is MBA visual D2E 2.5” - 2 April CH.KIM
To-BeTo-BeTo-BeTo-BeAs-IsAs-IsAs-IsAs-Is
effective
■ Combine VMI with label attaching
- label attach/VMI/stacking MBA
→ Moving MBA to Assy Cell (Marshal)
1. H/C optimization_SUB[T6]
■ operator’s role of this duty
- checking whether MBA are defected
- now’s process
. Label attach(①) → VMI(②) → Stacking MBA(②)
→ moving MBA to Assy cell(Marshal)
Two operator are allocated in D2E 2.5”
→ 2 men/shift can be reduced by combine the duty with label attaching
1
2
3. 對外秘
To-BeTo-BeTo-BeTo-BeAs-IsAs-IsAs-IsAs-Is
Effective
Operator : 5 名 → 1 名 , 4 名 reduction
- D2D[1F] : 5 名 → 1 名 ( 4 名↓ )
□ Machine state of each Area
- D2E : 1EA / 1 名 , D2D : 2EA / 4 名
- LCA is not including particle suction function
so separate machine is needed to suction particle
□ minimize machine from reallocation of Assy machine
- LCA 14EA → 1EA
※ reference : D2E LCA 14EA will be operated
1. H/C optimization_SUB[T6]
No ITEM SITE F/F cost H/C DATE Writer
3
[SUB – 11] removal Vacuum Suction Particle
machine by improving Assembly machine
D2D 3.5” - 4 April CH.KIM
4. 對外秘
To-BeTo-BeTo-BeTo-BeAs-IsAs-IsAs-IsAs-Is
effective
Operator reduction : 8 名 → 4 名 , 4 名 efficiency
- D2D[1F] : 8 名 → 4 名 ( 4 名↓ )
□ Allocation Status
- D2D : 4EA / 8men (1machine /2men allocated)
- stand-by time is too many due to moving speed
of ABA Filter Cylinder
□ allocating just 1 operator on a cell
- correlate balance with movement of cylinder
. 1operator/machine
No ITEM SITE F/F cost H/C DATE Writer
4
[WP special - 11] re-allocation of 3.5 Stick
ABA
operator (1op/machine)
D2D 3.5” - 4 April CH.KIM
1. H/C optimization_SUB[T6]
5. 對外秘
No ITEM Content SITE F/F cost H/C DATE Writer
- Assy
[WP Special] combine CASTW with HDA
collector
D2D 3.5” - 1 (4 → 3) May BR.LEE
To-BeTo-BeTo-BeTo-BeAs-IsAs-IsAs-IsAs-Is
The different point of AUTO line between GUMI and WP
- the moving from H/T to CASTW is automatic by conveyor but WP is manual
■ each operator’s role
① operator : CASTW & H/T
② operator : collect HDA & move to CASTW Cell
■ combine CASTW & HDA collect
- by changing layout of H/T Cell to enable one
operator manage two H/T cell
ETC
2. H/C optimization_C/R[T6]
21 2
※ Operator allocation of 3.5” Auto Line
- GUMI : 3 名 /line, WP : 4 名 /line
Remove HDA collect operator
6. 對外秘
No ITEM Content SITE F/F cost H/C DATE Writer
1 H/T
[CR – 12] Manual H/T&CASTW operator
reduction by re-layout
D2D 3.5” - 21 (70 → 49) June BR.LEE
To-BeTo-BeTo-BeTo-Be
■ allocation sate base on Re-Layout
ETC
2. H/C optimization_C/R [T6]
D2D 1F
- Total operator : 49 名 /shift
. STW : 25 名 /shift
.. Operator allocation : 1 名 / Line
.. Number of operating facility : 25EA
. H/T : 24 名 /shift
.. Operator allocation : 0.5 名 / Cell
.. Number of operating facility : 48EA
H/TCASTW
The different point of AUTO line between GUMI and WP
- the set moving from H/T to CASTW is automatic by conveyor but WP is manual
7. 對外秘
No ITEM Content SITE F/F cost H/C DATE Writer
2 H/T
[CR - 13 Manual H/T operator reduction by
re-layout
D2E
D2D
2.5” - 15 (28 → 13) June BR.LEE
To-BeTo-BeTo-BeTo-Be
The different point of AUTO line between GUMI and WP
