SlideShare a Scribd company logo
1 of 106
Download to read offline
1	
  	
  Page	
  	
  	
  	
  	
  	
  All	
  citations	
  are	
  from:	
  Project	
  Management	
  Institute.	
  (2013).	
  A	
  guide	
  to	
  the	
  project	
  management	
  body	
  
of	
  knowledge.	
  (5th	
  Ed.).	
  Newton	
  Square,	
  PA:	
  Author.	
  	
  
	
   	
  
This	
  table	
  of	
  Contents	
  is	
  automatically	
  generated.	
  	
  Press	
  the	
  F9	
  key	
  to	
  update	
  the	
  entire	
  table	
  and	
  the	
  page	
  
numbers.	
  	
  
Contents	
  
Instructions	
  for	
  Working	
  with	
  Templates	
  .................................................................................................................	
  2
Initiating	
  Process	
  Group	
  ...........................................................................................................................................	
  3
PMBOK®	
  Guide–	
  Initiating	
  Processes	
  ..................................................................................................................	
  3
PMBOK®	
  Guide	
  Chapter	
  4	
  -­‐	
  Integration	
  Management	
  Processes	
  .....................................................................	
  14
PMBOK®	
  Guide	
  Chapter	
  7	
  -­‐	
  Cost	
  Management	
  Planning	
  Processes	
  .................................................................	
  52
Planning	
  B	
  Process	
  Group	
  ......................................................................................................................................	
  56
PMBOK®	
  Guide	
  Chapter	
  11	
  –	
  Risk	
  Management	
  Planning	
  Processes	
  ...............................................................	
  56
	
  
	
  
	
  
This	
  List	
  of	
  Templates	
  is	
  automatically	
  generated.	
  	
  Press	
  the	
  F9	
  key	
  to	
  update	
  the	
  entire	
  table	
  and	
  the	
  page	
  
numbers.	
  	
  
	
  
List	
  of	
  Templates	
  
	
  
01a	
  Initiation	
  Template:	
  	
  Business	
  Case	
  for	
  a	
  Proposed	
  Project	
  ..................................................................	
  3
4.1a	
  Project	
  Charter	
  .....................................................................................................................................	
  7
13.1	
  a.	
  Stakeholder	
  Register	
  and	
  Stakeholder	
  Strategy	
  .............................................................................	
  11
13.1	
  b.	
  Stakeholder	
  Communication	
  Strategies	
  .........................................................................................	
  12
13.1	
  c.	
  	
  Impact	
  and	
  Interest	
  Stakeholder	
  Analysis	
  .....................................................................................	
  13
5.1a	
  Scope	
  Management	
  Plan	
  ....................................................................................................................	
  15
5.2a.	
  Requirements	
  Documentation	
  ..........................................................................................................	
  16
5.3a	
  Project	
  Scope	
  Statement	
  ....................................................................................................................	
  17
5.4a	
  WBS	
  –	
  Work	
  Breakdown	
  Structure	
  ....................................................................................................	
  21
6.2a	
  	
  Milestone	
  List	
  ....................................................................................................................................	
  26
6.3.a.	
  Activity	
  List	
  with	
  Dependency	
  Attributes	
  .........................................................................................	
  28
6.4a.	
  Activity	
  List	
  with	
  Resource	
  Attributes	
  ...............................................................................................	
  31
6.4b.	
  Resource	
  Summary	
  ...........................................................................................................................	
  50
7.2.a.	
  Activity	
  Cost	
  Estimates	
  .....................................................................................................................	
  53
7.3.a.	
  Cost	
  Performance	
  Baseline	
  ..............................................................................................................	
  54
11.2a	
  Risk	
  Register	
  .....................................................................................................................................	
  57
11.3a	
  Risk	
  Register	
  .....................................................................................................................................	
  58
11.5a	
  	
  Risk	
  Register	
  ....................................................................................................................................	
  61
11.3b	
  Risk	
  Probability	
  and	
  Impact	
  (P&I)	
  Matrix	
  .........................................................................................	
  63
	
  
Note:	
  Sections	
  6.6a	
  (Schedule	
  Baseline)	
  and	
  7.3a	
  (Cost	
  Performance	
  Baseline)	
  were	
  either	
  skipped	
  or	
  
partially	
  skipped	
  per	
  assignment	
  instructions	
  dated	
  –	
  2/4/2014	
  by	
  Professor	
  Johnson
2	
  	
  Page	
  	
  	
  	
  	
  	
  All	
  citations	
  are	
  from:	
  Project	
  Management	
  Institute.	
  (2013).	
  A	
  guide	
  to	
  the	
  project	
  management	
  body	
  
of	
  knowledge.	
  (5th	
  Ed.).	
  Newton	
  Square,	
  PA:	
  Author.	
  	
  
	
   	
  
	
  
Instructions	
  for	
  Working	
  with	
  Templates	
  
	
  
Draft	
  versions	
  of	
  project	
  documents:	
  	
  
	
  
• Work	
  directly	
  in	
  copies	
  of	
  the	
  templates	
  
• Replace	
  all	
  instances	
  of	
  “Your	
  text	
  here”	
  with	
  your	
  own	
  project	
  information.	
  	
  
• Each	
  table	
  has	
  a	
  header	
  row	
  that	
  is	
  automatically	
  repeated	
  when	
  the	
  document	
  spans	
  additional	
  
pages.	
  	
  
• Keeping	
  a	
  line	
  of	
  text	
  between	
  tables	
  (boxes)	
  will	
  avoid	
  problems	
  with	
  tables	
  accidentally	
  merging	
  
and	
  potentially	
  disappearing,	
  which	
  is	
  a	
  known	
  issue	
  with	
  Microsoft	
  Word	
  tables.	
  
• Consider	
  the	
  information	
  included	
  in	
  the	
  blocks	
  that	
  provide	
  overviews	
  of	
  the	
  inputs,	
  outputs,	
  tools	
  
and	
  techniques	
  to	
  help	
  answer	
  some	
  of	
  the	
  specific	
  questions.	
  
	
  
Final	
  versions	
  of	
  project	
  documents:	
  Copy	
  and	
  paste	
  the	
  appropriate	
  sections	
  into	
  your	
  final	
  document.	
  
• Include	
  a	
  project	
  title	
  block	
  at	
  the	
  beginning	
  of	
  a	
  section.	
  
• You	
  may	
  choose	
  to	
  include	
  the	
  blocks	
  that	
  provide	
  overviews	
  of	
  the	
  inputs,	
  outputs,	
  tools	
  and	
  
techniques	
  if	
  you	
  find	
  them	
  useful.	
  	
  
	
  
	
  
Project	
  Title	
  Block-­‐	
  Paste	
  this	
  block	
  above	
  project	
  documents	
  to	
  identify	
  the	
  revision	
  date,	
  the	
  project	
  name,	
  the	
  
sponsor	
  and	
  the	
  project	
  manager..	
  
	
  
Revision	
  Date:	
  Friday,	
  May	
  8,	
  2015	
  
	
  
Project	
  Name:	
  Swimlane	
  Cruise	
  Line	
  Gift	
  Shops	
  Project	
  
	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  
Sponsor:	
  	
  Mr.	
  Dennis	
  Horvatt,	
  President	
  of	
  Construction,	
  TFSB	
  Construction,	
  Inc.	
  	
  
	
  
Project	
  Manager(s):	
  Jerry	
  P.	
  Magaña	
  
	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  
	
  
	
  
3	
  	
  Page	
  	
  	
  	
  	
  	
  All	
  citations	
  are	
  from:	
  Project	
  Management	
  Institute.	
  (2013).	
  A	
  guide	
  to	
  the	
  project	
  management	
  body	
  
of	
  knowledge.	
  (5th	
  Ed.).	
  Newton	
  Square,	
  PA:	
  Author.	
  	
  
	
   	
  
	
  
Initiating	
  Process	
  Group	
  
	
  
The	
  initiating	
  process	
  group	
  is	
  summarized	
  in	
  section	
  3.3	
  of	
  the	
  PMBOK	
  Guide.	
  Specific	
  information	
  about	
  the	
  
purpose	
  and	
  characteristics	
  of	
  each	
  process	
  is	
  available	
  in	
  the	
  PMBOK	
  Guide	
  in	
  the	
  sections	
  noted.	
  	
  
PMBOK®	
  Guide–	
  Initiating	
  Processes	
  
Knowledge	
  Area	
   Process	
   Inputs	
   Tools	
  and	
  Techniques	
  
	
  
Outputs	
  
Integration	
   4.1	
  Develop	
  
Project	
  Charter	
  
Project	
  SOW,	
  Business	
  
Case,	
  Contracts,	
  	
  OPAs	
  
and	
  EEFs	
  	
  
Expert	
  Judgment	
   Input	
  01a:	
  Business	
  
Case	
  
4.1a	
  Project	
  Charter	
  
Communications	
   13.1	
  Identify	
  
Stakeholders	
  
Project	
  Charter,	
  
Procurement	
  
documents,	
  EEF,	
  OPA	
  	
  
Stakeholder	
  analysis,	
  
	
  Expert	
  Judgment,	
  
Meetings	
  
13.1a	
  Stakeholder	
  
Register.	
  
13.1b	
  Communication	
  
Strategies	
  
13.1c	
  Impact	
  and	
  
Interest	
  Analysis	
  
	
  
	
  
Initiating	
  Integration	
  Element	
  
01a	
  Initiation	
  Template:	
  	
  Business	
  Case	
  for	
  a	
  Proposed	
  Project	
  	
  
The	
  Business	
  Case	
  is	
  an	
  input	
  to	
  the	
  project	
  initiating	
  process	
  and	
  is	
  typically	
  prepared	
  by	
  the	
  “customer”.	
  
	
  
Proposed	
  Project	
  Name:	
  	
  	
  	
  
Swimlane	
  Cruise	
  Ship	
  (in	
  association	
  with	
  the	
  “No	
  More	
  Starving	
  Families”	
  program)	
  Gift	
  Shops	
  Project	
  
	
  
Proposed	
  Location:	
  	
  	
  
The	
  Starve	
  No	
  More	
  Foundation’s,	
  Swimlane	
  Cruise	
  Ship	
  (SCS)	
  
	
  
Type	
  of	
  Project:	
  	
  	
  
Not	
  for	
  Profit;	
  Maritime	
  Construction	
  
	
  
1.0	
  Introduction/Background	
  
Describe	
  the	
  sponsoring	
  organization	
  and	
  the	
  proposed	
  project	
  environment.	
  
TFSB	
  Construction,	
  Inc.	
  (heretofore	
  known	
  as,	
  the	
  Organization)	
  was	
  founded	
  in	
  1973	
  by	
  construction	
  magnate	
  and	
  
philanthropist,	
  Jonathon	
  H.	
  Temmingson	
  and	
  has	
  been	
  serving	
  various	
  commercial	
  and	
  not	
  for	
  profit	
  organizations	
  for	
  
more	
  than	
  40	
  years.	
  
	
  
After	
  more	
  than	
  40	
  years	
  of	
  providing	
  design	
  and	
  construction	
  services	
  for	
  non	
  for	
  profit	
  groups,	
  industrial,	
  residential,	
  
commercial	
  and	
  maritime	
  projects,	
  Mr.	
  Temmingson’s	
  lifelong	
  dedication	
  to	
  his	
  humanitarian	
  projects	
  prompted	
  him	
  to	
  
develop	
  a	
  division	
  dedicated	
  to	
  non	
  for	
  profit	
  maritime	
  construction	
  projects.	
  	
  
	
  
By	
  working	
  on	
  the	
  Foundation’s	
  Swimlane	
  Cruise	
  Ship	
  project,	
  the	
  Organization	
  will	
  help	
  to	
  ensure	
  that	
  the	
  Foundation	
  
will	
  be	
  able	
  to	
  continue	
  providing	
  for	
  the	
  families	
  that	
  depend	
  on	
  their	
  support,	
  even	
  long	
  after	
  Ms.	
  Corday’s	
  involvement	
  
with	
  the	
  Foundation	
  has	
  ended.	
  It	
  is	
  the	
  hope	
  of	
  both	
  the	
  Organization	
  (sponsor)	
  and	
  the	
  Foundation	
  (customer)	
  that	
  by	
  
creating	
  a	
  specialty	
  cruise	
  liner	
  that	
  appeals	
  to	
  affluent	
  patrons,	
  this	
  will	
  help	
  to	
  continue	
  to	
  raise	
  funds	
  for	
  Ms.	
  Corday’s	
  
Foundation,	
  thus	
  solving	
  the	
  problem	
  of	
  obtaining	
  and	
  maintaining	
  a	
  reliable	
  source	
  of	
  funding	
  as	
  well	
  as	
  solidifying	
  the	
  
longevity	
  of	
  the	
  Foundation	
  for	
  years	
  to	
  come.	
  
	
  
	
  
4	
  	
  Page	
  	
  	
  	
  	
  	
  All	
  citations	
  are	
  from:	
  Project	
  Management	
  Institute.	
  (2013).	
  A	
  guide	
  to	
  the	
  project	
  management	
  body	
  
of	
  knowledge.	
  (5th	
  Ed.).	
  Newton	
  Square,	
  PA:	
  Author.	
  	
  
	
   	
  
01a	
  Initiation	
  Template:	
  	
  Business	
  Case	
  for	
  a	
  Proposed	
  Project	
  	
  
The	
  Business	
  Case	
  is	
  an	
  input	
  to	
  the	
  project	
  initiating	
  process	
  and	
  is	
  typically	
  prepared	
  by	
  the	
  “customer”.	
  
	
  
2.0	
  Business	
  Objective:	
  
How	
  does	
  the	
  project	
  connect	
  to	
  the	
  mission	
  of	
  the	
  sponsoring	
  organization?	
  
The	
  scope	
  of	
  the	
  Swimlane	
  Cruise	
  Ship	
  project	
  includes	
  the	
  following:	
  a)	
  Ship	
  Structure	
  Build,	
  b)	
  Fixtures	
  and	
  Decorations,	
  
c)	
  Software/Hardware/Electronics,	
  d)	
  Kitchen	
  and	
  Food	
  Services,	
  e)	
  Events	
  Coordination,	
  and	
  f)	
  Gift	
  Shops.	
  	
  
	
  
This	
  project	
  will	
  focus	
  on	
  item	
  ‘f,’	
  Gift	
  Shops.	
  
	
  
The	
  opportunity	
  this	
  project	
  presents	
  is	
  a	
  means	
  to	
  provide	
  a	
  lasting	
  service	
  to	
  the	
  customer	
  in	
  an	
  effort	
  to	
  insure	
  
revenue	
  for	
  underprivileged	
  families	
  that	
  are	
  lacking	
  proper	
  nutritional	
  needs	
  to	
  sustain	
  life.	
  	
  
	
  
Due	
  to	
  challenging	
  conditions	
  of	
  financial	
  support,	
  combined	
  with	
  a	
  growing	
  trend	
  for	
  interest	
  in	
  consumers	
  selecting	
  
Cruises	
  for	
  vacations,	
  the	
  Organization	
  expects	
  that	
  this	
  opportunity	
  will	
  provide	
  the	
  necessary	
  funds	
  to	
  feed	
  in	
  excess	
  of	
  
1000	
  families	
  for	
  a	
  six-­‐month	
  period,	
  as	
  well	
  as	
  pay	
  for	
  the	
  costs	
  of	
  the	
  project	
  through	
  pre-­‐purchased	
  vacation	
  packages	
  
by	
  wealthy	
  SCS	
  patrons.	
  
	
  
The	
  project	
  deliverables	
  shall	
  include	
  a	
  total	
  of	
  5	
  gift	
  shops:	
  1,	
  centrally	
  located,	
  ‘main,’	
  2-­‐level	
  gift	
  shop,	
  and	
  4	
  additional	
  
smaller	
  ‘satellite’	
  gift	
  shops	
  located	
  around	
  the	
  various	
  common	
  areas	
  of	
  the	
  ship.	
  
	
  
	
  
3.0	
  Current	
  Situation	
  and	
  Problem/Opportunity	
  Statement	
  
Provide	
  a	
  high	
  level	
  overview.	
  What	
  is	
  the	
  problem	
  that	
  needs	
  to	
  be	
  solved	
  or	
  the	
  opportunity	
  that	
  can	
  be	
  captured?	
  	
  
To	
  date,	
  Ms.	
  Corday	
  and	
  her	
  Foundation	
  have	
  relied	
  on	
  personal	
  funds	
  to	
  organize	
  charitable	
  events	
  in	
  an	
  attempt	
  to	
  
attract	
  other	
  wealthy	
  donors.	
  Now	
  that	
  Ms.	
  Corday’s	
  funds	
  are	
  in	
  jeopardy	
  of	
  being	
  exhausted,	
  new	
  methods	
  for	
  
attracting	
  donors	
  have	
  become	
  necessary.	
  	
  
	
  
In	
  years	
  past,	
  effective	
  fundraising	
  has	
  been	
  an	
  issue	
  for	
  the	
  Starve	
  No	
  More	
  Foundation	
  and	
  Ms.	
  Corday	
  and	
  the	
  
Foundation	
  has	
  relied	
  heavily	
  on	
  her	
  own	
  personal	
  contributions	
  to	
  ensure	
  the	
  success	
  of	
  their	
  mission.	
  	
  
	
  
In	
  a	
  proactive	
  attempt	
  to	
  prevent	
  the	
  Foundation’s	
  imminent	
  insolvency,	
  Ms.	
  Corday	
  strongly	
  desires	
  the	
  legacy	
  of	
  her	
  
and	
  her	
  family’s	
  hard	
  work	
  to	
  be	
  nationally	
  recognized	
  by	
  an	
  unprecedented	
  undertaking:	
  the	
  building	
  of	
  a	
  privately	
  
owned	
  and	
  operated	
  pleasure	
  cruise	
  line	
  that	
  will	
  continue	
  to	
  raise	
  funds	
  to	
  support	
  the	
  mission	
  of	
  the	
  Foundation	
  for	
  
the	
  foreseeable	
  future.	
  
	
  
The	
  SCS	
  Gift	
  Shops	
  will	
  provide	
  luxurious	
  amenities	
  and	
  feature	
  quality	
  custom	
  items	
  for	
  retail	
  purchase	
  of	
  the	
  SCS	
  
patrons	
  for	
  years	
  to	
  come.	
  The	
  profits	
  from	
  the	
  SCS	
  Gift	
  Shops	
  will	
  be	
  used	
  to	
  support	
  the	
  day-­‐to-­‐day	
  SCS	
  operating	
  costs	
  
as	
  well	
  as	
  the	
  funding	
  needs	
  of	
  the	
  Foundation	
  in	
  further	
  support	
  of	
  its	
  mission.	
  
	
  
	
  
4.0	
  Critical	
  Assumptions	
  and	
  Constraints	
  
For	
  the	
  purposes	
  of	
  planning,	
  what	
  future	
  events	
  or	
  factors	
  should	
  be	
  considered	
  to	
  be	
  true,	
  real	
  or	
  certain	
  that	
  are	
  
currently	
  not	
  fully	
  understood?	
  	
  	
  
Currently,	
  no	
  cruise	
  ship	
  exists	
  and	
  must	
  be	
  constructed	
  per	
  the	
  specification	
  of	
  the	
  sponsor,	
  Ms.	
  Corday,	
  and	
  the	
  
Foundation.	
  The	
  structure	
  of	
  the	
  vessel	
  must	
  be	
  completed	
  and	
  its	
  structural	
  integrity	
  approved	
  prior	
  to	
  the	
  construction	
  
of	
  the	
  Gift	
  Shops	
  within	
  the	
  interior	
  of	
  its	
  hull.	
  
	
  
Constraints:	
  What	
  are	
  the	
  some	
  of	
  the	
  most	
  important	
  known	
  limitations	
  to	
  the	
  options	
  available	
  to	
  the	
  project	
  team?	
  
Work	
  on	
  the	
  gift	
  shops	
  must	
  begin	
  after	
  the	
  completion	
  of	
  the	
  SCS	
  hull	
  and	
  super-­‐structure.	
  The	
  vessels	
  hull	
  must	
  be	
  
considered	
  sea-­‐worthy	
  and	
  approved	
  by	
  various	
  US	
  Government	
  Agencies	
  including	
  the	
  US	
  Coast	
  Guard	
  and	
  the	
  
American	
  Bureau	
  of	
  Shipping	
  prior	
  to	
  starting	
  the	
  construction	
  of	
  any	
  of	
  the	
  5	
  gift	
  shops.	
  	
  
	
  
	
  
5	
  	
  Page	
  	
  	
  	
  	
  	
  All	
  citations	
  are	
  from:	
  Project	
  Management	
  Institute.	
  (2013).	
  A	
  guide	
  to	
  the	
  project	
  management	
  body	
  
of	
  knowledge.	
  (5th	
  Ed.).	
  Newton	
  Square,	
  PA:	
  Author.	
  	
  
	
   	
  
01a	
  Initiation	
  Template:	
  	
  Business	
  Case	
  for	
  a	
  Proposed	
  Project	
  	
  
The	
  Business	
  Case	
  is	
  an	
  input	
  to	
  the	
  project	
  initiating	
  process	
  and	
  is	
  typically	
  prepared	
  by	
  the	
  “customer”.	
  
	
  
	
  
5.0	
  Analysis	
  of	
  Options	
  and	
  Recommendations	
  
Describe	
  the	
  alternative	
  approaches	
  that	
  could	
  be	
  used	
  to	
  meet	
  the	
  organizational	
  objective.	
  
The	
  gift	
  shops	
  project	
  can	
  begin	
  the	
  design	
  deliverables	
  phase	
  concurrent	
  to	
  the	
  trails	
  of	
  the	
  SCS	
  hull	
  and	
  super-­‐structure.	
  
Should	
  the	
  hull	
  structural	
  project	
  incur	
  delays	
  as	
  a	
  result	
  of	
  work	
  stoppage,	
  USCG,	
  or	
  ABS	
  approval	
  delays,	
  upon	
  approval	
  
of	
  the	
  gift	
  shops	
  designs,	
  the	
  gift	
  shops	
  structural	
  construction	
  can	
  begin	
  off-­‐site	
  and	
  be	
  completed	
  in	
  modular	
  sections	
  
allowing	
  them	
  to	
  be	
  installed	
  into	
  the	
  SCS’s	
  super-­‐structure	
  when	
  it	
  is	
  safe	
  to	
  do	
  so.	
  
	
  
	
  
6.0	
  Preliminary	
  Project	
  Requirements	
  
Provide	
  a	
  high	
  level	
  overview.	
  How	
  will	
  you	
  know	
  when	
  you	
  are	
  done?	
  	
