START FINISH
DUR'N START FINISH DUR'N START FINISH VARIANCE VARIANCE
SECTION 1 TO 4
ALL AREAS
PRELIMINARIES (208/00) 81 - UP
PREPARATION WORKS (208/00) 66 - 80
Award : Main Contract 0 9/Nov/97 0 09.Nov.97 0 0 51 - 65
Possession of Site 0 29.Nov.97 0 29.Nov.97 0 0 41 - 50
BUILDING SERVICES (208/00) 31 - 40
PLUMBING & DRAINAGE 21 - 30
Submission Form 25 to DSD - M.S. C25 0 20.Sep.98 0 20.Sep.98 0 0 11 - 20
Submission Form H for P/D and FSI - M.S. P27 1 20.Nov.98 20.Nov.98 19 30.Apr.98 18.May.98 204 186 5% 203 1 - 10
NOMINATED SUBCONTRACTORS' PRELIMINARY WORKS 0 Progress on Programme
LIFT & ESCALATORS (208/01) (1) - (30)
Award : Nominated Subcontract - Fujitec (HK) Co 0 12.Dec.97 0 09.Dec.97 3 3 (31) - (60)
Lead-In Period : Award > Initial Site Work 272 12.Dec.97 09.Sep.98 267 09.Dec.97 01.Sep.98 3 8 102% 4 5 6 6 7 7 8 8 9 (62) - (100)
Effective Completion : Submission Form 5 - M.S. C29 0 15.Nov.97 0 04.May.98 (170) (170) (101) - (140)
ELECTRICAL SYSTEMS (208/02) (141) - (190)
Award : Nominated Subcontract - ATAL Eng. Co. Ltd. 0 12.Dec.97 0 12.Dec.97 0 0 (191) - (240)
Lead-In Period I : Award > Initial Cast-In 29 12.Dec.97 09.Jan.98 31 12.Dec.97 11.Jan.98 0 (2) 94% (0) (241) - (300)
Lead-In Period II : Award > Initial 1st Fix 197 12.Dec.97 26.Jun.98 186 12.Dec.97 15.Jun.98 0 11 106% 2 4 6 8 9 11 (300) - UP
Power On : Sections 3 & 4 - M.S. C17 0 01.Dec.98 0 01.Apr.99 (121) 30 0 (31) (62) (90) (121)
MVAC & BMS SYSTEMS (208/03)
Award : Nominated Subcontract - ATAL Eng. Co. Ltd. 0 12.Dec.97 0 12.Dec.97 0 0
Lead-In Period I : Award > Initial Cast-In 29 12.Dec.97 09.Jan.98 31 12.Dec.97 11.Jan.98 0 (2) 94% (0)
Lead-In Period II : Award > Initial 1st Fix 190 12.Dec.97 19.Jun.98 216 12.Dec.97 15.Jul.98 0 (26) 88% (2) (5) (9) (12) (16) (20) (23)
Submission of Form FX 172 for Ventilation : Sections 3 & 4 - M.S. P320 01.Dec.98 0 02.Jun.99 (183) (183)
FIRE SERVICES SYSTEMS (208/04)
Award : Nominated Subcontract - Tridant Plb & Eng. Co. Ltd. 0 12.Dec.97 0 04.Dec.97 8 8
Lead-In Period I : Award > Initial Cast-In 29 12.Dec.97 09.Jan.98 39 04.Dec.97 11.Jan.98 8 (2) 74% 2
Lead-In Period II : Award > Initial 1st Fix 190 12.Dec.97 19.Jun.98 210 04.Dec.97 01.Jul.98 8 (12) 90% 6 3 1 (2) (5) (8) (11)
Submission of Form 501 : Sections 3 & 4 - M.S. C31 0 01.Dec.98 0 02.Jun.99 (183) (183)
FIRE & SECURITY SHUTTERS (208/05)
Award : Nominated Subcontract - Sanwo Shutter (HK) Ltd. 0 31.Dec.97 0 15.Apr.98 (105) (105)
Lead-In Period : Award > Initial Site Work 194 31.Dec.97 12.Jul.98 201 15.Apr.98 01.Nov.98 (105) (112) 97% (105) (106) (107) (108) (109) (110) (111)
OFFICE BUILDING CURTAIN WALLS (208/06)
Award : Nominated Subcontract - Builders Federal (HK) Ltd. 0 20.Dec.97 0 06.Jan.98 (17) (17)
Lead-In Period : Award > Initial Site Work 277 20.Dec.97 22.Sep.98 239 06.Jan.98 01.Sep.98 (17) 21 116% (12) (7) (2) 2 7 12 17 22
BD Approval : of Office Tower Curtain Wall Sub. - M.S. C18 0 01.Apr.98 0 10.Sep.98 (162) (162)
PODIUM GLASS WALLS, CLADDING & SKYLIGHT (208/07)
Award : Nominated Subcontract - Untied Reliance Corp. Ltd 0 20.Dec.97 0 03.Jan.98 (14) (14)
Lead-In Period : Award > Initial Site Work 314 20.Dec.97 29.Oct.98 333 03.Jan.98 01.Dec.98 (14) (33) 94% (15) (16) (18) (20) (22) (23) (25) (27) (29) (30) (32)
BD Approval : of Metal Roof - Podium - M.S. P19 0 01.May.98 0 24.Sep.98 (146) (146)
BD Approval :of Glass Wall - Podium - M.S. C20 0 01.Mar.98 0 04.Jul.98 (125) (125)
STEEL ROOF STRUCTURE (208/08)
Award : Nominated Subcontract - Keplel Fels China Ltd. 0 02.Jan.98 0 24.Dec.97 9 9
Lead-In Period : Award > Initial Site Work 200 02.Jan.98 20.Jul.98 235 24.Dec.97 15.Aug.98 9 (26) 85% 9 4 (0) (5) (9) (14) (18) (23)
SPECIAL ROOFING SYSTEMS (208/09)
Award : Nominated Subcontract - S&D Design & Eng. (HK) Ltd. 0 31.Dec.97 0 02.Jan.98 (2) (2)
Lead-In Period : Award > Initial Site Work 197 31.Dec.97 15.Jul.98 262 02.Jan.98 20.Sep.98 (2) (67) 75% (9) (16) (23) (31) (38) (46) (54) (61)
PUBLIC AREAS FITTING OUT (208/12)
Award : Nominated Subcontract - Vaford Contracting Co., Ltd. 0 02.Mar.98 0 27.Aug.98 (178) (178)
Lead-In Period : Award > Initial Site Work 194 02.Mar.98 11.Sep.98 111 27.Aug.98 15.Dec.98 (178) (95) 175% (173) (150) (127) (104)
FOOD COURT FITTING OUT (208/13)
Award : Nominated Subcontract - Vaford Contracting Co., Ltd. 0 02.Mar.98 0 27.Aug.98 (178) (178)
Lead-In Period : Award > Initial Site Work 194 02.Mar.98 11.Sep.98 128 27.Aug.98 01.Jan.99 (178) (112) 152% (174) (158) (142) (127) (111)
IRONMONGERY (208/14)
Award : Nominated Subcontract to Arnold & Co., Ltd. 0 01.May.98 0 15.Sep.98 (137) (137)
Lead-In Period : Award > Initial Site Work 145 01.May.98 22.Sep.98 48 15.Sep.98 01.Nov.98 (137) (40) 302% (102) (39)
SIGNAGE & GRAPHICS (208/18)
Award : Nominated Subcontract - Yet To Be Awarded 0 01.May.98 0 01.Oct.99 (518) (518)
SECTION 4
BRIDGE DECK
STRUCTURAL CONSTRUCTION (208/00)
R.C. SUPERSTRUCTURE
Installation : Commence > Effective Completion 61 01.Apr.98 31.May.98 137 01.Apr.98 15.Aug.98 0 (76) 45% 0 (16) (33) (50) (67)