- All of moving from Assembly to H/T is automatic by conveyor but WP is not all
■ allocation sate base on Re-Layout
ETC
2. H/C optimization_C/R [T6]
H/T relayout
D2ED2D 2F
- Total operator : 13 名 /shift
. D2D 2F : 9 名 /shift
.. STA Line : 3men/line (total 3 Line)
. D2E : 4 名 /shift
.. N-HIT : 2 名 /shift
→ Total 3 Line 中 2Line is auto, 1Line is manual
. Block Cell : 2 名 / shift
.. 1 名 / block (total 2 block)
8. 對外秘
To-BeTo-BeTo-BeTo-Be
No ITEM Content SITE F/F cost H/C DATE Writer
3
H/T
DIST
[C/R - 14] reallocation label attaching
operator in TAB block
D2D 3.5” - 16 (24 → 8) June BR.LEE
To-BeTo-BeTo-BeTo-Be
ETC
2. H/C optimization_C/R [T6]
Reference data for this Item
- TAB Assy (TCT : 20sec) – 1 block is including three TAB cells
→ Attaching Label operator only need to finish a set within 6.3sec
Allocation state of CASTW & H/T
DISTLabel attaching (24
名 )
■ Re-allocation of attaching label operator to dist step
- 2men/block can be reduced (total 8 block)
→ H/C reduction effective : 16men/shift
■ now’s operator allocation plan
- 1 men/cell
→ Total 24 名 are needed
9. 對外秘
Effect
H/C Optimization by Efficiency of PCBA supply process up
D2D 4 名 , D2E 2 名 → D2D 2 名 , D2E 1 名
■ WP Status : PCBA ~ PBA Assy supply once a hour
. Adjust supply interval/quantity (1 回 ) after analyzing daily/hourly output
¼¼ºÎºÐ¼®
No ITEM Content SITE F/F cost H/C DATE Writer
1 PCBA [B/E – 21] PCBA logistics improvement ALL ALL - 3 July
SM.LEE
YM.KWON
3. H/C optimization_B/E[T6]
10. 對外秘
Effect
Cut down 2 operators that belonged to“Packing & pallet distribution”(12 名 → 10 名 )
: It may have workload gap according to allocation of each Site
※ Analyze it based on not using auto taping machine ( when reflect auto taping machine,
Expected that additional workload decrease
▷ Run the GF,1F’s Output by “1 Operator ( D1E Pallet distribution)”
: 1F Packing Operator perform “ moving to EV “ after stacking Box on the pallet”
■ Vacuum Packing & Distribution Operator Analysis
Unit
3.5" 2.5"
D1E 1F D1E GF D2D 1F D2E D2D 2F
Output(bade on 630 萬 ) 台 440,000
1,460,000
550,000
1,850,000 1,750,000
Hourly Qty. 台 771.93 2561.40 964.91 3245.61 3070.18
Hourly Box Qty. ea 38.60 128.07 48.25 64.91 61.40
Packing Box Cycle sec 93.27 28.11 74.62 55.46 58.63
Actual work time for Vacuum sec 50
Allocated Operator(current) 名 1 2 2 2 -
pallet distribution
operator(current)
名 1 1 2 1 -
Allocated Operator(expect) 名 1 2 1 1 1
pallet distribution
operator(expect)
名 - 1 1 1 1
No ITEM Content SITE F/F cost H/C DATE Writer
5 PCBA [B/E – 21] PCBA logistics improvement
D2E, D2D
D1E
2.5”
3.5”
- 2 名 (12 → 10) July
SM.LEE
YM.KWON
3. H/C optimization_B/E[T6]
11. 對外秘
To-BeTo-BeTo-BeTo-BeAs-IsAs-IsAs-IsAs-Is
개선
효과
□ too many operator is allocated : 4 (preparing 3, distribution 1)
□ no rule to distribute box to line
□ preparing without table : particle and low quality
□ right person is 3 (preparing 2, distribution 1)
□ make rule with set up Call System
□ set up working table (L 2000 * W400 * H600)
1ea attach each linepreparing
③ ① operator
- Box
folding
- Pe-bag
- Cushion①
②
② operator
- inject
Guide
- Box
stacking
③
distribution
Box
Cushion Pe Bag
가이드
- H/C reduction 1 名 (preparing 1 名 )