  How	
  will	
  you	
  know	
  when	
  you	
  have	
  been	
  successful	
  
	
  
• Allow	
  ample	
  shopping	
  space	
  for	
  SCS	
  patrons,	
  
• Allow	
  ample	
  retail	
  space	
  for	
  merchandizing	
  fixtures,	
  refrigerated	
  coolers,	
  glass	
  jewelry	
  display	
  cases,	
  and	
  point	
  of	
  
sale	
  counters	
  for	
  all	
  gift	
  shops,	
  	
  
• Allow	
  more	
  than	
  the	
  minimum	
  required	
  points	
  of	
  egress	
  in	
  the	
  event	
  of	
  emergencies	
  for	
  all	
  gift	
  shops,	
  
• Procure	
  and	
  install	
  plumbing	
  and	
  fixtures	
  for	
  two	
  (2)	
  gender	
  specific	
  restrooms	
  in	
  the	
  main	
  gift	
  shop	
  and	
  one	
  (1)	
  
family	
  restroom	
  for	
  each	
  of	
  the	
  satellite	
  gift	
  shops,	
  
• Design	
  and	
  construct	
  and	
  install	
  at	
  least	
  two	
  (2)	
  fitting	
  rooms	
  in	
  the	
  main	
  gift	
  shop	
  and	
  one	
  (1)	
  fitting	
  room	
  for	
  
each	
  of	
  the	
  satellite	
  gift	
  shops,	
  
• Design	
  and	
  construct	
  the	
  main	
  gift	
  shop	
  with	
  enough	
  storage/stocking	
  space	
  and	
  administrative	
  office	
  space	
  to	
  
accommodate	
  all	
  gift	
  shops.	
  
7.0	
  Budget	
  Estimate	
  and	
  Financial	
  Analysis	
  
Project	
  Costs	
  
Estimate	
  key	
  project	
  costs	
  
What	
  will	
  you	
  have	
  to	
  purchase?	
  	
  Who	
  will	
  fund	
  the	
  project?	
  
The	
  majority	
  of	
  the	
  gift	
  shops	
  project	
  will	
  be	
  spent	
  in	
  both	
  labor	
  and	
  construction	
  materials	
  for	
  the	
  SCS	
  Gift	
  Shops	
  Project.	
  
	
  
The	
  budget	
  baseline	
  for	
  the	
  gift	
  shops	
  project	
  (minus	
  10%	
  contingency)	
  is	
  currently	
  $1,076,467.11	
  and	
  is	
  broken	
  down	
  
into	
  the	
  following	
  sub-­‐categories:	
  
	
  
Wages:	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  $197,219.76	
  -­‐	
  includes	
  estimates	
  for	
  overtime	
  and	
  various	
  fringes.	
  
Materials:	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  $836,187.35	
  -­‐	
  includes	
  estimates	
  for	
  structural,	
  interior,	
  and	
  exterior	
  construction	
  materials.	
  
Fixed	
  Costs:	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  $43,060	
  -­‐	
  includes	
  costs	
  associated	
  with	
  inspection	
  fees,	
  licensing,	
  material	
  storage	
  and	
  security,	
  
elevator	
  fabrication	
  and	
  freight	
  to	
  construction	
  site,	
  and	
  miscellaneous	
  expenses.	
  
10%	
  Contingency:	
  	
  $107,647.00	
  
GRAND	
  TOTAL:	
  	
  	
  	
  	
  	
  $	
  1,184,114.11	
  
	
  
The	
  Starve	
  No	
  More	
  foundation	
  is	
  financially	
  responsible	
  for	
  all	
  SCS	
  Gift	
  Shop	
  Project	
  related	
  costs	
  and	
  fees.	
  
	
  
8.0	
  Schedule	
  Estimate	
  
Provide	
  key	
  project	
  milestones	
  such	
  as	
  when	
  the	
  project	
  starts	
  and	
  ends	
  and	
  key	
  points	
  that	
  indicate	
  progress.	
  
Start	
  date:	
  Monday,	
  April	
  21
st
,	
  2014	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  End	
  Date:	
  Monday,	
  January	
  19
th
,	
  2015	
  
Key	
  milestones	
  include:	
  
6	
  	
  Page	
  	
  	
  	
  	
  	
  All	
  citations	
  are	
  from:	
  Project	
  Management	
  Institute.	
  (2013).	
  A	
  guide	
  to	
  the	
  project	
  management	
  body	
  
of	
  knowledge.	
  (5th	
  Ed.).	
  Newton	
  Square,	
  PA:	
  Author.	
  	
  
	
   	
  
01a	
  Initiation	
  Template:	
  	
  Business	
  Case	
  for	
  a	
  Proposed	
  Project	
  	
  
The	
  Business	
  Case	
  is	
  an	
  input	
  to	
  the	
  project	
  initiating	
  process	
  and	
  is	
  typically	
  prepared	
  by	
  the	
  “customer”.	
  
	
  
	
  
Project	
  Plan	
  Approval:	
  Friday,	
  May	
  2
nd
,	
  2014	
  
Gift	
  Shops	
  Design	
  Approval:	
  Tuesday,	
  July	
  8
th
,	
  2014	
  
Floor	
  plan,	
  Structural,	
  and	
  Utility	
  Drawings	
  Approval:	
  Wednesday,	
  October	
  1
st
,	
  2014	
  
Structural	
  Construction	
  Approval:	
  Friday,	
  December	
  26
th
,	
  2014	
  
Completed	
  Interiors	
  Approval:	
  Friday,	
  January	
  9
th
,	
  2015	
  
Completed	
  Exteriors	
  Approval:	
  Tuesday,	
  January	
  13
th
,	
  2015	
  
Final	
  Approval	
  and	
  Delivery	
  of	
  Gift	
  Shops:	
  Monday,	
  January	
  19
th
,	
  2015	
  
	
  
9.0	
  Potential	
  Risks	
  
What	
  events	
  might	
  occur	
  that	
  could	
  negatively	
  (or	
  positively)	
  impact	
  the	
  project	
  objectives	
  if	
  they	
  did	
  happen?	
  
	
  
• The	
  ship	
  hull,	
  or	
  super-­‐structure,	
  is	
  not	
  finished	
  before	
  the	
  scheduled	
  start	
  date	
  of	
  the	
  gift	
  shops	
  construction.	
  
	
  
• The	
  Starve	
  No	
  More	
  Foundation	
  runs	
  out	
  of	
  funds	
  before	
  the	
  Gift	
  Shops	
  Project	
  is	
  scheduled	
  to	
  start.	
  
	
  
• Approval	
  milestones	
  may	
  take	
  longer	
  than	
  anticipated.	
  
	
  
• Construction	
  and	
  final	
  approval	
  of	
  Gift	
  Shops	
  occurs	
  ahead	
  of	
  schedule.	
  
	
  
• The	
  Foundation	
  could	
  abandon	
  the	
  project	
  in	
  favor	
  of	
  procuring	
  a	
  cruise-­‐liner	
  to	
  refurbish	
  instead	
  of	
  design	
  and	
  
build.	
  
	
  
10.0	
  Financial	
  Analysis	
  
Evaluate	
  the	
  return	
  on	
  investment	
  for	
  the	
  proposed	
  project.	
  
The	
  SCS	
  Gift	
  Shops	
  will	
  provide	
  luxurious	
  amenities	
  and	
  feature	
  quality	
  custom	
  items	
  for	
  retail	
  purchase	
  of	
  the	
  SCS	
  
patrons	
  for	
  years	
  to	
  come.	
  The	
  profits	
  from	
  the	
  SCS	
  Gift	
  Shops	
  will	
  be	
  used	
  to	
  support	
  the	
  day-­‐to-­‐day	
  SCS	
  operating	
  costs	
  
as	
  well	
  as	
  the	
  funding	
  needs	
  of	
  the	
  Foundation	
  in	
  further	
  support	
  of	
  its	
  mission.	
  
	
  
The	
  5	
  Gift	
  Shops	
  of	
  the	
  SCS	
  will	
  be	
  designed	
  with	
  the	
  highest	
  quality	
  and	
  amenities	
  to	
  attract	
  patrons	
  who	
  are	
  conscience	
  
of	
  the	
  Starve	
  No	
  More	
  Foundations	
  mission	
  statement.	
  With	
  the	
  on-­‐going	
  patronage	
  of	
  the	
  SCS	
  patrons,	
  the	
  Foundation	
  
can	
  expect	
  to	
  see	
  a	
  15%	
  -­‐	
  25%	
  ROI	
  within	
  5	
  –	
  10	
  years	
  of	
  receipt	
  of	
  completed	
  and	
  approved	
  gift	
  shops.	
  	
  
	
  
	
  
	
  
	
  
	
  
7	
  	
  Page	
  	
  	
  	
  	
  	
  All	
  citations	
  are	
  from:	
  Project	
  Management	
  Institute.	
  (2013).	
  A	
  guide	
  to	
  the	
  project	
  management	
  body	
  
of	
  knowledge.	
  (5th	
  Ed.).	
  Newton	
  Square,	
  PA:	
  Author.	
  	
  
	
   	
  
Initiating	
  Integration	
  Element	
  	
  (PRM600-­‐	
  	
  Complete	
  all	
  items	
  in	
  the	
  project	
  charter).	
  	
  
	
  
4.1a	
  Project	
  Charter	
  
The	
  Project	
  Charter	
  formally	
  authorizes	
  a	
  project	
  or	
  project	
  phase	
  and	
  documents	
  initial	
  requirements.	
  Multiple	
  
charters	
  may	
  be	
  used	
  to	
  validate	
  or	
  refine	
  decisions	
  made	
  for	
  multi-­‐phase	
  projects.	
  
	
  
Business	
  Need	
  /	
  Who	
  Will	
  Benefit:	
  
What	
  events	
  or	
  conditions	
  helped	
  create	
  the	
  need	
  for	
  this	
  project?	
  Who	
  will	
  benefit	
  from	
  this	
  endeavor?	
  
In	
  a	
  proactive	
  attempt	
  to	
  prevent	
  the	
  Foundation’s	
  imminent	
  insolvency,	
  Ms.	
  Corday	
  strongly	
  desires	
  the	
  legacy	
  of	
  her	
  
and	
  her	
  family’s	
  hard	
  work	
  to	
  be	
  nationally	
  recognized	
  by	
  an	
  unprecedented	
  undertaking:	
  the	
  building	
  of	
  a	
  privately	
  
owned	
  and	
  operated	
  pleasure	
  cruise	
  line,	
  the	
  Swimlane	
  Cruise	
  Ship,	
  which	
  will	
  continue	
  to	
  raise	
  funds	
  to	
  support	
  the	
  
mission	
  of	
  the	
  Foundation	
  for	
  the	
  foreseeable	
  future.	
  
	
  
Project	
  Purpose	
  /	
  Justification	
  –	
  Alignment	
  with	
  Mission	
  
Why	
  is	
  the	
  project	
  being	
  approved?	
  	
  How	
  does	
  it	
  align	
  with	
  the	
  organization’s	
  mission	
  or	
  strategic	
  plan?	
  
This	
  Charter	
  formally	
  authorizes	
  a	
  project	
  to	
  perform	
  the	
  research,	
  development	
  and	
  implementation	
  of	
  the	
  design	
  and	
  
production	
  of	
  a	
  Swimlane	
  Cruise	
  Ship	
  (SCS)	
  with	
  its	
  sole	
  purpose	
  to	
  raise	
  funds	
  to	
  help	
  feed	
  starving	
  families	
  around	
  the	
  
world.	
  
	
  
Project	
  Objectives	
  	
  
What	
  will	
  the	
  project	
  produce?	
  How	
  will	
  we	
  know	
  that	
  the	
  project	
  objectives	
  have	
  been	
  successfully	
  accomplished?	
  
	
  
This	
  project	
  will	
  produce:	
  	
  
	
  
1)	
  Designs	
  for	
  a	
  total	
  of	
  five	
  (5)	
  SCS	
  Gift	
  Shops.	
  
2)	
  A	
  total	
  of	
  ten	
  (10)	
  unique	
  artistic	
  renderings	
  and	
  perspective	
  drawings	
  of	
  each	
  of	
  the	
  five	
  (5)	
  Gift	
  Shops	
  for	
  
Foundation	
  approval.	
  
3)	
  Floor	
  plans,	
  structural	
  blue	
  prints,	
  construction	
  plans	
  and	
  bill	
  of	
  materials,	
  and	
  utility	
  drawings	
  for	
  each	
  of	
  the	
  five	
  (5)	
  
Gift	
  Shops	
  for	
  Foundation	
  approval.	
  
4)	
  Constructed	
  five	
  (5)	
  Gift	
  Shops	
  in	
  accordance	
  to	
  the	
  approval	
  guidelines	
  of	
  the	
  Foundation.	
  
5)	
  Project	
  management	
  services	
  throughout	
  the	
  planning,	
  design,	
  and	
  construction	
  phases	
  of	
  the	
  SCS	
  Gift	
  Shops	
  project.	
  	
  
	
  
The	
  following	
  success	
  criteria	
  will	
  be	
  used	
  to	
  demonstrate	
  accomplished	
  objectives.	
  
• Provide	
  ten	
  (10)	
  unique	
  artistic	
  renderings,	
  including	
  perspective	
  drawings	
  that	
  depict	
  all	
  five	
  (5)	
  gift	
  shops	
  in	
  
use,	
  which	
  will	
  specifically	
  demonstrate	
  design	
  elements	
  of	
  both	
  interiors	
  and	
  exteriors	
  of	
  each	
  gift	
  shop.	
  
• Design	
  one	
  (1)	
  rectangular-­‐shaped,	
  centralized,	
  two-­‐level,	
  4500	
  sq.	
  ft.	
  main	
  gift	
  shop	
  with	
  an	
  ‘open	
  atrium’	
  
(looking	
  down	
  to	
  the	
  first	
  floor)	
  second	
  level	
  with	
  one	
  (1)	
  single	
  landing	
  stair	
  case	
  on	
  the	
  north	
  side	
  and	
  one	
  (1)	
  
eight	
  (8)	
  person	
  capacity	
  hydraulic	
  elevator	
  on	
  the	
  south	
  side.	
  
• Design	
  the	
  remaining	
  four	
  (4)	
  oval-­‐shaped,	
  single-­‐level,	
  1500	
  sq	
  ft.	
  satellite	
  gift	
  shops.	
  
• Provide	
  an	
  “open	
  air”	
  access	
  design	
  of	
  the	
  main	
  gift	
  shop,	
  with	
  multiple	
  entrances	
  into	
  the	
  first	
  floor	
  of	
  no	
  less	
  
than	
  20	
  feet	
  per	
  entrance	
  on	
  all	
  four	
  sides.	
  	
  
• Provide	
  an	
  “open	
  air”	
  access	
  design	
  of	
  the	
  satellite	
  gift	
  shops,	
  with	
  one	
  (1)	
  entrance	
  of	
  no	
  less	
  than	
  15	
  feet	
  on	
  
only	
  one	
  side	
  per	
  gift	
  shop.	
  
• Provide	
  motorized,	
  concealable,	
  and	
  recessed	
  security	
  roll-­‐up	
  doors	
  for	
  all	
  entranceways	
  for	
  each	
  gift	
  shop	
  
using	
  durable,	
  transparent,	
  and	
  scratch-­‐resistant	
  materials.	
  Each	
  door	
  should	
  be	
  able	
  to	
  be	
  locally	
  and	
  
remotely	
  operated.	
  
• Provide	
  no	
  less	
  than	
  500	
  sq	
  ft.	
  of	
  concealable	
  stocking	
  space	
  within	
  the	
  main	
  gift	
  shop,	
  and	
  no	
  less	
  than	
  100	
  sq	
  
ft.	
  of	
  concealable	
  stocking	
  space	
  within	
  the	
  satellite	
  gift	
  shops.	
  	
  
• Provide	
  no	
  less	
  than	
  300	
  sq	
  ft.	
  of	
  administrative	
  office	
  space	
  within	
  the	
  centralized	
  gift	
  shop.	
  
• Provide	
  two	
  (2)	
  gender	
  specific,	
  120	
  sq	
  ft.,	
  single	
  stall	
  restrooms	
  within	
  the	
  main	
  gift	
  shop	
  and	
  one	
  (1)	
  single	
  
8	
  	
  Page	
  	
  	
  	
  	
  	
  All	
  citations	
  are	
  from:	
  Project	
  Management	
  Institute.	
  (2013).	
  A	
  guide	
  to	
  the	
  project	
  management	
  body	
  
of	
  knowledge.	
  (5th	
  Ed.).	
  Newton	
  Square,	
  PA:	
  Author.	
  	
  
	
   	
  
4.1a	
  Project	
  Charter	
  
The	
  Project	
  Charter	
  formally	
  authorizes	
  a	
  project	
  or	
  project	
  phase	
  and	
  documents	
  initial	
  requirements.	
  Multiple	
  
charters	
  may	
  be	
  used	
  to	
  validate	
  or	
  refine	
  decisions	
  made	
  for	
  multi-­‐phase	
  projects.	
  
	
  
fixture,	
  80	
  sq	
  ft.	
  family	
  restroom	
  within	
  each	
  of	
  the	
  satellite	
  gift	
  shops.	
  
• Provide	
  two	
  (2)	
  changing	
  rooms	
  within	
  the	
  main	
  gift	
  shop	
  and	
  one	
  (1)	
  changing	
  room	
  within	
  each	
  of	
  the	
  
satellite	
  gift	
  shops.	
  No	
  changing	
  room	
  should	
  exceed	
  15	
  sq	
  ft.	
  
• Provide	
  enough	
  area	
  to	
  accommodate	
  various	
  merchandizing	
  fixtures	
  for	
  all	
  gift	
  shops,	
  including	
  refrigerated	
  
coolers,	
  jewelry	
  display	
  cases,	
  apparel	
  racks,	
  wall	
  and	
  floor	
  rack	
  shelving,	
  and	
  miscellaneous	
  counter	
  tops.	
  
• Provide	
  enough	
  area	
  to	
  accommodate	
  one	
  (1)	
  100	
  sq	
  ft.	
  circular	
  point	
  of	
  sale	
  (POS)	
  counter	
  in	
  each	
  gift	
  shop.	
  
The	
  POS	
  counter	
  will	
  be	
  located	
  in	
  the	
  center	
  of	
  the	
  first	
  floor	
  of	
  the	
  main	
  gift	
  shop	
  and	
  within	
  the	
  center	
  of	
  all	
  
of	
  the	
  satellite	
  gift	
  shops.	
  
• Provide	
  detailed	
  blue	
  prints	
  and	
  construction	
  plans	
  for	
  all	
  five	
  (5)	
  gift	
  shops.	
  
• Construct	
  all	
  gift	
  shops	
  utilizing	
  best	
  practices	
  of	
  retail	
  and	
  maritime	
  construction	
  techniques.	
  
• Provide	
  finishing	
  construction	
  (carpeting,	
  paint,	
  accents,	
  fixtures,	
  etc.)	
  work	
  upon	
  completion	
  of	
  structural	
  
construction	
  in	
  accordance	
  to	
  the	
  approval	
  guidelines	
  of	
  the	
  Foundation.	
  
• Project	
  Management	
  services	
  must	
  be	
  conducted	
  using	
  PMI	
  methodologies	
  incorporating	
  monthly	
  status	
  
report	
  meetings.	
  
Approved	
  Budget:	
  	
  (See	
  detailed	
  Funding	
  Request)	
  	
  $	
  1,184,114.11	
  
How	
  much	
  will	
  the	
  project	
  cost?	
  How	
  much	
  spending	
  should	
  be	
  authorized	
  on	
  this	
  project?	
  	
  	
  	
  	
  
	
  
The	
  budget	
  baseline	
  for	
  the	
  gift	
  shops	
  project	
  (minus	
  10%	
  contingency)	
  is	
  currently	
  $1,076,467.11	
  and	
  is	
  broken	
  down	
  
into	
  the	
  following	
  sub-­‐categories:	
  
	
  
Wages:	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  $197,219.76	
  -­‐	
  includes	
  estimates	
  for	
  overtime	
  and	
  various	
  fringes.	
  
Materials:	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  $836,187.35	
  -­‐	
  includes	
  estimates	
  for	
  structural,	
  interior,	
  and	
  exterior	
  construction	
  materials.	
  
Fixed	
  Costs:	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  $43,060	
  -­‐	
  includes	
  costs	
  associated	
  with	
  inspection	
  fees,	
  licensing,	
  material	
  storage	
  and	
  security,	
  
elevator	
  fabrication	
  and	
  freight	
  to	
  construction	
  site,	
  and	
  miscellaneous	
  expenses.	
  
10%	
  Contingency:	
  	
  $107,647.00	
  
GRAND	
  TOTAL:	
  	
  	
  	
  	
  	
  $	
  1,184,114.11	
  
	
  
Project	
  Milestones	
  	
  	
  
When	
  will	
  key	
  events	
  happen?	
  What	
  deadlines	
  are	
  known?	
  How	
  will	
  we	
  know	
  progress	
  is	
  being	
  made?	
  
	
  
Project	
  Start:	
  Monday,	
  April	
  21
st
,	
  2014	
  
Project	
  Plan	
  Approval:	
  Friday,	
  May	
  2
nd
,	
  2014	
  
Gift	
  Shops	
  Design	
  Approval:	
  Tuesday,	
  July	
  8
th
,	
  2014	
  
Floor	
  plan,	
  Structural,	
  and	
  Utility	
  Drawings	
  Approval:	
  Wednesday,	
  October	
  1
st
,	
  2014	
  
Structural	
  Construction	
  Approval:	
  Friday,	
  December	
  26
th
,	
  2014	
  
Completed	
  Interiors	
  Approval:	
  Friday,	
  January	
  9
th
,	
  2015	
  
Completed	
  Exteriors	
  Approval:	
  Tuesday,	
  January	
  13
th
,	
  2015	
  
Final	
  Approval	
  and	
  Delivery	
  of	
  Gift	
  Shops:	
  Monday,	
  January	
  19
th
,	
  2015	
  
	
  
	
  
	
  
	
  
	
  
	
  
	
  
	
  
9	
  	
  Page	
  	
  	
  	
  	
  	
  All	
  citations	
  are	
  from:	
  Project	
  Management	
  Institute.	
  (2013).	
  A	
  guide	
  to	
  the	
  project	
  management	
  body	
  
of	
  knowledge.	
  (5th	
  Ed.).	
  Newton	
  Square,	
  PA:	
  Author.	
  	
  
	
   	
  
4.1a	
  Project	
  Charter	
  
The	
  Project	
  Charter	
  formally	
  authorizes	
  a	
  project	
  or	
  project	
  phase	
  and	
  documents	
  initial	
  requirements.	
  Multiple	
  
charters	
  may	
  be	
  used	
  to	
  validate	
  or	
  refine	
  decisions	
  made	
  for	
  multi-­‐phase	
  projects.	
  
	
  
Constraints:	
  
What	
  are	
  the	
  known	
  limitations	
  to	
  the	
  options	
  available	
  to	
  the	
  project	
  team?	
  
	
  
Currently,	
  no	
  cruise	
  ship	
  exists	
  and	
  must	
  be	
  constructed	
  per	
  the	
  specification	
  of	
  the	
  sponsor,	
  Ms.	
  Corday,	
  and	
  the	
  
Foundation.	
  The	
  structure	
  of	
  the	
  vessel	
  must	
  be	
  completed	
  and	
  its	
  structural	
  integrity	
  approved	
  prior	
  to	
  the	
  
construction	
  of	
  the	
  Gift	
  Shops	
  within	
  the	
  interior	
  of	
  its	
  hull.	
  