BUILDING WORKS & FINISHES (208/00)
BUILDERS WORKS
Installation : Commence > Effective Completion 93 05.Aug.98 05.Nov.98 100 13.Oct.98 20.Jan.99 (69) (76) 93% (69) (72) (74)
BUILDING SERVICES (208/00)
PLUMBING & DRAINAGE
Installation : Commence > Effective Completion 213 15.Apr.98 13.Nov.98 345 01.Jul.98 10.Jun.99 (77) (209) 62% (76) (88) (100) (112) (123) (135) (147) (159) (169) (181) (193) (205)
NOMINATED SUBCONTRACTORS' WORKS
Activity Description
As-Planned vs. As-Built Programme Analysis
Visual Illustration of Activity Delay
1.Nov.991.Oct.991.Jan.99 1.Sep.991.Aug.991.Jul.991.Jun.991.Jun.981.Mar.98 1.Apr.98 1.May.981.Dec.97 1.Jan.98 1.Feb.98
ACTUAL - AS-BUILT
1.Oct.981.Aug.98 1.Sep.98 1.May.991.Apr.991.Mar.991.Feb.991.Dec.981.Jul.98 1.Nov.981.Nov.97
PRODUCTION
RATE
VARIANCE
PLANNED - HHC Prog. 9/4/98
Number of Days Progress is Behind
Programme
Number of Days Progress is Ahead
of Programme
ProgrammeKey
As-Planned vs. As-Built Programme Analysis
Visual Illustration of Activity Delay
ELECTRICAL SYSTEMS (208/02)
Installation : NSC Possession > Effective Completion 153 15.Jun.98 14.Nov.98 334 01.Aug.98 30.Jun.99 (47) (228) 46% (47) (63) (80) (96) (113) (129) (146) (161) (178) (194) (211)
MVAC & BMS SYSTEMS (208/03)
Installation : NSC Possession > Effective Completion 169 16.Jun.98 01.Dec.98 334 01.Aug.98 30.Jun.99 (46) (211) 51% (45) (61) (76) (91) (106) (121) (136) (150) (166) (180) (196)
FIRE SERVICES SYSTEM (208/04)
Installation : NSC Possession > Effective Completion 156 16.Jun.98 18.Nov.98 359 01.Jul.98 24.Jun.99 (15) (218) 43% (15) (32) (50) (67) (84) (101) (119) (136) (152) (170) (186) (204)
FIRE & SECURITY SHUTTERS (208/05)
Installation : NSC Possession > Effective Completion 94 01.Aug.98 02.Nov.98 272 01.Nov.98 30.Jul.99 (92) (270) 35% (92) (111) (132) (152) (170) (190) (210) (230) (250)
PODIUM GLASS WALLS, CLADDING & SKYLIGHTS(208/07)
Installation : NSC Possession > Effective Completion (Ex. Metal Cladd.)90 29.Jul.98 26.Oct.98 305 30.Sep.98 31.Jul.99 (63) (278) 30% (63) (85) (106) (128) (150) (170) (192) (213) (235) (256)
CINEMA STRUCTURE
STRUCTURAL CONSTRUCTION (208/00)
SUPERSTRUCTURE
Installation : Commence > Effective Completion 94 15.Mar.98 16.Jun.98 269 01.Feb.98 27.Oct.98 42 (133) 35% 42 24 4 (16) (36) (55) (75) (96) (115)
BUILDING WORKS & FINISHES (208/00)
BUILDING WORKS & FINISHES
Installation : Commence > Effective Completion 174 29.Jun.98 19.Dec.98 165 02.Jan.99 15.Jun.99 (187) (178) 105% (184) (183) (181) (179) (178)
BUILDING SERVICES (208/00)
PLUMBING & DRAINAGE
Installation : Commence > Effective Completion 115 22.Jul.98 13.Nov.98 196 01.Jan.99 15.Jul.99 (163) (244) 59% (162) (175) (187) (200) (212) (225) (237)
NOMINATED SUBCONTRACTORS' WORKS
LIFTS & ESCALATORS (208/01)
Installation : NSC Possession > Effective Completion - M.S. C29 92 16.Aug.98 15.Nov.98 246 01.Sep.98 04.May.99 (16) (170) 37% (16) (34) (54) (73) (92) (111) (129) (148) (167)
Completion : Initial Certified Use (F6) > Handover to E.M.O. 84 27.Dec.98 20.Mar.99 132 22.Jun.99 31.Oct.99 (177) (225) 64% (180) (191) (202) (213)
ELECTRICAL SYSTEMS (208/02)
Installation : NSC Possession > Effective Completion 122 15.Jul.98 13.Nov.98 197 01.Dec.98 15.Jun.99 (139) (214) 62% (138) (150) (162) (173) (184) (196) (208)
MVAC & BMS SYSTEMS (208/03)
Installation : NSC Possession > Effective Completion 140 15.Jul.98 01.Dec.98 218 05.Dec.98 10.Jul.99 (143) (221) 64% (152) (163) (173) (184) (195) (206) (217)
STEEL ROOF STRUCTURE (208/08)
Installation : NSC Possession > Effective Completion 90 15.Jul.98 12.Oct.98 153 01.Sep.98 31.Jan.99 (48) (111) 59% (47) (60) (73) (85) (98)
SPECIAL ROOFING SYSTEMS (208/09)
Installation : NSC Possession > Effective Completion 132 15.Jul.98 23.Nov.98 284 20.Sep.98 30.Jun.99 (67) (219) 46% (72) (89) (105) (122) (138) (153) (170) (186) (202)
Completion : Podium Metal Roof Structure - M.S. C23 0 01.Jan.99 0 07.Jul.99 (187) (187)
FOOD COURT FITTING OUT(208/13)
Handover to NSC : Food Court - M.S. P7 0 15.Jun.98 0 01.Jan.99 (200) (200)
Installation : NSC Possession > Effective Completion 80 13.Oct.98 31.Dec.98 334 01.Jan.99 30.Nov.99 (80) (334) 24% (80) (103) (125) (148) (171) (195) (217) (241) (265) (287)
OFFICE TOWER
STRUCTURAL CONSTRUCTION (208/00)
R.C. SUPERSTRUCTURE
Construction : Commencement > Effective Completion 195 15.Feb.98 28.Aug.98 297 05.Jan.98 28.Oct.98 41 (61) 66% 32 23 12 2 (9) (19) (30) (40) (51)
BUILDING WORKS & FINISHES (208/00)
BUILDING WORKS & FINISHES
Installation : Commence > Effective Completion 160 11.Jul.98 17.Dec.98 273 01.Sep.98 31.May.99 (52) (165) 59% (51) (64) (77) (89) (102) (115) (126) (139) (152)
Completion of Sample Floor for Office Tower - M.S. P14 0 01.Jun.98 0 01.Dec.98 (183) (183)
BUILDING SERVICES (208/00)
PLUMBING & DRAINAGE
Installation : Commence > Effective Completion 116 25.Jul.98 17.Nov.98 310 25.Aug.98 30.Jun.99 (31) (225) 37% (35) (54) (73) (92) (111) (131) (148) (168) (186) (206)
NOMINATED SUBCONTRACTORS' WORKS