- make distribution rule with set up Call System
À̵¿½Ã°£ºÐ¼®
No ITEM Content SITE F/F cost H/C DATE Writer
2 Packing
[B/E - 19] Improvement of packing
material distribution
D2D ALL - 1 July BS.Jegal
3. H/C optimization_B/E[T6]
12. 對外秘
To-BeTo-BeTo-BeTo-BeAs-IsAs-IsAs-IsAs-Is
개선
효과
③
②
Cushion
①
Box
Pe Bag
가이드
높이 : 200mm
No ITEM Content SITE F/F cost H/C DATE Writer
3 Packing
[B/E - 19] Improvement of packing
material distribution
D2E ALL - 1 July BS.Jegal
□ too many operator is allocated : 4 (preparing 3, distribution 1)
□ no rule to distribute box to line
□ preparing without table : particle and low quality
□ right person is 3 (preparing 2, distribution 1)
□ make rule with set up Call System
□ set up working table (L 2000 * W400 * H600)
① operator
- Box
folding
- Pe-bag
- Cushion② operator
- inject
Guide
- Box
stacking
③
distribution
1ea attach each linepreparing
- H/C reduction 1 名 (preparing 1 名 )
- make distribution rule with set up Call System
3. H/C optimization_B/E[T6]
13. 對外秘
To-BeTo-BeTo-BeTo-BeAs-IsAs-IsAs-IsAs-Is
개선
효과
③
②
Cushion
①
Box
Pe Bag
가이드
높이 : 200mm
④
No ITEM Content SITE F/F cost H/C DATE Writer
4 Packing
[B/E - 19] Improvement of packing
material distribution
D1E ALL - 3 July BS.Jegal
□ too many operator is allocated : 7 (preparing 5, distribution 2)
□ no rule to distribute box to line
□ preparing without table : particle and low quality
□ right person is 4 (preparing 2, distribution 2)
□ make rule with set up Call System
□ set up working table (L 2000 * W400 * H600)
① operator
- Box
folding
- Pe-bag
- Cushion② operator
- inject
Guide
- Box
stacking
③
distribution
1ea attach each linepreparing
- H/C reduction 3 名 (preparing 2 名 )
- make distribution rule with set up Call System
3. H/C optimization_B/E[T6]
15. 對外秘
□ DMR Disk Burnish, Eraser Process efficiencies
▶ H/C point
● Burnish test waiting time is too long, so, could run with Disk Eraser.
- Burnish buffer conveyor is enough, there waiting time take too long
● So, each C/R, 1 operator could manage each Burnish & Eraser.
▶ Capacity simulation
Machine Capa. 1day 1shift
Burnish
Tape 3 7,500 22,500 11,250
Head 1 3,000 3,000 1,500
Total 4 25,500 12,750
Eraser
2.5" 2 7,500 15,000 7,500
3.5" 2 7,500 15,000 7,500
Total 4 30,000 15,000
RWK Disk Qty. 5.2M 6.3M
1month
(30days)
Product 5,200,000 6,300,000
HDA T/D 520,000 630,000
Disk T/D 810,000 981,346
1day Disk T/D 27,000 32,712
1shift Disk T/D 13,500 16,356
Disk Burnish
Machine
Disk Eraser
Machine
Disk Burnish
Conveyor
4. H/C optimization_RWK [T6]
16. 對外秘
To-BeTo-BeTo-BeTo-BeAs-IsAs-IsAs-IsAs-Is
Effect
□ WP C/R : Disk VMI Test
- 70pcs / 1 Hr
- 18 名 , (5.2M product)
Op : 18 名 → 15 名 , 3 名 ↓
. Current Op. status
: D2D 1F (8 名 ) / D2D 2F (5 名 ) / D2E (5 名 ) Arranged
□ WP C/R : Disk VMI Test
- 100pcs / 1 Hr (Standard of Gumi site)
- 15 名 , (6.3M product)
No ITEM Content SITE F/F cost H/C DATE Writer
2 RWK [RWK-4] Disk VMI Process D2D/D2E ALL - 3 ~4/15 DY.CHOI
4. H/C optimization_RWK [T6]
17. 對外秘
□ DMR Disk VMI Process efficiencies
▶ Different point from SEC
● SEC :
. SEC Disk VMI standard is 100pcs / 1hrs (1pcs VMI take 36 sec)
. Actually, Disk VMI time is more shorten than standard criteria.
