444budg
- 1. PROJECT BUDGET
Project Resources
Cost estimation
________________________
No. Required material Type Quantity Price in
Ethiopia (birr)
1. computer Dell 1 20000
2 internet -
3 cable RJ45 1 150
4 Servers 1
5 Working documents
6 papers
7
8
9
Total
- 2. Time-phased Budget
Tasks Work to be
accomplished
Intermediate
predecessor
Time(days) Duration Variance
optimistic Most
likely
Pessimistic
1 Reading reference,
collect data
2 3 4 3 1/9
2 Preparing the material
required by our project
1 3 4 5 4 1/9
3 Design modeling and
Write the program
2 2 3 4 3 1/9
4 Implementing the
design and testing
3 1 2 3 2 1/9
5 Implementing the
system
4 2 3 4 3 1/9
0.556