LIFTS & ESCALATORS (208/01)
Handover : Lift Shaft to NSC - M.S. C5 0 01.Sep.98 0 25.Nov.98 (85) (85)
Installation : NSC Possession > Effective Completion - M.S. C28 82 26.Aug.98 15.Nov.98 279 15.Sep.98 20.Jun.99 (20) (217) 29% (31) (53) (74) (96) (118) (138) (160) (181) (203)
Completion : Initial Certified Use (F6) > Handover to E.M.O. 84 27.Dec.98 20.Mar.99 195 20.Apr.99 31.Oct.99 (114) (225) 43% (120) (137) (155) (172) (190) (207)
ELECTRICAL SYSTEMS (208/02)
Installation : NSC Possession > Effective Completion 104 02.Aug.98 13.Nov.98 310 25.Aug.98 30.Jun.99 (23) (229) 34% (27) (47) (68) (88) (108) (129) (148) (168) (188) (209)
MVAC & BMS SYSTEMS (208/03)
Installation : NSC Possession > Effective Completion 122 02.Aug.98 01.Dec.98 257 01.Nov.98 15.Jul.99 (91) (226) 47% (91) (106) (123) (139) (154) (170) (186) (202) (218)
FIRE SERVICES SYSTEM (208/04)
Installation : NSC Possession > Effective Completion 109 02.Aug.98 18.Nov.98 334 01.Aug.98 30.Jun.99 1 (224) 33% 1 (20) (40) (61) (81) (102) (123) (141) (162) (183) (203)
OFFICE BUILDING CURTAIN WALLS (208/06)
Installation : NSC Possession > Effective Completion - M.S. C22 71 23.Aug.98 01.Nov.98 232 01.Sep.98 20.Apr.99 (9) (170) 31% (9) (30) (51) (72) (93) (115) (134) (156)
PODIUM GLASS WALLS, CLADDING & SKYLIGHTS(208/07)
Installation : NSC Possession > Effective Completion 70 27.Sep.98 05.Dec.98 212 01.Dec.98 30.Jun.99 (65) (207) 33% (65) (85) (106) (125) (146) (166) (187)
PODIUM STRUCTURE (GL. Sel-SL & S4-S7 & EXT. AREA)
STRUCTURAL CONSTRUCTION (208/00)
R.C. SUPERSTRUCTURE
Construction : Commencement > Effective Completion 80 06.Apr.98 24.Jun.98 215 08.Jan.98 10.Aug.98 88 (47) 37% 73 56 36 17 (2) (21) (40)
BUILDING WORKS & FINISHES (208/00)
BUILDING WORKS & FINISHES
Installation : Commence > Effective Completion 149 28.Jun.98 23.Nov.98 304 01.Jul.98 30.Apr.99 (3) (158) 49% (3) (18) (34) (49) (65) (81) (96) (112) (126) (142)
BUILDING SERVICES (208/00)
PLUMBING & DRAINAGE
Installation : Commence > Effective Completion 117 20.Jul.98 13.Nov.98 340 01.Jul.98 05.Jun.99 19 (204) 34% 19 (1) (21) (41) (61) (81) (101) (122) (140) (160) (180) (200)
NOMINATED SUBCONTRACTORS' WORKS
LIFTS & ESCALATORS (208/01)
As-Planned vs. As-Built Programme Analysis
Visual Illustration of Activity Delay
NSC Possession to Effective Completion 88 20.Aug.98 15.Nov.98 226 10.Sep.98 23.Apr.99 (21) (159) 39% (33) (52) (71) (90) (109) (126) (145)
Completion : Initial Certified Use (Form 6) > Handover to E.M.O. 84 27.Dec.98 20.Mar.99 181 04.May.99 31.Oct.99 (128) (225) 46% (143) (159) (175) (192) (208)
ELECTRICAL SYSTEMS (208/02)
Installation : NSC Possession > Effective Completion 116 21.Jul.98 13.Nov.98 371 15.Jun.98 20.Jun.99 36 (219) 31% 25 4 (17) (38) (59) (80) (101) (122) (142) (163) (184) (205)
MVAC & BMS SYSTEMS (208/03)
Installation : NSC Possession > Effective Completion 134 21.Jul.98 01.Dec.98 361 15.Jul.98 10.Jul.99 6 (221) 37% (4) (24) (43) (62) (81) (101) (120) (138) (157) (176) (195) (214)
FIRE SERVICES SYSTEM (208/04)
Installation : NSC Possession > Effective Completion 120 29.Jul.98 25.Nov.98 340 01.Jul.98 05.Jun.99 28 (192) 35% 28 8 (12) (31) (51) (71) (91) (111) (129) (149) (168) (188)
FIRE & SECURITY SHUTTERS (208/05)
Installation : NSC Possession > Effective Completion 96 19.Aug.98 22.Nov.98 120 01.Nov.98 28.Feb.99 (74) (98) 80% (73) (79) (85) (92)
PODIUM GLASS WALLS, CLADDING & SKYLIGHTS(208/07)
Installation : NSC Possession > Effective Completion 75 03.Sep.98 16.Nov.98 214 01.Dec.98 02.Jul.99 (89) (228) 35% (89) (109) (129) (147) (167) (187) (207) (226)
STEEL ROOF STRUCTURE (208/08)
Installation : NSC Possession > Effective Completion 84 21.Jul.98 12.Oct.98 129 25.Sep.98 31.Jan.99 (66) (111) 65% (67) (78) (89) (100)
PUBLIC AREAS FITTING OUT (208/12)
Installation : NSC Possession > Effective Completion 80 13.Oct.98 31.Dec.98 305 15.Dec.98 15.Oct.99 (63) (288) 26% (75) (98) (119) (142) (164) (187) (209) (232) (255) (277)
Completion : Sample Floor for Retail - M.S. P15 0 15.Jun.98 0 15.Dec.98 (183) (183)
ALL AREAS
COMPLETION PROCEDURE
FINAL CLEAN AND HANDOVER
Sectional Completion 0 15.Dec.98 0 01.Jul.99 (198) (198)
Submission of BA13 : Sections 3 & 4 - M.S. C33 (HHC>ANA) 0 31.Dec.98 0 01.Jun.99 (152) (152)
Practical Completion 0 21.Mar.99 0 01.Dec.99 (255) (255)
Whole Project : Average Delay (Based on 1-Dec-1999 Completion) 498 09.Nov.97 21.Mar.99 753 09.Nov.97 01.Dec.99 0 (255) 66% (7) (17) (28) (37) (48) (58) (68) (79) (89) (100) (110) (120) (130) (141) (151) (161) (171) (182) (192) (202) (213) (223) (233) (244)
DUR'N START FINISH DUR'N START FINISH START FINISH
VARIANCE VARIANCE
Copyright: David Greig of GreigConsulting.Com
ACTUAL - AS-BUILT
PRODUCTION
RATE
VARIANCE
1.Jul.99 1.Aug.99 1.Sep.991.Mar.99 1.Apr.99 1.May.991.Nov.98 1.Dec.98 1.Jan.991.Oct.981.May.98 1.Jun.98 1.Jul.98 1.Sep.98 1.Nov.991.Jun.99 1.Oct.99ACTIVITY DESCRIPTION 1.Nov.97 1.Dec.97 1.Jan.98 1.Feb.98 1.Mar.98
PLANNED - HHC Prog. 9/4/98
1.Aug.98 1.Feb.991.Apr.98