● W/P
. WP Disk VMI is 70pcs/1hrs ( 1pcs VMI take 51 sec)
● Conclusion :
. Based on Gumi site, W/P takes more time for Disk VMI.
. About 15sec more takes per 1 Disk (pcs)
※ Ref)
- DMR Disk Yield Comparison (Disk DMR & Prime HSA Based)
. Gumi Site : 2.5” 85.65%
. W/P Site : 3.5” 83.57%
→ There is no Yield Gap showed
▶ Capacity simulation
5.2M 6.3M Remark
Disk VMI Capacity
70 / 1 Hr 100 / 1 Hr 100 / 1Hrs is Gumi standard
45,150 / 1 month 64,500 / 1 month 1day, 21.5hrs Based
T/D HDA 520,000 630,000 TTL Yield 90%
T/D Disk 780,000 945,000 1 Month Based
(1 HDA is 1.5 Disk)NG Disk 30,000 36,000
TTL Disk waiting
810,000 975,000 1 Month Based
13,500 16,250 1shift Based
VMI Operator 18 名 15 名 - 3 名
4. H/C optimization_RWK [T6]
18. 對外秘
To-BeTo-BeTo-BeTo-BeAs-IsAs-IsAs-IsAs-Is
Effect
□ WP C/R :
- Separated Process
- Head Screen operator : 5 名
(Arranged 5.5 名 / 1 Shift)
Op : 5 名 → 0 名 , 5 名 ↓
.. D2D 1F (2 名 ) → (0 名 )
.. D2D 2F (2 名 ) → (0 名 )
.. D2E (1 名 ) → (0 名 )
Head screen
Machine
Operator
□ No need screen operator
- FA engineer manage the Head screen
machine for their Judgment tooling.
Head screen
Machine
FA
Engineer
No ITEM Content SITE F/F cost H/C DATE Writer
3 RWK [RWK-7] Head screen Test (STW Machine) D2D/D2E ALL - 5 JUNE DY.CHOI
4. H/C optimization_RWK [T6]
19. 對外秘
□ C/R Head screen machine process
▶ H/C point
● W/P C/R failures, too many Head screen test. So, need to operators.
- Need to FA engineer skill up.
. FA engineer education plan
① Gumi site prepare to education curriculum.
② Need to help for WPPE.
- If change the C/R FA process (head screen process),
could able to stably fix the prime STW capacity.
