SlideShare a Scribd company logo
1 of 1
Download to read offline
SUMMARY:
Artificial river has been designed to use
5cfs from the San Diego River to create a
varying depth and width channel that will
simulate a small stream. The artificial river
will serve as a local attraction and will
provide the City of San Diego a venue
from which to highlight the importance of
local water sources.
Calculations:
• Q=(1.49/n)AR2/3S0
1/2
Assumptions:
• Base: 10 feet
• Length: 2600 feet
• Change in Elevation: 2.6 feet
• Side Slope: 1
• Roughness Coefficient: 0.05
DESIGN:
The artificial river could have a depth of 8
inches to a foot with a base of 10feet.
Pump System:
The river will be pumped with 31hp
pumps:
COST:
Pump Cost: 6 x $2500 per pump =
$15,000
Electricity: 3 x 560 kWhr at $.08/kw-hr =
$134/day
Total cost: $50,000/year
SUMMARY:
Microfiltration will be used to
remove dissolved solids and
particles that cause turbidity in
water. This unit will be able to treat
2.6mgd of nonpotable water before
storage. (1.4mgd – Dewatering &
1.2mgd - Storm-water).
SPECS:
Membrane pore size: 0.1um - 5.0um.
Pressure: 30 psi to pushed the water
through the membrane.
USES:
• Irrigation
• Dual Plumbed Building
-Toilets
- Laundry
• CoolingTowers
• Augment Proposed Artificial River
COST:
Total: $3,630,000
SUMMARY:
WRE intends to provide the
Qualcomm site with an abundant
supply of non-potable water found
from excavating for construction
foundation. WRE has implemented a
permanent dewatering system that
will provide about 1.5 MGD of water
from two subgrade structures: a 40
MG water storage tank and parking
structure.
ASSUMPTIONS:
• Yields 1000gpm (1.4mgd)
groundwater
•Water Meets RWQCB Objectives
•Kinder Morgan Petroleum Facility
-Largely Complete
SUMMARY:
One of the water supply component
is storm-water captured from Serra
Mesa watershed.
An additional element of water
harvesting will be to capture and use
the storm-water runoff, specifically
from the Serra Mesa Canyon that
discharges in the northwest corner of
the site. Dry weather flows were
assumed to be 1.9cfs (1.2mgd).
Spatial analysis of the Mission Valley
Watershed was used to verify that
figure.
Project Objective:
Create a conceptual plan for water supply and water quality for the Qualcomm
Stadium Redevelopment. The conceptual plan will incorporate creative approaches to
offset the use of potable water that includes storm-water harvesting, groundwater,
and a creative approach that makes use of the San Diego River water.
Qualcomm Stadium Development Water Re-use Project
Dewatering System
Storage
MissionBay
San DiegoRiver
QualcommStadium
Serra MesaWatershed
Qualcomm
Stadium
I-15
San DiegoRiver
Serra MesaWatershed
I-8
Stormwater
Artificial River
Acknowledgement
Microfiltration
SUMMARY:
The tank is designed in accordance with
California Building Code 2013, AWWA D110, ACI
350, ACI 350.3 and incorporates state of the art
features such as close tolerance electro-servo
controlled wrapping, galvanized circumferential
prestressing, automated shotcrete, vertical post-