More Related Content

Similar to As plan v as-built graphical analysis (11 jun19)

Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Allan Leyte
 
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
gongfuao7509
 
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
f8usejkdmmd8i
 
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
tengtui535
 
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
jfkekd9d8di
 
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
f8usejkddmmd
 
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
udjkskmdm4e
 
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
jkdkkdsmmd
 
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
fujsekmd9dik
 
Caterpillar Cat 289D COMPACT TRACK LOADER (Prefix WCT) Service Repair Manual ...
Caterpillar Cat 289D COMPACT TRACK LOADER (Prefix WCT) Service Repair Manual ...Caterpillar Cat 289D COMPACT TRACK LOADER (Prefix WCT) Service Repair Manual ...
Caterpillar Cat 289D COMPACT TRACK LOADER (Prefix WCT) Service Repair Manual ...
gongfuao7509
 
Caterpillar Cat 289D COMPACT TRACK LOADER (Prefix WCT) Service Repair Manual ...
Caterpillar Cat 289D COMPACT TRACK LOADER (Prefix WCT) Service Repair Manual ...Caterpillar Cat 289D COMPACT TRACK LOADER (Prefix WCT) Service Repair Manual ...
Caterpillar Cat 289D COMPACT TRACK LOADER (Prefix WCT) Service Repair Manual ...
f8usejkdmmd8i
 
Caterpillar Cat 289D COMPACT TRACK LOADER (Prefix WCT) Service Repair Manual ...
Caterpillar Cat 289D COMPACT TRACK LOADER (Prefix WCT) Service Repair Manual ...Caterpillar Cat 289D COMPACT TRACK LOADER (Prefix WCT) Service Repair Manual ...
Caterpillar Cat 289D COMPACT TRACK LOADER (Prefix WCT) Service Repair Manual ...
tengtui535
 

Similar to As plan v as-built graphical analysis (11 jun19) (20)

Sachpazis_CHS Column base plate to EC3 1993-1 with NA CEN
Sachpazis_CHS Column base plate to EC3 1993-1 with NA CENSachpazis_CHS Column base plate to EC3 1993-1 with NA CEN
Sachpazis_CHS Column base plate to EC3 1993-1 with NA CEN
 
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
 
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
 
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
 
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
 
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
 
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
 
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
 
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
 
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
 
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
 
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
 
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
 
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
 
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
Caterpillar Cat 304E Mini Hydraulic Excavator (Prefix TSR) Service Repair Man...
 
Caterpillar Cat 289D COMPACT TRACK LOADER (Prefix WCT) Service Repair Manual ...
Caterpillar Cat 289D COMPACT TRACK LOADER (Prefix WCT) Service Repair Manual ...Caterpillar Cat 289D COMPACT TRACK LOADER (Prefix WCT) Service Repair Manual ...
Caterpillar Cat 289D COMPACT TRACK LOADER (Prefix WCT) Service Repair Manual ...
 
Caterpillar Cat 289D COMPACT TRACK LOADER (Prefix WCT) Service Repair Manual ...
Caterpillar Cat 289D COMPACT TRACK LOADER (Prefix WCT) Service Repair Manual ...Caterpillar Cat 289D COMPACT TRACK LOADER (Prefix WCT) Service Repair Manual ...
Caterpillar Cat 289D COMPACT TRACK LOADER (Prefix WCT) Service Repair Manual ...
 