	
  
Work	
  on	
  the	
  gift	
  shops	
  must	
  begin	
  after	
  the	
  completion	
  of	
  the	
  SCS	
  hull	
  and	
  super-­‐structure.	
  The	
  vessels	
  hull	
  must	
  be	
  
considered	
  sea-­‐worthy	
  and	
  approved	
  by	
  various	
  US	
  Government	
  Agencies	
  including	
  the	
  US	
  Coast	
  Guard	
  and	
  the	
  
American	
  Bureau	
  of	
  Shipping	
  prior	
  to	
  starting	
  the	
  construction	
  of	
  any	
  of	
  the	
  5	
  gift	
  shops.	
  
	
  
This	
  is	
  the	
  first	
  large-­‐scale,	
  long-­‐term	
  project	
  of	
  its	
  kind	
  for	
  the	
  project	
  sponsor,	
  Ms.	
  Corday	
  and	
  the	
  Starve	
  No	
  More	
  
Foundation.	
  Currently,	
  this	
  project	
  also	
  represents	
  the	
  first	
  maritime	
  construction	
  project	
  for	
  the	
  Foundation	
  and	
  as	
  
such,	
  contractors	
  will	
  need	
  to	
  rely	
  heavily	
  on	
  experienced	
  shipbuilder’s	
  expert	
  judgment	
  during	
  the	
  all	
  phases	
  of	
  the	
  
ship	
  build.	
  
Assumptions:	
  
For	
  the	
  purposes	
  of	
  planning,	
  what	
  uncertain	
  factors	
  will	
  be	
  considered	
  to	
  be	
  true,	
  real	
  or	
  certain?	
  	
  	
  
	
  
The	
  gift	
  shops	
  project	
  can	
  begin	
  the	
  Design	
  deliverables	
  phase	
  concurrent	
  to	
  the	
  trails	
  of	
  the	
  SCS	
  hull	
  and	
  super-­‐
structure.	
  Should	
  the	
  hull	
  structural	
  project	
  incur	
  delays	
  as	
  a	
  result	
  of	
  work	
  stoppage,	
  USCG,	
  or	
  ABS	
  mandates,	
  upon	
  
approval	
  of	
  the	
  gift	
  shops	
  designs,	
  the	
  gift	
  shops	
  structural	
  construction	
  can	
  begin	
  off-­‐site	
  and	
  be	
  completed	
  in	
  modular	
  
sections	
  allowing	
  them	
  to	
  be	
  installed	
  into	
  the	
  SCS’s	
  super-­‐structure	
  when	
  it	
  is	
  safe	
  to	
  do	
  so.	
  
	
  
Roles	
  
Who	
  is/	
  will	
  be	
  assigned	
  to	
  manage?	
  	
  What	
  are	
  they	
  authorized	
  to	
  approve	
  for	
  spending,	
  leading,	
  etc?	
  
	
  
Project	
  Manager:	
  Jerry	
  P.	
  Magaña	
  
	
  	
  	
  	
  	
  	
  
Authority	
  level:	
  	
  
Budget:	
  The	
  project	
  manager	
  is	
  authorized	
  to	
  distribute	
  funds	
  for	
  equipment,	
  fees,	
  construction	
  materials,	
  and	
  other	
  
related	
  expenses	
  to	
  the	
  current	
  baselined	
  amount	
  of	
  $879,247.35	
  
	
  
The	
  Organization’s	
  accounting	
  and	
  payroll	
  department	
  will	
  distribute	
  and	
  account	
  for	
  wages	
  applied	
  to	
  the	
  project,	
  
currently	
  estimated	
  not	
  to	
  exceed	
  $197,219.76.	
  	
  
	
  
The	
  project	
  manager	
  may	
  not	
  exceed	
  the	
  approved	
  baselined	
  amount	
  of	
  $879,247.35	
  by	
  no	
  more	
  than	
  3%	
  for	
  needs	
  
that	
  arise	
  as	
  a	
  result	
  of	
  unforeseen	
  circumstances	
  (or	
  contingency).	
  If	
  an	
  increase	
  it	
  required,	
  the	
  Project	
  Manager	
  will	
  
notify	
  the	
  project	
  sponsor,	
  Mr.	
  Horvatt	
  and	
  the	
  appropriate	
  project	
  stakeholders	
  prior	
  to	
  the	
  decision	
  to	
  release	
  
additional	
  contingency	
  funds.	
  If	
  the	
  Project	
  Manager	
  foresees	
  costs	
  exceeding	
  3%	
  over	
  the	
  current	
  baselined	
  budget,	
  
the	
  cause	
  will	
  need	
  to	
  be	
  presented	
  and	
  approved	
  by	
  the	
  project	
  sponsor.	
  	
  
	
  
Staffing:	
  The	
  project	
  manager	
  is	
  responsible	
  for	
  the	
  hiring	
  of	
  key	
  construction,	
  design,	
  and	
  engineering	
  staff.	
  These	
  key	
  
staff	
  members	
  will	
  be	
  responsible	
  the	
  hiring	
  and	
  direction	
  of	
  the	
  required	
  crew	
  necessary	
  for	
  completing	
  the	
  project	
  
sponsors	
  approved	
  design	
  and	
  construction	
  plans	
  for	
  the	
  SCS	
  Gift	
  Shops.	
  
	
  
Communication:	
  The	
  project	
  manager	
  is	
  required	
  to	
  review	
  and	
  advise	
  the	
  project	
  sponsor,	
  Ms.	
  Corday,	
  the	
  Board	
  of	
  
Directors	
  of	
  the	
  Starve	
  No	
  More	
  Foundation,	
  and	
  key	
  project	
  stakeholders	
  on	
  the	
  status	
  of	
  the	
  SCS	
  Gift	
  Shops	
  Project	
  on	
  
a	
  monthly	
  basis	
  throughout	
  the	
  duration	
  of	
  the	
  project.	
  
	
  
These	
  monthly	
  progress	
  meetings	
  will	
  take	
  place	
  on	
  the	
  first	
  Thursday	
  of	
  each	
  month	
  and	
  the	
  written	
  minutes	
  of	
  each	
  
status	
  report	
  are	
  due	
  no	
  later	
  than	
  the	
  following	
  Monday	
  via	
  email.	
  
10	
  	
  Page	
  	
  	
  	
  	
  	
  All	
  citations	
  are	
  from:	
  Project	
  Management	
  Institute.	
  (2013).	
  A	
  guide	
  to	
  the	
  project	
  management	
  body	
  
of	
  knowledge.	
  (5th	
  Ed.).	
  Newton	
  Square,	
  PA:	
  Author.	
  	
  
	
   	
  
4.1a	
  Project	
  Charter	
  
The	
  Project	
  Charter	
  formally	
  authorizes	
  a	
  project	
  or	
  project	
  phase	
  and	
  documents	
  initial	
  requirements.	
  Multiple	
  
charters	
  may	
  be	
  used	
  to	
  validate	
  or	
  refine	
  decisions	
  made	
  for	
  multi-­‐phase	
  projects.	
  
	
  
	
  
Change	
  Control:	
  Project	
  managers	
  are	
  in	
  charge	
  of	
  communicating	
  any	
  changes	
  made	
  to	
  the	
  project	
  to	
  the	
  project	
  
sponsor.	
  	
  Project	
  managers	
  are	
  allowed	
  to	
  make	
  changes	
  as	
  long	
  as	
  they	
  do	
  not	
  exceed	
  1%	
  of	
  the	
  allocated	
  budget	
  and	
  
do	
  not	
  push	
  a	
  deadline	
  over	
  10	
  days.	
  	
  Any	
  changes	
  outside	
  these	
  limitations	
  need	
  to	
  be	
  reviewed	
  and	
  approved	
  by	
  the	
  
project	
  sponsor.	
  
	
  
OPA	
  	
  Organizational	
  process	
  assets	
  	
  	
  
What	
  artifacts	
  from	
  the	
  organization	
  or	
  outside	
  could	
  be	
  useful	
  in	
  our	
  planning	
  process,	
  including	
  lessons	
  learned	
  on	
  
past	
  projects?	
  
	
  
• The	
  Organization’s	
  database	
  of	
  previously	
  used	
  and	
  approved	
  vendors	
  for	
  both	
  human	
  resources	
  in	
  various	
  
construction	
  trade	
  and	
  materials.	
  
• The	
  Organization’s	
  knowledge	
  base	
  of	
  previous	
  experience	
  working	
  with	
  non-­‐profit	
  entities	
  and	
  their	
  projects.	
  
• The	
  Organization’s	
  knowledge	
  base	
  of	
  planning,	
  lessons	
  learned,	
  and	
  previously	
  used	
  experiences	
  of	
  pleasure	
  
cruise	
  liner	
  and	
  other	
  maritime	
  construction	
  projects.	
  
• The	
  Organization’s	
  connections	
  to	
  and	
  understanding	
  of	
  various	
  approval	
  authorities	
  for	
  similar	
  construction	
  
projects	
  including	
  the	
  United	
  States	
  Coast	
  Guard	
  and	
  the	
  American	
  Bureau	
  of	
  Shipping.	
  
• The	
  Organization’s	
  policies	
  and	
  procedures	
  in	
  regards	
  to	
  working	
  with	
  non-­‐profit	
  projects.	
  
• The	
  Organization’s	
  expertise	
  within	
  engineering,	
  construction,	
  design,	
  and	
  staffing	
  similar	
  large-­‐scale	
  maritime	
  
construction	
  projects.	
  	
  
	
  
	
  
EEF	
  	
  	
  Enterprise	
  Environmental	
  Factors	
  	
  	
  	
  
What	
  external	
  factors	
  impact	
  our	
  planning?	
  From	
  what	
  sources	
  were	
  these	
  EEFs	
  gathered?	
  	
  
	
  
• The	
  Organization	
  requires	
  the	
  use	
  of	
  skilled	
  and	
  experienced	
  maritime	
  construction	
  trade	
  persons	
  to	
  undertake	
  
such	
  an	
  endeavor.	
  
• The	
  Organization	
  is	
  relying	
  exclusively	
  on	
  the	
  good	
  faith	
  of	
  the	
  Foundation	
  to	
  provide	
  the	
  financial	
  support	
  of	
  
the	
  project.	
  
• The	
  Organization	
  understands	
  that	
  the	
  Foundation	
  for	
  which	
  the	
  work	
  is	
  to	
  be	
  performed	
  has	
  little	
  to	
  no	
  
experience	
  in	
  such	
  large-­‐scale	
  projects,	
  and	
  non	
  with	
  respect	
  to	
  maritime	
  construction.	
  
• The	
  maritime	
  nature	
  of	
  the	
  project	
  is	
  subject	
  to	
  frequent	
  inclement	
  weather	
  delays.	
  
• The	
  nature	
  of	
  the	
  project	
  being	
  construction	
  is	
  subject	
  to	
  labor	
  union	
  staffing	
  and	
  as	
  such,	
  may	
  impose	
  a	
  work	
  
stoppage	
  as	
  a	
  result	
  of	
  a	
  contract	
  dispute.	
  
• The	
  success	
  of	
  the	
  Gift	
  Shops	
  project	
  relies	
  on	
  the	
  performance	
  of	
  other	
  entities	
  that	
  the	
  Foundation	
  (Sponsor)	
  
has	
  contracted	
  with;	
  ie:	
  hull	
  and	
  super-­‐structure	
  construction,	
  fixtures,	
  décor,	
  etc.	
  
	
  
	
  
	
  
Risks	
  	
  	
  	
  
What	
  are	
  the	
  potential	
  threats	
  and	
  opportunities?	
  What	
  uncertain	
  future	
  events	
  could	
  impact	
  the	
  project	
  if	
  they	
  did	
  
happen?	
  
	
  
• The	
  ship	
  hull,	
  or	
  super-­‐structure,	
  is	
  not	
  finished	
  before	
  the	
  scheduled	
  start	
  date	
  of	
  the	
  gift	
  shops	
  construction.	
  
	
  
• The	
  Starve	
  No	
  More	
  Foundation	
  runs	
  out	
  of	
  funds	
  before	
  the	
  Gift	
  Shops	
  Project	
  is	
  scheduled	
  to	
  start.	
  
	
  
• Approval	
  milestones	
  may	
  take	
  longer	
  than	
  anticipated.	
  
	
  
• Construction	
  and	
  final	
  approval	
  of	
  Gift	
  Shops	
  occurs	
  ahead	
  of	
  schedule.	
  
11	
  	
  Page	
  	
  	
  	
  	
  	
  All	
  citations	
  are	
  from:	
  Project	
  Management	
  Institute.	
  (2013).	
  A	
  guide	
  to	
  the	
  project	
  management	
  body	
  
of	
  knowledge.	
  (5th	
  Ed.).	
  Newton	
  Square,	
  PA:	
  Author.	
  	
  
	
   	
  
4.1a	
  Project	
  Charter	
  
The	
  Project	
  Charter	
  formally	
  authorizes	
  a	
  project	
  or	
  project	
  phase	
  and	
  documents	
  initial	
  requirements.	
  Multiple	
  
charters	
  may	
  be	
  used	
  to	
  validate	
  or	
  refine	
  decisions	
  made	
  for	
  multi-­‐phase	
  projects.	
  
	
  
RISKS	
  (CONTINUED)	
  
	
  
• The	
  Foundation	
  could	
  abandon	
  the	
  project	
  in	
  favor	
  of	
  procuring	
  a	
  cruise-­‐liner	
  to	
  refurbish	
  instead	
  of	
  design	
  
and	
  build.	
  
	
  
	
  
Initiating	
  Communication	
  Element	
  (PRM600	
  –	
  Create	
  at	
  least	
  8	
  rows	
  of	
  stakeholders).	
  
	
  
13.1	
  a.	
  Stakeholder	
  Register	
  and	
  Stakeholder	
  Strategy	
  
The	
  stakeholder	
  register	
  identifies	
  the	
  stakeholder	
  groups	
  and	
  analyzes	
  their	
  influence	
  and	
  interest	
  in	
  the	
  project,	
  
which	
  allows	
  them	
  to	
  be	
  classified	
  into	
  categories	
  so	
  that	
  appropriate	
  strategies	
  can	
  be	
  defined	
  for	
  each	
  category	
  of	
  
stakeholders.	
  	
  
Name	
  	
  
	
  
Include	
  the	
  title	
  or	
  
name	
  of	
  the	
  group	
  or	
  
Individual	
  	
  
Category	
  
A,	
  B,	
  	
  	
  	
  	
  	
  	
  	
  
	
  C	
  or	
  D?	
  
(See	
  
matrix)	
  	
  
Interest	
  in	
  the	
  Project	
  
(High	
  or	
  Low)	
  
What	
  makes	
  them	
  a	
  
stakeholder?	
  Are	
  they	
  impacted	
  
or	
  do	
  they	
  impact	
  the	
  project?	
  
Will	
  they	
  be	
  users	
  of	
  the	
  project	
  
deliverables?	
  Are	
  they	
  directly	
  or	
  
tangentially	
  interested?	
  
Influence	
  on	
  the	
  Project	
  
(High	
  or	
  Low)	
  
What	
  power	
  or	
  influence	
  on	
  the	
  
project	
  could	
  this	
  group	
  generate?	
  	
  
Do	
  they	
  create	
  or	
  assess	
  
deliverables?	
  Are	
  they	
  financially	
  
committed?	
  	
  
	
  
Mr.	
  Dennis	
  Horvatt,	
  
Pres.	
  Of	
  Const.	
  TFSB	
  
Const.,	
  Inc.,	
  Project	
  
Sponsor	
  
A	
   High	
   High	
   	
  
Ms.	
  Marie	
  Corday,	
  
Customer	
  
	
  
A	
  
	
  
High	
  
	
  
High	
  
	
  
	
  
Board	
  of	
  Directors,	
  
Starve	
  No	
  More	
  
Foundation,	
  Customer	
  
A	
   High	
   High	
   	
  
United	
  States	
  Coast	
  
Guard	
  (USCG)	
  
C	
   Low	
   High	
   	
  
American	
  Bureau	
  of	
  
Shipping	
  (ABS)	
  
C	
   Low	
   High	
   	
  
Project	
  Management	
  
Team	
  
B	
   High	
   Low	
   	
  
Construction	
  
Foreperson	
  
B	
   High	
   Low	
   	
  
Interior	
  Design	
  
Manager	
  
B	
   High	
   Low	
   	
  
Construction	
  Material	
  
Vendors	
  
D	
   Low	
   Low	
   	
  
12	
  	
  Page	
  	
  	
  	
  	
  	
  All	
  citations	
  are	
  from:	
  Project	
  Management	
  Institute.	
  (2013).	
  A	
  guide	
  to	
  the	
  project	
  management	
  body	
  
of	
  knowledge.	
  (5th	
  Ed.).	
  Newton	
  Square,	
  PA:	
  Author.	
  	
  
	
   	
  
Construction	
  
Inspectors	
  
D	
   Low	
   Low	
   	
  
Port	
  Master	
   D	
   Low	
   Low	
   	
  
SCS	
  Patrons	
   D	
   Low	
   Low	
   	
  
Organization’s	
  Chief	
  
Engineer	
  
C	
   Low	
   High	
   	
  
	
  
Initiating	
  Communication	
  Element	
  	
  (PRM600-­‐	
  Complete	
  all	
  items).	
  	
  
13.1	
  b.	
  Stakeholder	
  Communication	
  Strategies	
  	
  
Communications	
  strategies	
  must	
  be	
  identified	
  for	
  each	
  stakeholder	
  category	
  to	
  increase	
  the	
  support	
  and	
  minimize	
  
the	
  negative	
  impacts	
  of	
  stakeholders	
  throughout	
  the	
  entire	
  life	
  cycle	
  of	
  the	
  project.	
  	
  	
  
	
  
Name	
  	
  
	
  
List	
  the	
  key	
  groups	
  
in	
  each	
  	
  category	
  of	
  
stakeholders	
  
	
   Strategies	
  for	
  Gathering	
  
Support	
  
What	
  will	
  you	
  do	
  to	
  
encourage	
  positive	
  
influences	
  from	
  them?	
  
Strategies	
  for	
  Reducing	
  
Obstacles	
  
	
  
What	
  will	
  you	
  do	
  to	
  reduce	
  
negative	
  influences	
  from	
  
them?	
  
Expectations	
  
	
  
What	
  does	
  this	
  group	
  
expect	
  from	
  you	
  for	
  
communications,	
  
support,	
  etc.	
  
A-­‐High	
  Interest	
  and	
  
High	
  Influence	
  
1.	
  Mr.	
  Dennis	
  
Horvatt,	
  Pres.	
  Of	
  
Const.	
  TFSB	
  Const.,	
  
Inc.,	
  Proj.	
  Sponsor	
  
2.	
  Ms.	
  Marie	
  
Corday,	
  Customer	
  
3.	
  Board	
  of	
  
Directors,	
  Starve	
  No	
  
More	
  Foundation,	
  
Customer	
  
	
   Manage	
  Closely	
  
Closely	
  monitor	
  and	
  relay	
  
information	
  as	
  it	
  develops.	
  
Be	
  transparent	
  with	
  project	
  
related	
  activities	
  and	
  
expenses.	
  Encourage	
  
efficient	
  and	
  clear	
  
presentation	
  of	
  all	
  
correspondences.	
  
	
  
Remain	
  transparent	
  on	
  
project	
  budget	
  issues;	
  
provide	
  interior	
  design	
  
samples,	
  create	
  and	
  foster	
  
an	
  open	
  channel	
  of	
  
communication	
  between	
  
these	
  stakeholders	
  and	
  key	
  
project	
  personnel.	
  	
  
	
  
Timeliness	
  of	
  all	
  
important	
  reports	
  or	
  
project-­‐related	
  events	
  
and	
  milestones.	
  
Provide	
  monthly	
  status	
  
reports	
  of	
  the	
  project	
  
that	
  will	
  take	
  place	
  on	
  
the	
  first	
  Thursday	
  of	
  
each	
  month,	
  then	
  email	
  
the	
  typed	
  minutes	
  of	
  
each	
  status	
  meeting	
  no	
  
later	
  than	
  the	
  following	
  
Monday.	
  
	
  
B-­‐High	
  Interest	
  but	
  
low	
  influence	
  
1.	
  Project	
  
Management	
  Team	
  
2.	
  Construction	
  
Foreperson	
  
	
  
	
   Keep	
  Informed	
  
Stay	
  organized,	
  but	
  avoid	
  
information	
  overload.	
  
Provide	
  relevant	
  project	
  
materials	
  required	
  for	
  
feedback	
  and	
  approval	
  only.	
  
Keep	
  reports	
  concise	
  and	
  at	
  
a	
  level	
  of	
  detail	
  that	
  can	
  be	
  
considered	
  ‘snapshots.’	
  
	
  
Verify	
  activities	
  and	
  
resources	
  required	
  to	
  
achieve	
  project	
  
requirements.	
  Advise	
  on	
  
changes	
  to	
  these	
  
requirements	
  as	
  soon	
  as	
  
possible.	
  Meet	
  project	
  
deadlines	
  and	
  milestones	
  
as	
  indicated,	
  take	
  
responsibility	
  and	
  avoid	
  
assigning	
  blame.	
  
	
  
Inform	
  about	
  major	
  
events	
  or	
  project	
  
changes,	
  continue	
  to	
  
update	
  through	
  bi-­‐
weekly	
  video,	
  tele-­‐
conference,	
  face-­‐to-­‐
face	
  meetings,	
  or	
  
written	
  and	
  emailed	
  
memorandum	
  
distribution	
  as	
  
required.	
  	
  
	
  
C-­‐	
  High	
  Influence	
  
but	
  low	
  interest	
  
	
   Keep	
  Satisfied	
  
Keep	
  project	
  materials	
  in	
  
Don’t	
  delay	
  providing	
  
information	
  on	
  unexpected	
  
Share	
  significant	
  
project	
  milestones	
  and	
  
13	
  	
  Page	
  	
  	
  	
  	
  	
  All	
  citations	
  are	
  from:	
  Project	
  Management	
  Institute.	
  (2013).	
  A	
  guide	
  to	
  the	
  project	
  management	
  body	
  
of	
  knowledge.	
  (5th	
  Ed.).	
  Newton	
  Square,	
  PA:	
  Author.	
  	
  
	
   	
  
1.	
  USCG	
  
2.	
  ABS	
  
3.	
  Construction	
  
Inspectors	
  
4.	
  Organization’s	
  
Chief	
  Engineer	
  
	
  
order,	
  concise	
  and	
  efficient.	
  
Ensure	
  the	
  lines	
  of	
  
communication	
  between	
  
other	
  project	
  stakeholders	
  
remain	
  open	
  and	
  flowing	
  at	
  
all	
  times.	
  Inform	
  on	
  
important	
  project	
  milestones	
  
or	
  project	
  events	
  that	
  may	
  
impact	
  these	
  stakeholders	
  at	
  
all	
  times.	
  	
  
	
  
project	
  variables.	
  Keep	
  
them	
  in	
  the	
  loop	
  and	
  up	
  to	
  
date	
  on	
  significant	
  changes	
  
to	
  the	
  project	
  schedule,	
  
requirements,	
  and/or	
  
budget	
  (if	
  required).	
  
	
  
keep	
  these	
  
stakeholders	
  in	
  all	
  
critical	
  project	
  
conversations.	
  	