▶ Different point from SEC
※ SEC : FA engineer help from the Head screen for their exactly Judgment
Main C/R
Failure
C/R FA engineer
T/D or Re test
Head Screen
Main C/R
Failure
C/R FA engineer
T/D or Re test
FA Head Screen
Debug
Debug ( FA engineer )
Head screen
or not
There is already fixed
Head screen inputting
failures
Debug
1. SEC 2. W/P
All debug controlled
from FA Engineer
4. H/C optimization_RWK [T6]
20. 對外秘
No ITEM Content SITE F/F cost H/C DATE Writer
4 RWK [RWK-3] DMR HSA VMI process removal D2D/D2E ALL - 11 immediately DY.CHOI
To-BeTo-BeTo-BeTo-BeAs-IsAs-IsAs-IsAs-Is
Effect
□ Move to DMR vendor for VMI Process
→ Replacement BU3, H&T VMI Process
□ WP just view the HSA Bent & recycle scrap
□ WP C/R : HSA VMI Test
- By using microscope
Op : 11 名 → 0 名 , 11 名 ↓
- D2D 1F : 4 名 → 0 名 (4 名 ↓ )
- D2D 2F : 4 名 → 0 名 (4 名 ↓ )
- D2E : 3 名 → 0 名 (3 名 ↓ )
WP (Remove 1st
VMI)
- HSA Bent (naked eye VMI)
& Recycle over check
BU3 (2nd
VMI)
- Using the microscope VMI
WP (1st
VMI)
- Using the microscope VMI
BU3 (2nd
VMI)
- Using the microscope VMI
4. H/C optimization_RWK [T6]
21. 對外秘
B/L (430 萬 ) WP Target (630 萬 )
Remark
Location Operator Location Operator
D2D 1F 8 名 D2D 1F 0 名 8 名 ↓
D2D 2F 8 名 D2D 2F 0 名 8 名 ↓
D2E 6 名 D2E 0 名 6 名 ↓
Total 22 名 Total 0 名 22 名↓
□ DMR HSA VMI Process efficiencies
▶ Different point from SEC
● SEC :
. SEC 1st VMI : Naked-eye VMI → HSA Bent(viewed naked eye) & Recycle over HSA check
. DMR vendor 2nd
VMI : Microscope VMI (More detailed VMI)
● W/P
. WP 1st
VMI : Microscope VMI
. DMR vendor 2nd
VMI : Microscope VMI (More detailed VMI)
● Conclusion : Because DMR vendor has been tested incoming visual inspection.
So, no need overlapped VMI test at the WP.
→ For working efficiency of the WP, 1st
WP VMI process removing and making like as SEC VMI process
※ Ref)
- In SEC, currently HSA packing and sorting operators has been inspected the HSA Bent and recycle over check
- BU3 incoming VMI result : additional 5% ~8% VMI detect → enough to VMI screen skill
BU3 Ãß°¡ VMI
ºÒ·®(2.5")
BU3 Ãß°¡ VMI
ºÒ·® (3.5")
▶ Line & operator allocation
4. H/C optimization_RWK [T6]
23. 對外秘
□ HDA T/D Process efficiencies
▶ WP has separated Top screw T/D & HDA T/D
→ It takes too more time and it need to more human resource.
. Gumi site : 1 step HDA T/D. → Gumi site is just 1 Step T/D process (① + ②)
. W/P site : 2 step HDA T/D. → After top screw T/D(①), moving to original T/D Cell and HDA T/D(②)
( W/P only applied process )
[ 3.5” T/D Process of W/P ]
( Gumi site has not separated Top screw & HDA T/D )
DMR
Process
③ ~⑩
② The other Screw T/D① Top screw T/D
4. H/C optimization_RWK [T6]
24. 對外秘
To-BeTo-BeTo-BeTo-BeAs-IsAs-IsAs-IsAs-Is
Effect
□ WP C/R :
- Specially WP has F41H Disk Swap process.
(operator 1 名 arranged)
Op : 1 名 → 0 名 , 1 名 ↓
.. D2D 1F (1 名 ) → (0 名 )
□ WP C/R :
- When F41H EOL, it will cancel.
Re-STW Set
Cover Re-Assy
HT Test
Cover Open
Disk Swap
T/D
Process
HSA T/D
Disk T/D
DMR processF4-1H T/D
Process
□ F41H Disk Swap process removal
Re-STW Set
Cover Re-Assy
HT Test
Cover Open
Disk Swap
HSA T/D
Disk T/D
DMR process
□ F41H Disk Swap (Operator 1 名 Arranged)
No ITEM Content SITE F/F cost H/C DATE Writer
6 RWK [RWK-2] HDA T/D (F41H Disk Swap) D2D 3.5” - 1 4/30 DY.CHOI
4. H/C optimization_RWK [T6]
25. 對外秘
□ HDA T/D Process efficiencies
▶ Specially, WP has F4-1H Disk Swap process.
- F4_1H Disk Swap : For reducing the T/D qty.
- It couldn’t run to the CASTW and F4-1H using the up-head,
so could swap the Disk without damage of the disk.
- Gumi site, has not applied above process because the its product very small.
(Now, already Gumi F4_1H has been EOL.
- Also, WP site, if F41H has EOL, this process no more need.