Caterpillar Cat 289D COMPACT TRACK LOADER (Prefix WCT) Service Repair Manual ...
Caterpillar Cat 289D COMPACT TRACK LOADER (Prefix WCT) Service Repair Manual ...Caterpillar Cat 289D COMPACT TRACK LOADER (Prefix WCT) Service Repair Manual ...
Caterpillar Cat 289D COMPACT TRACK LOADER (Prefix WCT) Service Repair Manual ...
 
Caterpillar Cat 289D COMPACT TRACK LOADER (Prefix WCT) Service Repair Manual ...
Caterpillar Cat 289D COMPACT TRACK LOADER (Prefix WCT) Service Repair Manual ...Caterpillar Cat 289D COMPACT TRACK LOADER (Prefix WCT) Service Repair Manual ...
Caterpillar Cat 289D COMPACT TRACK LOADER (Prefix WCT) Service Repair Manual ...
 
Caterpillar Cat 289D COMPACT TRACK LOADER (Prefix WCT) Service Repair Manual ...
Caterpillar Cat 289D COMPACT TRACK LOADER (Prefix WCT) Service Repair Manual ...Caterpillar Cat 289D COMPACT TRACK LOADER (Prefix WCT) Service Repair Manual ...
Caterpillar Cat 289D COMPACT TRACK LOADER (Prefix WCT) Service Repair Manual ...
 

More from David Greig

More from David Greig (6)

No Networked Baseline? Then Create One by Untangling a Later Update!
No Networked Baseline?   Then Create One by Untangling a Later Update!No Networked Baseline?   Then Create One by Untangling a Later Update!
No Networked Baseline? Then Create One by Untangling a Later Update!
 
Delay Analysis - Correcting for Programme Errors
Delay Analysis - Correcting for Programme ErrorsDelay Analysis - Correcting for Programme Errors
Delay Analysis - Correcting for Programme Errors
 
Delay Analysis - Correcting for Programme Errors
Delay Analysis - Correcting for Programme ErrorsDelay Analysis - Correcting for Programme Errors
Delay Analysis - Correcting for Programme Errors
 
As built programmes (7 Apr 2020) Part 1
As built programmes (7 Apr 2020) Part 1As built programmes (7 Apr 2020) Part 1
As built programmes (7 Apr 2020) Part 1
 
As-built Programmes - Part 2
As-built Programmes - Part 2As-built Programmes - Part 2
As-built Programmes - Part 2
 
Health check (9 jul19)
Health check (9 jul19)Health check (9 jul19)
Health check (9 jul19)
 

Recently uploaded

Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
Nauman Safdar
 
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan CytotecJual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
ZurliaSoop
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
allensay1
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
daisycvs
 

Recently uploaded (20)

Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdf
 
HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGBerhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan CytotecJual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
 
PHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation Final
 
Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
 
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
 
Falcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business Growth
 
Berhampur Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Berhampur Call Girl Just Call 8084732287 Top Class Call Girl Service AvailableBerhampur Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Berhampur Call Girl Just Call 8084732287 Top Class Call Girl Service Available
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investors
 
GUWAHATI 💋 Call Girl 9827461493 Call Girls in Escort service book now
GUWAHATI 💋 Call Girl 9827461493 Call Girls in  Escort service book nowGUWAHATI 💋 Call Girl 9827461493 Call Girls in  Escort service book now
GUWAHATI 💋 Call Girl 9827461493 Call Girls in Escort service book now
 
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
 
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGBerhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR ESCORTS
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR  ESCORTSJAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR  ESCORTS
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR ESCORTS
 

As plan v as-built graphical analysis (11 jun19)