  
	
  
D-­‐	
  Low	
  Interest	
  and	
  
Low	
  Influence	
  
1.	
  Construction	
  
Material	
  Vendors	
  
2.	
  SCS	
  Patrons	
  
3.	
  Port	
  Master	
  
	
  
	
   Monitor	
  	
  
Provide	
  information	
  that	
  is	
  
easy	
  to	
  understand	
  and	
  
access,	
  keep	
  informed	
  via	
  
email	
  on	
  changes.	
  Provide	
  
simple	
  status	
  and	
  project	
  
communications	
  via	
  a	
  
project	
  based	
  website.	
  
	
  
Provide	
  access	
  to	
  a	
  project	
  
database	
  via	
  the	
  Internet	
  
that	
  will	
  relay	
  information	
  
between	
  these	
  
stakeholders	
  and	
  other	
  key	
  
project	
  team	
  members.	
  
	
  
Provide	
  a	
  project-­‐
related	
  website	
  with	
  
information	
  available	
  in	
  
multiple	
  languages	
  that	
  
is	
  easily	
  downloadable	
  
and	
  easily	
  accessible.	
  
Keep	
  it	
  current	
  and	
  up-­‐
to-­‐date	
  with	
  important	
  
project	
  changes	
  and	
  
information.	
  
	
  
	
  
Initiating	
  Communication	
  Element	
  (Type	
  the	
  names	
  of	
  the	
  stakeholders	
  in	
  the	
  appropriate	
  boxes.).	
  	
  
	
   13.1	
  c.	
  	
  Impact	
  and	
  Interest	
  Stakeholder	
  Analysis	
  
The	
  Stakeholder	
  Analysis	
  Matrix	
  portrays	
  the	
  relationships	
  between	
  stakeholder	
  groups	
  and	
  
the	
  management	
  strategy	
  appropriate	
  for	
  each	
  stakeholder	
  group.	
  
	
   	
  STAKEHOLDER	
  ANALYSIS	
  MATRIX	
  
	
  	
  	
  <<	
  	
  	
  Influence	
  or	
  Power	
  of	
  Stakeholder	
  
	
   Little/No	
  Interest	
   Significant	
  
Interest	
  
Significant	
  
Influence	
  
	
  
1.	
  United	
  States	
  Coast	
  Guard	
  
(USCG)	
  
2.	
  American	
  Bureau	
  of	
  Shipping	
  
(ABS)	
  
3.	
  Construction	
  Inspectors	
  
4.	
  Organization’s	
  Chief	
  Engineer	
  
	
  
C	
  
	
  
Keep	
  Satisfied	
  
	
  
1.	
  Mr.	
  Dennis	
  Horvatt,	
  President	
  of	
  
Construction,	
  TFSB	
  Construction,	
  Inc.,	
  
Project	
  Sponsor	
  
2.	
  Ms.	
  Marie	
  Corday,	
  Customer	
  
3.	
  Board	
  of	
  Directors,	
  Starve	
  No	
  More	
  
Foundation,	
  Customer	
  
	
  
A	
  
	
  
Manage	
  Closely	
  
Little	
  or	
  No	
  
Influence	
  
	
  
	
  
	
  
	
  
1.	
  Construction	
  Material	
  Vendors	
  
2.	
  SCS	
  Patrons	
  
3.	
  Port	
  Master	
  
	
  
D	
  
	
  
	
  
Monitor	
  (minimum	
  effort)	
  
	
  
1.	
  Project	
  Management	
  Team	
  
2.	
  Construction	
  Foreperson	
  
3.	
  Interior	
  Design	
  Manager	
  
	
  
B	
  
	
  
	
  
Keep	
  Informed	
  
Importance	
  or	
  Interest	
  Level	
  of	
  Stakeholder	
  >>	
  
	
   	
  
End	
  of	
  Initiating	
  Documents	
  
14	
  	
  Page	
  	
  	
  	
  	
  	
  All	
  citations	
  are	
  from:	
  Project	
  Management	
  Institute.	
  (2013).	
  A	
  guide	
  to	
  the	
  project	
  management	
  body	
  
of	
  knowledge.	
  (5th	
  Ed.).	
  Newton	
  Square,	
  PA:	
  Author.	
  	
  
	
   	
  
Planning	
  A	
  Process	
  Group	
  
	
  
Purpose:	
  The	
  purpose	
  of	
  the	
  planning	
  process	
  group	
  is	
  to	
  establish	
  the	
  total	
  scope	
  of	
  the	
  effort,	
  define	
  
and	
  refine	
  the	
  project	
  objectives,	
  and	
  develop	
  the	
  course	
  of	
  action	
  required	
  to	
  attain	
  those	
  objectives.	
  
These	
  processes	
  develop	
  the	
  project	
  management	
  plan	
  and	
  the	
  project	
  documents	
  that	
  will	
  be	
  used	
  to	
  
carry	
  out	
  the	
  project.	
  	
  
	
  
Specific	
  information	
  about	
  the	
  purpose	
  and	
  characteristics	
  of	
  each	
  process	
  is	
  available	
  in	
  the	
  PMBOK	
  
Guide	
  in	
  the	
  sections	
  noted.	
  The	
  planning	
  process	
  group	
  is	
  split	
  into	
  two	
  sections,	
  labeled	
  A	
  and	
  B,	
  to	
  
reduce	
  the	
  size	
  of	
  the	
  template.	
  
	
  
Planning	
  Group	
  A	
  includes	
  the	
  knowledge	
  areas	
  of	
  Integration,	
  Scope,	
  Time	
  and	
  Cost.	
  (Secs.	
  4,5	
  6	
  &	
  7).	
  
Planning	
  Group	
  B	
  includes	
  the	
  knowledge	
  areas	
  of	
  Quality,	
  Human	
  Resources,	
  Communications,	
  Risk,	
  
Procurement	
  and	
  Stakeholder	
  Management.	
  (Secs..	
  8,9,10,11,12	
  &	
  13).	
  
PMBOK®	
  Guide	
  Chapter	
  4	
  -­‐	
  Integration	
  Management	
  Processes	
  
Project	
  Name:	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  Revision	
  Date:	
  	
  	
  	
  
Sponsor:	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  Date	
  Signed:	
  	
  
Sponsoring	
  Organization:	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  Signature:	
  __________________	
  
	
  
Knowledge	
  
Area	
  
Process	
   Inputs	
   Tools	
  and	
  Techniques	
  
	
  
Outputs	
  
	
  
Integration	
  
4.2	
  Develop	
  
Project	
  
Management	
  
Plan	
  
Project	
  charter,	
  
Outputs	
  of	
  other	
  
processes,	
  EEF	
  and	
  
OPA	
  
	
  
Expert	
  Judgment,	
  
facilitation	
  techniques	
  
4.2	
  Project	
  Management	
  
Plan	
  
	
  
	
  
Planning	
  A	
  Integration	
  Element	
  –	
  PRM600	
  	
  No	
  revisions	
  needed.	
  
4.2a.	
  Integrated	
  Project	
  Management	
  Plan	
  
The	
  Project	
  Management	
  Plan	
  integrates	
  and	
  consolidates	
  all	
  of	
  the	
  subsidiary	
  management	
  plans	
  and	
  
baseline.	
  	
  Every	
  project	
  methodology	
  should	
  be	
  tailored	
  to	
  the	
  size	
  and	
  complexity	
  of	
  the	
  project.	
  	
  	
  
Results	
  of	
  Tailoring	
  by	
  the	
  Project	
  Management	
  Team	
  
• Project	
  Baselines	
  will	
  be	
  included	
  for:	
  scope,	
  schedule	
  and	
  cost.	
  	
  	
  
• Detailed	
  Subsidiary	
  Plans	
  will	
  NOT	
  be	
  provided	
  in	
  this	
  plan.	
  	
  An	
  OPA	
  will	
  be	
  used	
  without	
  
tailoring.	
  	
  This	
  OPA	
  includes	
  an	
  organizational	
  mandate	
  for	
  common	
  management	
  plans	
  for	
  
scope,	
  requirements,	
  schedule,	
  cost,	
  quality,	
  process	
  improvement,	
  HR,	
  communications,	
  risk,	
  
procurement	
  and	
  stakeholder	
  management.	
  	
  
• No	
  specific	
  life	
  cycle	
  plan	
  will	
  be	
  used.	
  	
  
• Certain	
  detailed	
  plans	
  will	
  be	
  used.	
  	
  See	
  the	
  LIST	
  OF	
  TEMPLATES	
  included	
  at	
  the	
  beginning	
  of	
  this	
  
document	
  for	
  a	
  detailed	
  list.	
  	
  
	
  
	
  
	
  
15	
  	
  Page	
  	
  	
  	
  	
  	
  All	
  citations	
  are	
  from:	
  Project	
  Management	
  Institute.	
  (2013).	
  A	
  guide	
  to	
  the	
  project	
  management	
  body	
  
of	
  knowledge.	
  (5th	
  Ed.).	
  Newton	
  Square,	
  PA:	
  Author.	
  	
  
	
   	
  
PMBOK®	
  Guide	
  Chapter	
  5	
  -­‐	
  Scope	
  Management	
  Processes	
  
Knowledge	
  
Area	
  
Process	
   Inputs	
   Tools	
  and	
  Techniques	
  
	
  
Outputs	
  
Scope	
  	
   5.1	
  Plan	
  
Scope	
  
Management	
  
PM	
  plan,	
  
charter,	
  EEF,	
  
OPA	
  
Expert	
  judgment	
  and	
  
meetings.	
  
5.1a	
  Scope	
  Management	
  
Plan	
  and	
  Requirements	
  
Management	
  Plan	
  
	
  
Scope	
  
5.2	
  Collect	
  
Requirements	
  
Scope	
  mgmt.	
  
plan,	
  Req.	
  
mgmt.	
  plan,	
  
stakeholder	
  
mgmt.	
  plan.	
  
Project	
  
charter	
  
Stakeholder	
  
register	
  
Group	
  and	
  individual	
  data	
  
collection	
  and	
  decision-­‐
making	
  
techniques,(interviews,	
  
focus	
  groups,	
  observations,	
  
surveys,	
  prototypes)	
  	
  expert	
  
judgment,	
  product	
  analysis	
  
and	
  facilitated	
  workshops	
  
such	
  as	
  JAD	
  sessions,	
  
context	
  diagrams,	
  	
  
	
  
5.2a	
  Requirements	
  
Documentation	
  
	
  
	
  
Scope	
   5.3	
  Define	
  
Scope	
  
Outputs	
  of	
  5.1	
  
and	
  5.2,	
  
Charter,	
  EEF	
  &	
  
OPA	
  
	
  
Expert	
  judgment,	
  product	
  
analysis,	
  alternatives	
  
identification	
  and	
  
facilitated	
  workshops	
  such	
  
as	
  JAD	
  sessions	
  
	
  
5.3a	
  Project	
  Scope	
  
Statement,	
  	
  project	
  
document	
  updates.	
  
Scope	
   5.4	
  Create	
  
WBS	
  
Outputs	
  of	
  
5.1,	
  5.2	
  and	
  
5.3,	
  EEF	
  and	
  
OPA	
  	
  
Decomposition	
  and	
  Expert	
  
Judgment	
  
Scope	
  Baseline	
  	
  consisting	
  
of:	
  	
  
5.3a	
  WBS	
  and	
  	
  
5.3b	
  WBS	
  Dictionary	
  
	
  
Scope	
  Planning	
  Element	
  –	
  (PRM600	
  	
  -­‐No	
  revisions	
  needed.)	
  
5.1a	
  Scope	
  Management	
  Plan	
  	
  
The	
  Scope	
  Management	
  Plan	
  describes	
  how	
  the	
  scope	
  will	
  be	
  defined,	
  developed,	
  monitored,	
  controlled	
  and	
  
verified.	
  	
  
Inputs	
  Used	
  
Identify	
  specific	
  inputs	
  needed	
  before	
  the	
  Scope	
  Management	
  Plan	
  and	
  the	
  Requirements	
  Management	
  Plan	
  
can	
  be	
  created.	
  	
  	
  
	
  
The	
  Charter	
  is	
  used	
  to	
  provide	
  a	
  high-­‐level	
  project	
  description	
  and	
  high-­‐level	
  product	
  characteristics.	
  EEF:	
  	
  
The	
  organizational	
  culture	
  can	
  be	
  described	
  as:	
  	
  
	
  
The	
  Organization	
  contracts	
  with	
  various	
  clients	
  around	
  the	
  globe	
  and	
  is	
  a	
  leader	
  in	
  the	
  construction	
  industry.	
  From	
  
projects	
  that	
  include	
  commercial,	
  industrial,	
  agricultural,	
  residential,	
  and	
  maritime,	
  this	
  organization	
  works	
  with	
  a	
  
variety	
  of	
  clients	
  who	
  specializes	
  in	
  not	
  for	
  profit	
  endeavors.	
  	
  	
  
	
  
OPA:	
  	
  The	
  policies	
  and	
  procedures	
  are	
  provided	
  by	
  the	
  main	
  organization’s	
  PMO.	
  	
  	
  
16	
  	
  Page	
  	
  	
  	
  	
  	
  All	
  citations	
  are	
  from:	
  Project	
  Management	
  Institute.	
  (2013).	
  A	
  guide	
  to	
  the	
  project	
  management	
  body	
  
of	
  knowledge.	
  (5th	
  Ed.).	
  Newton	
  Square,	
  PA:	
  Author.	
  	
  
	
   	
  
Tools	
  and	
  Techniques	
  Used	
  
Identify	
  the	
  tools	
  and	
  techniques	
  used	
  to	
  create	
  the	
  plans.	
  Explain	
  how	
  you	
  used	
  the	
  tools.	
  
Expertise	
  on	
  methods	
  used	
  to	
  define,	
  develop,	
  monitor	
  and	
  control	
  scope	
  will	
  be	
  provided	
  by	
  the	
  
organization’s	
  PMO.	
  	
  
Meetings	
  will	
  be	
  held	
  where	
  the	
  PMO	
  can	
  tailor	
  the	
  plans	
  to	
  the	
  size	
  and	
  complexity	
  of	
  this	
  project.	
  	
  
	
  
Output:	
  The	
  Scope	
  management	
  plan	
  to	
  be	
  provided	
  by	
  the	
  organization’s	
  PMO	
  includes	
  a	
  process	
  for	
  
preparing	
  a	
  detailed	
  scope	
  statement	
  and	
  a	
  WBS,	
  and	
  processes	
  to	
  manage	
  changes	
  and	
  to	
  track	
  
acceptance	
  of	
  deliverables.	
  
	
  
Output:	
  The	
  Requirements	
  Management	
  Plan	
  to	
  be	
  provided	
  by	
  the	
  organization’s	
  PMO.	
  Includes	
  templates	
  
and	
  instructions	
  for	
  determining	
  how	
  requirements	
  will	
  be	
  planned,	
  tracked	
  and	
  reported.	
  The	
  consultants	
  
will	
  help	
  implement	
  a	
  process	
  for	
  prioritizing	
  requirements,	
  managing	
  changes	
  to	
  requirements,	
  and	
  using	
  a	
  
traceability	
  matrix	
  and	
  developing	
  metrics.	
  	
  
	
  
Planning	
  A	
  Scope	
  Element	
  (PRM600	
  	
  -­‐Add	
  rows	
  for	
  five	
  specific	
  requirements.)	
  
5.2a.	
  Requirements	
  Documentation	
  
This	
  table	
  describes	
  how	
  individual	
  requirements	
  meet	
  the	
  business	
  need	
  for	
  the	
  project.	
  During	
  early	
  
planning	
  stages,	
  requirements	
  are	
  defined	
  at	
  a	
  high	
  level	
  and	
  become	
  progressively	
  more	
  detailed	
  during	
  
project	
  execution.	
  	
  Requirements	
  must	
  be	
  unambiguous	
  so	
  that	
  they	
  can	
  be	
  traced.	
  
Stakeholder	
  
(group)	
  
Person	
  /	
  group	
  
that	
  will	
  
approve	
  or	
  
accept	
  a	
  
deliverable	
  
	
  
Requirement	
  
	
  
Describe	
  a	
  part	
  of	
  the	
  product	
  
that	
  will	
  be	
  delivered	
  such	
  as	
  a	
  
document,	
  service,	
  product	
  or	
  
result.	
  
Acceptance	
  Criteria	
  
	
  
Describe	
  how	
  the	
  
stakeholder	
  will	
  evaluate	
  
the	
  finished	
  element.	
  
Priority	
  (HML)	
  
Category	
  
Select	
  High,	
  
Medium	
  or	
  
Low	
  for	
  
priority	
  level.	
  	
  	
  
ID	
  
#	
  
PMO	
  
	
  
Project	
  Baselines	
  for	
  Scope,	
  Cost	
  and	
  
Schedule	
  
The	
  senior	
  member	
  of	
  the	
  
PMO	
  will	
  sign	
  off	
  on	
  the	
  
baselines	
  if	
  they	
  meet	
  
criteria	
  for	
  level	
  of	
  detail	
  and	
  
attainability.	
  	
  
High	
   R1	
  
1.	
  Mr.	
  Dennis	
  
Horvatt,	
  Pres.	
  Of	
  
Const.	
  TFSB	
  
Const.,	
  Inc.,	
  Proj.	
  
Sponsor	
  
2.	
  Ms.	
  Marie	
  
Corday,	
  Customer	
  
3.	
  Board	
  of	
  
Directors,	
  Starve	
  
No	
  More	
  
Foundation,	
  
Customer	
  
Completed	
  SCS	
  Gift	
  Shops,	
  approved	
  
plans,	
  designs,	
  construction,	
  interior	
  
and	
  exterior	
  elements	
  
The	
  Project	
  Sponsor,	
  Ms.	
  
Corday,	
  and	
  the	
  
Foundation’s	
  Board	
  will	
  sign	
  
off	
  on	
  project	
  milestones	
  via	
  
regular	
  consultation,	
  
monthly	
  status	
  meetings,	
  
written	
  correspondence,	
  
written	
  approval	
  letters,	
  and	
  
a	
  formal	
  letter	
  of	
  
acceptance.	
  	
  
High	
   R2	
  
1.	
  USCG	
  
2.	
  ABS	
  
3.	
  Construction	
  
Inspectors	
  
4.	
  Organization’s	
  
Chief	
  Engineer	
  
Formal	
  written	
  approvals	
  and	
  official	
  
seals	
  for	
  construction	
  including	
  
structural,	
  utility,	
  and	
  for	
  the	
  safety,	
  
security,	
  and	
  seaworthy	
  integrity	
  of	
  
its	
  patrons	
  and	
  staff.	
  	
  
Through	
  comprehensive	
  
inspections,	
  review,	
  and	
  
engineering	
  tests.	
  
Medium	
   R3	
  
1.	
  Project	
   Plan,	
  execute,	
  monitor,	
  control,	
  and	
   Through	
  the	
  use	
  of	
  OPA	
  and	
   Medium	
   R4	
  
17	
  	
  Page	
  	
  	
  	
  	
  	
  All	
  citations	
  are	
  from:	
  Project	
  Management	
  Institute.	
  (2013).	
  A	
  guide	
  to	
  the	
  project	
  management	
  body	
  
of	
  knowledge.	
  (5th	
  Ed.).	
  Newton	
  Square,	
  PA:	
  Author.	
  	
  
	
   	
  
5.2a.	
  Requirements	
  Documentation	
  
This	
  table	
  describes	
  how	
  individual	
  requirements	
  meet	
  the	
  business	
  need	
  for	
  the	
  project.	
  During	
  early	
  
planning	
  stages,	
  requirements	
  are	
  defined	
  at	
  a	
  high	
  level	
  and	
  become	
  progressively	
  more	
  detailed	
  during	
  
project	
  execution.	
  	
  Requirements	
  must	
  be	
  unambiguous	
  so	
  that	
  they	
  can	
  be	
  traced.	
  
Stakeholder	
  
(group)	
  
Person	
  /	
  group	
  
that	
  will	
  
approve	
  or	
  
accept	
  a	
  
deliverable	
  
	
  
Requirement	
  
	
  
Describe	
  a	
  part	
  of	
  the	
  product	
  
that	
  will	
  be	
  delivered	
  such	
  as	
  a	
  
document,	
  service,	
  product	
  or	
  
result.	
  
Acceptance	
  Criteria	
  
	
  
Describe	
  how	
  the	
  
stakeholder	
  will	
  evaluate	
  
the	
  finished	
  element.	
  
Priority	
  (HML)	
  
Category	
  
Select	
  High,	
  
Medium	
  or	
  
Low	
  for	
  
priority	
  level.	
  	
  	
  
ID	
  
#	
  
Management	
  
Team	
  
2.	
  Construction	
  
Foreperson	
  
3.	
  Interior	
  Design	
  
Manager	
  
close	
  the	
  project	
  management	
  plan,	
  
construction	
  plan,	
  and	
  interior	
  
design	
  milestones.	
  	
  	
  
understanding	
  of	
  EFF’s	
  of	
  
similar	
  projects,	
  lessons	
  
learned,	
  and	
  expert	
  
judgment.	
  
1.	
  Construction	
  
Material	
  Vendors	
  
2.	
  SCS	
  Patrons	
  
3.	
  Port	
  Master	
  
Will	
  provide	
  construction	
  materials,	
  
furtherance	
  the	
  support	
  of	
  the	
  
Foundation’s	
  mission	
  and	
  goals	
  in	
  
the	
  form	
  of	
  patronage	
  of	
  the	
  Gift	
  
Shops	
  for	
  years	
  to	
  come,	
  and	
  access	
  
to	
  various	
  resources	
  during	
  the	
  
construction	
  of	
  the	
  SCS	
  Gift	
  Shops.	
  	
  
In	
  the	
  form	
  of	
  banners	
  to	
  
demonstrate	
  materials	
  and	
  
services	
  by;	
  the	
  enjoyment	
  of	
  
the	
  amenities;	
  by	
  providing	
  
access	
  to	
  resources	
  and	
  
skilled	
  labor	
  specific	
  to	
  the	
  
maritime	
  industry.	
  
Low	
   R5	
  
	
  
Planning	
  A	
  Scope	
  Element	
  (PRM600	
  –	
  Fill	
  out	
  the	
  content	
  areas.)	
  
5.3a	
  Project	
  Scope	
  Statement	
  
The	
  Project	
  Scope	
  Statement	
  provides	
  a	
  common	
  understanding	
  of	
  the	
  project	
  scope	
  among	
  all	
  
stakeholders	
  and	
  provides	
  a	
  baseline	
  for	
  evaluating	
  whether	
  requests	
  for	
  changes	
  or	
  additional	
  work	
  are	
  
inside	
  or	
  outside	
  the	
  project’s	
  boundaries.	
  	
  	
  
Description	
  of	
  the	
  Product	
  
Describe	
  the	
  end	
  product,	
  service	
  or	
  result	
  that	
  the	
  project	
  will	
  produce.	
  	
  
	
  
1. Provide	
  ten	
  (10)	
  unique	
  artistic	
  renderings,	
  including	
  perspective	
  drawings	
  that	
  depict	
  all	
  five	
  (5)	
  gift	
  
shops	
  in	
  use,	
  which	
  will	
  specifically	
  demonstrate	
  design	
  elements	
  of	
  both	
  interiors	
  and	
  exteriors	
  of	
  
each	
  gift	
  shop.	
  