tensioning and utilizes flexible connections at the
wall base and wall top to improve seismic
performance.
CAPACITY:
40 Million gallons
450 ft. diameter and 40ft depth
Well Design
Structure Perimeter = 600 feet
Well Spacing = 50 feet
Number of Wells = 600/50 = 12 Wells
Cost of construction per
well = $20,000
Total Cost = $20,000 x 12 = $240,000
Pump Design
Pump Require = 12 pumps
Cost of each pump = $6,500
Total Cost of Pump = $6,500 x 12 = $78,000
Component Total Cost = $240,000 + $78,000 $318,000
Precipitation Data for San Diego
Water Year
(Oct. - Sep.)
Actual
Rainfall (in.)
Normal
Rainfall (in.)
2010 10.6 10.77
2011 12.7 10.34
2012 7.9 10.34
2013 6.55 10.34
2014 5.09 10.34
COST:
The estimate includes all work associated
with the construction and design of the
floor, wall footing, core wall, round
columns, two way, flat slab roof
(designed for 100 psf live load),
circumferential and vertical pre-
stressing, automated shotcrete and
standard appurtenances attached to the
tank (i.e. vent, hatch and exterior and
interior ladders.
$17,000,000.00
WRE would like to thank the following Professors and mentors: Alicia Kinoshita, Natalie Mladenov, John Prince, Tim Smith,
Tom Bloomer. Especially: James R. Haughey and Jim Rasmus from
.
Project Manager: Ismael Marquez
Civil : Rob Lane
Environmental: Jose Alcaraz
Environmental: Loren Miller
Environmental: Fed Pinongcos
Environmental: Heather Tegley
Team
The New Qualcomm stadium conceptual plan by the City of San Diego including an
Artificial River.
An Artificial River from Seoul Korea.
Conceptual Plan:
The final design that was created by Water
Resources Engineering (WRE) has four
primary components:
• An artificial river,
• A groundwater dewatering system,
• A storage reservoir for dry weather storm-
water flow
• A microfiltration unit that will treat the water
to non-potable standards to be used on any
future development plan.
If this conceptual plan is implemented, the
combination of storm-water flow and
dewatering system will generate 2.6MGD of
water that could be used to offset the
demand of potable water.
(Unit cost x flow)
= $9,000/MGD x 3 MGD =
= $27,000/*3 years = $9,000 per year
Membrane Filtration
equipment
(Estimated equipment cost x total
capacity)
= $.5/gpd x 3 MGD = $1,500,000
Energy cost to operate = (111356.233 m3/day x .05 kwh/m3) = 567.81 kwh/day
= (.1351/kwh x 567.81 kwh/day) = $77/day
= ($77/day x 365 days) = $28,105/year
Total annual Operation
and Maintenance cost $1,537,105
Capital Cost $3,630,000
Membrane replacement
*Filtration membranes should be replaced about every 3 years because the
membranes will not be put under too much stress.
Microfiltration: Operation and Maintenance Cost for 3 MGD flow
Project Cost:
Component Cost + Annual Operations and
Maintenance
=$23,231,500 + $286,365
=$23,517,865!
DS,
$1,285,760
, 6%
ST,
$17,000,000,
72%
AR,
$100,000,
0%
MS,
$5,167,105,
22%
Original
Groundwater Level
Made Ground
Proposed
Basement
ExcavationDewatering
Well Installed
Int. or Ext.
Temporary Reduced
Groundwater Level