  • 1. START FINISH DUR'N START FINISH DUR'N START FINISH VARIANCE VARIANCE SECTION 1 TO 4 ALL AREAS PRELIMINARIES (208/00) 81 - UP PREPARATION WORKS (208/00) 66 - 80 Award : Main Contract 0 9/Nov/97 0 09.Nov.97 0 0 51 - 65 Possession of Site 0 29.Nov.97 0 29.Nov.97 0 0 41 - 50 BUILDING SERVICES (208/00) 31 - 40 PLUMBING & DRAINAGE 21 - 30 Submission Form 25 to DSD - M.S. C25 0 20.Sep.98 0 20.Sep.98 0 0 11 - 20 Submission Form H for P/D and FSI - M.S. P27 1 20.Nov.98 20.Nov.98 19 30.Apr.98 18.May.98 204 186 5% 203 1 - 10 NOMINATED SUBCONTRACTORS' PRELIMINARY WORKS 0 Progress on Programme LIFT & ESCALATORS (208/01) (1) - (30) Award : Nominated Subcontract - Fujitec (HK) Co 0 12.Dec.97 0 09.Dec.97 3 3 (31) - (60) Lead-In Period : Award > Initial Site Work 272 12.Dec.97 09.Sep.98 267 09.Dec.97 01.Sep.98 3 8 102% 4 5 6 6 7 7 8 8 9 (62) - (100) Effective Completion : Submission Form 5 - M.S. C29 0 15.Nov.97 0 04.May.98 (170) (170) (101) - (140) ELECTRICAL SYSTEMS (208/02) (141) - (190) Award : Nominated Subcontract - ATAL Eng. Co. Ltd. 0 12.Dec.97 0 12.Dec.97 0 0 (191) - (240) Lead-In Period I : Award > Initial Cast-In 29 12.Dec.97 09.Jan.98 31 12.Dec.97 11.Jan.98 0 (2) 94% (0) (241) - (300) Lead-In Period II : Award > Initial 1st Fix 197 12.Dec.97 26.Jun.98 186 12.Dec.97 15.Jun.98 0 11 106% 2 4 6 8 9 11 (300) - UP Power On : Sections 3 & 4 - M.S. C17 0 01.Dec.98 0 01.Apr.99 (121) 30 0 (31) (62) (90) (121) MVAC & BMS SYSTEMS (208/03) Award : Nominated Subcontract - ATAL Eng. Co. Ltd. 0 12.Dec.97 0 12.Dec.97 0 0 Lead-In Period I : Award > Initial Cast-In 29 12.Dec.97 09.Jan.98 31 12.Dec.97 11.Jan.98 0 (2) 94% (0) Lead-In Period II : Award > Initial 1st Fix 190 12.Dec.97 19.Jun.98 216 12.Dec.97 15.Jul.98 0 (26) 88% (2) (5) (9) (12) (16) (20) (23) Submission of Form FX 172 for Ventilation : Sections 3 & 4 - M.S. P320 01.Dec.98 0 02.Jun.99 (183) (183) FIRE SERVICES SYSTEMS (208/04) Award : Nominated Subcontract - Tridant Plb & Eng. Co. Ltd. 0 12.Dec.97 0 04.Dec.97 8 8 Lead-In Period I : Award > Initial Cast-In 29 12.Dec.97 09.Jan.98 39 04.Dec.97 11.Jan.98 8 (2) 74% 2 Lead-In Period II : Award > Initial 1st Fix 190 12.Dec.97 19.Jun.98 210 04.Dec.97 01.Jul.98 8 (12) 90% 6 3 1 (2) (5) (8) (11) Submission of Form 501 : Sections 3 & 4 - M.S. C31 0 01.Dec.98 0 02.Jun.99 (183) (183) FIRE & SECURITY SHUTTERS (208/05) Award : Nominated Subcontract - Sanwo Shutter (HK) Ltd. 0 31.Dec.97 0 15.Apr.98 (105) (105) Lead-In Period : Award > Initial Site Work 194 31.Dec.97 12.Jul.98 201 15.Apr.98 01.Nov.98 (105) (112) 97% (105) (106) (107) (108) (109) (110) (111) OFFICE BUILDING CURTAIN WALLS (208/06) Award : Nominated Subcontract - Builders Federal (HK) Ltd. 0 20.Dec.97 0 06.Jan.98 (17) (17) Lead-In Period : Award > Initial Site Work 277 20.Dec.97 22.Sep.98 239 06.Jan.98 01.Sep.98 (17) 21 116% (12) (7) (2) 2 7 12 17 22 BD Approval : of Office Tower Curtain Wall Sub. - M.S. C18 0 01.Apr.98 0 10.Sep.98 (162) (162) PODIUM GLASS WALLS, CLADDING & SKYLIGHT (208/07) Award : Nominated Subcontract - Untied Reliance Corp. Ltd 0 20.Dec.97 0 03.Jan.98 (14) (14) Lead-In Period : Award > Initial Site Work 314 20.Dec.97 29.Oct.98 333 03.Jan.98 01.Dec.98 (14) (33) 94% (15) (16) (18) (20) (22) (23) (25) (27) (29) (30) (32) BD Approval : of Metal Roof - Podium - M.S. P19 0 01.May.98 0 24.Sep.98 (146) (146) BD Approval :of Glass Wall - Podium - M.S. C20 0 01.Mar.98 0 04.Jul.98 (125) (125) STEEL ROOF STRUCTURE (208/08) Award : Nominated Subcontract - Keplel Fels China Ltd. 0 02.Jan.98 0 24.Dec.97 9 9 Lead-In Period : Award > Initial Site Work 200 02.Jan.98 20.Jul.98 235 24.Dec.97 15.Aug.98 9 (26) 85% 9 4 (0) (5) (9) (14) (18) (23) SPECIAL ROOFING SYSTEMS (208/09) Award : Nominated Subcontract - S&D Design & Eng. (HK) Ltd. 0 31.Dec.97 0 02.Jan.98 (2) (2) Lead-In Period : Award > Initial Site Work 197 31.Dec.97 15.Jul.98 262 02.Jan.98 20.Sep.98 (2) (67) 75% (9) (16) (23) (31) (38) (46) (54) (61) PUBLIC AREAS FITTING OUT (208/12) Award : Nominated Subcontract - Vaford Contracting Co., Ltd. 0 02.Mar.98 0 27.Aug.98 (178) (178) Lead-In Period : Award > Initial Site Work 194 02.Mar.98 11.Sep.98 111 27.Aug.98 15.Dec.98 (178) (95) 175% (173) (150) (127) (104) FOOD COURT FITTING OUT (208/13) Award : Nominated Subcontract - Vaford Contracting Co., Ltd. 0 02.Mar.98 0 27.Aug.98 (178) (178) Lead-In Period : Award > Initial Site Work 194 02.Mar.98 11.Sep.98 128 27.Aug.98 01.Jan.99 (178) (112) 152% (174) (158) (142) (127) (111) IRONMONGERY (208/14) Award : Nominated Subcontract to Arnold & Co., Ltd. 0 01.May.98 0 15.Sep.98 (137) (137) Lead-In Period : Award > Initial Site Work 145 01.May.98 22.Sep.98 48 15.Sep.98 01.Nov.98 (137) (40) 302% (102) (39) SIGNAGE & GRAPHICS (208/18) Award : Nominated Subcontract - Yet To Be Awarded 0 01.May.98 0 01.Oct.99 (518) (518) SECTION 4 BRIDGE DECK STRUCTURAL CONSTRUCTION (208/00) R.C. SUPERSTRUCTURE Installation : Commence > Effective Completion 61 01.Apr.98 31.May.98 137 01.Apr.98 15.Aug.98 0 (76) 