2. Design	
  one	
  (1)	
  rectangular-­‐shaped,	
  centralized,	
  two-­‐level,	
  4500	
  sq.	
  ft.	
  main	
  gift	
  shop	
  with	
  an	
  ‘open	
  
atrium’	
  (looking	
  down	
  to	
  the	
  first	
  floor)	
  second	
  level	
  with	
  one	
  (1)	
  single	
  landing	
  stair	
  case	
  on	
  the	
  
north	
  side	
  and	
  one	
  (1)	
  eight	
  (8)	
  person	
  capacity	
  hydraulic	
  elevator	
  on	
  the	
  south	
  side.	
  
3. Design	
  the	
  remaining	
  four	
  (4)	
  oval-­‐shaped,	
  single-­‐level,	
  1500	
  sq	
  ft.	
  satellite	
  gift	
  shops.	
  
4. Provide	
  an	
  “open	
  air”	
  access	
  design	
  of	
  the	
  main	
  gift	
  shop,	
  with	
  multiple	
  entrances	
  into	
  the	
  first	
  floor	
  
of	
  no	
  less	
  than	
  20	
  feet	
  per	
  entrance	
  on	
  all	
  four	
  sides.	
  	
  
5. Provide	
  an	
  “open	
  air”	
  access	
  design	
  of	
  the	
  satellite	
  gift	
  shops,	
  with	
  one	
  (1)	
  entrance	
  of	
  no	
  less	
  than	
  15	
  
feet	
  on	
  only	
  one	
  side	
  per	
  gift	
  shop.	
  
6. Provide	
  motorized,	
  concealable,	
  and	
  recessed	
  security	
  roll-­‐up	
  doors	
  for	
  all	
  entranceways	
  for	
  each	
  gift	
  
18	
  	
  Page	
  	
  	
  	
  	
  	
  All	
  citations	
  are	
  from:	
  Project	
  Management	
  Institute.	
  (2013).	
  A	
  guide	
  to	
  the	
  project	
  management	
  body	
  
of	
  knowledge.	
  (5th	
  Ed.).	
  Newton	
  Square,	
  PA:	
  Author.	
  	
  
	
   	
  
5.3a	
  Project	
  Scope	
  Statement	
  
The	
  Project	
  Scope	
  Statement	
  provides	
  a	
  common	
  understanding	
  of	
  the	
  project	
  scope	
  among	
  all	
  
stakeholders	
  and	
  provides	
  a	
  baseline	
  for	
  evaluating	
  whether	
  requests	
  for	
  changes	
  or	
  additional	
  work	
  are	
  
inside	
  or	
  outside	
  the	
  project’s	
  boundaries.	
  	
  	
  
shop	
  using	
  durable,	
  transparent,	
  and	
  scratch-­‐resistant	
  materials.	
  Each	
  door	
  should	
  be	
  able	
  to	
  be	
  
locally	
  and	
  remotely	
  operated.	
  
7. Provide	
  no	
  less	
  than	
  500	
  sq	
  ft.	
  of	
  concealable	
  stocking	
  space	
  within	
  the	
  main	
  gift	
  shop,	
  and	
  no	
  less	
  
than	
  100	
  sq	
  ft.	
  of	
  concealable	
  stocking	
  space	
  within	
  the	
  satellite	
  gift	
  shops.	
  	
  
8. Provide	
  no	
  less	
  than	
  300	
  sq	
  ft.	
  of	
  administrative	
  office	
  space	
  within	
  the	
  centralized	
  gift	
  shop.	
  
9. Provide	
  two	
  (2)	
  gender	
  specific,	
  120	
  sq	
  ft.,	
  single	
  stall	
  restrooms	
  within	
  the	
  main	
  gift	
  shop	
  and	
  one	
  (1)	
  
single	
  fixture,	
  80	
  sq	
  ft.	
  family	
  restroom	
  within	
  each	
  of	
  the	
  satellite	
  gift	
  shops.	
  
10. Provide	
  two	
  (2)	
  changing	
  rooms	
  within	
  the	
  main	
  gift	
  shop	
  and	
  one	
  (1)	
  changing	
  room	
  within	
  each	
  of	
  
the	
  satellite	
  gift	
  shops.	
  No	
  changing	
  room	
  should	
  exceed	
  25	
  sq	
  ft.	
  
11. Provide	
  enough	
  area	
  to	
  accommodate	
  various	
  merchandizing	
  fixtures	
  for	
  all	
  gift	
  shops,	
  including	
  
refrigerated	
  coolers,	
  jewelry	
  display	
  cases,	
  apparel	
  racks,	
  wall	
  and	
  floor	
  rack	
  shelving,	
  and	
  
miscellaneous	
  counter	
  tops.	
  
12. Provide	
  enough	
  area	
  to	
  accommodate	
  one	
  (1)	
  220	
  sq	
  ft.	
  circular	
  point	
  of	
  sale	
  (POS)	
  counter	
  in	
  each	
  
gift	
  shop.	
  The	
  POS	
  counter	
  will	
  be	
  located	
  in	
  the	
  center	
  of	
  the	
  first	
  floor	
  of	
  the	
  main	
  gift	
  shop	
  and	
  
within	
  the	
  center	
  of	
  all	
  of	
  the	
  satellite	
  gift	
  shops.	
  
13. Provide	
  detailed	
  blue	
  prints	
  and	
  construction	
  plans	
  for	
  all	
  five	
  (5)	
  gift	
  shops.	
  
14. Construct	
  all	
  gift	
  shops	
  utilizing	
  best	
  practices	
  of	
  retail	
  and	
  maritime	
  construction	
  techniques.	
  
15. Provide	
  finishing	
  construction	
  (carpeting,	
  paint,	
  accents,	
  fixtures,	
  etc.)	
  work	
  upon	
  completion	
  of	
  
structural	
  construction	
  in	
  accordance	
  to	
  the	
  approval	
  guidelines	
  of	
  the	
  Foundation.	
  
16. Project	
  management	
  services	
  must	
  be	
  conducted	
  using	
  PMI	
  methodologies	
  incorporating	
  monthly	
  
status	
  reports.	
  
	
  
Product	
  Acceptance	
  Criteria	
  
Describe	
  how	
  the	
  stakeholder	
  will	
  accept	
  the	
  final	
  product.	
  	
  
	
  
The	
  Foundations	
  acceptance	
  of	
  the	
  deliverables	
  will	
  be	
  based	
  on	
  reports,	
  approval	
  and	
  inspections	
  of	
  the	
  project	
  
management	
  plan,	
  designs,	
  construction	
  plans	
  and	
  requirements	
  as	
  listed	
  in	
  the	
  section	
  above	
  as	
  well	
  as	
  the	
  
following	
  deliverable	
  requirements	
  below:	
  	
  
	
  
i) Submit	
  for	
  Foundation	
  approval	
  a	
  total	
  of	
  fifty	
  (50)	
  artists’	
  renderings	
  and	
  perspective	
  drawings	
  
demonstrating	
  unique	
  design	
  elements	
  of	
  the	
  interior	
  and	
  exterior	
  for	
  each	
  gift	
  shop.	
  Ten	
  (10)	
  
drawings	
  per	
  gift	
  shop.	
  
ii) Submit	
  for	
  Foundation	
  approval	
  a	
  total	
  of	
  one	
  hundred	
  (100)	
  photographic	
  and	
  physical	
  samples	
  of	
  
colors,	
  fixtures,	
  textures,	
  and	
  interior	
  design	
  elements	
  for	
  each	
  gift	
  shop	
  and	
  relative	
  areas,	
  which	
  
demonstrate	
  a	
  unique	
  look	
  and	
  feel	
  for	
  each	
  gift	
  shop.	
  	
  	
  
19	
  	
  Page	
  	
  	
  	
  	
  	
  All	
  citations	
  are	
  from:	
  Project	
  Management	
  Institute.	
  (2013).	
  A	
  guide	
  to	
  the	
  project	
  management	
  body	
  
of	
  knowledge.	
  (5th	
  Ed.).	
  Newton	
  Square,	
  PA:	
  Author.	
  	
  
	
   	
  
5.3a	
  Project	
  Scope	
  Statement	
  
The	
  Project	
  Scope	
  Statement	
  provides	
  a	
  common	
  understanding	
  of	
  the	
  project	
  scope	
  among	
  all	
  
stakeholders	
  and	
  provides	
  a	
  baseline	
  for	
  evaluating	
  whether	
  requests	
  for	
  changes	
  or	
  additional	
  work	
  are	
  
inside	
  or	
  outside	
  the	
  project’s	
  boundaries.	
  	
  	
  
iii) Detailed	
  and	
  approved	
  structural	
  construction	
  floor	
  plans,	
  in	
  plan	
  view,	
  for	
  each	
  gift	
  shop.	
  
iv) Detailed	
  and	
  approved	
  Construction	
  blue	
  prints	
  for	
  each	
  gift	
  shop.	
  
v) Detailed	
  and	
  approved	
  electrical,	
  plumbing,	
  and	
  hydraulics	
  plans	
  for	
  each	
  gift	
  shop.	
  
vi) Detailed	
  and	
  approved	
  bill	
  of	
  construction	
  materials	
  that	
  are	
  in	
  keeping	
  with	
  modern	
  retail	
  and	
  
maritime	
  building	
  codes	
  subject	
  to	
  the	
  laws	
  of	
  the	
  United	
  States,	
  and	
  the	
  US	
  Coast	
  Guard	
  for	
  each	
  gift	
  
shop.	
  
vii) Finalized	
  structural	
  construction	
  of	
  one	
  (1)	
  rectangular-­‐shaped,	
  two-­‐level,	
  4500	
  sq.	
  ft.	
  main	
  gift	
  shop	
  
and	
  four	
  (4)	
  oval-­‐shaped,	
  single	
  level,	
  1500	
  sq	
  ft.	
  satellite	
  gift	
  shops.	
  
viii) Finalized	
  structural	
  construction,	
  installation,	
  and	
  testing	
  of	
  one	
  (1)	
  single	
  landing	
  staircase	
  to	
  be	
  
located	
  at	
  the	
  north	
  end	
  and	
  one	
  (1)	
  eight-­‐person	
  capacity,	
  hydraulic	
  elevator	
  to	
  be	
  installed	
  at	
  the	
  
south	
  end	
  of	
  the	
  main	
  gift	
  shop.	
  
ix) Completed	
  finish	
  construction	
  elements,	
  design	
  and	
  accents,	
  carpeting,	
  tile,	
  paint,	
  lighting	
  and	
  
restroom	
  fixtures,	
  telecommunications	
  and	
  data	
  ports,	
  installed	
  and	
  tested	
  safety	
  and	
  security	
  
systems,	
  CCTV,	
  loss	
  prevention	
  systems,	
  etc.	
  for	
  each	
  gift	
  shop.	
  
x) Project	
  management	
  plan	
  with	
  monthly	
  status	
  reports.	
  
	
  
Project	
  Deliverables	
  
Please	
  refer	
  to	
  the	
  WBS	
  for	
  a	
  complete	
  list	
  of	
  project	
  deliverables	
  	
  
	
  
Project	
  Exclusions	
  
Describe	
  any	
  items	
  stakeholder	
  may	
  have	
  considered	
  that	
  are	
  outside	
  of	
  the	
  project	
  boundaries.	
  
	
  
The	
  product	
  specifically	
  excludes:	
  	
  
	
  
• Stocking	
  the	
  completed	
  Gift	
  Shops	
  with	
  merchandise	
  
• Procure	
  merchandise	
  for	
  the	
  completed	
  Gift	
  Shops	
  
• Staffing	
  the	
  completed	
  Gift	
  Shops	
  
• Training	
  staff	
  of	
  the	
  completed	
  Gift	
  Shops	
  
• Procuring,	
  storing,	
  assembling,	
  or	
  handling	
  the	
  placement	
  of	
  specialized	
  merchandizing	
  fixtures	
  for	
  the	
  
completed	
  Gift	
  Shops	
  
• Sub-­‐contracting	
  the	
  work	
  required	
  to	
  procure,	
  store,	
  assemble,	
  handle,	
  or	
  place	
  specialized	
  
merchandizing	
  fixtures	
  for	
  the	
  completed	
  Gift	
  Shops	
  
• Design,	
  place,	
  install,	
  or	
  make	
  arrangements	
  thereof	
  for	
  any	
  SCS	
  specialized	
  marketing	
  signage,	
  or	
  other	
  
related	
  artwork	
  for	
  the	
  completed	
  Gift	
  Shops	
  
• Provide	
  or	
  assemble	
  any	
  of	
  the	
  completed	
  Gift	
  Shops	
  with	
  any	
  additional	
  furnishings	
  
• Install	
  additional	
  video	
  or	
  audio	
  systems	
  for	
  any	
  of	
  the	
  completed	
  Gift	
  Shops	
  
• Procuring,	
  storing,	
  assembling,	
  or	
  handling	
  the	
  placement	
  of	
  specialized	
  Point-­‐Of-­‐Sale	
  computer	
  
equipment,	
  workstations,	
  cash	
  registers,	
  etc.	
  for	
  the	
  completed	
  Gift	
  Shops	
  
• Sub-­‐contracting	
  the	
  work	
  required	
  to	
  procure,	
  store,	
  assemble,	
  handle,	
  or	
  place	
  specialized	
  Point-­‐Of-­‐Sale	
  
computer	
  equipment,	
  workstations,	
  cash	
  registers,	
  etc.	
  for	
  the	
  completed	
  Gift	
  Shops	
  
20	
  	
  Page	
  	
  	
  	
  	
  	
  All	
  citations	
  are	
  from:	
  Project	
  Management	
  Institute.	
  (2013).	
  A	
  guide	
  to	
  the	
  project	
  management	
  body	
  
of	
  knowledge.	
  (5th	
  Ed.).	
  Newton	
  Square,	
  PA:	
  Author.	
  	
  
	
   	
  
5.3a	
  Project	
  Scope	
  Statement	
  
The	
  Project	
  Scope	
  Statement	
  provides	
  a	
  common	
  understanding	
  of	
  the	
  project	
  scope	
  among	
  all	
  
stakeholders	
  and	
  provides	
  a	
  baseline	
  for	
  evaluating	
  whether	
  requests	
  for	
  changes	
  or	
  additional	
  work	
  are	
  
inside	
  or	
  outside	
  the	
  project’s	
  boundaries.	
  	
  	
  
Project	
  Constraints	
  
List	
  any	
  factors	
  that	
  limit	
  the	
  options	
  available	
  to	
  the	
  project	
  team.	
  
	
  
Constraints	
  include:	
  	
  
• That	
  the	
  hull	
  and	
  super-­‐structure	
  of	
  the	
  ship	
  will	
  be	
  completed	
  prior	
  to	
  the	
  commencing	
  of	
  the	
  Gift	
  Shops	
  
construction.	
  
• Approvals	
  of	
  the	
  design,	
  floor	
  plans,	
  structure,	
  and	
  utilities	
  must	
  be	
  approved	
  by	
  the	
  various	
  governing	
  
authority	
  in	
  maritime	
  construction	
  and	
  the	
  Organization’s	
  Chief	
  Engineer	
  prior	
  to	
  the	
  commencement	
  of	
  
the	
  construction	
  phase	
  of	
  the	
  Gift	
  Shops.	
  
• In	
  addition	
  to	
  the	
  various	
  governing	
  authorities’	
  approval,	
  the	
  Organization	
  must	
  obtain	
  written	
  
acknowledgement	
  from	
  the	
  Project	
  Sponsor	
  before	
  any	
  of	
  the	
  project	
  approval	
  milestones	
  can	
  be	
  
considered	
  completed.	
  
• Approvals	
  of	
  the	
  structural	
  construction	
  and	
  the	
  completed	
  interiors	
  (including	
  utilities	
  of	
  all	
  Gift	
  Shops,	
  
the	
  staircase,	
  elevator	
  construction,	
  and	
  operation	
  of	
  the	
  main	
  Gift	
  Shop)	
  must	
  be	
  approved	
  by	
  the	
  
various	
  governing	
  authority	
  in	
  maritime	
  construction	
  and	
  the	
  Organization’s	
  Chief	
  Engineer	
  prior	
  to	
  final	
  
delivery	
  and	
  approval	
  of	
  the	
  completed	
  Gift	
  Shops	
  to	
  the	
  Project	
  Sponsor.	
  
• Approvals	
  of	
  the	
  completed,	
  installed,	
  and	
  operational	
  components	
  of	
  all	
  Gift	
  Shop	
  exteriors	
  must	
  be	
  
approved	
  by	
  the	
  various	
  governing	
  authority	
  in	
  maritime	
  construction	
  and	
  the	
  Organization’s	
  Chief	
  
Engineer	
  prior	
  to	
  final	
  delivery	
  and	
  approval	
  of	
  the	
  completed	
  Gift	
  Shops	
  to	
  the	
  Project	
  Sponsor.	
  
	
  
Project	
  Assumptions	
  
List	
  any	
  factors	
  that	
  were	
  assumed	
  in	
  project	
  planning,	
  and	
  indicate	
  what	
  may	
  happen	
  if	
  it	
  turns	
  out	
  that	
  these	
  
assumptions	
  were	
  false.	
  	
  
	
  
Assumption	
  #1	
  -­‐	
  The	
  ship	
  hull,	
  or	
  super-­‐structure,	
  is	
  finished	
  before	
  the	
  scheduled	
  start	
  date	
  of	
  the	
  gift	
  shops	
  
construction.	
  
	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  
If	
  Assumption	
  #1	
  is	
  false,	
  then:	
  designs,	
  structural	
  blue	
  prints,	
  and	
  utility	
  drawings	
  packages	
  can	
  occur	
  concurrently	
  
to	
  the	
  ship	
  hull	
  construction	
  project.	
  The	
  Gift	
  Shops	
  will	
  begin	
  structural	
  construction	
  and	
  fabrication	
  adjacent	
  to	
  
SCS	
  super-­‐structure	
  port	
  and	
  be	
  assembled	
  in	
  a	
  modular	
  fashion	
  after	
  ship	
  hull	
  is	
  complete.	
  
	
  
Assumption	
  #2	
  -­‐	
  The	
  Starve	
  No	
  More	
  Foundation	
  will	
  provide	
  full	
  funding	
  to	
  the	
  Gift	
  Shops	
  Project	
  and	
  throughout	
  
the	
  projects	
  final	
  delivery.	
  
	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  
If	
  Assumption	
  #2	
  is	
  false,	
  then:	
  the	
  Organization	
  will	
  file	
  a	
  mechanics	
  lien	
  on	
  the	
  SCS	
  project	
  and	
  secure	
  a	
  bond	
  in	
  
the	
  amount	
  of	
  the	
  project	
  budget	
  (plus	
  contingency)	
  to	
  ensure	
  the	
  full	
  project	
  funding.	
  
	
  
Assumption	
  #3	
  -­‐	
  The	
  amount	
  of	
  qualified	
  and	
  experienced	
  personnel	
  will	
  be	
  available	
  to	
  work	
  on	
  the	
  project	
  until	
  
the	
  project	
  is	
  closed	
  and	
  the	
  Gift	
  Shops	
  have	
  been	
  delivered	
  to	
  the	
  Foundation.	
  
	
  
If	
  Assumption	
  #3	
  is	
  false,	
  then:	
  The	
  Organization	
  will	
  provide	
  local	
  accommodations	
  to	
  experienced	
  and	
  qualified	
  
workers	
  outside	
  the	
  region	
  of	
  the	
  construction	
  site.	
  
	
  
	
  
Planning	
  A	
  Scope	
  Element	
  -­‐	
  	
  	
  (PRM600-­‐	
  complete	
  a	
  full	
  WBS	
  for	
  the	
  project	
  to	
  Level	
  2.	
  	
  The	
  major	
  
deliverable	
  6-­‐	
  Project	
  Management	
  –	
  has	
  been	
  completed	
  for	
  you.	
  .	
  	
  	
  
	
  
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J
PRM601 Final Project_Magana_J

More Related Content

What's hot

Powerful presentations handout
Powerful presentations handoutPowerful presentations handout
Powerful presentations handoutltresalu
 
Sap Solman Imptools Implementation Cycle
Sap Solman Imptools Implementation CycleSap Solman Imptools Implementation Cycle
Sap Solman Imptools Implementation Cyclewlacaze
 
SFCG_CMM-Evaluation-Report
SFCG_CMM-Evaluation-ReportSFCG_CMM-Evaluation-Report
SFCG_CMM-Evaluation-ReportClaudios Hakuna
 
Rapport pebi-anap-atih-2020
Rapport pebi-anap-atih-2020Rapport pebi-anap-atih-2020
Rapport pebi-anap-atih-2020Sawsen Larbi
 
about start up for you 3
about start up for you 3about start up for you 3
about start up for you 3aliaalistartup
 

What's hot (8)

Fp7 evrules en
Fp7 evrules enFp7 evrules en
Fp7 evrules en
 
Powerful presentations handout
Powerful presentations handoutPowerful presentations handout
Powerful presentations handout
 
Sap Solman Imptools Implementation Cycle
Sap Solman Imptools Implementation CycleSap Solman Imptools Implementation Cycle
Sap Solman Imptools Implementation Cycle
 
SFCG_CMM-Evaluation-Report
SFCG_CMM-Evaluation-ReportSFCG_CMM-Evaluation-Report
SFCG_CMM-Evaluation-Report
 
Rapport pebi-anap-atih-2020
Rapport pebi-anap-atih-2020Rapport pebi-anap-atih-2020
Rapport pebi-anap-atih-2020
 
Mendes2011
Mendes2011Mendes2011
Mendes2011
 
Draft plan pdf
Draft plan pdfDraft plan pdf
Draft plan pdf
 
about start up for you 3
about start up for you 3about start up for you 3
about start up for you 3
 

Similar to PRM601 Final Project_Magana_J

Monitoring of project implementation
Monitoring of project implementationMonitoring of project implementation
Monitoring of project implementationDejened
 
Group charter projectcode_v1
Group charter projectcode_v1Group charter projectcode_v1
Group charter projectcode_v1caramurf
 
QBD_1464843125535 - Copy
QBD_1464843125535 - CopyQBD_1464843125535 - Copy
QBD_1464843125535 - CopyBhavesh Jangale
 
Chat Application [Full Documentation]
Chat Application [Full Documentation]Chat Application [Full Documentation]
Chat Application [Full Documentation]Rajon
 
A.R.C. Usability Evaluation
A.R.C. Usability EvaluationA.R.C. Usability Evaluation
A.R.C. Usability EvaluationJPC Hanson
 
Trinity Impulse - Event Aggregation to Increase Stundents Awareness of Events...
Trinity Impulse - Event Aggregation to Increase Stundents Awareness of Events...Trinity Impulse - Event Aggregation to Increase Stundents Awareness of Events...
Trinity Impulse - Event Aggregation to Increase Stundents Awareness of Events...Jason Cheung
 
10 guidetoproposalwriting
10 guidetoproposalwriting10 guidetoproposalwriting
10 guidetoproposalwritingPlut Kumkm Aceh
 
Application Of Microsoft Project To Manage Successful Project
Application Of Microsoft Project To Manage Successful ProjectApplication Of Microsoft Project To Manage Successful Project
Application Of Microsoft Project To Manage Successful ProjectJennifer Daniel
 
Where tonight mobile application.pdf
Where tonight  mobile application.pdfWhere tonight  mobile application.pdf
Where tonight mobile application.pdfokorisolo
 
Smart Speaker as Studying Assistant by Joao Pargana
Smart Speaker as Studying Assistant by Joao ParganaSmart Speaker as Studying Assistant by Joao Pargana
Smart Speaker as Studying Assistant by Joao ParganaHendrik Drachsler
 
Supporting Collaboration and Harnessing of OER Within the Policy Framework of...
Supporting Collaboration and Harnessing of OER Within the Policy Framework of...Supporting Collaboration and Harnessing of OER Within the Policy Framework of...
Supporting Collaboration and Harnessing of OER Within the Policy Framework of...Saide OER Africa
 
Health OER Inter-Institutional Project Formative Evaluation of Health OER Des...
Health OER Inter-Institutional Project Formative Evaluation of Health OER Des...Health OER Inter-Institutional Project Formative Evaluation of Health OER Des...
Health OER Inter-Institutional Project Formative Evaluation of Health OER Des...Saide OER Africa
 
M.Sc Dissertation: Simple Digital Libraries
M.Sc Dissertation: Simple Digital LibrariesM.Sc Dissertation: Simple Digital Libraries
M.Sc Dissertation: Simple Digital LibrariesLighton Phiri
 

Similar to PRM601 Final Project_Magana_J (20)

Monitoring of project implementation
Monitoring of project implementationMonitoring of project implementation
Monitoring of project implementation
 
Project Management Sample
Project Management SampleProject Management Sample
Project Management Sample
 
Mbg spmp project_management
Mbg spmp project_managementMbg spmp project_management
Mbg spmp project_management
 
Group charter projectcode_v1
Group charter projectcode_v1Group charter projectcode_v1
Group charter projectcode_v1
 
QBD_1464843125535 - Copy
QBD_1464843125535 - CopyQBD_1464843125535 - Copy
QBD_1464843125535 - Copy
 
Chat Application [Full Documentation]
Chat Application [Full Documentation]Chat Application [Full Documentation]
Chat Application [Full Documentation]
 
A.R.C. Usability Evaluation
A.R.C. Usability EvaluationA.R.C. Usability Evaluation
A.R.C. Usability Evaluation
 
CS4099Report
CS4099ReportCS4099Report
CS4099Report
 
Trinity Impulse - Event Aggregation to Increase Stundents Awareness of Events...
Trinity Impulse - Event Aggregation to Increase Stundents Awareness of Events...Trinity Impulse - Event Aggregation to Increase Stundents Awareness of Events...
Trinity Impulse - Event Aggregation to Increase Stundents Awareness of Events...
 