More Related Content

What's hot

akshi jain_suruchi shah
akshi jain_suruchi shahakshi jain_suruchi shah
akshi jain_suruchi shahguestf0d083
 
Power point asce seawater desal project hb
Power point   asce seawater desal project hbPower point   asce seawater desal project hb
Power point asce seawater desal project hbRobert Martinez, PE
 
Water Supply - Design Approach And Methodologies
Water  Supply - Design Approach And MethodologiesWater  Supply - Design Approach And Methodologies
Water Supply - Design Approach And MethodologiesIr. Abdul Aziz Abas
 
Midterm presentation
Midterm presentationMidterm presentation
Midterm presentationcarolyncoffey
 
Midterm presentation
Midterm presentationMidterm presentation
Midterm presentationkarrisr
 
Suez Victorian Desalination Project
Suez Victorian Desalination ProjectSuez Victorian Desalination Project
Suez Victorian Desalination ProjectRick Nabett
 
Sustainable Hydropower Development Alternatives for the Mekong
Sustainable Hydropower Development Alternatives for the MekongSustainable Hydropower Development Alternatives for the Mekong
Sustainable Hydropower Development Alternatives for the MekongJessicaNagtalon
 
SULI_SUMMER_2015 Research POSTER_Cronin_John
SULI_SUMMER_2015 Research POSTER_Cronin_JohnSULI_SUMMER_2015 Research POSTER_Cronin_John
SULI_SUMMER_2015 Research POSTER_Cronin_JohnJack Cronin
 
India; Rain Water Harvesting and Artificial Recharge
India;  Rain Water Harvesting and Artificial RechargeIndia;  Rain Water Harvesting and Artificial Recharge
India; Rain Water Harvesting and Artificial RechargeD5Z
 
Revival of Open Wells in Belgaum
Revival of Open Wells in BelgaumRevival of Open Wells in Belgaum
Revival of Open Wells in Belgaumbiomeshubha
 
2014: Designing Dredge - Reconsidering the Toledo Riverfront
2014: Designing Dredge - Reconsidering the Toledo Riverfront2014: Designing Dredge - Reconsidering the Toledo Riverfront
2014: Designing Dredge - Reconsidering the Toledo Riverfrontnorthcoastdesigncompetition
 
Desalination of the Sea Around Us, Part I
Desalination of the Sea Around Us, Part IDesalination of the Sea Around Us, Part I
Desalination of the Sea Around Us, Part ICarol Reeb
 
Action taken by BWSSB in preventing pollution of Lakes
Action taken by BWSSB in preventing pollution of LakesAction taken by BWSSB in preventing pollution of Lakes
Action taken by BWSSB in preventing pollution of LakesEkonnect
 
Cubbon Park recharge wells completion report
Cubbon Park recharge wells completion reportCubbon Park recharge wells completion report
Cubbon Park recharge wells completion reportbiometrust
 
Robert Hughes and Michael Hewitt, EPCAMR, “3D Modeling of Eastern Pennsylvani...
Robert Hughes and Michael Hewitt, EPCAMR, “3D Modeling of Eastern Pennsylvani...Robert Hughes and Michael Hewitt, EPCAMR, “3D Modeling of Eastern Pennsylvani...
Robert Hughes and Michael Hewitt, EPCAMR, “3D Modeling of Eastern Pennsylvani...Michael Hewitt, GISP
 

What's hot (20)

akshi jain_suruchi shah
akshi jain_suruchi shahakshi jain_suruchi shah
akshi jain_suruchi shah
 
Power point asce seawater desal project hb
Power point   asce seawater desal project hbPower point   asce seawater desal project hb
Power point asce seawater desal project hb
 
Resource Recovery Panel
Resource Recovery PanelResource Recovery Panel
Resource Recovery Panel
 
Water Supply - Design Approach And Methodologies
Water  Supply - Design Approach And MethodologiesWater  Supply - Design Approach And Methodologies
Water Supply - Design Approach And Methodologies
 
Checkdam
CheckdamCheckdam
Checkdam
 
Midterm presentation
Midterm presentationMidterm presentation
Midterm presentation
 
Midterm presentation
Midterm presentationMidterm presentation
Midterm presentation
 
Suez Victorian Desalination Project
Suez Victorian Desalination ProjectSuez Victorian Desalination Project
Suez Victorian Desalination Project
 
today
todaytoday
today
 
Sustainable Hydropower Development Alternatives for the Mekong
Sustainable Hydropower Development Alternatives for the MekongSustainable Hydropower Development Alternatives for the Mekong
Sustainable Hydropower Development Alternatives for the Mekong
 
SULI_SUMMER_2015 Research POSTER_Cronin_John
SULI_SUMMER_2015 Research POSTER_Cronin_JohnSULI_SUMMER_2015 Research POSTER_Cronin_John
SULI_SUMMER_2015 Research POSTER_Cronin_John
 
India; Rain Water Harvesting and Artificial Recharge
India;  Rain Water Harvesting and Artificial RechargeIndia;  Rain Water Harvesting and Artificial Recharge
India; Rain Water Harvesting and Artificial Recharge
 
Revival of Open Wells in Belgaum
Revival of Open Wells in BelgaumRevival of Open Wells in Belgaum
Revival of Open Wells in Belgaum
 