45% 0 (16) (33) (50) (67) BUILDING WORKS & FINISHES (208/00) BUILDERS WORKS Installation : Commence > Effective Completion 93 05.Aug.98 05.Nov.98 100 13.Oct.98 20.Jan.99 (69) (76) 93% (69) (72) (74) BUILDING SERVICES (208/00) PLUMBING & DRAINAGE Installation : Commence > Effective Completion 213 15.Apr.98 13.Nov.98 345 01.Jul.98 10.Jun.99 (77) (209) 62% (76) (88) (100) (112) (123) (135) (147) (159) (169) (181) (193) (205) NOMINATED SUBCONTRACTORS' WORKS Activity Description As-Planned vs. As-Built Programme Analysis Visual Illustration of Activity Delay 1.Nov.991.Oct.991.Jan.99 1.Sep.991.Aug.991.Jul.991.Jun.991.Jun.981.Mar.98 1.Apr.98 1.May.981.Dec.97 1.Jan.98 1.Feb.98 ACTUAL - AS-BUILT 1.Oct.981.Aug.98 1.Sep.98 1.May.991.Apr.991.Mar.991.Feb.991.Dec.981.Jul.98 1.Nov.981.Nov.97 PRODUCTION RATE VARIANCE PLANNED - HHC Prog. 9/4/98 Number of Days Progress is Behind Programme Number of Days Progress is Ahead of Programme ProgrammeKey
  • 2. As-Planned vs. As-Built Programme Analysis Visual Illustration of Activity Delay ELECTRICAL SYSTEMS (208/02) Installation : NSC Possession > Effective Completion 153 15.Jun.98 14.Nov.98 334 01.Aug.98 30.Jun.99 (47) (228) 46% (47) (63) (80) (96) (113) (129) (146) (161) (178) (194) (211) MVAC & BMS SYSTEMS (208/03) Installation : NSC Possession > Effective Completion 169 16.Jun.98 01.Dec.98 334 01.Aug.98 30.Jun.99 (46) (211) 51% (45) (61) (76) (91) (106) (121) (136) (150) (166) (180) (196) FIRE SERVICES SYSTEM (208/04) Installation : NSC Possession > Effective Completion 156 16.Jun.98 18.Nov.98 359 01.Jul.98 24.Jun.99 (15) (218) 43% (15) (32) (50) (67) (84) (101) (119) (136) (152) (170) (186) (204) FIRE & SECURITY SHUTTERS (208/05) Installation : NSC Possession > Effective Completion 94 01.Aug.98 02.Nov.98 272 01.Nov.98 30.Jul.99 (92) (270) 35% (92) (111) (132) (152) (170) (190) (210) (230) (250) PODIUM GLASS WALLS, CLADDING & SKYLIGHTS(208/07) Installation : NSC Possession > Effective Completion (Ex. Metal Cladd.)90 29.Jul.98 26.Oct.98 305 30.Sep.98 31.Jul.99 (63) (278) 30% (63) (85) (106) (128) (150) (170) (192) (213) (235) (256) CINEMA STRUCTURE STRUCTURAL CONSTRUCTION (208/00) SUPERSTRUCTURE Installation : Commence > Effective Completion 94 15.Mar.98 16.Jun.98 269 01.Feb.98 27.Oct.98 42 (133) 35% 42 24 4 (16) (36) (55) (75) (96) (115) BUILDING WORKS & FINISHES (208/00) BUILDING WORKS & FINISHES Installation : Commence > Effective Completion 174 29.Jun.98 19.Dec.98 165 02.Jan.99 15.Jun.99 (187) (178) 105% (184) (183) (181) (179) (178) BUILDING SERVICES (208/00) PLUMBING & DRAINAGE Installation : Commence > Effective Completion 115 22.Jul.98 13.Nov.98 196 01.Jan.99 15.Jul.99 (163) (244) 59% (162) (175) (187) (200) (212) (225) (237) NOMINATED SUBCONTRACTORS' WORKS LIFTS & ESCALATORS (208/01) Installation : NSC Possession > Effective Completion - M.S. C29 92 16.Aug.98 15.Nov.98 246 01.Sep.98 04.May.99 (16) (170) 37% (16) (34) (54) (73) (92) (111) (129) (148) (167) Completion : Initial Certified Use (F6) > Handover to E.M.O. 84 27.Dec.98 20.Mar.99 132 22.Jun.99 31.Oct.99 (177) (225) 64% (180) (191) (202) (213) ELECTRICAL SYSTEMS (208/02) Installation : NSC Possession > Effective Completion 122 15.Jul.98 13.Nov.98 197 01.Dec.98 15.Jun.99 (139) (214) 62% (138) (150) (162) (173) (184) (196) (208) MVAC & BMS SYSTEMS (208/03) Installation : NSC Possession > Effective Completion 140 15.Jul.98 01.Dec.98 218 05.Dec.98 10.Jul.99 (143) (221) 64% (152) (163) (173) (184) (195) (206) (217) STEEL ROOF STRUCTURE (208/08) Installation : NSC Possession > Effective Completion 90 15.Jul.98 12.Oct.98 153 01.Sep.98 31.Jan.99 (48) (111) 59% (47) (60) (73) (85) (98) SPECIAL ROOFING SYSTEMS (208/09) Installation : NSC Possession > Effective Completion 132 15.Jul.98 23.Nov.98 284 20.Sep.98 30.Jun.99 (67) (219) 46% (72) (89) (105) (122) (138) (153) (170) (186) (202) Completion : Podium Metal Roof Structure - M.S. C23 0 01.Jan.99 0 07.Jul.99 (187) (187) FOOD COURT FITTING OUT(208/13) Handover to NSC : Food Court - M.S. P7 0 15.Jun.98 0 01.Jan.99 (200) (200) Installation : NSC Possession > Effective Completion 80 13.Oct.98 31.Dec.98 334 01.Jan.99 30.Nov.99 (80) (334) 24% (80) (103) (125) (148) (171) (195) (217) (241) (265) (287) OFFICE TOWER STRUCTURAL CONSTRUCTION (208/00) R.C. SUPERSTRUCTURE Construction : Commencement > Effective Completion 195 15.Feb.98 28.Aug.98 297 05.Jan.98 28.Oct.98 41 (61) 66% 32 23 12 2 (9) (19) (30) (40) (51) BUILDING WORKS & FINISHES (208/00) BUILDING WORKS & FINISHES Installation : Commence > Effective Completion 160 11.Jul.98 17.Dec.98 273 01.Sep.98 31.May.99 (52) (165) 59% (51) (64) (77) (89) (102) (115) (126) (139) (152) Completion of Sample Floor for Office Tower - M.S. P14 0 01.Jun.98 0 01.Dec.98 (183) (183) BUILDING SERVICES (208/00) PLUMBING & DRAINAGE Installation : Commence > Effective Completion 116 25.Jul.98 17.Nov.98 310 25.Aug.98 30.Jun.99 (31) (225) 37% (35) (54) (73) (92) (111) (131) (148) (168) (186) (206) NOMINATED SUBCONTRACTORS' WORKS