Semester 5 Experts in Teams Project - Opus
Semester 5 Experts in Teams Project - OpusSemester 5 Experts in Teams Project - Opus
Semester 5 Experts in Teams Project - Opus
 
10 guidetoproposalwriting
10 guidetoproposalwriting10 guidetoproposalwriting
10 guidetoproposalwriting
 
SW605F15_DeployManageGiraf
SW605F15_DeployManageGirafSW605F15_DeployManageGiraf
SW605F15_DeployManageGiraf
 
Application Of Microsoft Project To Manage Successful Project
Application Of Microsoft Project To Manage Successful ProjectApplication Of Microsoft Project To Manage Successful Project
Application Of Microsoft Project To Manage Successful Project
 
Where tonight mobile application.pdf
Where tonight  mobile application.pdfWhere tonight  mobile application.pdf
Where tonight mobile application.pdf
 
Smart Speaker as Studying Assistant by Joao Pargana
Smart Speaker as Studying Assistant by Joao ParganaSmart Speaker as Studying Assistant by Joao Pargana
Smart Speaker as Studying Assistant by Joao Pargana
 
Supporting Collaboration and Harnessing of OER Within the Policy Framework of...
Supporting Collaboration and Harnessing of OER Within the Policy Framework of...Supporting Collaboration and Harnessing of OER Within the Policy Framework of...
Supporting Collaboration and Harnessing of OER Within the Policy Framework of...
 
Health OER Inter-Institutional Project Formative Evaluation of Health OER Des...
Health OER Inter-Institutional Project Formative Evaluation of Health OER Des...Health OER Inter-Institutional Project Formative Evaluation of Health OER Des...
Health OER Inter-Institutional Project Formative Evaluation of Health OER Des...
 
M.Sc Dissertation: Simple Digital Libraries
M.Sc Dissertation: Simple Digital LibrariesM.Sc Dissertation: Simple Digital Libraries
M.Sc Dissertation: Simple Digital Libraries
 
Montero thesis-project
Montero thesis-projectMontero thesis-project
Montero thesis-project
 