2013: Designing Dredge Studio Toledo
2013: Designing Dredge Studio Toledo2013: Designing Dredge Studio Toledo
2013: Designing Dredge Studio Toledo
 
2014: Designing Dredge - Reconsidering the Toledo Riverfront
2014: Designing Dredge - Reconsidering the Toledo Riverfront2014: Designing Dredge - Reconsidering the Toledo Riverfront
2014: Designing Dredge - Reconsidering the Toledo Riverfront
 
Desalination of the Sea Around Us, Part I
Desalination of the Sea Around Us, Part IDesalination of the Sea Around Us, Part I
Desalination of the Sea Around Us, Part I
 
Action taken by BWSSB in preventing pollution of Lakes
Action taken by BWSSB in preventing pollution of LakesAction taken by BWSSB in preventing pollution of Lakes
Action taken by BWSSB in preventing pollution of Lakes
 
Cubbon Park recharge wells completion report
Cubbon Park recharge wells completion reportCubbon Park recharge wells completion report
Cubbon Park recharge wells completion report
 
Louisville MSD
Louisville MSDLouisville MSD
Louisville MSD
 
Robert Hughes and Michael Hewitt, EPCAMR, “3D Modeling of Eastern Pennsylvani...
Robert Hughes and Michael Hewitt, EPCAMR, “3D Modeling of Eastern Pennsylvani...Robert Hughes and Michael Hewitt, EPCAMR, “3D Modeling of Eastern Pennsylvani...
Robert Hughes and Michael Hewitt, EPCAMR, “3D Modeling of Eastern Pennsylvani...
 

Similar to Capstone

Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014
Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014
Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014Joseph Merzlak
 
NY: A Green Infrastructure Approach - Onondaga Creek Water Quality
NY: A Green Infrastructure Approach - Onondaga Creek Water QualityNY: A Green Infrastructure Approach - Onondaga Creek Water Quality
NY: A Green Infrastructure Approach - Onondaga Creek Water QualitySotirakou964
 
Lake Manzala Engineered Wetland, Port Said, Egypt [IWC4 Presentation]
Lake Manzala Engineered Wetland, Port Said, Egypt [IWC4 Presentation]Lake Manzala Engineered Wetland, Port Said, Egypt [IWC4 Presentation]
Lake Manzala Engineered Wetland, Port Said, Egypt [IWC4 Presentation]Iwl Pcu
 
Transbay Presentation Sustainable Silicon Valley
Transbay Presentation Sustainable Silicon ValleyTransbay Presentation Sustainable Silicon Valley
Transbay Presentation Sustainable Silicon Valleyjennyhenry
 
Permanent Canal Closures and Pumps Design-Build Project
Permanent Canal Closures and Pumps Design-Build ProjectPermanent Canal Closures and Pumps Design-Build Project
Permanent Canal Closures and Pumps Design-Build Projectfascinatedcatca33
 
Day 2 Innovative Programs
Day 2  Innovative ProgramsDay 2  Innovative Programs
Day 2 Innovative ProgramsGreg Gearheart
 
Organic Growth -- In a Manner of Speaking
Organic Growth -- In a Manner of SpeakingOrganic Growth -- In a Manner of Speaking
Organic Growth -- In a Manner of SpeakingDon Talend
 
Underground Wet Ponds for Stormwater Management in Wisconsin
Underground Wet Ponds for Stormwater Management in WisconsinUnderground Wet Ponds for Stormwater Management in Wisconsin
Underground Wet Ponds for Stormwater Management in WisconsinContech Engineered Solutions
 
1 How to Overcome Public Perception Issues on Potable R.docx
1  How to Overcome Public Perception Issues on Potable R.docx1  How to Overcome Public Perception Issues on Potable R.docx
1 How to Overcome Public Perception Issues on Potable R.docxpoulterbarbara
 
1 How to Overcome Public Perception Issues on Potable R.docx
1  How to Overcome Public Perception Issues on Potable R.docx1  How to Overcome Public Perception Issues on Potable R.docx
1 How to Overcome Public Perception Issues on Potable R.docxjeremylockett77
 