LIFTS & ESCALATORS (208/01) Handover : Lift Shaft to NSC - M.S. C5 0 01.Sep.98 0 25.Nov.98 (85) (85) Installation : NSC Possession > Effective Completion - M.S. C28 82 26.Aug.98 15.Nov.98 279 15.Sep.98 20.Jun.99 (20) (217) 29% (31) (53) (74) (96) (118) (138) (160) (181) (203) Completion : Initial Certified Use (F6) > Handover to E.M.O. 84 27.Dec.98 20.Mar.99 195 20.Apr.99 31.Oct.99 (114) (225) 43% (120) (137) (155) (172) (190) (207) ELECTRICAL SYSTEMS (208/02) Installation : NSC Possession > Effective Completion 104 02.Aug.98 13.Nov.98 310 25.Aug.98 30.Jun.99 (23) (229) 34% (27) (47) (68) (88) (108) (129) (148) (168) (188) (209) MVAC & BMS SYSTEMS (208/03) Installation : NSC Possession > Effective Completion 122 02.Aug.98 01.Dec.98 257 01.Nov.98 15.Jul.99 (91) (226) 47% (91) (106) (123) (139) (154) (170) (186) (202) (218) FIRE SERVICES SYSTEM (208/04) Installation : NSC Possession > Effective Completion 109 02.Aug.98 18.Nov.98 334 01.Aug.98 30.Jun.99 1 (224) 33% 1 (20) (40) (61) (81) (102) (123) (141) (162) (183) (203) OFFICE BUILDING CURTAIN WALLS (208/06) Installation : NSC Possession > Effective Completion - M.S. C22 71 23.Aug.98 01.Nov.98 232 01.Sep.98 20.Apr.99 (9) (170) 31% (9) (30) (51) (72) (93) (115) (134) (156) PODIUM GLASS WALLS, CLADDING & SKYLIGHTS(208/07) Installation : NSC Possession > Effective Completion 70 27.Sep.98 05.Dec.98 212 01.Dec.98 30.Jun.99 (65) (207) 33% (65) (85) (106) (125) (146) (166) (187) PODIUM STRUCTURE (GL. Sel-SL & S4-S7 & EXT. AREA) STRUCTURAL CONSTRUCTION (208/00) R.C. SUPERSTRUCTURE Construction : Commencement > Effective Completion 80 06.Apr.98 24.Jun.98 215 08.Jan.98 10.Aug.98 88 (47) 37% 73 56 36 17 (2) (21) (40) BUILDING WORKS & FINISHES (208/00) BUILDING WORKS & FINISHES Installation : Commence > Effective Completion 149 28.Jun.98 23.Nov.98 304 01.Jul.98 30.Apr.99 (3) (158) 49% (3) (18) (34) (49) (65) (81) (96) (112) (126) (142) BUILDING SERVICES (208/00) PLUMBING & DRAINAGE Installation : Commence > Effective Completion 117 20.Jul.98 13.Nov.98 340 01.Jul.98 05.Jun.99 19 (204) 34% 19 (1) (21) (41) (61) (81) (101) (122) (140) (160) (180) (200) NOMINATED SUBCONTRACTORS' WORKS LIFTS & ESCALATORS (208/01)
  • 3. As-Planned vs. As-Built Programme Analysis Visual Illustration of Activity Delay NSC Possession to Effective Completion 88 20.Aug.98 15.Nov.98 226 10.Sep.98 23.Apr.99 (21) (159) 39% (33) (52) (71) (90) (109) (126) (145) Completion : Initial Certified Use (Form 6) > Handover to E.M.O. 84 27.Dec.98 20.Mar.99 181 04.May.99 31.Oct.99 (128) (225) 46% (143) (159) (175) (192) (208) ELECTRICAL SYSTEMS (208/02) Installation : NSC Possession > Effective Completion 116 21.Jul.98 13.Nov.98 371 15.Jun.98 20.Jun.99 36 (219) 31% 25 4 (17) (38) (59) (80) (101) (122) (142) (163) (184) (205) MVAC & BMS SYSTEMS (208/03) Installation : NSC Possession > Effective Completion 134 21.Jul.98 01.Dec.98 361 15.Jul.98 10.Jul.99 6 (221) 37% (4) (24) (43) (62) (81) (101) (120) (138) (157) (176) (195) (214) FIRE SERVICES SYSTEM (208/04) Installation : NSC Possession > Effective Completion 120 29.Jul.98 25.Nov.98 340 01.Jul.98 05.Jun.99 28 (192) 35% 28 8 (12) (31) (51) (71) (91) (111) (129) (149) (168) (188) FIRE & SECURITY SHUTTERS (208/05) Installation : NSC Possession > Effective Completion 96 19.Aug.98 22.Nov.98 120 01.Nov.98 28.Feb.99 (74) (98) 80% (73) (79) (85) (92) PODIUM GLASS WALLS, CLADDING & SKYLIGHTS(208/07) Installation : NSC Possession > Effective Completion 75 03.Sep.98 16.Nov.98 214 01.Dec.98 02.Jul.99 (89) (228) 35% (89) (109) (129) (147) (167) (187) (207) (226) STEEL ROOF STRUCTURE (208/08) Installation : NSC Possession > Effective Completion 84 21.Jul.98 12.Oct.98 129 25.Sep.98 31.Jan.99 (66) (111) 65% (67) (78) (89) (100) PUBLIC AREAS FITTING OUT (208/12) Installation : NSC Possession > Effective Completion 80 13.Oct.98 31.Dec.98 305 15.Dec.98 15.Oct.99 (63) (288) 26% (75) (98) (119) (142) (164) (187) (209) (232) (255) (277) Completion : Sample Floor for Retail - M.S. P15 0 15.Jun.98 0 15.Dec.98 (183) (183) ALL AREAS COMPLETION PROCEDURE FINAL CLEAN AND HANDOVER Sectional Completion 0 15.Dec.98 0 01.Jul.99 (198) (198) Submission of BA13 : Sections 3 & 4 - M.S. C33 (HHC>ANA) 0 31.Dec.98 0 01.Jun.99 (152) (152) Practical Completion 0 21.Mar.99 0 01.Dec.99 (255) (255) Whole Project : Average Delay (Based on 1-Dec-1999 Completion) 498 09.Nov.97 21.Mar.99 753 09.Nov.97 01.Dec.99 0 (255) 66% (7) (17) (28) (37) (48) (58) (68) (79) (89) (100) (110) (120) (130) (141) (151) (161) (171) (182) (192) (202) (213) (223) (233) (244) DUR'N START FINISH DUR'N START FINISH START FINISH VARIANCE VARIANCE Copyright: David Greig of GreigConsulting.Com ACTUAL - AS-BUILT PRODUCTION RATE VARIANCE 1.Jul.99 1.Aug.99 1.Sep.991.Mar.99 1.Apr.99 1.May.991.Nov.98 1.Dec.98 1.Jan.991.Oct.981.May.98 1.Jun.98 1.Jul.98 1.Sep.98 1.Nov.991.Jun.99 1.Oct.99ACTIVITY DESCRIPTION 1.Nov.97 1.Dec.97 1.Jan.98 1.Feb.98 1.Mar.98 PLANNED - HHC Prog. 9/4/98 1.Aug.98 1.Feb.991.Apr.98