ASSY
SC~FT
AT
DIST
PCBA
Pass
Fai
l
Disk Swap
HT
※ Disk Swap 2times → Fail
RW
transfer
Re STW
Debug
<Pass / Fail
>
[ Disk Swap Process ] Re-STW Set
Cover Re-Assy
HT Test
Cover Open
Disk Swap
Set Barcode
Reading
T/D
Preparation
<Disk Swap Check>
T/D
Process
4. H/C optimization_RWK [T6]
26. 對外秘
To-BeTo-BeTo-BeTo-BeAs-IsAs-IsAs-IsAs-Is
Effect
□ Marshaling operating :
→ Separated each Sub-operating.
□ HSA Sub operating
→ Separated from each station.
Op : 18 名 → 8 名 , 10 名 ↓
.. All C/R (18 名 ) → (8 名 )
□ Marshaling operating :
→ Combine the Sub-operating and
controlled by the Marshal.
□ HSA sub operating combined from the
HSA sorting operator
Marshal
Return MRB
Dispense Empty Tray
Dispense Material (HDA)
HDA input to C/R from B/E
HSA sorting by Model
HSA Packing
3 名
3 名
2.5 名
2 名
2.5 名
3 名
2 名
Total
18 名
Marshal ( 마샬 )
Return MRB
Dispense Empty Tray
Dispense Material (HDA)
HDA input to C/R from B/E
HSA sorting by Model
HSA Packing
5 名
3 名
Total
8 名
※ WP, Current 5.2M Product Based ※ WP, After H/C 6.3M Product Based
No ITEM Content SITE F/F cost H/C DATE Writer
7 RWK [RWK-5] Sub Operating All All - 10 4/15 DY.CHOI
4. H/C optimization_RWK [T6]
27. 對外秘
□ C/R Sub operating Process efficiencies
Station
Current
(5.2M)
H/C
Simulate
(6.3M)
Change Description Picture
Marshal 3 名 - 3 名 0 名
Marshaling
operating
Gumi arranged 2 person of Marshaling operating
(Gumi 1.55M Based)
- Return MRB (0.2 名 )
- Dispense Empty Tray (0.4 名 )
- Dispense Material (HDA) (0.4 名 )
- HDA input to C/R from B/E (0.2 名 )
- MBA label removal (0.8 名 )
So, WP (6.3M) arranged about 8 名
- Return MRB (0.8 名 )
- Dispense Empty Tray (1.6 名 )
- Dispense Material (HDA) (1.6 名 )
- HDA input to C/R from B/E (0.9 名 )
- MBA label removal (3 名 )
cf.) MBA label removal H/C will cover
at Sub Material VMI H/C
Return MRB 3 名 -2.2 名 0.8 名
Dispense Empty Tray 2.5 名 -0.9 名 1.6 名
Dispense Material (HDA) 2 名 -0.4 名 1.6 名
HDA input to C/R from B/E 2.5 名 -1.6 名 0.9 名
HSA sorting by Model 3 名 -0 名 3 名
Combine
the operating
※ HSA VMI operating (3 名 / 1shift)
- Naked eye VMI
- HSA sorting by Model
- RTV HSA Packing
※ Process
- Naked eye VMI → HSA sorting → Packing.
- This is 1 process charged from HSA VMI op.HSA Packing 2 名 -2 名 0 名
Total 18 名 10 名 8 名
4. H/C optimization_RWK [T6]
28. 對外秘
No ITEM Content SITE F/F cost H/C DATE Writer
8
Label
remove
[RWK – ] Label removal D2E, D2D
2.5”
3.5”
- 5 名 (10 → 5) 5 月
Effect
RWK Process, Label removal 5 名 H/C (10 名 → 5 名 )
: Based to Gumi process, Human resource optimization need to operator skill up.
▷ SEC : 1 operator arranged (1.55M product based) → Change the 6.3M based, could able to run 5 名 (4.3 名 )
▷ Detail analysis
■ RWK Process, Label removal.
Process Unit
SEC
1.55M
WP
5.2M
WP
6.3M
SEC
6.3M
H/C efficient
Cover label removal 名 0.2 3.0 3.6 0.8 2.2
MBA label removal 名 0.8 4.5 5.5 3.0 1.5
HDA label removal 名 0.1 2.5 3.0 0.4 2.1
Total 名 1.1 10.0 12.0 4.3 5.7
▶ 現 , WP arranged 10 名 (5.2M), Label removal op. could able to 5 名 (4.3 名 ) from the Gumi based.