DSD-INT 2023 Example of unstructured MODFLOW 6 modelling in California - Romero
DSD-INT 2023 Example of unstructured MODFLOW 6 modelling in California - RomeroDSD-INT 2023 Example of unstructured MODFLOW 6 modelling in California - Romero
DSD-INT 2023 Example of unstructured MODFLOW 6 modelling in California - RomeroDeltares
 
Max KroschelResume061715
Max KroschelResume061715Max KroschelResume061715
Max KroschelResume061715Max Kroschel
 
Rainwater Harvesting For Decision Makers
Rainwater Harvesting For Decision MakersRainwater Harvesting For Decision Makers
Rainwater Harvesting For Decision MakersVictor Zapanta Manlapaz
 
Dew point proposal for city of santa cruz v6
Dew point   proposal for city of santa cruz v6Dew point   proposal for city of santa cruz v6
Dew point proposal for city of santa cruz v6ru55e11
 
ENVIRONMENTAL IMPACT ASSESSMENT ON DAL LAKE SRINAGAR KASHMIR
ENVIRONMENTAL IMPACT ASSESSMENT ON DAL LAKE SRINAGAR KASHMIRENVIRONMENTAL IMPACT ASSESSMENT ON DAL LAKE SRINAGAR KASHMIR
ENVIRONMENTAL IMPACT ASSESSMENT ON DAL LAKE SRINAGAR KASHMIRIRJET Journal
 

Similar to Capstone (20)

Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014
Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014
Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014
 
NY: A Green Infrastructure Approach - Onondaga Creek Water Quality
NY: A Green Infrastructure Approach - Onondaga Creek Water QualityNY: A Green Infrastructure Approach - Onondaga Creek Water Quality
NY: A Green Infrastructure Approach - Onondaga Creek Water Quality
 
Lake Manzala Engineered Wetland, Port Said, Egypt [IWC4 Presentation]
Lake Manzala Engineered Wetland, Port Said, Egypt [IWC4 Presentation]Lake Manzala Engineered Wetland, Port Said, Egypt [IWC4 Presentation]
Lake Manzala Engineered Wetland, Port Said, Egypt [IWC4 Presentation]
 
Transbay Presentation Sustainable Silicon Valley
Transbay Presentation Sustainable Silicon ValleyTransbay Presentation Sustainable Silicon Valley
Transbay Presentation Sustainable Silicon Valley
 
Permanent Canal Closures and Pumps Design-Build Project
Permanent Canal Closures and Pumps Design-Build ProjectPermanent Canal Closures and Pumps Design-Build Project
Permanent Canal Closures and Pumps Design-Build Project
 
EXCITE: Wing Tam
EXCITE: Wing Tam EXCITE: Wing Tam
EXCITE: Wing Tam
 
Day 2 Innovative Programs
Day 2  Innovative ProgramsDay 2  Innovative Programs
Day 2 Innovative Programs
 
INFORM: Adel Hagekhalil
INFORM: Adel HagekhalilINFORM: Adel Hagekhalil
INFORM: Adel Hagekhalil
 
Organic Growth -- In a Manner of Speaking
Organic Growth -- In a Manner of SpeakingOrganic Growth -- In a Manner of Speaking
Organic Growth -- In a Manner of Speaking
 
Assessment of Low Impact Design (LID)
Assessment of Low Impact Design (LID)Assessment of Low Impact Design (LID)
Assessment of Low Impact Design (LID)
 
Underground Wet Ponds for Stormwater Management in Wisconsin
Underground Wet Ponds for Stormwater Management in WisconsinUnderground Wet Ponds for Stormwater Management in Wisconsin
Underground Wet Ponds for Stormwater Management in Wisconsin
 
Mc Quirk Sess1 101509
Mc Quirk Sess1 101509Mc Quirk Sess1 101509
Mc Quirk Sess1 101509
 