thesis
thesisthesis
thesis
 

PRM601 Final Project_Magana_J

  • 1. 1    Page            All  citations  are  from:  Project  Management  Institute.  (2013).  A  guide  to  the  project  management  body   of  knowledge.  (5th  Ed.).  Newton  Square,  PA:  Author.         This  table  of  Contents  is  automatically  generated.    Press  the  F9  key  to  update  the  entire  table  and  the  page   numbers.     Contents   Instructions  for  Working  with  Templates  .................................................................................................................  2 Initiating  Process  Group  ...........................................................................................................................................  3 PMBOK®  Guide–  Initiating  Processes  ..................................................................................................................  3 PMBOK®  Guide  Chapter  4  -­‐  Integration  Management  Processes  .....................................................................  14 PMBOK®  Guide  Chapter  7  -­‐  Cost  Management  Planning  Processes  .................................................................  52 Planning  B  Process  Group  ......................................................................................................................................  56 PMBOK®  Guide  Chapter  11  –  Risk  Management  Planning  Processes  ...............................................................  56       This  List  of  Templates  is  automatically  generated.    Press  the  F9  key  to  update  the  entire  table  and  the  page   numbers.       List  of  Templates     01a  Initiation  Template:    Business  Case  for  a  Proposed  Project  ..................................................................  3 4.1a  Project  Charter  .....................................................................................................................................  7 13.1  a.  Stakeholder  Register  and  Stakeholder  Strategy  .............................................................................  11 13.1  b.  Stakeholder  Communication  Strategies  .........................................................................................  12 13.1  c.    Impact  and  Interest  Stakeholder  Analysis  .....................................................................................  13 5.1a  Scope  Management  Plan  ....................................................................................................................  15 5.2a.  Requirements  Documentation  ..........................................................................................................  16 5.3a  Project  Scope  Statement  ....................................................................................................................  17 5.4a  WBS  –  Work  Breakdown  Structure  ....................................................................................................  21 6.2a    Milestone  List  ....................................................................................................................................  26 6.3.a.  Activity  List  with  Dependency  Attributes  .........................................................................................  28 6.4a.  Activity  List  with  Resource  Attributes  ...............................................................................................  31 6.4b.  Resource  Summary  ...........................................................................................................................  50 7.2.a.  Activity  Cost  Estimates  .....................................................................................................................  53 7.3.a.  Cost  Performance  Baseline  ..............................................................................................................  54 11.2a  Risk  Register  .....................................................................................................................................  57 11.3a  Risk  Register  .....................................................................................................................................  58 11.5a    Risk  Register  ....................................................................................................................................  61 11.3b  Risk  Probability  and  Impact  (P&I)  Matrix  .........................................................................................  63   Note:  Sections  6.6a  (Schedule  Baseline)  and  7.3a  (Cost  Performance  Baseline)  were  either  skipped  or   partially  skipped  per  assignment  instructions  dated  –  2/4/2014  by  Professor  Johnson
  • 2. 2    Page            All  citations  are  from:  Project  Management  Institute.  (2013).  A  guide  to  the  project  management  body   of  knowledge.  (5th  Ed.).  Newton  Square,  PA:  Author.           Instructions  for  Working  with  Templates     Draft  versions  of  project  documents:       • Work  directly  in  copies  of  the  templates   • Replace  all  instances  of  “Your  text  here”  with  your  own  project  information.     • Each  table  has  a  header  row  that  is  automatically  repeated  when  the  document  spans  additional   pages.     • Keeping  a  line  of  text  between  tables  (boxes)  will  avoid  problems  with  tables  accidentally  merging   and  potentially  disappearing,  which  is  a  known  issue  with  Microsoft  Word  tables.   • Consider  the  information  included  in  the  blocks  that  provide  overviews  of  the  inputs,  outputs,  tools   and  techniques  to  help  answer  some  of  the  specific  questions.     Final  versions  of  project  documents:  Copy  and  paste  the  appropriate  sections  into  your  final  document.   • Include  a  project  title  block  at  the  beginning  of  a  section.   • You  may  choose  to  include  the  blocks  that  provide  overviews  of  the  inputs,  outputs,  tools  and   techniques  if  you  find  them  useful.         Project  Title  Block-­‐  Paste  this  block  above  project  documents  to  identify  the  revision  date,  the  project  name,  the   sponsor  and  the  project  manager..     Revision  Date:  Friday,  May  8,  2015     Project  Name:  Swimlane  Cruise  Line  Gift  Shops  Project                                                     Sponsor:    Mr.  Dennis  Horvatt,  President  of  Construction,  TFSB  Construction,  Inc.       Project  Manager(s):  Jerry  P.  Magaña                                                                        
  • 3. 3    Page            All  citations  are  from:  Project  Management  Institute.  (2013).  A  guide  to  the  project  management  body   of  knowledge.  (5th  Ed.).  Newton  Square,  PA:  Author.           Initiating  Process  Group     The  initiating  process  group  is  summarized  in  section  3.3  of  the  PMBOK  Guide.  Specific  information  about  the   purpose  and  characteristics  of  each  process  is  available  in  the  PMBOK  Guide  in  the  sections  noted.     PMBOK®  Guide–  Initiating  Processes   Knowledge  Area   Process   Inputs   Tools  and  Techniques     Outputs   Integration   4.1  Develop   Project  Charter   Project  SOW,  Business   Case,  Contracts,    OPAs   and  EEFs     Expert  Judgment   Input  01a:  Business   Case   4.1a  Project  Charter   Communications   13.1  Identify   Stakeholders   Project  Charter,   Procurement   documents,  EEF,  OPA     Stakeholder  analysis,    Expert  Judgment,   Meetings   13.1a  Stakeholder   Register.   13.1b  Communication   Strategies   13.1c  Impact  and   Interest  Analysis       Initiating  Integration  Element   01a  Initiation  Template:    Business  Case  for  a  Proposed  Project     The  Business  Case  is  an  input  to  the  project  initiating  process  and  is  typically  prepared  by  the  “customer”.     Proposed  Project  Name:         Swimlane  Cruise  Ship  (in  association  with  the  “No  More  Starving  Families”  program)  Gift  Shops  Project     Proposed  Location:       The  Starve  No  More  Foundation’s,  Swimlane  Cruise  Ship  (SCS)     Type  of  Project:       Not  for  Profit;  Maritime  Construction     1.0  Introduction/Background   Describe  the  sponsoring  organization  and  the  proposed  project  environment.   TFSB  Construction,  Inc.  (heretofore  known  as,  the  Organization)  was  founded  in  1973  by  construction  magnate  and   philanthropist,  Jonathon  H.  Temmingson  and  has  been  serving  various  commercial  and  not  for  profit  organizations  for   more  than  40  years.     After  more  than  40  years  of  providing  design  and  construction  services  for  non  for  profit  groups,  industrial,  residential,   commercial  and  maritime  projects,  Mr.  Temmingson’s  lifelong  dedication  to  his  humanitarian  projects  prompted  him  to   develop  a  division  dedicated  to  non  for  profit  maritime  construction  projects.       By  working  on  the  Foundation’s  Swimlane  Cruise  Ship  project,  the  Organization  will  help  to  ensure  that  the  Foundation   will  be  able  to  continue  providing  for  the  families  that  depend  on  their  support,  even  long  after  Ms.  Corday’s  involvement   with  the  Foundation  has  ended.  It  is  the  hope  of  both  the  Organization  (sponsor)  and  the  Foundation  (customer)  that  by   creating  a  specialty  cruise  liner  that  appeals  to  affluent  patrons,  this  will  help  to  continue  to  raise  funds  for  Ms.  Corday’s   Foundation,  thus  solving  the  problem  of  obtaining  and  maintaining  a  reliable  source  of  funding  as  well  as  solidifying  the   longevity  of  the  Foundation  for  years  to  come.      
  • 4. 4    Page            All  citations  are  from:  Project  Management  Institute.  (2013).  A  guide  to  the  project  management  body   of  knowledge.  (5th  Ed.).  Newton  Square,  PA:  Author.         01a  Initiation  Template:    Business  Case  for  a  Proposed  Project     The  Business  Case  is  an  input  to  the  project  initiating  process  and  is  typically  prepared  by  the  “customer”.     2.0  Business  Objective:   How  does  the  project  connect  to  the  mission  of  the  sponsoring  organization?   The  scope  of  the  Swimlane  Cruise  Ship  project  includes  the  following:  a)  Ship  Structure  Build,  b)  Fixtures  and  Decorations,   c)  Software/Hardware/Electronics,  d)  Kitchen  and  Food  Services,  e)  Events  Coordination,  and  f)  Gift  Shops.       This  project  will  focus  on  item  ‘f,’  Gift  Shops.     The  opportunity  this  project  presents  is  a  means  to  provide  a  lasting  service  to  the  customer  in  an  effort  to  insure   revenue  for  underprivileged  families  that  are  lacking  proper  nutritional  needs  to  sustain  life.       Due  to  challenging  conditions  of  financial  support,  combined  with  a  growing  trend  for  interest  in  consumers  selecting   Cruises  for  vacations,  the  Organization  expects  that  this  opportunity  will  provide  the  necessary  funds  to  feed  in  excess  of   1000  families  for  a  six-­‐month  period,  as  well  as  pay  for  the  costs  of  the  project  through  pre-­‐purchased  vacation  packages   by  wealthy  SCS  patrons.     The  project  deliverables  shall  include  a  total  of  5  gift  shops:  1,  centrally  located,  ‘main,’  2-­‐level  gift  shop,  and  4  additional   smaller  ‘satellite’  gift  shops  located  around  the  various  common  areas  of  the  ship.       3.0  Current  Situation  and  Problem/Opportunity  Statement   Provide  a  high  level  overview.  What  is  the  problem  that  needs  to  be  solved  or  the  opportunity  that  can  be  captured?     To  date,  Ms.  Corday  and  her  Foundation  have  relied  on  personal  funds  to  organize  charitable  events  in  an  attempt  to   attract  other  wealthy  donors.  Now  that  Ms.  Corday’s  funds  are  in  jeopardy  of  being  exhausted,  new  methods  for   attracting  donors  have  become  necessary.       In  years  past,  effective  fundraising  has  been  an  issue  for  the  Starve  No  More  Foundation  and  Ms.  Corday  and  the   Foundation  has  relied  heavily  on  her  own  personal  contributions  to  ensure  the  success  of  their  mission.       In  a  proactive  attempt  to  prevent  the  Foundation’s  imminent  insolvency,  Ms.  Corday  strongly  desires  the  legacy  of  her   and  her  family’s  hard  work  to  be  nationally  recognized  by  an  unprecedented  undertaking:  the  building  of  a  privately   owned  and  operated  pleasure  cruise  line  that  will  continue  to  raise  funds  to  support  the  mission  of  the  Foundation  for   the  foreseeable  future.     The  SCS  Gift  Shops  will  provide  luxurious  amenities  and  feature  quality  custom  items  for  retail  purchase  of  the  SCS   patrons  for  years  to  come.  The  profits  from  the  SCS  Gift  Shops  will  be  used  to  support  the  day-­‐to-­‐day  SCS  operating  costs   as  well  as  the  funding  needs  of  the  Foundation  in  further  support  of  its  mission.       4.0  Critical  Assumptions  and  Constraints   For  the  purposes  of  planning,  what  future  events  or  factors  should  be  considered  to  be  true,  real  or  certain  that  are   currently  not  fully  understood?       Currently,  no  cruise  ship  exists  and  must  be  constructed  per  the  specification  of  the  sponsor,  Ms.  Corday,  and  the   Foundation.  The  structure  of  the  vessel  must  be  completed  and  its  structural  integrity  approved  prior  to  the  construction   of  the  Gift  Shops  within  the  interior  of  its  hull.     Constraints:  What  are  the  some  of  the  most  important  known  limitations  to  the  options  available  to  the  project  team?   Work  on  the  gift  shops  must  begin  after  the  completion  of  the  SCS  hull  and  super-­‐structure.  The  vessels  hull  must  be   considered  sea-­‐worthy  and  approved  by  various  US  Government  Agencies  including  the  US  Coast  Guard  and  the   American  Bureau  of  Shipping  prior  to  starting  the  construction  of  any  of  the  5  gift  shops.        
  • 5. 5    Page            All  citations  are  from:  Project  Management  Institute.  (2013).  A  guide  to  the  project  management  body   of  knowledge.  (5th  Ed.).  Newton  Square,  PA:  Author.         01a  Initiation  Template:    Business  Case  for  a  Proposed  Project     The  Business  Case  is  an  input  to  the  project  initiating  process  and  is  typically  prepared  by  the  “customer”.       5.0  Analysis  of  Options  and  Recommendations   Describe  the  alternative  approaches  that  could  be  used  to  meet  the  organizational  objective.   The  gift  shops  project  can  begin  the  design  deliverables  phase  concurrent  to  the  trails  of  the  SCS  hull  and  super-­‐structure.   Should  the  hull  structural  project  incur  delays  as  a  result  of  work  stoppage,  USCG,  or  ABS  approval  delays,  upon  approval   of  the  gift  shops  designs,  the  gift  shops  structural  construction  can  begin  off-­‐site  and  be  completed  in  modular  sections   allowing  them  to  be  installed  into  the  SCS’s  super-­‐structure  when  it  is  safe  to  do  so.       6.0  Preliminary  Project  Requirements   Provide  a  high  level  overview.  How  will  you  know  when  you  are  done?    How  will  you  know  when  you  have  been  successful     • Allow  ample  shopping  space  for  SCS  patrons,   • Allow  ample  retail  space  for  merchandizing  fixtures,  refrigerated  coolers,  glass  jewelry  display  cases,  and  point  of   sale  counters  for  all  gift  shops,     • Allow  more  than  the  minimum  required  points  of  egress  in  the  event  of  emergencies  for  all  gift  shops,   • Procure  and  install  plumbing  and  fixtures  for  two  (2)  gender  specific  restrooms  in  the  main  gift  shop  and  one  (1)   family  restroom  for  each  of  the  satellite  gift  shops,   • Design  and  construct  and  install  at  least  two  (2)  fitting  rooms  in  the  main  gift  shop  and  one  (1)  fitting  room  for   each  of  the  satellite  gift  shops,   • Design  and  construct  the  main  gift  shop  with  enough  storage/stocking  space  and  administrative  office  space  to   accommodate  all  gift  shops.   7.0  Budget  Estimate  and  Financial  Analysis   Project  Costs   Estimate  key  project  costs   What  will  you  have  to  purchase?    Who  will  fund  the  project?   The  majority  of  the  gift  shops  project  will  be  spent  in  both  labor  and  construction  materials  for  the  SCS  Gift  Shops  Project.     The  budget  baseline  for  the  gift  shops  project  (minus  10%  contingency)  is  currently  $1,076,467.11  and  is  broken  down   into  the  following  sub-­‐categories:     Wages:                                          $197,219.76  -­‐  includes  estimates  for  overtime  and  various  fringes.   Materials:                                $836,187.35  -­‐  includes  estimates  for  structural,  interior,  and  exterior  construction  materials.   Fixed  Costs:                          $43,060  -­‐  includes  costs  associated  with  inspection  fees,  licensing,  material  storage  and  security,   elevator  fabrication  and  freight  to  construction  site,  and  miscellaneous  expenses.   10%  Contingency:    $107,647.00   GRAND  TOTAL:            $  1,184,114.11     The  Starve  No  More  foundation  is  financially  responsible  for  all  SCS  Gift  Shop  Project  related  costs  and  fees.     8.0  Schedule  Estimate   Provide  key  project  milestones  such  as  when  the  project  starts  and  ends  and  key  points  that  indicate  progress.   Start  date:  Monday,  April  21 st ,  2014                                                                      End  Date:  Monday,  January  19 th ,  2015   Key  milestones  include:  
  • 6. 6    Page            All  citations  are  from:  Project  Management  Institute.  (2013).  A  guide  to  the  project  management  body   of  knowledge.  (5th  Ed.).  Newton  Square,  PA:  Author.         01a  Initiation  Template:    Business  Case  for  a  Proposed  Project     The  Business  Case  is  an  input  to  the  project  initiating  process  and  is  typically  prepared  by  the  “customer”.       Project  Plan  Approval:  Friday,  May  2 nd ,  2014   Gift  Shops  Design  Approval:  Tuesday,  July  8 th ,  2014   Floor  plan,  Structural,  and  Utility  Drawings  Approval:  Wednesday,  October  1 st ,  2014   Structural  Construction  Approval:  Friday,  December  26 th ,  2014   Completed  Interiors  Approval:  Friday,  January  9 th ,  2015   Completed  Exteriors  Approval:  Tuesday,  January  13 th ,  2015   Final  Approval  and  Delivery  of  Gift  Shops:  Monday,  January  19 th ,  2015     9.0  Potential  Risks   What  events  might  occur  that  could  negatively  (or  positively)  impact  the  project  objectives  if  they  did  happen?     • The  ship  hull,  or  super-­‐structure,  is  not  finished  before  the  scheduled  start  date  of  the  gift  shops  construction.     • The  Starve  No  More  Foundation  runs  out  of  funds  before  the  Gift  Shops  Project  is  scheduled  to  start.     • Approval  milestones  may  take  longer  than  anticipated.     • Construction  and  final  approval  of  Gift  Shops  occurs  ahead  of  schedule.     • The  Foundation  could  abandon  the  project  in  favor  of  procuring  a  cruise-­‐liner  to  refurbish  instead  of  design  and   build.     10.0  Financial  Analysis   Evaluate  the  return  on  investment  for  the  proposed  project.   The  SCS  Gift  Shops  will  provide  luxurious  amenities  and  feature  quality  custom  items  for  retail  purchase  of  the  SCS   patrons  for  years  to  come.  The  profits  from  the  SCS  Gift  Shops  will  be  used  to  support  the  day-­‐to-­‐day  SCS  operating  costs   as  well  as  the  funding  needs  of  the  Foundation  in  further  support  of  its  mission.     The  5  Gift  Shops  of  the  SCS  will  be  designed  with  the  highest  quality  and  amenities  to  attract  patrons  who  are  conscience   of  the  Starve  No  More  Foundations  mission  statement.  With  the  on-­‐going  patronage  of  the  SCS  patrons,  the  Foundation   can  expect  to  see  a  15%  -­‐  25%  ROI  within  5  –  10  years  of  receipt  of  completed  and  approved  gift  shops.              
  • 7. 7    Page            All  citations  are  from:  Project  Management  Institute.  (2013).  A  guide  to  the  project  management  body   of  knowledge.  (5th  Ed.).  Newton  Square,  PA:  Author.         Initiating  Integration  Element    (PRM600-­‐    Complete  all  items  in  the  project  charter).       4.1a  Project  Charter   The  Project  Charter  formally  authorizes  a  project  or  project  phase  and  documents  initial  requirements.  Multiple   charters  may  be  used  to  validate  or  refine  decisions  made  for  multi-­‐phase  projects.     Business  Need  /  Who  Will  Benefit:   What  events  or  conditions  helped  create  the  need  for  this  project?  Who  will  benefit  from  this  endeavor?   In  a  proactive  attempt  to  prevent  the  Foundation’s  imminent  insolvency,  Ms.  Corday  strongly  desires  the  legacy  of  her   and  her  family’s  hard  work  to  be  nationally  recognized  by  an  unprecedented  undertaking:  the  building  of  a  privately   owned  and  operated  pleasure  cruise  line,  the  Swimlane  Cruise  Ship,  which  will  continue  to  raise  funds  to  support  the   mission  of  the  Foundation  for  the  foreseeable  future.     Project  Purpose  /  Justification  –  Alignment  with  Mission   Why  is  the  project  being  approved?    How  does  it  align  with  the  organization’s  mission  or  strategic  plan?   This  Charter  formally  authorizes  a  project  to  perform  the  research,  development  and  implementation  of  the  design  and   production  of  a  Swimlane  Cruise  Ship  (SCS)  with  its  sole  purpose  to  raise  funds  to  help  feed  starving  families  around  the   world.     Project  Objectives     What  will  the  project  produce?  How  will  we  know  that  the  project  objectives  have  been  successfully  accomplished?     This  project  will  produce:       1)  Designs  for  a  total  of  five  (5)  SCS  Gift  Shops.   2)  A  total  of  ten  (10)  unique  artistic  renderings  and  perspective  drawings  of  each  of  the  five  (5)  Gift  Shops  for   Foundation  approval.   3)  Floor  plans,  structural  blue  prints,  construction  plans  and  bill  of  materials,  and  utility  drawings  for  each  of  the  five  (5)   Gift  Shops  for  Foundation  approval.   4)  Constructed  five  (5)  Gift  Shops  in  accordance  to  the  approval  guidelines  of  the  Foundation.   5)  Project  management  services  throughout  the  planning,  design,  and  construction  phases  of  the  SCS  Gift  Shops  project.       The  following  success  criteria  will  be  used  to  demonstrate  accomplished  objectives.   • Provide  ten  (10)  unique  artistic  renderings,  including  perspective  drawings  that  depict  all  five  (5)  gift  shops  in   use,  which  will  specifically  demonstrate  design  elements  of  both  interiors  and  exteriors  of  each  gift  shop.   • Design  one  (1)  rectangular-­‐shaped,  centralized,  two-­‐level,  4500  sq.  ft.  main  gift  shop  with  an  ‘open  atrium’   (looking  down  to  the  first  floor)  second  level  with  one  (1)  single  landing  stair  case  on  the  north  side  and  one  (1)   eight  (8)  person  capacity  hydraulic  elevator  on  the  south  side.   • Design  the  remaining  four  (4)  oval-­‐shaped,  single-­‐level,  1500  sq  ft.  satellite  gift  shops.   • Provide  an  “open  air”  access  design  of  the  main  gift  shop,  with  multiple  entrances  into  the  first  floor  of  no  less   than  20  feet  per  entrance  on  all  four  sides.     • Provide  an  “open  air”  access  design  of  the  satellite  gift  shops,  with  one  (1)  entrance  of  no  less  than  15  feet  on   only  one  side  per  gift  shop.   • Provide  motorized,  concealable,  and  recessed  security  roll-­‐up  doors  for  all  entranceways  for  each  gift  shop   using  durable,  transparent,  and  scratch-­‐resistant  materials.  Each  door  should  be  able  to  be  locally  and   remotely  operated.   • Provide  no  less  than  500  sq  ft.  of  concealable  stocking  space  within  the  main  gift  shop,  and  no  less  than  100  sq   ft.  of  concealable  stocking  space  within  the  satellite  gift  shops.     • Provide  no  less  than  300  sq  ft.  of  administrative  office  space  within  the  centralized  gift  shop.   • Provide  two  (2)  gender  specific,  120  sq  ft.,  single  stall  restrooms  within  the  main  gift  shop  and  one  (1)  single  
  • 8. 8    Page            All  citations  are  from:  Project  Management  Institute.  (2013).  A  guide  to  the  project  management  body   of  knowledge.  (5th  Ed.).  Newton  Square,  PA:  Author.         4.1a  Project  Charter   The  Project  Charter  formally  authorizes  a  project  or  project  phase  and  documents  initial  requirements.  Multiple   charters  may  be  used  to  validate  or  refine  decisions  made  for  multi-­‐phase  projects.     fixture,  80  sq  ft.  family  restroom  within  each  of  the  satellite  gift  shops.   • Provide  two  (2)  changing  rooms  within  the  main  gift  shop  and  one  (1)  changing  room  within  each  of  the   satellite  gift  shops.  No  changing  room  should  exceed  15  sq  ft.   • Provide  enough  area  to  accommodate  various  merchandizing  fixtures  for  all  gift  shops,  including  refrigerated   coolers,  jewelry  display  cases,  apparel  racks,  wall  and  floor  rack  shelving,  and  miscellaneous  counter  tops.   • Provide  enough  area  to  accommodate  one  (1)  100  sq  ft.  circular  point  of  sale  (POS)  counter  in  each  gift  shop.   The  POS  counter  will  be  located  in  the  center  of  the  first  floor  of  the  main  gift  shop  and  within  the  center  of  all   of  the  satellite  gift  shops.   • Provide  detailed  blue  prints  and  construction  plans  for  all  five  (5)  gift  shops.   • Construct  all  gift  shops  utilizing  best  practices  of  retail  and  maritime  construction  techniques.   • Provide  finishing  construction  (carpeting,  paint,  accents,  fixtures,  etc.)  work  upon  completion  of  structural   construction  in  accordance  to  the  approval  guidelines  of  the  Foundation.   • Project  Management  services  must  be  conducted  using  PMI  methodologies  incorporating  monthly  status   report  meetings.   Approved  Budget:    (See  detailed  Funding  Request)    $  1,184,114.11   How  much  will  the  project  cost?  How  much  spending  should  be  authorized  on  this  project?             The  budget  baseline  for  the  gift  shops  project  (minus  10%  contingency)  is  currently  $1,076,467.11  and  is  broken  down   into  the  following  sub-­‐categories:     Wages:                                          $197,219.76  -­‐  includes  estimates  for  overtime  and  various  fringes.   Materials:                                $836,187.35  -­‐  includes  estimates  for  structural,  interior,  and  exterior  construction  materials.   Fixed  Costs:                          $43,060  -­‐  includes  costs  associated  with  inspection  fees,  licensing,  material  storage  and  security,   elevator  fabrication  and  freight  to  construction  site,  and  miscellaneous  expenses.   10%  Contingency:    $107,647.00   GRAND  TOTAL:            $  1,184,114.11     Project  Milestones       When  will  key  events  happen?  What  deadlines  are  known?  How  will  we  know  progress  is  being  made?     Project  Start:  Monday,  April  21 st ,  2014   Project  Plan  Approval:  Friday,  May  2 nd ,  2014   Gift  Shops  Design  Approval:  Tuesday,  July  8 th ,  2014   Floor  plan,  Structural,  and  Utility  Drawings  Approval:  Wednesday,  October  1 st ,  2014   Structural  Construction  Approval:  Friday,  December  26 th ,  2014   Completed  Interiors  Approval:  Friday,  January  9 th ,  2015   Completed  Exteriors  Approval:  Tuesday,  January  13 th ,  2015   Final  Approval  and  Delivery  of  Gift  Shops:  Monday,  January  19 th ,  2015                  
  • 9. 9    Page            All  citations  are  from:  Project  Management  Institute.  (2013).  A  guide  to  the  project  management  body   of  knowledge.  (5th  Ed.).  Newton  Square,  PA:  Author.         4.1a  Project  Charter   The  Project  Charter  formally  authorizes  a  project  or  project  phase  and  documents  initial  requirements.  Multiple   charters  may  be  used  to  validate  or  refine  decisions  made  for  multi-­‐phase  projects.     Constraints:   What  are  the  known  limitations  to  the  options  available  to  the  project  team?     Currently,  no  cruise  ship  exists  and  must  be  constructed  per  the  specification  of  the  sponsor,  Ms.  Corday,  and  the   Foundation.  The  structure  of  the  vessel  must  be  completed  and  its  structural  integrity  approved  prior  to  the   construction  of  the  Gift  Shops  within  the  interior  of  its  hull.     Work  on  the  gift  shops  must  begin  after  the  completion  of  the  SCS  hull  and  super-­‐structure.  The  vessels  hull  must  be   considered  sea-­‐worthy  and  approved  by  various  US  Government  Agencies  including  the  US  Coast  Guard  and  the   American  Bureau  of  Shipping  prior  to  starting  the  construction  of  any  of  the  5  gift  shops.     This  is  the  first  large-­‐scale,  long-­‐term  project  of  its  kind  for  the  project  sponsor,  Ms.  Corday  and  the  Starve  No  More   Foundation.  Currently,  this  project  also  represents  the  first  maritime  construction  project  for  the  Foundation  and  as   such,  contractors  will  need  to  rely  heavily  on  experienced  shipbuilder’s  expert  judgment  during  the  all  phases  of  the   ship  build.   Assumptions:   For  the  purposes  of  planning,  what  uncertain  factors  will  be  considered  to  be  true,  real  or  certain?         The  gift  shops  project  can  begin  the  Design  deliverables  phase  concurrent  to  the  trails  of  the  SCS  hull  and  super-­‐ structure.  Should  the  hull  structural  project  incur  delays  as  a  result  of  work  stoppage,  USCG,  or  ABS  mandates,  upon   approval  of  the  gift  shops  designs,  the  gift  shops  structural  construction  can  begin  off-­‐site  and  be  completed  in  modular   sections  allowing  them  to  be  installed  into  the  SCS’s  super-­‐structure  when  it  is  safe  to  do  so.     Roles   Who  is/  will  be  assigned  to  manage?    What  are  they  authorized  to  approve  for  spending,  leading,  etc?     Project  Manager:  Jerry  P.  Magaña               Authority  level:     Budget:  The  project  manager  is  authorized  to  distribute  funds  for  equipment,  fees,  construction  materials,  and  other   related  expenses  to  the  current  baselined  amount  of  $879,247.35     The  Organization’s  accounting  and  payroll  department  will  distribute  and  account  for  wages  applied  to  the  project,   currently  estimated  not  to  exceed  $197,219.76.       The  project  manager  may  not  exceed  the  approved  baselined  amount  of  $879,247.35  by  no  more  than  3%  for  needs   that  arise  as  a  result  of  unforeseen  circumstances  (or  contingency).  If  an  increase  it  required,  the  Project  Manager  will   notify  the  project  sponsor,  Mr.  Horvatt  and  the  appropriate  project  stakeholders  prior  to  the  decision  to  release   additional  contingency  funds.  If  the  Project  Manager  foresees  costs  exceeding  3%  over  the  current  baselined  budget,   the  cause  will  need  to  be  presented  and  approved  by  the  project  sponsor.       Staffing:  The  project  manager  is  responsible  for  the  hiring  of  key  construction,  design,  and  engineering  staff.  These  key   staff  members  will  be  responsible  the  hiring  and  direction  of  the  required  crew  necessary  for  completing  the  project   sponsors  approved  design  and  construction  plans  for  the  SCS  Gift  Shops.     Communication:  The  project  manager  is  required  to  review  and  advise  the  project  sponsor,  Ms.  Corday,  the  Board  of   Directors  of  the  Starve  No  More  Foundation,  and  key  project  stakeholders  on  the  status  of  the  SCS  Gift  Shops  Project  on   a  monthly  basis  throughout  the  duration  of  the  project.     These  monthly  progress  meetings  will  take  place  on  the  first  Thursday  of  each  month  and  the  written  minutes  of  each   status  report  are  due  no  later  than  the  following  Monday  via  email.  