Label removal operator was also arranged to Sub material VMI, so could effect to 5 名 reduction
- Sub Material VMI need to more 0.7 operator.
4. H/C optimization_RWK [T6]
29. 對外秘
Process
Gumi
1.55M
Gumi
6.3M
WP
5.2M
WP
6.3M
Effect H/C Charged
Sub-VMI
Sub material Visual 1.4 5.7 3.0 3.6 -2.7 5.7 Sub Material VMI operator
Ramp & Latch Visual 0.3 1.2 2.0 2.4 0.8 1.2 Sub Material VMI operator
MBA Visual 1.3 5.3 6.5 7.9 1.2 5.3 MBA VMI operator
Total 3.0 12.2 11.5 13.9 -0.7 12.2
Label
Cover label removal 0.2 0.8 3.0 3.6 2.2 0.8 Sub Material VMI operator
MBA label removal 0.8 3.0 4.5 5.5 1.5 3.0 Marshal
HDA label removal 0.1 0.4 2.5 3.0 2.1 0.4 Sub Material VMI operator
Stick label 0.0 0.0 2.0 2.4 Main process
Window label stick of
MBA
0.0 0.0 1.0 1.2 Main process
Total 1.1 4.3 10.0 12.1 5.7 4.3
Total 4.1 16.5 21.5 26.0 5.0 16.5
■ RWK Label removal operator.
- Based Gumi arranged operator, same rate applied.
→ VMI operator and Label removal operator is same process.
※ Sub-material H/C 5.7 名 reduction.
① Sub material VMI H/C (-0.7 名 )
- Sub material VMI (except, MBA, Ramp & Latch) : 2.7 名 increase
- Ramp & Latch : 0.8 名 reduction (microscope VMI)
- MBA VMI : 1.2 名 reduction (Except MBA Air-blowing operator)
② Label removal H/C ( 5.7 名 )
- Cover, HDA Label : Sub material VMI operator : 4.3 名 reduction
- MBA Label removal : MBA VMI operator : 1.5 名 reduction
- Label (include, Window Label ) Stick : Main process. (except)
[ Unit : 名 ]
4. H/C optimization_RWK [T6]
30. 對外秘
No ITEM Content SITE F/F cost H/C DATE Writer
9 RWK
[WP special - 11] Unify RWK with Re-
STW/HT
D2D 3.5” -
2 名 (3.5 →
1.5)
June
effective
Re-STW H/C optimization in RWK Process (3.5 名 → 1.5 名 )
: H/C optimization from modify WP process to GUMI’s one
To-BeTo-BeTo-BeTo-BeAs-IsAs-IsAs-IsAs-Is
□ separate MAIN process from RWK process
- port gap of each cell in Main process
- RWK Status : 5.5Cell / 3.5 名
□ MIAN □ RWK
□ Unify MAIN with RWK
- Unify Main Prime & RWK
- correlation the number of facility in each cell
□ MIAN □ RWK
4. H/C optimization_RWK [T6]
31. 對外秘
To-BeTo-BeTo-BeTo-BeAs-IsAs-IsAs-IsAs-Is
Effect
□ WP, C/R inputting HDA process.
. Human resource was separated for two station.
. Gumi based, It is just one station and could optimize H/C.
Op : 5 名 → 3 名 , 2 名 ↓
.. B/E, C/R inputting process optimize (5 名 ) → (3 名 )
※ WP, Current 5.2M product based
→ 5 名 (4.5 名 ) Arranged
※ 6.3M Product Based (After H/C)
→ 3 名 (2.4 名 ) Arranged
C/R inputting HDA Cleaning
HDA input to C/R
5 名
□ Gumi based, it could able to one operator for each C/R (D2D
1F, D2D 2F, D2E).