1 How to Overcome Public Perception Issues on Potable R.docx
1  How to Overcome Public Perception Issues on Potable R.docx1  How to Overcome Public Perception Issues on Potable R.docx
1 How to Overcome Public Perception Issues on Potable R.docx
 
1 How to Overcome Public Perception Issues on Potable R.docx
1  How to Overcome Public Perception Issues on Potable R.docx1  How to Overcome Public Perception Issues on Potable R.docx
1 How to Overcome Public Perception Issues on Potable R.docx
 
DSD-INT 2023 Example of unstructured MODFLOW 6 modelling in California - Romero
DSD-INT 2023 Example of unstructured MODFLOW 6 modelling in California - RomeroDSD-INT 2023 Example of unstructured MODFLOW 6 modelling in California - Romero
DSD-INT 2023 Example of unstructured MODFLOW 6 modelling in California - Romero
 
Max KroschelResume061715
Max KroschelResume061715Max KroschelResume061715
Max KroschelResume061715
 
Rainwater Harvesting For Decision Makers
Rainwater Harvesting For Decision MakersRainwater Harvesting For Decision Makers
Rainwater Harvesting For Decision Makers
 
Dew point proposal for city of santa cruz v6
Dew point   proposal for city of santa cruz v6Dew point   proposal for city of santa cruz v6
Dew point proposal for city of santa cruz v6
 
Seminar aparna
Seminar aparnaSeminar aparna
Seminar aparna
 
ENVIRONMENTAL IMPACT ASSESSMENT ON DAL LAKE SRINAGAR KASHMIR
ENVIRONMENTAL IMPACT ASSESSMENT ON DAL LAKE SRINAGAR KASHMIRENVIRONMENTAL IMPACT ASSESSMENT ON DAL LAKE SRINAGAR KASHMIR
ENVIRONMENTAL IMPACT ASSESSMENT ON DAL LAKE SRINAGAR KASHMIR
 