  • 10. 10    Page            All  citations  are  from:  Project  Management  Institute.  (2013).  A  guide  to  the  project  management  body   of  knowledge.  (5th  Ed.).  Newton  Square,  PA:  Author.         4.1a  Project  Charter   The  Project  Charter  formally  authorizes  a  project  or  project  phase  and  documents  initial  requirements.  Multiple   charters  may  be  used  to  validate  or  refine  decisions  made  for  multi-­‐phase  projects.       Change  Control:  Project  managers  are  in  charge  of  communicating  any  changes  made  to  the  project  to  the  project   sponsor.    Project  managers  are  allowed  to  make  changes  as  long  as  they  do  not  exceed  1%  of  the  allocated  budget  and   do  not  push  a  deadline  over  10  days.    Any  changes  outside  these  limitations  need  to  be  reviewed  and  approved  by  the   project  sponsor.     OPA    Organizational  process  assets       What  artifacts  from  the  organization  or  outside  could  be  useful  in  our  planning  process,  including  lessons  learned  on   past  projects?     • The  Organization’s  database  of  previously  used  and  approved  vendors  for  both  human  resources  in  various   construction  trade  and  materials.   • The  Organization’s  knowledge  base  of  previous  experience  working  with  non-­‐profit  entities  and  their  projects.   • The  Organization’s  knowledge  base  of  planning,  lessons  learned,  and  previously  used  experiences  of  pleasure   cruise  liner  and  other  maritime  construction  projects.   • The  Organization’s  connections  to  and  understanding  of  various  approval  authorities  for  similar  construction   projects  including  the  United  States  Coast  Guard  and  the  American  Bureau  of  Shipping.   • The  Organization’s  policies  and  procedures  in  regards  to  working  with  non-­‐profit  projects.   • The  Organization’s  expertise  within  engineering,  construction,  design,  and  staffing  similar  large-­‐scale  maritime   construction  projects.         EEF      Enterprise  Environmental  Factors         What  external  factors  impact  our  planning?  From  what  sources  were  these  EEFs  gathered?       • The  Organization  requires  the  use  of  skilled  and  experienced  maritime  construction  trade  persons  to  undertake   such  an  endeavor.   • The  Organization  is  relying  exclusively  on  the  good  faith  of  the  Foundation  to  provide  the  financial  support  of   the  project.   • The  Organization  understands  that  the  Foundation  for  which  the  work  is  to  be  performed  has  little  to  no   experience  in  such  large-­‐scale  projects,  and  non  with  respect  to  maritime  construction.   • The  maritime  nature  of  the  project  is  subject  to  frequent  inclement  weather  delays.   • The  nature  of  the  project  being  construction  is  subject  to  labor  union  staffing  and  as  such,  may  impose  a  work   stoppage  as  a  result  of  a  contract  dispute.   • The  success  of  the  Gift  Shops  project  relies  on  the  performance  of  other  entities  that  the  Foundation  (Sponsor)   has  contracted  with;  ie:  hull  and  super-­‐structure  construction,  fixtures,  décor,  etc.         Risks         What  are  the  potential  threats  and  opportunities?  What  uncertain  future  events  could  impact  the  project  if  they  did   happen?     • The  ship  hull,  or  super-­‐structure,  is  not  finished  before  the  scheduled  start  date  of  the  gift  shops  construction.     • The  Starve  No  More  Foundation  runs  out  of  funds  before  the  Gift  Shops  Project  is  scheduled  to  start.     • Approval  milestones  may  take  longer  than  anticipated.     • Construction  and  final  approval  of  Gift  Shops  occurs  ahead  of  schedule.  
  • 11. 11    Page            All  citations  are  from:  Project  Management  Institute.  (2013).  A  guide  to  the  project  management  body   of  knowledge.  (5th  Ed.).  Newton  Square,  PA:  Author.         4.1a  Project  Charter   The  Project  Charter  formally  authorizes  a  project  or  project  phase  and  documents  initial  requirements.  Multiple   charters  may  be  used  to  validate  or  refine  decisions  made  for  multi-­‐phase  projects.     RISKS  (CONTINUED)     • The  Foundation  could  abandon  the  project  in  favor  of  procuring  a  cruise-­‐liner  to  refurbish  instead  of  design   and  build.       Initiating  Communication  Element  (PRM600  –  Create  at  least  8  rows  of  stakeholders).     13.1  a.  Stakeholder  Register  and  Stakeholder  Strategy   The  stakeholder  register  identifies  the  stakeholder  groups  and  analyzes  their  influence  and  interest  in  the  project,   which  allows  them  to  be  classified  into  categories  so  that  appropriate  strategies  can  be  defined  for  each  category  of   stakeholders.     Name       Include  the  title  or   name  of  the  group  or   Individual     Category   A,  B,                  C  or  D?   (See   matrix)     Interest  in  the  Project   (High  or  Low)   What  makes  them  a   stakeholder?  Are  they  impacted   or  do  they  impact  the  project?   Will  they  be  users  of  the  project   deliverables?  Are  they  directly  or   tangentially  interested?   Influence  on  the  Project   (High  or  Low)   What  power  or  influence  on  the   project  could  this  group  generate?     Do  they  create  or  assess   deliverables?  Are  they  financially   committed?       Mr.  Dennis  Horvatt,   Pres.  Of  Const.  TFSB   Const.,  Inc.,  Project   Sponsor   A   High   High     Ms.  Marie  Corday,   Customer     A     High     High       Board  of  Directors,   Starve  No  More   Foundation,  Customer   A   High   High     United  States  Coast   Guard  (USCG)   C   Low   High     American  Bureau  of   Shipping  (ABS)   C   Low   High     Project  Management   Team   B   High   Low     Construction   Foreperson   B   High   Low     Interior  Design   Manager   B   High   Low     Construction  Material   Vendors   D   Low   Low    
  • 12. 12    Page            All  citations  are  from:  Project  Management  Institute.  (2013).  A  guide  to  the  project  management  body   of  knowledge.  (5th  Ed.).  Newton  Square,  PA:  Author.         Construction   Inspectors   D   Low   Low     Port  Master   D   Low   Low     SCS  Patrons   D   Low   Low     Organization’s  Chief   Engineer   C   Low   High       Initiating  Communication  Element    (PRM600-­‐  Complete  all  items).     13.1  b.  Stakeholder  Communication  Strategies     Communications  strategies  must  be  identified  for  each  stakeholder  category  to  increase  the  support  and  minimize   the  negative  impacts  of  stakeholders  throughout  the  entire  life  cycle  of  the  project.         Name       List  the  key  groups   in  each    category  of   stakeholders     Strategies  for  Gathering   Support   What  will  you  do  to   encourage  positive   influences  from  them?   Strategies  for  Reducing   Obstacles     What  will  you  do  to  reduce   negative  influences  from   them?   Expectations     What  does  this  group   expect  from  you  for   communications,   support,  etc.   A-­‐High  Interest  and   High  Influence   1.  Mr.  Dennis   Horvatt,  Pres.  Of   Const.  TFSB  Const.,   Inc.,  Proj.  Sponsor   2.  Ms.  Marie   Corday,  Customer   3.  Board  of   Directors,  Starve  No   More  Foundation,   Customer     Manage  Closely   Closely  monitor  and  relay   information  as  it  develops.   Be  transparent  with  project   related  activities  and   expenses.  Encourage   efficient  and  clear   presentation  of  all   correspondences.     Remain  transparent  on   project  budget  issues;   provide  interior  design   samples,  create  and  foster   an  open  channel  of   communication  between   these  stakeholders  and  key   project  personnel.       Timeliness  of  all   important  reports  or   project-­‐related  events   and  milestones.   Provide  monthly  status   reports  of  the  project   that  will  take  place  on   the  first  Thursday  of   each  month,  then  email   the  typed  minutes  of   each  status  meeting  no   later  than  the  following   Monday.     B-­‐High  Interest  but   low  influence   1.  Project   Management  Team   2.  Construction   Foreperson       Keep  Informed   Stay  organized,  but  avoid   information  overload.   Provide  relevant  project   materials  required  for   feedback  and  approval  only.   Keep  reports  concise  and  at   a  level  of  detail  that  can  be   considered  ‘snapshots.’     Verify  activities  and   resources  required  to   achieve  project   requirements.  Advise  on   changes  to  these   requirements  as  soon  as   possible.  Meet  project   deadlines  and  milestones   as  indicated,  take   responsibility  and  avoid   assigning  blame.     Inform  about  major   events  or  project   changes,  continue  to   update  through  bi-­‐ weekly  video,  tele-­‐ conference,  face-­‐to-­‐ face  meetings,  or   written  and  emailed   memorandum   distribution  as   required.       C-­‐  High  Influence   but  low  interest     Keep  Satisfied   Keep  project  materials  in   Don’t  delay  providing   information  on  unexpected   Share  significant   project  milestones  and  
  • 13. 13    Page            All  citations  are  from:  Project  Management  Institute.  (2013).  A  guide  to  the  project  management  body   of  knowledge.  (5th  Ed.).  Newton  Square,  PA:  Author.         1.  USCG   2.  ABS   3.  Construction   Inspectors   4.  Organization’s   Chief  Engineer     order,  concise  and  efficient.   Ensure  the  lines  of   communication  between   other  project  stakeholders   remain  open  and  flowing  at   all  times.  Inform  on   important  project  milestones   or  project  events  that  may   impact  these  stakeholders  at   all  times.       project  variables.  Keep   them  in  the  loop  and  up  to   date  on  significant  changes   to  the  project  schedule,   requirements,  and/or   budget  (if  required).     keep  these   stakeholders  in  all   critical  project   conversations.       D-­‐  Low  Interest  and   Low  Influence   1.  Construction   Material  Vendors   2.  SCS  Patrons   3.  Port  Master       Monitor     Provide  information  that  is   easy  to  understand  and   access,  keep  informed  via   email  on  changes.  Provide   simple  status  and  project   communications  via  a   project  based  website.     Provide  access  to  a  project   database  via  the  Internet   that  will  relay  information   between  these   stakeholders  and  other  key   project  team  members.     Provide  a  project-­‐ related  website  with   information  available  in   multiple  languages  that   is  easily  downloadable   and  easily  accessible.   Keep  it  current  and  up-­‐ to-­‐date  with  important   project  changes  and   information.       Initiating  Communication  Element  (Type  the  names  of  the  stakeholders  in  the  appropriate  boxes.).       13.1  c.    Impact  and  Interest  Stakeholder  Analysis   The  Stakeholder  Analysis  Matrix  portrays  the  relationships  between  stakeholder  groups  and   the  management  strategy  appropriate  for  each  stakeholder  group.      STAKEHOLDER  ANALYSIS  MATRIX        <<      Influence  or  Power  of  Stakeholder     Little/No  Interest   Significant   Interest   Significant   Influence     1.  United  States  Coast  Guard   (USCG)   2.  American  Bureau  of  Shipping   (ABS)   3.  Construction  Inspectors   4.  Organization’s  Chief  Engineer     C     Keep  Satisfied     1.  Mr.  Dennis  Horvatt,  President  of   Construction,  TFSB  Construction,  Inc.,   Project  Sponsor   2.  Ms.  Marie  Corday,  Customer   3.  Board  of  Directors,  Starve  No  More   Foundation,  Customer     A     Manage  Closely   Little  or  No   Influence           1.  Construction  Material  Vendors   2.  SCS  Patrons   3.  Port  Master     D       Monitor  (minimum  effort)     1.  Project  Management  Team   2.  Construction  Foreperson   3.  Interior  Design  Manager     B       Keep  Informed   Importance  or  Interest  Level  of  Stakeholder  >>       End  of  Initiating  Documents  
  • 14. 14    Page            All  citations  are  from:  Project  Management  Institute.  (2013).  A  guide  to  the  project  management  body   of  knowledge.  (5th  Ed.).  Newton  Square,  PA:  Author.         Planning  A  Process  Group     Purpose:  The  purpose  of  the  planning  process  group  is  to  establish  the  total  scope  of  the  effort,  define   and  refine  the  project  objectives,  and  develop  the  course  of  action  required  to  attain  those  objectives.   These  processes  develop  the  project  management  plan  and  the  project  documents  that  will  be  used  to   carry  out  the  project.       Specific  information  about  the  purpose  and  characteristics  of  each  process  is  available  in  the  PMBOK   Guide  in  the  sections  noted.  The  planning  process  group  is  split  into  two  sections,  labeled  A  and  B,  to   reduce  the  size  of  the  template.     Planning  Group  A  includes  the  knowledge  areas  of  Integration,  Scope,  Time  and  Cost.  (Secs.  4,5  6  &  7).   Planning  Group  B  includes  the  knowledge  areas  of  Quality,  Human  Resources,  Communications,  Risk,   Procurement  and  Stakeholder  Management.  (Secs..  8,9,10,11,12  &  13).   PMBOK®  Guide  Chapter  4  -­‐  Integration  Management  Processes   Project  Name:                                                                              Revision  Date:         Sponsor:                                                                                                Date  Signed:     Sponsoring  Organization:                                      Signature:  __________________     Knowledge   Area   Process   Inputs   Tools  and  Techniques     Outputs     Integration   4.2  Develop   Project   Management   Plan   Project  charter,   Outputs  of  other   processes,  EEF  and   OPA     Expert  Judgment,   facilitation  techniques   4.2  Project  Management   Plan       Planning  A  Integration  Element  –  PRM600    No  revisions  needed.   4.2a.  Integrated  Project  Management  Plan   The  Project  Management  Plan  integrates  and  consolidates  all  of  the  subsidiary  management  plans  and   baseline.    Every  project  methodology  should  be  tailored  to  the  size  and  complexity  of  the  project.       Results  of  Tailoring  by  the  Project  Management  Team   • Project  Baselines  will  be  included  for:  scope,  schedule  and  cost.       • Detailed  Subsidiary  Plans  will  NOT  be  provided  in  this  plan.    An  OPA  will  be  used  without   tailoring.    This  OPA  includes  an  organizational  mandate  for  common  management  plans  for   scope,  requirements,  schedule,  cost,  quality,  process  improvement,  HR,  communications,  risk,   procurement  and  stakeholder  management.     • No  specific  life  cycle  plan  will  be  used.     • Certain  detailed  plans  will  be  used.    See  the  LIST  OF  TEMPLATES  included  at  the  beginning  of  this   document  for  a  detailed  list.          
  • 15. 15    Page            All  citations  are  from:  Project  Management  Institute.  (2013).  A  guide  to  the  project  management  body   of  knowledge.  (5th  Ed.).  Newton  Square,  PA:  Author.         PMBOK®  Guide  Chapter  5  -­‐  Scope  Management  Processes   Knowledge   Area   Process   Inputs   Tools  and  Techniques     Outputs   Scope     5.1  Plan   Scope   Management   PM  plan,   charter,  EEF,   OPA   Expert  judgment  and   meetings.   5.1a  Scope  Management   Plan  and  Requirements   Management  Plan     Scope   5.2  Collect   Requirements   Scope  mgmt.   plan,  Req.   mgmt.  plan,   stakeholder   mgmt.  plan.   Project   charter   Stakeholder   register   Group  and  individual  data   collection  and  decision-­‐ making   techniques,(interviews,   focus  groups,  observations,   surveys,  prototypes)    expert   judgment,  product  analysis   and  facilitated  workshops   such  as  JAD  sessions,   context  diagrams,       5.2a  Requirements   Documentation       Scope   5.3  Define   Scope   Outputs  of  5.1   and  5.2,   Charter,  EEF  &   OPA     Expert  judgment,  product   analysis,  alternatives   identification  and   facilitated  workshops  such   as  JAD  sessions     5.3a  Project  Scope   Statement,    project   document  updates.   Scope   5.4  Create   WBS   Outputs  of   5.1,  5.2  and   5.3,  EEF  and   OPA     Decomposition  and  Expert   Judgment   Scope  Baseline    consisting   of:     5.3a  WBS  and     5.3b  WBS  Dictionary     Scope  Planning  Element  –  (PRM600    -­‐No  revisions  needed.)   5.1a  Scope  Management  Plan     The  Scope  Management  Plan  describes  how  the  scope  will  be  defined,  developed,  monitored,  controlled  and   verified.     Inputs  Used   Identify  specific  inputs  needed  before  the  Scope  Management  Plan  and  the  Requirements  Management  Plan   can  be  created.         The  Charter  is  used  to  provide  a  high-­‐level  project  description  and  high-­‐level  product  characteristics.  EEF:     The  organizational  culture  can  be  described  as:       The  Organization  contracts  with  various  clients  around  the  globe  and  is  a  leader  in  the  construction  industry.  From   projects  that  include  commercial,  industrial,  agricultural,  residential,  and  maritime,  this  organization  works  with  a   variety  of  clients  who  specializes  in  not  for  profit  endeavors.         OPA:    The  policies  and  procedures  are  provided  by  the  main  organization’s  PMO.      
  • 16. 16    Page            All  citations  are  from:  Project  Management  Institute.  (2013).  A  guide  to  the  project  management  body   of  knowledge.  (5th  Ed.).  Newton  Square,  PA:  Author.         Tools  and  Techniques  Used   Identify  the  tools  and  techniques  used  to  create  the  plans.  Explain  how  you  used  the  tools.   Expertise  on  methods  used  to  define,  develop,  monitor  and  control  scope  will  be  provided  by  the   organization’s  PMO.     Meetings  will  be  held  where  the  PMO  can  tailor  the  plans  to  the  size  and  complexity  of  this  project.       Output:  The  Scope  management  plan  to  be  provided  by  the  organization’s  PMO  includes  a  process  for   preparing  a  detailed  scope  statement  and  a  WBS,  and  processes  to  manage  changes  and  to  track   acceptance  of  deliverables.     Output:  The  Requirements  Management  Plan  to  be  provided  by  the  organization’s  PMO.  Includes  templates   and  instructions  for  determining  how  requirements  will  be  planned,  tracked  and  reported.  The  consultants   will  help  implement  a  process  for  prioritizing  requirements,  managing  changes  to  requirements,  and  using  a   traceability  matrix  and  developing  metrics.       Planning  A  Scope  Element  (PRM600    -­‐Add  rows  for  five  specific  requirements.)   5.2a.  Requirements  Documentation   This  table  describes  how  individual  requirements  meet  the  business  need  for  the  project.  During  early   planning  stages,  requirements  are  defined  at  a  high  level  and  become  progressively  more  detailed  during   project  execution.    Requirements  must  be  unambiguous  so  that  they  can  be  traced.   Stakeholder   (group)   Person  /  group   that  will   approve  or   accept  a   deliverable     Requirement     Describe  a  part  of  the  product   that  will  be  delivered  such  as  a   document,  service,  product  or   result.   Acceptance  Criteria     Describe  how  the   stakeholder  will  evaluate   the  finished  element.   Priority  (HML)   Category   Select  High,   Medium  or   Low  for   priority  level.       ID   #   PMO     Project  Baselines  for  Scope,  Cost  and   Schedule   The  senior  member  of  the   PMO  will  sign  off  on  the   baselines  if  they  meet   criteria  for  level  of  detail  and   attainability.     High   R1   1.  Mr.  Dennis   Horvatt,  Pres.  Of   Const.  TFSB   Const.,  Inc.,  Proj.   Sponsor   2.  Ms.  Marie   Corday,  Customer   3.  Board  of   Directors,  Starve   No  More   Foundation,   Customer   Completed  SCS  Gift  Shops,  approved   plans,  designs,  construction,  interior   and  exterior  elements   The  Project  Sponsor,  Ms.   Corday,  and  the   Foundation’s  Board  will  sign   off  on  project  milestones  via   regular  consultation,   monthly  status  meetings,   written  correspondence,   written  approval  letters,  and   a  formal  letter  of   acceptance.     High   R2   1.  USCG   2.  ABS   3.  Construction   Inspectors   4.  Organization’s   Chief  Engineer   Formal  written  approvals  and  official   seals  for  construction  including   structural,  utility,  and  for  the  safety,   security,  and  seaworthy  integrity  of   its  patrons  and  staff.     Through  comprehensive   inspections,  review,  and   engineering  tests.   Medium   R3   1.  Project   Plan,  execute,  monitor,  control,  and   Through  the  use  of  OPA  and   Medium   R4  
  • 17. 17    Page            All  citations  are  from:  Project  Management  Institute.  (2013).  A  guide  to  the  project  management  body   of  knowledge.  (5th  Ed.).  Newton  Square,  PA:  Author.         5.2a.  Requirements  Documentation   This  table  describes  how  individual  requirements  meet  the  business  need  for  the  project.  During  early   planning  stages,  requirements  are  defined  at  a  high  level  and  become  progressively  more  detailed  during   project  execution.    Requirements  must  be  unambiguous  so  that  they  can  be  traced.   Stakeholder   (group)   Person  /  group   that  will   approve  or   accept  a   deliverable     Requirement     Describe  a  part  of  the  product   that  will  be  delivered  such  as  a   document,  service,  product  or   result.   Acceptance  Criteria     Describe  how  the   stakeholder  will  evaluate   the  finished  element.   Priority  (HML)   Category   Select  High,   Medium  or   Low  for   priority  level.       ID   #   Management   Team   2.  Construction   Foreperson   3.  Interior  Design   Manager   close  the  project  management  plan,   construction  plan,  and  interior   design  milestones.       understanding  of  EFF’s  of   similar  projects,  lessons   learned,  and  expert   judgment.   1.  Construction   Material  Vendors   2.  SCS  Patrons   3.  Port  Master   Will  provide  construction  materials,   furtherance  the  support  of  the   Foundation’s  mission  and  goals  in   the  form  of  patronage  of  the  Gift   Shops  for  years  to  come,  and  access   to  various  resources  during  the   construction  of  the  SCS  Gift  Shops.     In  the  form  of  banners  to   demonstrate  materials  and   services  by;  the  enjoyment  of   the  amenities;  by  providing   access  to  resources  and   skilled  labor  specific  to  the   maritime  industry.   Low   R5     Planning  A  Scope  Element  (PRM600  –  Fill  out  the  content  areas.)   5.3a  Project  Scope  Statement   The  Project  Scope  Statement  provides  a  common  understanding  of  the  project  scope  among  all   stakeholders  and  provides  a  baseline  for  evaluating  whether  requests  for  changes  or  additional  work  are   inside  or  outside  the  project’s  boundaries.       Description  of  the  Product   Describe  the  end  product,  service  or  result  that  the  project  will  produce.       1. Provide  ten  (10)  unique  artistic  renderings,  including  perspective  drawings  that  depict  all  five  (5)  gift   shops  in  use,  which  will  specifically  demonstrate  design  elements  of  both  interiors  and  exteriors  of   each  gift  shop.   2. Design  one  (1)  rectangular-­‐shaped,  centralized,  two-­‐level,  4500  sq.  ft.  main  gift  shop  with  an  ‘open   atrium’  (looking  down  to  the  first  floor)  second  level  with  one  (1)  single  landing  stair  case  on  the   north  side  and  one  (1)  eight  (8)  person  capacity  hydraulic  elevator  on  the  south  side.   3. Design  the  remaining  four  (4)  oval-­‐shaped,  single-­‐level,  1500  sq  ft.  satellite  gift  shops.   4. Provide  an  “open  air”  access  design  of  the  main  gift  shop,  with  multiple  entrances  into  the  first  floor   of  no  less  than  20  feet  per  entrance  on  all  four  sides.     5. Provide  an  “open  air”  access  design  of  the  satellite  gift  shops,  with  one  (1)  entrance  of  no  less  than  15   feet  on  only  one  side  per  gift  shop.   6. Provide  motorized,  concealable,  and  recessed  security  roll-­‐up  doors  for  all  entranceways  for  each  gift  
  • 18. 18    Page            All  citations  are  from:  Project  Management  Institute.  (2013).  A  guide  to  the  project  management  body   of  knowledge.  (5th  Ed.).  Newton  Square,  PA:  Author.         5.3a  Project  Scope  Statement   The  Project  Scope  Statement  provides  a  common  understanding  of  the  project  scope  among  all   stakeholders  and  provides  a  baseline  for  evaluating  whether  requests  for  changes  or  additional  work  are   inside  or  outside  the  project’s  boundaries.       shop  using  durable,  transparent,  and  scratch-­‐resistant  materials.  Each  door  should  be  able  to  be   locally  and  remotely  operated.   7. Provide  no  less  than  500  sq  ft.  of  concealable  stocking  space  within  the  main  gift  shop,  and  no  less   than  100  sq  ft.  of  concealable  stocking  space  within  the  satellite  gift  shops.     8. Provide  no  less  than  300  sq  ft.  of  administrative  office  space  within  the  centralized  gift  shop.   9. Provide  two  (2)  gender  specific,  120  sq  ft.,  single  stall  restrooms  within  the  main  gift  shop  and  one  (1)   single  fixture,  80  sq  ft.  family  restroom  within  each  of  the  satellite  gift  shops.   10. Provide  two  (2)  changing  rooms  within  the  main  gift  shop  and  one  (1)  changing  room  within  each  of   the  satellite  gift  shops.  No  changing  room  should  exceed  25  sq  ft.   11. Provide  enough  area  to  accommodate  various  merchandizing  fixtures  for  all  gift  shops,  including   refrigerated  coolers,  jewelry  display  cases,  apparel  racks,  wall  and  floor  rack  shelving,  and   miscellaneous  counter  tops.   12. Provide  enough  area  to  accommodate  one  (1)  220  sq  ft.  circular  point  of  sale  (POS)  counter  in  each   gift  shop.  The  POS  counter  will  be  located  in  the  center  of  the  first  floor  of  the  main  gift  shop  and   within  the  center  of  all  of  the  satellite  gift  shops.   13. Provide  detailed  blue  prints  and  construction  plans  for  all  five  (5)  gift  shops.   14. Construct  all  gift  shops  utilizing  best  practices  of  retail  and  maritime  construction  techniques.   15. Provide  finishing  construction  (carpeting,  paint,  accents,  fixtures,  etc.)  work  upon  completion  of   structural  construction  in  accordance  to  the  approval  guidelines  of  the  Foundation.   16. Project  management  services  must  be  conducted  using  PMI  methodologies  incorporating  monthly   status  reports.     Product  Acceptance  Criteria   Describe  how  the  stakeholder  will  accept  the  final  product.       The  Foundations  acceptance  of  the  deliverables  will  be  based  on  reports,  approval  and  inspections  of  the  project   management  plan,  designs,  construction  plans  and  requirements  as  listed  in  the  section  above  as  well  as  the   following  deliverable  requirements  below:       i) Submit  for  Foundation  approval  a  total  of  fifty  (50)  artists’  renderings  and  perspective  drawings   demonstrating  unique  design  elements  of  the  interior  and  exterior  for  each  gift  shop.  Ten  (10)   drawings  per  gift  shop.   ii) Submit  for  Foundation  approval  a  total  of  one  hundred  (100)  photographic  and  physical  samples  of   colors,  fixtures,  textures,  and  interior  design  elements  for  each  gift  shop  and  relative  areas,  which   demonstrate  a  unique  look  and  feel  for  each  gift  shop.      
  • 19. 19    Page            All  citations  are  from:  Project  Management  Institute.  (2013).  A  guide  to  the  project  management  body   of  knowledge.  (5th  Ed.).  Newton  Square,  PA:  Author.         5.3a  Project  Scope  Statement   The  Project  Scope  Statement  provides  a  common  understanding  of  the  project  scope  among  all   stakeholders  and  provides  a  baseline  for  evaluating  whether  requests  for  changes  or  additional  work  are   inside  or  outside  the  project’s  boundaries.       iii) Detailed  and  approved  structural  construction  floor  plans,  in  plan  view,  for  each  gift  shop.   iv) Detailed  and  approved  Construction  blue  prints  for  each  gift  shop.   v) Detailed  and  approved  electrical,  plumbing,  and  hydraulics  plans  for  each  gift  shop.   vi) Detailed  and  approved  bill  of  construction  materials  that  are  in  keeping  with  modern  retail  and   maritime  building  codes  subject  to  the  laws  of  the  United  States,  and  the  US  Coast  Guard  for  each  gift   shop.   vii) Finalized  structural  construction  of  one  (1)  rectangular-­‐shaped,  two-­‐level,  4500  sq.  ft.  main  gift  shop   and  four  (4)  oval-­‐shaped,  single  level,  1500  sq  ft.  satellite  gift  shops.   viii) Finalized  structural  construction,  installation,  and  testing  of  one  (1)  single  landing  staircase  to  be   located  at  the  north  end  and  one  (1)  eight-­‐person  capacity,  hydraulic  elevator  to  be  installed  at  the   south  end  of  the  main  gift  shop.   ix) Completed  finish  construction  elements,  design  and  accents,  carpeting,  tile,  paint,  lighting  and   restroom  fixtures,  telecommunications  and  data  ports,  installed  and  tested  safety  and  security   systems,  CCTV,  loss  prevention  systems,  etc.  for  each  gift  shop.   x) Project  management  plan  with  monthly  status  reports.     Project  Deliverables   Please  refer  to  the  WBS  for  a  complete  list  of  project  deliverables       Project  Exclusions   Describe  any  items  stakeholder  may  have  considered  that  are  outside  of  the  project  boundaries.     The  product  specifically  excludes:       • Stocking  the  completed  Gift  Shops  with  merchandise   • Procure  merchandise  for  the  completed  Gift  Shops   • Staffing  the  completed  Gift  Shops   • Training  staff  of  the  completed  Gift  Shops   • Procuring,  storing,  assembling,  or  handling  the  placement  of  specialized  merchandizing  fixtures  for  the   completed  Gift  Shops   • Sub-­‐contracting  the  work  required  to  procure,  store,  assemble,  handle,  or  place  specialized   merchandizing  fixtures  for  the  completed  Gift  Shops   • Design,  place,  install,  or  make  arrangements  thereof  for  any  SCS  specialized  marketing  signage,  or  other   related  artwork  for  the  completed  Gift  Shops   • Provide  or  assemble  any  of  the  completed  Gift  Shops  with  any  additional  furnishings   • Install  additional  video  or  audio  systems  for  any  of  the  completed  Gift  Shops   • Procuring,  storing,  assembling,  or  handling  the  placement  of  specialized  Point-­‐Of-­‐Sale  computer   equipment,  workstations,  cash  registers,  etc.  for  the  completed  Gift  Shops   • Sub-­‐contracting  the  work  required  to  procure,  store,  assemble,  handle,  or  place  specialized  Point-­‐Of-­‐Sale   computer  equipment,  workstations,  cash  registers,  etc.  for  the  completed  Gift  Shops  
  • 20. 20    Page            All  citations  are  from:  Project  Management  Institute.  (2013).  A  guide  to  the  project  management  body   of  knowledge.  (5th  Ed.).  Newton  Square,  PA:  Author.         5.3a  Project  Scope  Statement   The  Project  Scope  Statement  provides  a  common  understanding  of  the  project  scope  among  all   stakeholders  and  provides  a  baseline  for  evaluating  whether  requests  for  changes  or  additional  work  are   inside  or  outside  the  project’s  boundaries.       Project  Constraints   List  any  factors  that  limit  the  options  available  to  the  project  team.     Constraints  include:     • That  the  hull  and  super-­‐structure  of  the  ship  will  be  completed  prior  to  the  commencing  of  the  Gift  Shops   construction.   • Approvals  of  the  design,  floor  plans,  structure,  and  utilities  must  be  approved  by  the  various  governing   authority  in  maritime  construction  and  the  Organization’s  Chief  Engineer  prior  to  the  commencement  of   the  construction  phase  of  the  Gift  Shops.   • In  addition  to  the  various  governing  authorities’  approval,  the  Organization  must  obtain  written   acknowledgement  from  the  Project  Sponsor  before  any  of  the  project  approval  milestones  can  be   considered  completed.   • Approvals  of  the  structural  construction  and  the  completed  interiors  (including  utilities  of  all  Gift  Shops,   the  staircase,  elevator  construction,  and  operation  of  the  main  Gift  Shop)  must  be  approved  by  the   various  governing  authority  in  maritime  construction  and  the  Organization’s  Chief  Engineer  prior  to  final   delivery  and  approval  of  the  completed  Gift  Shops  to  the  Project  Sponsor.   • Approvals  of  the  completed,  installed,  and  operational  components  of  all  Gift  Shop  exteriors  must  be   approved  by  the  various  governing  authority  in  maritime  construction  and  the  Organization’s  Chief   Engineer  prior  to  final  delivery  and  approval  of  the  completed  Gift  Shops  to  the  Project  Sponsor.     Project  Assumptions   List  any  factors  that  were  assumed  in  project  planning,  and  indicate  what  may  happen  if  it  turns  out  that  these   assumptions  were  false.       Assumption  #1  -­‐  The  ship  hull,  or  super-­‐structure,  is  finished  before  the  scheduled  start  date  of  the  gift  shops   construction.                                                 If  Assumption  #1  is  false,  then:  designs,  structural  blue  prints,  and  utility  drawings  packages  can  occur  concurrently   to  the  ship  hull  construction  project.  The  Gift  Shops  will  begin  structural  construction  and  fabrication  adjacent  to   SCS  super-­‐structure  port  and  be  assembled  in  a  modular  fashion  after  ship  hull  is  complete.     Assumption  #2  -­‐  The  Starve  No  More  Foundation  will  provide  full  funding  to  the  Gift  Shops  Project  and  throughout   the  projects  final  delivery.                                       If  Assumption  #2  is  false,  then:  the  Organization  will  file  a  mechanics  lien  on  the  SCS  project  and  secure  a  bond  in   the  amount  of  the  project  budget  (plus  contingency)  to  ensure  the  full  project  funding.     Assumption  #3  -­‐  The  amount  of  qualified  and  experienced  personnel  will  be  available  to  work  on  the  project  until   the  project  is  closed  and  the  Gift  Shops  have  been  delivered  to  the  Foundation.     If  Assumption  #3  is  false,  then:  The  Organization  will  provide  local  accommodations  to  experienced  and  qualified   workers  outside  the  region  of  the  construction  site.       Planning  A  Scope  Element  -­‐      (PRM600-­‐  complete  a  full  WBS  for  the  project  to  Level  2.    The  major   deliverable  6-­‐  Project  Management  –  has  been  completed  for  you.  .