C/R inputting HDA Cleaning
+
HDA input to C/R
3 名
No ITEM Content SITE F/F cost H/C DATE Writer
10 RWK [RWK – 12] C/R inputting process D2E, D2D
2.5”
3.5”
- 2 名 (5 → 3) MAY DY.CHOI
4. H/C optimization_RWK [T6]
32. 對外秘
□ C/R inputting process optimization
※ C/R inputting HDA Cleaning + HDA input to C/R
Each C/R 1 operator arrange (6.3M Based)
. SEC (1.55M) : 0.3 名 + 0.3 名 = 0.6 名 arranged
. SEC (6.3M) : 1.2 名 + 1.2 名 = 2.4 名 arranged
. W/P (5.2M) : 3.5 名 + 1.0 名 = 4.5 名 arranged
→ About 3 operator could optimize.
And more reduction of inputting HDA cleaning is need to more discussion.
4. H/C optimization_RWK [T6]
33. 對外秘
No ITEM Content SITE F/F cost H/C DATE Writer
11 RWK [RWK – 9] B/E FA engineer D2E, D2D
2.5”
3.5”
- 2 名 (10 → 8) 5 月
Effect
RWK, B/E FA engineer required, 10 →名 8 名 (6.3M product)
▷ SEC : 1 FA Engineer controlled OOB set is 15.9K per shift.
▷ WP : 1 FA Engineer controlled OOB set is 12.1K(5.2M) and 14.6K(6.3M) per shift. (current engineer based)
■ RWK Process, B/E FA Engineer.
1 shift 1 shift based
B/E 月 Capacity
月 OOB
(Qty)
1 FA engineer
control count
(Qty)
WP need
engineer
現 engineer
arranged
Effect
Gumi (1.55M) 1.55M 95K 15.9K 3 3 0
WP (5.2M) 5.2M 193K 15.9K 6 10 4
WP (6.3M) 6.3M 234K 15.9K 7.3 10 2.7
▷ It based each product Qty, so if changed product Qty, could able to change the FA engineer count.
4. H/C optimization_RWK [T6]
35. 對外秘
To-BeTo-BeTo-BeTo-BeAs-IsAs-IsAs-IsAs-Is
Effect
□ WP, PCBA Rework Process.
. Separated PCB Code D/L process,
PCBA VMI (PCBA Discolor repair)
and PCBA dispose process.
. So, each process arranged operator.
Op : 2 名 → 1 名 , 1 名 ↓
.. B/E PBA VMI & Dispose process improving (2 名 ) → (1 名 )
※ WP, Current 5.2M product based
→ 2 名 (1.5 名 ) Arranged
※ 6.3M Product Based (After H/C)
→ 1 名 (0.8 名 ) Arranged
RTV PCBA Dispose
MRB Material Dispose
2 名
PCB discolor repair & VMI 3 名
RTV PCBA Dispose
MRB Material Dispose
1 名
PCB discolor repair & VMI 0.5 名
□ WP, PCBA Rework Process improving.
. From the Gumi site based,
PCBA VMI operator control the PCBA dispose process.
( effect : 2 名 → 1 名 )
. cf.) Gumi has not issued PCBA discolor, so VMI process
combined PCBA code D/L process
No ITEM Content SITE F/F cost H/C DATE Writer
12 RWK [RWK – 10 ] RTV PCBA & MRB material dispose D2E, D2D
2.5”
3.5”
- 1 名 (2 → 1) 5 月
4. H/C optimization_RWK [T6]
36. 對外秘
□ B/E PCBA Process optimization
1. W/P site : Each PBCA Rework process separated.
- PCBA T/D
- PCBA code D/L
- PCBA discolor repair and VMI
- RTV PCBA & MRB material dispose
2. Gumi site : For efficiently operating, some process has combined and simplified.
- PCBA T/D
- PCBA code D/L and VMI
- RTV PCBA & MRB material dispose
※ Gumi has not issued PCBA discolor, so VMI process has combined with PCBA D/L station.
3. From the Gumi’s resource standard, RTV PCBA & MRB material dispose operator has arranged 1 operator.
4. PCBA D/L machine : Need to study for its efficiency (D/L Port increase & Code D/L speed up, etc)
5. Discolor issue : Need to study of root cause for its process removal.
4. H/C optimization_RWK [T6]