Capstone

  • 1. SUMMARY: Artificial river has been designed to use 5cfs from the San Diego River to create a varying depth and width channel that will simulate a small stream. The artificial river will serve as a local attraction and will provide the City of San Diego a venue from which to highlight the importance of local water sources. Calculations: • Q=(1.49/n)AR2/3S0 1/2 Assumptions: • Base: 10 feet • Length: 2600 feet • Change in Elevation: 2.6 feet • Side Slope: 1 • Roughness Coefficient: 0.05 DESIGN: The artificial river could have a depth of 8 inches to a foot with a base of 10feet. Pump System: The river will be pumped with 31hp pumps: COST: Pump Cost: 6 x $2500 per pump = $15,000 Electricity: 3 x 560 kWhr at $.08/kw-hr = $134/day Total cost: $50,000/year SUMMARY: Microfiltration will be used to remove dissolved solids and particles that cause turbidity in water. This unit will be able to treat 2.6mgd of nonpotable water before storage. (1.4mgd – Dewatering & 1.2mgd - Storm-water). SPECS: Membrane pore size: 0.1um - 5.0um. Pressure: 30 psi to pushed the water through the membrane. USES: • Irrigation • Dual Plumbed Building -Toilets - Laundry • CoolingTowers • Augment Proposed Artificial River COST: Total: $3,630,000 SUMMARY: WRE intends to provide the Qualcomm site with an abundant supply of non-potable water found from excavating for construction foundation. WRE has implemented a permanent dewatering system that will provide about 1.5 MGD of water from two subgrade structures: a 40 MG water storage tank and parking structure. ASSUMPTIONS: • Yields 1000gpm (1.4mgd) groundwater •Water Meets RWQCB Objectives •Kinder Morgan Petroleum Facility -Largely Complete SUMMARY: One of the water supply component is storm-water captured from Serra Mesa watershed. An additional element of water harvesting will be to capture and use the storm-water runoff, specifically from the Serra Mesa Canyon that discharges in the northwest corner of the site. Dry weather flows were assumed to be 1.9cfs (1.2mgd). Spatial analysis of the Mission Valley Watershed was used to verify that figure. Project Objective: Create a conceptual plan for water supply and water quality for the Qualcomm Stadium Redevelopment. The conceptual plan will incorporate creative approaches to offset the use of potable water that includes storm-water harvesting, groundwater, and a creative approach that makes use of the San Diego River water. Qualcomm Stadium Development Water Re-use Project Dewatering System Storage MissionBay San DiegoRiver QualcommStadium Serra MesaWatershed Qualcomm Stadium I-15 San DiegoRiver Serra MesaWatershed I-8 Stormwater Artificial River Acknowledgement Microfiltration SUMMARY: The tank is designed in accordance with California Building Code 2013, AWWA D110, ACI 350, ACI 350.3 and incorporates state of the art features such as close tolerance electro-servo controlled wrapping, galvanized circumferential prestressing, automated shotcrete, vertical post- tensioning and utilizes flexible connections at the wall base and wall top to improve seismic performance. CAPACITY: 40 Million gallons 450 ft. diameter and 40ft depth Well Design Structure Perimeter = 600 feet Well Spacing = 50 feet Number of Wells = 600/50 = 12 Wells Cost of construction per well = $20,000 Total Cost = $20,000 x 12 = $240,000 Pump Design Pump Require = 12 pumps Cost of each pump = $6,500 Total Cost of Pump = $6,500 x 12 = $78,000 Component Total Cost = $240,000 + $78,000 $318,000 Precipitation Data for San Diego Water Year (Oct. - Sep.) Actual Rainfall (in.) Normal Rainfall (in.) 2010 10.6 10.77 2011 12.7 10.34 2012 7.9 10.34 2013 6.55 10.34 2014 5.09 10.34 COST: The estimate includes all work associated with the construction and design of the floor, wall footing, core wall, round columns, two way, flat slab roof (designed for 100 psf live load), circumferential and vertical pre- stressing, automated shotcrete and standard appurtenances attached to the tank (i.e. vent, hatch and exterior and interior ladders. $17,000,000.00 WRE would like to thank the following Professors and mentors: Alicia Kinoshita, Natalie Mladenov, John Prince, Tim Smith, Tom Bloomer. Especially: James R. Haughey and Jim Rasmus from . Project Manager: Ismael Marquez Civil : Rob Lane Environmental: Jose Alcaraz Environmental: Loren Miller Environmental: Fed Pinongcos Environmental: Heather Tegley Team The New Qualcomm stadium conceptual plan by the City of San Diego including an Artificial River. An Artificial River from Seoul Korea. Conceptual Plan: The final design that was created by Water Resources Engineering (WRE) has four primary components: • An artificial river, • A groundwater dewatering system, • A storage reservoir for dry weather storm- water flow • A microfiltration unit that will treat the water to non-potable standards to be used on any future development plan. If this conceptual plan is implemented, the combination of storm-water flow and dewatering system will generate 2.6MGD of water that could be used to offset the demand of potable water. (Unit cost x flow) = $9,000/MGD x 3 MGD = = $27,000/*3 years = $9,000 per year Membrane Filtration equipment (Estimated equipment cost x total capacity) = $.5/gpd x 3 MGD = $1,500,000 Energy cost to operate = (111356.233 m3/day x .05 kwh/m3) = 567.81 kwh/day = (.1351/kwh x 567.81 kwh/day) = $77/day = ($77/day x 365 days) = $28,105/year Total annual Operation and Maintenance cost $1,537,105 Capital Cost $3,630,000 Membrane replacement *Filtration membranes should be replaced about every 3 years because the membranes will not be put under too much stress. Microfiltration: Operation and Maintenance Cost for 3 MGD flow Project Cost: Component Cost + Annual Operations and Maintenance =$23,231,500 + $286,365 =$23,517,865! DS, $1,285,760 , 6% ST, $17,000,000, 72% AR, $100,000, 0% MS, $5,167,105, 22% Original Groundwater Level Made Ground Proposed Basement ExcavationDewatering Well Installed Int. or Ext. Temporary Reduced Groundwater Level